I could summarize the trailing emails (last two) the contractor is trying to catch up on the lost time during
Ramadan Mid break in summer
Please share the approved time schedule (share it for our review and if required to amend)
It means that we have not accounted for the mentioned limitations during the Ramadan and summer inBayti planning. If it is mistake in planning and please share the details if this has been brought to AHRED notice and advise.
We appreciate the contractor recognize Bayti as prestigious project for them, then they should also know that the occupants in the villas are human beings and night sleep is of utmost importance and non-negotiable and as a project manager you might have also accounted this consideration in our project.
You are requested to manage and deliver the project in the set and agreed guidelines with no noise generating work from late evening till morning.
If you tend to disagree, let us have meeting along with AHRED management along with the contractor. You need to arrange the reasons and AHRED approvals for the delay as prerequisites for the meeting.