Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
M/s. SMR BUILDERS PVT LTD, PHASE-II
PROPOSED RESIDENTIAL COMPLEX
At SY.NO’S. 113 to 119, 121 & 126 Kondapur (V)
Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
FORM-1
FORM-1A
SUBMITTED TO
MINISTRY OF ENVIRONMENT & FORESTS,
GOVERNMENT OF INDIA
SUBMITTED BY
M/s. SMR BUILDERS PVT LTD
SMR HOUSE
5th Floor, Plot # 73,
Nagarjuna Hills, Panjagutta,
Hyderabad - 500 082
TELANGANA STATE
PREPARED BY
M/S PRIDHVI ENVIROTECH
(P) LIMITED,
184/C, 4th
Floor,
Vengal RaoNagar,
Hyderabad – 500 038
e-Mail : [email protected]
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 1
I) Basic information
S. No. Item Details
1 Name of the project/s M/s. SMR Builders Pvt. Ltd.
Residential Complex
2 S. No. in the schedule Project Activity – 8a
Category B1
3 Proposed capacity /area/ length/
tonnage to be
handled/command area/lease
area/ No of the well to be drilled
Blocks No. of
Floors
No. of
Flats
Area
(Sq.mts)
Block-IA 25 275 44094.24
Block-IB 20 240 40245.60
Block-IIA 25 225 33281.25
Block-IIB 20 140 25656.80
Block-III 28 224 39226.60
Block-IV 28 532 96701.36
Block-V 40 320 80291.20
Total 1956 3,59,497.05
Ameniti
es Block
9 20000.0
Total 3,79,497.05
Parking:
BASMENT –
1
SQ.MTS
BASMENT
– 2
SQ.MTS
BASMENT
– 3
SQ.MTS
BLOCK
I
10184.58 10184.58 10519.
62
BLOCK
II
8774.68 8774.68 9065.2
5
BLOCK
III
4544.98 4544.98 4702.1
2
BLOCK
IV
11688.48 11688.48 12070.
95
BLOCK
V
9620.62 9620.62 9937.8
7
Ameniti
es Block
2183.33 2183.33 2183.3
3
TOTAL 46996.67 46996.3
7
48479.
14
( In Square Meters)
Total Area of the residential flats: 3,79,497.05
Total Parking Area : 1,42,472.48
Total Built-up area including parking area
: 5,21,969.53 Sq. Mtrs
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 2
4 New/Expansion /Modernization Proposed to develop a residential project
obtained TOR vide File No. F.No.21-
54/2015-IA. III dated 18.06.2015. As there
are changes from the original plan, this
application is made for amendment of
previous TOR
5 Existing capacity/Area etc… NA
6 Category of project A or B Category B1
7 Does it attract the general
condition? If yes please specify
No
8 Does it attract the specific
condition? If yes please specify
No
9 Location
Plot/ survey /Khasra no
Village
Tehsil/Mandal
District
State
Sy.No: 113 to 119, 121 &126
Kondapur (V),
Serilingampally (M),
Ranga Reddy District
Telangna
10 Nearest Railway station/Air port
along with the distance in kms
LIngampally – 4.0 Kms
Shamshabad Air port – 40 KM
11 Nearest Town, City, District
Headquarters along with distances
in kms.
This is Part of Kondapur Village
12 Village Panchayats Zilla Parishad
Municipal Corporation, Local body
(complete postal Address with
telephone no. to be given
Greater Hyderabad Municipal Corporation
13 Name of the applicant Mr. S. Ram Reddy,
Chairman & Managing Director
14 Registered address SMR House,
Plot No 73,
Nagarjuna Hills,Panjagutta,
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 3
Hyderabad -500 082
Ph: +91 40 2335 3722, 2335 3726
Fax: +91 40 2335 3297
15 Address of the correspondence
Name
Designation /owner/partner/CEO
Address
Pin code
Telephone no
Fax no
Mr. S. Ram Reddy,
Chairman & Managing Director
SMR House,
Plot No 73,
Nagarjuna Hills,Panjagutta,
Hyderabad -500 082, Telangana
Ph: +91 40 2335 3722, 2335 3726
Fax: +91 40 2335 3297
16 Details of Alternative Sites
examined if any.
Location of these sites Should be
shown on a Topo sheet.
This Semi Constructed site was taken over by
SMR Builders (P) Limited from Kondapur
Towers (P) Limited and will be developed by
SMR Builders (P) Limited
17 Interlinked Projects No
18 Whether separate application of
interlinked projects has been
submitted
Not Applicable
19 If yes, date of submission Not Applicable
20 If no reason Not Applicable
21 Whether the proposal involves
approval / clearances under: if
yes, details of the same and their
status to be given.
(a) The Forest (conservation) Act,
1980?
(b) The Wild life (protection) Act,
1972?
(c) The C.R.Z notification, 1991?
No
No
No
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 4
22 Whether there is any Government
order/policy relevant/relating to
the site?
No
23 Forest land involved (Hectares) No
24 Whether there is any litigation
pending against the project
and/or land in which the project is
propose to be set up?
(a)Name of the court
(b)Case no.
(c) Orders/directions of the court, if
any and its relevance with the
proposed project.
No
(II) Activity
1.0 Construction, operation or decommissioning of the Project involving actions, which
will cause Physical Changes in the locality (topography, land use, changes in
water bodies, etc.).
S.No. Information /Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
1.1 Permanent or temporary change
in land use, land cover or
topography including increase in
intensity of land use (with respect
to local land use plan)
Yes The proposed project activity is
construction of Residential Complex.
The site area is located in GHMC area.
Part of the site is under development
and is taken over by SMR Builders. This
area is earmarked as residential zone as
per the Master plan of Hyderabad
Urban Development Authority.
