16
Arboricultural assessment & method statement Westminster Ceremonial Street Project, The Green Park Wall Jeremy Barrell BSc FArborA DipArb CBiol FICFor FRICS 30 th July 2018 18214‐AA‐300718‐JB

Arboricultural assessment & method statement

  • Upload
    others

  • View
    15

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Arboricultural assessment & method statement

Arboricultural assessment & method statement Westminster Ceremonial Street Project, The Green Park Wall

 

Jeremy Barrell BSc FArborA DipArb CBiol FICFor FRICS

 

 

 

 

 

30th July 2018 

18214‐AA‐300718‐JB

Page 2: Arboricultural assessment & method statement

  Site location and report purpose 

Page 1/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

Site location 

 

This aerial image is provided courtesy of Google.  The yellow line indicates the approximate site boundary and is illustrative only. 

Report purpose 

This  arboricultural  assessment  report  provides  sufficient  information  for  the  Local  Planning Authority (LPA) to consider the effect of the proposed development on local character from a tree perspective.  It is fully compliant with the BS 5837 advice relating to the planning application stage of the process and it meets national standard planning application validation requirements. 

More specifically, the development proposal is to remove the existing boundary wall and railings along the north side of The Green Park boundary with Piccadilly, and to install a new wall. 

This report includes: 

A  Tree  protection  plan  illustrating  tree  locations,  categories,  the  location  of  the  proposed development, and the proposed tree protection measures. 

An Arboricultural assessment (section 1 of the report) providing an analysis of the tree issues to assist the LPA in assessing the impact on local character. 

An Arboricultural method statement (section 2 of the report) describing how retained trees will be protected and managed during the development activity. 

Appendices (Appendix 1 – Background administrative information and data collection;  Appendix 2 – Tree schedule and explanatory notes;  and, Appendix 3 – QR Codes for SGNs). 

A  companion  document  to  supplement  the  main  report  titled Manual  for  managing  trees  on development sites (Version 2.1), which provides explanations of how retained trees will be managed on site in the form of Site Guidance Notes (SGNs) covering the relevant issues. 

Page 3: Arboricultural assessment & method statement

  1:  Arboricultural assessment 

Page 2/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

1.1  Table 1:  Summary of trees affected and protected by the proposal 

From my review of the constraints and the proposed layout, my assessment of the impact on trees, both during and after development, and those that need protection using special precautions, is summarised in Table 1: 

 British Standard 5837 Category 

A (High quality)  B (Moderate quality)  C (Low quality) 

Remove  None  None  H35 

Prune  None  None  None 

Protect using special precautions See Notes below  All living trees (T1–T18 & T20–T34) 

H = Hedge;  T = Tree 

Note on  types of protection:   All  retained trees will be protected during development by using fencing and ground protection, and only those requiring special precautions to limit the impact of encroachment are listed in Table 1. 

Note on category U trees:  Tree 19 is categorised as U because it is dead and is likely to be removed for management reasons irrespective of any development proposals.  Removal of category U trees is a management decision and not caused by this proposal, so should not be considered a direct impact. 

1.2  Discussion of specific tree issues 

RPA adjustment for all the mature plane 

All the large plane trees close to the proposed activity are on the Piccadilly boundary.  Although there can be little certainty, it is likely that fewer roots extend beneath the road and it would be prudent  to  extend  the  notional  BS  advised  RPAs  on  the  Park  side  to  compensate  for  this.  Realistically, it is likely that all the work areas are within RPAs and this report has been prepared based on that assumption. 

1.3  The impact of tree removals on local character 

No trees are planned to be removed because of this development and so there will be no impact on local character for that reason.  Hedge 35 is scheduled for removal, but this is a matter being managed by The Royal Parks and has not been considered in any detail this report.  It is replaceable and so any impact can be mitigated by new planting. 

