47
Heat Treating Task Group Audit Handbook Released: December 01, 2009 PERFORMANCE REVIEW INSTITUTE 161 THORN HILL ROAD WARRENDALE, PA 15086-7527 724-772-1616

Audit Handbook 01-Dec-09 Doc Mc

Embed Size (px)

Citation preview

Page 1: Audit Handbook 01-Dec-09 Doc Mc

Heat Treating Task Group Audit Handbook

Released:

December 01, 2009

PERFORMANCE REVIEW INSTITUTE 161 THORN HILL ROAD

WARRENDALE, PA 15086-7527 724-772-1616

Page 2: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK HEAT TREATING TASK GROUP ........................................................................................................................................... 1 

Released: ...................................................................................................................................................................................... 1 A. FOREWORD ...................................................................................................................................................................... 3 B. DEFINITIONS .................................................................................................................................................................... 4 C. AUDITING TO NADCAP AUDIT CRITERIA ...................................................................................................................... 9 

C.1  SPECIFICATION ADHERENCE ..................................................................................................................................... 9 C.2  AUDITOR GENERAL GUIDELINES ............................................................................................................................. 13 C.3  SUPPLIER GUIDELINES ........................................................................................................................................... 14 C.4  GUIDELINES FOR TIME MANAGEMENT OF THE AUDIT ................................................................................................ 15 C.5  VERIFICATION OF CORRECTIVE ACTION (VCA) AUDITS ............................................................................................ 16 C.6  SNAPSHOT AUDITS DEFINITION ............................................................................................................................... 16 C.7  SATELLITE AUDITS ................................................................................................................................................. 16 C.8  SPEC CANCELLATIONS & SUPERCESSION ............................................................................................................... 18 C.9  AC7102/S ............................................................................................................................................................ 18 

D. QUALITY SYSTEMS ....................................................................................................................................................... 19 D.1  TRAINING ............................................................................................................................................................... 19 D.2  ELECTRONIC PROGRAM CONTROL AND DATA ACQUISITION ...................................................................................... 19 

E.  GENERAL HEAT TREATMENT ITEMS AND STEELS (AC7102) ............................................................................... 20 E.1  TEST AND INSPECTION ............................................................................................................................................ 20 

E1.1  Room Temperature Tensile Testing ................................................................................................................ 20 E1.1.1  Sub – Contract Machining of RTT Test Pieces ............................................................................................... 20 E1.2  Round Robin Programs for Metallography and Microhardness ....................................................................... 21 E1.3  Surface Contamination Testing ....................................................................................................................... 22 E1.4  IGA/IGO Evaluation ......................................................................................................................................... 22 E1.5  Hardness Testing (AC7102/5 Rev. NA) ........................................................................................................... 22 

E.2  FURNACE DOCUMENT CONTROL ............................................................................................................................. 23 E.3  CONTROL OF HEATING ENVIRONMENT ..................................................................................................................... 23 

E3.1  Hi-Limit Instruments ......................................................................................................................................... 23 E.4  QUENCH SYSTEMS ................................................................................................................................................. 23 E.5  VACUUM CONSIDERATIONS ..................................................................................................................................... 24 E.6  RACKING ............................................................................................................................................................... 25 E.7  RE-HEAT TREATMENT ............................................................................................................................................ 25 

F.  PYROMETRY AUDIT INTERPETATION ..................................................................................................................... 25 G.  JOB AUDITS................................................................................................................................................................. 26 

G.1  JOB SELECTION ..................................................................................................................................................... 26 G.2  AUDITING NOTES FOR JOB AUDITS ......................................................................................................................... 27 

H.  BRAZING ...................................................................................................................................................................... 28 H.1  CONSIDERATIONS .................................................................................................................................................. 28 

I.  ALUMINUM HEAT TREATING ..................................................................................................................................... 29 I.1 CONSIDERATIONS ........................................................................................................................................................... 29 I.2  REFRIGERATION CONSIDERATION ........................................................................................................................... 29 I.3  CONDUCTIVITY TESTING ......................................................................................................................................... 29 

APPENDIX A: ALUMINUM SPECIFICATIONS .................................................................................................................... 30 APPENDIX B: PRIME SPECIFICATION MATRIX ............................................................................................................. 34 APPENDIX C: AMS 2750 VS RPS 953 COMPARISON CHART ......................................................................................... 38 APPENDIX D: AMS HEAT TREATING SPECIFICATION – START OF SOAK TIME RECOMMENDATIONS .................. 39 APPENDIX E: LEAD AUDITOR HANDBOOK ..................................................................................................................... 43 

Page 3: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

3

A. FOREWORD

This Auditor/Supplier Handbook has been prepared to assist the Heat Treating Auditors and Suppliers as follows: • Where necessary, provide clarification on the intent and rationale of the Heat Treating Task Group as it

pertains to specific questions contained in the current revision of AC7102 and its corresponding slash sheets, as well as heat treat specific issues with Materials Testing Laboratories (MTL) checklists commonly used during heat treating audits.

• Clarify the material to be reviewed in addressing audit questions

• Standardize the audit from Auditor to Auditor

• Standardize definitions

• Provide general guidance on Task Group expectations as to the Supplier’s preparation for an audit and on an auditor’s execution of the audit

• Provide general information on unique requirements of participating prime contractors to aid the Auditor in determining supplier conformance to customer requirements

This handbook was prepared to directly reference the most current audit checklist revision. Sections are divided to correspond to audit criteria slash sheets. Current Heat Treating controlled checklists are:

AC7102 Nadcap Audit Criteria for Heat Treating

AC7102/S Nadcap Supplemental Audit Criteria for Heat Treating (Primes specific requirements)

AC7102/1 Nadcap Audit Criteria for Brazing

AC7102/2 Nadcap Audit Criteria for Aluminum Heat Treating

AC7102/3 Nadcap Audit Criteria for Carburizing

AC7102/4 Nadcap Audit Criteria for Gas and/or Ion Nitriding

AC7102/5 Nadcap Audit Criteria for Hardness Testing for Heat Treating

AC7110/1 Nadcap Audit Criteria for Brazing (Torch/Induction)

Additional checklists may be required during an audit (including AQS and/or MTL Task Group checklists). This handbook will not give guidance for questions based on other task group’s checklists; however, if an interpretation conflicts between Task Groups, the Task Group that controls the given checklist will be the governing body.

Note: Paragraph numbers in this document that do not begin with a letter correspond to the Audit Checklist question with the same paragraph number. Italicized text next to an audit checklist paragraph number is the text from that checklist question.

Page 4: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

4

B. DEFINITIONS NOTE: Many of the detailed requirements for the items defined below are found in the applicable specification. These definitions apply only if no customer requirements are specified.

Activation - A process by which the surface to be Nitrided is prepared by using various processes (chemical/mechanical) so that the Nitriding process can proceed at a higher intensity, resulting in a harder surface with greater depth.

Control Thermocouple - A thermocouple installed within the furnace volume which is used to control the heat input to the working zone.

Conversions from Fahrenheit [°F] into Celsius [°C] - When assessing Suppliers against customer requirements which are expressed in degrees Celsius take a special note of conversions from degrees Fahrenheit in TUS, SAT, etc. Customer and governing specifications, especially of European origin, may have temperature tolerances which are less than the similar North American (e.g. AMS) material. For example, solution treatment of aluminium alloys is typical +/- 10 °F in AMS, but +/- 5°C(±9°F) in European standards.

North American standards for heat treatment may also have definitions which are not in line with the European Prime requirements (e.g. AMS-H-81200, clause 6.3.9 Metrication).

Example:

A European Prime requires an aluminium solution heat treat temperature of 475 °C +/- 5°C. In the case where the Supplier is working and calibrating in Fahrenheit they have to be within the +/- 5°C (±9°F) maximum allowable tolerance. If the furnace(s) are tested/certified to a uniformity of +/- 10 °F, this converts to +/- 5.6 °C and exceeds the required tolerance. This is a NCR.

Correction Factor – The number of degrees, determined from the most recent calibration that must be added algebraically to, the temperature reading of a sensor, or an instrument, or a combination thereof (system) to obtain true temperature. The correction factors of sensors and instruments are usually kept separately and added together algebraically when a combination is used (from AMS2750 Rev D). Your procedures must clearly state how you calculate and use correction factors.

Dead Band – The range within which the temperature input can be altered upscale and downscale without registering a change on the instrumentation (from AMS2750 Rev D).

Heat Sink - A mass of material equivalent to the heat transfer characteristics of the thinnest section of the part being heat treated. A thermocouple surrounded by the heat sink is expected to represent the temperature of the limiting section thickness of the part. Heat sinks may be used during TUS per section 3.5.10.1 of AMS2750 Rev D.

Intergranular Oxidation/Intergranular Attack (IGO/IGA) – Per ASTM definitions.

Intermediate Temperature - A temperature that the part must be cooled to or below or heated to or above prior to continuing the next sequence stage of the heat treat process

Leak Up Rate (leak rate) - A test in which the furnace chamber is evacuated, isolated from the evacuation source, and the leakage determined within the system by observing the pressure rise per unit of time. NOTE: Leak up rate expressed in microns/hours. 1 micron is approximately = 1 X 10-3 torr = 0.001 mm Hg = 133 X 10-3 Pascal.

For example, when 1 micron is specified, 0.1 micron is a higher Vacuum or lower pressure.

Load Sensors – Sensors that are attached to the production material or a representation of the production material, that supply temperature data of the production material to process instrumentation.

Long Job Audit – Audit of multi-step heat treat process on a job which has been completed (questions 10.1 and 10.2 in checklist). Long jobs MUST be selected from history and MUST include the completed testing results for the jobs.

Page 5: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

5

Major Findings – The absence of, or systemic breakdown of, the Process Control and/or Quality Management system and any non-conformance where the effect impacts or has the potential to impact the integrity of the product. Heat Treating Task Group Examples - Any violation of engineering processing parameters either required by customer-invoked specification or stated in Supplier’s planning, or a lack of documentation demonstrating compliance to it. Parameters may also include ones not stated in the examples below:

1. Atmosphere/vacuum levels

The Supplier's shop paper stated the use of Argon up to a pressure of 500 microns during a heat treatment. The Customer did not specify pressure, and it was not stated in other Supplier documents. The actual pressure during the heat treatment could not be determined because the chart recorder was not configured to read pressures greater than 100 microns.

• Why an NCR? Lack of documentation demonstrating compliance to the pressure stated in the Supplier’s planning.

2. Inspection and Testing – Acceptance of (signing or stamping off) a process or test before that process or test has been completed. The Supplier’s shop paper/job planning or test records indicate that a process or test has been accepted before that process or test has been fully completed.

• Why an NCR? Violation of fundamental Quality principles and Quality System requirements.

Note: An isolated occurrence will result in a Major NCR. If these actions are determined to be systemic an additional Major NCR will be issued against the Supplier’s Quality System for allowing this practice or not detecting it, and a Supplier Advisory will be issued.

3. Pyrometry Testing -- Systemic violations or excessive extensions of testing intervals

The Supplier had no records of System Accuracy Testing for three furnaces.

• Why an NCR? Systemic violation of customer and Nadcap-invoked requirements for periodic equipment testing.

4. Pyrometry Testing -- Incorrect application of correction factors resulting in an out-of-tolerance condition

The Supplier’s procedures did not clearly state the difference between error and correction factors. Evidence of incorrect application of these was found. This included a TUS test thermocouple Correction Factor at 700°C that was subtracted rather than added, incorrectly producing an acceptable result, and TUS reports that indicated that an instrument’s Correction Factors are declared and stated as being applied without being included in the calculations.

• Why an NCR? Violation of the application of correction factors resulting in an out-of-tolerance condition.

5. Quenchant media, temperature or time

The Supplier’s planning did not state a quenchant oil temperature. The Customer invoked Specification required that initial quenchant oil temperature to be between 60°F and 160°F. The oil temperature at the start of quench was 150°F.

• Why an NCR? Breakdown of the flow down of Customer requirements to Supplier’s planning.

6. Repeat Findings (Non-sustaining Corrective Action) from Last 2 Audits

The Supplier’s procedure required biannual evaluations of Heat Treating operators. The Supplier stated the evaluations had been done and recorded on a skill matrix, but no objective evidence of this was available. This is a Non-sustaining Corrective Action from the prior audit.

Page 6: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

6

• Why an NCR? Lack of documentation demonstrating compliance to the periodic evaluations for Heat Treating operators required by the Supplier’s procedure.

• Major NCR because repeat finding from previous audits.

7. Temperatures and temperature tolerances.

The Supplier’s shop paper stated a tolerance of +/-25°F for a 775°F heat treatment. The Customer invoked Specification required a tolerance of +/-15°F. During the treatment, some recorded load thermocouple readings remained below 760°F.

• Why an NCR? Breakdown of the flow down of Customer requirements to Supplier’s planning with a violation of the temperature requirements of the customer-invoked specification.

