43
BChydro CD FOR GEf\lE IONS Joanna Sofield Chief Regulatory Officer Phone: (604) 623-4046 Fax: (604) 623-4407 bchydroregulatoryg [email protected] January 19, 2010 Ms. Erica M. Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor - 900 Howe Street Vancouver, BC V6Z 2N3 Dear Ms. Hamilton: RE: Project No. 3698588 British Columbia Utilities Commission (BCUC) British Columbia Hydro and Power Authority (BC Hydro) Stave Falls Spillway Gates Replacement Project Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010. For further information, please contact Lyle McClelland at 604 623-4306. Yours sincerely, Joanna Sofield Chief Regulatory Officer Enclosure c.· BCUC Project No. 3698588 Stave Falls Spillway Gates Project' Registered Intervenor Distribution List. British Co1umbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3 www.bchydro.com B-2

B-2 BChydro CD...Hoist System Portion of Radial Gate 27 Consequences of Failure Dam Overtopping • If the spillway gates become inoperable during flood conditions, the Stave Falls

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • BChydro CDFOR GEf\lE IONS

    Joanna SofieldChief Regulatory OfficerPhone: (604) 623-4046Fax: (604) [email protected]

    January 19, 2010

    Ms. Erica M. HamiltonCommission SecretaryBritish Columbia Utilities CommissionSixth Floor - 900 Howe StreetVancouver, BC V6Z 2N3

    Dear Ms. Hamilton:

    RE: Project No. 3698588British Columbia Utilities Commission (BCUC)British Columbia Hydro and Power Authority (BC Hydro)Stave Falls Spillway Gates Replacement Project

    Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway GatesProject Workshop held on January 18, 2010.

    For further information, please contact Lyle McClelland at 604 623-4306.

    Yours sincerely,

    Joanna SofieldChief Regulatory Officer

    Enclosure

    c.· BCUC Project No. 3698588 Stave Falls Spillway Gates Project' Registered IntervenorDistribution List.

    British Co1umbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3www.bchydro.com

    B-2

    markhudsBCH-Stave Falls Spillway Gates Replacement Project

  • Stave Falls Spillway Gates Replacement Project Workshop

    January 18, 2010

  • 2

    Introduction

    • BCUC Order• Introduction to Spillway Gate Systems• Spillway Gates Program• Facility Description• Need for the Project• Project Description• Alternatives Considered• Project Costs• Project Schedule• Project Effects (Rate Impact, Environmental & Social)• Project Risks• Project Consultation• Conclusions

  • 3

    BCUC Order

    • 44.2 (3)(a) of the Utilities Commission Act (the UCA) • BCUC acceptance that the expenditures for Stave Falls Spillway

    Gates Replacement Project are in the public interest • Considerations:

    > the Government’s energy objectives; > BC Hydro’s most recent Long-Term Resource Plan; > whether the expenditure schedule is consistent with sections 64.01

    and 64.02 of the UCA in respect of electricity self sufficiency and clean and renewable resources; and

    > the interests of present and future ratepayers.• Project Costs:

    > Expected Cost: $61.5M> Authorized Cost: $70.6M

    BCUC Order

  • 4

    Functions of a Gate

    Introduction to Spillway Gate Systems

    Water barrier• Part of the dam• Don’t open without

    demand

    Flood discharge• Open on demand• Close on demand

  • 5

    Spillway Gate Operations

    Introduction to Spillway Gate Systems

    Operated to ensure: • safe release of excess flows or floods to prevent

    overtopping• essential to ensure safe dam operation

    Other Operations :• proper regulation of water flow downstream• rapid release of water for emergency or

    precautionary reservoir drawdown• post catastrophe operational requirement

  • 6

    Zipingpu Dam, China, 2005• Concrete Face Rockfill

    Dam• Damage to upstream

    concrete face slabs• Reservoir was

    immediately lowered• Declared structurally

    stable and safe

    Emergency Reservoir Drawdown

    Introduction to Spillway Gate Systems

    PresenterPresentation NotesThe permanent seismic deformations caused the rockfill to shift, cracking of concrete slabs exposing voids in the underling rockfill.Created new seepage pathways - although seepage increased it did not exceed the maximum recorded at 51 L/s in 2006 at RWL = 874 m.

