Avedøre Holme Wind Turbines – DONG Energy
EHEN conference 29-30 October 2009
Contents
The company DONG Energy
The authority/environment process for Avedøre
What is being built at Avedøre?g
Why are we installing these turbines?y g
2
DONG Energy – Overview
DONG Energy is one of the leading energy companies in Northern Europe
We are headquartered in Denmark. Our business is based on procuring, producing distributing and trading inproducing, distributing and trading in energy and related products in Northern Europe
The average number of employeesin 2008 was 5,347, an increase of 385 employees compared to 2007
Business overview
Approximately 6000 full time employees
4
Approximately 6000 full time employees
Avedøre wind turbines, selection of locationAvedøre wind turbines, selection of location
As DONG Energy erects many wind turbines off shore, it is important to be able to test the wind turbinesit is important to be able to test the wind turbines.
Therefore, it is necessary to have a demonstration site with easy access for our employees.
Consequently, options for location in the Greater Copenhagen Area were considered.
The wind regime at Avedøre Holme bears close resemblance to the offshore wind regimeThe wind regime at Avedøre Holme bears close resemblance to the offshore wind regime.
Thus, the idea of erecting demonstration wind turbines at Avedøre Holme was born.
Avedøre wind turbines, the approval processsupreme authority
The approving authority for offshore wind turbines in Denmark is the Danish Energy Agency (ENS)Agency (ENS).
Usually, offshore wind turbines must be submitted for tender through the ENS, similar to eg Horns Rev 1 and 2to eg Horns Rev 1 and 2.
Offshore demonstration projects, however, are not subject to tender, but must still be approved by the ENSapproved by the ENS.
The ENS is the supreme authority and coordinates the approval process with other relevant authorities.relevant authorities.
Avedøre wind turbines, the approval processAvedøre wind turbines, the approval processBefore the EIS and the application for the wind turbines were submitted to the ENS, DONG Energy was in close contact with several stakeholders for contributions, and the below follow‐up committee was established, which among others include :committee was established, which among others include :
• Municipality of Hvidovre• Avedøre Wastewater Services• AV Miljø (waste deposit)A d k CHP l• Avedøreværket CHP plant
• The local dike guild• Representatives for the industrial area at Avedøre Holme• The local wind turbine guild – Hvidovre VindmøllelaugThe local wind turbine guild Hvidovre Vindmøllelaug• Brøndby Harbour, yacht club/kayak club.
Furthermore, sail trips to the Middelgrunden were arranged to visit a similar project.
From the very beginning, it has been important to involve all stakeholders to create a sustainable project and to hear everyone's point of view – including the external controlling authorities.
Avedøre wind turbines, the approval processEIS for the wind turbines
The focal areas in the EIS were influenced by the follow‐up committee and were intended toThe focal areas in the EIS were influenced by the follow up committee and were intended to disclose the impact on the following environmental aspects:
• Coastal morphological conditions• Marine biological conditions• Marine biological conditions• Bird life• Protected species• Visualisation• Noise• Noise• Wake effect and reflection• Cultural historical conditions• Recreational conditions• Sailing/fishing• Sailing/fishing• Aviation• Planning• Safety.
Of the examined aspects, only the Protected species involve a potential impact:
The green toad.
The toad is listed in Appendix IV of the EU Habitats Directive and is under special protection.
Avedøre wind turbines, the approval processAvedøre wind turbines, the approval process
During the EIA, a meeting was held to inform the public of the preliminary results. After the EIS another public meeting was held to present the final results of theAfter the EIS, another public meeting was held to present the final results of the EIS.
Based on the EIS and hearings of stakeholders the approval for the construction ofBased on the EIS and hearings of stakeholders, the approval for the construction of the Avedøre wind turbines was given by the ENS on 18 November 2008.
The foundations
1200 m3 concrete a piece.
25 x 25m bundplade Approx. 10m offshore
10
Siemens 3.6MW 120m rotor turbine – Denmarks Largest Wind Turbine
Hub height 93m a.s.l.
Turbine
Blade length 58.5m
Rotor diameter 120m
Nacelle weight >230tNacelle weight >230t
Tower weight >300t
11
Annual Energy Yield
Approx. 11GWh per turbine
More than 11% uplift from 107m
Corresponds to 2500 households
12
Ownership and strategic partnerships
Hvidovre VindmøllelaugWind turbine guild DONG Energy
Ownership
PowerPower
Tivoli KLS graphical company Codan
13
Two offshore turbines in Copenhagen – WHY?
Test facility close to our officesImpossible to erect
these turbines h t A d
DONG Energy has
onshore at Avedøre
bought 500 of theseturbines – testing is
crucialOffshore wind is an important part of the no-carbon
t tenergy strategy Positioned nect to the power
plant it symbolises the synergies between the two
Related to COP 15 this is a goodway to show that DONG Energy
synergies between the two
14
way to show that DONG Energy has focus on responsible energy
Thank you for listening
15080304-DONG-LOP-ny forretningsmodel