59
CRICOS No. 00213J Assessment of Precision Timing and Real-Time Data Networks for Digital Substation Automation David M. E. Ingram Electrical Engineering & Computer Science PhD Final Seminar

Assessment of Precision Timing and Real-Time Data Networks for Digital Substation ... · 2017. 11. 27. · CRICOS No. 00213J Assessment of Precision Timing and Real-Time Data Networks

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

CRICOS No. 00213J

Assessment of Precision Timing and Real-Time Data Networks for

Digital Substation Automation

David M. E. IngramElectrical Engineering &

Computer Science

PhD FinalSeminar

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Principal SupervisorProfessor Duncan Campbell

• Associate Supervisor (QUT)Adjunct Professor Richard Taylor

• Associate Supervisor (Industry)Mr Pascal Schaub, QGC

Supervisory Team

2

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Powerlink Queensland supported this project.

• Research took place at Powerlink’s Secondary Systems Test & Development Centre.

• Other funding provided by the Australian Government and QUT.

Project Support & Funding

3

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Summary

• Background

• Research Objectives

• Review of Past Work

• Experimental Methodology

• Research Findings

• Conclusions

• Publications

Presentation Outline

4

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Utility drivers

– Environmental & safety risk from aging plant

– Cost of conventional connections in large substations

• Technology options

– NCITs available, but not being used.

– Standards in place since early 2000s

– Product only just coming onto the market

• Research focus

– Creation of test methods for a multi-function process bus

– Provide evidence for decision makers.

Summary of the Project

5

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Research domains

• Transmission substation information

– Australian power grid

– Substation definitions

• The need for digital switchyard connections

• Communication standards

• Participants in substation design & construction

• Research objectives

INTRODUCTION

6

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Research Domains

7

Power SystemAutomation

Real-timeData

Networking

PrecisionTiming

DigitalProtection &

Control

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Transmission Substations

8

350 m

460 m

500 kVswitchyard

330 kVswitchyard

Aerial photograph from NearMap Pty Ltd (www.nearmap.com)

Control Room

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Current Transformer Failures

9

Photograph courtesy of Irvin Piraman

David Ingram
Web Watermark 20pc

Use of NCITs in Queensland

• Fibre Optic Current Transformer

– Large measuring dynamic range

– No oil or SF6

• Rogowski Coil & capacitive voltage sensor

– Integrated into switchgear

– First process bus outside of China

Photograph courtesy of Powerlink Queensland

Sensor Head

Insulator stringwith fibre optic

cable

Sensor Units

10

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• History

– EPRI Utility Communications Architecture1986-1999

– IEC and UCA combined efforts in 1997

– Result was IEC 61850, released in 2002-2004

• IEC 61850 “Communication networks and systems for power utility automation”

– Not just substations

– Wind, hydro, distributed & conventional generation

• IEEE Std 1588 “Precision Time Protocol” (PTP)

• IEEE Std C37.238 “PTP Power System Profile”

Substation Automation Standards

11

David Ingram
Web Watermark 20pc

Process Bus Networks

12

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

The Merging Unit

13

Vizimax AMU

Schniewindt SAMU

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

1 Fibre ≈ 10× 8-core (CT) & 20× 4-core (VT) cables

Secondary Connections

14

Ø 4 mm18 g/m

Ø 23 mm, 1000 g/m

Ø 19 mm600 g/m

8 core 6 mm² • 3× 8 core CT cables• 2× 4 core VT cables• 3× 2 core CB cables• $50/m, 6 kg/m

• 1× 2 core FO cable• $1/m, 18 g/m• Ethernet Switch $4000

4 core 6 mm²

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Who Builds an Automation System?

15

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Create test procedures to be used by system integrators, end users & researchers:

– Time synchronising systems

– Real-time Ethernet data networks

– Fully-digital process bus protection systems

• Examine in detail the behaviour & operation of process bus networks

– Behaviour of sub-systems

– Interaction of components

– Provide quantitative evidence of performance

Research Objectives

16

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

1. Do the protocols used to implement a shared process-level network interact with each other, and can the performance requirements specified by grid codes and international standards be met?

2. How do the devices used in a network-based timing system contribute to error, and how do these devices affect protection performance?