  • Precautionary Reservoir Drawdown

    W.A.C. Bennett Dam, 1996

    Introduction to Spillway Gate Systems

  • 8

    Post-Catastrophe Operational Requirement

    Sayano Hydroelectric Plant, Russia, August 17, 2009

    •6400 MW Facility•Unreliable backup power•Overtopping potential in 2 days•Just made it in time….

    Introduction to Spillway Gate Systems

  • 9

    Examples of Spillway Gate Failures

    Introduction to Spillway Gate Systems

    Structural Failures:Folsom Dam, California• Commissioned in

    1956• Failed, July 1995• Trunnion friction not

    included in design; not checked

  • 10

    Examples of Spillway Gate Failures

    Introduction to Spillway Gate Systems

    Operational Failures:Manatee Dam, Florida• Spillway Gate

    jammed in half-open position in July 2003

    • 600 homes evacuated

    • Workers managed to open Gate before dam overtopped

  • 11

    Examples of Spillway Gate Failures

    Introduction to Spillway Gate Systems

    Tirlyan Dam, Russia• August, 1994• Spillway Gate jammed

    in half-open position

  • 12

    Examples of Spillway Gate FailuresCatastrophic Embankment failure

    Introduction to Spillway Gate Systems

  • 13

    Examples of Spillway Gate Failures

    Introduction to Spillway Gate Systems

    • caused about 20 deaths• significant property destruction

  • 14

    Spillway Gates Program

    In 2005, BC Hydro began an initiative to improve equipment and procedures to ensure reliable operation of spillway gate systems• Equipment• Power supplies• Control systems• Testing and Maintenance, Management 2005 Condition evaluated against a set of design and operation principles

    Spillway Gates Program

  • 15

    Reliability Principles and ALARP

    • Formalized and adopted in 2006, based on work by external consultant on spillway gate systems

    • New concept to hydroelectric industry, but common practice in other high-hazard industries

    • System should operate on demand with less than a 1 in 1000 chance of failure

    • Reduce risk to As Low As Reasonably Practicable

    Spillway Gates Program

  • 16

    Prioritization of Sites

    All 22 sites with spillways were evaluated and prioritized based upon:• Current physical condition of equipment• Availability of alternative ways to control water• Frequency of use• Current reliability• Possibility of interim risk management methods• Consequences of failure

    Spillway Gates Program

  • 17

    Summary

    Spillway Gate Systems are:• Critical Infrastructure for Public Safety• Cannot be taken for granted

    Spillway Gates Program

  • 18

    Stave Falls Facility

    Stave Falls Facility is located about 16 kilometres northwest of the town of Mission, on the Stave River.

    Facility Description

    Stave Falls Facility

  • 19

    Stave Falls Facility

    Facility Description

  • 20

    Stave Falls Facility

    • Originally constructed between 1910 and 1927• Facility includes Stave Reservoir, Stave Falls

    Generating Station, main dam, two intake structures and the Blind Slough Dam (provides flood discharge control)

    • Part of the Alouette-Stave Falls Hydroelectric System which consists of three facilities: Alouette (upstream), Stave Falls, and Ruskin (downstream)

    • Operation of Stave Falls and Ruskin facilities closely coordinated in order to maximize use of water and ensure water licence compliance

    Facility Description

  • 21

    Stave Falls Facility (Blind Slough Dam)

    • Blind Slough Dam constructed to impound Stave Reservoir and to provide controlled release of water during flood conditions

    • Passing of water to the spillway is controlled via 4 radial gates and 10 vertical gates

    • When all 14 gates are fully open, they allow safe passage of the most severe inflow flood

    • The four radial gates provide about 45% of the overall discharge capacity and are the preferred means of passing water through Blind Slough because they allow BC Hydro to more precisely control water releases

    Facility Description

  • 22

    Stave Falls Facility (Blind Slough Dam)

    Facility Description

    Longitudinal view of Blind Slough Dam Spillway Gates

    PresenterPresentation NotesNotes

  • 23

    Stave Falls Facility (Blind Slough Dam)

    Facility Description

    Radial Gate (Side Profile)

