41
ASH Ad HA Na Rockv Techni Photo Courtesy of Ryan Struct dvisor: Dr ationa ville, M ical Rep f Boggs & Partner n Dalrymp tures Opti r. Thomas al Offi MD port I rs Architects ple ion Boothby ce

ASHA Na tiona l Office Rockville, MDthe North-South direction were found to control the design of the structure with a base shear of ... C Mid-Atla sually 6’x6 October 5, Page 6

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • ASH

    Ad

    HA Na

    Rockv

    Techni

    Photo Courtesy of

    RyanStruct

    dvisor: Dr

    ationa

    ville, M

    ical Rep

    f Boggs & Partner

    n Dalrymptures Opti

    r. Thomas

    al Offi

    MD

    port I

    rs Architects

    ple ion

    Boothby

    ce

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 2 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Table of Contents

    Executive Summary……………………………………………… Page 3

    Introduction …………………………………………………….... Page 4

    Structural System Substructure Foundation………………………………………………… Page 6 Floor Structure…………………………………………….. Page 8 Columns…………………………………………………… Page 9 Superstructure Floor Structure……………………………………………. Page 10 Columns…………………………………………………... Page 11 Roof Structure…………………………………………….. Page 12 Lateral System………………………………………………… Page 13

    Codes and References…………………………………………… Page 14

    Material Properties………………………………………………. Page 16

    Design Loads Gravity Loads……………………………………………... Page 17 Wind Loads……………………………………………….. Page 19 Seismic Loads…………………………………………….. Page 22

    Spot Checks……………………………………………………… Page 24

    Appendix A: Typical Framing Plans……………………………. Page 25

    Appendix B: Calculations……………………………………….. Page 28

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 3 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Executive Summary

    In this technical report, the existing structural system of the ASHA National Office building is discussed and analyzed. The report includes a detailed description of the building’s structural system. The ASHA National Office is a five story office building with two floors of subgrade parking. The substructure is composed of a flat slab system with drop panels and the superstructure is composite steel. Images are used to allow for a better understanding of the system and its components. A list of building codes and standards used to design the building are also included in this report. The properties and strengths of the materials used for the structure of the building are also provided.

    The wind and seismic loads were analyzed for the building using ASCE 7-10. The MWFRS Directional Procedure was used to determine the wind loads on the building in both directions. Seismic loads were calculated using The Equivalent Lateral Force Procedure. The wind loads in the North-South direction were found to control the design of the structure with a base shear of 435 kips.

    Spot checks were done on a beam, girder and column to verify the sizes that were chosen by the structural engineer. A typical composite wide flange beam and girder on the second floor were checked, and a typical steel column was checked below the second floor and below the fourth floor. This was done because the columns are spliced above the third floor. The spot checked members were determined to be adequate for the gravity loads.

    The appendix includes the hand calculations done for the snow, wind and seismic loads. The detailed spot check calculations are also shown. Typical framing plans are also provided in the appendix to help describe the structural framing of the building.

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 4 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Introduction

    The ASHA National Office building is a five story office building in Rockville, MD. The American Speech-Language-Hearing Association owns and operates the building. The building was designed with the employees in mind. There is a generous amount of workspace for the employees and the conference rooms are very flexible. A café and kitchen are provided for the employees on the first floor of the office building. There are two levels of subgrade parking beneath the building in addition to surface parking with a total of 446 spaces.

    One of the main architectural themes that Boggs & Partners incorporated throughout the building is curves. This was done to mimic the sound waves in the ASHA logo. The pre-function space has the curve incorporated into it, and there is a curved piece of art on the landing of the stairway that leads from the lobby to the second floor. The exterior façade has large three story curved glass curtain wall above the main entrance, and the sidewalks on the exterior of the building are curved as well to further emphasize the main theme of the building.

    The five story office building has a total floor area of 133,870 square feet and the roof the building is 69 feet above grade. The top of the penthouse roof is 85 feet above grade. The building façade of the office tower consists of a window wall system and precast concrete spandrels.

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Structur Substruc

    The subsparking. structure parking bshown in

    tional Office –

    rymple – StruDr. Thomas Bo

    ral System

    cture

    structure of tThere is parthat is adjac

    below the ofn yellow.

