31
Approach for Estimating a Probable Range of Pit Lake Concentrations for Mine Pits with Sulfide Wall Rock Sarah Doyle; Cory Conrad; Colleen Kelley; Steve Lange; Rick Frechette; Houston Kempton August 14, 2014

Approach for Estimating a Probable Range of Pit Lake

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Approach for Estimating a Probable Range of Pit Lake

Approach for Estimating a Probable Range of Pit Lake Concentrations for Mine Pits

with Sulfide Wall Rock

Sarah Doyle; Cory Conrad; Colleen Kelley; Steve Lange; Rick Frechette; Houston Kempton

August 14, 2014

Page 2: Approach for Estimating a Probable Range of Pit Lake

Outline

• What is a probabilistic model? • Benefits using a probabilistic approach • Methods • Example presentation of results • Limitations and ongoing challenges • Summary

2

Page 3: Approach for Estimating a Probable Range of Pit Lake

Session 2: Tailings Technologies

• Scaling of lab data (temp, grain size, accelerated weathering) • Thermodynamic database: assume constants are correct and that

our system is in equilibrium • Assume complete mixing of ponds • Complex mechanisms (cyanide attenuation, sorption) are simplified.

Some are not modeled (coprecipitation)

3

Limitations of Modeling

• We can model uncertainty using Monte Carlo methods (represent inputs as range of values to get range of outcomes)

• We can avoid scaling issues by using field testing results as much as possible

“All models are wrong, but some are useful” - George E.P. Box, statistician

Page 4: Approach for Estimating a Probable Range of Pit Lake

What is a probabilistic model?

4

0.00

0.10

0.20

0.30

1 2 3 4 5 6 7 8 9 10 11 12Pr

obab

ility

Den

sity

Total Iron [mg/L]

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0 1 2 3 4 5

Pro

babi

lity

Initial Percent Sulfide [%]

0.00

0.05

0.10

0.15

70 71 72 73 74 75 76 77 78 79 80

Pro

babi

lity

Pan Evap Coefficient [%]

Pro

babi

lity

INPUTS OUTPUTS

Page 5: Approach for Estimating a Probable Range of Pit Lake

Benefits of Probabilistic Models

• Probabilistic models may reduce comments on EISs by allowing parties to “agree to disagree”

• Why is this important? – Rosemont (AZ): >43,000 comments; – NorthMet (MN): >50,000 comments; – Average EIS contractor cost for the DOE in 2013:

$2.9 million* – Federal Agencies are moving towards requiring EIS’s

for changes to existing projects

5 *U.S. Government Accountability Office, National Environmental Policy Act: Little Information Exists on NEPA Analyses, April 2014

Page 6: Approach for Estimating a Probable Range of Pit Lake

Benefits of Probabilistic Models

• Increases understanding of project risks – Helps with: closure

cost estimates, alternatives analyses, etc.

• Worst-case scenario isn’t always obvious for complex, dynamic systems

6

Page 7: Approach for Estimating a Probable Range of Pit Lake

Benefits of Probabilistic Models

7 Data from INAP Pit Lake Database

Page 8: Approach for Estimating a Probable Range of Pit Lake

Modeling Methods

8

MODELING

Page 9: Approach for Estimating a Probable Range of Pit Lake

Conceptual Water Balance

9

Evaporation

PIT LAKE

Direct Precipitation

Pit Wall Runoff

Groundwater

BEDROCK

Other Inflows

Page 10: Approach for Estimating a Probable Range of Pit Lake

Conceptual Solute Balance

10

Damaged Rock Zone

Other Inflows

Pit Wall Runoff

Groundwater Oxidation of Sulfide Wall Rock

Evapo-Concentration

Page 11: Approach for Estimating a Probable Range of Pit Lake

Pit Wall Runoff

11

𝑃𝑃𝑃 𝑊𝑊𝑊𝑊 𝑅𝑅𝑅𝑅𝑅𝑅 = 𝐶𝑅𝑅𝐶𝐶𝑅𝑃𝐶𝑊𝑃𝑃𝑅𝑅 ∗ 𝐹𝑊𝑅𝐹 𝑅𝑊𝑃𝐶 + 𝑆𝑅𝑊𝑅𝑃𝐶𝑆 𝑅𝐶𝑊𝐶𝑊𝑆𝐶𝑅 𝑅𝐶𝑅𝑓 𝑆𝑅𝑊𝑅𝑃𝑅𝐶 𝑂𝑂𝑃𝑅𝑊𝑃𝑃𝑅𝑅

Page 12: Approach for Estimating a Probable Range of Pit Lake

Session 2: Tailings Technologies

• Data available for modeling depends on the phase of the project.

