28
Are You Getting the Most from Your Quality Engineer? Presented by Charles B Robinson Certified Lead Auditor / Senior Quality Engineer Quality Assurance & Risk Management Services, Inc.

Are You Getting the Most from Your Quality Engineer?...Quality Engineer ¾Confirm that all non-conformances have been addressed and closed. ¾Verify that any mitigation plans have

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • Are You Getting the Most from Your Quality Engineer?

    Presented by

    Charles B RobinsonCertified Lead Auditor / Senior Quality Engineer

    Quality Assurance & Risk Management Services, Inc.

  • This session is intended to provide an outline of how Quality Engineering (QE) should be adding value during the Life Cycle phases of a Project.

    This session will:

    Correlate the Life Cycle model with NASA Procedural Directives (NPD’s), NASA Procedural Requirements (NPR’s), AS9100, and the QE Disciplines

    Explain a QE’s mission assurance contribution to processes and procedures during the project life cycle

    Provide a reference tool that QE’s can use during the Life Cycle of a project.

    Provide an understanding of how a project has embraced the mission assurance aspects of AS9100D from a QE's perspective

    Software Disciplines are not addressed in this Session

    Purpose

  • AS9100Life Cycle

    Mission AssuranceRequirements

    NPD’s & NPR’s

    Competency Wheel

    NASAQuality Engineers

    Supportive Systems

  • PLAN DO CHECK ACT4

    Context of Organization

    5Leadership

    6Planning

    7Support

    8Operation

    9Performance Evaluation

    10Improvement

    No Requirements1

    Scope2

    Reference3

    Terms & Definitions

  • Conduct QualityEvaluations &Data Analysis

    PerformQuality Assurance

    Management& Planning

    Define & PerformInspection Testing& Acceptance

    Activities

    Conduct Procurement

    QualityEngineering

    Define &ImplementProduction,Material &

    Process Controls

    ImplementProblem Reporting& CorrectiveActions (PRACA)

    AssuresAdequateDesign &

    DevelopmentControls

    QualityEngineer

    For more detail contact:Michael P. Kelly

    NASA Safety Center302-286-0662

    [email protected]

    mailto:[email protected]

  • NASA Life-Cycle Phases

    Phase CFinal Design

    & Fabrication

    Phase FCloseout

    Phase EOperations

    & Sustainment

    Phase BPreliminary Design &

    Technology Completion

    Phase DSystem

    Assembly,Integration &

    TestLaunch

    Phase AConcept & Technology

    Development

    Pre-Phase AConcept Studies

    Project Life-Cycle Phases

    OR

    R

    FRR

    PLA

    R

    CER

    R

    Key Decision Points

    MC

    R

    SR

    R

    PD

    R

    CD

    R/

    PR

    R SIR

    TRR

    DR

    SA

    R

    PFA

    R

    Launch

    Formulation ImplementationApproval

    MCR – Mission Concept ReviewSRR – System Requirements ReviewMDR – Mission Definition ReviewSDR – System Definition ReviewPDR – Preliminary Design ReviewCDR/PRR – Critical Design Review / Production Readiness ReviewSIR – System Integration Review

    TRR – Test Readiness ReviewSAR – System Acceptance ReviewORR – Operations Readiness ReviewFRR – Flight Readiness ReviewPLAR – Post Launch Assessment ReviewCERR – Critical Events Readiness ReviewPFAR – Post-Flight Assessment ReviewDR – Decommissioning Review

    MD

    RS

    DR

    NPR 7123.1NASA Systems

    EngineeringProcesses and Requirements

    NPR 7120.5NASA Space

    Flight Program & Project Mgmt. Requirements

  • SRR – System Requirements ReviewTo evaluate whether the functional and performancerequirements defined for the system are responsive tothe program's requirements on the project andrepresent achievable capabilities.

    The Quality Engineer understands the System Definition to assure their future activity is focused on mission success

    Understand initial requirements - End Items functional baselineUnderstand clarity of system definition - architectural level of designCreate the SMA quality level requirements, e.g., develop the SMA Plan. Identify workmanship standards, critical technology, long lead items.NASA Advisories (NPR 8735.1) and GIDEP are addressed in the Safety & Mission Assurance PlanCommunicate concerns (schedule, technology, long lead items, etc.)

