Auxiliary Equipment of Generator 1

  • Upload
    aadie

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 8/8/2019 Auxiliary Equipment of Generator 1

    1/6

    Auxiliary equipment of generator

    1. Stator air coolers: (water cooling) for cooling of stator, located on the

    periphery of stator.

    2. Oil coolers for thrust, lower and upper bea

    2. Oil coolers for thrust, lower and

    upper bearings: Bearing

    submerged in oil for reduction of

    friction, oil sucked the heat

    produced by bearings and then oil

    cooled by the water cooling system.

    Whole weight of rotating part rest

    upon the thrust bearing.

    Guide bearing: Guide bearing is

    used to hold the shaft in place and

    guide it properly during rotation. It

    also prevents the vertical &

    horizontal movement of shaft during

    rotation. Distance b/w the shaft &

    bearing is in microns.

    Bearing of any kind helps in rotation or movement. Stationary parts dont

    require any kind of bearing as they are stationary with no rotation associate with

    them.

    Each of the thrust bearing and guide bearing (upper & lower) shall be equipped

    with:

    1. Oil level indicator with high & low alarm indicator.

    2. Two dial type thermometers to indicate the temperature of the bearing

    pads & one for that of the oil.

    3. Resistance temperature detector (RTD) located in all balance pads & in

    the oil reservoir.

    4. Oil water contamination detector.

    5. Water flow meters of electro-magnetic induction type shall be provided at

    **Resistance temperature detector (RTD): (RTDs) are temperature sensors that exploit thepredictable change in electrical resistance of some materials with changing temperature. As theyare almost invariably made of platinum, they are often called platinum resistance thermometers(PRTs). They are slowly replacing the use of thermocouples in many industrial applications below600 C, due to higher accuracy and repeatability.

    Auxiliary equipment of

    generator

  • 8/8/2019 Auxiliary Equipment of Generator 1

    2/6

    3. Anti condensation heaters: (Thermostats: - Determine the temperature of

    a system) In order to avoid water condensation during long non-operative

    period of machine, heating elements are installed inside the generator

    housing. These elements are rated for three phase 415 V AC, 50 Hz. Duringthe stoppage or non-operative period of machine, temperature starts

    decreasing gradually as a result, formation of moisture takes place because of

    presence of air cooling system which directly affects the insulation of

    machine. At this instant we used anti condensation heater to stop the

    formation of moisture due to water cooling ducts around the periphery of

    machine. Anti condensation heater will be remain on till the machine attains

    90 % rated speed after that machine temperature would be sufficient to

    ensure the absence of moisture, therefore heater will be get switched off.

    4. Brake/jet system: This system is used for braking, this system used brake

    liner located below the rotor, and Brake system is equipped with LP air

    compressor pressure system (Pneumatic system). Each generator is equipped

    with pneumatically operated asbestos-free brakes of sufficient capacity to

    bring the rotating parts of generator and turbine to stop from 20% rated

    speed in normal condition. Under emergency condition it shall be possible to

    apply the brakes at 50% of rated speed without any damage to brakes and

    break ring. Brakes can be operated from unit control board and brake control

    panel.

    5. High pressure hydrostatic lubrication: This lubrication required at thestarting & stoppage of machine, shaft of the machine is surrounded by a disk

    of metal that hold the shaft on thrust bearing. When shaft starts rotating in

    certain direction, the surface of metal grate with the surface of thrust bearing.

    This will reduce the life of the metal disk as well destroy the thrust bearing. In

    order to prevent the metal disk as well as thrust bearing, Metal disk provided

    with some holes through which oil can be injected to lubricate its surface,

    there by facilitating the movement of metal disk as well as shaft without any

    disturbance.

    For startup-shut down, a high pressure lubrication system shall be

    provided for thrust bearing.

    6. Sole plates, Foundation bolts, Sleeves, Anchor plates: These parts are

    used to fix the stationary parts of the system.

  • 8/8/2019 Auxiliary Equipment of Generator 1

    3/6

    7. Fire protection system: Fire extinguishing device or system. Fire fighting

    system is just outside the generator barrel. The thermostatic temperature &

    smoke detectors are located at the strategic points inside the generator

    housing. Upon sensing smoke, system will generate audible alarm and signal

    for related action through protection system and plant SCADA system.

    8. Carbon dust collection system: The purpose of brushes is to ensure

    electrical connections b/w the rotating commutator & stationary external load

    circuit. The brushes are made of carbon and rest on the commutator. Brush

    pressure is adjusted by means of adjustable springs. If the brush pressure is

    very large, the friction produces heating of the commutator and the brushes.

    On the other hand if it is too weak, the imperfect contact with the commutator

    may produce sparking & impaired by wear. So, carbon dust collection system

    suck carbon dust generated from carbon brushes.

    9. Brake dust collection system: Each generator is equipped with pneumatically

    operated asbestos-free brakes of sufficient capacity to bring the rotating parts of

    generator and turbine to stop from 20% rated speed in normal condition. Brake

    residues must be efficiently sucked by brake dust collector. Dust collection system is

    used to suck brake dust generated during braking action. It is the same as that of

    carbon dust collection system.

