Upload
leo-horn
View
218
Download
0
Tags:
Embed Size (px)
Citation preview
ARUSHA EXERCISE BRIEFINGNahom Beyene, PhD
Including slides from Cherice Moore (NASA) and Craig Maynard (NASA)
Exercise Design & Lessons Learned 1
Speaker Intro• Past Experiences @ Johnson Space Center
• Co-op Student• Grad Co-op• Aerospace Engineer
• Present Vocation: Assoc. Engineer @ RAND Corporation• Part-Time Passion: Technology Commercialization – a
testing methodology to validate the capabilities and forecast the risks of automated vehicles
Exercise Design & Lessons Learned 2
Exercise Equipment Design, Planning & ISS Lessons LearnedDeep Space Habitat SE&I Human Performance and Reliability TIM
March 27, 2012
Presenters:Cherice Moore (281-483-8780/ Adv. CMS Technology Development Manager)Craig Maynard (281-483-9316/ CMS System Manager)Patty Meyer (281-483-4496/ SA CMS Integration Lead)
ISS Capabilities
Any mission that exceeds approx. 30 days is expected to require the full set of capabilities that are reflected on ISS*.
*(<30 days requires a subset of the capabilities)
Exercise Design & Lessons Learned
4
Physiological Needs and ISS Answers
Countermeasure Purpose/Equipment
Aerobic Conditioning
Musculature Conditioning
Bone Loss
Sensorimotor
Psychological
DCS
T2
TVIS*
CEVIS
VELO*
ARED (USOS & RSA)
Exercise Tubing (Bungees)
For rehab only
Table Notes: Green = primary role of equipment; Yellow = partially supports; * = used for Russian crew
• Research is ongoing for requirements on future exercise equipment design.
• ISS equipment is meant to support 3 crewmembers within a single shift day.
Exercise Design & Lessons Learned
5
Equipment Capabilities and Resource Needs
T2 TVIS CEVIS AREDCapabilities Summary
0-12 mph treadmill, bungee restraint system
0-10 mph treadmill, active loading system
0-300W resistive ergometer
0-600 lb resistive exercise device
Total Operational Volume* in cu. Ft. (cu. m)
268 (7.6) ~106 (3) 154 (4.3) 228 (6.4)
Operational Mass (lbs) 2354 ~800 227 1200
Peak Power at max capability
2400 W 900W 60W 60W(includes laptop pwr)
Annual Mx Time (hrs) 18 31 4 38
Annual Usage Time (hrs for 3 crew)
~375 ~375 ~181 (not tracked by hours)
Requires additional Stowage volume?
Y Y Y Y
Has Software? Y Y Y Y
Has VIS? Y Y Y Y
* Volume includes installed/deployed hardware + human dynamic envelope
Exercise Design & Lessons Learned
6
Overview of Lessons Learned• Fail Operable • Scheduling Exercise• Importance of Life Cycle Testing • Corrective Maintenance• Planning for Software
Exercise Design & Lessons Learned 7
Plan for Arusha Exercise• Analyze Conditions Of Greatest RiskA lack of exercise capability for an extended timeframe is reason to bring the crew home and cancel the mission
• Prioritize Features and Subsystems by Protective Benefit
• Recommend Top Solution(s) with Full List of Alternatives/Contingency Measures
Exercise Design & Lessons Learned 8
Greatest Risk: Mission Abort
3 Criteria are proposed with quantities yet to be determined
• Consecutive Days without Exercise Countermeasures• 2 weeks, other?
• Cumulative Days (%) without Exercise Countermeasures• 33% of mission days by the end of week 6 and cont’d to mission
completion?
• Minimum combination of Exercise Countermeasures• Cardiovascular/strength training ratio (CSR) over the same time
frame?
Exercise Design & Lessons Learned 9
Workday Availability Analysis• Condition 1: Nominal Availability
A. Stationary Rover vs. Moving Rover Blackout DaysImplication of exercise while rover is in motion could be development of a VIS: Vibration Isolation System
B. Hyper Stacking Exercise CountermeasuresNeed to discover full-size interchangability or modular swap out design alternatives
C. Exercise Prescription Review
D. Planned Maintenance Scheduling (Hardware & Software)
• Condition 2: Reduced AvailabilityE. Priority Ops List – Activities that take precedence over exercise
F. Adjacent Nods Conflict Analysis – Activities in neighboring nodes that violate the exercise activity space envelope
Exercise Design & Lessons Learned 10
Team Invitation• Skill sets desired
• Architecture• Structures• VIS: Vibration Isolation (maybe)• Logistics/Mission Ops• Space/Life Sciences or Exercise Physiology• Sustaining Engineering• Software• Power• Hardware (me + anyone interested)
• Team size desired – 7• Minimum team size – 3
Exercise Design & Lessons Learned 11
Exercise Equipment Design
All flight exercise equipment tends to be composed of the following subsystems:
Technology concepts to improve each of these areas are being proposed.
Human-to-Machine Interface (e.g. handles, harnesses, control panel, etc.)
Machine
Software (e.g. firmware, laptop software, etc.)
Vibration Isolation System/Mounting Hardware
Crew Monitoring Equipment (e.g. for heart rate, ECG, etc.)
