Follow-Up of Last TB Risk analysis ongoing ! – Plasma cell: oil and rubidium – Electron source: oil handling RF specifications for laser system to Menlo: – Done, waiting for comments from Menlo Compressor has been ordered. Plasma cell: – Tests in EHN1 done! – Plasma cell end flange design ongoing Electron spectrometer system: – Test of optical system – Test of screens 3 see Patric’s talks today See Stefano/Lawrence’ talks today
Citation preview
AWAKE Technical Board, 19 August 2015
1
E. Gschwendtner, CERN
2
News
Welcome• Florence Friebel fellow in laser beam line Coordination Package• Gennady Plyushchev Project Associate at CERN, plasma simulations
First discussion with Frederic Bordry on setting up the Steering Board
3
Follow-Up of Last TB
• Risk analysis ongoing ! – Plasma cell: oil and rubidium– Electron source: oil handling
• RF specifications for laser system to Menlo:– Done, waiting for comments from Menlo
• Compressor has been ordered.• Plasma cell:
– Tests in EHN1 done!– Plasma cell end flange design ongoing
• Electron spectrometer system:– Test of optical system – Test of screens
see Patric’s talks today
See Stefano/Lawrence’ talks today
4
Follow-Up of Last TB
• Interlock– General: interlock team work on this
– Laser: Valentine, Josh to find a solution how it can be clearly defined in which power mode the laser system is.
– BTV screens: the proton beam line to be confirmed!
5
AWAKE EDMS, WPs
6
WP/Engineering SpecificationsWorkpackage Work-Package Documents EDMS link to document
1 SPS Beams2 RF Synchr3 e- source https://edms.cern.ch/document/1504591/14 p line https://edms.cern.ch/document/1504433/15 e-line https://edms.cern.ch/document/1503845/16 Shielding https://edms.cern.ch/document/1505517/0.1
7 Laser BeamLine and Clean room8 SMI Measurement https://edms.cern.ch/document/1504590/19 Secondary Beamline https://edms.cern.ch/document/1506691/1
10 Plasmas Simulations https://edms.cern.ch/document/1504590/111 Magnets12 Power Converters13 Vacuum https://edms.cern.ch/document/1407357/1
14.1 BI.BPM
14.2 BI.BTV https://edms.cern.ch/document/1503645/0.0; https://edms.cern.ch/document/1503646/0.0; https://edms.cern.ch/document/1501342/114.3 BI.BCT14.4 BI.BLM15.1 Beam Interlock https://edms.cern.ch/document/1531912/1.015.2 Magnet Interlock https://edms.cern.ch/document/1523701/116 Mechanical Design https://edms.cern.ch/document/1531991/117 Civil engineering https://edms.cern.ch/document/1505016/118 Cooling and Vent https://edms.cern.ch/document/1503785/0.1
19.1 Electrical Services https://edms.cern.ch/document/1500403/119.2 Cabling https://edms.cern.ch/document/1502788/120 Transp+Handling21 Access https://edms.cern.ch/document/1453638/122 Fire+Gas https://edms.cern.ch/document/1502570/123 Survey https://edms.cern.ch/document/1503228/124 Ethernet25 Control
26.1 RP Monitoring https://edms.cern.ch/document/1505690/126.2 RP Simulations https://edms.cern.ch/document/1505689/1
Institute's WPs
I1 Plasma Cell https://edms.cern.ch/document/1506635/1I2 SMI Diagnostics https://edms.cern.ch/document/1529772/1; https://edms.cern.ch/document/1506854/1I3 Laser https://edms.cern.ch/document/1506630/1I4 Electron Spectrometer https://edms.cern.ch/document/1503551/0.5I5 DAQ (Who writes?)I6 Accelerating Structure https://edms.cern.ch/document/1506739/1
I7 Electron Line Diagnostics TRIUMF https://edms.cern.ch/document/1508566/1I8 Laser Dump https://edms.cern.ch/document/1506855/2
7
Document Release Procedure
8
WP/Engineering Specifications
• Owner/main author of the WP send the document for engineering check to check list! (Deadline: now!) • Include all comments. (Deadline: end of August)• Then ready to send out for approval. (Beginning of September)
For questions, please ask Marlene!
9
Next Meetings