43
ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT BETWEEN NIB AND UON Year II Project Highlights By Gichuki F., Wanjogu R. K., and Okinyi., M. D. Date: 3 rd July 2014 Mwea, Ahero and Bura Irrigation Schemes case studies 1

ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

Embed Size (px)

Citation preview

Page 1: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE

SYSTEMS:CASE STUDIES OF AHERO, BURA AND

MWEA IRRIGATION SCHEMES

A COLLABORATIVE RESEARCH PROJECT BETWEEN NIB AND UON

Year II Project Highlights

By

Gichuki F., Wanjogu R. K., and Okinyi., M. D.

Date: 3rd July 2014

Mwea, Ahero and Bura Irrigation Schemes case studies

1

Page 2: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

PRESENTATION OUTLINE

Development and research objectives Project elements and its organization Year I highlight Year II Results and their implications Project outputs

Page 3: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

3

INTRODUCTION Irrigation in Kenya faces serious challenges which

have negatively affected the productivity, profitability and sustainability of most irrigation schemes. The following is a partial listing of the main challenges High pumping costs; High levels of siltation; unpredictable flooding & drought High conveyance and application losses; High mismatch between water demand and supply; Inadequate drainage of excess water and removal of

excess salts; and Inequity in water delivery in different irrigation blocks and

irrigated fields. Inadequate irrigation skills among farmers and other

stakeholdersSource: NIB Strategic Plan 2008-2012

MIS, AIS & BIS water loss study-NIB & UON

Page 4: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

4

RATIONALE FOR CONVEYANCE SYSTEM RESEARCH:

Low efficiency (30-70%) of conveyance and distribution system with major implications on:Scheme water intake sub-systemOperation and maintenance of

conveyance sub-systemOn-farm sub-system

Page 5: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

5

RATIONALE FOR CONVEYANCE SYSTEM RESEARCH:IMPLICATION ON WATER INTAKE SUBSYSTEM

Irrigation scheme withdraws 30-70% more water than it needs – This increase potential for water use conflicts in dry seasons;

Large intake infrastructure are required resulting in high development costs

High pumping (O&M) costs

Page 6: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

6

RATIONALE FOR CONVEYANCE SYSTEM RESEARCH:IMPLICATION ON CONVEYANCE SUBSYSTEM

30-70% more silt brought into the scheme;

Large conveyance infrastructure are required resulting in high development costs

High conveyance (O&M) costs

Page 7: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

7

RATIONALE FOR CONVEYANCE SYSTEM RESEARCH:IMPLICATION ON ON-FARM SUBSYSTEM

30-70% more silt brought into the fields; May enhance soil fertility Will over time raise field levels making it less commandable

30-70% more salts brought into the field will enhance the rate of salt build up

May enhance drainage problemsHigh on-farm (O&M) costs

Page 8: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

8

HYPOTHESIS

The main hypothesis of this research is that the performance of water delivery and application sub-systems can significantly be improved-hence irrigated agriculture- by reducing irrigation water loss.

AIS & BIS water loss study-NIB & UON

Page 9: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

9

AIS

& B

IS w

ate

r loss stu

dy-N

IB &

UO

NKEY ISSUES THAT WILL ADDRESSED

1. Assess performance and opportunities and constraints for improving performance;

2. Identify innovative solutions that will enhance the performance of the water delivery and water application sub-systems;

3. Evaluate technical performance of the innovative solutions;

4. Evaluate costs and benefits of performance improvements;

5. Formulate strategies and plans for performance improvements;

6. Identify investment priorities; and 7. Propose financing/ options.

Page 10: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

10

MAIN DELIVERABLES (OUTPUTS)

Reports on the status and performance of irrigation subsystems for the past 5 years- from abstraction point thru conveyance to the farm

Report on cause, effect and magnitude of conveyance and distribution losses in MIS, AIS and BIS

Options for reducing irrigation water losses and improving delivery performance including lining options

Information on improving delivery performance will be available to irrigation engineers, managers, farmers and policy makers