8. Testing Methods for Parts

The Supplier performed verification using a Vickers test block as recorded on a machine verification sheet for microhardness testing, but the machine was used to perform Knoop hardness testing using 200-gram force. The Supplier's procedure did not state the required internal weekly verification of the microhardness testing machine to the hardness testing scale being used. The Customer-invoked specification required that verification be done using the hardness scale that will be used for testing. The Supplier’s verification sheet provided no objective evidence that the machine has been verified using a Knoop test block.

• Why an NCR? Lack of documentation demonstrating compliance to the testing method required by the Customer-invoked specification.

9. Times and time tolerances

The Supplier’s shop paper stated an allowed set temperature between 1750°F and 1850°F, and a 25 to 50 minutes soak time. The Customer did not specify the processing time or temperature, and only specifies a hardness requirement. An 1800°F set point was selected and used. During the heat treatment, the load thermocouple was between 1750°F and 1775°F for 15 minutes.

• Why an NCR? Violation of the time requirements stated in the Supplier’s planning.

Material Specification – Industry or Prime specification which defines the properties of the parts or raw material.

Metal Temperature – When called out in a spec or procedure, mandates the use of load thermocouples unless otherwise specified by the Prime.

Minor Finding – A non-systemic lapse in conformance to the Process Control and/or Quality Management system

Heat Treating Task Group Examples - Inadequate or non-existent procedures when supported by evidence that the processing or testing is performed correctly per the requirements.

1 Pyrometry Testing -- Procedure

Page 7: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

7

The Supplier’s procedure stated a provision to suspend equipment from use and to evaluate product impact following a TUS failure, but no actions were stated for an instrument calibration failure or SAT failure. No evidence of SAT or TUS failures were found. Correct actions were evident after instrument calibration failures.

• Why an NCR? Inadequacy of a required procedure.

2 Pyrometry Testing -- Short, isolated extension of periodic testing intervals

The Supplier performed a SAT test monthly for a Class 2 Type B air furnace number 17 on two separate occasions. The Customer and Nadcap-invoked requirement was biweekly. All other records were conforming.

• Why an NCR? Isolated extension of a periodic testing interval.

3 Pyrometry Testing -- Incorrect application of correction factors that does not result in an out-of-tolerance condition

The Supplier applied the correction factor based on the “as found” value to the SAT test instrument. The Customer-invoked specification required the correction factor based on the “as left” value to be used. The actual Correction Factor for the instrument was within 0.2°F, and was determined not to produce any unacceptable SAT results.

• Why an NCR? Violation of the application of correction factors that does not result in an out-of tolerance condition.

NCR – Non-Conformance Report, findings during an audit that require the full five part response as outlined in the Supplier’s guide.

Non-Automated Processes & Recordings – If cycle is operator controlled i.e. temp and time, software control section in AC7004 is not required. AC7004 applies for those systems that only require an operator to enter a recipe number or for any part of the process from a sealed menu

Nonsustaining / Repeat Findings – Non-conformances that are generated as a result of not implementing corrective actions from either of the 2 immediate previous audits or those where corrective actions may have been implemented but were determined to be ineffective.

Objective Evidence – Shall include, but may not be limited to: job travelers, furnace charts, various types of logs and logbooks, training records, document change records, customer documents such as purchase orders, packing slips, etc., or a direct demonstration. Objective evidence is required to be submitted for all findings, regardless their designation.

Over-temperature Instrumentation – A sensor/instrument combination installed in the furnace, which is used to monitor any over-temperature occurrence and generate an alarm and/or cut back or shut down the heat input. The purpose for this control is protect material and/or the furnace from overheating (from AMS2750 Rev D.

Parts – (From AMS-H-6875, 6088, 81200, etc.) Usually identified by a part number, produced from raw material in accordance with the requirements of a drawing, and are usually tested by nondestructive techniques only. They are heat treated, by or for a fabricator; in accordance with a drawing, purchase order, fabrication order, or heat treat specification. At the time of heat treatment, they may resemble raw material.

The Heat Treating Task Group further states: In the absence of other specific direction, material should be treated as a “part” if it has a specific Prime part number and if it is being supplied in either partial or full heat treatment to establish final properties (e.g., solution heat-treated).

Raw Material – (From AMS-H-6875, 6088, 81200, etc.) Usually includes, but is not limited to, such items as sheet, plate, wire, rod, bar, forgings and extrusions. It is usually identified by a heat or lot number and is usually tested destructively for acceptance. It is heat treated, by or for a material producer, in accordance with a material specification which may require, by reference, conformance to a heat treating specification.

Round Robin – Heat treating requires an internal round robin. An internal round robin is an intra-laboratory

Page 8: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

8

study or measure of the reproducibility of results generated by the laboratory personnel using the laboratory procedures. The intent of the internal round robin is to address the reproducibility of the results by operators and equipment.

Slash Sheet – Audit criteria on a specific area that may be optional dependent on a supplier’s facilities. Slash sheets are numbered on the base checklist as “AC7102/X”.

Soak Time – The amount of time required by specification, blueprint, purchase order for the furnace/parts to be at set temperature, taking into account the furnace tolerance.

Short Job Audit – A single complete thermal cycle that should be in process during the audit.

Stabilization – (also referred to as equalization, equilibrium, steady state or soaked condition). Furnace stabilization occurs when all control thermocouples are within the allowable TUS tolerance span and controllers are cycling and/or maintaining the desired temperature in each zone.

System Accuracy Check/Test (or Probe Check) (SAC/SAT) – An on-site comparison of the instrument/leadwire/sensor readings or values, with the readings or values of a calibrated test instrument/leadwire/sensor to determine if the measured temperature deviations are within applicable requirements. Performed to assure the accuracy of the furnace control and recorder system in each control zone. (from AMS2750 Rev D).

Systemic – Procedures, actions, or events that are not isolated, but found to be part of the Supplier’s system. When multiple occurrences of the same violation are observed, it is termed as being systemic.

Temperature Uniformity – The temperature variation (usually expressed as +/- degrees) within the qualified work zone with respect to the set point temperature. For retort furnaces where a sensor is used to control temperature, the temperature variation is with respect to the sensor in the retort and not to the furnace set temperature (from AMS2750 Rev D).

Temperature Uniformity Survey (TUS) – A test or series of tests where calibrated field test instrumentation and sensors are used to measure temperature variation within the qualified work zone prior to and after thermal stabilization (from AMS2750 Rev D).

Vacuum Level – "Higher" or "better" vacuum means "lower" pressure. Required levels will usually be specified by the drawing or material specification, and unless otherwise stated are maximum pressure levels. For conversion: 1 torr= 1mm Hg = 133 Pascal = 1x103 microns. For examples, when 1 micron is specified, 0.1 micron is a higher Vacuum or lower pressure.

Voided Nonconformance – A nonconformance generated as the result of a clear misunderstanding by the Auditor and struck out as a “void”. Requires rationale for voiding and may require review by the Task Group or Staff Engineer. Number assigned should not be re-used.

Qualified Work Zone – The defined portion of a furnace volume where temperature variation conforms to the required uniformity tolerance.

• All parts or material must be contained in this working zone.

• Furnaces may have more than one zone

Page 9: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

9

C. AUDITING TO NADCAP AUDIT CRITERIA

C.1 Specification Adherence

While the Heat Treating Task Group identifies industry specifications for use and guidance, Suppliers are not automatically allowed to default to those requirements. They are, automatically, to adhere to whatever their Customer requires of them. As a general reference, a matrix of Nadcap Mandating Primes and the specifications they generally require their Suppliers can be found at the end of this document in the Appendix.

Question: What is the Nadcap Auditor to do when during a job audit they find that the Supplier has a P/N frozen/ fixed planning process signed by the Prime Customer that deviates from the specification referenced in the frozen/fixed planning?

Nadcap Primes

YES - The Auditor Should Raise an NCR Because My Company

Only Uses Frozen Planning to Guarantee That The Referenced

Specification is Properly Flowed. The Supplier and Person Approving the Frozen

Planning Made An Error.

NO - The Auditor Should Not Raise An NCR. My Company

Uses the Frozen Planning Process to Authorize Deviations To The Specification Requirements. If The

Frozen Process Is Approved/Signed By

The Prime, No Further Investigation Is

Required.

N/A - My Company Does Not Utilize

Frozen Planning or Processes.

Airbus SAS

X Remark: Supplier

should have a Supplier-PFA(= Permit

of Alternative) ,Deviation has to be

approved and accepted by customer, if not

than raise NCR

Alenia Aeronautica

Any Supplier can deviate from a

specification using an approved PSD

(Process Specification Deviation)

Page 10: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

10

BAE Systems X

Bell Helicopter X

Boeing

"Heritage" Douglas (DPS) X

"Heritage" Boeing (BAC) X

"Heritage" McDonnell (PS) X

"Heritage" McDonnell Helicopters (HP) X

"Heritage" Rockwell X - except SMPP

Bombardier Aerospace "Group Specifications".

Montreal - Process Specs ( MPS / BAPS ). X de-Havilland - Process Specs (PPS). X Lear Jet - Process Specs ( LES / P Specs ). X

Shorts - Process Specs (P Specs ). X

Cessna Aircraft

Any Supplier can deviate from a

specification using an approved SDR

(Specification Deviation Request) -- Casting

Suppilers can deviate if listed on an approved

Foundry Control Approval -- Forging

Suppliers can deviate if listed on an approved

Pre-Production Forging Approval.

X - For all other cases

GE Aviation X

Page 11: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

11

Goodrich Aerostructures X

Hamilton Sundstrand X

Hawker Beechcraft X

Honeywell Aerospace X * see comment below

Liebherr-Aerospace X

Lockheed Martin

A NCR should be written for deviations of not following the frozen planning. It is not the

auditors place to assume an error was

made. It is possible for the planning to contain a requirement that was

approved via an approved procedure.

Any Supplier can deviate from a

specification using an approved VRIC

(Vendor Request for Information and Change). There

should be some kind of notification or follow up action by the supplier

to their customer.

MTU Aero Engines

X Remark: Supplier

should have a SAPA (=Supplier Alternative Process Approval) , if not than raise NCR

Northrop Grumman X

Parker Aerospace X

Rockwell Collins X

Rolls-Royce

X - But would request that Nadcap auditor advise the Prime to

permit confirmation that an error had not been

made.

SAFRAN Group

Aircelle

X - if the deviation is not formalised in a DEP

Demande d'Ecart Procédé (process deviation request)

Messier-Bugatti, Microturbo, Snecma, Turboméca X

Page 12: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

12

Sikorsky Aircraft X

Sonaca X(1)

Spirit Aerosystems X(Boeing work which Spirit has delegation to freeze.) Not for Spirit Work.

Textron Aerospace X

Textron Lycoming Engines X

United Space Alliance

Ares

X - any deviations to specs

will be identified on drawing or in a USA

approved Request For Information (RFI)

Orbiter - "Heritage" Rockwell X - except SMPP

Solid Rocket Booster - "Heritage" Pratt & Whitney

(USBI)

X - any deviations to specs

will be identified on drawing or in a USA

approved Request For Information (RFI)

Vought Aircraft X

(1) Deviations are approved by Sonaca only by use of RFA form (Request For Deviation).

*Honeywell Comment: The Prime should be notified so that they can investigate. If the problem turns out to be at the Prime’s end, then the NCR can be voided.

Page 13: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

13

Suppliers certify their work to a host of different documents. The requirements of many Customer specifications are different than AMS or MIL specs. Process certifications should only be to the specs followed.

If a checklist question requires something of a Supplier that is not in their Customer’s requirements, the Supplier must adhere to the checklist question. The checklist is considered to be the established requirements of any Prime mandating Nadcap accreditation. In other words, a checklist / Nadcap requirement is a Prime / Customer requirement.

C.2 Auditor General Guidelines

Heat Treating Auditors shall comply with the general requirements for completion of the checklist contained in the core Nadcap Auditor Handbook. These requirements include, but are not limited to, the information in this table.

Table I Checklist Guidelines All NAs shall be explained with supporting remarks

Yes

NCRs may be voided on-site by the Auditor; Supplier need not answer

Yes

All questions must be answered

Yes

All paragraphs involving an NCR must be referenced on the NCR

Yes

Auditor to validate NCR's from the previous audit; Result of this validation is reported in the cover letter

Yes

For Initial audits, the auditor shall visit all attended shifts when feasible.

For Reaccreditation audits, the auditor should visit all attended shifts when feasible.

In addition to the general Auditor requirements for completion of the checklist, Heat Treating Auditors shall comply with the following:

a. Abbreviations shall not be used unless explained in the cover letter attached to the audit. b. The use of acronyms shall be limited to commonly accepted and understood acronyms (i.e., FAA, DoD, etc.)