    – Technical Re

    ctures Optionoothby 

    m

    the ASHA Nrking underncent to the offfice tower is

    Fig

    eport I

    National Offineath the offiffice tower. s shown in b

    gure 1: Over

    ce building iice tower aloSee Figure 1

    blue and the p

    rall Parking

    is comprisedong with a se1: Overall Paparking adja

    Floor Plan

    d of two flooection of thearking Flooracent to the o

    October 5,

    Page 5

    ors of subgrae parking r Plan. The office tower

    , 2010 

    5 of 41 

    ade

    is

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Foundati

    The founslab withof all conrecommeFigure 2:12” to 18

    tional Office –

    rymple – StruDr. Thomas Bo

    ion

    ndation of theh strip footinncrete columendations inc: Partial Fou8” thick. See

    – Technical Re

    ctures Optionoothby 

    e ASHA Nags around th

    mns. The founcluded in the

    undation Plane Figure 3: C

    F

    eport I

    ational Officehe perimeterndations for e geotechnicn. The interio

    Column Footi

    Figure 2: Par

    e building coof the buildthe building

    cal report preor column foing Schedule

    rtial Foundat

    onsists of a 5ding. There ag were desigepared by ESootings are ue.

    ation Plan

    5” thick reinare also footigned in accorSC Mid-Atlausually 6’x6

    October 5,

    Page 6

    nforced concings at the bardance with antic, LLC. S’ and range f

    , 2010 

    6 of 41 

    crete ase the See from

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    Fi

    eport I

    igure 3: Coluumn Footing

    g Schedule

    October 5,

    Page 7

    , 2010 

    7 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Floor Str

    The parkcompriseare 7’-0”the typica14” eachor #7 bar

    tional Office –

    rymple – StruDr. Thomas Bo

    ructure

    king structureed of a 9” thi”x9’-0” and 1al span rang way. The to

    rs. See Figur

    – Technical Re

    ctures Optionoothby 

    e is composeick slab and 10’-0”x10’-0es from 20’

    op reinforcinre 4: Parking

    Fig

    eport I

    ed of a two w5 ½” thick d

    0”. The bay to 40’. The b

    ng bars vary g Level Fram

    gure 4: Parki

    way reinforcdrop panels. sizes vary dbottom reinfdepending o

    ming Plan.

    ing Level Fra

    ced concrete Unless othe

    depending onforcing mat on the locatio

    aming Plan

    flat slab syserwise notedn the part of consists of #on, but are ty

    October 5,

    Page 8

    stem that is d, the drop pa

    the building#5 bars at 12ypically #5,

    , 2010 

    8 of 41 

    anels g, but 2” or

    #6

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Columns

    The conc24”x21” See FiguconnecteBaseplate

    tional Office –

    rymple – StruDr. Thomas Bo

    s

    crete columnwith 8 #8 bare 5: Partial d to the steee Pocket Det

    – Technical Re

    ctures Optionoothby 

    ns in the parkars. The coluColumn Sch

    el columns intail.

    F

    F

    eport I

    king structurumns have ahedule. The n the office t

    igure 5: Part

    Figure 6: Bas

    re are generaa minimum 2concrete col

    tower above

    tial Column

    seplate Pock

    ally 18”x30”28 day complumns of thewith column

    Schedule

    ket Detail

    ” with 10 #7 pressive strene parking strun base plates

    October 5,

    Page 9

    bars, and ngth of 4000ucture are s. See Figure

    , 2010 

    9 of 41 

    0 psi.

    e 6:

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Superstr

    A five stolevel hasupper fouspace wittower tha

    Floor Str

    The floorfloor slab2” deep 1and W14the build

    tional Office –

    rymple – StruDr. Thomas Bo

    ructure

    ory office to a large confur floors are th cubicles oat houses me

    ructure

    r structure fob on metal d18 gauge gal4x22 membeding vary in s

    – Technical Re

    ctures Optionoothby 

    ower is the suference roomcomposed o

    on the exterioechanical and

    or the tower eck. The comlvanized comrs with ¾” dsize, but are

    eport I

    uperstructurem that can beof offices in or of the buid elevator eq

    consists of cmposite slabmposite steeldiameter shemostly W18

    Figure 7: P

    e of the ASHe subdividedthe central cilding. Therequipment.

    cambered steb consists of l deck. The car studs. The

    8x35 membe

    artial Framin

    HA Nationald into five smcore of the be is a pentho

    eel beams w3 ½” norma

    composite bee girders runers. See Figu

    ng Plan

    l Office buildmaller conferuilding, and

    ouse on top o

    with a compoal weight coneams are gennning along ure 7: Partial

    October 5,

    Page 10

    ding. The firrence rooms

    d open officeof the office

    site concretencrete on topnerally W21the exterior l Framing Pl

    , 2010 

    0 of 41 

    rst . The

    e

    e p of 1x44 of

    lan.