1.4  The impact of tree pruning on local character 

At  this  planning  stage,  it  is  not  anticipated  that  any  trees  will  be  pruned  because  of  this development.  There are several low category small trees with small lower branches (less than 5cm diameter) that extend towards some of the work areas.  These may need to be reduced in length or removed to allow access, but they are so small that they will not have any significant adverse impact on tree health or overall appearance.  However, there is a possibility that some pruning may be required as work progresses due to unavoidable damage to roots that has a knock‐on impact on tree stability.  This will be a last resort fall‐back position and, if necessary, the extent of any works will  be  agreed between all  the parties  before  it  is  carried out,  in  accordance with  the protocol described in the arboricultural method statement (see note 2 of section 2.4). 

Page 4: Arboricultural assessment & method statement

  1:  Arboricultural assessment 

Page 3/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

1.5  The impact of works in precautionary areas 

All the proposed works will be within RPAs and that encroachment will be managed, as follows: 

Arboricultural supervision 

All operations that could adversely affect trees will be overseen by the project arboriculturist as explained in section 2 of this report, and in SGN1 Monitoring tree protection. 

Protection of the whole site from compaction using fencing and ground protection 

Although  the  locations  of  the  new  installations  are  shown with  the  yellow  outline  on  the  tree protection plan as the principal precautionary areas, those works could extend out into adjacent RPAs, which extend over the whole site, so care must be taken throughout the site.  It is proposed to work mainly from the street, where the existing hard surfacing will act as ground protection, and to protect the RPAs within the Park through a combination of fencing and ground protection.  The work site will be fenced from the public footpath in the Park by a single continuous fence to prevent work  operations  extending  beyond  it  into  the  Park.    The  precise  location  of  this  fence will  be adjusted at  the time of  installation to account for  low branches on some of the small  trees and some trunks of the larger trees, which may require minor deviations from the location shown on the tree protection plan.  The detail of the final location will be agreed on site with the supervising arboriculturist.  The secondary function of the fencing will be to control access by the public into the work site.   All  the unprotected soil between that  fence and the hard surfacing on Piccadilly shown in blue on the tree protection plan will be protected with ground protection to prevent any soil compaction through foot or mechanical  traffic, and storage.   As an additional precaution to protect  the  trunks of  trees within  the  fencing  from accidental damage,  they will be  individually protected with a robust hoarding. 

More detail on how this will be done is explained in section 2 of this report, and in SGN2 Fencing protected trees and SGN3 Ground protection.  Adhering to this guidance will allow the trees to be retained without any  long  term detrimental  impact on  tree health, and  therefore no significant adverse impact on local character. 

Removal of the existing wall 

The existing boundary wall and railings, and the adjacent hedge will be removed before the new wall is installed.  I understand that the hedge will be removed by The Royal Parks in advance of the main construction works, and so I have not dealt with that issue in this report.  Once the hedge is gone, the wall will be removed using machines and operatives working from the street, taking care to identify and avoid damage to any significant roots during the operations. 

More detail on how this will be done is explained in section 2 of this report, and in SGN8 Removing surfacing and  structures  in RPAs.   Adhering  to  this  guidance will  allow  the  trees  to be  retained without  any  long  term detrimental  impact on  tree health,  and  therefore no  significant  adverse impact on local character. 

Excavating in RPAs 

The replacement wall will be along the same line as the existing wall, but its linear support footings may have to extend slightly deeper than the existing wall footings along its full length.  Additionally, all the new support piers will require significantly deeper footings than the current wall.  The full extent of excavation into undisturbed ground will not be known until the work starts on site, but due to the proximity to large trees, it is possible that conflicts with roots will arise.  It is proposed 

Page 5: Arboricultural assessment & method statement

  1:  Arboricultural assessment 

Page 4/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

to manage these through an agreed customised protocol based on liaison between all the parties on how to react as and when roots are discovered (see Note 2 in section 2.4).  This will involve a combination of design flexibility to adjust structure locations, and controlled root pruning.    If all parties agree that there is no alternative to substantial root pruning, it may be necessary to crown reduce some trees to address stability concerns.  Plane are known to be resilient to significant root and crown pruning, and it is not anticipated that any trees will be lost through the works.  However, the  crown  pruning  my  need  to  be  substantial,  which  would  have  an  adverse  impact  on  local character until the trees recover and grow back to their unpruned size. 