    10.Oil, air & water pipes ,fittings, valves ,pressure gauges and flow relay

    11.Piping, tubing & valves: All the internal piping and valves for the following shall be

    included in the scope of the generator manufacturer:

    a. Cooling water inlet, outlet and drain for generator air and oil coolers.

    b. High pressure lubrication oil supply to thrust bearing meant for lubrication during

    start up & shut down of the unit.

    c. Oil fills and drains connections at the bearings.

    Advantages of

    carbon brushes

    1. They lubricate &

    polish the commuator.

    2. If sparking occurs,

    they damage the

    commuator less than

    with the copper

    brushes.

    3. They provide good

    commuataion.

    Disadvantages of carbon

    brushes

    1. The contact resistance is high

    & causes a loss of about 2V.Hence

    they are unsuited for low voltage

    machines in which this forms a

    larger percentage loss.

    2. Due to high voltage drop, the

    commutator must be made larger

    than for copper brushes.

    3. Their low current density

    necessitates large brush holders.

  • 8/8/2019 Auxiliary Equipment of Generator 1

    4/6

    d. Piping for brakes and jacks (mechanical device used to lift the heavy load).

    e. Tubing for connections b/w temperature sensing elements (vapor bulbs) to dial

    type thermometers, pressure gauge tubing.

    12.Creep detector with alarm & tripping control

    13.Metering instruments/devices/ports for SCADA

    14.Couplers for measuring partial discharge: Partial discharge means remnant of air

    bubbles & vacuum in an insulation which left there as a manufacture defect, which

    has to be remove from the point of view of good insulation otherwise it will break

    down the insulation of the system.

    15.Moisture detector system for upper & lower bearing oil: It is a solid state type

    instrument based on resistance principle.

    16.Special lifting and turning devices along with hardware

    17.Electrical brazing/Soldering equipment/devices

    18. Ventilation & cooling system

    Flywheel effect: Flywheel means stored energy. Suppose we suddenly stop the flowing

    of water from head race level or we suddenly close the main inlet valve. As a result the

    whole coupled system (turbine+Generator) speed decreasing gradually but doesnt stop

    suddenly due to inertia or because of stored energy; it is the energy system gains while

    running.

    As the load varies time to time, the speed of the turbine has to be varied in order to meet

    the load requirement. Therefore, during varying period of load, coupled system or

    machine may experience jerk of large extent. In order to avoid the occurrence of jerk,

    flow of water to the turbine has to be varied in such a way that machine doesnt

    experience any kind of vibration or jerk.

  • 8/8/2019 Auxiliary Equipment of Generator 1

    5/6

    For example, if the machine is running at full load, suddenly the load requirement gets

    reduced to 50% of full load, during this switch over, machine experience huge jerk .By

    varying the flow of water to turbine from full load to 50% load ,we can reduce the jerk

    within the tolerable range.

    Run-away speed: Run-away is the max. Speed governor being disengaged, at which a

    turbine would run when there is no external load but operated under full level head

    discharge. The generator shall be designed and constructed in such a way that it will be

    capable of withstanding maximum run away speed as defined by the turbine

    manufacturer, for a period of 30 minutes without incurring damage from stresses under

    such condition. (Runaway speed is 50% of rated speed of turbine in teesta project Rated

    speed-166.67 rpm, max.run away-166.67+83.34(50% of rated speed)=250 rpm)

    **Crawling due to the torque contribution of 7th harmonics mainly (for induction machines)

    **Hunting is the oscillation of rotor about its final equilibrium position due to high speed

    because of weakening of field.

    **Creeping:

    DESIGN CLACULATION

    1. Electrical calculation & characteristics including magnetic circuit

    2. Structural analysis of different generator parts

    3. Foundation loads

    4. Runaway speed

    5. Critical speeds

    6. Strength of all rotating parts to withstand run away speed and vibration.

    7. Number of coolers for stator and all bearings, the normal working pressure

    and pressure drop through the coolers.

    8. GD2 calculations.

  • 8/8/2019 Auxiliary Equipment of Generator 1

    6/6

    9. Coupling bolts size

    10.Stress calculation on shaft and rotor

    11.Size of thrust bearing, effective surface area /specific load on thrust

    bearing with respect to total load (static/dynamic) etc. under worst

    conditions/runaway condition.

    12.Max. Stresses / loads during normal operation, run away speed conditions,

    two phases and three phases short-circuit conditions or single phase earth

    fault at max. Output for which generator are capable of 180 degree and 120

    degree out-of-phase synchronization, magnetic unbalance at rated speed

    with 50% of the poles short-circuited and brake application.

    13.Guide bearing coolers, stator air coolers ,temperature rise calculations

    14.Ventilation of generator.

    15.Size and no. of brake /jack assemblies.

    Classification generator on the basis of bearing location

    1. Umbrella type: Lower bracket-Guide bearing, thrust bearing

    Lower bracket-NO bearing

    2. Semi-umbrella Type: Lower bracket-Thrust bearing ,guide bearing

    Upper bracket- guide bearing

    3. Suspended type: upper bearing-Thrust bearing, lower bracket-guide bearing.

    4. Short coupled: Upper bearing-Thrust & guide bearing, lower bracket-no bearing

    Used for high speed, most

    common, mostly used in hi

    areas

    Rarely

    used

    For small

    project

    For medium

    project