3. Can the components of an advanced digital substation automation system be tested in isolation to predict performance in the completed system?

Research Questions

17

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Protection performance standards

• Process bus substations

• Sampled value protection

• Real-time power system simulation

• Precision timing for industrial applications

• Real-time Ethernet networks

REVIEW OF PAST WORK

18

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• National Electricity Rules

• IEC 61850-5 “P2” transmission substations

Performance Standards

19

Voltage Fault Clearance Time

CB Operating Time

≥ 400 kV 80 ms 40 ms

250 – 400 kV 100 ms 40-60 ms

100 – 250 kV 120 ms 60 ms

Class Application

T4 Time Sync Sampled value time sync accuracy ±4 µs

Type 1A Message “Fast Trip” network latency: 600 µs

Type 4 Message “Raw data” network latency: 600 µs

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Event Based Simulation

– Tools include OPNET and OMNeT++.

– Require detailed Ethernet switch models.

– Results are not valid if protocol assumptions are wrong.

– Kanabar et al. (2009), Thomas & Ali (2010)

• COMTRADE replay of EMTP simulations

– Kanabar et al. (2011)

• Protection secondary injection test sets

– Crossley et al. (2011)

– Sun et al. (2012)

Sampled Value Protection

20

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Real Time Digital Simulator (RTDS) for “hardware in the loop” testing.

• Established as a mean of testing protection (McLaren et al., 1992).

• “GTNET” IEC 61850 specific interface (Desjardine et al., 2007)

– Publish sampled values

– Publish and subscribe to GOOSE messages

• No power amplifiers required for process bus protection testing.

Real Time Power System Simulation

21

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Message passing time transfer.

• Ethernet based

• Significantly improved & revised in 2008

– IEEE Standard 1588-2008, PTPv2

– Introduced the “transparent clock”

– Introduced “profiles” that restrict settings

• Used in factory automation and telecoms

• Error models developed:

– Giorgi & Narduzzi (2007) and Scheiterer et al. (2009).

– Loschmidt et al. (2012) recently updated models.

Precision Time Protocol (PTP)

22

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Recommended by IEC and NIST smart grid roadmaps.

• NIST (US) have a PTP test bed for synchrophasors (Amelot et al., 2010).

• Most interest is synchronising of Phasor Monitoring Units (PMUs)– Ferrari et al. (2008), Lixia et al. (2009)

• Sync for sampled values discussed, but no experimental work– Brunner & Antonova (2011), Skendzic &

Steinhauser (2012).

Use of PTP for Substation Applications

23

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Collisions eliminated with recent changes.

– Ethernet switches instead of hubs + full duplex

• IEEE Std 802.1Q introduced Virtual LANs and prioritisation to Ethernet.

– Affects the way that switches handle frames

• Real-time performance improved with multiple classes of traffic (Jasperneite et al. 2007).

• Classes of traffic (Decotignie, 2005):– Real-time periodic (e.g. sampled values & PTP)

– Real-time sporadic (e.g. GOOSE)

– Best effort (e.g. MMS & SNMP)

Ethernet Prioritisation & Performance

24

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Software and hardware options for tools– Software is lower cost

– Hardware has higher performance

• Tools

– Capture: software capture may drop frames

• (Schafer & Felser, 2007).

– Traffic Generation: need to validate software based systems (Botta et al., 2010).

• tcpreplay (software),

• Calibre, Endace DAG, Napatech NT4 (hardware)

– Network Impairment Emulation

• Anue GEM, Simena, Ixia N2X (Layer 2, hardware)

Network Testing

25

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Experimental, using “live equipment”.

– Most products are commercially available.

– First published experimental evaluation of sampled values and PTP.

– Capable of loading process and station bus networks to 100%.

• Real-time simulation.