More detail on how this will be done is explained in section 2 of this report, and in SGN7 Excavating in RPAs and SGN10 Installing structures in RPAs.  It is anticipated that adhering to this guidance will allow all trees to be retained without any long term detrimental impact on tree health, but there may need to be some pruning that will temporarily adversely impact on local character. 

Pollution control in RPAs 

Wet concrete will be poured within RPAs and this will need to be carefully managed to ensure that there is no contamination through spillages or seepage out into adjacent soil.  In principle, this will require the excavations to be lined with an impermeable membrane, with similar precautions to contain spillages. 

More detail on how this will be done is explained in section 2 of this report, and in SGN4 Pollution control.  It is anticipated that adhering to this guidance will allow all trees to be retained without any long term detrimental impact on tree health, and therefore no significant adverse impact on local character. 

1.6  Summary of impact on local character 

No trees will be removed because of this proposal, but some may need to be pruned.  One hedge will  need  to  be  removed,  but  this  impact  can  be mitigated  by  new planting.    The  construction activity could affect all  the  trees  if appropriate protective measures are not  taken.   However,  if adequate precautions are specified and implemented through the arboricultural method statement included  in  this  report,  it  is  feasible  for  all  the  trees  to  be  retained  without  any  long  term detrimental impact on tree health, and therefore no significant adverse impact on local character.  If  trees do need to be pruned,  this will affect  local character  in the short  term, but that  impact would reduce over time as the trees recover and grow back to their unpruned size. 

Page 6: Arboricultural assessment & method statement

  2:  Arboricultural method statement 

Page 5/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

2.1  Site Guidance Notes (SGNs) 

This section of the report identifies which trees on this site will be protected and managed, and by what  means.    This  site‐specific  summary  is  supplemented  by  more  detailed  explanations  and descriptions  of  specific  operations  set  out  in  the  accompanying Manual  for managing  trees  on development sites.  That document is a compilation of 12 individual SGNs addressing the following tree  protection  and  management  issues  that  regularly  arise  in  the  construction  phase  of development: 

SGN1 Monitoring tree protection (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn01?stage=Stage) 

SGN2 Fencing protected trees (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn02?stage=Stage) 

SGN3 Ground protection (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn03?stage=Stage) 

SGN4 Pollution control (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn04?stage=Stage) 

SGN5 Site cranes & piling rigs (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn05?stage=Stage) 

SGN6 Height restrictions (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn06?stage=Stage) 

SGN7 Excavating in RPAs (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn07?stage=Stage) 

SGN8 Removing surfacing and structures in RPAs (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn08?stage=Stage) 

SGN9 Installing/upgrading surfacing in RPAs (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn09?stage=Stage) 

SGN10 Installing structures in RPAs (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn10?stage=Stage) 

SGN11 Installing services in RPAs (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn11?stage=Stage) 

SGN12 Landscaping in RPAs (https://www.barrelltreecare.co.uk/resources/technical‐guidance/sgn12?stage=Stage) 

NOTE:  Each individual SGN can be downloaded by using the links above and the QR Code links in Appendix 3. 

2.2  Identification of areas to be protected 

The  tree  protection  plan  shows  the  areas  where  protective  measures  are  necessary.    The approximate fencing location is shown by the heavy black dashed lines (with flexibility to adjust its precise location on site to account for low branches on some of the small trees and trunks on the larger trees), the principal precautionary areas are shown with a yellow outline, and new temporary ground protection is shown by a blue fill. 

