Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
ASH
Ad
HA Na
Rockv
Techni
Photo Courtesy of
RyanStruct
dvisor: Dr
ationa
ville, M
ical Rep
f Boggs & Partner
n Dalrymptures Opti
r. Thomas
al Offi
MD
port I
rs Architects
ple ion
Boothby
ce
ASHA National Office – Technical Report I October 5, 2010
Page 2 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Table of Contents
Executive Summary……………………………………………… Page 3
Introduction …………………………………………………….... Page 4
Structural System Substructure Foundation………………………………………………… Page 6 Floor Structure…………………………………………….. Page 8 Columns…………………………………………………… Page 9 Superstructure Floor Structure……………………………………………. Page 10 Columns…………………………………………………... Page 11 Roof Structure…………………………………………….. Page 12 Lateral System………………………………………………… Page 13
Codes and References…………………………………………… Page 14
Material Properties………………………………………………. Page 16
Design Loads Gravity Loads……………………………………………... Page 17 Wind Loads……………………………………………….. Page 19 Seismic Loads…………………………………………….. Page 22
Spot Checks……………………………………………………… Page 24
Appendix A: Typical Framing Plans……………………………. Page 25
Appendix B: Calculations……………………………………….. Page 28
ASHA National Office – Technical Report I October 5, 2010
Page 3 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Executive Summary
In this technical report, the existing structural system of the ASHA National Office building is discussed and analyzed. The report includes a detailed description of the building’s structural system. The ASHA National Office is a five story office building with two floors of subgrade parking. The substructure is composed of a flat slab system with drop panels and the superstructure is composite steel. Images are used to allow for a better understanding of the system and its components. A list of building codes and standards used to design the building are also included in this report. The properties and strengths of the materials used for the structure of the building are also provided.
The wind and seismic loads were analyzed for the building using ASCE 7-10. The MWFRS Directional Procedure was used to determine the wind loads on the building in both directions. Seismic loads were calculated using The Equivalent Lateral Force Procedure. The wind loads in the North-South direction were found to control the design of the structure with a base shear of 435 kips.
Spot checks were done on a beam, girder and column to verify the sizes that were chosen by the structural engineer. A typical composite wide flange beam and girder on the second floor were checked, and a typical steel column was checked below the second floor and below the fourth floor. This was done because the columns are spliced above the third floor. The spot checked members were determined to be adequate for the gravity loads.
The appendix includes the hand calculations done for the snow, wind and seismic loads. The detailed spot check calculations are also shown. Typical framing plans are also provided in the appendix to help describe the structural framing of the building.
ASHA National Office – Technical Report I October 5, 2010
Page 4 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Introduction
The ASHA National Office building is a five story office building in Rockville, MD. The American Speech-Language-Hearing Association owns and operates the building. The building was designed with the employees in mind. There is a generous amount of workspace for the employees and the conference rooms are very flexible. A café and kitchen are provided for the employees on the first floor of the office building. There are two levels of subgrade parking beneath the building in addition to surface parking with a total of 446 spaces.
One of the main architectural themes that Boggs & Partners incorporated throughout the building is curves. This was done to mimic the sound waves in the ASHA logo. The pre-function space has the curve incorporated into it, and there is a curved piece of art on the landing of the stairway that leads from the lobby to the second floor. The exterior façade has large three story curved glass curtain wall above the main entrance, and the sidewalks on the exterior of the building are curved as well to further emphasize the main theme of the building.
The five story office building has a total floor area of 133,870 square feet and the roof the building is 69 feet above grade. The top of the penthouse roof is 85 feet above grade. The building façade of the office tower consists of a window wall system and precast concrete spandrels.
ASHA Nat
Ryan DalrAdvisor: D
Structur Substruc
The subsparking. structure parking bshown in
tional Office –
rymple – StruDr. Thomas Bo
ral System
cture
structure of tThere is parthat is adjac
below the ofn yellow.
