Automated Contract Administration
Project
PIP Level II Presentation
byLisa A. Bowden
August 24, 1999
7/30/2019 Automated Contract Admin
2/21
Outline
I. IntroductionII. Project Approach
III. Data ResultsIV. Advantages
V. Disadvantages VI. Implementation Recommendations
2
7/30/2019 Automated Contract Admin
3/21
Introduction
Selected for Contract Administrator position inSeptember 1997
Role of the Contract Administrator Enforcing terms & conditions Ensuring timely deliverables Managing the overall business relationship
3
7/30/2019 Automated Contract Admin
4/21
Introduction (Continued )
What tools are currently available to assist the Contract Administrator? Checklist for Contract Award File Content, NF 1098
(Enclosure 1) Contract Closeout Checklist, NF 1612 (Enclosure 2) Autoclause for generation of solicitations and
contracts Current and planned tools are limited IFMP implementation October 1, 2000
4
7/30/2019 Automated Contract Admin
5/21
Introduction (Continued)
Approach to Contract Administration Become familiar with the requirements and
obligations of both the government and thecontractor
Generate a checklist for each of the major tasksidentified in the contract
5
7/30/2019 Automated Contract Admin
6/21
Introduction (Continued)
Importance to Directorate Provide a baseline for project monitoring and
scheduling Serve as a simple reference sheet indicating the
status of the contract Provide a tool for efficient and effective contract
administration to all contract specialists and/oradministrators at GSFC and standardize proceduresthroughout the entire agency
6
7/30/2019 Automated Contract Admin
7/21
Project Approach
Phase I - Research List of clauses from Autoclause For Cost-
Reimbursement Type Contract Federal Acquisition Regulations (FAR) NASA FAR Supplement Goddard Handbook
Ten Clauses were chosen for demonstration purposes(Attachment A)
7
7/30/2019 Automated Contract Admin
8/21
Project Approach (Continued)
Choice of Clauses and Deliverables Report of Work SF298
NASA Contractor Financial Management ReportingNF 533 New Technology Reporting NF 1679 & DD 882 Financial Report of NASA Property NF 1018
Subcontracting Plan and Reports for SmallBusiness Concerns SF 294 & SF 295
8
7/30/2019 Automated Contract Admin
9/21
Project Approach (Continued)
On-Site Contractor Personnel Requirements andReports GF 24-27
Insurance - Work on Government Installation,Certificate of Insurance
Submission of Voucher for Payment SF 1034
Past Performance Evaluation NF 1680 Exercise of Option SF 30
9
7/30/2019 Automated Contract Admin
10/21
Project Approach (Continued)
Phase II - Options available to implement systemMicrosoft Suite (Access)
Available on all computersIFMP programmed to recognize deliverables attime of solicitation
Award date signals calculation of deliverable
dates Availability of charts from programmed data toplot performanceLink to all possible contract deliverables
10
7/30/2019 Automated Contract Admin
11/21
Project Approach (Continued)
Additional features available Automatic reminders via email
Automatic posting of reports as they arereceived electronicallyCalculation of variance charts from deliverabledates
Automatic posting of final report dates to thecontract closeout milestone schedule
11
7/30/2019 Automated Contract Admin
12/21
12
Data Input Screen
12
7/30/2019 Automated Contract Admin
13/21
13
Milestone Schedule
13
7/30/2019 Automated Contract Admin
14/21
Advantages
Provide a tool for contract administrationBetter service to our customers
Provide more efficient contract administration bylinking pre-award, post-award, and closeoutmilestonesProvide clear and concise documents of contractadministration for our quality recordsProvide new CAs with a guide of key points tomonitorChecklist will be unique and individually tailored toeach contract
14
7/30/2019 Automated Contract Admin
15/21
Advantages (Continued)
Quick glance guidance for outstanding issuesProvide informative data on receipt of various
deliverables and/or outstanding issues Automated reminders could be programmed to notifyCAs through email or another system compatiblewith IFMP
Post milestone schedule on InternetMilestone schedule conversion to variance chartProactive approach to ensure timely deliverables
15
7/30/2019 Automated Contract Admin
16/21
Advantages (Continued)
Tool to assist in contract closeoutLink milestone schedule to closeout milestoneschedule automaticallyProvide a tool for more effective contractadministration at GSFC and standardize proceduresthroughout agencyTie in implementation of milestone schedule with thecurrent implementation of the IFMP system
16
7/30/2019 Automated Contract Admin
17/21
Disadvantage
Implementation Costs Time and labor required to design and program
the software Opportune time to incorporate the beginning of
the new system, IFMP
17
7/30/2019 Automated Contract Admin
18/21
ImplementationRecommendations
Key feature - generation at time of contract solicitationComputer automatically generates dates based on awarddateLink could be made when forms are submittedelectronically to automatically indicate deliverable receivedSoftware for implementation currently available on desktopcomputers
18
7/30/2019 Automated Contract Admin
19/21
ImplementationRecommendations (Continued)
With Managements approval - present to CA meeting forfurther ideas, suggestions, etc.Work with Code 290 for implementationPresent final results to DivisionFinal Implementation
19
7/30/2019 Automated Contract Admin
20/21
Final Recommendation
In an environment of meeting or exceeding our customerrequirements, with a scaled-down workforce, theimplementation of an automated contract administrationchecklist is essential!
20
7/30/2019 Automated Contract Admin
21/21
Questions?
Thank You
21
Conclusion