2.3  Arboricultural supervision 

An arboricultural consultant will be appointed to advise on the tree management for the site and to attend: 

a pre‐commencement meeting before any work starts; 

Page 7: Arboricultural assessment & method statement

  2:  Arboricultural method statement 

Page 6/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

regular  supervision  visits  to  oversee  the  agreed  tree  protection,  as  agreed  at  the  pre‐commencement meeting;  and 

further supervision visits, as necessary, to oversee any unexpected works that could affect trees. 

The detail of how the arboricultural supervision will be carried out is explained in SGN1 Monitoring tree protection in the accompanying Manual. 

2.4  Table 2:  Summary of the site operations requiring arboricultural input 

For this site, arboricultural input will be needed for the following operations: 

Brief operation summary  Trees affected Location of detailed 

explanations 

Pre‐commencement meeting:  Meeting on site with all  parties  to  agree  protective  measures,  as described in SGN1.  Will be carried out before any significant site works begin. 

All trees SGN1 Monitoring tree protection 

Installing  fencing and ground protection:   Agreed tree  protection  measures  will  be  installed  and checked, as described in SGN2 and SGN3 (See Note 1 below for more detail).  Will be completed before any significant site works begin. 

All trees fenced, all trunks within the fencing boxed, and ground protection 

Tree protection plan, SGN2 Fencing protected trees, and SGN3 Ground protection 

Pollution control near retained trees:  Any pollution control measures identified during risk assessment will  be  installed  as  described  in  SGN4.    Will  be completed before any potential pollutants arrive on site. 

All trees  SGN4 Pollution control 

Operation of site cranes and piling rigs:  Provision will be made to prevent site cranes and piling rigs damaging trees, as described in SGN5. 

All trees SGN5 Site cranes & piling rigs 

Regular  arboricultural  supervision:    Provision will be  made  to  carry  out  and  record  agreed arboricultural supervision, as described in SGN1. 

All trees SGN1 Monitoring tree protection 

Excavating  in  RPAs:    These  operations  will  be carried out as described in SGN7 (See Note 2 below for more detail). 

All trees  SGN 7 Excavating in RPAs 

Removing surfacing and structures in RPAs:  These operations will be carried out as described in SGN8. 

All trees SGN8 Removing surfacing and structures in RPAs 

Installing structures in RPAs:  These operations will be carried out with care, as described in SGN10. 

All trees SGN10 Installing structures in RPAs 

Removing tree protection:  Protection can only be removed  when  there  is  no  risk  of  damage  to retained trees, as described in SGN1. 

All trees SGN1 Monitoring tree protection 

The operations summarised in this table, and supplemented by the more detailed explanations set out in the SGNs and the rest of this document, form the arboricultural method statement for this site.   The Site Manager will ensure  that  its details and any agreed amendments are known and understood by all site personnel.   Copies of the agreed documents will be available on site.   All personnel  who  could  have  an  impact  on  trees  will  be  briefed  on  the  specific  tree  protection 

Page 8: Arboricultural assessment & method statement

  2:  Arboricultural method statement 

Page 7/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

requirements as part of the site induction procedures.  This requirement will be written into the site management documentation.  If unanticipated issues arise on site not referenced in the above explanations, further guidance on how to manage them can be found in the accompanying Manual. 

NOTE 1:  Fencing and ground protection 

SGN2 Fencing protected trees and SGN3 Ground protection explain the detail of installing fencing and  ground  protection.    The  location  shown  on  the  plan  is  approximate  and  intended  to  be intelligently interpreted on site to fit around the lower branches of the smaller trees and the trunks of  the  larger  trees  with  minimal  adverse  impact  on  them.    The  soil  surfaces  needing  ground protection  slope  to  varying  degrees  throughout  the  length  of  the  site  and  this will  need  to  be accounted for in the ground protection.  This will require a customised solution to provide a level working area like the approaches shown in SGN3 images SGN3‐02 and SGN3‐04. 

