August 2014
Lee, Myung Key
KEPCO International Nuclear Graduate School
Contents
1. Overview of Localization Program
2. Localization Experience
3. Development of Korean NPP
4. Recommended Program on Localization
Overview of Localization Program
4
History of Technology Development
Late 1990s
2000s 1980s
Introduction
of NPP(‘71~
Kori 1
Kori 2
Wolsong 1
Early 1990s
Establishment of
Localization (`~’85)
Kori 3&4
Ulchin 1&2
Yonggwang 1&2
1970s
Technology Self-reliance
Turn-Key Approach
Component Approach
OPR1000
Development (`95)
Yonggwang 3&4
OPR1000 Const.&Opr.
APR1400
Development (`02)
Ulchin 3,4,5&6
Wolsong 2,3&4
Yonggwang 5&6
Shin-Kori 1&2
Shin-Wolsong 1&2
2010s
APR1400 Construction
APR+
Development (`15)
Shin-Kori 3&4
(Under Const.)
Shin-Ulchin 1&2
(Under Const.)
Shin-Kori 5&6
(Planning)
Shin-Ulchin 3&4
(Planning)
4
5
1970's
Introduction of NPP
Turnkey approach
1980's
Accumulation of NPP
Technology
Component approach
1990's
Technology Self-Reliance
Development of OPR1000
Development of APR1400
Foreign - Local Joint Design, Joint Manufacturing
- Foreign : Prime Contractors
- Local : Sub-contractors
Step by Step Approach
Foreign Contractors
Led by Local Contractors
- Local : Prime Contractors
- Foreign : Sub-contractors
Basic Policy
6
Basic Policy
1970's
1st Generation
1980's
2nd Generation
1990's
3rd Generation
Turn-Key Non Turn-Key Non Turn-Key
KRN #1,2
WSN #1
KRN #3,4, YGN #1,2,
UCN #1,2 YGN #3,4, UCN #3,4
Foreign Contractor
Local Labor Supply
Foreign Prime Contractors
Local Sub-contractors Local Prime Contractors
Foreign Sub-contractors
Technology
Dependency
Technology
Accumulation Technology
Self-Reliance
Evolution of Project Structure
■ NPP Introduction Program
■ Technology Accumulation Program
■ Korean Technology Development Program
Localization Experiences
8
Preparation for 1st NPP
Tasks
NPP Steering Committee
NPP Feasibility Study Team
Candidate Sites Survey
Manpower Development
Nuclear Technology Survey
Site Selection
Reactor Type Selection
Contract
Construction Start
’62 ’63 ’64 ’65 ’66 ’67 ’68 ’69 ’70 ’71
10 years
NPP Introduction Program
NPP Introduction Program
1st NPP, Turnkey Approach
Bidding & contract scheme
Kori #1 : International open bidding, Turnkey
Kori #2, Wolsong #1 : Sole source bidding, Turnkey
Division of responsibility
Prime contractor
Project management, including quality control
Design and Engineering
Equipment & material supply
Construction & Start-up
Owner (KHNP)
Site preparation & miscellaneous building construction
Supply of sand, cement, etc.