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Columns

    The columembersare splice

    tional Office –

    rymple – StruDr. Thomas Bo

    s

    mns for the s. The columed again abo

    – Technical Re

    ctures Optionoothby 

    office towermns are spliceove level 5. S

    F

    eport I

    r are steel wied above levSee figure 8:

    igure 8: Part

    ide flanges. vel 3. The co Partial Colu

    tial Column

    The columnolumns that eumn Schedu

    Schedule

    ns are all W1extend to the

    ule.

    October 5,

    Page 11

    2 and W14 e penthouse

    , 2010 

    1 of 41 

    roof

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Roof Sys

    The roof consists oFigure 9:

    tional Office –

    rymple – StruDr. Thomas Bo

    stem

    f structure coof 3 ½” norm: Partial roof

    – Technical Re

    ctures Optionoothby 

    onsists of “Kmal weight cf framing pla

    Fi

    eport I

    K” joists and concrete on tan.

    igure 9: Parti

    wide flange top of 2” dee

    ial Roof Fra

    members. Tep 18 gauge

    aming Plan

    The structuracomposite s

    October 5,

    Page 12

    al roof slab steel deck. S

    , 2010 

    2 of 41 

    ee

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Lateral S

    The laterin the subwalls belbuilding.of the buthen are ttransfere10: Brace

    tional Office –

    rymple – StruDr. Thomas Bo

    System

    ral force resibgrade parkilow work in The wind lo

    uilding. Thestransmitted td to the sheaed Frame an

    – Technical Re

    ctures Optionoothby 

    sting elemening structurecombinationoads are colle loads are tto the bracedar walls belond Shear Wal

    Figure 10

    eport I

    nts in the ASe of the buildn with the brlected by thethen distribud frames in tow and to thell Elevation.

    : Braced Fra

    SHA Nationading and bracraced framese precast conuted to the cothe core of the footings at .

    ame and She

    al Office buiced frames is above to rencrete spandomposite flohe building. t the base of

    ear Wall Elev

    ilding consisin the office esist the laterdrels that makor slabs andThese loadsthe shear wa

    vation

    October 5,

    Page 13

    st of shear wtower. The sral loads on ke up the faç

    d beams whics are then alls. See figu

    , 2010 

    3 of 41 

    walls shear the çade ch

    ure

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 14 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Codes and References

    Design Codes and References

    “The International Building Code – 2003”, International Code Council. “Minimum Design Loads for Buildings and Other Structures” (ASCE 7), American Society of Civil Engineers. “Building Code Requirements for Structural Concrete, ACI 318-02”, American Concrete Institute. “ACI Manual of Concrete Practice – Parts 1 through 5”, American Concrete Institute. “Manual of Standard Practice”, Concrete Reinforcing Steel Institute. “Building Code Requirements for Masonry Structures (ACI 530, ASCE 5/ TMS 402)”, American Concrete Institute, American Society of Civil Engineers, and The Masonry Society. “Specifications for Masonry Structures (ACI 530.1/ASCE 6/TMS 602)”, American Concrete Institute, American Society of Civil Engineers, and The Masonry Society. “Manual of Steel Construction – Load and Resistance Factor Design”, Third Edition, 2001, American Institute of Steel Construction (Including Specifications for Structural Steel Buildings, Specification for Structural Joints using ASTM A325 or A490 bolts, and AISC Code of Standard Practice. “Detailing for Steel Construction”, American Institute of Steel Construction. “Structural Welding Code ANSI/AWS D1.1” American Welding Society. “Design Manual for Floor Decks and Roof Decks”, Steel Deck Institute. “Standard Specifications for Open Web Steel Joists, K-Series”, Steel Joist Institute. “Standard Specifications for Longspan Steel Joists, LH-Series and Deep Longspan Steel Joists, DLH-Series”, Steel Joist Institute.

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 15 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Thesis Codes and References Steel Construction Manual 13th edition, American Institute of Steel Construction (AISC). Building Code Requirements for Structural Concrete, American Concrete Institute (ACI 318-08). Minimum Design Loads for Buildings and Other Structures, American Society of Civil Engineers (ASCE 7-10).