NOTE 2:  Protocol of managing the discovery of roots during the excavations 

1. SGN7 Excavating in RPAs explains the detail of excavating in RPAs. 

2. All excavations will be carried out by hand or with air tools as set out in bullet points 7, 8, and 9, in SGN7. 

3. Discovery  of  individual  roots  or  clumps  less  than  2.5cm width  that  need  to  be  cut  can  be removed without consulting the supervising arboriculturist. 

4. Discovery of individual roots or clumps 2.5–10cm in width that need to be cut will be notified to the supervising arboriculturist.  The supervising arboriculturist will decide if the roots can be cut or if a design change needs to be considered. 

5. Discovery of individual roots or clumps greater than 10cm in width that need to be cut will be notified to the supervising arboriculturist.  The supervising arboriculturist will decide if the roots can be cut or if a design change needs to be considered.  If a design change cannot be made and  the  roots  must  be  cut,  a  decision  will  be  made  and  copied  to  The  Royal  Parks  and Westminster City Council to provide an opportunity for input. 

6. If  cutting  large  roots  is  unavoidable,  and  that  operation may  adversely  affect  tree  stability, crown reduction may be necessary to remove significant risks.  These are matters that would be agreed with The Royal Parks and Westminster City Council in advance of any works being carried out. 

2.5  Construction method statement (heads of terms summary) 

A construction method statement is a description of how operations that may affect trees will be carried out to minimise any adverse impact on them.  The details of how the site will be managed are construction and contractual matters that can only be finalised once the post‐consent detailed planning begins.  For that reason, at this stage in the planning process, as explained in clause 5.5.6 of BS 5837, it is normally sufficient to list a heads of terms summary of the issues requiring more detailed consideration once consent is issued.  On this site, those issues are likely to include: 

1. Preparation  of  a  written  site  management  protocol  for  dealing  with  tree  issues,  to  be incorporated  into  formal  site management procedures, and  to  specifically  include  induction training for all operatives related to tree protection. 

2. The order of work on  site,  including  the  installation of protective measures,  the phasing of successive work locations, the removal of existing structures, the installation of new structures, the removal of tree protection, and any necessary reinstatement. 

Page 9: Arboricultural assessment & method statement

  2:  Arboricultural method statement 

Page 8/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

3. Erection and maintenance of tree protection measures. 

4. Who will be responsible for protecting the trees on site. 

5. Detailed proposals for inspecting and supervising the tree protection. 

6. How accidents and emergencies involving trees will be managed, including accidental damage to roots and their treatment. 

7. A schedule of emergency contact numbers relating to trees. 

8. Areas for loading and unloading of materials and storage of materials and plant. 

9. Where site facilities will be located and when will they be installed. 

10. How machinery and equipment (such as excavators, cranes and their loads, concrete pumps and piling rigs) will enter, move on, work on, and leave the site. 

11. Pollution  control  to  specifically  consider  chemical  storage  and  wheel  washing  facilities  in relation to trees. 

12. Recycling and storage of waste in relation to trees. 

13. Details  of  earthworks,  grading  and mounding  and  removal  of  spoil,  including  any  planned lowering or raising of ground levels. 

14. Precise services locations, including the method of excavation when near trees. 

15. How and when any temporary surfacing will be laid and removed. 

16. How post‐construction impacts through compaction to soil near trees will be ameliorated. 

Page 10: Arboricultural assessment & method statement

  Appendix 1:  Background administrative information and data collection 

Page 9/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

A1.1 Table 3:  Background administrative information 

  Background administrative information 

Report date & reference  30/07/18;  18214‐AA‐300718‐JB 

Tree protection plan reference 

BT1 

Instructing client  Conway Consulting Services 

Instructions 

Visit the site, assess the relevant trees, prepare a schedule of their details, describe  the  impact  of  the  proposal  on  those  trees,  and  identify  the  tree protection  issues  in  an  arboricultural  method  statement  with  a  tree protection plan 

Provided documents Topographical survey, drawing number M‐GA‐01‐04‐MFD, received by email on 22nd June 2018, and layout drawing number 238038‐04M 610, received by email on 30th July 2018 

Report author and credentials 

Jeremy Barrell is a Chartered Forester (www.charteredforesters.org) and an AA  Registered  Consultant  (www.trees.org.uk),  and  fully  qualified  to undertake the assessments in this report.  Further details of his credentials can be found at https://www.barrelltreecare.co.uk/assets/Uploads/J‐Barrell‐CV.pdf. 

