1Arlington Town Center Pedestrian Plan

Arlington Town Center Pedestrian Plan

Town BoardJanuary 11, 2017

Poughkeepsie-Dutchess County Transportation Council

2Arlington Town Center Pedestrian Plan

Plan Objectives

Improve pedestrian access to the Town Center

Enhance the pedestrian experience in Arlington

Establish a vision for what the Town Center could look like

Focus: Create a walkable, pedestrian-friendly Main Street

3Arlington Town Center Pedestrian Plan

2010/11: Village of Rhinebeck Subcommittees for research & outreach, trees,

construction & finance, code enforcement

New crosswalks; sidewalk repairs

2012/13: Hyde Park Town Center Economic development/commercial center

New sidewalks; TAP & CDBG funding; zoning

2013/14: Pine Plains Town Center Coordinated with Town’s trail planning process

Sidewalk repairs

2016/17: Arlington Town Center Worked with Business Improvement District (BID)

Results TBD

PDCTC’s Sidewalk Inventories

4Arlington Town Center Pedestrian Plan

Work Program

Organize Pedestrian Task Force

- Liaison between Town, BID, & PDCTC

Conduct Sidewalk Inventory

- Identify conditions and issues

- Global Positioning System (GPS) data

Review Town Plan, Other Plans, & Zoning

Develop Pedestrian Plan

- Plan with prioritized recommendations

- Maps and GIS files

Solicit Public Input

- Street Fair; BID Presentation

- Final Plan presentations

5Arlington Town Center Pedestrian Plan

Project Milestones

BID request: Spring 2015

Town Resolution, Task Force formed: Fall 2015

Scoping Meeting: March 2016

Sidewalk Inventory: April/May 2016

Task Force meetings: Mar., Jun., Sep., Oct., Dec. 2016; Jan. 2017

County DPW meetings: July 2016

NYSDOT Region 8 meeting: Aug. 2016

Draft Recommendations: summer - fall 2016

Feedback & Revisions: December 2016 - January 2017

6Arlington Town Center Pedestrian Plan

7Arlington Town Center Pedestrian Plan

Key Data Elements

Condition: Excellent, Good, Fair, Poor/Unusable; or No Sidewalk

Issues: Broken, Lifted, Obstruction, Clearance, Removed, Crumbled, Other

Amenities: Street trees, street lamps, benches, trash cans, bike racks

Other Data Elements

Sidewalk width & material

Buffer width & material

Crosswalk locations & type

Curb ramps; detectable warnings

Pedestrian signals & pushbuttons

Commercial driveways

Comments; photos

Sidewalk Inventory

8Arlington Town Center Pedestrian Plan

Sidewalk Conditions

Excellent/Good Fair Poor/Unusable

Very few/some improvements needed

Significant improvements needed Sidewalk should be replaced

9Arlington Town Center Pedestrian Plan

Sidewalk Condition

10Arlington Town Center Pedestrian Plan

Sidewalk Issues

(Main St) (Haight Ave)(N. Grand Ave)

(Fairmont Ave)(Fairmont/Haight)

CrumbledLifted

ClearanceObstruction Removed

(Lagrange Ave)

Broken

11Arlington Town Center Pedestrian Plan

12Arlington Town Center Pedestrian Plan

Most sidewalks are in good condition

─ Exceptions: Jones/Springside; parts of Main St,

Fulton Ave

Lack of connecting sidewalks north of Maple St

Very few marked crosswalks

─ Especially across Main St, Haight, Maple

Many pedestrian signal issues

─ Signage, button placement, signal timing

Curb ramp issues

─ Missing ramps; not flush; missing warning strips

Field Observations

13Arlington Town Center Pedestrian Plan

Many driveways and parking lots

─ Opportunities for more pedestrian-oriented land use

Few/inconsistent pedestrian amenities

─ Lack of benches, bike racks,

trash/recycling cans, street trees

─ Opportunity to promote the Arlington

‘brand’

