THE NEPA PROCESS AZ SOLAR 1 INTERCONNECTION PROJECT DOE/EA-2098 HOW TO SUBMIT COMMENTS FOR MORE INFORMATION Oct. ‘18 Dec. ‘18 to Feb. ‘19 Oct. ‘18 to Nov. ‘18 March ‘19 to April ‘19 May ‘19 to June ‘19 WAPA Determination to Prepare EA Resource Studies & Analysis Scoping Period Public Draft EA Final EA WAPA Decision BLM Decision PUBLIC INVOLVEMENT OPPORTUNITY PUBLIC INVOLVEMENT OPPORTUNITY Comments on the proposed project can be submitted by November 26, 2018, in the following ways: • Phone: (602) 605-2536 • Email: [email protected] • Send written comments via postal mail to: Western Area Power Administration Desert Southwest Region ATTN: Matthew Bilsbarrow NEPA Document Manager PO BOX 6457 Phoenix, Arizona 85005 www.wapa.gov/regions/DSW/Environment/ Pages/Arizona-Solar-1-Interconnection- Project.aspx OVERVIEW Western Area Power Administration (WAPA) is responding to a request from AZ Solar 1, LLC, to interconnect its proposed photovoltaic solar plant, located near Salome, La Paz County, Arizona, to WAPA’s electrical transmission system via the Little Harquahala to Harcuvar 115-kilovolt transmission line (see map). WAPA evaluates interconnection requests based on available transmission capacity, the safety and reliability of the bulk electrical system, and the results of the environmental planning processes; WAPA lacks authority over the requester’s electrical generation methods, equipment, or location. e Bureau of Land Management (BLM) and Bureau of Reclamation (Reclamation) are cooperating agencies in the environmental planning process. e transmission line is located on BLM land in an existing right-of-way held by Reclamation. WAPA’S ACTION If the interconnection request is approved, WAPA would enter into an interconnection agreement to 1) install and maintain two new pole structures in the existing transmission line easement; 2) add and maintain the less than 500-foot-long connections across BLM land from the transmission line to the new structures and into applicant’s switchyard; 3) modify existing right-of-way documents to support these connections as needed; and 4) review the reliability features of the applicant’s switchyard equipment. AZ Solar 1, LLC Facility Description AZ Solar 1, LLC, proposes to build, operate, and maintain an approximately 32.5-megawatt photovoltaic solar energy generation facility on up to a 480-acre parcel of private land. An optional 27.5 megawatts of photovoltaic solar energy generation and an optional 10-megawatt battery storage facility may be added to the parcel based on market considerations. Although the total nameplate capacity of the planned facility and the optional installation totals approximately 60 megawatts, Arizona Solar 1, LLC, plans to operate the facility such that the annual output is equal to or less than 50 average megawatts. Construction of the facility would include solar panels, access roads, an underground electrical collection system, and an on-site collection point switchyard. e AZ Solar 1, LLC, facilities are not part of the Federal action, but their impacts will be presented alongside that of the Federal action as part of a comprehensive analysis in a Draft Environmental Assessment. GET INVOLVED WAPA is seeking comments from the public on the proposed project to help in determining the scope of the environmental analysis. WAPA will use the public comments to identify significant issues for analysis and potential project alternatives. WAPA prefers to receive your comments by November 26, 2018 or be post-marked by this date. WAPA will consider late comments to the extent practicable. We Are Here

AZ SOLAR 1 INTERCONNECTION PROJECT€¦ · AZ Solar 1, LLC Facility Description AZ Solar 1, LLC, proposes to build, operate, and maintain an approximately 32.5-megawatt photovoltaic

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: AZ SOLAR 1 INTERCONNECTION PROJECT€¦ · AZ Solar 1, LLC Facility Description AZ Solar 1, LLC, proposes to build, operate, and maintain an approximately 32.5-megawatt photovoltaic

We Are Here

Get Involved

THE NEPA PROCESS

AZ SOLAR 1 INTERCONNECTION PROJECT DOE/EA-2098

HOW TO SUBMIT COMMENTS

FOR MORE INFORMATION

Oct. ‘18

Dec. ‘18 to

Feb. ‘19

Oct. ‘18 to

Nov. ‘18

March ‘19to

April ‘19

May ‘19to

June ‘19

WAPA Determination to Prepare EA

Resource Studies & Analysis

Scoping Period

Public Draft EA

Final EAWAPA DecisionBLM Decision

PUBLIC INVOLVEMENT OPPORTUNITY

PUBLIC INVOLVEMENT OPPORTUNITY

Comments on the proposed project can be submitted by November 26, 2018, in the following ways:

• Phone: (602) 605-2536• Email:

[email protected]• Send written comments via postal mail to:

Western Area Power Administration Desert Southwest Region ATTN: Matthew Bilsbarrow NEPA Document Manager PO BOX 6457 Phoenix, Arizona 85005

www.wapa.gov/regions/DSW/Environment/Pages/Arizona-Solar-1-Interconnection-

Project.aspx

OVERVIEWWestern Area Power Administration (WAPA) is responding to a request from AZ Solar 1, LLC, to interconnect its proposed photovoltaic solar plant, located near Salome, La Paz County, Arizona, to WAPA’s electrical transmission system via the Little Harquahala to Harcuvar 115-kilovolt transmission line (see map). WAPA evaluates interconnection requests based on available transmission capacity, the safety and reliability of the bulk electrical system, and the results of the environmental planning processes; WAPA lacks authority over the requester’s electrical generation methods, equipment, or location.The Bureau of Land Management (BLM) and Bureau of Reclamation (Reclamation) are cooperating agencies in the environmental planning process. The transmission line is located on BLM land in an existing right-of-way held by Reclamation.

WAPA’S ACTIONIf the interconnection request is approved, WAPA would enter into an interconnection agreement to 1) install and maintain two new pole structures in the existing transmission line easement; 2) add and maintain the less than 500-foot-long connections across BLM land from the transmission line to the new structures and into applicant’s switchyard; 3) modify existing right-of-way documents to support these connections as needed; and 4) review the reliability features of the applicant’s switchyard equipment.

AZ Solar 1, LLC Facility DescriptionAZ Solar 1, LLC, proposes to build, operate, and maintain an approximately 32.5-megawatt photovoltaic solar energy generation facility on up to a 480-acre parcel of private land. An optional 27.5 megawatts of photovoltaic solar energy generation and an optional 10-megawatt battery storage facility may be added to the parcel based on market considerations. Although the total nameplate capacity of the planned facility and the optional installation totals approximately 60 megawatts, Arizona Solar 1, LLC, plans to operate the facility such that the annual output is equal to or less than 50 average megawatts. Construction of the facility would include solar panels, access roads, an underground electrical collection system, and an on-site collection point switchyard.

The AZ Solar 1, LLC, facilities are not part of the Federal action, but their impacts will be presented alongside that of the Federal action as part of a comprehensive analysis in a Draft Environmental Assessment.

GET INVOLVEDWAPA is seeking comments from the public on the proposed project to help in determining the scope of the environmental analysis. WAPA will use the public comments to identify significant issues for analysis and potential project alternatives. WAPA prefers to receive your comments by November 26, 2018 or be post-marked by this date. WAPA will consider late comments to the extent practicable.

We Are

Here

Page 2: AZ SOLAR 1 INTERCONNECTION PROJECT€¦ · AZ Solar 1, LLC Facility Description AZ Solar 1, LLC, proposes to build, operate, and maintain an approximately 32.5-megawatt photovoltaic

Service Layer Credits:

£¤60

TransmissionLine Interconnection

(See Inset)

Hall Avenue

Salome Road

Little

Harq

uaha

la–Harc

uvar

115-k

ilovo

lt Tran

smiss

ion Li

ne

Salome

Wenden

I-1022 Miles

Littl

e H

arqu

ahal

a–H

arcu

var

115-

kilo

volt

Tran

smis

sion

Lin

e

Proposed Overhead Line

Private Land

ApplicantSubstation/Switchyard

BLM Land

Inset: Transmission Line

La Paz

Overview Arizona: Site Location

³Basemap: ESRI USA Topo Maps

T5N R13W Section 18T5N R14W Section 13

La Paz County, AZUTM NAD 83 Zone 12

Date: 10/22/2018

Project AreaBureau of Land ManagmentPrivate State TrustTransmission LineRoads

0 0.5 1Miles

0 0.5 1Kilometers

AZ Solar 1 Interconnection DOE/EA-2098 Project

0 250 500 Feet

PROJECT LOCATION

AZ SOLAR 1 INTERCONNECTION PROJECT

Location to be DeterminedProposed Overhead LineThe project is located 2 miles west of

Salome, La Paz County, Arizona. The proposed interconnection would occur on BLM land in the east half of Section 13 in Township 5 North, Range 14 West on the Gila and Salt River Baseline and Meridian (GSRBM). The solar facility would be located on private land within portions of Section 18 in Township 5 North, Range 13 West on the GSRBM.