AusNet Electricity Services Pty Ltd
Electricity Distribution Price Review 2016–20
Appendix 7C: Unit Rates (Public Version)
Submitted: 30 April 2015
Unit Rates
EDPR (PUBLIC)
Issue number 1
Status APPROVED
Approver Suresh Damani
Date of approval 08/04/2015
AusNet Services
EDPR Unit Rates
ISSUE 1 2/ 14
UNCONTROLLED WHEN PRINTED
ISSUE/AMENDMENT STATUS
Issue Number
Date
Description Author Approved by
1 08/04/15 Approved Terry Jong Suresh Damani
Disclaimer
This document belongs to AusNet Services and may or may not contain all available information on the subject matter this document purports to address.
The information contained in this document is subject to review and AusNet Services may amend this document at any time. Amendments will be indicated in the Amendment Table, but AusNet Services does not undertake to keep this document up to date.
To the maximum extent permitted by law, AusNet Services makes no representation or warranty (express or implied) as to the accuracy, reliability, or completeness of the information contained in this document, or its suitability for any intended purpose. AusNet Services (which, for the purposes of this disclaimer, includes all of its related bodies corporate, its officers, employees, contractors, agents and consultants, and those of its related bodies corporate) shall have no liability for any loss or damage (be it direct or indirect, including liability by reason of negligence or negligent misstatement) for any statements, opinions, information or matter (expressed or implied) arising out of, contained in, or derived from, or for any omissions from, the information in this document.
Contact
This document is the responsibility of AusNet Services.
Please contact the indicated owner of the document with any inquiries.
Suresh Damani
AusNet Services
Level 31, 2 Southbank Boulevard
Melbourne Victoria 3006
Ph: (03) 9695 6000
AusNet Services
EDPR Unit Rates
ISSUE 1 3/ 14
UNCONTROLLED WHEN PRINTED
Table of Contents
1 Introduction .................................................................................................................................. 4
2 Basis of Rates .............................................................................................................................. 4
2.1 Methodology ................................................................................................................................................ 4
3 Unit Rates ..................................................................................................................................... 5
3.1 Lines ............................................................................................................................................................ 5
3.2 Stations ........................................................................................................................................................ 7
3.3 Secondary ................................................................................................................................................. 11
3.4 Enhanced Safety Programs ..................................................................................................................... 13
AusNet Services
EDPR Unit Rates
ISSUE 1 4/ 14
UNCONTROLLED WHEN PRINTED
1 Introduction
The purpose of this document is to provide the unit rates that been applied to forecast capital expenditure for the 2016-2020 EDPR and to explain the basis of each of the rates.
All rates are P50 and are presented in $2014/151. A P50 estimate is an estimate prepared at any stage of a
project which has a 50% confidence factor of not being exceeded by cost at completion.
2 Basis of Rates
The basis of the unit rates used to develop the capital expenditure forecast is described in this section.
2.1 Methodology
2.1.1 Lines & Enhanced Safety Programs
The unit rates used to forecast costs of most lines related works, including the majority of the safety related expenditure, are based on the historical rates. These rates are calculated by summing the direct costs incurred for each category of asset replacement over the 12 month period from November 2013 to October 2014
2 and dividing this by the volume of replacement activities.
Where a unit rate has not been developed on this basis, the alternative methodology is noted in the rates tables shown in Section 3.
All rates are the direct cost of undertaking the activity and do not include overheads or finance charges.
2.1.2 Substations
The approach to forecasting capital expenditure categories is explained in the Project Cost Estimating Methodology. This document details the unit rates used in each category of capital expenditure.
The unit rates are compiled based on the project cost estimating spreadsheet (Top-down distribution estimate for option selection only). This spreadsheet is built up using a bottom up approach, with labour and materials itemised individually. The spreadsheet is maintained by Project Development Team.
The following have been adopted in the preparation of the unit rates for works within the substation:
Material costs are based on period contract pricing from suppliers as of April 2014
Design Service Provider (DSP) panel rates have been used to estimate design costs
Installation Service Provider (ISP) services agreement rates for labour and plant rates have been used to estimate construction costs
AusNet Services internal cost i.e. Project Management, Quality Assurance, Site Supervision and Engineering support rates are based on DSP panel rates
Project Components Uncertainty3 (value applied to reference estimate to arrive at P50 outcome)
Further explanation of the project cost estimating database and methodology is contained in the Project Cost Estimating Methodology.