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 16 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Material Properties Minimum Concrete Compressive Strength (f’c) 

    Member Type  28 Day Strength Footings  3000 psi Grade Beams  3000 psi Foundation Walls  4000 psi Shear Walls  4000 psi Columns  4000 psi Slabs‐on‐grade  3500 psi Reinforced Slabs  5000 psi Reinforced Beams  5000 psi Parking Structure  5000 psi Normal Weight on Steel Deck  3000 psi Elevator Machine Room  4000 psi Lightweight Topping  3000 psi 

    Reinforcement: Deformed Reinforcing Bars ASTM A615, Grade 60 Weldable Deformed Reinforcing Bars ASTM A706 Welded Wire Reinforcement (WWF) ASTM A185 Full Mechanical Connection Splices Dywidag, Lenton or equal meeting (Threadbar and Coupler) ACI 318 Section 12.14.3 Adhesive Reinforcing Bar Dowels Hilti HIT HY-150 System or equal Slab Shear Reinforcement Decon Studrails or equal Steel: Wide Flange Shapes and Tees ASTM A992 Round Hollow Structural Shapes ASTM A53, Grade B, Fy=35 ksi or ASTM A501, Fy=36 ksi Square or Rectangular Hollow ASTM A500, Grade B, Fy=46 ksi Structural Shapes Base Plates and Rigid Frame ASTM A572, Grade 50 Continuity Plates Other Structural Shapes and Plates ASTM A36 High Strength Bolts ASTM A325-N or ASTM F1852 Anchor Bolts ASTM F1554, Grade 36 Galvanized Steel Floor Deck ASTM A653 SS, Grade 33, G-60 Galvanized Steel Roof Deck ASTM A653 SS, Grade 33, G-90 Grout ASTM C1107, Non-Shrink, Non-Metallic f’c = 5000 psi

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 17 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Gravity Loads

    Live Loads Area  Design Load  ASCE 7‐10 LoadAssembly Areas  100 psf  100 psf Corridors  100 psf  100 psf Corridors Above the First Floor  80 psf  80 psf Mechanical Rooms  150 psf  ‐ Offices  80 + 20 psf  50 + 20 psf Parking Garages  50 psf  40 psf Stairs & Exitways  100 psf  100 psf Storage (Light)  125 psf  125 psf Roof (Minimum)  30 psf  20 psf 

    Snow Loads 

    Load Type  Design Load  ASCE 7‐10 Load

    Flat Roof Snow Load pf  21.0 psf  21.0 psf

    Drift Surcharge Load pd  ‐  55.5 psf

    Superimposed Dead Loads Area  Design Load Floors  10 psf Roof  15 psf Mech/Elec  15 psf 

    Composite Slab and Deck Weight Floor  Area (sq. ft.)  Load (psf)  Weight    2nd  24116  54  1302.3 k3rd  24116  44  1061.1 k4th  24116  44  1061.1 k5th  23615  44  1039.1 kRoof  23615  44  1039.1 k

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 18 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Column Self Weight 

    Floor Height Below 

    (ft) Height Above 

    (ft) Weight Below 

    (plf) Weight Above 

    (plf)  Total Weight    

    2nd  15  6.75  3097  3097  67.4  k 

    3rd  10.75  2.75  3097  2167  39.3  k 

    4th  6.75  6.75  2167  2167  29.3  k 

    5th  6.75  6.75  2167  2167  29.3  k 

    Roof  6.75  0  2167  0  14.6  k 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Wind L The windused to c210’x100to controon each sthe wind

    Wall      

    Windwa        

    Leewa

    tional Office –

    rymple – StruDr. Thomas Bo

    Loads

    d loads werealculate the 0’ rectangle

    ol because thstory of the bloads are sh

    East‐West D  heigh

    0‐22

    ard  34566

    rd  A

    – Technical Re

    ctures Optionoothby 

    e determinedloads. Whenfor simplifice wind loadsbuilding. Thhown in App

    Design Wind Pht z (ft)  kz‐15  0.520  0.625  0.630  0.740  0.750  0.860  0.869  0.8All  0.8

    Figure 1

    eport I

    d using ASCEn calculatingcation. The ws act upon a e total base

    pendix B.