12

Available Data

Static Tests • ABA • Whole rock • Leach Tests

(MWMP, SPLP)

• NAG

Kinetic Tests • Humidity

cells

Field Tests • Field barrels • Test plots

Field Data • Site samples

Better Modeling Data

Page 13: Approach for Estimating a Probable Range of Pit Lake

Kinetic Program Comparing FB and HC

• Field barrel acidity greater and faster • Humidity cells have such high flush rates that they do not develop “hot spots”

or acidic micro-environments where the sulphide oxidizing bacteria thrive.

2

3

4

5

6

7

8

9

10-Aug-10 7-Jan-11 6-Jun-11 3-Nov-11 1-Apr-12

Lab

pH

COL 28 - EBX2 (S=1.86%)

HC 1 EBX2 (S=2.04%)

COL 48 - IBX(S=2.10%)HC 2 IBX (S=2.16%)

COL 55-01 - DA(S=1.26%)HC 3 DA (S=1.26%)

COL 19 - H (S=1.12%)

Page 14: Approach for Estimating a Probable Range of Pit Lake

Kinetic Program Comparing FB and HC

• Greater flush of alkalinity in the humidity cells than in the field barrel due to high water infiltration rates and volumes

0.001

0.01

0.1

1

10

100

10-Aug-10 7-Jan-11 6-Jun-11 3-Nov-11 1-Apr-12

Alka

linity

(mg/

kg/w

k) COL 28 - EBX2

(S=1.86%)HC 1 EBX2 (S=2.04%)

COL 48 - IBX(S=2.10%)HC 2 IBX (S=2.16%)

COL 55-01 - DA(S=1.26%)HC 3 DA (S=1.26%)

Page 15: Approach for Estimating a Probable Range of Pit Lake

Kinetic Program Comparing FB and HC

• Greater sulphate release in the humidity cell tests than in field barrels due to lack of secondary mineral precipitation

0.1

1

10

100

1000

10-Aug-10 7-Jan-11 6-Jun-11 3-Nov-11 1-Apr-12

SO4

(mg/

kg/w

k)

COL 28 - EBX2 (S=1.86%)

HC 1 EBX2 (S=2.04%)

COL 48 - IBX (S=2.10%)

HC 2 IBX (S=2.16%)

COL 55-01 - DA (S=1.26%)

HC 3 DA (S=1.26%)

COL 19 - H (S=1.12%)

HC 4 H (S=1.12%)

Page 16: Approach for Estimating a Probable Range of Pit Lake

Solute Release from Sulfide Oxidation

16

• Rate of sulfate formed from oxidation of sulfide wall rock was estimated based on humidity cell data.

• Defined in model by

slope and y-intercept

Page 17: Approach for Estimating a Probable Range of Pit Lake

Solute Release from Sulfide Oxidation

17

• Solute assumed to be released from sulfide oxidation if statistically significant correlation exists between sulfate and the solute in NAG Leachate

• Solute release modeled as ratio to sulfate release.

Page 18: Approach for Estimating a Probable Range of Pit Lake

Solute Release from Sulfide Oxidation

18

• If solute is not correlated to sulfate concentrations in NAG leachate, then it is not released with sulfide oxidation in the model.

• Solute can still be released from pit wall runoff based on leach test results.

Page 19: Approach for Estimating a Probable Range of Pit Lake

Damaged Rock Zone Properties

19

DAMAGED ROCK

Parameter Min Max

Thickness1 3 m 15 m

Size Factor2 0.05 0.2

Percent in Contact with Runoff3

30% 90%

Sulfate Leach Rate From Humidity Cell Data

1Radian 1997; McClosky et al. 2003 2Malmstrom et al. 2000; Lopez et al. 1997 3Frostad et al. 2005; Hollings et al. 2001

Page 20: Approach for Estimating a Probable Range of Pit Lake

Model Input

20

• Inflow concentrations are defined by probability distribution, in this case normal distribution, defined by mean and standard error of the mean

3.1416

MW_Stderr

3.1416

MW_Mean MW_Conc

Page 21: Approach for Estimating a Probable Range of Pit Lake

Solute Balance Simulations

21

• GoldSim uses Monte Carlo method for propagating uncertainty in model inputs into uncertainties in model outputs.