– Technical Re
ctures Optionoothby
m
the ASHA Nrking underncent to the offfice tower is
Fig
eport I
n
National Offineath the offiffice tower. s shown in b
gure 1: Over
ce building iice tower aloSee Figure 1
blue and the p
rall Parking
is comprisedong with a se1: Overall Paparking adja
Floor Plan
d of two flooection of thearking Flooracent to the o
October 5,
Page 5
ors of subgrae parking r Plan. The office tower
, 2010
5 of 41
ade
is
ASHA Nat
Ryan DalrAdvisor: D
Foundati
The founslab withof all conrecommeFigure 2:12” to 18
tional Office –
rymple – StruDr. Thomas Bo
ion
ndation of theh strip footinncrete columendations inc: Partial Fou8” thick. See
– Technical Re
ctures Optionoothby
e ASHA Nags around th
mns. The founcluded in the
undation Plane Figure 3: C
F
eport I
n
ational Officehe perimeterndations for e geotechnicn. The interio
Column Footi
Figure 2: Par
e building coof the buildthe building
cal report preor column foing Schedule
rtial Foundat
onsists of a 5ding. There ag were desigepared by ESootings are ue.
ation Plan
5” thick reinare also footigned in accorSC Mid-Atlausually 6’x6
October 5,
Page 6
nforced concings at the bardance with antic, LLC. S’ and range f
, 2010
6 of 41
crete ase the See from
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
Fi
eport I
n
igure 3: Coluumn Footing
g Schedule
October 5,
Page 7
, 2010
7 of 41
ASHA Nat
Ryan DalrAdvisor: D
Floor Str
The parkcompriseare 7’-0”the typica14” eachor #7 bar
tional Office –
rymple – StruDr. Thomas Bo
ructure
king structureed of a 9” thi”x9’-0” and 1al span rang way. The to
rs. See Figur
– Technical Re
ctures Optionoothby
e is composeick slab and 10’-0”x10’-0es from 20’
op reinforcinre 4: Parking
Fig
eport I
n
ed of a two w5 ½” thick d
0”. The bay to 40’. The b
ng bars vary g Level Fram
gure 4: Parki
way reinforcdrop panels. sizes vary dbottom reinfdepending o
ming Plan.
ing Level Fra
ced concrete Unless othe
depending onforcing mat on the locatio
aming Plan
flat slab syserwise notedn the part of consists of #on, but are ty
October 5,
Page 8
stem that is d, the drop pa
the building#5 bars at 12ypically #5,
, 2010
8 of 41
anels g, but 2” or
#6
ASHA Nat
Ryan DalrAdvisor: D
Columns
The conc24”x21” See FiguconnecteBaseplate
tional Office –
rymple – StruDr. Thomas Bo
s
crete columnwith 8 #8 bare 5: Partial d to the steee Pocket Det
– Technical Re
ctures Optionoothby
ns in the parkars. The coluColumn Sch
el columns intail.
F
F
eport I
n
king structurumns have ahedule. The n the office t
igure 5: Part
Figure 6: Bas
re are generaa minimum 2concrete col
tower above
tial Column
seplate Pock
ally 18”x30”28 day complumns of thewith column
Schedule
ket Detail
” with 10 #7 pressive strene parking strun base plates
October 5,
Page 9
bars, and ngth of 4000ucture are s. See Figure
, 2010
9 of 41
0 psi.
e 6:
ASHA Nat
Ryan DalrAdvisor: D
Superstr
A five stolevel hasupper fouspace wittower tha
Floor Str
The floorfloor slab2” deep 1and W14the build
tional Office –
rymple – StruDr. Thomas Bo
ructure
ory office to a large confur floors are th cubicles oat houses me
ructure
r structure fob on metal d18 gauge gal4x22 membeding vary in s
– Technical Re
ctures Optionoothby
ower is the suference roomcomposed o
on the exterioechanical and
or the tower eck. The comlvanized comrs with ¾” dsize, but are
eport I
n
uperstructurem that can beof offices in or of the buid elevator eq
consists of cmposite slabmposite steeldiameter shemostly W18
Figure 7: P
e of the ASHe subdividedthe central cilding. Therequipment.
cambered steb consists of l deck. The car studs. The
8x35 membe
artial Framin
HA Nationald into five smcore of the be is a pentho
eel beams w3 ½” norma
composite bee girders runers. See Figu
ng Plan
l Office buildmaller conferuilding, and
ouse on top o
with a compoal weight coneams are gennning along ure 7: Partial
October 5,
Page 10
ding. The firrence rooms
d open officeof the office
site concretencrete on topnerally W21the exterior l Framing Pl
, 2010
0 of 41
rst . The
e
e p of 1x44 of
lan.