1.2 Clearance of existing land,
vegetation and buildings?
No The land is semi constructed. Except
few bushes, there is no vegetation
1.3 Creation of new land uses? Yes The purpose of proposed project is
construction of Residential Complex
hence there will not be any change in
land use
1.4 Pre-construction investigations Yes Soil bearing tests were conducted
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 5
e.g. bore holes, soil testing? before construction of current blocks by
previous management.
1.5 Construction works? Yes The project is residential complex. 5
blocks would be constructed as a part
of the plan
1.6 Demolition Works? Yes There will be partial demolitions to
modify the existing structures
1.7 Temporary sites used for
construction works or housing of
construction works?
Yes Temporary shelters for construction
workers are not required as f labor will
be hired from the surrounding locations
1.8 Above ground buildings,
structures or earthworks including
linear structures, cut and fill or
excavations
Yes The proposed development is
Construction of Residential Complex.
Cut and fill activity will be there for
basement and foundations
1.9 Underground works including
mining or tunneling?
No Not Applicable as this is a Construction
of Residential Complex.
1.10 Reclamation Works? No Not envisaged.
1.11 Dredging? No Not Applicable as this is a Construction
of Residential Complex.
1.12 Offshore structures? No Not Applicable as this is a Construction
of Residential Complex.
1.13 Production and manufacturing
processes?
No No manufacturing activity.
Activity is Construction of Residential
Complex.
1.14 Facilities for storage of goods or
materials?
Yes Storage space of building materials will
be earmarked onsite.
1.15 Facilities for treatment or disposal
of solid waste or liquid effluents?
Yes Solid waste generated from the
construction includes rubble, used up
cement, broken bricks etc, which will be
used for filling up low lying areas during
developmental stage.
Treated liquid effluents from domestic
waste water will be used for flushing
and gardening and rest would be sent
to municipal drains.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 6
STP Sludge will be used as manure in
green belt development
1.16 Facilities for long term housing of
operational workers?
No Manpower requirement of operational
workers is nominal and will be recruited
from surroundings therefore no long
term housing facilities are envisaged.
1.17 New road, rail or sea traffic during
construction or operation?
No Existing facilities will be used for the
proposed project.
1.18 New road, rail, air waterborne or
other transport infrastructure
including new or altered routes
and stations, ports, airports etc?
No Not envisaged
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No Not envisaged
1.20 New or diverted transmission lines
or pipelines?
No -
1.21 Impoundment, damming,
culverting, realignment or other
changes to the hydrology of
watercourses or aquifers?
No The proposed development will not
disturb the natural terrain of the area
and will not disturb the water courses in
any ways i.e. no drain flows through the
site.
Rain Water Harvesting system is
proposed to recharge the GWL
1.22 Stream crossings? No There are no stream crossings the
proposed site.
1.23 Abstraction or transfers of water
from ground or surface waters?
Yes Water requirement of the project will be
met from HMWS&SB & Borewell
1.24 Changes in water bodies or the
land surface affecting drainage
or run-off?
No The development will be carried out
with no disturbance to major water or
the land surface, affecting drainage or
runoff.
1.25 Transport of personnel or
materials for construction,
Yes Transportation of personnel or material
will be by trucks on road
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 7
operation or decommissioning?
1.26 Long-term dismantling or
decommissioning which could
have an impact on the
environment?
No Not envisaged
1.27 Ongoing activity during
decommissioning which could
have an impact on the
environment?
No Not envisaged
1.28 Influx of people to an area in
either temporarily or
permanently?
Yes Total of 1956 flats are proposed. The
local area is developing at a faster
pace due to development in the
surrounding areas.
1.29 Introduction of alien species? No --
1.30 Loss of native species or genetic
diversity?
No --
1.31 Any other actions? No --
2.0 USE OF NATURAL RESOURCES for construction or operation of the Project (Such as
land, water, materials or energy, especially any resources which are non-
renewable or in short supply):
S.No. Information /Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
2.1 Land especially undeveloped or
agricultural land (ha)
No Proposed to develop a residential
project obtained TOR vide File No.
F.No.21-54/2015-IA. III dated
18.06.2015. As there are changes
from the original plan, this
application is made for amendment
of previous TOR
The total cost of the project is Rs. 525
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 8
Crores
2.2 Water (expected source &
competing users) Unit : KLD
Yes Water Requirement : 1352.0 KLD
Fresh water requirement – 890 KLD
Source: HMWS&SB.
Recycled water –462.0 KLD
Source : S.T.P
2.3 Minerals (MT) Yes Not Applicable as this is a construction
project.
2.4 Construction material – stone,
aggregates, and / soil (expected
source- MT)
Yes Construction materials like coarse
aggregate, fine aggregate, granite.
Kota stone, Dolhpur stone, Marble,
bricks, sand, cement, steel will be used.
The raw materials will be sourced from
local dealers & traders.
2.5 Forests and timber (source – MT) Yes Wood will be used only for preparing
window and door frames.
The required timber will be procured
from local authorized timer dipos
2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes Power Required : 11195 KVA
Source: Central Power Distribution
Company Limited (TSCPDL).
Back-up power: 6 x 500 KVA DG sets for
emergency during power failures.
Fuel: HSD required @ 900 Liters, will be
sourced from local traders
2.7 Any other natural resources (use
appropriate standard units)
No Not Applicable
3.0 Use, storage, transport, handling or production of substances or materials which
could be harmful to human health or THE ENVIRONMENT or raise concerns about
actual or perceived RISKS TO HUMAN HEALTH.