    Pressures, p z  qz (psf) 7  16.40 

    62  17.84 66  18.99 70  20.14 76  21.87 81  23.31 85  24.46 89  25.61 89  25.61 

    11: Wind Pre

    E 7-10. The g the wind lowind loads inlarger surfacshear came t

    p (psf) 15.63 16.60 17.37 18.14 19.31 20.27 21.05 21.82 ‐11.06 

    essures East

    MWFRS Dioads, the buin the North-ce area, therto be 434.7 k

    t-West Direc

    irectional Prilding was as-South Direcrefore creatinkips. Detaile

    ction

    October 5,

    Page 19

    rocedure wasssumed to bection were fong a larger foed calculatio

    , 2010 

    9 of 41 

    s e a ound force ons of

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Wall      

    Windwa        

    Leewa

    tional Office –

    rymple – StruDr. Thomas Bo

    North‐South   heigh

    0‐22

    ard  34566

    rd  A

    – Technical Re

    ctures Optionoothby 

    Figure 12

    Design Windht z (ft)  kz‐15  0.520  0.625  0.630  0.740  0.750  0.860  0.869  0.8All  0.8

    Figure 12

    eport I

    2: Wind Stor

     Pressures, pz  qz (psf) 7  16.40 

    62  17.84 66  18.99 70  20.14 76  21.87 81  23.31 85  24.46 89  25.61 89  25.61 

    2: Wind Pres

    ry Forces Ea

    p (psf) 15.24 16.17 16.92 17.66 18.78 19.71 20.46 21.21 ‐14.98 

    ssures North

    ast-West Dire

    h-South Dire

    ection

    ection

    October 5,

    Page 20

    , 2010 

    0 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    Figure 13:

    eport I

    Wind Storyy Forces Nor

    rth-South Dirrection

    October 5,

    Page 21

    , 2010 

    1 of 41 

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 22 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Seismic Loads The seismic loads on the building were calculated using The Equivalent Lateral Force Procedure of ASCE 7-10. The effective seismic weight of the building was estimated and used to calculate the total base shear of the building due to the seismic loads. The total base shear was calculated to be 288.3 kips which is very close to the base shear of 277 kips on the structural drawings. Detailed seismic load calculations are shown in Appendix B. Effective Seismic Weight Floor  Weight    

    2nd  2420.5  k 3rd  2135.0  k 4th  2125.0  k 5th  2102.9  k Roof  2303.6  k Total  11087.1  k 

    V=CsW=  288.3  k 

    Vertical Distribution of Seismic Forces Floor  wx  hx  (ft)  wxhx^k  Cvx  Fx    2nd  2035.566  15.0  48385.1 0.068 19.6 k3rd  1773.251  28.5  89317.9 0.126 36.3 k4th  1763.254  42.0  139803.0 0.197 56.8 k5th  1741.21  55.5  191281.9 0.269 77.7 kRoof  1700.687  69.0  241033.8 0.340 97.9 k

    Sum  709821.7 1.000 288.3 k

    Overturning Moment  14778.4 ft‐k 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Compar Total Ba Overturn

    tional Office –

    rymple – StruDr. Thomas Bo

    rison of W

    se Shear:

    Wind Wind Seism

    ning Moment

    Wind Wind Seism

    – Technical Re

    ctures Optionoothby 

    Wind and Se

    East-West: North-South

    mic Both Dire

    t:

    East-West: North-South

    mic Both Dire

    eport I

    Figure 14: S

    eismic Loa

    h: ections:

    h: ections:

    Seismic Story

    ads

    184.3 kips434.7 kips 288.3 kips

    7387 ft-kips17258 ft-kip14778 ft-kip

    y Forces

    Controls

    s ps Contrps

    s

    rols

    October 5,

    Page 23

    , 2010 

    3 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Spot Ch

    Spot checwas also 15: Partiafor the lobecause tactual dethe actuaare used may alsoso the str

    tional Office –

    rymple – StruDr. Thomas Bo

    hecks

    cks were dondone for col

    al Second Floads. The colthe steel coluesign of the cal designed mthroughout t

    o be because rength of the

    – Technical Re

    ctures Optionoothby 

    ne on a typiclumn H1. Thloor Plan. Thlumn was chumns are splcomposite bemembers are the building,these memb

    e composite m

    Fig

    MeCompoCompo

    Column H1Column H1

    eport I

    cal composithe members he members hecked belowliced 4’ aboveam and girdlarger may

    , including sbers are usedmembers wi

    gure 15: Par

    Sp

    ember osite Beam osite Girder : Below Level: Below Level

    te beam and that were spin the actua

    w the secondve the third fder is differebe attributed

    spaces that hd on other floill be reduce

    rtial Second

    pot Checks ActuaDesig

    W21x44W18x35

    l 2  W12xl 4  W12x4

    girder on thpot checked al design werd floor and bfloor. As seeent than the d to the fact have higher loors that havd.