AIS & BIS water loss study-NIB & UON

Page 11: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

11

ANTICIPATED OUTCOMES AND IMPACTS Enhanced adoption of water saving technologies; Increased irrigated areas, cropping intensities and crop yields; Increased yield, production and net benefits; Increases in farmer contribution to O&M expenses; Irrigation water savings; More efficient and productive use of water. More equitable water allocation among sectors and users; More reliable yields and production. Reduced environmental degradation; Reduced impacts of extreme events, particularly flood and

destruction of irrigation infrastructure; Reduced mismatch between water demand and supply; Reduced water use conflicts associated with more equitable

water distribution; Yield, production and profit increases; and Reduced variability in irrigated agricultural production

AIS & BIS water loss study-NIB & UON

Page 12: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

12

OBJECTIVESOverall goal: To generate and enhance utilization of data,

information and knowledge on irrigation water management in ways that promote innovation and effective and efficient utilization of the resources.

AIS & BIS water loss study-NIB & UON

Page 13: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

PROJECT OBJECTIVES AND MAIN TASKS

1. Objective 1: Rapid assessment

1.1 Task 1: Mapping

1.2 Task 2: Characterization

1.3 Task 3: SWOT analysis

2. Objective 2: Assess water demand and supply

2.1 Task 1: Water requirements

2.2 Task 2: Water supply

2.3 Task 3: Equity and reliability

Page 14: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

PROJECT OBJECTIVES AND MAIN TASKS

3. Objective 3: Assess water losses3.1 Task 1: Seepage loss3.2 Task 2: Evaporation loss3.3 Task 3: Operational losses4. Objective 4: Assess loss reduction options4.1 Task 1: Earth liners4.2 Task 2: Hard surface liners4.3 Task 3: Flexible membrane liners5. Objective 5: Assess O&M costs5.1 Task 1: Pumping cost5.2 Task 2: De-silting cost5.3 Task 3: Operating cost

Page 15: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

PROJECT OBJECTIVES AND MAIN TASKS

6. Objective 6: Assess water productivity6.1 Task 1: Yield and production6.2 Task 2: Gross product value6.3 Task 3: Water productivity7. Objective 7: Assess costs and benefits7.1 Task 1: C/B ratio for earth liners7.2 Task 2: C/B ratio for hard surface liners7.3 Task 3: C/B ratio for flexible membrane liners8. Objective 8: Synthesis, Dissemination and Mobilization for action8.1 Task 1: Synthesis8.2 Task 2: Dissemination8.3 Task 3: Mobilization for action

Page 16: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

16

YEAR 1 HIGHLIGHTS : AHERO SYSTEM

AIS & BIS water loss study-NIB & UON

Page 17: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

17

YEAR 1 HIGHLIGHTS : AHERO SYSTEM

AIS & BIS water loss study-NIB & UON

UCA Length(km) Area(ha) Canal density m/ha

U1 6.76 136.48 49.56

U2 5.25 110.18 47.64

U3 6.73 134.16 50.16

U4 4.63 105.07 44.10

U5 5.14 126.65 40.58

U6 3.30 59.94 55.01

U7 5.69 107.73 52.80

U8 5.23 120.94 43.24

U9 3.65 70.10 52.04

U10 3.16 61.18 51.60

U11 2.49 44.41 56.03

GrandTotal 64.48 1,076.85 59.88

Page 18: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

18

YEAR 1 HIGHLIGHTS : BURA SYSTEM

AIS & BIS water loss study-NIB & UON

Page 19: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

19

YEAR 1 HIGHLIGHTS : BURA SYSTEM

AIS & BIS water loss study-NIB & UON

UCA Length (km)