Participation in Start-up
NPP Introduction Program
Localization with Turnkey Approach
No experience in NPP construction
Fully dependent on foreign technology due to limited infra-
structures to promote localization
No localization & technology transfer programs, except for
operation & maintenance
Localization achieved through implementation of projects
Kori #1 : 8.0 %
Kori #2 : 12.9 %
Wolsong #1 : 13.9 %
11
Project structure
♣ Project implemented by foreign prime contractor
Prime Contractor
W/H or AECL
NSSS T / G A / E Construction BOP Commission-
ing
Foreign Foreign Foreign/Local Foreign/Local Foreign Foreign
Owner
KHNP(KEPCO)
NPP Introduction Program
12
Technology Accumulation Program
Outline
Kori #3,4, Yonggwang #1,2, Ulchin #1,2
Component approach
International open bidding
Major Policies
Perform under the leadership of government & KHNP
Key role in project management by KHNP
Set-up localization execution committee & implement long-
term localization plan
Establish national localization policy for project management,
equipment supply, construction & start-up
Overview
13
Technology Accumulation Program
♣ Overall Project Management performed by Owner
Owner (KHNP) Foreign Technical
Consultant
NSSS
Foreign Prime Contractor
T / G
Foreign Prime Contractor
S / U
KHNP
BOP
KHNP
A / E
Foreign Prime Contractor
Construction
Local Constructor
Local
Doosan
Local
KOPEC
Project Management
Local &
Foreign
Project Structure
14
Machinery Industry Promotion Act (1967~)
Long-term Power Development Plan
MOCIE / KHNP
Program for machinery Industry Promotion
MOCIE
Submittal of Equipment Procurement Sources
KHNP
Decision of Procurement Sources
Localization Execution Committee Items not to be localized Items to be localized
Localization
Local Suppliers
Import
Foreign Suppliers
Technology Accumulation Program
Imported Item Report and Approval System
15
Technology Accumulation Program
■ Major components supplied solely by Doosan
■ BOP supplied by open bidding under responsibility of KHNP
■ Enhancing manufacturing capability by categorizing
equipment procurement source
CASE I : Local Supply
CASE II : Local/Foreign Joint Supply
CASE III : Foreign Supply
■ Construction by local companies as prime contractor
■ No technology transfer program for A/E and NSSS / TG
design, except for partial participation in the projects in the
form of OJT
Localization Program
16
Technology Accumulation Program
44
35
-
13
-
14
Design (%)
Equipment (%)
-
8
46
10
20
30
40
50
KRN #1 KRN #2 WSN #1 KRN
#3,4
YGN
#1,2
UCN
#1,2
Design (%) Equipment (%)
(%)
40
37
29
Results of Technology Accumulation Efforts
17
Goal : 95% by 1995
MOCIE KHNP
Establish Nuclear Technology
Self-reliance Program (1984)
Overall PM
KHNP
Maintenance
KPS
Construction
Local Constructor
Start-Up
KHNP
NSSS, T/G
Doosan
Design & Engineering
KOPEC
BOP
Local/Foreign Suppliers
Fuel
KNFC
Korean Technology Development Program
Basic Strategy
18
Korean Technology Development Program
Experience feedback from Previous NPPs
Implementation of Yonggwang #3 & 4 Project
Technology Transfer Contract
Technology Development
- Design Evaluation & Qualification
- Equipment Manufacture and Test
- Step by Step, Project by Project
Technology Accumulation
T/T Documentation
Acquisition of
Tech. Document Manpower Qualification
Manufacturing Design & Engineering
Project Management
Training Technical Consultant
Nuclear
Technology
Self-
reliance
Implementation Plan
19
Technology Self- reliance Program
Project Contract (YGN 3&4) - Phase I : S&L/WEC lead - Phase II : KOPEC lead
Technology Transfer Contract (YGN 3&4)
- Reference Document and Drawing - Computer Program - Training
Technology Localization - Utilizing reference document transferred from S&L/WEC
- Developing KOPEC reference document
Achieved Technology Self- reliance
Korean Technology Development Program
Engineering Technology Development
20
Year '80 '85 '90 '95
Self-Reliant A/E
Basic Design: Local Detail Design: Local
UCN #3,4 Self-Reliance Implementation
Basic Design: Local + Foreign Detail Design: Local
YGN #3,4 Self-Reliance Preparation
Basic Design: Foreign
Detail Design: Foreign + Local
KRN #3,4, UCN #1,2, YGN #1,2 Foreign A/E
KRN #1,2
Korean Technology Development Program
Self-Reliance
Progress
Partial
Foreign Manpower
Participation
Self Commitment
of Basic/Detail
Design Supported
by Foreign
Manpower Aux System Design : Intake/Discharge,
Water Treatment, Aux Boiler sys., SWRD etc
Main System Detail Design :
Small Pipe Design, Stress Analysis etc Self Commitment of Minor Facilities
Evolution of Engineering Technology
21
Scope of Technology * Component Design * Manufacturing * Project Management
Licensed
Products
* Reactor Vessel * Reactor Vessel Internal
* Steam Generator * Control Element Drive Mechanism
* Pressurizer * Reactor Coolant System Support
* Primary Piping * Refueling Equipment
Objective
To obtain the capability of component design, manufacturing and project
management for NSSS and T/G
Technology Transfer Agreement was made between Doosan and WEC(NSSS)/GE(T/G)
To provide ; 1) Technical Documents & Computer Codes
2) On the Job Training
3) Technical Support & Consultation
Equipment Manufacturing Technology Development
Korean Technology Development Program
22
Korean Technology Development Program
Contract: Local
UCN #3,4 Main Contract: Local
Sub Contract: Foreign
YGN #3,4
Cement, Aggregate
BOP (PP, HVAC, SW/YD...)