ASHA Nat
Ryan DalrAdvisor: D
Columns
The columembersare splice
tional Office –
rymple – StruDr. Thomas Bo
s
mns for the s. The columed again abo
– Technical Re
ctures Optionoothby
office towermns are spliceove level 5. S
F
eport I
n
r are steel wied above levSee figure 8:
igure 8: Part
ide flanges. vel 3. The co Partial Colu
tial Column
The columnolumns that eumn Schedu
Schedule
ns are all W1extend to the
ule.
October 5,
Page 11
2 and W14 e penthouse
, 2010
1 of 41
roof
ASHA Nat
Ryan DalrAdvisor: D
Roof Sys
The roof consists oFigure 9:
tional Office –
rymple – StruDr. Thomas Bo
stem
f structure coof 3 ½” norm: Partial roof
– Technical Re
ctures Optionoothby
onsists of “Kmal weight cf framing pla
Fi
eport I
n
K” joists and concrete on tan.
igure 9: Parti
wide flange top of 2” dee
ial Roof Fra
members. Tep 18 gauge
aming Plan
The structuracomposite s
October 5,
Page 12
al roof slab steel deck. S
, 2010
2 of 41
ee
ASHA Nat
Ryan DalrAdvisor: D
Lateral S
The laterin the subwalls belbuilding.of the buthen are ttransfere10: Brace
tional Office –
rymple – StruDr. Thomas Bo
System
ral force resibgrade parkilow work in The wind lo
uilding. Thestransmitted td to the sheaed Frame an
– Technical Re
ctures Optionoothby
sting elemening structurecombinationoads are colle loads are tto the bracedar walls belond Shear Wal
Figure 10
eport I
n
nts in the ASe of the buildn with the brlected by thethen distribud frames in tow and to thell Elevation.
: Braced Fra
SHA Nationading and bracraced framese precast conuted to the cothe core of the footings at .
ame and She
al Office buiced frames is above to rencrete spandomposite flohe building. t the base of
ear Wall Elev
ilding consisin the office esist the laterdrels that makor slabs andThese loadsthe shear wa
vation
October 5,
Page 13
st of shear wtower. The sral loads on ke up the faç
d beams whics are then alls. See figu
, 2010
3 of 41
walls shear the çade ch
ure
ASHA National Office – Technical Report I October 5, 2010
Page 14 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Codes and References
Design Codes and References
“The International Building Code – 2003”, International Code Council. “Minimum Design Loads for Buildings and Other Structures” (ASCE 7), American Society of Civil Engineers. “Building Code Requirements for Structural Concrete, ACI 318-02”, American Concrete Institute. “ACI Manual of Concrete Practice – Parts 1 through 5”, American Concrete Institute. “Manual of Standard Practice”, Concrete Reinforcing Steel Institute. “Building Code Requirements for Masonry Structures (ACI 530, ASCE 5/ TMS 402)”, American Concrete Institute, American Society of Civil Engineers, and The Masonry Society. “Specifications for Masonry Structures (ACI 530.1/ASCE 6/TMS 602)”, American Concrete Institute, American Society of Civil Engineers, and The Masonry Society. “Manual of Steel Construction – Load and Resistance Factor Design”, Third Edition, 2001, American Institute of Steel Construction (Including Specifications for Structural Steel Buildings, Specification for Structural Joints using ASTM A325 or A490 bolts, and AISC Code of Standard Practice. “Detailing for Steel Construction”, American Institute of Steel Construction. “Structural Welding Code ANSI/AWS D1.1” American Welding Society. “Design Manual for Floor Decks and Roof Decks”, Steel Deck Institute. “Standard Specifications for Open Web Steel Joists, K-Series”, Steel Joist Institute. “Standard Specifications for Longspan Steel Joists, LH-Series and Deep Longspan Steel Joists, DLH-Series”, Steel Joist Institute.
ASHA National Office – Technical Report I October 5, 2010
Page 15 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Thesis Codes and References Steel Construction Manual 13th edition, American Institute of Steel Construction (AISC). Building Code Requirements for Structural Concrete, American Concrete Institute (ACI 318-08). Minimum Design Loads for Buildings and Other Structures, American Society of Civil Engineers (ASCE 7-10).
