ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid N. Delruelle on behalf of the TE/CRG group LS1 Infrastructure Meeting – 09 Jul 2014

ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid

Embed Size (px)

DESCRIPTION

ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid. N. Delruelle on behalf of the TE/CRG group LS1 Infrastructure Meeting – 09 Jul 2014. 3D-model of the new supply. Existing transfer line TL2. New transfer line TL4. New 10’000 L dewar. - PowerPoint PPT Presentation

Citation preview

Page 1: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

ATLAS LS1 infrastructure: Installation of a new 10’000 litre

LHe dewar for the Solenoid

N. Delruelle on behalf of the TE/CRG groupLS1 Infrastructure Meeting – 09 Jul 2014

Page 2: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

2

3D-model of the new supply

TE/CRG/N.Delruelle – LS1 infrastructure – 09 Jul 2014

New 10’000 L dewar

New valve box

New transfer line TL4

Existing transfer line TL2

Existing transfer line TL3 to solenoid

Courtesy of Jos Metselaar

Page 3: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

3

New supply installed

TE/CRG/N.Delruelle – LS1 infrastructure – 09 Jul 2014

New 10’000 L dewarNew transfer line TL4 (during transport)

Page 4: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

4TE/CRG/N.Delruelle – LS1 infrastructure – 09 Jul 2014

New supply installed

Page 5: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

5TE/CRG/N.Delruelle – LS1 infrastructure – 09 Jul 2014

UPDATED 8th july 2014

09/0

6/2

014

16/0

6/2

014

23/0

6/2

014

30/0

6/2

014

07/0

7/2

014

14/0

7/2

014

21/

07/2

014

28/0

7/2

014

04/0

8/2

014

11/0

8/2

014

18/0

8/2

014

TL5 transfert line

Connection on VB

Helium leak test

Pressure test

Degazing and vacuum

Connection on existing line

TL4 transfert line

Connection on VB and helium dewar

X rays 10%

Helium leak test

Pressure test

Degazing and vacuum

Valve box

Pressure test

Connection on existing TL3

10000 L Helium tank

Pumping pipe modifi cation

Pressure test

Test acceptance

Main electrical box

Handling in USA15

Electrical connection

Test acceptance

09/0

6/2

014

16/0

6/2

014

23/0

6/2

014

30/0

6/2

014

07/0

7/2

014

14/0

7/2

014

21/

07/2

014

28/0

7/2

014

04/0

8/2

014

11/0

8/2

014

18/0

8/2

014

CERN CONTRACT N° F623/PH/ATLAS

26 27 28 29 30

27 28 29 30

25

25 26

31 32 33 34

31 32 33

Page 6: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

6

Installation & Tests planning

► 10% X-rays on weldings between dewar, TL4 and valve box: Tue 15 July 2014

► Helium leak test on dewar, TL4 and valve box: Thu 17 & Fri 18 July 2014

► Pressure test of the whole supply before connection (cutting) to the existing system: Mon 21 & Tue 22 July 2014

► Outgassing of TL4 & TL5 with hot GN2 (~100 °C) sent from USA15 towards UX15: From Wed 23 till Tue 29 July 2014

TE/CRG/N.Delruelle – LS1 infrastructure – 09 Jul 2014

Page 7: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

7

Installation & Tests planning

► Cutting of the existing TL3 (going to Solenoid control dewar): From Thu 24 till Thu 31 July 2014

► 100% X-rays on weldings done on the existing TL3: Thu 31 July 2014

► Final tests after connection to existing system: From Mon 04 till Fri 08 Aug 2014

TE/CRG/N.Delruelle – LS1 infrastructure – 09 Jul 2014

Point of no-return…