Report limitations  This report does not consider ecological or archaeological  issues, or any 

other matter beyond the assessment of the trees. 

Technical references 

In  preparing  the  analysis  in  this  report,  we  considered  the  guidance  and advice in the following technical references: 

Climate Change Act (2008) www.legislation.gov.uk/ukpga/2008/27/contents 

Town and Country Planning Act 1990 www.legislation.gov.uk/ukpga/1990/8/contents 

National  Planning  Policy  Framework,  published  by  the  DCLG www.gov.uk/government/publications/national‐planning‐policy‐framework‐‐2 

BS 5837 (2012) Trees in relation to design, demolition and construction – Recommendations,  BSI www.shop.bsigroup.com/ 

BS 8545 (2014) Trees:    from nursery to  independence in the  landscape – Recommendations, www.shop.bsigroup.com/ 

BS 3998 (2010) Tree work – Recommendations, BSI www.shop.bsigroup.com/ 

Trees  in the Townscape:   A Guide for Decision Makers, published by the 

Trees & Design Action Group http://www.tdag.org.uk/  Trees in Hard Landscapes:  A Guide for Delivery, published by the Trees & 

Design Action Group www.tdag.org.uk/  National Joint Utilities Group (2007) Volume 4, Issue 2:  Guidelines for the 

planning, installation and maintenance of utility apparatus in proximity to trees www.njug.org.uk/publications/ 

   

Page 11: Arboricultural assessment & method statement

  Appendix 1:  Background administrative information and data collection 

Page 10/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

A1.2 Table 4:  Data collection 

  Data collection 

Date of site visit  10th July 2018 

People present during site visit 

Jeremy Barrell 

Weather & visibility  Dull, still, and dry, with good visibility 

Limitations to observations 

The  inspection of  the trees  for  the purposes of assessing their condition and work requirements was made on the basis that they will be annually inspected in the future to identify any changes in condition and review the original recommendations.  For these reasons, the tree assessment advice only  remains  valid  for  one  year  from  the  date  that  the  trees  were  last inspected. 

All  observations  were  of  a  preliminary  nature  and  did  not  involve  any climbing or detailed investigation beyond what was visible from accessible points at ground level. 

Observations of trees outside the site boundaries are confined to what was visible from within the site. 

All dimensions were estimated unless otherwise indicated. 

Tree Preservation Orders (TPOs), Conservation Areas, and tree categorisation 

The site is in a Conservation Area. 

Tree location and numbering 

Each tree and hedge was inspected, and the numbering scheme is indicated on the tree protection plan. 

Recording of tree data For each identified tree and hedge, the information collected was recorded on the tree schedule in Appendix 2 and the tree protection plan. 

Compliance of data collection with BS 5837 

The data collection is fully compliant with the advice in subsection 4.4.2 of BS 5837.  When collecting this information, specific consideration was given to any  low  branches  that  may  influence  future  use,  age  class,  physiological condition,  structural  condition,  and  remaining  contribution.    Where appropriate, crown spreads were also noted where they differed from those shown on the provided land survey. 

Calculation of RPAs 

Following the recommendations in Table D1 of BS 5837, the diameter of each tree  was  rounded  up  to  the  next  2.5cm  increment,  with  the  radius  of  a nominal  circle  and  the  resultant  RPA  taken  directly  from  that  table.    This information is listed for each tree in the tree schedule in Appendix 2. 