Writing NCRs: a. Be sure to always have checklist question and reference number. b. The finding must be a checklist nonconformance, a specification non-conformance , or a Prime

requirement non conformance, not an opinion, not a best practice criticism, c. Don’t combine different findings because they appear on the same job unless RCCA are the same. d. Be aware of the requirements for classification of Major Findings, Minor Findings, and

Nonsustaining/Repeat Findings. e. When an NCR is issued against a checklist question and it is determined that the NCR is a nonsustaining corrective action, DO NOT issue an extra NCR against Chapter 3 (General Quality System) in AC7102, but link the issued NCR with the correspondent question in Chapter 3 of AC7102. f. When one (1) NCR is issued against checklist questions and it is determined that the NCR is a nonsustaining corrective action, DO NOT issue an extra NCR against Chapter 3 (General Quality System) in AC7102, but link the issued NCR with the corresponding question in Chapter 3 of AC7102. g. When two (2) NCRs are issued against checklist questions and it is determined that both NCRs are nonsustaining corrective actions, ISSUE an extra Major NCR against Chapter 3 (General Quality System) in AC7102. h. Review the guidelines for acceptance of NCRs on site.

Voiding, and Accepting On-site NCRs:

Page 14: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

14

a. If an Auditor initiates a NCR and then the Supplier provides additional information that proves that the NCR in fact does not exist, then the Auditor can void the NCR. Reason for voiding the NCR must be documented by the Auditor letter. Do not assign the same NCR number.

b. On-Site Acceptance of Non-conformances by Auditors: The nonconformance must meet the definition of a Minor finding, be of the nature of a paperwork oversight or administrative issue, and be properly corrected and closed out within the audit period. It must still be reported to the Task Group and include appropriate documentation of closure. Inclusion of root cause analysis is required when appropriate. Staff Engineers or Task Group members have the option to reopen the NCR and request additional information or action.

When an NCR is written and noted as having an escape and/or Supplier to Evaluate Product on hardware,

the following is required: • Need to review other jobs to determine if it is an isolated case. • Need to review other jobs for potential product impact • Supplier must notify the direct Customer of the discrepancy in writing. • The notification must include:

What the nonconformance consisted of A request of your customer to notify the Prime A request for written acknowledgement of the receipt of the Product Impact/Potential Product

Impact notification

Attach a copy of supplier’s written “Notification to Customer” and the “Acknowledgement” from your customer into the applicable NCR in your audit report in eAuditNet

C.3 Supplier Guidelines

Para 1.0 of AC7102 covers specific instructions for Suppliers to be audited. While many items in this section are not requirements, it is in the best interest of the Supplier to perform all duties properly to avoid delays during or after the audit.

It is mandatory to perform a self-audit per 1.1.1 of AC7102 and have all corrective actions implemented prior to the Nadcap audit. Auditors have been directed to write an NCR against a Supplier who does not perform a self audit to the required checklists. It is the experience of the Task Group that Suppliers who fail to perform the self-audit are more likely to fail the audit, receive a higher number of findings, and take longer to become accredited.

If upon review of the checklist before an audit, a Supplier has difficulty interpreting the checklist question, they shall attempt to perform the following:

a. Cross-reference that question with the corresponding section of this handbook for guidance b. Contact the Heat Treating Staff Engineer for clarification c. Contact a Prime representative on the task group for clarification

Waiting to clarify a question with the Auditor may result in a NCR if corrective action was required. Knowingly waiting to correct a non-conformance until an audit is questionable quality practice.

Suppliers may obtain the current failure criteria from NOP-11 and NTGOP-001 Appendix 3.. This can be downloaded from “User Documents” in eAuditNet.

On the last day of an audit, the Auditor should direct the Supplier to Supplier’s Guide in eAuditNet as an aid for their responses to findings. The Supplier shall follow the proper response format stated in eAuditNet Supplier Guide in order to keep the review times as short as possible. The link to this guide is listed in the Supplier Response Guidelines posted in NCR 1 of their audit findings. It will also be advisable for the Supplier to review the tutorial on RCCA (Root Cause Corrective Action) on the PRI website.

Page 15: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

15

C.4 Guidelines for Time Management of the Audit

Time management of the audit is absolutely essential. The basic purpose of the Nadcap audit is four fold. a. Accurate identification of the Customer requirements b. Careful determination that the Customer requirements are flowed down to shop paperwork and any

sub-tier Suppliers. c. Verification that the Heat Treater and other shop personnel (cleaning, inspection, test personnel) have

correctly implemented and documented the heat treating requirements required by the Customer. d. Assure there is an effective quality assurance system functioning within the heat treating department.

Heat Treat Task Group time management recommendations for Auditors are to ensure the purposes of an audit are maintained.

Auditors should arrive at the facility on the first day early enough to put a strong first day in, but allow time for the company to get organized, especially on a Monday. If possible, the Auditor should arrive about one half hour after the Quality Manager or Supplier point of contact arrives. Try not to inconvenience Supplier and work within their designated work times.

Auditor and Supplier representatives should jointly plan the audit, this point is especially important in larger facilities. It is recommended that the audit should be performed in the following order:

a. Brief tour of the facility b. Job Audits c. Pyrometry d. Material Testing (Hardness, Tensile, etc.) e. Validation of Previous NCRs (reaccreditation audits only) f. Additional areas as necessary

The Supplier and Auditor should settle issues of proprietary information, trade secrets, non-disclosure agreements and intellectual property early in the audit process (preferably prior to the on-site audit).

A brief tour is usually in order at the beginning of the audit. In captive shops only a review of the heat treating area is necessary. During the tour, the Supplier and Auditor should try to identify any parts that may qualify for an in-process job audit. All or at least half of the job audits should be selected during the first morning. Supplier supervision should assist in scheduling heat treatments while Auditors are at the facility. This is also an opportunity to review calibration stickers on the equipment.

Perform the job audits and take the time to verify that Customer requirements are identified. Both short job and long job audits should be completed by the end of the second day or least by mid-day of third day of auditing for regular audits. Reference Appendix D, pages 33 – 37.

It is the best practice to complete the pyrometry section of AC7102 checklist while performing the job audits. This will speed up the audit by reviewing the SAT and TUS data for the furnaces from which you are performing job audits. The balance of the pyrometry section can be completed after all of the job audits have been performed.

Perform all Pyrometry auditing paying attention to correction factor, stabilization of the furnace, correct identification of the high and low temperatures the number of surveys per operating range and frequency of surveys. Arrange to witness a System Accuracy Test (SAT).

Each potential NCR identified at the time of the audit shall be mentioned to the Supplier.

A daily out-brief shall be performed at the end of each day so the Supplier knows the status of the audit on a daily basis.

Auditors should avoid on-site NCR acceptance on the last day of the audit as there may not be sufficient time for the Supplier to conduct an adequate RCCA analysis in order to support acceptance on site..

Auditors shall carefully review the heat treating processes that are recommended for accreditation together with the Supplier early in the audit. At that time verify all appropriate specifications are in the facility. At this point the scope of accreditation shall be discussed with the Supplier, and any required additions or deletions should be made by the Auditor. Scope changes can be made in eAuditNet as part of the “Scope

Page 16: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

16

Verification” process. Refer to the eAuditNet Auditors” Guide under “Public Documents”

C.5 Verification of Corrective Action (VCA) Audits

VCA audits are required by the Task Group whenever there are significant findings is areas such as pyrometry or Customer flow down which would indicate corrective actions need on-site confirmation. The scope of the audit shall be limited to the requirements established by the Staff Engineer and Heat Treating Task Group, and any NCRs shall be answered in the same manner as a standard audit. A letter will be sent to the Auditor from PRI which details the required scope of the VCA audit. This letter is to be attached to the checklist on page 2 of the VCA audit in eAuditNet. The original audit will not be closed until the VCA audit is closed.

A complete and thorough Cover Letter is now the official method allowed by the Task Group when documenting the review of previous NCR’s written when performing a VCA audit. Each NCR shall be listed and what actions were taken to close that NCR. If the letter is not complete and thorough, it will be rejected and the Auditor will have to rewrite the Cover Letter to the satisfaction of the Task Group. This letter is to be attached to page 2 of the audit in eAuditNet.

C.6 Snapshot Audits Definition

A Snapshot audit is an audit performed upon Task Group request, by a PRI/Nadcap Auditor, at PRI/Nadcap expense, without extended notice given to the Supplier. The purpose of Snapshot audits is to verify the implementation of corrective action responses. Snapshot audits are very focused, with the scope of the audit defined by the requesting Task Group and not to last more than two (2) days. Poor performance on a Snapshot audit could result in revocation of accreditation.

C.7 Satellite Audits

• Unless specifically directed by PRI, DO NOT visit more than one Supplier location as part of the audit, even if the Supplier tells you that their facility is comprised of more than one site. Call PRI for confirmation regarding the extent of the audit.

• When more than one location of a Supplier is authorized for inclusion under an accreditation certificate, separate checklists should be completed, for each location, per method, independently. Audits of each independent location have requirements that differ from Task Group to Task Group. eAuditNet will contain the individual checklists to be used with separate audit numbers.

• The Main and Satellite facility audits shall be scheduled consecutively with the same Auditor(s). Staff Engineer approval of deviations shall be noted in eAuditNet.

For Satellite(s) the following criteria apply:

Must be within 25 miles/40 kilometers radius distance of the Main facility;

Must have the same Quality Manual and Procedures as the Main facility;

Must have the same Quality Manager (day-to day operational control) as the Main facility (for NDT can substitute the same Level III / for MTL can substitute the same Lab Manager/Supervisor);

Must have onsite an individual who is part of the Quality Function and reports directly to the Quality Manager;

Are owned by the same company.

The Auditor shall verify during the audit that the Satellite meets the above criteria and shall immediately report any deviations to Scheduling. The Auditor shall document that the above criteria was met or not met in the audit report cover letter.

Facilities currently classified as Satellites may retain this classification at the discretion of PRI Scheduling, even though they may deviate from the criteria outlined above. When Auditors report deviations to the above criteria, Scheduling shall determine if this was an existing condition on the Supplier’s previous Main/Satellite and document the exemption to the criteria in eAuditNet

Page 17: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

17

If you have a question regarding a satellite facility, contact PRI Scheduling immediately.

Page 18: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

18

C.8 Spec Cancellations & Supercession

• Suppliers and Auditor must not assume that the latest revision of a specification is the one to be used. Many Primes, for certification and qualification reasons, are required to continue to use prior revisions or even to continue to follow superseded or cancelled documents. Most Primes provide a flowdown to at least their first tier. When in doubt, consult the Prime. All active Task Group member Primes have committed to supplying this information if help is needed.

For ASTM, AMS and other national standards specification revisions, the Heat Treating Task Group has agreed that the Supplier shall, within 90 days, have the latest revision of the specification on site in the absence of other direction from Prime or customer specifications.

C.9 AC7102/S • General and specific requirements for application of AC7102/S:

• DO NOT respond to any question in AC7102/S where the cited Prime specification has NOT

been flowed down. Enter “N/A” instead.

• DO respond to those questions where the cited Prime specification has been flowed down.

• The GE-Aviation (U10) questions are rated as follows for the purpose of categorizing an NCR:

Minor: 11.2.1 (Vacuum leak rate test’s starting pressure) 11.2.1 (Dew point measurement frequency)

Major: 9.1.2 (Cooling Rate)

10.2 (Load Sensor Accuracy) 11.1.4 (Type D + 2 recording load sensors) 11.2.1 (Vacuum system calibration interval) 11.2.1 (Dew point instrument calibration frequency) 11.2.4 (Vacuum level above 1000F)

• Rolls-Royce PLC (U3) questions are rated as Minor for the purpose of categorizing an NCR. No

questions should be answered “N/A” or partially answered questions.

• GE Aviation specifications that flows down P10TF1:

o C50TF8 o C50TF22 o C50TF26 o C50TF113 o C50TF119 o P11TF18

Page 19: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

19

D. QUALITY SYSTEMS

• The Supplier should maintain a Process Control Matrix that lists all of the specifications that they process hardware to, the applicable process control requirements, and the Suppliers schedule for meeting them.

• The Supplier must have a documented and effective internal audit system. Evidence of these audits including schedule, audit criteria, and results including associated corrective actions must be available for review by the Auditor.

• The heat treating job planning must include the specific time and temperature requirements for the specific job. This information can be directly on the shop paper or on other instructional media traceable to the job planning. It is not acceptable to reference by specification and have the operator look up the time and temperature requirements in the specification.

• For fixed process planning, the Supplier must be able to document to the Auditor that they are processing to the latest Customer approved revision of the fixed process planning.

• The Boeing Company requires for BAC heat treating specification that each furnace chart is stamped to indicate acceptance for temperature and time at temperature. If this inspection is delegated to shop production personnel by QA, then the operators must receive documented training and QA must perform oversight audits on sampling frequency of the jobs accepted by the operator. A record must be kept to document this oversight.

• Sampling Plans - Personnel utilizing sampling inspections must be trained and tested to document that they know how to properly perform sampling inspection.

D.1 Training

• The Supplier must have a documented personnel training program. The Supplier can use ARP1962 for a guide, or develop their own training program. The program must include documented training to an established outline and initial and periodic evaluation of the competency. The AMEC committee is concerned about the quality of the training programs at heat treaters and feels that we have not been putting enough emphasis in this area. This is an area that we need to highlight.