Area (ha) Canal density

m/ha

MainCanal 69.01 2,641.55 26.12

U1 27.54 196.32 140.27

U2 29.04 550.74 52.72

U3 33.19 433.09 76.63

U4 53.80 1,044.01 51.53

U5 16.74 361.64 46.29

U6 6.40 55.73 114.83

Total 166.71 2,641.55 63.11

Page 20: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

20

YEAR 1 HIGHLIGHTS : MWEA SYSTEM

AIS & BIS water loss study-NIB & UON

Page 21: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

21

YEAR 1 HIGHLIGHTS : MWEA SYSTEM

AIS & BIS water loss study-NIB & UON

UCA Length(km) Area(ha) Canallengthm/haMIAD 7.77 90.00 86.34M10 3.51 33.00 106.27M9 5.92 51.00 116.04M11 2.98 48.00 61.99M17 8.92 139.00 64.14M12 5.06 77.00 65.66M13 4.19 68.00 61.58M14 8.11 106.00 76.48M15 4.84 47.00 103.03M16 10.88 132.00 82.43H18 8.99 115.00 78.19H20 6.96 115.00 60.49H19 8.17 111.00 73.65M5 6.64 75.00 88.57M6 7.16 64.00 111.88M7 3.29 49.00 67.24M8 2.20 25.00 87.98M1 9.05 80.00 113.16M2 3.24 41.00 79.01M3 4.67 53.00 88.17M4 10.47 132.00 79.28H1 4.44 73.00 60.77H6 13.13 111.00 118.28H7 7.79 83.00 93.86H8 7.97 96.00 83.06H2 7.30 92.00 79.32H3 8.20 108.00 75.96H4 6.02 90.00 66.92H5 17.23 156.00 110.47W7 6.64 60.00 110.69W1 12.40 130.00 95.39W2 14.44 195.00 74.05W3 11.37 173.00 65.71W7 6.52 61.00 106.94W4 14.40 132.00 109.06W5 10.94 163.00 67.09W6 22.04 206.00 106.97K1 21.24 208.00 102.10K2 13.86 165.00 84.01K3 15.70 132.00 118.96K4 12.63 145.00 87.08K5 16.54 148.00 111.73K6 10.97 111.00 98.87K7 9.05 131.00 69.08K8 3.32 30.00 110.70

Page 22: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

22

AIS

& B

IS w

ate

r loss stu

dy-N

IB &

UO

N

SOIL PERMEABILITY TEST RESULTS

Page 23: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

23

YEAR II METHODOLOGY: LOSS ASSESSMENT

AIS & BIS water loss study-NIB & UON

Canal loss mainly comprise of seepage, evapotranspiration (EVT) & leakages

The water balance (inflow/outflow) method used for quantifying canal loss-this will not interrupt irrigation program

Seepage rates measured using inflow/outflow, ponding and seepage meter methods

Calibration and possibly repair of all measuring/regulating canal structures to facilitate flow measurements-critical in this study

Page 24: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

24

METHODOLOGY: LOSS ASSESSMENT

AIS & BIS water loss study-NIB & UON

Page 25: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

25

METHODOLOGY: LOSS ASSESSMENT

AIS & BIS water loss study-NIB & UON

Ponding methodTo eliminate the effect of wind, the rate of drop was measured at each end of the pool and averaged. Staff or hook gauges attached to existing structures or stakes driven into the canal bed were used as shown in the figure below.

Page 26: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

26

PRELIMINARY RESULTS: LOSS ASSESSMENT

AIS & BIS water loss study-NIB & UON

Distance from point [m]

Depth [m]

Width [m]

Area [m^2]

Velocity 1 [cm/s]

Velocity 2

[cm/s]

Velocity 3

[cm/s]

Average

Velocity at Point [cm/s

]Discharge [m^3/s]

2.3 0 0 0 0 0 0.00 0.0002.1 0.25 0.2 0.05 23.5 24.1 20.2 22.60 0.0111.8 0.42 0.3 0.126 51.9 50.4 49.5 50.60 0.0641.5 0.47 0.3 0.141 44.2 40.3 39.5 41.33 0.0581.2 0.43 0.3 0.129 27.7 28 28.5 28.07 0.0360.9 0.35 0.3 0.105 22.1 22.1 21.6 21.93 0.0230.6 0.2 0.3 0.06 4.1 3.9 2 3.33 0.0020.4 0 0.2 0 0 0 0 0.00 0.000