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
3.1 Use of substance or materials,
which are hazardous (as per
MSIHC rules) to human health or
No Only HSD in small quantities will be used
for back up power DG sets. Paints are
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 9
the environment (flora, fauna,
and water supplies)
used during construction
3.2 Changes in occurrence of
disease or affect disease vectors
(e.g. insect or water borne
diseases)
No
3.3 Affect the welfare or people e.g.
by changing living conditions?
Yes Good quality housing is proposed with
good living environment for 1956
families
3.4 Vulnerable groups of people
who could be affected by the
project e.g. hospital patient’s children, the elderly etc.,
No --
3.5 Any other causes No --
4.0 Production of SOLID WASTES during construction or operation or decommissioning
(MT/ month)
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
4.1 Soil, overburden or mine wastes No --
4.2 Municipal waste (domestic and
or commercial wastes)
Yes Garbage – 4900 kgs/day
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
No Used Oils from – 300 LPA
Used Batteries – 10 no’s/year Transformer Oil – 100 LPA
4.4 Other industrial process wastes No Not Applicable
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge
from effluent treatment
Yes Sewage Sludge @ 100 kg/d will be used
as manure for green belt development.
4.7 Construction or demolition Yes During construction some amount of
construction debris may be generated
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 10
wastes which will be segregated and whatever
re-saleable will be sold to supplier and
rest waste will be used for filling up of
low lying areas and development of
internal roads and boundary walls etc
4.8 Redundant machinery or
equipment
No Most of the equipment used for the
construction will be hired.
4.9 Contaminated soils or other
materials
No No soil contamination is anticipated as
the proposed project is a construction
project all the waste generated will be
in the form of solid waste of reusable
nature.
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes No --
5.0 Release of pollutants or any hazardous, toxic or noxious substances to AIR (Kg/hr)
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
5.1 Emissions from combustion of
fossil fuels from stationary or
mobile sources
Yes Emissions will be mainly from vehicles
moving at the project site during
construction and operation period and
secondly from the 6 x 500 KVA DG sets
used for backup power source
operated only during power failures
only for a short duration.
As HSD will be used for the DG sets, the
main emissions will be SO2 and NOx.
For Proper dispersion of pollutants, the
stack height meeting CPCB Norms will
be maintained.
5.2 Emissions from production
processes
NO Only emissions would be from Kitchen
5.3 Emissions from materials handling
including storage or transport
Yes Vehicular emissions are anticipated
both during construction and during
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 11
operation.
5.4 Emissions from construction
activities including plant and
equipment
Yes Fugitive emissions are likely during
construction activities from the
materials. These are temporary in
nature.
The main emissions during the
construction will be PM from the loading
and unloading of materials on the site.
SO2 and NOx from the combustion of
fossil fuels and from vehicles.
5.5 Dust or odors from handling of
materials including construction
materials, sewage and waste.
Yes The particulate matter will be mainly
generated from loading and unloading
of the material at the site.
Other municipal solid waste will be
disposed off to the Municipal solid
waste dump yard.
The construction material will be
handled carefully to prevent any spill
over or wastage. Construction labor will
be provided with proper sanitation to
avoid any unhygienic conditions.
Therefore no odor generation is
expected
5.6 Emissions from incineration of
waste
No --
5.7 Emissions from burning of waste
in open air (e.g. slash materials,
construction debris)
No --
5.8 Emissions from any other sources No --
6.0 Generation of Noise and Vibration, and Emissions of Light and Heat:
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
6.1 From operation of equipment
e.g. engines, ventilation plant,
Yes Noise is anticipated during construction
activities, movement of construction
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 12
crushers
material and use of machinery.
These are temporary in nature and will
be minimized by adopting proper
maintenance such as greasing, oiling
and insulations (acoustic enclosures) for
DG Set.
6.2 From industrials or similar
processes
No --
6.3 From construction or demolition Yes Construction activity create noise and
vibrations.
These will be temporary in nature and
will be phased out once the
construction is over.
6.4 From blasting or piling No --
6.5 From construction or operational
traffic.
Yes Yes during the construction. Once the
flats are completed, two wheelers and
Cars can create noise
6.6 From lighting or cooling systems No --.
6.7 From any other sources No --
7.0 Risks of CONTAMINATION OF LAND OR WATER from releases of pollutants into the
ground or into sewers, surface waters, groundwater, coastal waters or the sea :
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
7.1 From handling, storage, use or
spillage of hazardous materials
No Used batteries and waste oil shall be
stored separately and shall not lead to
contamination of land during normal
operation.
7.2 From discharge of sewage or
other effluents to water or the
land (expected mode and
place of discharge )
No The sewage shall be treated to achieve
the standards prescribed by MoE&F
during operation phase. While the
discharges from temporary toilets during
construction shall be sent to septic tank
followed by municipal sewer lines.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 13
7.3 By deposition of pollutants
emitted to air into the land or
into water
No No pollutants are emitted in to air.
Hence no deposition of pollutants into
land or water.
7.4 From any other sources No --
7.5 Is there a risk of long term build
up of pollutants in the
environment from these sources?
No Proper Environmental management
plan will be followed for air, water, noise
and solid waste. Hence no long term
impacts are envisaged.
8.0 Risk of accidents during construction or operation of the Project, which could
affect human or the environment
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
8.1 From explosions, spillages, fires
etc from storage, handling, use
or production of hazardous
substances
No Fire hydrant and Fire fighting systems will
be installed and safety precautions will
be followed as per the safety rules.
Only Diesel in small quantity and paints
during construction phase will be
flammable material used and stored.
8.2 From any other causes No Not Applicable
8.3 Could the project be affected
by natural disasters causing
environmental damage (e.g.
floods, earthquakes, landslides,
cloudburst etc)?
No The project site is located at a higher
elevation and the seismic zone for the
project area is Zone-II, which is
considered safe.