• Where written testing is not permitted (for example, in certain union shops), "Observational" testing is acceptable. In this kind of test management observes an operator during the performance of their job duties. Management fills in the questions and the result is graded. The results of the observation should be reviewed with the operator. Records of the observations and review must be retained.

D.2 Electronic Program Control and Data Acquisition

• These requirements pertain to computerized furnace programming, paperless recording equipment, and any other electronic media used by a heat treater that historically was performed in a hard copy format. The Heat Treating Task Group does not want to discourage the use of this type of equipment (in fact would rather encourage it), only to ensure the proper steps are taken to control software and data to be as reliable and auditable as the hard copies they replace. For more specific information, refer to AMS2750 Rev D and the Pyrometry Reference Guide.

D.3 Contract Review

Where the Customers instructions are ambiguous with regards to thermal processing and mechanical testing requirements, e.g. 17-4PH, Heat Treat to Condition H1025 per AMS5643, it could imply that Customer requires testing with heat treatment; heat treaters shall contact Customer for further clarification of all requirements, which may include verification of delivery condition.

Page 20: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

20

E. GENERAL HEAT TREATMENT ITEMS AND STEELS (AC7102)

• Refrigeration of Steels - If the specification requires a refrigeration time at temperature process, it must be recorded to document compliance. This includes dry ice/alcohol baths. Refer to AMS2750 Rev D and the Pyrometry Reference Guide for further information.

• If the Supplier is performing in-house testing covered by one of the MTL checklists, e.g. Hardness Testing, Tensile testing, etc., they will need to consult the MTL Supplier/Auditor Handbooks for guidance to those checklists.

E.1 Test and Inspection

• Supplemental Material Testing Laboratory Checklists - As part of Nadcap Heat Treating audit, Suppliers may be audited to checklists that are to standard operations in a heat treating facility, but out of the Heat Treating Task Group’s control. For instance, checklists handled by Materials Testing Laboratories (MTL) Task Group for such testing like Mechanical Testing (AC7101/3) and Metallography and Microhardness (AC7101/4) are common. Interpretation and guidance on these checklists are available from the MTL Task Group.

E1.1 Room Temperature Tensile Testing

• Round Robin testing is required when the Supplier performs RTT per AC7101/3 Table 1. (Guidelines to follow when available.)

• When the Supplier only performs RTT, calibration and monitoring of temperature and humidity is NOT required, do not write an NCR, the question is N/A.

• The following are the only areas in AC7101/3 & 4 the Heat Treating Auditors are allowed to verify for approval.

• The only allowed category of testing in AC7101/3 is RTT.

• The only allowed categories of testing in AC7101/4 for approval are the following: L, L5, L6, L7, L8 and L9.

E1.1.1 Sub – Contract Machining of RTT Test Pieces These are the minimum requirements for the control of machining of RT Tensile test pieces against the clause in AC7101/3 Para 9.4. The machining source does not need to be listed on AC7101/1 Figure 3.

Machining source

The source must be listed on the Supplier’s approved vendor listing. They must be able to demonstrate a quality review of the source.

Control of RT Tensile Test Piece Manufacture:

1) Are procedures written which establish specific values for each process variable for each test piece and material combination, i.e. machining speeds, feed, grinding wheel, etc?

2) Does the preparation of the test piece eliminate any adverse effects on the properties resulting from the test?

Example: a) Test piece distortion b) Physical damage c) Residual stresses d) Metallurgical damage (from local overheating etc)

Page 21: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

21

3) Are the test pieces inspected for the following?

a) Visual inspection for surface damage b) Finished surface exhibiting an uniform texture

4) Is dimensional inspection controlled by one of the following methods?

a) Statistical Process Control (SPC) b) Inspection of characteristics prior to shipment c) 100% inspection of all characteristics d) Sample inspection of characteristics.

5) Are the packaging and shipping requirements defined?

Are each of the specimens packaged and labeled in a manner to protect its integrity and unique identity?

E1.2 Round Robin Programs for Metallography and Microhardness

Internal round robins are required for accredited Heat Treating Suppliers for their microhardness testing equipment and other measurable metallographic evaluations. External round robins are not required. The internal round robin test should include: a. Operators who use the same tester: using the same specimen, with none of the operators aware of

the hardness block value, at least five readings are taken for each operator and compared statistically.

b. If there are two microhardness testing machines using the same scale (ex. Knoop) one individual should test both machines with the same block to determine if there is a statistical difference between the two machines?

c. For both machine and operator, the results shall be analyzed quantitatively. Any valid statistical

method that compares the data with 95% confidence is acceptable. For example, individual test averages should fall between two standard deviations of the total test data.

Round robin testing shall be performed on each microhardness tester used to verify or certify material regardless of the type of tester. This includes digital microhardness testers.

The Krautkramer Microdur microhardness tester requires the use of a separate material standard test block that corresponds to each alloy system to be tested.

For the purposes of the Heat Treating Task Group (this is not a true Gage R&R): A statistical comparison of microhardness test machine operator results on a given microhardness test machine (including digital machines) and hardness test block. Operators should be “blind” to the test block value being used. Readings should not be rounded. An individual’s mean shall be within +/-2 sigma of the group mean. If more than one machine is to be used, each machine must be checked. Have one “standard” microhardness test machine operator check each machine and compare other microhardness test machine operators against the “standard operator”. Round Robins are also required for IGA/IGO and diffusion coatings and RTT, grain size, alpha case. (Review MTL data)

The following may be considered to assist in Round Robin calculations: Round Robin testing is a comparison between two or more operators or between same scale microhardness testers to assure there is no significant statistical difference in the testing methods used between operators or between the functioning of hardness testers. For operators, the same microhardness tester and same certified test block (test value of the test block is obscured to prevent bias - production material is not recommended, as this material is often not consistent in hardness and the test will be confounded) is used and a number of test readings (five or more) is taken by each operator. The test results of each operator are compared statistically to each other. If there are more than two operators, one is always used as the standard of comparison. The same method is applied to microhardness test machines when there is more than one microhardness tester. Recommended

Page 22: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

22

statistical methods are” t” test, 2 sigma average comparison (individual average does not exceed two

sigma of total average)

When comparisons are made where only one measurement is made (depth of IGO, depth of alpha case, grain size, etc), the same sample is measured by different individuals using the same equipment. A recommended statistical comparison is a “Z” test, Z=(x-X)/s, where Z (the number of standard deviations the value of “x” lies above or below “X”), “s” is the measured standard deviation of the average of the readings to obtain “X” , “x” is the participant’s result, “X” is the determined value from a number of acceptable readings. For IZI less than or equal to 2, the test is satisfactory; for 2 less than IZI which is less than 3, the test is questionable; for IZI greater than or equal to 3 the test is unsatisfactory (reference ISO/IEC Guide 43-1:1997, ASTM E 1301

E1.3 Surface Contamination Testing

Some Primes require or allow the use of ARP1820 for the testing of surface contamination/decarburization. The following specifications reference surface contamination requirements in Section 3.5 of each specification and ARP1820 is referenced in all AMS 2759/#’s.

AMS 2759/1(ARP 1820 is referenced, but not required)

AMS 2759/2(ARP 1820 is required)

AMS 2759/4(ARP 1820 is referenced, but not required)

AMS 2759/5(Requires ARP 1820 or equivalent that provide 3X magnification)

NOTE: AMS-H-6875 requires etching the IGA sample in boiling acid. AMS 2759 specifies that samples should be evaluated unetched.

E1.4 IGA/IGO Evaluation

IGO is an oxidation of the grain boundaries, leaving the grain intact. IGA is a corrosion attack in the grain boundaries that usually results in the grain(s) being removed or damaged. All alloys exposed to thermal treatments are susceptible to IGA/IGO, with the exception of single crystal castings. Always refer to controlling specifications for requirements. Refer to ASTM E 3 for preparation of sample or indicated specification. Individual Prime requirements may differ.

• Do procedures reference compliance to ASTM E 3 or indicated specification? • Do records show compliance to ASTM E 3 for specimen preparation or indicated specification?

E1.5 Hardness Testing (AC7102/5 Rev. NA)

Question 13.4.1 was intended only as a reminder that the requirements of ASTM E18-08b Paragraph 6.4 apply, where it states "When testing on convex cylindrical surfaces, the result may not accurately indicate the true Rockwell hardness; therefore, the corrections given in Annex A6 shall be applied." Whenever a Supplier certifies that they have performed hardness testing per ASTM E18, they are certifying that corrections were applied to hardness values taken from convex cylindrical surfaces. The question 13.4.1 from AC7102/5 Rev. NA will be removed from the checklist at the next revision.

It is assumed that the Conductivity and Hardness testing specification flowed down in AMS 2770 is AMS 2658 and it is the only testing specification mentioned in AMS 2770. AMS 2770H, Section 4.3, does not directly flow down any Conductivity and Hardness testing specification except for 4.3.1.2 for 6XXXX alloys and 4.3.3 under Failures. It is apparent that this was an oversight and will be corrected at the next revision of AMS 2770. In the interim, AMS 2658 will be considered the Conductivity and Hardness testing specification flowed down by AMS 2770, in the absence of any other direction by customer purchase order

Page 23: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

23

or contract.

E.2 Furnace Document Control

Do records on the furnace chart or log indicate that the procedure is followed? When looking for furnace logs, follow the specification governing the job of concern. Some require actual logs with specific information on them be kept, others require only written traceable records.

E.3 Control of Heating Environment

Do procedures specify how atmosphere from each generator/blender is to be controlled? Refers to generated atmospheres (endothermic for example), not for blended cryogenic atmospheres

E3.1 Hi-Limit Instruments

While out on the shop floor be sure to check the Hi-Limit Instruments and to verify they are properly being set. There are several different specifications that require them to be set at a specific range above the set temperature. If the specifications do not call out such a requirement, the Supplier needs to define in a procedure what the hi-limit instruments need to be set at.

E.4 Quench Systems

There are three types of delays to be considered in heat treating, dependent on the Customer specification: a. Quench delay: from the time which the furnace door starts to open (i.e the furnace seal is broken) until

the parts are completely under the water, polymer, salt or oil. b. As Quenched Retention Delay: The times from removal from the quench bath until the parts are put in

refrigeration / sub-zero treatment (usually 45 minutes maximum for steels and 1 hr. for aluminum, but frequently less depending on alloy and specification).

c. Age/Temper Delay: the time the parts must remain at room temperature after removal from the refrigerator prior to placement (usually some minimum time) into the aging/tempering furnace.

When these requirements are imposed by specification, records of time in/time out need to be kept by the heat treaters.

Are the quench mechanisms operational and capable of meeting maximum quench delay provisions of specifications? Quench delay measurement should be verified to assure specification compliance. Measurement begins with movement of the door. Tabulated maximum delays may be exceeded if allowed by specification i.e. AMS2770G states that the specified maximum quench delay may be exceed if tests made within the last year demonstrate that the part temperatures do not fall below 775 °F (900 °F for 2219) before immersion. In addition, there should be documentation of how the temperature of the parts is validated when using this provision. The measurement of quench delays should be done with a stopwatch. Too many new furnaces measure from the initiation of ram movement or from the time the door is fully open, and not door movement. Lengthy delays can cause defective parts.

Do procedures specify how quenchant temperature is to be controlled and documented? There should be a document describing how the temperature in the quench bath is measured at the start and end of the quench.

Do records on or traceable to, the traveler demonstrate that quenchants have been at the specified temperatures before and after the parts were quenched? Supplier should be checking the quenchant temperature rise with a full load. Load sizes should be controlled to ensure that quench media does not exceed the maximum quenchant temperature allowed by specification or the maximum allowable increase in quenchant temperature allowed by the specification.

Page 24: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

24

Control of glycol quenching solutions. The current industry/Customer specs have rigid controls with respect to glycol concentrations, salt content in the quenchants, and require approved products. Checking of quenchants approval is essential. The adequacy of the quench in aluminum heat treating operations is dependent upon the use of specific products, and the continued control of those quenchants.

Do records indicate that quenchant effectiveness is consistent and meets specification requirements?

Quench effectivity testing may include (either separately or in combination) comparative cooling curve analysis, analysis of mechanical property test results, chemical, physical & thermal analysis of the quench media, and hardness of cross-section analysis against harden ability curves. See the governing heat teat specifications for details.

E.5 Vacuum Considerations

Do procedures control the following: a. Leak-up Rate

Leak-up rate test should be run at normal operating pressures. Allow vacuum system to equilibrate for 15 minutes minimum then check leak-up rate. The typical leak up rate is expressed in microns/hour and the arithmetic should be performed accordingly.

Example if the test is run for 15 minutes, the pressure difference during the time period multiplied by 4 equals total leak up rate per hour. b. Quench Gas Purity and Dew Point (Does gas certification meet specification requirements)? Quench Gas Purity: This relates to the purity and dew point requirements of the quench gas. For example, GE Specification, P101TF1, requires inert gas purity of 99.995% and dew point of -60 degrees F or colder . Boeing BAC specification requirement is Compressed Gas Association (CGA) specification G–11.1, Grade E (dew point –76 F or colder, oxygen 5 ppm or less).