Total Discharge [m^3/s] 0.195

Page 27: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

27

PRELIMINARY RESULTS: LOSS ASSESSMENT

AIS & BIS water loss study-NIB & UON

Site Offtake

Gross loss m/day Efficiency

% loss to closed offtakes

Gross loss due to INFILTRATION and EVAPO. mm/day

% % Site 1 Site 2 0.094 0.98 0.70 28.05Site 3 0.358 0.89 0.80 71.53 Site 4 Site 5 0.470 0.88 0.85 70.48 Site 6

Site 7 0.707 0.51 0.90 70.73Site 8 Site 9 0.177 0.85 0.50 88.33

Page 28: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

--------------------------------------------------------------------------------------------------------------------

Character of material Seepage loss in Cumecs per Million sq. m of wetted perimeter_____________________________________________________________________

Impervious clay Loam 0.90 to 1.20Medium clay loam under laid with hard pan at depth 1.20 to 1.80of not over 0.60 to 0.90m below level Ordinary clay loam silt soil 1.80 to 2.70Gravelly or sandy clay loam, cemented gravel, 2.70 to 3.70Sand and claySandy loam 3.60 to 5.20Loose sandy soils 5.20 to 6.10Gravelly to sandy soils 7.00 to 8.80Porous gravelly soil 8.80 to 10.70Very gravelly soils 10.70 to 21.30

___________________________________________________________________

PRELIMINARY RESULTS: SEEPAGE LOSSES IN UNLINED CANALS

Page 29: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

29

METHODOLOGY: WATER BALANCE MODELING Thiba system linkages

AIS & BIS water loss study-NIB & UON

Page 30: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

30

METHODOLOGY: WATER BALANCE MODELING Elements of the water balance model

AIS & BIS water loss study-NIB & UON

Page 31: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

31

PRELIMINARY RESULTS: WATER BALANCE MODEL

AIS & BIS water loss study-NIB & UON

Unit IWR m3/day SL m3/day EL m3/day

Main Canals - 179.56 359.11

U1 11,792.28 32.47 64.94

U2 9,519.29 24.94 49.89

U3 11,591.65 33.99 67.99

U4 9,078.19 22.41 44.82

U5 10,942.63 25.11 50.23

U6 5,178.76 18.20 36.39

U7 9,308.14 27.12 54.24

U8 10,449.02 24.95 49.89

U9 6,056.82 16.48 32.97

U10 5,285.65 14.72 29.44

U11 3,837.36 12.04 24.08

Grand Total 93,040 432

864

Page 32: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

32

PRELIMINARY RESULTS: WATER BALANCE MODEL

AIS & BIS water loss study-NIB & UON

Page 33: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

33

PRELIMINARY RESULTS: WATER BALANCE MODEL

AIS & BIS water loss study-NIB & UON

Page 34: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

34

ON-GOING SIMULATION STUDIES

Design, operation and maintenance issues for example what is the effect of changes on cropping calendar and system layout

AIS & BIS water loss study-NIB & UON

Page 35: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

35

AIS

& B

IS w

ate

r loss stu

dy-N

IB &

UO

NPRELIMINARY SIMULATION RESULTS - MWEA

Page 36: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

36

AIS

& B

IS w

ate

r loss stu

dy-N

IB &

UO

NECONOMICS OF CANAL LINING

Page 37: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

ECONOMICS OF CANAL LINING: CALCULATION

Annual benefits: (a) Saved seepage water by lining: Let, the rate of water is sold to the cultivators = c/cumec If m cumecs of water is saved by lining the canal annually, then

the money saved by lining = c. m/yr

Saving in maintenance cost: Let, the average cost of annual upkeep of unlined channel = Cuc

If p is the percentage fraction of the saving achieved in maintenance cost by lining the canal, then the amount saved = pCuc

The total annual benefits = c. m/yr + pCuc

Page 38: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

Annual Costs: Let, the capital expenditure required on lining is LC and

the lining has a life of N years.Annual depreciation charges = LC/N.