9.0 Factors which should be considered (such as consequential DEVELOPMENT) which
could lead to ENVIRONMENTAL EFFECTS or the potential for cumulative impacts with
other existing or planned activates in the locality
S. No. Information /Checklist
confirmation
Yes/No Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
9.1 Lead to development of
supporting. utilities, ancillary
development or development
stimulated by the project which
could have impact on the
Yes
The proposed project is a
construction of Residential Complex.
So it leads to development of
supporting facilities and ancillary &
related activities.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 14
environment e.g.:
Supporting infrastructure
(roads, power supply,
waste or waste water
treatment, etc.)
Housing development
Extractive industries
Supply industries
Other
Yes
Yes
No
No
No
Existing
9.2 Lead to after use of the site,
which could have impact on the
environment
No --
9.3 Set a precedent for later
developments
Yes The area is developed residential
and commercial area.
9.4 Have cumulative effects due to
proximity to other existing or
planned project as with similar
effects )
No --
(III) Environment Sensitivity
S. No. Areas Name/
Identity
Aerial distances (within 15 km.)
Proposed project location boundary
1. Areas protected under
international conventions,
national or local legislation for
their ecological, landscape,
cultural or other related values
Yes Kasu Brahmananda Reddy National
Park - 9.6 KM
2. Areas which are important or
sensitive for ecological reasons –
Wetlands, water courses or other
water bodies, coastal zone,
biospheres. Mountains, forests
Yes Osman sagar – 8.4 kms upstream
Duram Cheruvu – 8.0 KM
3. Areas and by protected, Yes Kothaguda RF – 2.3 kms
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 15
important or sensitive species of
flora or fauna for breeding,
nesting, foraging, resting, over
wintering, migration
4. Inland, coastal, marine or
underground waters
No Few rain fed tanks within 10 KM radius
of the site
5. State, National boundaries No -
6. Routes or facilities used by the
public for access to recreation
or other tourist, pilgrim areas
No Durgam Cheruvu is boating area &
Silparamam cultural importance
7. Defense installations No None
8. Densely populated or built-up
area
Yes The area is developing into a densely
populated area.
9. Areas occupied by sensitive
man-made land uses (hospitals,
schools, places of worship,
community facilities )
Yes There are many colleges, schools,
hospitals and places of work ship
within 10 KM radius
10. Areas containing important, high
quality or scarce resources
(ground water resources, surface
resources, forestry, agriculture,
fisheries, tourism, minerals)
Yes
Osman Sagar within 10 KM radius
which is one the drinking water
source for Hyderabad
11. Areas susceptible to natural
hazard which could cause the
project to present environmental
problems (earthquakes,
subsidence, landslides, erosion,
flooding or extreme or adverse
climatic conditions)
No --
IV. Proposed Terms of Reference for
EIA Studies
B-1 Category Project
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 16
Proposed Terms of Reference for EIA studies
Scope of Work of EIA
...The EIA shall co er the follo i g:
Description of the proposed project:
The first task: Descriptio of the proposed project for s a ital co po e t of the E iro e tal I pact Assessment (EIA) as it provides the basis for evaluating the likely causes of Environmental Impacts.
Existing Environment and Baseline Conditions:
The baseline assessment will be carried out to identify potentially sensitive and critical areas that may be affected
by the project in an area of 10 km surrounding the project location. The critical and sensitive targets shall be
plotted on land use map of project impact area. The existing environment and baseline conditions should be
established from:-
Analysis of existing information published and secondary data.
-Consultation with relevant statutory authorities, and Field visits for supplementation of missing gaps.
The key subject areas which the EIA shall address include Ecology and Nature conservation, Air quality, surface
and water quality in project impact area, soil quality, cultural heritage, landscape, land use, noise quality, etc.
Natural habitats like national parks, wildlife reserves, sanctuaries, sacred grove, protected areas, forests,
wetlands, major rivers and waterways if any, shall also be identified and marked.
Assessment of Environmental Impacts:
Based upon the results from the review of existing information, field visits, site data collection and consultation,
for each component of environment (physical, biological and socio economic) the positive, negative, direct and
indirect, temporary and permanent impacts will be evaluated along with an indication of the degree of impact,
i.e., whether the impact is significant, moderate, minor or negligible. The degree of impact shall also be
quantified by using state of the art air quality impact prediction models based on ISCST3 algorithms.
Environment Management Plan And Mitigation Plan:
For each significant negative impact identified, specialist shall work closely with the engineering team/technical
consultants to suggest practicable measures to avoid or mitigate the impact. The mitigation of environmental
impacts will be by three mechanisms.
=>Introduction of mitigation features through the engineering practices.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 17
=>Implementation of environmental controls during construction and operation.
=>Legislative control involving compliance with Indian environmental laws.
The Environmental management plan shall include an estimate of capital and recurring costs of mitigation
measures and will identify the institutional framework for implementation.
Monitoring Plan:
Having identified the significant environmental impact that is likely to arise as a result of the project, the project
team shall specify what monitoring is required during the various phases of the project cycle.
The monitoring plan will identify parameters and frequency of monitoring and responsible organization.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 18
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 19
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 1
FORM-1 A
(Only for construction projects listed items 8 of the Schedule)
CHECK LIST OF ENVIRONMETNAL IMPACTS
(Projects proponents are required to provide full information and wherever
necessary attach explanatory notes with the Form and submit along with proposed
environmental management plan & monitoring programme)
1. LAND ENVIRONMENT
S.N
o.
ITEM DETAILS
1.1 Will the existing land use get
significantly altered from the
project that is not consistent with
the surroundings? (Proposed
landuse must conform to the
approved Master Plan /
Development Plan of the area.
Change of landuse if any and the
statutory approval from the
competent authority be submitted).