ASHA National Office – Technical Report I October 5, 2010
Page 16 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Material Properties Minimum Concrete Compressive Strength (f’c)
Member Type 28 Day Strength Footings 3000 psi Grade Beams 3000 psi Foundation Walls 4000 psi Shear Walls 4000 psi Columns 4000 psi Slabs‐on‐grade 3500 psi Reinforced Slabs 5000 psi Reinforced Beams 5000 psi Parking Structure 5000 psi Normal Weight on Steel Deck 3000 psi Elevator Machine Room 4000 psi Lightweight Topping 3000 psi
Reinforcement: Deformed Reinforcing Bars ASTM A615, Grade 60 Weldable Deformed Reinforcing Bars ASTM A706 Welded Wire Reinforcement (WWF) ASTM A185 Full Mechanical Connection Splices Dywidag, Lenton or equal meeting (Threadbar and Coupler) ACI 318 Section 12.14.3 Adhesive Reinforcing Bar Dowels Hilti HIT HY-150 System or equal Slab Shear Reinforcement Decon Studrails or equal Steel: Wide Flange Shapes and Tees ASTM A992 Round Hollow Structural Shapes ASTM A53, Grade B, Fy=35 ksi or ASTM A501, Fy=36 ksi Square or Rectangular Hollow ASTM A500, Grade B, Fy=46 ksi Structural Shapes Base Plates and Rigid Frame ASTM A572, Grade 50 Continuity Plates Other Structural Shapes and Plates ASTM A36 High Strength Bolts ASTM A325-N or ASTM F1852 Anchor Bolts ASTM F1554, Grade 36 Galvanized Steel Floor Deck ASTM A653 SS, Grade 33, G-60 Galvanized Steel Roof Deck ASTM A653 SS, Grade 33, G-90 Grout ASTM C1107, Non-Shrink, Non-Metallic f’c = 5000 psi
ASHA National Office – Technical Report I October 5, 2010
Page 17 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Gravity Loads
Live Loads Area Design Load ASCE 7‐10 LoadAssembly Areas 100 psf 100 psf Corridors 100 psf 100 psf Corridors Above the First Floor 80 psf 80 psf Mechanical Rooms 150 psf ‐ Offices 80 + 20 psf 50 + 20 psf Parking Garages 50 psf 40 psf Stairs & Exitways 100 psf 100 psf Storage (Light) 125 psf 125 psf Roof (Minimum) 30 psf 20 psf
Snow Loads
Load Type Design Load ASCE 7‐10 Load
Flat Roof Snow Load pf 21.0 psf 21.0 psf
Drift Surcharge Load pd ‐ 55.5 psf
Superimposed Dead Loads Area Design Load Floors 10 psf Roof 15 psf Mech/Elec 15 psf
Composite Slab and Deck Weight Floor Area (sq. ft.) Load (psf) Weight 2nd 24116 54 1302.3 k3rd 24116 44 1061.1 k4th 24116 44 1061.1 k5th 23615 44 1039.1 kRoof 23615 44 1039.1 k
ASHA National Office – Technical Report I October 5, 2010
Page 18 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Column Self Weight
Floor Height Below
(ft) Height Above
(ft) Weight Below
(plf) Weight Above
(plf) Total Weight
2nd 15 6.75 3097 3097 67.4 k
3rd 10.75 2.75 3097 2167 39.3 k
4th 6.75 6.75 2167 2167 29.3 k
5th 6.75 6.75 2167 2167 29.3 k
Roof 6.75 0 2167 0 14.6 k
ASHA Nat
Ryan DalrAdvisor: D
Wind L The windused to c210’x100to controon each sthe wind
Wall
Windwa
Leewa
tional Office –
rymple – StruDr. Thomas Bo
Loads
d loads werealculate the 0’ rectangle
ol because thstory of the bloads are sh
East‐West D heigh
0‐22
ard 34566
rd A
– Technical Re
ctures Optionoothby
e determinedloads. Whenfor simplifice wind loadsbuilding. Thhown in App
Design Wind Pht z (ft) kz‐15 0.520 0.625 0.630 0.740 0.750 0.860 0.869 0.8All 0.8
Figure 1
eport I
n
d using ASCEn calculatingcation. The ws act upon a e total base
pendix B.