Support Equipment (e.g. mx, calibration equip, spares)
Exercise Design & Lessons Learned
12
Systems IntegrationCoordination during mission concept phase prior to vehicle development needs to include Exercise Countermeasures inputs for strategy and initial vehicle design requirements planning.
Environmental Control & Life Support System – for regulation of localized ppO2, ppCO2, humidity, air flow, heat, odors
Structures & Mechanics System – for interface reinforcement, vehicle vibration and harmonic concerns
Acoustics System – for planning noise and equipment placement Vehicle Stowage – for planning stowage volume for regular use items, maintenance items and
spares Power System – for planned hardware power usage Avionics/Software – for planned data communications Transfer Vehicle Logistics – for upmass (and downmass), volume, hatch constraints
coordination Flight Crew Equipment System – for coordinating responsibility for exercise clothing and tools
delineations
(Countermeasures System (CMS) is responsible for integrating Vehicle Systems, International Partners, Countermeasures Hardware Providers, Safety and Mission Assurance, Operations, Medical and Research for the corresponding program)
Exercise Design & Lessons Learned
13
Some Lessons Learned
Risk A lack of exercise
capability for an extended timeframe is reason to bring the crew home and cancel the mission
Lessons Learned Fail Operable Scheduling Exercise Importance of Life Cycle
Testing Corrective Maintenance Planning for Software
Exercise Design & Lessons Learned
14
Fail Operable
Observed ALL exercise equipment has had failures in some manner during its
use on ISS. Hardware designs have allowed for redundant capability for
continued crew exercise ARED Instrumentation Box failure and CEVIS Control Panel
failure are designed to operate without power Both TVIS and T2 allow for passive modes in the case of a motor
failure Most of ARED cable exercises may also be performed with bar
Lesson Learned Design to fail operable where possible Provide alternate equipment to meet physiological needs in case of
total failure
Exercise Design & Lessons Learned
15
Scheduling Exercise Observed
Scheduling exercise tends to be the primary driver on how the rest of the day’s timeline is constructed.
Of 6.5 hours available time, aerobic exercise equipment usage requires about 1 hour/crew/day and resistive exercise requires about 1.5 hrs/crew/day.
Individuals have preferred times of day and order for exercises Exercise may be constrained by co-located operations and vehicle
structural constraints (e.g. re-boosts, docking, etc.)
Lessons Learned More equipment provides more operational flexibility Either design the location for the equipment to avoid co-located
operations or vehicle constraints, or have multiple locations for exercise equipment.
Research may require additional scheduling constraints Hardware should be designed so as not to be the limiting factor on
scheduling (e.g. thermal or powered-on constraints)
Exercise Design & Lessons Learned
16
Importance of Life Cycle Testing Observed
Very limited life cycle testing was originally performed on TVIS, and subsequently TVIS required numerous, unexpected on-orbit corrective maintenance activities.
Life cycle testing is MUCH more expensive on-orbit than on the ground
Designers can be overconfident in believing their equipment will perform reliably
Life cycle testing is only as good as its ability to replicate actual on-orbit usage and environment
Life cycle testing performed on ARED, T2 and TVIS SLDs identified most of the limited life issues during development phase and subsequently had far fewer unexpected on-orbit corrective maintenance activities.
Lesson Learned Life cycle testing is mandatory if you want reliability and insight into performance and
maintenance needs. Test as you fly; Fly as you test Life cycle testing should be performed on flight-identical hardware; Workmanship
variability can invalidate your life-cycle test results Mechanical simulation of exercise can be an inadequate representation of actual
human usage Human usage is unpredictable and can induce unexpected failure modes
Exercise Design & Lessons Learned
17
Corrective Maintenance
Observations Unexpected failure modes can (and will) occur (e.g. bearings,
wire ropes, control boards, etc.) If no (or limited) ORU spares available, sub-ORU sparing and
repair may be preferred. Without design for sub-ORU repair capability, repair becomes
more complex if possible.
Lesson Learned Design for sub-ORU level repair (e.g. swappable bearings,
connectors instead of soldering) Design with commonality in mind for parts and available
tooling Provide sub-ORU spares
Exercise Design & Lessons Learned
18
Planning for Software
Observed ALL exercise equipment (except unpowered iRED) has had Control Panels
and data transfer requirements
ALL software (except for TVIS) has required subsequent updates after delivery
Frequent cause due to inadequate development schedule prior to delivery
ALL equipment has experienced regular data transfer issues (both human and technical)
Lesson Learned Adequately plan for software development and testing
Consciously design for wired vs. wireless vs. sneaker-net (not recommended)
A single control panel/laptop platform with equipment-specific software will allow for cross-equipment redundancy (and minimize sparing)
Exercise Design & Lessons Learned
19
Backup - Acronyms
ARED – Advanced Resistive Exercise Device
CEVIS – Cycle Ergometer with Vibration Isolation Stabilization
CMS – Countermeasures System
ECG – Electrocardiogram
iRED – interim Resistive Exercise Device
Mx – Maintenance
ORU – Orbital Replacement Unit
RSA – Russian Space Agency
VELO – Russian Ergometer
T2 – Second Treadmill
TVIS – Treadmill with Vibration Isolation Stabilization
USOS – US On-Orbit Segment
VIS – Vibration Isolation Stabilization
Exercise Design & Lessons Learned
20