– “Hardware in the loop”

– Only the power system is simulated

– Very flexible testing approach• No risk to power system security

PROCESS BUS TEST BED

26

David Ingram
Web Watermark 20pc

Test BedPhotos (1)

27

PTPSlaveclock

GTNET-SVmerging units

GTNET-GSEGOOSE publisher/subscriber

PTP slave andTransparent clocks

RTDS power systemsimulator

David Ingram
Web Watermark 20pc

28

Test BedPhotos (2)

PTP master &transparent clock

Process Busswitches

PTP masterclocks

Protectionrelays

Station Busswitch

Ethernet tap

Digitaloscilloscope

Networkemulator

Server withEthernet

capture card

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Performance of the Precision Time Protocol

• Characterisation of real-time network traffic

• “Closed loop” protection performance

RESEARCH METHOD

29

David Ingram
Web Watermark 20pc

Assessing Synchronising Performance

30

Sync performance of PTP devices

Effect of sampled value traffic on PTP performance

(3 devices)

(4 devices)

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

PTP Grandmaster & Slave Clock Selection

31

XO XO TCXO

Slave ClocksOCXO

XO

OC

XO

TC

XO

Gra

nd

maste

r C

locks

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Protocol Interaction – SV & PTP

32

60 80 100 120 140 160 180

0.0

00.0

10.0

20.0

30.0

40.0

5

Effect of Sampled Value Traffic on PTP Performance

Offset (ns)

Den

sit

y

SV Traffic

none1x MU3x MU6x MU12x MU 21x MU

40 60 80 100 120 140

0.0

00.0

20.0

4

Effect of Prioritisation – 12x SV MU

Offset (ns)

Den

sit

y

PTP Priority

247

40 60 80 100 120 1400.0

00.0

20.0

40.0

6

Effect of Prioritisation – 21x SV MU

Offset (ns)

Den

sit

y

PTP Priority

247

PTP Priority = 4, Sampled Value Priority =4

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Assessing Transparent Clock Corrections

33

Background trafficto stress switch

Makes reference clock onDAG7.5G4 extremely accurate

(syntonisation)

Normal PTP messagessent by grandmaster

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Transparent Clock Corrections

34

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Effect of GPS Outages on PTP

Without Redundancy With Redundancy

35

0 20 40 60 80

-0.5

0.0

0.5

1.0

1.5

PTPA Correction

Off

set

(µs)

PTPA GPS Drift

0 20 40 60 80

-1.5

-1.0

-0.5

0.0

0.5

Time (s)

Off

set

(µs)

PTPB SlavePTPF Slave

0 20 40 60 80

-1.5

-1.0

-0.5

0.0

0.5

PTPC Correction

Off

set

(µs)

PTPC GPS Drift

0 20 40 60 80

-0.5

0.0

0.5

1.0

1.5

Time (s)

Off

set

(µs)

PTPB SlavePTPF Slave

-1000

-500

0500

GPS Antenna Failure on Grandmaster PTPA

Off

set

(ns)

17:46:00 17:48:00 17:50:00 17:52:00 17:54:00 17:56:00

Dis

connect

Reconnect

Slave c.f. PTPC

PTPBPTPF

PTPA c.f. PTPC

PTPA

Time

G'm

aste

r

17:46:00 17:48:00 17:50:00 17:52:00 17:54:00 17:56:00C

A

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• “Coherent transmission” by merging units

• Queuing effects in switches

• Interaction between SV, GOOSE and PTP

Characterisation of Network Traffic

36

David Ingram
Web Watermark 20pc

Measuring Latency & Publishing Times

37

Measuring latency introduced by an Ethernet switch

Measuring publishing time of a merging unit

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Coherent TransmissionRTDS Substation Merging Unit

38

80 100 120 140 160 180 200

0.0

00

0.0

10

0.0

20

Delay Distribution – Direct Connect

Delay (µs)

Den

sit

y

99.97%

Logarithmicy-axis

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Queuing Effects – Bunched/Spaced

39

0 20 40 60 80 100 120

0.0

0.2

0.4

0.6

0.8

1.0

Bunched Data — One Switch

Latency (µs)

Cu

mu

lati

ve P

rob

ab

ilit

y

MU 1MU 2MU 3MU 4MU 5MU 6

0 20 40 60 80 100 120

0.0

0.2

0.4

0.6

0.8

1.0

Bunched Data — Five Switches

Latency (µs)

Cu

mu

lati

ve P

rob

ab

ilit

y MU 1MU 2MU 3MU 4MU 5MU 6

0 20 40 60 80 100 120

0.0

0.2

0.4

0.6

0.8

1.0

Spaced Data — One Switch

Latency (µs)