    I – Initiate, P – Preliminary, B – Baseline, U – Update, F- Final -&- 1 – Develop, 2 – Research & Review Requirements

    Life Cycle Phase A B C D E FAS9100

    ↓ NPR 7120.5 (Sections) ↓ SRR MDRSDR PDRCDRPRR SIR TRR ORR FRR DR

    Risk Management Plan (G-3.3) P/2 B/1 U/1 6.1, 8.1.1Risk Mitigation Plan (F-7.0) I/2 U/2 U/2 U/2 U/2 U/2 U/2 8.2.2Safety & Mission Assurance Plan (G-3.2) P/1 B/1 U/1 U/1 U/1 6.0Material Requirements Plan (NPR 8730.2) I/2 U/2 U/2 U/2 8.1, 8.1.4Configuration Management Plan (G-3.14) P/2 B/2 U/2 8.1.2Acquisition Plan (G-3.4) P/2 B/2 8.4Technology Development Plan (G-3.5) P/2 B/2 8.2.2.d

  • MissionSuccess

    Environment

    Ground

    Suppliers

    University

    Workmanship

    Training

    Mission AssuranceStaff

    Material

    Length of Mission

    Instruments

    New Supplier

    Documents

    Spares

    Software

    Reliability

    GIDEP

    SOW

    LOD

    Durationof Mission

    Components

    Safety & Mission Assurance Plan

    Problem / Failure Reports from similar Projects

    Experienced?

    SupplierHistory

    Equipment

    Mandatory Inspection

    Points

    Areas to consider to prepare for your involvement

    Launch vehicle

    Spacecraft

    On‐Site Personnel ?

    Safety

    Materials

  • High Risk Electronic

    Parts [ERAI, Inc.]

    GIDEP Information

    [NANADARTS]

    NASA Advisories

    [NANADARTS, NARS]

    Customs & Border

    Protection C/F Parts Seizures

    [CBP]Commodity Information

    [SAM]

    General Supplier

    Information [DLIS]

    PQA “Surveyed

    Supplier” Info [GRC, JSC]

    Supplier Information

    Surveys [Supplier Provided]

    Audit Reports [NASA Audits]

    Debarred Suppliers

    [DLIS]

    Supplier QMS Certifications[Audit Teams,

    Suppliers, OASIS]

    Supplier Ratings

    [DCMA, Navy, SAS]

    Supplier Assessment System (SAS)

    NPR 8735.2, ¶2.6.3.5

    SAS Administrator - [email protected] Web site - http://sas.nasa.gov/

  • MDR (R) – Mission Definition ReviewSDR (H) – System Definition Review

    The Quality Engineer.Knowing the project's mission/system definition and associated plans,analysis the risks, identifies the resources needed for mission assurance,and starts a compliance matrix.As a component of the Verification & Validation Plan, Mandatory InspectionPoints are identified by the QE.Identifies any concerns prior to beginning Phase B.

    To evaluate the credibility and responsiveness of theproposed mission/system architecture to the programrequirements and constraints, including available resources. To determinewhether the maturity of the project's mission/system definition and associatedplans are sufficient to begin Phase B.

    I – Initiate, P – Preliminary, B – Baseline, U – Update, F- Final -&- 1 – Develop, 2 – Research & Review Requirements

    Life Cycle Phase A B C D E FAS9100

    ↓ NPR 7120.5 (Sections) ↓ SRR MDRSDR PDRCDRPRR SIR TRR ORR FRR DR

    Risk Management Plan (G-3.3) P2 B1 U1 6.1, 8.1.1Safety & Mission Assurance Plan (G-3.2) P1 B1 U1 U1 U/1 U/1 6.0

    Verification & Validation Plan (G-3.9) P2 B2 U2 U2 8.4.2, 8.4.3, 8.5.1.m

  • Baseline the Safety & Mission Assurance Plan (SMAP)

    QEStart

    GSFC ‐ 380‐WI‐7120 1 1AProject and or Program Mission Assurance Requirements (MAR) Preparation – Figure 1

  • PDR – Preliminary Design ReviewTo evaluate the completeness/consistency of theplanning, technical, cost, and schedule baselinesdeveloped during Formulation. To assess complianceof the preliminary design with applicable requirements and to determine if theproject is sufficiently mature to begin Phase C.