1 2014/15 is the AusNet Service financial year commencing 1 April 2014 and ending 31 March 2015
2 This period was chosen as it was the most recent 12 month period for which unit rates were available.
3 Project Components Uncertainty is a calculation (or estimate) of the variability that occurs in all projects. This variability
arises from uncertainty in pricing or volumes of component activities. The uncertainties are a portion of the difference between
the outturn and assumptions in the reference estimate.
AusNet Services
EDPR Unit Rates
ISSUE 1 5/ 14
UNCONTROLLED WHEN PRINTED
All rates are the direct cost of undertaking the activity and do not include overheads or finance charges.
3 Unit Rates
3.1 Lines
The rates in this section have been used to estimate programs of expenditure associated with replacement of lines assets.
3.1.1 Assumptions
Lines asset replacement works are delivered by a combination of internal and external resources depending upon the region and work delivery volumes. The unit rates are the average across the network and are not reflective of highest or lowest rates.
3.1.2 Limitations
Financial information is not captured at the works specification level. This limits the ability to calculate a historic unit rate specific to some of the asset categories.
It was not possible to split the historic rates between the 3 different pole types, Wood, Concrete or Steel.
Distribution substation replacement costs have been calculated as an average across all types. The cost of replacing a distribution substation varies greatly. A 25 kVA pole type transformer is an order of magnitude less expensive than a 500 kVA kiosk. A change in the mix of substations replaced could result in a materially different replacement cost.
3.1.3 Contractor overheads
A delivery partner is engaged to deliver a significant proportion of lines related capital work in one of the three delivery regions. The contract with this supplier specifies that AusNet Services will pay a component of the supplier’s overhead. The overhead is not included in the unit rates paid to the contractor and is not incorporated into the historical direct costs used to develop the unit rates.
The rates shown in the Table 1 do not incorporate contractor overheads. The overheads have been incorporated into the total costs in the Capex model.
3.1.4 Rates
Table 1- Lines Unit Rates
Category Description Rate Basis and Unit of Measure
Poles - Sub transmission (66 kV)
Complex Structure HV/LV structures including Substation Poles, Switch Poles, Cable Head Poles, Regulator & ACR Poles – Open Wire and ABC conductor
[C.I.C] Per pole
Includes pole top hardware
Simple Structure Single Circuit Intermediate or angle structure - Open Wire and ABC conductor
[C.I.C] Per Pole
Includes pole top hardware
Poles Distribution (22/11/6.6 kV)
Complex Structure HV/LV structures including Substation Poles,
[C.I.C] Per Pole
Includes pole top
AusNet Services
EDPR Unit Rates
ISSUE 1 6/ 14
UNCONTROLLED WHEN PRINTED
Category Description Rate Basis and Unit of Measure
Switch Poles, Cable Head Poles, Regulator & ACR Poles – Open Wire and ABC conductor
hardware
Simple Structure HV/LV Structures – Intermediate/Angles, Strains, Terminations, and Small Substation Poles (Single Phase & SWER Distribution) – Open Wire and ABC conductor
[C.I.C] Per Pole
Includes pole top hardware
Low Voltage (<1 kV) Intermediate, Strain, Termination, Anchor, Tee-off – LV Open Wire or LVABC
[C.I.C] Per Pole
Includes pole top hardware
Aerial Guy Pole/Public Lighting Pole/Column/Service Pole
[C.I.C] Per Pole
Pole – Staking or Reinforcement
Installation of RFD Pole Stakes to reinstate an Unserviceable or Limited Life pole – Sub-transmission, HV and LV poles
Re-butting of an Unserviceable or Limited Life pole – Sub-transmission, HV and LV poles
[C.I.C] Per Pole
Crossarms Sub transmission (66 kV) Intermediate, Strain, Termination, Anchor
[C.I.C] Per Crossarm
Includes associated hardware
High Voltage (22/11/6.6 kV) Intermediate, Strain, Termination, Anchor, Angle, Tee-off, Dressing-Down Crossarm
[C.I.C] Per Crossarm
Includes associated hardware
Low Voltage (<1 kV) [C.I.C] Per Crossarm
Includes associated hardware
Conductor4 Span of Defective Conductor (1 Phase or 3
Phase) Replacement of HVABC Conductor (Per Span > 3 Metres In Length) Replacement of LVABC Conductor - Per Span
[C.I.C] Per span
Distribution Substation Transformers
Replace Defective or Faulted Transformer on Pole Type Substation, or Ground Type Substation
[C.I.C] Per Substation
Switches and ACR (Auto Circuit Recloser)
High Voltage [C.I.C] Per Switch
Low Voltage Services
Overhead Service Line From Pole to Installation
[C.I.C] Per Service
Average of proactive (planned) and reactive (replace on failure)
Surge Arresters Line Class [C.I.C] Per Surge Arrester
Voltage Regulators All [C.I.C] Per Regulator (3 phases)