Main Equip. ( Partial Ass'y of S/G, T/G...)
NSSS, T/G, BOP
(T/T contract with
Foreign Contractors)
NSSS, T/G, BOP
Year '80 '85 '90 '95
Main Contract: Foreign
Sub Contract: Local
KRN #3,4, UCN #1,2, YGN #1,2 Foreign Supply
KRN #1,2
Localization
Progress
NSSS : Nuclear Steam Supply System, T/G : Turbine/Generator,
BOP : Balance of Plant, A/E: Architect Engineering
Evolution of Equipment Manufacturing
23
Korea Nuclear Fuel
Co.,Ltd ( KNFC ) KAERI
TIC with SIEMENS
License agreement
for manufacturing of
Fuel Assembly and
core components
Training
Supervisory services
during installation
ESC with SIEMENS
Basic design of the
plant
Foreign equipments
Upon request : Delivery
of FA structural
components and
conversion services
TIC with SIEMENS
License agreement for
FA design, engineering
& core management.
Joint design in 1989/90
Technical information
Training
Licensing and Localized Equipment
Construction and Installation
Korean Technology Development Program
TIC : Technology Introduction Contract
ESC : Engineering Support Contract
FA : Fuel Assembly
Fuel Manufacturing Technology
Development of Korean NPP
■ Development Program
■ OPR1000 Development
■ APR1400 Development
25
2010 2005 2000 1995 1990 2019 1980
APR 1400 (construction
/planning) Shin-Ulchin 1&2
APR 1400 Nth
Shin-Kori 3& 4 APR 1400 Development
Shin-Kori 1& 2
Shin-Wolsong 1& 2
Improved
OPR 1000 (construction)
Ulchin 3&4
Yonggwang 3&4
Yonggwang 5&6
Ulchin 5&6
OPR1000 (Operation)
Development Program
26
Applied Project
Yonggwang #3,4 and the following projects
Contract scheme
Prime contractors : Local companies
Doosan, KOPEC, KNFC were selected as the prime contractors to
promote technology accumulation
Sub-contractors : International open bidding
Technology transfer to Korean companies was one of the major
bidding requirements
ABB-CE, GE and S/L were selected as the sub-contractors
because of their favorable technology transfer conditions
OPR1000 Development
Development Outline
27
OPR1000 Development
Owner (KHNP)
NSSS
DOOSAN / KOPEC
T / G
DOOSAN
BOP
KHNP
A / E
KOPEC
Construction
Local Constructor
ABB-CE
Project Management
GE S & L
Start-Up
KHNP
Local / Foreign
Implementation Structure
28
Experience of Previous Projects (KRN #1, KRN #2, KRN #3,4, YGN #1,2)
OPR1000
(UCN #3,4, YGN #5,6, UCN #5,6)
Accumulation of Technology Projects
(YGN #3,4)
• Implementation of Projects
- Joint Design/Manufacturing
- Independent Procurement,
Project Management
• TT for Design/Manufacturing
- Reference Document
- Computer Code
- Training & Consultant
• Self Technology Development
- Design Verification
- Repetitive Design
- R&D
Development Methods
OPR1000 Development
29
In Operation
1000MWe
COD: 1995
In Operation
1000MWe
COD: 1998
Technology Transfer
Reference
Project
YGN 3&4 (1000MW)
OPR
T/G Perry#2
(GE,1000MW)
PLANT DESIGN Yonggwang#1&2,
Byron & Braidwood
(KOPEC/S&L,1000MW)
NSSS Palo Verde
(CE,1300MW)
Replication
of
OPR UCN 3&4
(1000MW)
ERPI URD
ADF
Design
Improvements
NPPs
Experience
Feed-Back
Latest Codes & Std
Construction & Operation
- YGN # 5,6, UCN # 5,6
- Shin KRN #1,2
- Shin WSN #1,2
Development Process
OPR1000 Development
30
Design Features of OPR1000
2 Loop, 4 Pump RCS Design Power Level : 1,050MWe/2,825MWt Plant Design Life : 40 years Plant Availability : 80~87%
Advanced Design Features
Human Factors Engineering