The following table will assist in interpreting certifications from gas suppliers:

Page 25: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

25

Table II Moisture Conversion Data Dew Point (°F) Dew Point (°C) Moisture Content [ppm

(v/v)] Moisture Content

(mg/L) -100 -73.3 1.5 0.0011 -95 -70.5 2.3 0.0017 -90 -67.8 3.5 0.0026 -85 -65.0 5.3 0.0040 -80 -62.2 7.8 0.0058 -75 -59.4 11.4 0.0085 -70 -56.7 16.2 0.012 -65 -53.9 23.0 0.017 -60 -51.1 32.0 0.024 -55 -48.3 45.0 0.034

c. Gas Quench System Integrity/Dew point

When dew point testing of inlet gases to a line of furnaces; take the gas sample just past the farthest

furnace in the line. Look for periodic calibration of dew point tester.

E.6 Racking

• Racking spacing should be conveyed by planning callout, set up cards, or in the general procedure depending applicable specifications/Customer requirements.

• Heat treatment of fasteners frequently requires specific qualification of containers to insure that that the soak time is adequate for a given thickness of charge and that the charge is not too thick for adequate quenching. Various specifications have specific requirements in this area.

E.7 Re-Heat Treatment

All re-heat treatments must be documented on the Suppliers manufacturing and nonconformance system, even if re-heat treatment is allowed by specification. If re-heat treatment is not specifically allowed by specification, Customer approval in writing is required.

F. PYROMETRY AUDIT INTERPETATION

PLEASE REFER TO THE “PYROMETRY REFERENCE GUIDE” FOR GUIDENCE ON THE REQUIREMENTS OF AMS2750.

Page 26: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

26

G. JOB AUDITS

G.1 Job Selection

Job audits shall be selected to provide a representative appraisal of the type of work to be accredited. Job audits are a good test for the effectiveness of the Supplier’s contract review procedures, process planning and manufacturing controls. Be careful of customer specific flowdown requirements that may preclude the use of “generic” or “industry-specification” based process plans or cycles. Survey the facility early in the audit to find enough in-process jobs for a minimum of 4 in-process job audits. Make Supplier aware that other completed job audits will be required if all materials/processes cannot be covered in-process.

If a Supplier wants approval for any of the following materials/processes listed in Table III, then an audit must be conducted on that materials/process. It is essential that the Supplier be contacted prior to the audit to ensure he has material in process to cover the scope of approval If the Supplier does not have current orders in house, he may run “dummy” jobs to the requirements which he wishes to include in the scope of his audit. This needs to be agreed to prior to the start of the audit. The job audits can be either long or short. If an in-process job is not available, then the auditor can select a Supplier's completed job. As many job audits as necessary to completely document a Supplier's capability should be performed. This applies to both initial and reaccreditation audits..

Table III Job Audit Selection

Titanium solution treatment Furnace Brazing

Aluminum solution treatment Carburizing and heat treatment

Austenitize and quench Nitriding

Superalloy solution with controlled cooling requirements or aging with controlled cooling requirement

Induction Brazing

Dip Brazing

Induction hardening Ion Nitriding

Tempering and/or Stress Relieving alone can’t be used as a job audit unless that is the only process the Supplier performs. Solution treating and aging of same part number should be considered as one long job audit.

Preference should be given in selecting jobs to Subscribing Prime members of the Heat Treating Task Group. Should avoid “breakout” job, i.e. direct government buy of Prime part numbers.

Preference should also be given to non-proprietary jobs and/or non-ITAR/EAR when choosing to do an audit. If there is no choice and a proprietary job has to be chosen, a record of specification requirements, set values, and actual values should not be placed in the audit report unless agreed to by the Supplier. Instead, the Auditor shall verify the specification requirements versus the shop paper requirements versus the actuals and make a statement that the condition found was acceptable. If an NCR exists, it is acceptable to record the variance from requirements. Please refer to NIP 7-07 for additional information on ITAR/EAR.

Long job audits shall be performed on completed aerospace jobs. Long job audits should be performed on jobs completed within the last four months. Only if there is no other work available should a completed job be more than 6 months old. If it is older than 6 months:

o Make a specific note

o Make an assessment of the Supplier's capability to perform the process of H/T the material

o When looking at an "old" job do not write up an NCR if the current procedures would have addressed the problem

Page 27: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

27

At least four short job audits should be performed on in-process jobs if eight in-processes are not available. If it is impossible to witness a minimum of four in process jobs, a Staff Engineer must be contacted. The Staff Engineer will give direction to the Auditor in proceeding with the audit and proper documentation in the cover letter. The remaining jobs must be selected from the completed jobs since last certification was issued.

A minimum of at least one in-process job needs to be witnessed to observed racking details, placement of load t/c (if used), placement in furnace, quenching and unloading. The balance of the in-process jobs may be in soak, in cool down cycle or just completed.

G.2 Auditing Notes for Job Audits

Identify alloys/materials specifically-not just by specification number.

Ensure that material is heat treated in furnaces that meet the uniformity requirements of that material (i.e. material requiring ±5 F ovens are not aged in ovens that only meet ±10 F limits).

Solution heat treating and aging of the same aluminum part number may be treated as two separate short job audits, especially since two different furnaces will likely be used. There are some that are used for both solution treat and age but this is not common.

Each question in each job audit must be answered. For example, Pre Heat Treat Requirements; Pre Heat Treat Requirements on shop paper, Pre Heat Treatment actually performed, must be answered. If there are no requirements, write "NONE" or "NONE SPECIFIED".

If the customer requirements are not specified, the heat treaters must provide objective evidence of the origin of the requirements imposed.

When recording the “Actual Temperature Data”, it is best to record the stabilized temperature and not the temperature as the thermocouple crosses the lower uniformity requirement.

Specification, B/P and/or P.O. calls out a minimum time only, it is permissible but NOT required that the Supplier specify a maximum. The Supplier may simply flow down the minimum time requirement to the shop paperwork. If Specification, B/P and/or P.O. calls out a single time only and does NOT state Minimum/Maximum, the Supplier Shall have a default in their procedure. Either a (+/-) tolerance or a statement that time at temperature shall be considered as Minimum or Maximum. This also applies to a “Fixed Process”. The only exception is for a fully automated process outside the control of the operator. A single time may be specified in such cases.

During all job audits where quench delay requirement exists, the Auditor needs to verify that the requirement was met.

The preferred practice is to list the date & time of day on the recorder chart. Additionally, there needs to be traceability from the chart to the heat treat log, for example, by using a job number and date or unique job number.

Page 28: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

28

H. BRAZING

H.1 Considerations

Because there are a number of requirements unique to brazing, the Heat Treating Task Group has developed a separate slash sheet (AC7102/1). Suppliers wishing to be approved for furnace brazing, dip brazing or vacuum brazing shall be audited to this slash sheet.

Suppliers wishing to be approved for torch brazing or induction brazing shall be audited using AC7110/1 checklist.

Adjusting of temperature during the hi-temperature portion of braze cycles, based on load t/c data is allowed in order to avoid adverse affects of exposure at elevated temperatures.

NOTE: This is not considered ‘Offsetting” as it is used during temperature uniformity surveys.

Not all Primes require a separate enclosed preparation/assembly area, but area used for this must be reasonably free of shop dirt and potential sources of contamination.

Fit is critical to a strong braze joint make a special point of reviewing the Suppliers data and assembly procedures to assure B/P or specification requirements for gap are met.

Post braze cleaning instructions shall include residual flux test if flux is used.

Page 29: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

29

I. ALUMINUM HEAT TREATING

I.1 Considerations

Because there are a number of requirements unique to aluminum heat treating, the Heat Treating Task Group developed AC7102/2 to cover those unique requirements. This checklist shall be completed for Suppliers performing aluminum heat treating.

MIL-H-6088 & AMS-H-6088 are obsolete specifications and, unless Primes have directed otherwise, are replaced with AMS 2770, AMS 2771, & AMS 2772. If not covered by the applicable Prime specification the following shall apply: a. AMS 2770 covers heat treatment of parts. b. AMS 2771 covers heat treatment of castings. c. AMS 2772 covers wrought raw materials only.

I.2 Refrigeration Consideration

Following quench, many solution heat treated aluminum alloys (specifically 2XXX series) require refrigeration. This process is to retain the parts in an as-quenched (W) condition, rather than allowing natural aging to occur. It is typical for parts that will be worked (sheet metal forming) as the W condition is softer and more ductile.

Documentation shall exist to show time parts took to get from the furnace to the refrigerator, and how long they have been kept in the refrigerator. The temperature at which to refrigerate will define the maximum time the parts can be retained in the refrigerator. Non-conformances should be written if parts are not in refrigerators in the required time and if they are retained in refrigerators beyond their maximum allowable time; however, the effect on the product is not metallurgical (only affects manufacturability) and should not be considered as potential product impact. AQ retention of sheet aluminum is for the purpose of formability only.

It is typical for a refrigeration unit to go through periodic defrost cycles. During these cycles, temperatures can exceed a refrigerator’s temperature tolerance. These departures are typically short enough to not allow parts to not lose their as-quenched condition. Unless Customer specifications specifically state otherwise, these temperature deviations are allowed and a non-conformance should not be written.

I.3 Conductivity Testing

AC7102/2 includes questions specific to conductivity testing; however, no separate approval for conductivity testing will be listed on supplier Nadcap certifications.

If Customer specifications do not give guidance, Supplier procedures shall specify allowable tolerance of acceptance for calibrations. It is not expected that calibration on shop floor standards will exactly meet values on the block; however, the allowed deviation must be proceduralized and the operator shall be aware of the allowance.

Do procedures reference compliance to ASTM E 1004 or MIL-STD-1537?

Do procedures reference that the conductivity test equipment shall require a periodic standardization every hour of continuous operation?

Do procedures state that equipment which does not provide accurate or repeatable results shall be corrected and recalibrated?

Does the inspection source report show the actual minimum and maximum values obtained?

It is assumed that the Conductivity and Hardness testing specification flowed down in AMS 2770 is AMS 2658 and it is the only testing specification mentioned in AMS 2770. AMS 2770H, Section 4.3, does not directly flow down any Conductivity and Hardness testing specification except for 4.3.1.2 for 6XXXX alloys and 4.3.3 under Failures. It is apparent that this was an oversight and will be corrected at the next revision of AMS 2770. In the interim, AMS 2658 will be considered the Conductivity and Hardness testing specification flowed down by AMS 2770, in the absence of any other direction by customer purchase order or contract.

Page 30: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

30

APPENDIX A: ALUMINUM SPECIFICATIONS Commodity: Aluminum Prime: Alenia Aeronautica SpA Governing Specification: NTA 71250 (parts) NTA 71251 & NTA 71252 (rivets) Allowable Specifications: AMS 2770, AMS 2771 (as applicable to the most current revision). Requirements: Pyrometry: NTA 98252 Process Control Tests: Monthly - HTO, IGC, Eutectic Melting, Clad Diffusion & Tensile:

• tensile (9 specimens symmetrically distributed within the working zone), • susceptibility to intergranular corrosion (1 test carried out on the specimen with the

lowest tensile yield strength), • eutectic melting and high temperature oxidation (1 test carried out on the specimen

with the lowest % elongation), • diffusion of alloying elements in the cladding

Load T/C: Not required Load Verification: Hardness and conductivity inspection Hardness Testing: Required on at least 10% of parts for every load (to be performed on parts with

minimum and maximum value of conductivity) or 100% if conductivity testing is not carried out (6xxx alloys)., Test per NTA 95051

Conductivity Testing: Required at 100% with registration of minimum and maximum values for each work order. Test per NTA 94551

Tensile Testing: Required for 7050-T74 forgings, extrusions and plates; 7075-T76xx sheets, extrusions and plates; 7475-T76xx sheets

Test per ASTM B 557

Commodity: Aluminum Prime: Bell Helicopter Textron Governing Specification: BPS 4139 Allowable Specifications: none Requirements: Pyrometry: AMS 2750 Purging compounds: 2000 and 7000 series, ammonium fluoborate, BPS 4139, par 2.2.1.2 Polymer Quenchants: composition IAW AMS 3025, Type I, no mixing of glycol manufacturers,

maximum salt contamination, par 2.3.7 and Table 8. Salt Bath Salts: MIL-S-10699, Class 2 with slight modifications, par 2.2.2 Quenchability Tests: Monthly on all solution heat treat furnaces, par 5.1.6 Load T/C: Not required Load Verification: Alloy dependent, par 6.2.3 Hardness Testing: Conditional on all parts as a substitute for tensile testing except for alloys listed

below. Test per BPS 4467 Tensile Testing: All 7XXX series. Test per ASTM B557 Conductivity Testing: Conditional on all parts as a substitute for tensile testing except for alloys listed

above. Test per BPS 4453 Note: When auditing jobs to Bell Helicopter Specifications, they allow Pyrometry to AMS2750 requirements In-

House ONLY, not for Outside Supplier’s. Bell has granted specific deviations (in writing) allowing AMS 2750.