    Vertical Gate (Side Profile)

    PresenterPresentation NotesNotes

  • 24

    Operating History

    Facility Description

    • The Blind Slough Dam’s radial gates were originally installed around 1923

    • BC Hydro refurbished the radial gates in 1997/1998 in order to extend their life by about 15 years; refurbishment consisted of replacing corroded components and repainting of the gates

    • New radial gates are scheduled be installed in 2011 & 2012; about 14 years after the 1997/1998 refurbishment

    • Radial Gate ropes replaced in 2007 as a result of rope failure

  • 25

    Key Concerns

    1. Installed in the 1920s, the four radial gates and hoists are at end-of-life and do not meet current seismic criteria.

    2. Existing design deficiencies could lead to a common cause failure which could result in all spillway gates becoming inoperable.

    Consequently, the Spillway Gate System cannot currently be relied upon to operate effectively during flood conditions

    Need for the Project

  • 26

    Key Concerns

    Need for the Project

    Hoist System

    Portion ofRadial Gate

  • 27

    Consequences of Failure

    Dam Overtopping• If the spillway gates become inoperable during flood

    conditions, the Stave Falls Dam and Blind Slough Dam could be overtopped by 1 to 2 metres depth of water flow

    • This level of overtopping would result in a catastrophic dam failure at both the Stave Falls facility and the downstream Ruskin facility

    • Catastrophic dam failures have the potential to result in loss of life and significant financial and environmental damage

    Need for the Project

  • 28

    Consequences of Failure

    Other Failure ModesGiven the current condition of the Spillway Gates system, the gates could experience the following failure modes:

    • gates not opening when commanded,• gates opening when not commanded,• gates over-travelling (moving beyond the intended position)

    Failures of this type could lead to serious public and worker safety and environmental impacts

    Need for the Project

  • 29

    Project Scope

    This project focuses on the upgrade of the radial gates and hoists and does not include the 10 vertical gates

    The radial gates are more critical because:

    • The radial gates provide quick push button operation

    • The radial gates can more easily be designed and

    • Upgraded to meet a high level of reliability

    • The radial gates are required to draw down the reservoir after a seismic event

    • Tighter hydraulic control

    Project Description

  • 30

    Project Scope

    The Project will address:

    • Replacement of radial gates and radial gate hoists,

    • Installation of new seals, rollers and maintenance access for radial gates, and

    • Upgrades to electrical power supply system, protection and controls.

    Project Description

  • 31

    Alternatives

    • Alternatives that were considered but found to be unacceptable include:• Doing nothing• Deferring capital improvements

    • A component-by-component review of the Spillway Gate System was then carried out to determine whether components should be replaced or refurbished

    Alternatives Considered

  • 32

    Alternatives – Replacement Selected

    Replacement was selected over refurbishment due to the following factors:• Age and condition of components (installed in

    1920’s),• Levels of corrosion for certain components,• Inherent design deficiencies that would not be

    addressed through refurbishment

    Alternatives Considered

  • 33

    Project Cost

    Project Cost

    PROJECT COMPONENT PROJECT COST ($ Millions) Identification Phase (Direct) 0.1 Definition Phase (Direct) 3.3 Capital Overhead and IDC 1.0 Total Identification and Definition Phase Cost 4.4 Direct Construction Cost 30.1 Project Management and Engineering 5.8 Project Contingency for Expected Cost 9.1 Dismantling and Removal and Inflation 0.5 Inflation, Capital Overhead and IDC 11.4 Implementation Phase Costs 57.0 TOTAL EXPECTED COST 61.5 Project Reserve 9.2 TOTAL AUTHORIZED COST 70.6