Cu

mu

lati

ve P

rob

ab

ilit

y

MU 1MU 2MU 3MU 4MU 5MU 6

0 20 40 60 80 100 120

0.0

0.2

0.4

0.6

0.8

1.0

Spaced Data — Five Switches

Latency (µs)

Cu

mu

lati

ve P

rob

ab

ilit

y

MU 1

MU 2MU 3MU 4MU 5MU 6

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Protocol Interaction – SV & GOOSE

40

P0 G

OO

SE

, 0S

V

P4 G

OO

SE

, 0S

V

P7 G

OO

SE

, 0S

V

P0 G

OO

SE

, 12S

V

P4 G

OO

SE

, 12S

V

P7 G

OO

SE

, 12S

V

P0 G

OO

SE

, 20S

V

P4 G

OO

SE

, 20S

V

P7 G

OO

SE

, 20S

V

36

38

40

Outgoing GOOSE Latency with SV Traffic

GO

OS

E L

ate

ncy (

µs)

P0 G

OO

SE

, 0S

V

P4 G

OO

SE

, 0S

V

P7 G

OO

SE

, 0S

V

P0 G

OO

SE

, 12S

V

P4 G

OO

SE

, 12S

V

P7 G

OO

SE

, 12S

V

P0 G

OO

SE

, 20S

V

P4 G

OO

SE

, 20S

V

P7 G

OO

SE

, 20S

V

50

150

250

Incoming GOOSE Latency with SV Traffic

GO

OS

E L

ate

ncy

(µs)

No G

OO

SE

MU

1

No G

OO

SE

MU

20

Pri 0

GO

OS

EM

U 1

Pri 4

GO

OS

EM

U 1

Pri 7

GO

OS

EM

U 1

Pri 0

GO

OS

EM

U 2

0

Pri 4

GO

OS

EM

U 2

0

Pri 7

GO

OS

EM

U 2

0

50

150

Effect of Outbound GOOSE on Sampled Values

SV

La

tency (

µs)

No G

OO

SE

MU

1

No G

OO

SE

MU

20

Pri 0

GO

OS

EM

U 1

Pri 4

GO

OS

EM

U 1

Pri 7

GO

OS

EM

U 1

Pri 0

GO

OS

EM

U 2

0

Pri 4

GO

OS

EM

U 2

0

Pri 7

GO

OS

EM

U 2

0

50

150

250

Effect of Inbound GOOSE on Sampled Values

SV

La

tency (

µs)

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Comparison of SV+GOOSE to CT+relays

• Effect of artificial network traffic

• Effect of controlled sync errors

• Network latency effects

Protection System Performance

41

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Protection Test Schematic

42

RET670TransformerProtection

Load~GTNET-SV

Merging UnitGTNET-SV

Merging Unit

MACH1040Ethernet Switch

HV SV(9-2LE)

HV SV(9-2LE)

HV SV + LV SV(9-2LE)

GTNET-GSESmart CB +Tap Changer

PDIF.ST.Op(GOOSE)

Tap Position(GOOSE)

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Comparison of Relay Connections

43

RT

DS

GO

OS

E

OM

ICR

ON

SV

/GO

OS

E

OM

ICR

ON

CT

/GO

OS

E

RT

DS

Rela

y

OM

ICR

ON

SV

/Rela

y

OM

ICR

ON

CT

/Rela

y

10

12

14

16

18

20

Three-phase HV Faults

Re

sp

on

se

Tim

e (

ms)

RTDSOMICRON SVOMICRON CTGOOSERelay

RT

DS

GO

OS

E

OM

ICR

ON

SV

/GO

OS

E

OM

ICR

ON

CT

/GO

OS

E

RT

DS

Rela

y

OM

ICR

ON

SV

/Rela

y

OM

ICR

ON

CT

/Rela

y

22

24

26

28

30

32

34

36

Line-ground LV Faults

Re

sp

on

se

Tim

e (

ms)

RTDSOMICRON SVOMICRON CTGOOSERelay

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Effect of Traffic – Sampled Values

44

0 3 6 12 18

10

12

14

16

18

20

Different Multicast Destination

SV Load (Background Merging Units)

Re

sp

on

se

Tim

e (

ms)

0 3 6 12 16 17 1810

12

14

16

18

20

Same Multicast Destination

SV Load (Background Merging Units)

Re

sp

on

se

Tim

e (

ms)

900 ms

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Change in Restraint Characteristic

45

0 1 2 3 4 5

0.0

0.5

1.0

1.5

2.0

2.5

3.0

No Fixed Delay

Ibias (p.u.)

