14

Athletic Field Feasibility Study

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Athletic Field Feasibility Study
Page 2: Athletic Field Feasibility Study

Athletic Field Feasibility Study

• Discuss approval and permitting requirements

• Examine 3 potential sites for baseball/softball/multi-purpose use

• Provide options, costs and timelines

• Determine next steps for further refinement

Page 3: Athletic Field Feasibility Study

Approval and Permitting Requirements

• All ballfields exceed 1 acre in disturbance for construction requiring an

NPDES permit from the Bucks County Conservation District

• Ballfields and structures may require Township/Borough land development

approvals

• Building structures require Township/Borough building code review

• Ballfields are most commonly designed and publicly bid or delivered

through a competitive State Contract procurement process

… the design, approval and procurement process takes time. This effort, unfortunately does not permit a Summer 2021 construction timeline.

Page 4: Athletic Field Feasibility Study

Nazareth Baseball Stadium – Public bid• Natural grass Field• Dugouts• Protective netting• Scoreboard• Outfield wall• Ideal site/no fill• Bleachers for 75• Bull pen/no cages• Minimal site fencing• Paved walk/no parking• No lights ($500K to add)• No concession building• No restroom building• Constructed in 2019• $1.15M Construction• $172K in soft costs

$1.3M overall

Escalate to midpoint 2022 at 4%...say $1.5M - $2M

Page 5: Athletic Field Feasibility Study

• Synthetic baseball, softball & multi-purpose field

• Dugouts• No netting• Scoreboard• Outfield fence• Ideal site/no fill• Portable bleachers• Bullpen and cages• Minimal site fencing• Paved walk/no parking• Lights• No concession building• No restroom building• Constructed in 2020• $2.4M Construction• $200K in soft costs

$2.65M overall

Escalate to midpoint 2022 at 4%...say $2.8M-$3.0M

Perk Valley Baseball Stadium – State Contract

Page 6: Athletic Field Feasibility Study

6th Grade Center Option – 1 baseball field

6

• Quakertown Borough• 1 baseball field fits (w/ site modifications)

w/ good orientation• Crowds the site• Outfield overlaps soccer field & shot put• Adjacent to but not in flood plain• Requires fill and underdrain system• Not a synthetic option due to moisture• Not a suitable for lights• Protective nets required at road/parking

Page 7: Athletic Field Feasibility Study

Strayer MS Option – 1 baseball field

7

• Richland Township• 1 baseball field fits • Eliminates current baseball field• Requires fill to level• Outfield overlaps soccer field• Adjacent to but not in flood plain• Requires fill/underdrains to keep “drier”• Not a preferred synthetic option• Not a site suitable for lights (neighbors)

Page 8: Athletic Field Feasibility Study

Pumping Station Road Property – Multi-field option

• Milford Township• Future school site• Space for multiple fields, parking,

spectators, concession and toilet facilities• Elevated site, no underdrain system• Suitable for lights• Requires land planning, access roads and

a more extensive approvals process

Page 9: Athletic Field Feasibility Study

Pumping Station Road Property – Multi-field option

SCHRADERGROUP2017 Site Master Plan Option

Page 10: Athletic Field Feasibility Study

Pumping Station Road Property – Multi-field option

Site Master Plan Option

• Natural Grass Field • Align new entrance(s) with St. Isidore• Create the future site development

driveway• Install new site utilities for sewer,

water and power• Parking (187)• Bleacher seating for 400/300• Buildings for concessions and toilet

rooms• Lights on 1 field at least• Sod could be an alternate in lieu of

seeding• Option for 1 synthetic field +$1M

• Assume 6 months for design and permitting and 6 months for construction and a “grow in” seasonfor sod (if selected)

Page 11: Athletic Field Feasibility Study

Pumping Station Road Property – Multi-field optionItem

Concept Budget

5/5/2021

Construction of Baseball Stadium and walkways 1,600,000$

Construction of Softball stadium 900,000$

Option for Lights on one field 500,000$

Construction of Concessions & Toilet Room Outbuilding 680,000$

Other Site Improvements 2,200,000$

Allowance for Off-Site Improvements 100,000$

TOTAL CONSTRUCTION COSTS 5,980,000$

Site Surveying Costs 30,000$

Hazardous Materials Investigation -$

Geotechnical Investigation /Materials Testing 60,000$

Design fees 358,800$

Civil Engineering & Land Development Approval fees 85,000$

Construction Management fees 239,000$

Legal fees and Builders Risk- Allowance 60,000$

Building permit 100,000$

Land Development Inspection Escrow 250,000$

Water, electric, sewer utility (no gas) 105,000$

FF&E -$

Printing, reimburseables, etc. 10,000$

Design/Estimating Contingency 111,000$

Construction Contingency 299,000$

TOTAL SOFT COSTS 1,707,800$

TOTAL PROJECT COSTS 7,687,800$

If just 1 field is built, this parking lot could be removed

Page 12: Athletic Field Feasibility Study

Pumping Station Road Property – Multi-field optionSite Master Plan Option

• Natural Grass Field• Align the entrance(s) with St. Isidore• Create the future site development

driveway• Install site utilities for sewer, water

and power• Parking (187)• Bleacher seating for 400/300• Building for concessions and toilet

rooms• Lights on 1 field at least• Sod could be an alternate in lieu of

seeding• Option for synthetic +$1million

• Assume 6 months for design and permitting and 6 months for construction and a “grow in” seasonfor sod (if selected)

Page 13: Athletic Field Feasibility Study

Pumping Station Road Property – Multi-field optionItem

Concept Budget

5/5/2021

Construction of Baseball Stadium and walkways 1,600,000$

Construction of Softball stadium 900,000$

Option for Lights on one field 500,000$

Construction of Additional Baseball Field 500,000$

Construction of Concessions & Toilet Room Outbuilding 680,000$

Other Site Improvements 2,200,000$

Allowance for Off-Site Improvements 100,000$

TOTAL CONSTRUCTION COSTS 6,480,000$

Site Surveying Costs 30,000$

Hazardous Materials Investigation -$

Geotechnical Investigation /Materials Testing 60,000$

Design fees 388,800$

Civil Engineering & Land Development Approval fees 85,000$

Construction Management fees 259,000$

Legal fees and Builders Risk- Allowance 60,000$

Building permit 100,000$

Land Development Inspection Escrow 250,000$

Water, electric, sewer utility (no gas) 105,000$

FF&E -$

Printing, reimburseables, etc. 10,000$

Design/Estimating Contingency 111,000$

Construction Contingency 324,000$

TOTAL SOFT COSTS 1,782,800$

TOTAL PROJECT COSTS 8,262,800$

Page 14: Athletic Field Feasibility Study

Next Steps

• Identify the preferred number of fields and features

• Identify the preferred site

• Refine the preferred concept

14

Athletic Field Feasibility Study