Design against Severe Accidents
Leak Before Break (LBB) Concept
Increased Operability and Maintainability
Lower Occupational Radiation Exposure
31
APR1400 Development
■ Evolutionary ALWR based on OPR1000 and System 80+
■ Development Period : ’92 ~ ’02,
■ Standard Design Certificate : May 2002
■ First Concrete of First Commercial Plant (SKN #3,4) : Oct., 2008
Under Const. : 4 units
- SKN #1,2 (’12/’13)
- SWN #1,2 (’13/’14)
In Operation : 8 units
- YGN #3,4 / UCN #3,4
- YGN #5,6 / UCN #5,6
Under Const. : 4 units
- SKN #3,4 (’14/’15)
- SUN #1,2 (’16/’17)
Improved
OPR1000
OPR1000
1,000 MWe 1,000 MWe
APR1400
1,400 MWe
EPRI URD/EURD
KURD System. 80+ (CE, 1300MWe)
ADF/PDF
Latest Code & Std
Development Outline
32
Korea Brand Standard Nuclear Power Plants
APR1400 OPR1000
Pro
ven
Tec
hn
olo
gy
Power : 1,000 MWe
Life Time : 40 years
Const. : 51 months
Seismic : 0.2g (5.6)*
Evo
luti
on
ary
Gen
-III
Rea
cto
r
Power : 1,400 MWe
Life Time : 60 years
Const. : 54 months
Seismic : 0.3g (7.0)*
Advanced Power Reactor 1000 development currently under way
Recommended Program on Localization
■ Localization Program
■ Typical Program for Localization
34
Localization Program
Establishment of long-term Localization Program based
on the long-term energy plan led by Government &
project owner
Selection of one type of NPP Technology and repeated
order for standardization
Set-up of Localization Planning Committee
Set-up of policies for promoting national participation
Improvement of local industry’s capability
Basic Guideline
35
Localization Program
Connected with National Industry Development Plan
Covering all industrial sectors: heavy machinery, electrical,
chemistry, etc. as well as nuclear industry
Government’s strong support
Legislation and financial assistance to promote systematic
cooperation among local suppliers and plant owner
Assessment of local industries
For A/E, NSSS (Design & Manufacture), T/G, BOP, Construction,
Start-up and Overall Project Management
Long Term Plan
36
Government Long Term Energy Plan
Long Term Electric Power Development Plan
- Fossil (Coal, Oil, Gas, etc), Hydro, etc
- Nuclear Power Plant
Long Term NPP Development Plan
- 1st
NPP Introduction Plan
- NPP Technology Development Plan
NPP Technology Development Plan
- Infrastructure Development
- National Participation and Capacity Building
- Localization and Technology Self Reliance
Implementation Sequence
Localization Program
37
Organize project structures and responsibilities
Define scopes and responsibilities for government
authorities and related organizations
Decide leading entity for nuclear power plant construction
Close coordination and teamwork among Government,
project leading entity, local and foreign vendors
Active participation of local vendors
Localization Program
Implementation Program
38
Promote cooperative relationship with foreign partner that
possesses the following:
Proven technology with operational experience
Experience in technology transfer and equipment localization
through NPP projects
Ability to construct and operate NPPs most safely and
economically
Ability to arrange favorable financing
Localization Program
Implementation Program
39
Establishment of long-term localization plan led by
Government & Owner
Establishment of NPP standardization program