Page 12: Arboricultural assessment & method statement

Appendix 2: Tree schedule and explanatory notes

Page 11/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

NOTE:  Colour annotation is A & B trees with green background;  C & U trees with blue background;  trees to be removed in red text.  

Tree No Species Height (m)

Diameter (cm) @ 1.5m

Maturity Low Branches Category Notes Tree Works RPA radius

(m) RPA area

(m2)

All retained

trees Carry out safety check

T1 London plane (5030) 30 110* Mature - A - 13.2 547

T2 Thorn sp (5081) 5 15* Maturing - C Small tree - 1.8 10

T3 Crab sp (5080) 4 15* Maturing - C - 1.8 10

T4 London plane 18 52.5 Maturing - A On street - 6.3 125

T5 Thorn sp 6 20* Maturing - C Small tree - 2.4 18

T6 Thorn sp 5 15* Maturing - C Small tree - 1.8 10

T7 Thorn sp (5085) 6 20* Maturing - C Small tree - 2.4 18

T8 Silver-leaved lime 6 12.5* Young - C Small tree - 1.5 7

T9 London plane 12 30* Maturing - C On street, interfering with adjacent tree - 3.6 41

T10 Horse chestnut (5040) 14 42.5* Maturing - B Growing as a group - 5.1 82

T11 Horse chestnut (5042) 13 37.5* Maturing - B Growing as a group - 4.5 64

T12 Catalpa (5044) 16 35* Maturing - B Slightly suppressed by adjacent tree - 4.2 55

T13 London plane 18 50* Maturing - A On street - 6.0 113

T14 Crab sp 6 20* Maturing - C Small tree - 2.4 18

T15 Crab sp 2 5 Young - C Small tree - 0.6 1

T16 Field maple 5 20* Young - C Small tree - 2.4 18

T17 Crab sp 2 5 Young - C Small tree - 0.6 1

T18 London plane (43000) 30 122.5* mature - A - 14.7 679

T19 London plane 10 25 Maturing - U Dead - 3.0 28

T20 London plane (43002) 30 105* Mature - A - 12.6 499

T21 London plane (43003) 30 100* Mature - A - 12.0 452

Page 13: Arboricultural assessment & method statement

Appendix 2: Tree schedule and explanatory notes

Page 12/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

Tree No Species Height (m)

Diameter (cm) @ 1.5m

Maturity Low Branches Category Notes Tree Works RPA radius

(m) RPA area

(m2)

T22 London plane (43004) 30 110* Mature - A - 13.2 547

T23 London plane (43005) 30 107.5* Mature - A - 12.9 523

T24 London plane (43006) 30 97.5* Mature - A - 11.7 430

T25 London plane (43007) 18 50* Maturing - A - 6.0 113

T26 London plane 5 5 Young - C Small tree - 0.6 1

T27 London plane (43009) 30 105* Mature - A - 12.6 499

T28 London plane 25 100* Mature - B Interfering with adjacent tree - 12.0 452

T29 London plane 8 15 Maturing - C Young tree - 1.8 10

T30 London plane (43013) 30 110* Mature - A - 13.2 547

T31 London plane (43014) 30 110* Mature - A - 13.2 547

T32 London plane (43015) 30 82.5* Mature - A - 9.9 308

T33 London plane (43016) 30 97.5 Mature - A - 11.7 430

T34 London plane (43017) 30 102.5* Mature - B Active basal fungal bracket - 12.3 475

H35 Holly sp 2 15 Maturing - C Clipped hedge Fell 1.8 10

 

Page 14: Arboricultural assessment & method statement

  Appendix 2:  Tree schedule and explanatory notes 

Page 13/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

Explanatory Notes 

Abbreviations:   H:  Hedge   T:  Tree 

Botanical tree names:   Catalpa  :  Catalpa bignonioides   Crab  :  Malus sp   Field maple  :  Acer campestre   Holly  :  Ilex sp   Horse chestnut   :  Aesculus hippocastanum   London plane  :  Platanus x hispanica   Silver‐leaved lime  :  Tilia tomentosa   Thorn  :  Crataegus sp 

BS 5837 (2012) compliance:  All data has been collected based on the recommendations set out in subsection 4.4 of BS 5837. 