Page 31: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

31

Commodity: Aluminum Prime: Cessna Aircraft Company Governing Specification: CSMP003 – Heat Treatment of Aluminum

CSMP004 – Heat Treatment & Surface Enhancement of Steels (Includes Stainless Steels and Carburizing)

CSMP010 – Heat Treatment of Nickel-Based Alloys CSMP047 – Heat Treatment of Titanium and Titanium Alloys Allowable Specifications: SEE BELOW Requirements: If the Auditor sees a Cessna drawing or parts where Cessna is identified as the Prime; the Auditor can assume that the above four specs will apply. How that conclusion is reached is very complicated. We may flow down the above specs on outside process specification sheets (OPSS) that state the processes we know have to be performed, but just because OPSS does not cover a heat treat spec doesn’t mean it’s not required. All Cessna designed parts have a note on the drawing in the tolerance block that says “Process per CSPS004”. That spec defines all processes that if performed are required to be performed per a Cessna spec. To our engineers, they don’t care if you use a process or not when they design a part, but if you do and its one we want controlled we want you to control it to our spec. It’s confusing, that’s why its safe to assume that if it is a Cessna part, Cessna heat treat specs apply. The other key issue is our limitations on industry heat treating specs. We do allow suppliers to use either our heat treating spec or industry specs in-part or in-full within a series of exceptions. For example, a heat treater working to CSMP003 can use the times and temperatures from AMS 2770. There are limitations on the extent a Supplier can use the industry spec. For all four of the Cessna specs listed above, the exceptions to industry standards are listed in Paragraph 9.0 (found on the last page of each document). While each alloy group has their own exceptions, the key exceptions are:

• Quality and Testing must be per the Cessna Spec (all items covered in Para 7.0) including all periodic testing listed

• Pyrometry is our spec, which states per AMS2750 with minor exceptions (e.g. aluminum solution treat must recover to low end of tolerance within 30 minutes)

We bring this issue up as some Suppliers are stating that they can run completely to industry specs if we call out CSMP003, which has more testing required.

Page 32: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

32

Commodity: Aluminum Prime: Goodrich Aerostructures Governing Specification: RPS 12.31 Requirements: Pyrometry: AMS 2750 Protective Compounds: Ammonium or sodium fluoborate per RPS 12.31 par 3.2.3. Polymer Quenchants: Compliant with AMS 3025, no mixing of Types I & II allowed. Salt Bath Salts: Compliant with Mil-S-10699, Class 2, test for Mg conc. if Al-Mg alloys used; test

quench/rinse media for salt/TDS as applicable per RPS 12.31 par 3.6. Quenchability Tests: Glycol concentration – test per RPS 12.31 par 4.7.7 & 4.7.8. Quenchant temperature - maintain per RPS 12.31 par 3.15.1.

Monthly – HTO, Eutectic Melting, IGA/Corrosion, Clad Diffusion and Mechanical Properties per RPS 12.31 par 4.7.6.

Load T/C: Not required. Load Verification: Hardness and conductivity inspection per RPS 18.11, tensile test as noted, per

ASTM B557. Refrigeration Control: Required per RPS 14.05. Hardness Testing: Required on 100% of parts on 7000 series heat treated to T7XXXX tempers;

required on 10% of parts on other aluminum alloys; except not required on perforated skin.

Tensile Testing: Required on each lot of alloy 7050 (also for monthly controls, as above). Conductivity Testing: Required on 100% of parts on all alloys. Commodity: Aluminum Prime: Vought Aircraft Industries, Inc. Governing Specification: 208-2-7 Rev. E Allowable Specifications: 208-2-7 allows suppliers to use AMS 2770, AMS 2771, & AMS 2772 (as applicable to the most current revision). Requirements: Pyrometry: AMS 2750 Polymer Quenchants: Compliant with AMS 3025 Salt Bath Salts: Compliant with MIL-S-10699 Quenchability Tests: Weekly – Glycol viscosity – Test per ASTM D 445 Monthly - HTO, IGC, Eutectic Melting, Clad Diffusion & Tensile Load T/C: Not required Load Verification: Hardness and conductivity inspection Hardness Testing: Required on at least 10% of parts for every load or 100% if conductivity testing

is 10%, except for 7000 series in T7XXX.. For 7000 series in T7XXX – 100% hardness inspection. Test per 208-14-16.

Tensile Testing: Each load of 7050T7XX & 7075 forgings quenched in glycol only– Test per ASTM B 557 Conductivity Testing: Required on all Al alloys 100% for every load or 10% if hardness testing is

100%– Test per 208-14-14

Page 33: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

33

Aluminum Specifications Commodity: Aluminum Prime: SONACA Governing Prime Specification: PS 6.4001 Allowable industry Specifications: None Requirements: Pyrometry: AMS 2750 Polymer Quenchants: Compliant with AMS 3025 Salt Bath Salts: Not accepted Quenchability Tests: Weekly and quarterly – Glycol concentration – test per PS 6.4001 par 3.4

Monthly – HTO, IGC, Eutectic Melting, Clad diffusion and Tensile – Test per PS 6.4001 par 6.1

Load T/C: Not required Load Verification: Hardness and conductivity inspection per PS 6.8003 Hardness Testing: Not required except for 6000 series - 100 % hardness inspection – Test per PS

6.8002 Tensile Testing: Not required on parts (only for monthly controls per ASTM B557) Conductivity Testing: Required on all alloys on 100 % of parts - Test per PS 6.8001

Page 34: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

34

APPENDIX B: PRIME SPECIFICATION MATRIX Alloy Specific Heat Treat Specifications

Prime Aluminum HT Steel HT Nickel-Based HT Titanium HT Magnesium HT Pyrometry

Airbus (UK) ABP3-1119 ABP3-1116 ABP3-1115 ABP3-1115 ABP3-1117 N/A BS M54

Airbus (Germany) 80-T-36-1010 80-T-36-1020 80-T-36-3300 N/A 80-T-36-1015

80-T-36-3400 N/A QVA-Z-09-10-00 QVA-Z-09-13-00 QVA-Z-09-14-00

Airbus (France) IPDA61-01 IPDA61-03 IPDA61-03 IPDA61-03 N/A IGC 04.63.100 IGC 04.63.105

Airbus (Spain) I+DP-220 I+DP-225 I+DP-226 N/A I+DP-222 N/A CASA-1036

Alenia Aeronautica

NTA 71250 NTA 71251 NTA 71252

NTA 71151 NTA 71152 NTA 71153

NA NTA 71351 NA NTA 98251 NTA 98252

Bell Helicopter BPS 4139 BPS 4140 N/A BPS 4212 MIL-M-6857 BPS 4416

Cessna Aircraft Co. CSMP003 CSMP004 CSMP010 CSMP049 MIL-M-6857 AMS 2750 &

Process Spec

Eurocopter France

MP 61.41.01 IGC 04.63.111 MP 61.48.10 MP 61.41.10 MP 61.41.11 IGC 04.24.103 EI 070-09-001 EI 070-09-006 IGC 04.63.130 ASNA written on the drawing

MP61.31.01 IGC 04.63.110 MP 61.31.02 IGC 04.63.122 EI 070-09-001 EI 070-09-006 IGC 04.63.130 ASNA written on the drawing

N/A

ASNA 6100 ASNA 6017 IFMa 247-50 EI 070-09-001 EI 070-09-006 IGC 04.63.130 ASNA written on the drawing

WE43: ECS 2133

IGC 04.63.100 IGC 04.63.105

Eurocopter Germany

EI045 36-1010

EI045 80-E-36-1020 EI045 80-E-36-3300 SAE AMS-H-6875

N/A

EI045 80-E-36-1015

N/A N/A

General Electric Aircraft Engines

P10TF1 (when vacuum ) AMS 2770 AMS 2771 AMS 2772 GE Part Drawings

P10TF1 (when vacuum ) AMS 2759

P10TF1 (when vacuum ) AMS 2773 AMS 2774 GE Part Drawings

P10TF1 (when vacuum ) AMS 2801 GE Part Drawings

N/A P10TF1 (vac) and AMS 2750

Goodrich Aerostructures

RPS 12.31 RPS 14.05 (Forming/ Icebox Ctrl)

RPS 12.01 RPS 12.02

RPS 12.01

RPS 14.02 n/a AMS 2750

Page 35: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

35

PRIME SPECIFICATION MATRIX-continued

Prime Aluminum HT Steel HT Nickel-Based HT Titanium HT Magnesium HT Pyrometry

Northrop Grumman

AMS 2770 H-101 HT-1 MIL-H-6088 SAE-AMS-2770

CVA 1-372 GSS 5100 GSS 5102 GSS 5103 GSS 5104 MIL-H-6875 H-105 H-106 H-110 H-109 H-108 HT-21 HT-15 HT-22 HT-19 HT-17 HT-18 HT-14

H-111 HT-13 208-16-1

MIL-H-81200B HT-10 H-102 GSS 5150 208-4-6

MIL-M-6857 AMS2750 QC-14 SC-301

Rolls-Royce Plc RPS953, RPS654 RPS953, RPS258, RPS356, RPS360, RPS394, RPS765

RPS953, RPS574 RPS953, RPS323 N/A RPS953

Rolls-Royce Corporation

EPS 285 EPS 290

EPS 242 EPS 251 EPS 253 EPS 259 EPS 260 EPS 499 EPS 484 EPS 486

EPS 415 EPS 416 EPS 423 EPS 433 EPS 435

N/A N/A AMS 2750

Sikorsky Aircraft

AMS 2770 AMS 2771 AMS 2772 SS8013 (7075-T73)

MIL-H-6875H(1) AMS 2759 SS8049 (4340 - 260ksi and above)

N/A

MIL-H-81200B AMS 2801 SS8445 SS8450 SS8452

AMS M 6857 AMS 2750

SONACA PS 6.4001 PS 6.4101 PS 6.4.201 N/A PS 6.4203 N/A AMS2750

Vought Aircraft Industries, Inc. 208-2-7

CVA 1-372 VSS 5100 VSS 5102 VSS 5103 VSS 5104

208-16-1 208-4-6 VSS 5150 N/A N/A

Honeywell E, S, &S AMS2770, AMS2771, AMS2772 P6000 91547- P6000

AMS2759 series HT5027 HT5045 HT5089 HT5100 HT5105 HT5106 P6000 91547-P6000

AMS2774 HT5086 HT5088 P6000 91547-P6000

MIL-H-81200 AMS2801 HT5061 P6000 91547 P-6000

AMS-M6857 P6000 91547-P6000

AMS2750

Page 36: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

36

Other Specifications

Prime Brazing Carburizing Nitriding Hardness Tensile Conductivity

Airbus (UK) N/A ABP3-1111 ABP3-1113 ABP6-5226 BS4A4 ASTME8 ABP6-5226

Airbus (Germany) N/A 80-T-36-3001

80-T-36-3201 80-T-36-3350 (Gas)

QVA-Z-10-41-00 QVA-Z-10-42-00 QVA-Z-10-43-00

QVA-Z-10-37-00 QVA-Z-10-50-01

Airbus (France) N/A N/A N/A IGC 04.29.100 IGC 04.21.11 IGC 04.25.120

Airbus (Spain) N/A I+DP-217 I+DP-218 ASTM E18 ASTM E8 I+DP-140

Alenia Aeronautica

NA NA NA NTA 95051 ASTM E8 ASTM B557

NTA 94551

Bell Helicopter BPS 4098 BPS 4420 BPS 4304 BPS 4467 ASTM E 8 BPS 4453

Cessna Aircraft Co.

