Upload
murad-khan
View
565
Download
11
Embed Size (px)
Citation preview
Auxiliary PRDS System
Auxiliary PRDS System:
Basic Layout
Technical Details
Protections & Provisions
Auxiliary PRDS System:
Basic Layout
Technical Details
Protections & Provisions
P & ID For Aux PRDS System
P & ID
Classification of System
The auxiliary PRDS system is basically divided into four
parts
– The inflow i.e the sources for steam to system
– HT PRDS i.e at higher temperature (15 Bar / 310 0C)
– LT PRDS i.e. at Lower temperature (15 Bar / 250 0C)
– The outflow i.e. the consumption ends
Layout for system
CRH
MS
BFP Interstage attemperation
Inflow HT PRDSUnitised
LT PRDSFor station
Deaerator initial heating
To CRH line for HP casing warmup
Mill inerting
APH soot blowing
Aux BoilerFuel oil atomising
Turbine Gland sealing
Supply to LT PRDS
CEP Attemp
VAM 1 & 2
Inte
rco
nn
ecte
d h
ead
er
for
all
5 u
nit
s Road oil Tanker
SLOP Oil drain heater
HFO heater
Tank floor coil heater
Suction heater
Auxiliary PRDS System:
Basic Layout
Technical Details
Protections & Provisions
Acid Cleaning
• Purpose: Steam will be required initially during the acid cleaning of the unit
• Parameters:
– Acid cleaning : 15 T/Hr / 10 Bar / 300 0C / Intermittent
• Details:
– Cleaning of all the internals of boiler and piping for making it free of foreign
materials, grease, oil and dirt.
– For establishing a protective magnetite layer in the boiler internals
– Removal of thick debris and other foreign material which have been ingressed
during construction phase
Fuel oil coil heater and suction heaters
• Purpose: Steam will be required for heating of HFO for achieving the flow
• Tapping point: LT PRDS
• Parameters:
– Bottom heaters : 1.2 T/Hr / 14 Bar / 250 0C / Continuous
– Suction heaters : 3.1 T/Hr / 14 Bar / 250 0C / Intermittent
• Details:
– Oil is heated in the HFO tanks to achieve the flowability at heater inlet
– In second step the heating is done in the suction heaters
Fuel oil heater
• Purpose: Steam will be required for heating of HFO for achieving the flow
• Tapping point: LT PRDS
• Parameters:
– Fuel oil heaters : 11 T/Hr / 14 Bar / 250 0C / Intermittent
• Details:
– Oil is heated in the oil heater to achieve minimum viscosity for getting effectieve
and complete combustion in the boiler
Atomizing Steam
• Purpose: Steam will be required for atomising fuel oil
• Tapping point: HT PRDS
• Parameters:
– Atomising steam : 6.1 T/Hr / 14 Bar / 300 0C / Intermittent
• Details:
– The steam assists for effective atomisation as required in the application of low
NOX burner.
– This also ensures for a safe operation
Fuel oil unloading
• Purpose: Steam will be required for fuel oil unloading
• Tapping point: LT PRDS
• Parameters:
– Fuel oil unloading : 2.0 T/Hr / 14 Bar / 250 0C / Intermittent
• Details:
– The HFO before unloading needs to be heated up above the flow point
temperature
– The heating needs to be carried out in the truck tanker itself
Mill Inerting
• Purpose: Steam will be required for mill inerting
• Tapping point: HT PRDS
• Parameters:
– Mill inerting : 61 T/Hr / 14 Bar / 300 0C / Intermittent
• Details:
– During routine operation coal is transported to boiler with the help of hot air. The
coal and hot air mixture forms a fire hazardous situation.
