Andrew Drager · juwi Renewable Energy · Australian Energy Storage Conferenece 04/06/15
Technical and commercial challenges/solutions for delivering
large scale solar PV on Australian mine sites
juwi at a Glance
Wind Energy
1,800 MW of installed capacity;
100 wind parks (840 turbines);
$3.4 billion investment volume.
Solar Energy
1,400 MW of installed capacity;
1,500 PV Installations;
$5.3 billion investment volume.
Company
1,000 employees worldwide;
Top 10 largest solar EPC.18 offices worldwide
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential 3
Sandfire Project
Degrussa Mine:
Mining: Gold and copper
Location: Doolgunna Region, WA
Customer: Sandfire Resources NL
Distance: 900 km North of Perth
Power Supply:
Diesel Generators: 20MW
Operator: 3rd party power station owner
Avg. load: ~ 11MW
Avg. consumption: ~ 100GWh p.a.
4
Sandfire Project
Hybrid Power Plant:
PV-Modules: 10.6 MWp
Tracking: East-West tracking
PV-Inverter: 10 MW
Storage: 4 MW / 1,8 MWh (6 MW peak)
Operator: juwi Australia
Storage tasks:
Spinning reserve
Ramp rate control
Provide frequency support
Power factor correction
Diesel-off mode
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential
5
Sandfire Project
Commercial:
Solar PV: 21 GWh p.a.
Diesel Savings: 5 million litres p.a.
CO2 Savings: 12,000 tonnes p.a.
Financial:
System Cost: $40m;
PPA term: 6 years;
Financiers: non-recourse debt.
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential
6
Mining:
Challenge:
Perceived technical risks (loss of mine production);
Non-core business drain on time and money;
Cost savings are not material;
Little technical understanding of renewable energy.
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential
7
System Cost:
Challenge:
Substantially more engineering;
Financing a higher risk project;
Additional equipment (battery, inverters etc.);
Installation costs (labor, transport etc.);
Remote operation and maintenance.
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential
Electricity Cost
PV vs Diesel Cost
TimeToday
8
3rd Party Power Station Owner:
Challenge:
Lost revenue due to solar;
Risk of damage and/or higher O&M;
Time resources required;
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential
9
Financing:
Challenge:
Higher risk (potential for a stranded asset);
Availability of non-recourse project finance
Due diligence requirements.
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential
10
Solar PV Production:
Challenge:
Soiling losses in dusty region with heavy equipment;
Solar curtailment due to constrained grid;
Longevity of equipment in harsh conditions.
juwi Presentation – Australian Energy Storage Conference 04/06/2015 - Confidential
Thank You for Your Attention!
Andrew Drager
Managing Directror - Australia-South Pacific
juwi Renewable Energies Pty Ltd
Level 1, 33 Queen St.
Brisbane Qld 4000
Tel. +61 7 3194 5052
Mob. +61 408 729 258
www.juwi.com