    The Quality EngineerReviews the flow-down requirements to assure they are properly identifiedincluding workmanship standards, NASA Advisories/GIDEP, etc.Confirm the preliminary design is sufficiently mature to protect missionassurance, including schedule.Identify potential risk using FMEA as appropriate.Contribute to the initial Hazard Analysis

    I – Initiate, P – Preliminary, B – Baseline, U – Update, F- Final -&- 1 – Develop, 2 – Research & Review Requirements

    Life Cycle Phase A B C D E FAS9100

    ↓ NPR 7120.5 (Sections) ↓ SRR MDRSDR PDRCDRPRR SIR TRR ORR FRR DR

    Mishap Preparedness and Contingency Plan (NPR 8621.1) P/1 U/1 B/1 U/1 8.2.1

    Safety Data Packages (NPR 8715.7) I/1 U/1 F/1 7.3, 8.1.3

    ELV Payload Safety Process Deliverables (NPR 8715.7) P/1 P/1 B/1 8.1.3

    Safety & Mission Assurance Plan (G-3.2) P/1 B/1 U/1 U/1 U/1 U/1 6.0

  • Failure Mode & Effect Analysis (FMEA) – Screening Process

    FMEA

    NASA, National Space Transportation System (NSTS) 22206, Req’ts. for Preparation & approval of FMEA & Critical Items List (CIL) – Figure 3-2

    Goddard Space Flight Center (GSFC)-FAP-322-208-FMEA-Draft – Functional, Design, Interface, Software, GSE, and Process FMEA instructions – Figure 1-2

  • 0%2%4%6%8%

    10%12%14%16%18%

    Review the Corrective Action history of the department or supplier to identify weaknesses that should be mitigated.

    The above are the combined supplier audit results performed by a NASA Centerfrom 2Q2015 to 1Q2016

  • CDR – Critical Design ReviewPRR – Production Readiness Review

    To evaluate the integrity of the project design and itsability to meet mission requirements with appropriatemargins and acceptable risk within defined project constraints, including

    available resources. To determine if the design is appropriately mature tocontinue with the final design and fabrication phase.

    I – Initiate, P – Preliminary, B – Baseline, U – Update, F- Final -&- 1 – Develop, 2 – Research & Review Requirements

    The Quality Engineer.Input Mandatory Inspections as appropriateComplete the Hazard Analysis and confirm controls are in placeConfirm the Test Plan is in placeValidate the requirements for integration are in place (if applicable)

    Life Cycle Phase A B C D E FAS9100

    ↓ NPR 7120.5 (Sections) ↓ SRR MDRSDR PDRCDRPRR SIR TRR ORR FRR DR

    Integration of systems P/2 U/2 4.4.1

  • Product Integration Process – NPR 7123.1, Figure C-7

  • SIR – System Integration ReviewTo evaluate the readiness of the project andassociated supporting infrastructure to begin systemAssembly Integration & Test (AI&T), evaluate whetherthe remaining project development can be completedwithin available resources, and determine if the projectis sufficiently mature to begin Phase D.

    I – Initiate, P – Preliminary, B – Baseline, U – Update, F- Final -&- 1 – Develop, 2 – Research & Review Requirements

    The Quality Engineer Review documentation prior to testing and/or integration to assure compliance.Verify compliance to the Test Plan

    Life Cycle Phase A B C D E FAS9100

    ↓ NPR 7120.5 (Sections) ↓ SRR MDRSDR PDRCDRPRR SIR TRR ORR FRR DR

    Mission Operations Plan (G-3.10) P/2 B/2 U/2 6.2Rank Safety Risk Management Process Documentation (H-3.24) B/1 6.1.1, 8.1

  • Subject Sample of areas to review Confirmed by QEFinal Design Change Notices clearly understoodSafety Data Package Assure that mitigations are in placeFMEA Analysis complete and mitigation plans in placeDrawings Reviewed for the ability to manufacture and inspectVerification Plans Mandatory Inspection PointsPQA Supplier flow-down appropriateQA Audit Audits complete and findings satisfiedHazard Analysis Created and hazards understood / mitigatedMission Assurance Requirements

    Risk Assessments addressed, As-built parts list approved…

    Develop a Checklist to assure theMission Assurance areas are covered.

