Presentation of a Construction Project. Assignment 3 Unit 21Kyle Barrass. First Stage of the Construction Building. The first step was to design a drawing of the building to give the client an idea of what he wanted. First Stage of the Construction Building. - PowerPoint PPT Presentation

Citation preview

Page 1: Assignment 3 Unit 21Kyle Barrass

Assignment 3 Unit 21 Kyle Barrass

Presentation of a Construction Project

Page 2: Assignment 3 Unit 21Kyle Barrass

First Stage of the Construction Building

• The first step was to design a drawing of the building to give the client an idea of what he wanted.

Page 3: Assignment 3 Unit 21Kyle Barrass

First Stage of the Construction Building

• The client decides on what he wants.

Page 4: Assignment 3 Unit 21Kyle Barrass

First stage of the construction Building

• Before the building was even started there was a Gant chart make to know what was going to happen, when it was going to happen and how long it should take.

Page 5: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• After the design on the building was chosen I designed a mini version of the timber frame.

Page 6: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• Before the brick walls started the timber frame flooring was put into place.

Page 7: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• After the mini model of the timber frame was done the work on the foundations had already been done so work on the brick and block walls was started.

Page 8: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• The work on the building was set back down to the bad weather, it was set back by a few weeks.

Page 9: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• As the brick walls had been held back the timber frame walls were being put together.

Page 10: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• After the timber frame walls were built the work on the window frames and door frames started.

Page 11: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• The Gant chart had to be changed as the bad weather set the building back by a few weeks, as you can see in the photo below.

Page 12: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• As you can see the brick walls had been kicked down by someone coming onto the site, so the brick and block building was set back even more.

Page 13: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• Here are the students putting the plywood on the timber floor.

Page 14: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• The timber framed walls were put up and as you can see we ran into a little problem that was easily solved.

Page 15: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• The first timber roof trust was built and the only thing that needed changing was the length of the overhang.

Page 16: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• The plywood was put onto the timber walls and the roof trusts were constructed with more overhang.

Page 17: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• The work on the brick and block building was started again and the block work was started on the timber and block building.

Page 18: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• The rest of the roof trusts were put in place and then the ply wood was put in place.

Page 19: Assignment 3 Unit 21Kyle Barrass

Designing the Building

• The work on the tiling being done and the rest of the brick and block building is being done at the same time.

Page 20: Assignment 3 Unit 21Kyle Barrass

Summary

• Timber frame construction was erected quicker than traditional building

• Adverse weather had little impact on timber frame construction

• Quality issues with some of the timber walls and roof construction – to improve inspection off-site