Attach Maps of (i) site location, (ii)
surrounding features of the
proposed site (within 500 meters)
and (iii)the site (indicating levels &
contours) to appropriate scales. If
not available attach only
conceptual plans.
The proposed project is Construction of
Residential complex.
This area is earmarked as residential Zone by
HMDA. The project is in semi construction stage
and was taken over by the current
management
1.2 List out all the major project
requirements in terms of the land
area, built up area, water
consumption, power requirement,
connectivity, community facilities,
parking needs etc.
The major requirements of the project is
summarized as below:
1. Plot area This is semi constructed
project which was taken
over by current
Management recently.
The total area of the plot
is 21.35 Acres. Out of this
in the first phase 9.237
acres is developed. Now
it is proposed to develop
second phase in the rest
of the land area-11.82
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 2
Acres. The total cost of
the project is Rs. 525
Crores
2. Built-up
area
5,21,969.53 Sq.mts
3 No. and
type of flats
5 BHK flats -352
4 BHK flats -201
3 BHK Flats -888
2 BHK Flats -515
Total - 1956 Flats
4 Water
consumptio
n
Daily water demand will
be 1352 KLD (890 KLD fresh
water demand + 462 KLD
recycled STP treated
water).
The fresh water Demand
will be met from HMWS&SB
and Borewell
5 Power
requirement
11195 KVA
6. Connectivit
y facilities
The project is well
connected with the
following:
Lingampally RS – 4.0 kms
Kondapur Bus Depot – 2
kms
Rajiv Gandhi
International Airport –
Shamshabad - 40 Kms
7 Parking
needs
1,42,472.48 Sq.mts
3600 four wheelers
parking and 2000 two
wheelers parking
8 Total Cost of
the project
Rs. 525 Crores
1.3 What are the likely impacts of the
proposed activity on the existing
facilities adjacent to the proposed
site? (Such as open spaces,
community facilities, details of the
existing landuse, disturbance to the
The area is already developed as residential
and commercial area. There is no significant
impact due to this project
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 3
local ecology).
1.4 Will there be any significant land
disturbance resulting in erosion,
subsidence & instability? (Details of
soil type, slope analysis, vulnerability
to subsidence, seismicity etc may
be given).
The area is not prone to any land disturbance
and no evident history of the same is available.
Soil Type – Hard morum soil with outcraps
Slope Analysis:
The topography of the site is almost flat. There
will not be any change in topography of the
area. The drainage pattern will remain as per
the existing pattern.
Vulnerability to Subsidence:
There is no subsidence anticipated.
Seismicity – Zone – II as per the IMD
1.5 Will the proposal involve alteration
of natural drainage systems? (Give
details on a contour map showing
the natural drainage near the
proposed project site)
No, there is no change in the overall natural
drainage system. However, the internal run off
drainage is channelized to the rain water
harvesting pits for re-charging the ground
water
1.6 What are the quantities of
earthwork involved in the
construction activity-cutting, filling,
reclamation etc. (Give details of
the quantities of earthwork
involved, transport of fill materials
from outside the site etc.)
There will be scrapping off soil to the tune of
10,457 cu. m., which will be used within the site
for filling purposes. No fill material is required
from outside as excavated soil, construction
and demolition waste (existing structures) will
be reused within the site.
1.7 Give details regarding water
supply, waste handling etc during
the construction period.
Water supply:
The domestic water demand during
construction phase will be about 50 KLD.
The water will be met from water tanker.
Solid waste:
50 kg/day of solid waste will be generated
during construction phase and will be sent to
GHMC.
1.8 Will the low lying areas & wetlands
get altered? (Provide details of how
low lying and wetlands are getting
modified from the proposed
activity)
There are no wetlands and low lying areas
around the site.
1.9 Whether construction debris &
waste during construction cause
health hazard? (Give quantities of
The construction debris consists of variety of
materials. Iron, glass, plastics, cartons of paper,
wood waste etc would be sold to re-users.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 4
various types of wastes generated
during construction including the
construction labor and the means
of disposal)
Demolished bricks, Cement Concrete etc
would be used in internal road formation and
as filling materials of basements.
Paint cans, adhesives, thinner cans etc would
be sold to authorized re-cyclers
2.0 WATER ENVIRONMENT:
S.No. ITEM DETAILS
2.1 Give the total quantity of water
requirement for the proposed
project with the breakup of
requirements for various uses. How
will the water requirement met?
State the sources & quantities and
furnish a water balance statement.
The daily water requirement for the
proposed project will be 1352 KLD. The daily
fresh water requirement will be 890 KLD,
sourced from HMWS&SB and Borewell and
the recycled water requirement will be 462
KLD, which will be used for flushing and
gardening.
The water balance chart showing break up
of requirements for various uses with
quantities of fresh and recycled water is
given at Table No.2.6
2.2 What is the capacity (dependable
flow or yield) of the proposed
source of water?
S.
No
Reservoir Storage
Capacity at
FTL (in MCM)
1. Osman sagar 110.43
2. Himayath
sagar
84.016
3. Singur 849.505
4. Manjira 41.399
5. Akkampally
(Krishna water)
41.031
Total 1126.381
(Source: HMWS&SB and Borewell)
2.3 What is the quality of water
required, in case, the supply is not
from a municipal source? (Provide
physical, chemical, biological
characteristics with class of water
quality)
Water will be sourced from HMWS&SB and
Borewell. In case of any emergency water
will be purchased from private sources
through tankers
2.4 How much of the water
requirement can be met from the
Out of 1352 KLD requirement, approximately
462 KLD of the water required will be met
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 5
recycling of treated wastewater?
(Give the details of quantities,
sources and usage)
through reuse of treated water from sewage
treatment plant.