• Simulations conducted several thousand times (realizations)

• For each realization, a different parameter value is selected from the input probability distribution.

0

1

2

3

4

5

6

0 10 20 30 40 50 60 70 80 90 100(m

g/L)

Time (yr)

Fluoride

Percentiles Greatest Result 95% Percentile 75% Percentile 25% Percentile 5% Percentile Least Result Mean Median

Page 22: Approach for Estimating a Probable Range of Pit Lake

Geochemical Controls

22

• Bulk concentrations from the GoldSIM are analyzed for geochemical controls using PHREEQC:

• Atmospheric O2 and CO2 • Solubility controls for

probable mineral phases in pit lakes*

• Sorption to precipitated ferrihydrite

*Eary, L.E., Geochemical and equilibrium trends in mine pit lakes, Applied Geochemistry 14 (1999) 963-987

Summary Chemical Processes

Page 23: Approach for Estimating a Probable Range of Pit Lake

Model Results

23

Page 24: Approach for Estimating a Probable Range of Pit Lake

Model Results

24

Page 25: Approach for Estimating a Probable Range of Pit Lake

Model Results

25

Page 26: Approach for Estimating a Probable Range of Pit Lake

Model Results

26

Page 27: Approach for Estimating a Probable Range of Pit Lake

Model Results

27

Page 28: Approach for Estimating a Probable Range of Pit Lake

Summary “ Doubt is not a pleasant condition, but certainty is absurd”

- Voltaire

• Focus should be on capturing the uncertainty • Oxidation of sulfide wall rock is a large source

of uncertainty and commonly represented inaccurately

• Allows parties to “agree to disagree”

28

Page 29: Approach for Estimating a Probable Range of Pit Lake

Ongoing Challenges

29

• When you set a percentile, there won’t be any interest in lower percentiles.

• 90th Percentile precedent:

• Idaho Cobalt EIS • PolyMet EIS • Ecological Risk Assessment Guidance

Page 30: Approach for Estimating a Probable Range of Pit Lake

References (1 of 2)

30

Eary, L.E., 1999. Geochemical and equilibrium trends in mine pit lakes, Applied Geochemistry 14, pp. 963-987 Frostad, S., Klein, B., and Lawrence, R.W. 2005. Determining the weathering characteristics of a waste dump with field tests. Int. J. of Surface Mining, Reclamation and Environment, 19(2), pp. 132 – 143. Hollings, P., Hendry, M.J., Nicholson, R.V., and Kirkland, R.A. 2001. Quantification of oxygen consumption and sulphate release rates for waste rock piles using kinetic cells: Cluff Lake uranium mine, northern Saskatchewan, Canada. Applied Geochemistry, Vol. 16, pp. 1215-1230. International Network for Acid Prevention, Pit Lake Database <http://pitlakesdatabase.org/database/home.asp> Lopez, D.L., Smith, L. and Beckie, R. 1997. Modeling water flow in waste rock piles using kinematic wave theory. In Proceedings of the Fourth InternationalConference on Acid Rock Drainange, Vancouver, B.C. Canada, May 31 – June 6, 1997. Vol. 2, pp. 497 – 513.

Page 31: Approach for Estimating a Probable Range of Pit Lake

References (2 of 2)

31

Malmstrom, M., Destouni, G., Banwart, S., and Stromberg, B.H.E. 2000. Resolving the scale-dependence of mineral weathering rates. Env. Sci. and Technol, 34(7), pp. 1375 – 1378. McClosky, L., R. Wilmoth, J.LeFever, and D. Jordan, 2003. Evaluation of technologies to prevent acid mine drainage generation from open pit highwalls, In: Proceedings of the 6th International Conference on Acid Rock Drainage, Cairns, Australia, 14-17 July, 2003, pp. 541-547. Radian, 1997. Predicted water quality in the Betze-Screamer pit lake. Prepared for Barrick Goldstrike Mines, Inc., Elko, NV. Prepared by Radian International. U.S. Government Accountability Office, 2014. National Environmental Policy Act: Little Information Exists on NEPA Analyses, April 2014.