Budget Timeline

Adoption of Tentative 2011 Budget April 7

Tentative Budget Submitted To StateApril 15

Adoption of Final 2011 Budget May 19

Final Budget Submitted to State June 8

2

Adoption of the tentative budget is required by April 15th. However, changes may be made prior to adoption of the final budget.

Page 3: April 7 Board Worksession Tentative Budget   Final

Where the District Spends Its $

3

Classroom In-struction, Coun-seling, Library, &

Transporting Students75.7%

School Adminis-tration8.6%

Finance, Human Resources, Pur-chasing, Tech-

nology2.7%

Maintenance, Custodial,

Grounds & Utili-ties

12.1%

General Administration0.9%

Page 4: April 7 Board Worksession Tentative Budget   Final

How the District Spends Its $

4

People89%

Things11%

($ in millions)

Electricity, Gas, and Utilities 88.4

Fuel & Vehicle Maintenance 9.9

Textbooks/Supplies 53.2

Property & Liability Insurance 5.0

Classroom Equipment 7.7

Technical Services 7.8

Field Trips 3.2

Postage 2.0

Repairs and Maintenance 4.1

Other Objects* 49.6

Total $230.9

*Other Objects: Legal Services, Financial Services, Professional Services, Staff Development, Training, Travel

Page 5: April 7 Board Worksession Tentative Budget   Final

Reductions in Positions To Date & Planned

5

Central Office

  

FY 2010 FY 2011

 Cumulative Positions

Positions Cut

% of Total in Central Office

Proposed Position Cuts

% of Total in Central Office

Administrators 27 10.2% 19 8.5% 46

Support Staff 231 24.4% 0 0.0% 231

School Based

  

FY 2010 FY 2011  Cumulative Positions

Positions Cut

% of Total in Schools

Proposed Position Cuts

% of Total in Schools

Administrators 16 1.6% 90 8.9% 106

Support Staff 100 1.3% 0 0.0% 100

Licensed 682 3.7% 540 3.2% 1,222

*General Operating Fund Positions

Page 6: April 7 Board Worksession Tentative Budget   Final

Tentative Budget Summary

6

Total General Fund Revenue

Down6.9%

- $ 141 million

Total General Fund Expenditures

Down3.4%

- $ 76 million

The difference is partially made up through use of $40 million in fund balance (due to efficiencies) and $25 million in one-time capital funding.

Page 7: April 7 Board Worksession Tentative Budget   Final

Use of One-Time Sources

7

Revenues Reve

nues

Fund Balance & Other One-

Time Sources

Revenues

OK for temporary downturns in

revenues

Not good to filllong-term shortfalls

Page 8: April 7 Board Worksession Tentative Budget   Final

Assumptions: Tentative Budget① All elementary schools on a nine-month

calendarElementary schools convert from year-round to nine-month as per Regulation 7124

② No changes in employee contract provisions

③ Class sizes in Grades 1-3 increased by 2 students

④ Textbook/supply budgets will be reduced

⑤ Student enrollment will decline slightly

⑥ Fund balance will be used to offset budget reductions

⑦ Administrative positions will be reduced by 10 percent

⑧ Federal Title I funding will be $6.9 million less

8

Page 9: April 7 Board Worksession Tentative Budget   Final

What These Assumptions Mean

① School calendar conversions

$5 million savings

② Employee contract provisions:Step Increases

$26 million costRetirement (PERS)

no change

③ Class sizes in Grades 1-3 (540 positions)

$30 million cut

④ Textbook/supply budgets

$10 million cut

⑤ Student enrollment

no change

⑥ Fund balance

$40 million one-time savings

⑦ Administrative staffing (109 positions)

$12 million cut

⑧ Federal Title I funding

$6.9 million less

9

Page 10: April 7 Board Worksession Tentative Budget   Final

Changes Since Tentative Budget

School calendar changes,other than by regulation,not implemented $12 million

State Department of Taxationupdated property tax estimates 18 million

Additional Shortfall $30 million

10

The following changes occurred after development of the Tentative Budget and will need to be addressed prior to adoption of the Final Budget.

$30 million, if taken from staffing, equates to an additional 428 positions that would need to be cut.

Page 11: April 7 Board Worksession Tentative Budget   Final

Options for Cutting $30 Million

11

1) Reduce salaries (and PERS benefit base)by 1.85 percent

2) Implement furlough days for all employees(4 for licensed, support staff and police; 6 for administrators)

3) Employees share 15 percent of overall costof health insurance

4) Employees share 2.4 percent of overall costof retirement (PERS)

5) Freeze step increases ($26 million)

The following are options for dealing with the remaining $30 million budget deficit (subject to collective bargaining):

$30 million, if taken from staffing, equates to 428 positions that would need to be cut.

Page 12: April 7 Board Worksession Tentative Budget   Final

Positions That Would Need to be Cut

12

540 Teaching positions (raising class sizes by 2 in grades 1-3)

109 Administrative Positions (90 school based,19 central office)

649 Already recommended to be eliminated+ 428 Additional positions to balance ($30

million)

1,077 Total number of positions that would need to be cut

With NO changes to salaries, benefits, or to the work year:

Page 13: April 7 Board Worksession Tentative Budget   Final

Alternative to Recommended Cuts

13

To restore the recommended increase in class size and the reduction in administrative staffing, as well as to accommodate other shortfalls…

…would require a 5.0 percent reduction in all employee salaries…

…and would allow restoration of 649 positions cut to balance the budget

Page 14: April 7 Board Worksession Tentative Budget   Final

For More Information…

Go to…

CCSD.net/finance

14

Page 15: April 7 Board Worksession Tentative Budget   Final

Budget Timeline

Adoption of Tentative 2011 Budget April 7

Tentative Budget Submitted To StateApril 15

Adoption of Final 2011 Budget May 19

Final Budget Submitted to State June 8

15

Adoption of the tentative budget is required by April 15th. However, changes may be made prior to adoption of the final budget.