Many people bicycle on the sidewalks

Very little transit signage/information

Field Observations

14Arlington Town Center Pedestrian Plan

Sidewalk Issues

15Arlington Town Center Pedestrian Plan

16Arlington Town Center Pedestrian Plan

17Arlington Town Center Pedestrian Plan

18Arlington Town Center Pedestrian Plan

Plan Outline

3 key intersections:- Main/Grand

- Main/Raymond

- Main/Fairmont

Main Street corridor

Town Center Infrastructure

Bicycle Access

Transit Access

Public Space

Land Use

Parking

Policies & Programs

19Arlington Town Center Pedestrian Plan

Issues

- Safety

- Incomplete crosswalks

- Incomplete sidewalks

- No pedestrian signals

- Many driveways

- Gateway?

Key Intersection 1:Main St & Grand Ave

21Arlington Town Center Pedestrian Plan

Construct a roundabout

- Improve safety; improve traffic flow

- Add crosswalk (west side)

- Add sidewalk (SW corner)

- Consolidate driveways

- Create a gateway to Arlington, Town, and City

- Longer-term: opportunity for more pedestrian-oriented buildings

Main St & Grand Ave:Recommendations

22Arlington Town Center Pedestrian Plan

Main St & Grand Ave:Existing View

23Arlington Town Center Pedestrian Plan

Main St & Grand Ave:Future Vision

24Arlington Town Center Pedestrian Plan

Issues

- Signal timing

- Crosswalk signage

- Pushbutton locations

- Drainage at curb ramps

- Empty corners

Key Intersection 2:Main St & Raymond Ave

25Arlington Town Center Pedestrian Plan

Main St & Raymond Ave:Recommendations

Remove all-pedestrian signal phase

Fix crosswalk signage & pushbuttons

Improve drainage

Intermodal hub: Bus stop with shelter; transit kiosk; bike parking

Public space/plaza?

Longer-term: Opportunity for more active uses

26Arlington Town Center Pedestrian Plan

Issues

- Broken/lifted sidewalks

- Poor ramp conditions

- Old/confusing crosswalk signage

- Gateway: Empty corners

Key Intersection 3:Main St & Fairmont/Taft Ave

27Arlington Town Center Pedestrian Plan

Repair/replace sidewalks & curb ramps

Update crossing signage & pushbuttons; extend crossing time

Mid-term: plaza on northeast corner

Longer-term: pedestrian-friendly gateway building on southwest corner

Main St & Fairmont/Taft Ave:Recommendations

28Arlington Town Center Pedestrian Plan

Repair/replace sidewalks & curb ramps

Update crossing signage & pushbuttons; extend crossing time

Mid-term: plaza on northeast corner

Longer-term: pedestrian-friendly gateway building on southwest corner

Main St & Fairmont/Taft Ave:Recommendations

29Arlington Town Center Pedestrian Plan

Issues

- Fair-Poor sidewalk conditions

- Few marked crosswalks

- Lack of pedestrian amenities

- Wide street

- Many driveways

- Auto-oriented land uses

Main St Corridor

30Arlington Town Center Pedestrian Plan

Short Term: Repair/replace sidewalks

Mark crosswalks across side streets

Install County Road shields, Share the Road signs

Medium Term: Street redesign: widen sidewalks & buffers; stripe/mark parking lane;

shared lane markings (sharrows)

Add crosswalks and curb extensions on Main Street

Install amenities: street trees, benches, lights, trash/recycling, tables/chairs, bike racks

Long Term: Redevelop/redesign auto-oriented uses; infill development

Consolidate driveways; share parking

Main St Corridor:Recommendations

31Arlington Town Center Pedestrian Plan

Main St Corridor:Sidewalks & Crosswalks

Repair/Replace sidewalks

Mark crosswalks

32Arlington Town Center Pedestrian Plan

Main St Corridor:Street Redesign

5’ 2’ 7.5’ 14.5’ 14.5’ 7.5’ 2’ 5’

6’ 4.5’ 7.5’ 11’ 11’ 7.5’ 4.5’ 6’

Widen sidewalks and/or buffers; stripe parking lane; mark sharrows

Install street trees, benches, lights, trash/recycling, tables/chairs, bike racks