Idiff

(p.u

.)

No TripTripRestraint Curve

0 1 2 3 4 5

0.0

0.5

1.0

1.5

2.0

2.5

3.0

100 µs Fixed Delay

Ibias (p.u.)

Idiff

(p.u

.)

No TripTripRestraint Curve

0 1 2 3 4 5

0.0

0.5

1.0

1.5

2.0

2.5

3.0

500 µs Fixed Delay

Ibias (p.u.)

Idiff

(p.u

.)

No TripTripRestraint Curve

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

Effect of Network Latency on Protection

46

0 2 5 8 10

10

15

20

25

Fixed Latency on SV

Latency (ms)

Re

sp

on

se

Tim

e (

ms)

0 5 10 15 201

01

52

02

53

03

54

0

Fixed Latency on GOOSE

Latency (ms)

Re

sp

on

se

Tim

e (

ms)

+1.4 ms

+4.4 ms

+7.4 ms

+9.4 ms

+5.0 ms

+10.3 ms

+15.0 ms

+19.4 ms

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Performance of the Precision Time Protocol

– Clock quality impacts performance

– Slave clock servo response introduces sync errors

• Characterisation of real-time network traffic

– PTP tolerant of traffic produced by merging units

– Protocols do not interact

• “Closed loop” protection performance

– Test system shown to be accurate

– Effect of network traffic on protection response

– Restraint characteristic tolerant of large sync errors

RESEARCH FINDINGS

47

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Risks posed by CTs & cost of substation cabling are challenges for utilities.

– NCITs and network process buses solve both

• Real-time networks and networked timing established in other industries.

– Power industry can learn from this.

– Other industries will learn from power industry too.

• Experimental approach used to assess performance.

– Avoids simulation and modelling uncertainty

CONCLUSIONS

48

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• PTP slave servo response undefined

• PTP grandmaster self-reporting is accurate and effective. Faster than previously reported.

• Quality of GM & slave directly affects sync performance

• Use of transparent clocks means SV/PTP interaction a non-issue

– Prioritisation not required

Key Findings – Precision Timing

49

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• ‘Coherent’ SV transmission can occur

• Most latency created at first switch

– Subsequent switches only have transmission delay

– Enables use of field switches to reduce cabling required.

• SV/GOOSE interaction

– Non-issue for outbound GOOSE

– Inbound GOOSE delays capped ~ 250 µs

• Multicast traffic management required

– Filter at switch or in protection relay

Key Findings – Real-time Networks

50

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Multiple test methods that use common hardware (precision Ethernet capture card)

– PTP transparent clock Correction accuracy test

– Direct measurement of MU publishing time

– Measurement of SV & GOOSE latency

• Process bus test bed design that incorporates SV, GOOSE and PTP

• Vendor independent test procedures

– Demonstrated that component tests predict performance at the system level

Major Contributions

51

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Long term performance

– Aging of precision time clocks

– Environmental effects on time clocks

• Assess wider range of protection devices

– Distance protection, feeder diff, over-current

– Increase number of manufacturers in test bed

• Use of sampled values for metering

– Needed for customer & generator connections

Future Work

52

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Multifunction process buses are surprisingly resilient. Precision Time Protocol is robust & compensates for network traffic.

• A model SAS was built to develop test procedures & to assess performance

• Success in this test bed does not guarantee all process buses will meet expectations

– Testing/validation is required

• Process bus meets utility needs, and performance exceeds that of conventional SAS.

Closing Thoughts

53

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• IEC 61850

– Presented at IEC TC57 WG10 meeting in Noosa and provided material for other meetings.

• IEEE Std C37.238 – Power Profile

– Corresponding member of IEEE PSRC Working Group H7/Sub C7

– Co-authored three conference papers

• IEEE Std 1588

– Study group member for PTPv3

Standards Participation

54

David Ingram
Web Watermark 20pc

Journal Publications

55

• Published / Early Access– D.M.E. Ingram, D.A. Campbell & P. Schaub (2012): “Use of Precision Time

Protocol to Synchronize Sampled-Value Process Buses”. IEEE Transactions on Instrumentation & Measurement, 61(5) pp. 1173-1180.