CSMP008 CSMP009 CSMP004 CSMP004 CSTI028

ASTM E8 or ASTM B557 as applicable

CSTI008

Eurocopter France N/A

IFMa 516 IGC 04.63.120 ASN 412.05 EI 070-09-001 EI 070-09-006 IGC 04.63.130 Copper plating : MP 62.31.16 IGC 04.73.112 IFMa 232

IFMa 372 IFMa 510 MP 61.31.11 ASN 412.04 HS 5008.010 EI 070-09-001 Phosphate conversion : MP 62.31.30 IGC 04.72.100 EI 070-09-006 IGC 04.63.130 Copper plating : MP 62.31.16 IGC 04.73.112 IFMa 232 Ion nitriding : HS 5008-040

IGC 04.21.100 L070-007 IGC 04.14.100

IGC 04.21.111 IGC 04.21.112

IGC 04.25.120 EI 070-09-012 L070-007

Eurocopter Germany N/A N/A N/A N/ADIN EN ISO

6507 DIN EN 10002 EI075 10-029 DIN EN 2004-1

General Electric Aircraft Engines

P9TF1 P29TF6 P10TF1 S-405 M50T1 GE Part Drawings

C50TF50 C50T16 C50T1506

C50TF5 C50TF14 P11TF2 P11TF10 P11TF1

S-400 S-400 AMS 2658

Goodrich Aerostructures

RPS 11.76 RPS 11.72 RPS 11.73 RPS 11.79 RPS 12.33

AMS 2759/7 RPS 12.06

RPS 12.03

RPS 18.11

ASTM B557 ASTM E8

RPS 18.11

Honeywell E, S, & S

WBS5027 HT5042 91547-P6030

HT5040 91547-P6031

ASTM E 10 ASTM E 18 ASTM E 384

ASTEM E 8 ASTM E 21

AMS2658

Page 37: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

37

Other Specifications - continued

Prime Brazing Carburizing Nitriding Hardness Tensile Conductivity

Northrop Grumman

W-26 W-25 W-27

H-107 H-113 HT-4 MIL-N-22061 SAE-AMS-S-6090

H-107 H-113 HT-4 MIL-N-22061 SAE-AMS-S-6090

N/A FED-STD-151 N/A

Rolls-Royce Plc

RPS371 RPS135 MSRR9969 MSRR9968 MSRR9922 BS L100 EN2004-1

Rolls-Royce Corporation

RPS 194 & RPS 953

EPS 200 EPS 206 EPS 214 EPS 215 EPS 216 EPS 222

EPS 227 EPS 270 EPS 271 EPS 272 EPS 292

ASTM E 18 N/A N/A

Sikorsky Aircraft

AWS C3.4 AWS C3.5 AWS C3.6 AWS C3.7

SS8015 N/A ASTM E 18 ASTM E 384 ASTM E 8 MIL-STD-1537B(1)

AMS 2658

SONACA N/A PS 6.4150 N/A PS 6.8002

ASTM B557 ASTM A370 ASTM E8

PS 6.8001

Vought Aircraft Industries, Inc.

N/A N/A N/A 208-14-26 N/A 208-14-14

Page 38: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

38

APPENDIX C: AMS 2750 VS RPS 953 Comparison Chart

Requirement AMS 2750 Rev D RPS 953 Issue 12 ELECTRONIC RECORDS Clause 3.2.7 As AMS clause 3.2.7 with the addition that back up records are

made and retained in a separate location, ref. RPS953 2.3.3.1.

RECORD RETENTION Clause 3.7.1 (5 years minimum) As AMS clause 3.7.1 modified by RPS900, ref. RPS953 2.3.1

WIRE ROLL CALIBRATION Clause 3.1.1.6 As AMS clause 3.1.1.6 except that rolls <305 meters (1000 feet) must also be calibrated at each end, ref. RPS953 2.8.

OVERTEMPERATURE SENSORS (Load Protect)

a. aluminum/ magnesium materials

Offset not defined in Rev D For load protect and set at +10C to set point, ref. RPS953 4.2.2.

b. others Offset not defined in Rev D For load protect and set at +20C to set point, ref. RPS953 4.2.2.

TEMPERATURE UNIFORMITY TEST FREQUENCY

As clause 3.2.5 and Table 8 and 9

AMS clause 3.2.5 & Table 8, except that for Class 2 furnaces relaxation is to semi annually. Note that RR don’t accept the classification ‘Raw Material’ furnaces (Table 9), ref. RPS953 4.3.4.

TEMPERATURE UNIFORMITY SURVEY

Spread Acceptance Levels As clause 3.3.1

• For < 750 C require Class 2 furnace, i.e. +/- 6 C. • For ≥ 750 C require Class 4 furnace, i.e. +/- 10 C. • For vacuum furnaces ≥ 500 C require Class 4, i.e. +/- 10 C. Ref. RPS953 4.3.3

As clause 3.5.6

As AMS clause 3.5.6 except that for Class 2 furnaces surveys shall be carried out at the highest and lowest temperature and intermediate temperatures such that the range is no greater than 400 C, ref. RPS953 4.3.4.

FURNACE SYTEM ACCURACY TEST FREQUENCY

As clause 3.4 and Tables 1, 3, 6 and 7.

As AMS clause 3.4 and Tables 1, 3 and 6. Note that RR don’t accept the classification of ‘Raw Material’ furnaces (Table 7), ref. RPS953 2.8 & 4.4.

FURNACE ACCURACY CHECKS

As clause 3.4 and Tables 6 and 7.

As AMS clause 3.4 and Table 6. Note that RR don’t accept the classification of ‘Raw Material’ furnaces (Table 7), ref. RPS953 2.8 & 4.4.

Note: 1. Rolls Royce RPS 953 Section 4.3.2 requires that all furnaces shall have a minimum of one recording thermocouple for

every one cubic meter up to a maximum of 5 cubic meters and there after the number shall be agreed with Rolls-Royce. 2. Rolls Royce RPS 953 Section 4.3.3 Note 2 states that none-critical heat treatments such as annealing (unless the final

heat treatment) pre-heating prior to hardening, homogenizing, normalizing or stress relieving (where the stress relief is at least 50 deg C (90 F) below the final transformation temperature) with agreement from Rolls-Royce are not considered as Thermal Process (Heat Treatment) furnaces and will not therefore require Nadcap approval. This also applies to ovens used for drying or fitting, which also don’t require Nadcap approval.

Page 39: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

39

APPENDIX D: AMS Heat Treating Specification – Start of Soak Time Recommendations

Spec Description Existing Start of Soak Method Suggested Start of Soak Method and HTTG approach

Comments

2759D HT of Steel - General

N/A N/A Refer to specific 2759/x

2759/1D HT of Steel < 220 KSI

Soaking shall commence when all control, indicating, and recording thermocouples reach the specified set temperature or, if load thermocouples as defined in AMS 2759 are used, when the part temperature reaches the minimum of the furnace uniformity tolerance at the set temperature.

Control thermocouple(s) within 5°F of setpoint and all other recording or indicating thermocouples reach the minimum of the required temperature uniformity tolerance at the set temperature. Load T/C portion can remain as is.

Needs to be revised

2759/2D HT of Steel ≥ 220 KSI

Soaking shall commence when all control, indicating, and recording thermocouples reach the specified set temperature or, if load thermocouples as defined in AMS 2759 are used, when the part temperature reaches the minimum of the furnace uniformity tolerance at the set temperature.

Control thermocouple(s) within 5°F of setpoint and all other recording or indicating thermocouples reach the minimum of the required temperature uniformity tolerance at the set temperature. Load T/C portion can remain as is.

Needs to be revised

2759/3D HT of PH CRES Steel

Soaking shall commence when all control, indicating, and recording thermocouples reach the specified set temperature or if load thermocouples, as defined in AMS 2759, are used, when the part temperature reaches the minimum of the furnace uniformity at the set temperature.

Currently under revision @ AMEC

Current proposal requires control T/C within 5°F and other furnace indicating or recording T/C’s must reach the minimum of the uniformity tolerance.

2759/4B HT of Austenitic CRES

Soaking shall commence when all control, indicating, and recording thermocouples reach the specified set temperature or, if load thermocouples as defined in AMS 2759 are used, when the part temperature reaches the minimum of the furnace uniformity at the set temperature.

Control thermocouple(s) within 5°F of setpoint and all other recording or indicating thermocouples reach the minimum of the required temperature uniformity tolerance at the set temperature. Load T/C portion can remain as is.

Needs to be revised

2759/5D HT of Martensitic CRES

Soaking shall commence when all control, indicating, and recording thermocouples reach the specified set temperature or if load thermocouples, as defined in AMS 2759, are used, when the part temperature reaches the minimum of the furnace uniformity at the set temperature.

Control thermocouple(s) within 5°F of setpoint and all other recording or indicating thermocouples reach the minimum of the required temperature uniformity tolerance at the set temperature. Load T/C portion can remain as is.

Needs to be revised

2759/6B Gas Nitriding N/A The load shall be held at nitriding temperature(s) in partially dissociated ammonia atmosphere for sufficient time to produce the specified depth of case.

Supplier needs to identify in their internal procedure the defined method of start of the soak.

Start of soak method must be defined in the internal procedure.

Page 40: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

40

APPENDIX D: AMS Heat Treating Specification – Start of Soak Time Recommendations (Contd)

Spec Description Existing Start of Soak Method Suggested Start of Soak Method and HTTG

approach

Comments

2759/7A Carburizing The charge shall be held within the specified temperature range for sufficient time for necessary diffusion and transformation to take place. The holding time intervals shown in Table 3 are suggested times starting when furnace control instruments reach set temperature or when the lowest load thermocouple reaches the lower limit of the required temperature range.

Supplier needs to identify in their internal procedure the defined method of start of the soak.

Start of soak method must be defined in the internal procedure.

2759/10A Automated Gas Nitriding (N2 Potential)

N/A Supplier needs to identify in their internal procedure the defined method of start of the soak.

Start of soak method must be defined in the internal procedure.

2759/11 Stress Relief Soaking time starts when all temperature sensors are within 25 °F (14 °C) of the specified temperature.

2759/12 Gaseous Nitrocarburizing – Automatically Controlled

N/A Supplier needs to identify in their internal procedure the defined method of start of the soak.

Start of soak method must be defined in the internal procedure.

2769A Vacuum Heat Treatment

Load Thermocouples (or Initial Load Qualification with Load Thermocouples) is required. Start of Soak would revert to the referenced heat treating specification.

Supplier needs to identify in their internal procedure the defined method of start of the soak and meet all the customer requirements.

N/A

2770H HT of Aluminum Parts 3.2.5.1 - Soaking time starts when all temperature control sensors reach the minimum of the uniformity tolerance range specified in 3.1.1.1, 3.1.1.2, or 3.1.1.3, as applicable. Load sensors should not be used to determine start of soaking time. This is modified by Table 3, Note 2 for Solution Heat Treating - Soaking time starts when all thermocouples are within 10 °F (6 °C) degrees of the set temperature; and by Table 8, Note 2 for Annealing - Soaking time starts when all thermocouples are within temperature range indicated.

Soaking time starts when all control, recording, and monitoring sensors reach the minimum of the uniformity tolerance range specified in 3.1.1.1, 3.1.1.2, or 3.1.1.3, as applicable. Load sensors should not be used to determine start of soaking time.

This is wording that was agreed upon at the 10/2009 AMEC meeting for inclusion in the next revision. Note: The specification says that, "Load sensors should not be used to determine start of soaking time.", but does not prohibit the use of load sensors for determining start of soak. Start of soak method must be defined in the internal procedure.

2771C HT of Aluminum Castings

Soaking: Soaking time starts when all temperature control sensing elements and load thermocouples (if used) are within 10 °F (6 °C) of the set or offset temperature.

No change necessary. N/A

Page 41: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

41

APPENDIX D: AMS Heat Treating Specification – Start of Soak Time Recommendations (Contd)

Spec Description Existing Start of Soak Method Suggested Start of Soak Method and HTTG approach

Comments

2772D HT of Aluminum Raw Material

Solution Treatment: Soaking time shall start when the readings of all load sensors indicate that the temperature of the load has reached the minimum of the required temperature range. Alternatively, determination that the temperature of the load has reached the minimum of the required temperature range (start of soaking time) may be based on readings of furnace instruments providing the lag between their readings and load temperature has been determined in a similarly arranged load. Aging: Times are recommended

No change necessary. N/A

2773A HT – Cast Nickel Alloy & Cobalt Alloy Parts

Batch Furnaces: Soaking time starts when all furnace temperature sensors reach the specified set or offset temperature or, if load thermocouples are used, when the coldest load thermocouple reaches the required temperature minus the appropriate tolerance. Vacuum Furnace: Unless otherwise specified by the cognizant engineering organization, load thermocouples shall be used to determine the start of soaking time except when this is impractical, such as with two or three chamber oil or gas quench furnaces, in which case tests shall be conducted to establish the correct heat-up time for the load. Once a load has been qualified with load thermocouples, subsequent loads may be run without load thermocouples provided records detailing the number of parts in the first qualified load are kept on file, and provided that subsequent loads have an equal or fewer number of similar parts in the load, and the distribution of the parts is the same as the distribution in the first load.

Batch Furnaces: Control thermocouple(s) within 5°F of setpoint and all other recording or indicating thermocouples reach the minimum of the required temperature uniformity tolerance at the set temperature. Load T/C portion can remain as is.

Needs to be revised

Page 42: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

42

APPENDIX D: AMS Heat Treating Specification – Start of Soak Time Recommendations (Contd)

Spec Description Existing Start of Soak Method Suggested Start of Soak Method and HTTG approach

Comments

2774A HT – Wrought Nickel Alloy & Cobalt Alloy Parts

Batch Furnaces: Soaking time starts when all temperature sensors reach the specified set or offset temperature or, if load thermocouples (See 8.4.4) are used, when the part temperature reaches the temperature described by the set or offset temperature minus the appropriate tolerance (3.1.2.1). Vacuum Furnaces: Unless otherwise specified by the cognizant engineering organization, load thermocouples shall be used to determine the start of soaking time except when this is impracticable, such as with two or three chamber oil or gas quench furnaces, in which case tests shall be conducted to establish the correct heat-up time for the load. Once a load has been qualified with load thermocouples, subsequent loads may be run without load thermocouples provided records detailing the number of parts in the first qualified load are kept on file, and provided that subsequent loads have an equal or fewer number of similar parts in the load, and the distribution of the parts is the same as the distribution in the first load.