4 For programmed conductor replacement, refer to section 3.4.2.
AusNet Services
EDPR Unit Rates
ISSUE 1 7/ 14
UNCONTROLLED WHEN PRINTED
3.2 Stations
The rates in this section have been used to estimate programs of expenditure associated with replacement of stations assets. These assets are located within the zone substations used to transform sub-transmission voltages to distribution voltages. Rates in this section are inclusive of civil, primary equipment and associated secondary works, unless otherwise specified.
3.2.1 Allowances
The following items have been allowed for within the stations unit rates:
Decommissioning and removal of existing equipment
Supply, installation, testing and commissioning of equipment
Earthworks, foundations and structures (where applicable)
Cabling (secondary and power) (where applicable)
Protection and control associated with the equipment including interfacing works (where applicable)
Interplant connections
Earthing modifications
Operational outage costs (i.e. planning preparation of outages & network switching)
Design
AusNet Services internal labour costs ( i.e. Project Management, Quality Assurance, Site Supervision and Engineering support)
Contractor indirect costs.
3.2.2 Exclusions
The following items have been excluded from the stations unit rates:
Planning and building permit applications
Land acquisitions and easement creation
Site surveys, geotechnical investigations and reports
Additional cable ducts or cable trenches - assume existing is suitable and sufficient capacity
Removal of contaminants such as asbestos, PCBs and contaminated soil
Costs associated with any environmental works
Communication systems and schemes
Management reserve5
Cost escalations
Financing cost and corporate overheads
Written-down values
Spares
Operations and maintenance costs.
5 An amount of funds, budget, or time needed above the estimate to cover the costs of unforeseen factors related to the
delivery of the project objectives, which are not provided for elsewhere in the total job costs. Management Reserve is to be
administered at program level. These can include but are not limited to the occurrence of an unplanned or unforeseen event
such as a natural event or a major safety incident and the change to planned assumptions, stakeholder issues (outage
restrictions, community) and delayed access to site, industrial relations issues external to the Project / Program, and
contractual issues or claims.
Management Reserve is the difference between P(90) (An estimate prepared at any stage of a project which has a 90%
confidence factor of not being exceeded by cost at completion) and P(50) outcomes.
AusNet Services
EDPR Unit Rates
ISSUE 1 8/ 14
UNCONTROLLED WHEN PRINTED
3.2.3 Primary Rates
Table 2 provides the unit rates for 22 kV stations primary equipment.
Table 2 – 22 kV Primary Equipment Unit Rates
Unit Rate Basis
Capacitor Bank – 6 MVAr with 7% (19.3 mH) current limiting series reactor
[C.I.C] Includes:
o Power cable and conduit (30m)
o New capacitor bank protection scheme and integration
o Safety fencing
Capacitor Bank Can – 603 kVAr [C.I.C]
Reactor (For Capacitor Bank) - 7% (19.3 mH) current limiting series reactor
[C.I.C]
Circuit Breaker: Dead Tank – Outdoor, 22 kV 2000A 31.5kA, 4 5 A bushing current transformer cores per phase: 0.2PX160, R0.55 on 1600/5
[C.I.C] Includes:
o Duplicated secondary cabling to Interface Termination Cubicle (ITC)
Neutral Earthing Resistor – 22/12.7 kV, 1600 A/10sec, Outdoor, single phase 8 ohm neutral earthing resistor with bypass Circuit Breaker and series Current Transformers and Voltage Transformers
[C.I.C] Includes:
o Neutral Current Transformers and isolator
o New earth fault back up protection scheme and integration
o Provision for SCADA RTU modifications
o Provision for Digital Interface Cubicle modifications
o Duplicated secondary cabling to ITC
o Monitoring accessories
o Power cable and conduit (40m)
Neutral Earthing Compensator [C.I.C] Includes:
o Power cabling (30m)
o Termination frame
o NEC protection and control scheme
Isolator: Underslung – 1600 A, 31.5 kA
[C.I.C] 3 phase, Hook stick operated
Includes:
o 8.9kN station post insulators
o Earthing receptacles (two sets)
Isolator: Rotary Double Break – 1600 A, 31.5 kA