Localization by step-by-step approach
Importance of owner's overall Project Management
capability
Close cooperation with experienced foreign companies
Localization Program
Implementation Program
40
Typical Program for Localization
1st Step Technology Accumulation
- Implemented by foreign supplier with Local
participation
3rd Step
2nd Step Foreign - Local Joint Implementation
- Implemented by Owner with foreign assistance
Accomplishment of technology self-reliance
- Implemented by local prime contractor with
foreign assistance as sub-contractor
Program Outline
41
■ Turnkey contract for first two units
Local companies will participate for limited areas as sub-
contractor to foreign contractor
Starting with civil work and equipment installation
Field engineering as sub-contractor
Civil and Structural bulk material, non nuclear equipment
Construction as sub-contractor
Commissioning support
1st step : Technology Accumulation
Typical Program for Localization
42
Items of Localization Ratio
1. Equipment Supply 20%
- Low Pressure Heat Exchanger, Tanks, Piping in Turbine Building
- Low Voltage Cables, Lighting System
2. Design & Engineering
- Field Civil Engineering (limited portion)
3. Preliminary & Supplementary Works
- Site Preparation, Construction Offices
- Power Supply System, Tele-Communication Facilities
4. Construction Material & Installation
- Aggregate, Cement, Steel Material, Painting
- Equipment Installation, Cable Installation & Termination
5. Start-up Material Supply & Support
Typical Program for Localization
43
For 2nd and 3rd projects
Implemented by Owner with foreign assistance
Local industry will acquire further skill and expert knowledge
Joint design and extend to nuclear grade equipment
manufacturing
Joint design for power block
Joint manufacturing of nuclear grade equipment in NSSS
Construction by local contractor with foreign assistance
Start-up by Owner with foreign assistance
2nd step: Joint Implementation
Typical Program for Localization
44
1. Civil Work & Building 40%
- Design of Power Block & Auxiliary Building
- Construction Planning and Management
2. Equipment Supply
- Heat Exchanger, Tanks, Piping in NSSS
- Cranes & Hoist
- HVAC Duct & Stack
- Turbine Lubricating Oil System
- Fuel Storage Rack
- Cable, Lighting System, Grounding System
3. Design & Engineering
- Some Portion by Joint Participation
4. Construction & Startup
- With Foreign Assistance
Items of Localization Ratio
Typical Program for Localization
45
For 4th and 5th projects
Establishment of technology self-reliance program
Development of standard NPP
Expected to participate in most areas of project:
Design by local prime contractor
Local supply of nuclear grade equipment
Construction by local prime contractor
Commissioning by Owner
3rd step: Technology Self-reliance
Typical Program for Localization
46
1. Equipment Supply 60%
- Safety & Non Safety Pump, Control Valve in NSSS
- Condenser
- Radwaste Processing System
- DC Power System, Auxiliary Motor
- Transformer, AC Power Distribution System
- Instrumentation & Control System
2. Design & Engineering
- Joint Implementation
3. Construction & Startup
- Technical Consultant
Items of Localization Ratio
Typical Program for Localization
47
Case Study and Experiences on Local Industrial
Involvement in supply chains in Korea