  • 34

    Project Schedule

    Date Decision Points and/or MilestonesDecember 2009 Application Submitted to the BCUCMarch 2010 Radial Gate and Hoist supply-install contract awardJune 2010 BCUC Decision IssuedAugust 2011 Completion of installation of electrical power supply

    upgradeSeptember 2011 Completion of installation of two of four radial gates

    and hoistsSeptember 2012 Completion of installation of remaining two radial

    gates and hoistsMay 2013 Project Completion

    Project Schedule

  • 35

    Annual Incremental Rate Impacts

    Project Effects

    0.00%

    0.05%

    0.10%

    0.15%

    0.20%

    0.25%

    F201

    0F2

    011

    F201

    2F2

    013

    F201

    4F2

    015

    F201

    6F2

    017

    F201

    8F2

    019

    F202

    0F2

    021

    F202

    2F2

    023

    F202

    4F2

    025

    F202

    6F2

    027

    F202

    8F2

    029

    F203

    0F2

    031

    F203

    2F2

    033

    F203

    4

    Fiscal Year

    Per c

    ent %

    Expected Cost

    Authorized Cost

    PresenterPresentation Notes

    F2014–

  • 36

    Environmental and Social Effects

    • There are minimal adverse impacts as the project footprint does not extend beyond existing BC Hydro property

    • BC Hydro has carried out an archeological assessment of portion the site being disturbed

    • BC Hydro will continue to operate within the current water license and water use plan.

    • Potential for road closures of Dewdney Trunk Road will be coordinated with the District of Mission and the Ministry of Transport.

    Project Effects

  • 37

    Project Cost Risks

    Cost risks have been mitigated by:• Clearly defining project scope• Applying previous experience gained on other

    Spillway Gates projects• Monte Carlo simulations and appropriate contingency

    level to accommodate risks• Project procurement strategy• Contract termination clauses should BC Hydro decide

    to delay the Project

    Project Risks

  • 38

    Project Schedule Risks

    Project Risks

    Schedule risks are being managed by:• Proactive project oversight including scheduling and

    construction reviews• Development of detailed project schedule• Managing progress and contractor performance

    relative to the approved construction schedule

  • 39

    Safety & Environmental Risks

    Safety Risks are mitigated by:• BC Hydro and Contractor Safety Management

    Plans which incorporate site specific safety and security work practices

    • Monitoring by BC Hydro during constructionEnvironmental Risks are mitigated by:• Environmental Management Plans and

    Environmental Protection Plans enforced through the contracts

    • On-site Environmental Monitor

    Project Risks

  • 40

    Consultation

    • BC Hydro has undertaken consultation with First Nations and with public stakeholders to identify issues specific to the Project

    • No or very minimal adverse Project impacts have been identified

    • No opposition to the Project has been identified• BC Hydro is of the view that the consultation

    conducted for the Project to date has been adequate• Consultation will be ongoing as the Project progresses

    Consultation

  • 41

    Conclusions

    • BC Hydro is seeking BCUC acceptance that expenditures to replace Stave Falls Spillway Gates system are in the public interest. Project costs are:

    > Expected cost of $61.5 Million> Authorized cost of $70.6 Million

    • BC Hydro has significant reliability concerns given the age of assets and design deficiencies in the existing spillway gate system

    • The project:1. Addresses end-of-life condition of assets2. Addresses design deficiencies that could lead to common cause failures and safety

    risks

    • BC Hydro has identified and is managing project risks through measures such as firm contractor pricing as well as schedule and performance guarantees

    Consultation

  • 42

    Questions?

    January 19, 2010 - Cover LetterExhibit B-2 - Stave Falls Spillway Gates Replacement Project Workshop - January 18, 2010 IntroductionBCUC OrderFunctions of a GateSpillway Gate OperationsSlide Number 6Slide Number 7Post-Catastrophe Operational RequirementExamples of Spillway Gate FailuresExamples of Spillway Gate FailuresExamples of Spillway Gate FailuresExamples of Spillway Gate FailuresExamples of Spillway Gate FailuresSpillway Gates Program Reliability Principles and ALARPPrioritization of SitesSummaryStave Falls FacilityStave Falls FacilityStave Falls FacilityStave Falls Facility (Blind Slough Dam)Stave Falls Facility (Blind Slough Dam)Stave Falls Facility (Blind Slough Dam)Operating HistoryKey ConcernsKey ConcernsConsequences of FailureConsequences of FailureProject ScopeProject ScopeAlternativesAlternatives – Replacement SelectedProject CostProject ScheduleAnnual Incremental Rate ImpactsEnvironmental and Social EffectsProject Cost RisksProject Schedule RisksSafety & Environmental RisksConsultationConclusionsQuestions