  • TRR – Test Readiness Review

    Ensure that for each planned test or series of tests thetest article (hardware / software), test facility, supportpersonnel, and test procedures are ready for testingand data acquisition, reduction, and control.

    A TRR for each planned test or series of tests ensures that the test article(hardware/software), test facility, support personnel, and test procedures areready for testing and data acquisition, reduction, and control.

    Life Cycle Phase A B C D E F

    AS9100↓ NPR 7120.5 (Sections) ↓ SRR

    MDR

    SDRPDR CDRPRR SIR TRR ORR FRR DR

    NPR 7123.1, Table G-10, TRR Entrance & Success Criteria B/2

    8.3.4.18.4.2

    I – Initiate, P – Preliminary, B – Baseline, U – Update, F- Final -&- 1 – Develop, 2 – Research & Review Requirements

    The Quality Engineer Review and/or contribute to the test proceduresIdentify Mandatory inspection points and assure they are incorporated into the test documents.Develop a plan to validate/witnessing test results (LOD for off-site, on-site SMA plan)

  • Documented, Accepted, Configuration Control, & Communicated

    A Sample of “Things” that need to be in place.

  • ORR – Operations Readiness ReviewTo evaluate the readiness of the program, including itsprojects, ground systems, personnel, procedures, anduser documentation. To operate the flight system andassociated ground systems in compliance withprogram requirements and constraints during theoperations phase.

    I – Initiate, P – Preliminary, B – Baseline, U – Update, F- Final -&- 1 – Develop, 2 – Research & Review Requirements

    The Quality Engineer Confirm that all non-conformances have been addressed and closed.Verify that any mitigation plans have been satisfied.Validate the “as built” configuration.Confirm all GIDEP’s or NASA Advisories have been addressed.Confirm the Safety Data Package is complete.

    Life Cycle Phase A B C D E FAS9100

    ↓ NPR 7120.5 (Sections) ↓ SRR MDRSDR PDRCDRPRR SIR TRR ORR FRR DR

    Nonconforming Product I/1 U/1 U/1 U/1 8.4Mitigation Plans P/2 U/2 U/2 U/2 8.1.1.d

    As-built Configuration P/1 U/1 U/1 U/1 U/1 8.1.2, 8.3.6, 8.5.2

  • GIDEP ALERT, SAFE-ALERT, Problem Advisory, Agency Action Notice, and NASA Advisory

    Safe AlertsAlertsProblem AdvisoriesAgency Action NoticesLessons LearnedProduct Chang NoticesProduct InformationDMSMSReliability MethodologyFailure AnalysisReliability PredictionsReliability StatisticsFacilities DocumentsComputer TechnologyProcess SpecificationsTest ReportsEngineering ReportsManagement ReportsSoldering TechnologiesTechnical ManualsGeneral MetrologyCalibration Procedures

    FailureExperience

    ProductInformation

    Reliability

    Engineering

    Metrology

    Advisories&

    An overview of GIDEP investigations throughout the Life-Cycle

  • NPR 1441.1E - NASA Records Management Program Requirements,Appendix D: Agency Filing Scheme

    5100 – Procurement (Contracts)5300 – Reliability and Quality Assurance5700 – Safety and Mission Assurance

    The Records Life-CycleNPR 1441.1, Figure 1

    National Archives & Records Administration (NARA)

  • Presented byCharles B. Robinson

    Quality Assurance & Risk Management Services, Inc. / Navarro Engineering Solutions, 22 Highridge DriveAmerican Canyon, CA 94503www.QAandRM.com / www.NavarroES.com

    Email: [email protected]: +1 480.276.7649

    http://www.qaandrm.com/http://www.navarroes.com/mailto:[email protected]

  • Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28