2.5 Will there be diversion of water from
other users? (Please assess the
impacts of the project on other
existing uses and quantities of
consumption)
No
Water will be sourced from HMWS&SB and
Borewell
2.6 What is the incremental pollution
load from wastewater generated
from the proposed activity? (Give
details of the quantities and
composition of wastewater
generated from the proposed
activity)
The waste water generated will be to the
tune of 1150 KLD. The waste water
generated will be treated in sewage
treatment plant based on FAB technology of
capacity 1300 KLD.
effluent characteristic is given as:
Parameter Unit Concentration
Quantity KLD 1150
pH -- 6.5-8.5
Oi l &
Grease Mg/l 20
TSS Mg/l 200
BOD Mg/l 300
COD Mg/l 500
2.7 Give details of the water
requirements met from water
harvesting? Furnish details of the
facilities created.
Elaborate plans have been made for
channelizing the storm water by constructing
water drains leading to the reservoirs. In
order to minimize the surface runoff loss,
groundwater recharging through
groundwater recharge pits at the project site
has been planned. Appropriate design
considerations have been taken while
designing the recharge pits.
The rainwater is proposed to be channelized
for storage in reservoirs to be used for project
needs after due treatment and also for
groundwater recharging through the
recharge pits.
2.8 What would be the impact of the
land use changes occurring due to
the proposed project on the runoff
characteristics (quantitative as well
The project will involve construction of
rooftop & paved areas and hence, quantity
of runoff will increase due to reduced
infiltration & increase in surface run off
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 6
as qualitative) of the area in the
post construction phase on a long
term basis? Would it aggravate the
problems of flooding or water
logging in any way?
coefficient in post construction phase as
compared to the pre-construction phase.
The overflow during abnormally heavy rains
will follow the run off pattern. The proposed
rainwater structures have been designed for
accommodating peak rainfall intensity,
which will not aggravate the problem of
flooding in the project area. The run-off from
roof top, paved and landscaped areas will
be used for ground water recharge.
Provisions of capturing the surface runoff to
the extent of 100% will be done.
2.9 What are the impacts of the
proposal on the ground water? (Will
there be tapping of ground water;
give the details of ground water
table, recharging capacity, and
approvals obtained from
competent authority, if any)
No Impacts will be on the ground water the
required water will be supplied by HMWS&SB
and part of the treated water is recycled
and used for gardening & flushing. Rain
water harvesting structures will be provided
in the site to tap the rain water which in turn
recharges the ground water table.
2.10 What precautions/measures are
taken to prevent the run-off from
construction activities polluting land
& aquifers? (Give details of
quantities and the measures taken
to avoid the adverse impacts)
There are effective measures adapted to
reduce the storm water run-off from the
construction site-
Ensuring vehicles stick to the access track.
Cleaning all mud and dirt deposited on
roads from construction-related activities.
Stabilizing a single entry/exit point to ensure
sediment is not tracked off site-this also
increase site durability during wet weather.
Excavation work will not be carried out
during monsoon season.
Constructing a fence around the site to
trap sediment whilst allowing water to flow
through.
Diverting up-slope water with turf and not
mixing mortar in locations that will drain into
storm water system.
Preventing wastewater from brick cutting
activities and stockpiles entering the storm
water system.
Construction material will be stored at the
earmarked places and will be covered with
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 7
a temporary shed ensuring that no
leachate or spoilage of land occurs.
Curing water will be sprayed and, after
liberal curing, all concrete structures will be
painted & covered with gunny bags, then
the water will be sprayed. This will help to
save water.
2.11 How is the storm water from within
the site managed?(State the
provisions made to avoid flooding
of the area, details of the drainage
facilities provided along with a site
layout indication contour levels)
Infrastructural facilities like provision of
adequate storm water drains, wastewater
collection and conveyance including
treatment and disposal have been planned
in the project.
2.12 Will the deployment of construction
labourers particularly in the peak
period lead to unsanitary conditions
around the project site (Justify with
proper explanation)
The local people will be deployed during
construction. There will be no stagnant water
at site, as the run off from the relevant areas
will be systematically drained.
The civil contractor will be held responsible
for site sanitation and will be bound by the
management to adhere to healthy level of
sanitation.
2.13 What on-site facilities are provided
for the collection, treatment & safe
disposal of sewage? (Give details of
the quantities of wastewater
generation, treatment capacities
with technology & facilities for
recycling and disposal)
Construction phase:
The waste water to the tune of 20 KLD from
toilets will be diverted to sewer system in the
area after getting necessary permissions
Post construction phase:
Sewage water will be collected and treated
in FAB based 1300 KLD STP.
Treatment efficiency: >85%
Reuse and disposal:
STP treated water: 462 KLD for flushing and
gardening and rest would be disposed the
drain
2.14 Give details of dual plumbing
system if treated waste used is used
for flushing of toilets or any other
use.
There will be separate pipelines for the supply
of the fresh water and treated water from STP.
Treated water will be used for the flushing
purposes & Gardening purposes, domestic
consumption.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 8
3. VEGETATION
S.No. ITEM DETAILS
3.1 Is there any threat of the project to
the biodiversity? (Give a description
of the local ecosystem with it’s unique features, if any)
There will be no threat on the biodiversity
due to the proposed project. Project site is
almost flat terrain mostly
dominated/covered with common grass
and shrub species. Moreover, site doesn’t support any critical or special habitat; which
can support threatened, endangered
species.
3.2 Will the construction involve
extensive clearing or modification
of vegetation? (Provide a
detailed account of the trees &
vegetation affected by the project)
The construction will not involve any
clearing and modification as the site is a
barren land with practically no vegetation
except few small shrubs.