Interest of the capital LC = LC(r/100) [r= percent of the rate of annual interest]

Average annual interest = LC/2(r/100) [v Since the capital value of the asset decreases from LC to zero in N years]

The total annual costs of lining = LC/N + LC/2(r/100)

ECONOMICS OF CANAL LINING: CALCULATION

Page 39: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

Benefit/Cost ratio example:

Annual Benefits

(a) Seepage loss Seepage loss in unlined canal @ 3.3 cumec per million sq. m = (3.3/106)* 18,800

cumec/km = 62,040* 10-6 cumec/kmFor seepage loss in lined channel at 0.01 cumesc per million square meter of wetted perimeterSeepage loss in unlined canal = (0.01/106)x18,800= 188*10-6cumecs/kmNet saving = (62,040* 10-6 - 188* 10-6) cumec/km = 0.06185 cumec/kmAnnual revenue of water = 35 ksh

Annual revenue saved per km of channel = (0.06185*35) = 216,480.

(b) Saving in maintenance Annual maintenance cost of unlined channel for 10 square meter = 10 Total wetted perimeter per 1 km length = 18,800 m" Annual maintenance charge for unlined channel per km = 18,800 Assume that 40% of this is saved in lined channel Annual saving in maintenance charges = (0.4* 18,800) = 7,520 Total annual benefits per km = (216,480 + 7,520) = 224,000

ECONOMICS OF CANAL LINING: CALCULATION

Page 40: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

Benefit/Cost ratio example:

Annual Costs Area of lining per km of channel= 18.5*1000= 18500 m2 Cost of lining per km of channel @ 1800 per 10 m2=

(18500*1800/10) = 3,330,000.Assume, life of lining as 40 years

Depreciation cost per year = (3,330,000/40) = 83250Assume 5% rate of interest

Average annual interest = C/2 (r/100) = 3,330,000/2*(5/100) = 83,250

Total annual cost = (83,250 + 83,250) = 166,500Benefit cost ratio = Annual benefits/Annual costs = 224,000/166,500 = 1.35Benefit cost ratio is more than unity, and hence, the lining is justified.

ECONOMICS OF CANAL LINING: CALCULATION

Page 41: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

Benefit/Cost ratio example:

Benefit cost ratio = Annual benefits/Annual costs = 224,000/166,500 = 1.35Benefit cost ratio is more than unity, and hence, the lining is justified.

ECONOMICS OF CANAL LINING: CALCULATION

Page 42: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

42

AIS

& B

IS w

ate

r loss stu

dy-N

IB &

UO

N

1. Solving Conveyance and On-farm Water Management Problems

2. Irrigation Water Research: Priority issues and the potential outcomes and impacts

3. Benchmarking irrigation performance: Issues, Concepts and Methods

4. Water Conveyance Study: Ahero Irrigation Scheme Case Study

5. Water Conveyance Study: Bura Irrigation Scheme Case Study

6. Water Conveyance Study: Mwea Irrigation Scheme Case Study

7. Ahero Irrigation water loss assessment

8. Bura Irrigation water loss assessment

9. Mwea Irrigation water loss assessment10. Irrigation water measurement: Developing flow rating curves

11. Ahero Flow Measurement

12. Bura Flow Measurement

13. Mwea Flow Measurement

14. A literature review on seepage assessment and remediation

LIST OF PROJECT OUTPUTS

Page 43: ASSESSING AND IMPROVING THE PERFORMANCE OF CONVEYANCE SYSTEMS: CASE STUDIES OF AHERO, BURA AND MWEA IRRIGATION SCHEMES A COLLABORATIVE RESEARCH PROJECT

43

AIS

& B

IS w

ate

r loss stu

dy-N

IB &

UO

N

THANK YOU