Batch Furnaces: Control thermocouple(s) within 5°F of setpoint and all other recording or indicating thermocouples reach the minimum of the required temperature uniformity tolerance at the set temperature. Load T/C portion can remain as is.

Needs to be revised

Spec Description Existing Start of Soak Method Suggested Start of Soak

Method and HTTG approach Comments

2728A HT – BeCu Parts Soaking shall commence when all control, indicating, and recording thermocouples reach the specified set temperature or, if load thermocouples are used, when the part temperature reaches the minimum of the furnace uniformity tolerance at the set temperature.

Control thermocouple(s) within 5°F of setpoint and all other recording or indicating thermocouples reach the minimum of the required temperature uniformity tolerance at the set temperature. Load T/C portion can remain as is.

Needs to be revised

Page 43: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

43

APPENDIX E: Lead Auditor Handbook Scope: The purpose of this manual is to provide lead auditors with a frame work for how a heat treating audit is to be properly conducted. This manual outlines the proper sequence in which an audit should be conducted and also gives guidance of the data and records which must be reviewed as part of a thorough audit. The manual also specifies the functions and testing which must be witnessed during the course of the audit. Lead auditors are to use this manual as a guide for conducting training audits. This manual will also be provided to auditor trainees so that they may adequately prepare themselves in advance of their training audits. Evaluation forms for trainees are to be completed after each training audit and submitted electronically to the Manager of Auditor Staffing and Training with a copy to the applicable staff engineers. The lead auditor should request the previous evaluations of any trainee which is scheduled for a T2 or higher and review the comments on the form prior to the next training audit. This will ensure that the areas of concern as identified by the previous lead auditor are addressed in the next training audit. All trainees must stay with the lead auditor at all times during the training audit, unless specifically instructed by the lead auditor to perform a special task. Before the Audit: The auditor needs to review the following:

• Previous Auditor Letters and NCR’s, so that they understand past areas of concern • Review quality manual and procedures

When the auditor contacts the supplier, the auditor must request:

• The supplier to process actual production or representative test material for the auditor to witness during the audit.

• The size and proximity of multiple heat treat areas in the same supplier, in case they are spread out. • Find out if there are any proprietary or Export controlled processes on site.

Conducting an Audit: The first day of the audit should include a short walk through to see what type of material is in process what the processing capabilities are, and identifying what materials and processes the supplier expects to be running that week. In general, the order of the audit should be: select and witness long jobs, select short jobs on floor, do long jobs, select and witness more short jobs, review and witness pyrometry , perform brazing job audit, witness hardness, do remainder of YES/NO questions in the checklist, and complete the quality system AC7004. Be sure to thoroughly explain how the entrance and exit interviews are to be performed and what supplier documents are required to be attached to the checklist by the auditor. Also, ensure that the trainees know to conduct a daily out briefing meeting each day to review the NCRs with the Supplier. The following will help to outline the audit flow:

Page 44: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

44

Job Selection and Observation:

• Select the eight short jobs trying to get all eight as in process jobs when possible. Use the long jobs from completed work which will fill in the gaps of the required materials/processes which cannot be observed as in process jobs.

• The priorities for job audit type selection are listed in the Audit Handbook. It is more important to cover the processes than to balance the primes whose work is selected.

• Supplier selection of long jobs to be audited should not be permitted. The auditor can advise the supplier what types of material, the primes, and the specifications, and then request the supplier to identify several jobs which satisfy these requirements. The auditor then can choose jobs from those which have been identified or pull the completed jobs from shipping.

• For short jobs in a captive shop where eight jobs are not available to be witnessed, the auditor is to select the jobs from either a shipping or furnace log. The auditor should witness as many in process jobs as possible. In a manufacturing house, it may be necessary to ask the supplier to have several people help to pull the required paperwork. Many times the required paperwork is in several places which are spread out.

• It is advisable to walk the floor several times a day during the audit. Once first thing in the morning, once at mid-morning, after lunch, mid-afternoon, and at the end of the day. This is necessary to encompass all of the furnaces and processes which the supplier needs to have covered in the scope of the audit. Being on the shop floor often affords the opportunity to select jobs which are not being run correctly, and gives a feel of the frequency of how often this happens. In manufacturing houses where the Heat Treating Department is far away or very spread out, try to set up a desk near the shops in a clean area, and work from here. Have numerous conversations with the operators to determine if they know what to do and how to do it in accordance with the procedures. Do not let the management answer for the operator.

• Review and discuss the work instructions as the audit is progressing through each area to ensure that procedures meet the requirements in the checklist. While the supplier is collecting all of the required paperwork and data, use this time to observe the hardness inspector performing periodic checks and actual part testing.

• If the shop has three shifts, stay late one day, come in early another, and at least get a feel for the work practices. Be especially conscious of handoffs between shifts. Look for the challenging or potential problem jobs.

• Be present for the job prior to being charged into the furnace and/or immediately after the job is pulled to verify the racking and T/C placement. Look into the furnace when the job is being pulled and/or loaded. Observe the multipoint positioning and/or load T.C. location vs. TUS high and low. Evaluate load T/C position, whether they are located or attached and how. Verify that all this is documented in procedures.

• The quench must be witnessed. This is mandatory for Aluminum, Titanium, and Alloy Steel. Pay attention to quench delay times. Also, pay attention to orientation of parts to preclude trapping gasses and to entrapment of fluids in fixtures.

• Compare the indicating temperature with the recorded temperatures, multipoint, over temperatures, and recordings for short jobs. Verify that all of the instrumentation is functioning properly.

• Witness jobs for operator accuracy and consistency in determining heat up times and soak times vs. thickness/load size, furnace type and size, etc. Verify that operators are following procedures.

• Watch automated start of soak to ensure the program starts soak at the correct time.

• Verify that the posted offset is correct and that the operator is entering the posted offset correctly. Verify that the procedure for offsetting is correct and that the operator is following the procedure.

• Verify that furnace instruments are adjusted/biased correctly when done by in-house personnel.

• When performing job audits assure that all customer specification requirements are flowed down correctly and that the requirements such as time, temperature, and periodic testing are being met.

Page 45: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

45

Review of Pyrometry:

• Verify that refrigeration controls, logs for time-in/time-out, etc are correct.

• Review TUS results. Ensure that the TUS is being performed in a manner which reflects the most severe operating conditions in production. If a TUS is not performed during the audit, talk to your trainee about the checklist requirements and explain what evidence should be reviewed for each question. Verify that all production overshoots also appear as overshoots during a TUS. Assure that there have not been any setting changes. Make sure that a recurrent temperature pattern is understood.

• Witness TUS set-up. Verify that the TUS racks are the same size as the work zone. Ensure that the T/Cs are not bent inward. Verify the correct application of correction factors based on the way they are being reported on the T/C certification.

• Witness probe checks during the audit, preferably for each of the different types of furnaces which the supplier has in use. Verify that actions are being taken if the difference is greater than specified in AMS 2750 for the furnace class and instrument type.

• Check a sampling of calibration certificates and even thermocouple wire certificates. And ensure that deviation/errors or corrections are applied correctly.

• Make sure that deadband (per BAC5621 only) and sensitivity are understood and correctly defined in procedures.

• Verify carbon potential and other atmosphere controls and tolerances are correct. Review of Required Records and Data:

• Observe the equipment and records to see if preventative maintenance such as oil and filter changes, etc., appear to be done as required.

• Verify that all required tests, such as probe checks appear to be done and probe temperatures match actual furnace temperatures.

• Review dew point logs, leak up rate records, maintenance records, etc. Go to the location where these records are being maintained. Do not request the supplier to bring the records to the auditor. The auditor should go to the data

Cleaning and Plating:

• Cleaning must be observed. Verify bath temperatures, composition, agitation, etch rates, etc. Brazing:

• Each step of the brazing process must be witnessed. Verify the set up, assembly, application of filler metal, etc. Verify the checklist requirements are being met for all applicable brazing process steps which are performed in house. An in process brazing job must be witnessed. If the supplier does not currently have brazing approval from a prime and there is not any in house work to evaluate, coupons or scrap parts can be run (in the case for initial approval only). The entire flow down and brazing process to the prime specs must be simulated in this event.

Testing:

• Witness hardness testing, including periodic tests on the test blocks and testing of parts. Witness the changing of an anvil and/or penetrator and verify that the reseating is done. Verify penetrator examination. Verify that the periodic check after a change of either the penetrator or load is done properly and in accordance with the procedure.

• Verify test block serial number change recordings and the test block has approximately the appropriate number of indentations.

• Verify 100% hardness testing or the required sampling is being performed by examining indentation on the parts in final inspection or shipping. Witness dew point checks and leak checks if they are at all questionable or time permits.

Page 46: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

46

• Witness a polymer refractometer test.

• Witness parts testing for conductivity. Also witness the stabilization and calibration checks.

• Talk with inspectors and ask questions to assess if they understand the internal procedures. AC7004:

• It is important to realize, when you are performing an AC7004 audit, you may be performing it for other disciplines as well. The audit should verify the entire quality system as it relates to all special processes, not just the technology with which you are most familiar. Look in their MRB Cage to assure everything is identified correctly. Ask about root cause and action to prevent recurrence.

NCR Writing:

• Writing NCRs. Make sure they are clearly written. It is better to include more information to ensure that they are clearly written at the expense of being concise. Define how and by how much the condition found deviates from the requirement.

• Combine NCRs whenever possible. Ensure that the root cause and action to prevent recurrence will be the same for those which will be combined.

• Review each NCR with the supplier as they are identified during the audit and at the end of each day. Make sure the supplier understands as exactly as possible the observed non-conformity.

• Make sure that the supplier knows where the root cause corrective action tutorial is on the PRI website. Provide them with the link to the tutorial and show them how to get to the website.

• Explain the difference between preventive action and action to prevent recurrence.

Ethics and Professionalism

• Be very careful when observing supplier and prime proprietary information. Avoid auditing proprietary processes if possible.

• Avoid auditing direct government procurements (break out) if possible. Many primes are not allowed to comment on or review such jobs.

• Let suppliers express their opinions and, if they have a case, listen and use staff and primes as resources. But, never argue with a supplier to the point of becoming emotional

• Never express the opinion or convey the impression that you are smarter than the supplier or can in any way affect his accreditation. You are an observer who documents your observations. Disposition of those findings lies with staff and primes.

• Avoid comments or actions that would give the supplier the idea that you are anything but a fair, objective, thorough, discreet and professional auditor.

• Keep the audit as positive as possible.

• Do not dwell on negative points - Make them once, emphatically, and move on to next issue.

• Please refer to NIP 7-07 for additional information on ITAR/EAR.

Page 47: Audit Handbook 01-Dec-09 Doc Mc

Nadcap December 01, 2009 HEAT TREATING TASK GROUP AUDIT HANDBOOK

47

DOCUMENT REVISION HISTORY

Effective Date Summary 11 May 2006 All Sections 8 Nov 2006 Replaced Major & Minor Definitions with new NMC approved definitions 9 February 2007 Adding Clarification on Cessna Specifications (page 23)

Adding –Major/Minor definitions (HT specific to support NMC definitions) Page 5

01 March 2007 Adding paragraphs E1.3.1, E1.3.2, E1.3.3, E1.3.4 and E1.3.5 to address the clarification for RT Tensile Testing Revised E1.3 clarification on allowed categories of testing in AC7101/4

12 March 2007 Revised paragraph C2 The following items are required to be attached to the checklist

on page 2: 1. Cover Letter 2. Staff Report form t-frm-71 3. Quality Systems Certificate 4. GT193 form (for General Electric) when applicable

30 August 2007 Changed Follow-up audits to VCA audits.

Activation definition added. Revised definitions for Major and Minor findings Revised Objective Evidence requirement wording Revised section C.2 regarding Staff Report

01 October 2007 Changed reference to AC7102 Revision C to Revision D Revised checklist listing to include AC7102/S. Added revised Intergranular Oxidation/Intergranular Attack (IGO/IGA) wording.

17-January 2008 Addition of C2.e. Correction of typographical errors. 4 March 2008 APPENDIX: AMS 2750 VS RPS 953 Comparison Chart revised 7 March 2008 Chapter D revised from “must maintain a Process Control Matrix” to

“should maintain a Process Control Matrix”. 22 April 2008 Addition of AMS Heat Treating Specifications – Start of Soak

Recommendations. Removed “GM Quench-O-Meter” from section E4.

31-July-2008 Section C2 revisions. Editorial changes.

31-October-2008 Update checklist listing in “Forward” Delete AC7101/5 reference in section E, Reorder section E Add Appendix E (merged Lead Auditor Handbook with Audit Handbook)

31-March-2009 Addition of C9 Clarification of E1.5

30-October 2009 Addition/Clarification for Conductivity Testing on E1.5 and I3. Clarification for Start of Soak for AMS 2770 in Appendix D. Editorial changes.