3.3 What are the measures proposed
to be taken to minimize the likely
impacts on important site features
(Give details of proposal for tree
plantation, landscaping, creation
of water bodies etc along with a
layout plan to an appropriate
scale)
Due care will be taken to protect the
important site features:
Tree plantation will be done to protect the
site features such as topsoil erosion,
ground water attenuation and avoiding
contamination by leachate.
The excavated soil will be stored at
earmarked places protected from
contamination and from polluting the
existing features and will be used for
surface leveling and for creation of
landscaped areas.
Piling will be done so as to minimize the
impacts on the existing structures in the
nearby areas.
Green belt will be developed in an area of
7280.52 Sq.mts.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 9
4. FAUNA
S.No. ITEM DETAILS
4.1 Is there likely to be any
displacement of fauna- both
terrestrial and aquatic or creation
of barriers for their movement?
Provide the details.
The proposed site does not have any
terrestrial and aquatic fauna, so no
displacement will take place.
4.2 Any direct or indirect impacts on
the avifauna of the area? Provide
details
No endangered or endemic species of
birds are found in the study area,
4.3 Prescribe measures such as
corridors, fish ladders etc to
mitigate adverse impacts on fauna
Not applicable
5. AIR ENVIRONMENT:
S.No. ITEM DETAILS
5.1 Will the project increase
atmospheric concentration of
gases & result in heat islands? (Give
details of background air quality
levels with predicted values based
on dispersion models taking into
account the increased traffic
generation as a result of the
proposed constructions)
There will be increase in intensity of land use
in the existing area, which may result in the
creation of heat islands. DG sets are
deployed for the project, which will result in
the increase in atmospheric concentration
of gases.
Impact:
Urban Heat island effect due to increase in
the paved areas (Roof +& Non Roof).
Emissions due to traffic load
An emission due to DG sets
Mitigation measures:
Heat Island Effect: Roof
The roofs will be covered with solar panels
which will reduce the exposed roof area.
The other exposed roof will be covered
with white china mosaic tiles/green roof to
reduce the heat gains inside the building.
Heat Island Effect: Non-roof:
Hard paving onsite has been reduced to
the best possible extent.
About 10% of the area will be under
greenbelt, which will mitigate heat island
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 10
effect.
Fugitive dust emissions:
Sources:
Construction activities.
Vehicular movement.
Road construction.
Paved and unpaved area emissions.
Mitigation:
Screening the construction site with the
help of tarpaulin to contain the emissions
within the site.
Water spraying on the haul roads.
Storage of construction material and
waste at earmarked places and well
covered.
Impact due to traffic emissions:
The impact of vehicular emissions varies with
rate of movement of vehicles, atmospheric
conditions and stability classes.
Mitigation:
About 7280.52 sq. m. area will be under
landscape.
The vehicles will be PUC certified.
Reduced vehicular speed will also avoid
the air borne fugitive emission on the
unpaved areas.
5.2 What are the impacts on
generation of dust, smoke, odorous
fumes or other hazardous gases?
Give details in relation to all the
meteorological parameters
The impacts of dust and gaseous pollutants
due to different construction activities will be
localized and will not affect the surrounding
environment. All necessary measures will be
taken.
Water spraying at dust generation sources
All transportation vehicles will be suitably
covered to prevent dust dispersion from the
trucks, and overloading of the vehicles will
be avoided and must be PUC certified
vehicle.
Plantation is proposed to be taken up
along the boundary of the project site to
the extent possible.
Eco-friendly D.G. Sets will be installed to
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 11
maintain the emission within the norms etc.
The D.G. sets will be provided with
adequate safe stack height to regulate the
emission within the permissible norms.
Low sulphur content fuel (HSD: sulphur
content: 0.05%) will be used which will help
to contain the emissions within the
permissible range.
5.3 Will the proposal create shortage of
parking space for vehicles? Furnish
details of the present level of
transport infrastructure and
measures proposed for
improvement including the traffic
management at the entry & exit to
the project site.
Adequate provision will be kept for parking
at the proposed project. Sufficient planning
is being done so that transport system is
organized by following the good traffic
management techniques.
Proposed parking area – 1,42,472.48 Sq. Mts.
No. of Vehicles – 3600 four wheelers & 2000
Two wheelers.
Following measures will be adopted for
smooth traffic movements:
Provisions of fully internalized parking
including the parking facilities for the
visitors.
Guided traffic ways within the project site.
Speed humps will be installed for speed
restrictions inside the project area.
5.4 Provide details of the movement
patterns with internal roads, bicycle
tracks, pedestrian pathways,
footpaths etc., with areas under
each category.
The movement pattern inside the project
area will be guided traffic ways. There will
not be any separate bicycle tracks or
pedestrian pathways on the periphery
(driveway).
5.5 Will there be significant increase in
traffic noise & vibrations? Give
details of the sources and the
measures proposed for mitigation
of the above.
There is no significant increase in noise and
vibration. The noise and vibrations level will
be well within the norms. Speed of the
vehicles will be limited to 15-20 Km/hr to
minimize noise and vibration.
The following measures will be adopted to
reduce the noise:
Trees with heavy foliage will be planted at
the periphery so as to restrict the noise
levels within the permissible norms.
Both entry and exit are manned with
trained and efficient security.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 12
Road markings, Stop lines, parking lanes are
painted to guide the internal road user.
Separate entry/exit is provided such that it
enables the smooth movement of the
vehicles.
5.6 What will be the impact of DG sets
& other equipment on noise levels
& vibration in & ambient air quality
around the project site? Provide
details.
Construction Phase:
The noise level due to construction activity
and in operational phase will be localized to
the source. During the construction phase,
noise will be generated from the
construction equipment’s and the operation of DG sets.
Fugitive emissions generated from various
construction activities will be contained by
screening the site by tarpaulin.
The noise level due to construction activity
and in operational phase will be localized.