    Floor Plan

    al gn 

    ThDe

    4 (42)  W18x5 (24)  W14x58  W140  W1

    he second floare shown bre determinebelow the fouen in the tablthesis designthat these ty

    live loads thave thinner co

    hesis esign x40 (26) x22 (32) 12x53 12x40 

    October 5,

    Page 24

    oor. A spot cbelow in Figued to be adequrth floor le below, then. The fact th

    ypical memban the officeomposite slab

    , 2010 

    4 of 41 

    check ure quate

    e hat

    bers es. It bs,

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Append

    tional Office –

    rymple – StruDr. Thomas Bo

    dix A: Typi

    – Technical Re

    ctures Optionoothby 

    ical Framin

    F

    F

    eport I

    ng Plans

    Figure 16: Fo

    Figure 17: Fo

    oundation Pl

    oundation Pl

    lan Part A

    lan Part B

    October 5,

    Page 25

    , 2010 

    5 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    Figure

    Figure

    eport I

    e 18: Plaza L

    e 19: Plaza L

    Level Framin

    Level Framin

    ng Plan Part

    ng Plan Part

    A

    t B

    October 5,

    Page 26

    , 2010 

    6 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    Fig

    eport I

    gure 20: Seco

    Figure 21:

    ond Floor Fr

    Roof Framin

    raming Plan

    ng Plan

    October 5,

    Page 27

    , 2010 

    7 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    Append

    tional Office –

    rymple – StruDr. Thomas Bo

    dix B: Calc

    – Technical Re

    ctures Optionoothby 

    culations

    eport I

    October 5,

    Page 28

    , 2010 

    8 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 29

    , 2010 

    9 of 41 

  • ASHA National Office – Technical Report I    October 5, 2010  

    Page 30 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby 

    Beam Self Weight Per Floor Beam Size  Length  Number  Weight W21x  44  40  35  61600  lb W24x  55  40  5  11000  lb W18x  35  20  20  14000  lb W21x  44  20  5  4400  lb W27x  84  40  2  6720  lb W12x  14  10  4  560  lb W10x  12  10  10  1200  lb W18x  40  20  4  3200  lb W24x  62  30  1  1860  lb W14x  22  20  5  2200  lb W10x  12  4  4  192  lb W24x  55  20  1  1100  lb W16x  26  15  1  390  lb W21x  50  20  1  1000  lb W16x  31  24  1  744  lb W16x  40  20  1  800  lb W14x  22  21  2  924  lb W14x  22  26  1  572  lb W16x  31  26  2  1612  lb W18x  35  26  1  910  lb W12x  16  12  1  192  lb W12x  14  15  1  210  lb W12x  16  18  1  288  lb W14x  22  23  1  506  lb W14x  22  25  1  550  lb W12x  19  25  1  475  lb W16x  26  28  1  728  lb W18x  35  30  1  1050  lb W16x  31  32  1  992  lb W18x  35  34  2  2380  lb W21x  44  37  1  1628  lb W21x  44  40  2  3520  lb W21x  44  43  1  1892  lb W14x  22  25  1  550  lb W16x  31  28  1  868  lb W18x  35  30  1  1050  lb W16x  31  32  1  992  lb W18x  35  34  1  1190  lb W18x  40  38  1  1520  lb W21x  50  20  2  2000  lb W14x  61  20  1  1220  lb 

    Total  138785  lb Total  138.8  k 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 31

    , 2010 

    1 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 32

    , 2010 

    2 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 33

    , 2010 

    3 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 34

    , 2010 

    4 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 35

    , 2010 

    5 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 36

    , 2010 

    6 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 37

    , 2010 

    7 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 38

    , 2010 

    8 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 39

    , 2010 

    9 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 40

    , 2010 

    0 of 41 

  • ASHA Nat 

    Ryan DalrAdvisor: D

    tional Office –

    rymple – StruDr. Thomas Bo

    – Technical Re

    ctures Optionoothby 

    eport I

    October 5,

    Page 41

    , 2010 

    1 of 41