Pressures, p z qz (psf) 7 16.40
62 17.84 66 18.99 70 20.14 76 21.87 81 23.31 85 24.46 89 25.61 89 25.61
11: Wind Pre
E 7-10. The g the wind lowind loads inlarger surfacshear came t
p (psf) 15.63 16.60 17.37 18.14 19.31 20.27 21.05 21.82 ‐11.06
essures East
MWFRS Dioads, the buin the North-ce area, therto be 434.7 k
t-West Direc
irectional Prilding was as-South Direcrefore creatinkips. Detaile
ction
October 5,
Page 19
rocedure wasssumed to bection were fong a larger foed calculatio
, 2010
9 of 41
s e a ound force ons of
ASHA Nat
Ryan DalrAdvisor: D
Wall
Windwa
Leewa
tional Office –
rymple – StruDr. Thomas Bo
North‐South heigh
0‐22
ard 34566
rd A
– Technical Re
ctures Optionoothby
Figure 12
Design Windht z (ft) kz‐15 0.520 0.625 0.630 0.740 0.750 0.860 0.869 0.8All 0.8
Figure 12
eport I
n
2: Wind Stor
Pressures, pz qz (psf) 7 16.40
62 17.84 66 18.99 70 20.14 76 21.87 81 23.31 85 24.46 89 25.61 89 25.61
2: Wind Pres
ry Forces Ea
p (psf) 15.24 16.17 16.92 17.66 18.78 19.71 20.46 21.21 ‐14.98
ssures North
ast-West Dire
h-South Dire
ection
ection
October 5,
Page 20
, 2010
0 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
Figure 13:
eport I
n
Wind Storyy Forces Nor
rth-South Dirrection
October 5,
Page 21
, 2010
1 of 41
ASHA National Office – Technical Report I October 5, 2010
Page 22 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Seismic Loads The seismic loads on the building were calculated using The Equivalent Lateral Force Procedure of ASCE 7-10. The effective seismic weight of the building was estimated and used to calculate the total base shear of the building due to the seismic loads. The total base shear was calculated to be 288.3 kips which is very close to the base shear of 277 kips on the structural drawings. Detailed seismic load calculations are shown in Appendix B. Effective Seismic Weight Floor Weight
2nd 2420.5 k 3rd 2135.0 k 4th 2125.0 k 5th 2102.9 k Roof 2303.6 k Total 11087.1 k
V=CsW= 288.3 k
Vertical Distribution of Seismic Forces Floor wx hx (ft) wxhx^k Cvx Fx 2nd 2035.566 15.0 48385.1 0.068 19.6 k3rd 1773.251 28.5 89317.9 0.126 36.3 k4th 1763.254 42.0 139803.0 0.197 56.8 k5th 1741.21 55.5 191281.9 0.269 77.7 kRoof 1700.687 69.0 241033.8 0.340 97.9 k
Sum 709821.7 1.000 288.3 k
Overturning Moment 14778.4 ft‐k
ASHA Nat
Ryan DalrAdvisor: D
Compar Total Ba Overturn
tional Office –
rymple – StruDr. Thomas Bo
rison of W
se Shear:
Wind Wind Seism
ning Moment
Wind Wind Seism
– Technical Re
ctures Optionoothby
Wind and Se
East-West: North-South
mic Both Dire
t:
East-West: North-South
mic Both Dire
eport I
n
Figure 14: S
eismic Loa
h: ections:
h: ections:
Seismic Story
ads
184.3 kips434.7 kips 288.3 kips
7387 ft-kips17258 ft-kip14778 ft-kip
y Forces
Controls
s ps Contrps
s
rols
October 5,
Page 23
, 2010
3 of 41
ASHA Nat
Ryan DalrAdvisor: D
Spot Ch
Spot checwas also 15: Partiafor the lobecause tactual dethe actuaare used may alsoso the str
tional Office –
rymple – StruDr. Thomas Bo
hecks
cks were dondone for col
al Second Floads. The colthe steel coluesign of the cal designed mthroughout t
o be because rength of the
– Technical Re
ctures Optionoothby
ne on a typiclumn H1. Thloor Plan. Thlumn was chumns are splcomposite bemembers are the building,these memb
e composite m
Fig
MeCompoCompo
Column H1Column H1
eport I
n
cal composithe members he members hecked belowliced 4’ aboveam and girdlarger may
, including sbers are usedmembers wi
gure 15: Par
Sp
ember osite Beam osite Girder : Below Level: Below Level
te beam and that were spin the actua
w the secondve the third fder is differebe attributed
spaces that hd on other floill be reduce
rtial Second
pot Checks ActuaDesig
W21x44W18x35
l 2 W12xl 4 W12x4
girder on thpot checked al design werd floor and bfloor. As seeent than the d to the fact have higher loors that havd.