[C.I.C] 3 phase, ganged manual operation
Includes:
o Manually operated earth switch
o Earthing receptacles (one set)
Current Transformer – 2000 A, 31.5 kA
[C.I.C] 3 phase set
Includes:
AusNet Services
EDPR Unit Rates
ISSUE 1 9/ 14
UNCONTROLLED WHEN PRINTED
Unit Rate Basis
o Marshalling box and secondary cabling to ITC
Voltage Transformer – 24 mS, 0.5M/1P
[C.I.C] 3 phase set
Includes:
o Marshalling box and secondary cabling to ITC
Surge Arrester – 31.5 kA short circuit withstand current, 10 kA peak nominal discharge current
[C.I.C] 3 phase set
Modular Switchroom – Including switchgear
[C.I.C] Approx. 4.5m x 12.5m steel framed building
Excludes:
o Demolition of existing switchroom
o 22kV power cabling
o DC supply and batteries
Building includes:
o Air conditioning system
o Fire detection system
o Control room complete with ITC
Protection panels included:
o Four (4) 22kV feeder protection
o Two (2) Capacitor bank protection
o X & Y Bus protection
o CB failure protection
o Bus Tie protection
Switchgear includes:
o One (1) 2000A, 20kA transformer panel including 5, 5 A current transformer cores
o Four (4) 1250A, 20 kA feeder panels including 2, 5A current transformer cores
o Two (2) 1250A, 20 kA capacitor panels including 2, 5A current transformer cores
o One (1) 2000A, 20 kA bus tie panel including 5, 5A current transformer cores
o Single bus with a 50 VA voltage transformer 0.5M/1P
AusNet Services
EDPR Unit Rates
ISSUE 1 10/ 14
UNCONTROLLED WHEN PRINTED
Table 3 provides the unit rates for 66 kV stations primary equipment.
Table 3 - 66 kV Primary Equipment Unit Rates
Unit Rate Basis
Power Transformer – Yyn0(d11), 66/22kV, 15/20 MVA with 4hr 30 MVA emergency rating, 10% nominal impedance, tapping range -26% to +5 %
[C.I.C] Reuse footings and firewall
Excludes protection upgrades
Includes:
o Removal of existing transformer
o Neutral isolator, neutral current transformers and associated isolation structure
o 66kV surge arresters
o Secondary cabling to ITC
Circuit Breaker: Dead Tank – 3150A, 40kA, 4 5A bushing current transformer cores per phase: 0.1PX1000, R1.6 on 3000/5
[C.I.C] Includes:
o Duplicated protection and control schemes, integrated into existing station
o Secondary cabling to ITC
Isolator: Underslung – 2000A, 31.5kA
[C.I.C] 3 phase, Hook stick operated
Includes:
o 12.5kN station post insulators
o Earthing receptacles (two sets)
Isolator: Rotary Double Break – 800A, 25kA
[C.I.C] 3 phase, ganged manual operation
Includes:
o Manually operated earth switch
o Earthing receptacles (one set)
Current Transformer – 2000A, 31.5kA, 5 5A cores per phase, 0.14PX700, R1.1 on 2100/5
[C.I.C] 3 phase set
Includes:
o Marshalling box and secondary cabling to ITC
Voltage Transformer - 24mS, 0.5M/1P
[C.I.C] 3 phase set
Includes:
o Marshalling box and secondary cabling to ITC
Surge Arresters – 31.5kA short circuit withstand current, 10kA peak nominal discharge current
[C.I.C] 3 phase set
Bus section – 100mm OD, 6mm WT welded aluminium tube, 2500A rating.
[C.I.C] Includes:
o 8 metre section of 3 phase rigid bus
o 12.5kN station post insulators
o Support structure and associated footings.
AusNet Services
EDPR Unit Rates
ISSUE 1 11/ 14
UNCONTROLLED WHEN PRINTED
3.3 Secondary
The rates in this section have been used to estimate programs of expenditure associated with secondary assets. These assets are located within zone substations and include items such as line protection, transformer protection and capacitor bank protection.
3.3.1 Allowances
The following items have been allowed for in the secondary unit rates:
Decommissioning and removal of existing equipment
Supply, installation, testing and commissioning
Control cabling from cubicle to ITC
Intercubicle wiring
Cubicle earthing and cable tray
Modification and interfacing works
Design
AusNet Services internal labour costs ( i.e. Project Management, Quality Assurance, Site Supervision and Engineering support)
Contractor indirect costs
3.3.2 Exclusions
The following items have been excluded from the secondary unit rates:
Building modification works
Removal of asbestos
Communication systems and schemes
Non-standard / site specific installations
Management reserve
Cost escalations
Financing costs and corporate overheads
Written-down values
Operation and maintenance costs
Spares.