– D. M. E. Ingram, F. Steinhauser, C. Marinescu, R. R. Taylor, P. Schaub & D. A. Campbell (2012): “Direct Evaluation of IEC 61850-9-2 Process Bus Network Performance”. IEEE Transactions on Smart Grid, 3(4) pp. 1853–1854.

– D.M.E. Ingram, P. Schaub, D.A. Campbell & R.R. Taylor (2012): “Performance Analysis of IEC 61850 Sampled Value Process Bus Networks”. IEEE Transactions on Industrial Informatics. Early access.

– D.M.E. Ingram, P. Schaub, R.R. Taylor & D.A. Campbell (2012): “Network Interactions and Performance of a Multi-Function IEC 61850 Process Bus”. IEEE Transactions Industrial Electronics. Early access.

• Accepted, In-press– D.M.E. Ingram, P. Schaub, D.A. Campbell & R.R. Taylor (2012): “Performance

Analysis of PTP Components for IEC 61850 Process Bus Applications”. IEEE Transactions on Instrumentation & Measurement.

– D.M.E. Ingram, P. Schaub, D.A. Campbell & R.R. Taylor (2013): “Quantitative Assessment of Fault Tolerant Precision Timing for Electricity Substations”. IEEE Transactions on Instrumentation & Measurement.

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• D.M.E. Ingram, P. Schaub & D.A. Campbell, “Use of IEEE 1588-2008 for a sampled value process bus in transmission substations”, 2011 IEEE Instrumentation and Measurement Technology Conference (I2MTC), Hangzhou, China, May 2011

• D. M. E. Ingram, D. A. Campbell, P. Schaub & G. Ledwich (2011), “Test and evaluation system for multi-protocol sampled value protection schemes”, 2011 IEEE Trondheim PowerTech, Trondheim, Norway, June 2011.

• D. M. E. Ingram, P. Schaub & D. A. Campbell (2011). “Multicast traffic filtering for sampled value process bus networks”, 37th Annual Conference of the IEEE Industrial Electronics Society, Melbourne, Australia, November 2011

• D. M. E. Ingram, P. Schaub, D. A. Campbell & R. R. Taylor, “Evaluation of precision time synchronisation methods for substation applications”, 2012 International IEEE Symposium on Precision Clock Synchronization for Measurement, Control and Communication (ISPCS), San Francisco, USA, September 2012

Conference Presentations

56

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• Powerlink process bus publications– P. Schaub, A. Kenwrick and D. Ingram (2012): “Powerlink leads with Process

Bus”. Transmission & Distribution World, Vol. 64, No. 5, pp. 25–32.

– P. Schaub, J. Haywood, D. M. E. Ingram, A. Kenwrick & G. Dusha (2011): “Test and evaluation of Non Conventional Instrument Transformers and sampled value process bus on Powerlink’s transmission network”. CIGRÉ South East Asia Protection and Automation Conference 2011 (SEAPAC), Sydney, Australia, March 2011.

• PSRC Working Group H7/Sub C7 Publications– IEEE PES PSRC Working Group H7/Sub C7 Members and Guests (2012).

“Standard profile for use of IEEE Std 1588-2008 Precision Time Protocol (PTP) in power system applications”. 2012 International IEEE Symposium on Precision Clock Synchronization for Measurement, Control and Communication (ISPCS), San Francisco, USA, September 2012.

– IEEE PSRC Working Group H7/Sub C7 Members and Guests (2012). “Standard profile for use of IEEE Std 1588-2008 Precision Time Protocol (PTP) in power system applications”. Western Protective Relaying Conference (WPRC), Spokane, WA, USA, October 2012.

Additional Publications

57

David Ingram
Web Watermark 20pc

CRICOS No. 00213JPhD Final Seminar

• The following people at Powerlink provided me assistance during this research:– Shane Williams, Alwyn Janke & Terry Easlea

– Bruce Capstaff, Katie Hadley & Lyndall Josey

– Geoff Dusha & Anthony Kenwrick

• Equipment was donated or lent by following companies, for use in the test bed:

Acknowledgements

58

David Ingram
Web Watermark 20pc