Floor Plan
al gn
ThDe
4 (42) W18x5 (24) W14x58 W140 W1
he second floare shown bre determinebelow the fouen in the tablthesis designthat these ty
live loads thave thinner co
hesis esign x40 (26) x22 (32) 12x53 12x40
October 5,
Page 24
oor. A spot cbelow in Figued to be adequrth floor le below, then. The fact th
ypical memban the officeomposite slab
, 2010
4 of 41
check ure quate
e hat
bers es. It bs,
ASHA Nat
Ryan DalrAdvisor: D
Append
tional Office –
rymple – StruDr. Thomas Bo
dix A: Typi
– Technical Re
ctures Optionoothby
ical Framin
F
F
eport I
n
ng Plans
Figure 16: Fo
Figure 17: Fo
oundation Pl
oundation Pl
lan Part A
lan Part B
October 5,
Page 25
, 2010
5 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
Figure
Figure
eport I
n
e 18: Plaza L
e 19: Plaza L
Level Framin
Level Framin
ng Plan Part
ng Plan Part
A
t B
October 5,
Page 26
, 2010
6 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
Fig
eport I
n
gure 20: Seco
Figure 21:
ond Floor Fr
Roof Framin
raming Plan
ng Plan
October 5,
Page 27
, 2010
7 of 41
ASHA Nat
Ryan DalrAdvisor: D
Append
tional Office –
rymple – StruDr. Thomas Bo
dix B: Calc
– Technical Re
ctures Optionoothby
culations
eport I
n
October 5,
Page 28
, 2010
8 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 29
, 2010
9 of 41
ASHA National Office – Technical Report I October 5, 2010
Page 30 of 41 Ryan Dalrymple – Structures Option Advisor: Dr. Thomas Boothby
Beam Self Weight Per Floor Beam Size Length Number Weight W21x 44 40 35 61600 lb W24x 55 40 5 11000 lb W18x 35 20 20 14000 lb W21x 44 20 5 4400 lb W27x 84 40 2 6720 lb W12x 14 10 4 560 lb W10x 12 10 10 1200 lb W18x 40 20 4 3200 lb W24x 62 30 1 1860 lb W14x 22 20 5 2200 lb W10x 12 4 4 192 lb W24x 55 20 1 1100 lb W16x 26 15 1 390 lb W21x 50 20 1 1000 lb W16x 31 24 1 744 lb W16x 40 20 1 800 lb W14x 22 21 2 924 lb W14x 22 26 1 572 lb W16x 31 26 2 1612 lb W18x 35 26 1 910 lb W12x 16 12 1 192 lb W12x 14 15 1 210 lb W12x 16 18 1 288 lb W14x 22 23 1 506 lb W14x 22 25 1 550 lb W12x 19 25 1 475 lb W16x 26 28 1 728 lb W18x 35 30 1 1050 lb W16x 31 32 1 992 lb W18x 35 34 2 2380 lb W21x 44 37 1 1628 lb W21x 44 40 2 3520 lb W21x 44 43 1 1892 lb W14x 22 25 1 550 lb W16x 31 28 1 868 lb W18x 35 30 1 1050 lb W16x 31 32 1 992 lb W18x 35 34 1 1190 lb W18x 40 38 1 1520 lb W21x 50 20 2 2000 lb W14x 61 20 1 1220 lb
Total 138785 lb Total 138.8 k
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 31
, 2010
1 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 32
, 2010
2 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 33
, 2010
3 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 34
, 2010
4 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 35
, 2010
5 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 36
, 2010
6 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 37
, 2010
7 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 38
, 2010
8 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 39
, 2010
9 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 40
, 2010
0 of 41
ASHA Nat
Ryan DalrAdvisor: D
tional Office –
rymple – StruDr. Thomas Bo
– Technical Re
ctures Optionoothby
eport I
n
October 5,
Page 41
, 2010
1 of 41