3.3.3 Secondary Rates
Table 4 provides the unit rates for stations secondary equipment.
Table 4 - Secondary Equipment Unit Rates
Unit Rate Basis
66kV Line Protection [C.I.C] X & Y modular scheme includes
o Current differential protection
o Back up distance protection
o Auto reclose
o Circuit breaker failure
o Circuit breaker management
o Circuit breaker control
o Line instrumentation quantities
AusNet Services
EDPR Unit Rates
ISSUE 1 12/ 14
UNCONTROLLED WHEN PRINTED
Unit Rate Basis
66kV Autoclose [C.I.C] Four (4) bus arrangement
Tap matching scheme
Autoclose panel includes:
o Autoclose relay
o Interface/tap matching relay
22kV Feeder Protection [C.I.C] Modular scheme includes
o Two (2) feeders on panel
o Overload protection
o Sensitive earth fault protection
o Auto reclose
o Circuit breaker management
o Circuit breaker control
o Feeder instrumentation quantities
66/22 kV Transformer Protection [C.I.C] X & Y modular scheme includes
o Differential Protection
o Overload
o Circuit breaker failure
o 66 kV circuit breaker management
o 66 kV circuit breaker control
o Transformer instrumentation quantities
22 kV Bus Protection [C.I.C] X & Y modular scheme includes
o Differential protection
o Bus Overload
o 22 kV Transformer and bus tie:
Circuit breaker failure
Circuit breaker management
Circuit breaker control
22 kV Earth Fault Backup Protection
[C.I.C] Earth Fault Backup Protection
22 kV Cap Bank Protection [C.I.C] X & Y modular scheme
o Overload protection
o Circuit breaker management
o Circuit breaker control
o Instrumentation quantities
Zone Substation RTU [C.I.C] SCIMS System – Large (3 rack RTU)
Includes:
o SCIMS Panel
o HMI
o GPS clock
o DSP Mapping & Design
o Testing
o NOC Review & Display Implementation
AusNet Services
EDPR Unit Rates
ISSUE 1 13/ 14
UNCONTROLLED WHEN PRINTED
3.4 Enhanced Safety Programs
The rates in this section have been used to estimate programs of expenditure associated with the Enhanced Safety Program.
3.4.1 Assumptions
Safety program works are delivered by a combination of internal and external resources depending upon the region, the program and work delivery volumes. The unit rates selected are the average across the network and are not reflective of highest or lowest rates.
3.4.2 Rates
Table 5 provides unit rates for enhanced safety program activities.
Table 5 - Enhanced Safety Programs Unit Rates
Category Description Rate Unit of Measure
Basis of Rates
Installation of Armour Rods and Vibration Dampers
Install or replace armour rods and vibration damper on the following structures
SWER Intermediate
SWER Angle
Intermediate Single Phase
Intermediate Three Phase
Angle Single Phase
Angle Three Phase
[C.I.C] Per Structure
Based on the historical average rate and mix of activities.
Conductor Replacement
Proactive program to replace conductor:
- Steel
- Copper
[C.I.C]
Per km
Average unit rate based on historic average cost
EDO Fuse Unit Replacement
Replacement of EDO to Boric Acid unit on the following structures
SWER
Single Phase
Three Phase
[C.I.C] Per Unit Based on reported volumes and costs in annual RINs 2011 to 2013
Animal Proofing
Animal Proofing of the following
The retrofitting of an existing concrete pole substation structure with Animal Proofing materials
The retrofitting of an existing complex (termination, strain, anchor) High Voltage or wood pole substation structure with Animal Proofing material
The retrofitting of an existing pole or ground type substation or Cable Head Pole structure with minor
[C.I.C] Per Structure
Average rate based on a mix of structure types and both full and minor animal proofing.
AusNet Services
EDPR Unit Rates
ISSUE 1 14/ 14
UNCONTROLLED WHEN PRINTED
Category Description Rate Unit of Measure
Basis of Rates
Animal Proofing materials.
Overhang Removals
Replacement of bare overhead wire classified as a 56M with High Voltage Aerial Bundled Cable
[C.I.C] Per 56M span
Based on historical rate of undertaking similar activity.
Line Clearance
Rectification of Line Clearance issues
[C.I.C] Per Span Based on historical cost of rectifying line clearance issues.
High Voltage Underground Cable Installation Program
Replacement of High Voltage Aerial Bundled Cable with High Voltage Underground cable
[C.I.C] Per km Based on forecast expenditure from the current High Voltage Underground Cable Installation Program