– The steam in such condition is utilised as an inerting media
Deaerator initial heating & pegging
• Purpose: Steam will be required for deaerator initial heating and pegging
• Tapping point: HT PRDS
• Parameters:
– Deaerator initial heating : 11 T/Hr / 2 Bar / 300 0C / Intermittent
– Deaerator pegging at 5% MCR flow : 12 T/Hr / 2 Bar / 300 0C / Intermittent
– Deaerator heating during SG under recirculation : 28 T/Hr / 2 Bar / 300 0C / Intermittent
• Details:
– During cold startup the heat will be sourced thorough aux PRDS header.
– Once the CRH parameter is established the source will be switched over to CRH and will be
pegged upto 2.5 bar
– The changeover from CRH to normal source i.e. IPT extraction will be done at about 30% load
– During the turbine trip condition the deaerator will be pegged through CRH line upto 7.45 bar
Turbine Gland sealing
• Purpose: Steam will be required for turbine gland sealing system
• Tapping point: HT PRDS
• Parameters:
– Start up : 8 T/Hr / 13.7 Bar / 300 0C / Intermittent
– At 35% MCR : 1.89 T/Hr / 13.7 Bar / 300 0C / Intermittent
– At 60% MCR : 0.298 T/Hr / 13.7 Bar / 300 0C / Intermittent
• Details:
– During the normal operating conditions the HP-IP turbine will be self sealed and
the leak off will be utilised for sealing of LP turbine.
– During startup the sealing steam will be taken from Aux PRDS in order to
establish vacuum
Air Heater soot blower
• Purpose: Steam will be required for air pre heater soot blowing
• Tapping point: HT PRDS
• Parameters:
– APH soot blowing : 10 T/Hr / 14 Bar / 300 0C / Intermittent
• Details:
– During normal operation condition the soot blowing for APH alongwith furnace
and economiser will be done from the steam tapped from outlet of LTSH header.
– During startup i.e. during oil firing the APH soot blowing will be done by the
steam from Aux PRDS to avoid fire.
Turbine casing warm up
• Purpose: Steam will be required for turbine casing warm up
• Tapping point: HT PRDS
• Parameters:
– Turbine casing warm up : 12 T/Hr / 13.7 Bar / 300 0C / Intermittent
• Details:
– As per the OEM recommendation if the Inner metal temperature for first stage is
less than 150 0C then turbine pre warming needs to be conducted prior to turbine
startup. Normally the warming time will be approximately 4 to 5 hrs.
Vapour Absorption Machine
• Purpose: Steam will be required for turbine casing warm up
• Tapping point: LT PRDS
• Parameters:
– VAM : 1.8 T/Hr / 9 Bar / 176 0C / Continuous
• Details:
– There will be 2 AC plants each having 3 VAM (2W + 1S). For cooling unit control
room.
– In VAMthe refrigerant is seperated from the low concentration low temperature
absorbent in the generator by using steam. The tapping point for the same will
be between the interconnection of aux header for unit 1, 2 & 3,4.
Points to be highlighted
• The steam required for acid cleaning for Unit #1 will be taken from Aux boiler but
units followed will be tapped of from Unit # 1.
• During hot startup i.e. after black out the steam for gland sealing purpose will be
catered from MS line through PRDS in order to avoid startup of aux boiler.
• The Aux PRDS will be charged through MS once the MS parameter is achieved at 80
bar and 380 0C. The same will be changed from MS to CRH once the parameter is
achieved to 23.2 bar which is at about 35% TGMCR
• The source for deaerator pegging will be changed from Aux PRDS to CRH once CRH
pressure reaches 16 bar and 320 0C.
Auxiliary PRDS System:
Basic Layout
Technical Details
Protections & Provisions
Protection and Provisions
• The HT PRDS is provided with 3 safety valves having the total
blowdown capacity of 55 T/Hr
• Also thee is a provision for a stub thorugh which a new connection
can be stablished if required in future.
• The HT PRDS can be charged from Aux boiler through a motorise
valve. Whereas the LT PRDS can be charged through a manual
valve having a NRV in line.
• HT and LT PRDS are directly connected through a motorised valves
and no manual isolation valves are provided on either side.
Thank You