Tree inspections and site limitations:  Each tree was subjected to a quick visual check level of inspection.  Where there is restricted access to the base of a tree, its attributes are assessed from the nearest point of access.  Climbing inspections are not carried out during this level of inspection and, if heavy ivy is present, tree condition is assessed from what can be seen from the ground.  A separate note is recorded if further investigation may be required to clarify its status. 

Crown spreads:  Crown spread dimensions are not listed in the tree schedule because they are illustrated on the land survey base to all the plans in this document. 

Dimensions:  All dimensions are estimated unless advised as measured. 

Species:  Species identification is based on visual observations.  Where there is some doubt over tree identity, sp is noted after the genus name to indicate that the species cannot be reliably identified at the time of the survey.  Where there is more than one species in a group, only the most frequent are noted and not all the species present may be listed. 

Height:  Height is estimated to provide a broad indication of the size of the tree. 

Trunk diameter:  Trunk diameter is estimated or measured and recorded in 2.5cm increments as advised in BS 5837 Table D1.  It is measured with a diameter tape unless access is restricted, direct measurement is not possible because of ivy on the trunk or the tree is assessed as low quality.  The point of measurement and the adjustments for stem variations are as advised in Figure C1 of BS 5837. 

Maturity:  In planning context, maturity provides a simplistic indication of a tree’s ability to cope with change and its potential for further growth.  For the purposes of this report, young indicates a potential to significantly increase in size and a high ability to cope with change, maturing indicates some potential to increase in size and a medium ability to cope with change, and mature indicates little potential to increase in size and limited ability to cope with change. 

Low branches:  Any low branches that would not be feasible for removal during normal management and should be considered as a design constraint are noted here and explained in the notes. 

Category:  Our assessment automatically considered tree physiological/structural condition (BS 5837, 4.4.2.5h), and  so  these are not  listed separately  in  the  schedule.   Additionally,  the  category accounts  for  the  remaining contribution (BS 5837, 4.4.2.5i) as greater than 40 years for A trees, greater than 20 years for B trees, at least 10 years for C trees and less than 10 years for U trees, so this is also not listed separately in the schedule.  Category A, B, and C trees are automatically listed as sub‐category 1 unless otherwise stated. 

Notes:   Only relevant features relating to physiological or structural condition and low branches that may help clarify the categorisation are recorded.  If there are no notes, then the presumption should be that no relevant features were observed. 

Future tree safety inspections:   Due to the time that may elapse between the original survey and the start of development, all trees should be re‐inspected as part of the standard risk management process before any works start on site.  Our assessment of the trees was carried out on the basis that a re‐inspection would be carried out within a year of the assessment visit and our advice on tree condition must be reviewed annually from the date of that visit. 

Page 15: Arboricultural assessment & method statement

  Appendix 3:  QR Codes for SGNs (Scan with reader to download) 

Page 14/14 

Arboricultural appraisal and method statement for Westminster Ceremonial Street Project, The Green Park Wall 18214‐AA‐300718‐JB  30/07/18 

© Barrell Tree Consultancy 2018 

     

SGN1 Monitoring tree protection  SGN2 Fencing protected trees  SGN3 Ground protection 

     

SGN4 Pollution control  SGN5 Site cranes & piling rigs  SGN6 Height restrictions 

     

SGN7 Excavating in RPAs SGN8 Removing surfacing and 

structures in RPAs SGN9 Installing/upgrading 

surfacing in RPAs 

     

SGN10 Installing structures in RPAs 

SGN11 Installing services in RPAs  SGN12 Landscaping in RPAs 

 

Page 16: Arboricultural assessment & method statement