33Arlington Town Center Pedestrian Plan

Main St Corridor:Land Use Opportunities

Consolidate driveways

Redevelop auto-oriented land uses

34Arlington Town Center Pedestrian Plan

Main St Corridor:Land Use Opportunities

35Arlington Town Center Pedestrian Plan

Main St Corridor:Land Use Opportunities

36Arlington Town Center Pedestrian Plan

Main St Corridor:Pedestrian-Friendly Uses/Buildings

37Arlington Town Center Pedestrian Plan

Main St Corridor:Existing View

38Arlington Town Center Pedestrian Plan

Main St Corridor:Future Vision

39Arlington Town Center Pedestrian Plan

Short Term: Repair/replace sidewalks, pedestrian signals, & signs Add detectable warnings on curb ramps Mark additional crosswalks Collegeview/Fairmont all way stop

Medium Term: Fill sidewalk gaps; add a Taft Ave sidewalk Install missing curb ramps; repair others Add controlled crossings on Maple St and Haight Ave

Long Term: Extend the Collegeview Ave sidewalk to Vassar’s north gate Install additional sidewalks Replace diagonal curb ramps Formalize the Collegeview-Lagrange cut through Redesign Maple St and Haight Ave

Town Center Infrastructure:Recommendations

40Arlington Town Center Pedestrian Plan

41Arlington Town Center Pedestrian Plan

Bicycle Access: Install bicycle parking Create a bicycle boulevard network Sign a rail trail connection

Transit Access: Increase awareness of transit service

(shelters, maps, schedules)

Public Space: Activate the triangle plaza (Raymond/Fulton) Develop/install an Arlington streetscape amenities package Plant additional street trees Create a plaza on the Vassar Alumnae House lawn

Land use: Pursue land use changes to support walkability

Town Center: Other Recommendations

42Arlington Town Center Pedestrian Plan

Conduct a Town Center parking study (supply/demand analysis)

Implement a parking management plan (enforcement, permits, signage, pricing)

Parking:Recommendations

43Arlington Town Center Pedestrian Plan

Zoning: Strengthen use of the ATC zoning code

Design Standards & Tools: Clarify applicability of design standards

Create a visual design ‘pattern book’

Develop a façade improvement program

Consider an Architectural Review Board

Site Design: Remove Drive-In Overlay District

Provide flexible parking standards; require rear or side parking

Policies & Programs:Recommendations

44Arlington Town Center Pedestrian Plan

Sidewalk Construction: Develop a capital plan for sidewalk

construction & maintenance

Enforce sidewalks standards in site plan reviews and field inspections

Education/Encouragement: Educate people on safe walking and

bicycling; evaluate sidewalk bicycling

Consider a Safe Routes to School program

Implementation: Adopt the Town Center Pedestrian Plan

Create a permanent Arlington Pedestrian Task Force

Policies & Programs:Recommendations

45Arlington Town Center Pedestrian Plan

Implementation: Funding

Local

General funds/Capital Program/CHIPS

Local bonds

Private

Development conditions of approval

Public-private partnerships; Cost sharing with property owners

Non-profit grants; Foundation grants

County & State

Community Development Block Grants

County DPW capital projects/bonds

NYS Multi-Modal program; Legislative Discretionary Funds

Consolidated Funding Application (CFA)

46Arlington Town Center Pedestrian Plan

Implementation: Funding

Federal

National Highway Performance Program (20% local match)

Surface Transportation Block Grant Program(20% local match)

Surface Transportation Block Grant Program Set-aside (20% local)

Highway Safety Improvement Program

FTA Section 5307 (transit enhancements)

TIGER Grants

47Arlington Town Center Pedestrian Plan

Present plan to BID & Town Planning Board (January)

Final Task Force meeting (January 31)

Provide final plan and supporting files to Town & BID

Next Steps

48Arlington Town Center Pedestrian Plan

Contact Information

Emily Dozier, Senior PlannerPoughkeepsie-Dutchess County Transportation Council

27 High Street, 2nd FloorPoughkeepsie, NY 12601

(845) 486-3600Email: [email protected]

Internet: http://www.dutchessny.gov/pdctc.htm