Post Construction phase:
The important source of pollution during post
construction phase will be emissions from
D.G. sets used in case of power cuts or failure
(for complete power back up).
The DG sets will be housed in an inbuilt
acoustic enclosure for maximum noise
attenuation.
The DG sets deployed will be EPA/ CPCB
certified for the permissible standards of
noise & vibrations.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 13
6. AESTHETICS
S.No. ITEM DETAILS
6.1 Will the proposed constructions in
any way result in the obstruction of
a view, scenic amenity or
landscapes? Are these
considerations taken into account
by the proponents?
The proposed project will not in any way
obstruct any view, scenic amenity or
landscapes. In fact it increases aesthetics of
the area due to large scale green belt
development
6.2 Will there be any adverse impacts
from new constructions on the
existing structures? What are the
considerations taken into account?
No, there will be no impact on existing
infrastructure due to the construction
activities.
6.3 Whether there are any local
considerations of urban form &
urban design influencing the design
criteria? They may be explicitly spelt
out.
The layout plan is on the basis of
development rules prescribed by GHMC.
6.4 Are there any anthropological or
archaeological sites or artefacts
nearby? State if any other
significant features in the vicinity of
the proposed site have been
considered.
None
7. SOCIO-ECONOMIC ASPECTS
S.No. ITEM DETAILS
7.1 Will the proposal result in any
changes to the demographic
structure of local population?
Provide the details.
No such changes envisaged
7.2 Give details of the existing social
infrastructure around the proposed
project.
The proposed project is conveniently
located close to LIngampally Railway Station
at 4.0 Km, while Kondapur Bus depot at 2.0
km distance. As the unit is located in city
area hence required infrastructures is
located nearby the project site. Other basic
infrastructural amenities like safe drinking
water, electricity, market, and medical
services are available around the proposed
project.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 14
7.3 Will the project cause adverse
effects on local communities,
disturbance to sacred sites or other
cultural values? What are the
safeguards proposed?
No, Project is not likely to have any adverse
effect on local population; rather the local
population will get benefit arising due the
proposed project.
8. BUILDING MATERIALS
S.No. ITEM DETAILS
8.1 May involve the use of building
materials with high-embodied
energy. Are the construction
materials produced with energy
efficient processes? (Give details of
energy conservation measures in
the selection of building materials
and their energy efficiency)
The basic materials used will be cement,
steel, bricks, stones, ready mix concrete,
sand, gypsum, plywood, hard wood,
aluminum, glass, etc.
Low energy embodied materials will be
given preference.
Energy efficient construction materials
such as Gypsum Plaster Concrete, Sand
Aggregate, Fly Ash Cement, will be used
to achieve the desired primary energy
efficiency.
Ready Mix concrete will be used for
construction of RCC structures. M-sand will
be used as an alternative to river sand
and the building blocks will be solid
cement blocks that are energy efficient
and work efficient compared to baked
bricks.
Ensuring that the building materials and
products have low energy embodied
energy.
Minimizing the transport of temporary
structures, scaffolding, formwork,
consumables and building product to the
construction site.
Minimizing overall waste and the transport
of waste from site.
Use of energy efficient lighting.
Ensuring idle construction equipment is
throttled down or switched off
All the items to be used in the project are as
per the National Building Code-2005 and
ECBC.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 15
8.2 Transport and handling of materials
during construction may result in
pollution, noise & public nuisance.
What measures are taken to
minimize the impacts?
During the construction phase, the following
measures will be taken to prevent pollution.
Top soil excavated during construction
activities will be stored for use in
horticulture/landscape development
within the project site to the possible
extent
Covering of the construction site from all
four sides to a substantial height to
prevent dust emissions and other
pollutants into surrounding area.
Covering loads to limit materials or litter
blowing off and reducing smells.
Ready mix concrete will be used for
concreting. This avoids cement and
aggregate handling fugitive emissions and
noises.
Noise machines will be preferred after
10.00 am. Loading and unloading will be
done with low height.
Unloading of construction material will not
be done during night
Water spraying to prevent dust pollution
from different sources of construction.
Speed restriction of all the vehicles
approaching the site and within the site.
All transportation vehicles will be suitably
covered with tarpaulin & overloading of
the vehicles will be avoided and must be
pollution checked vehicle.
Heavy earth working will be avoided
during night.
8.3 Are recycled materials used in
roads and structures? State the
extent of savings achieved?
The excavated soil will be used for backfilling
as well as for creating landscaped areas.
8.4 Give details of the methods of
collection, segregation & disposal
of the garbage generated during
the operation phases of the
project.
The estimated quantity of garbage will be
around 4900 kg/day of. It is proposed to
segregate the wastes and will be given to
GHMC waste collection center for disposal
to municipal solid waste management
facilities
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 16
9. ENERGY CONSERVATION
S.No. ITEM DETAILS
9.1 Give details of the power
requirements, source of supply,
backup source etc. What is the
energy consumption assumed per
square foot of built-up area? How
have you tried to minimize energy
consumption?
The source of the Power is from TSCPDL.
Power requirement: 11195 KVA
Backup power: 6 x 500 KVA DG sets for
emergency during power failure.
Energy saving measures proposed to
minimize energy consumption is as follows.
1) Use of energy saving methods in AC
cooling and lift (V3F) in place of
conventional methods
2) Corridors, walkways and staircases
have been provided with natural lighting to
the maximum extent possible
3) Use of Compact fluorescent lamps (CFL)
& low voltage lighting.
9.2 What type of, and capacity of,
power back-up to you plan to
provide?
6x 500 KVA DG sets will be used as backup
power for emergency during power failure.
APFC panel will switch the above loads onto
DG supply within 10 – 12 seconds. In case of
repair/ maintenance or operational difficulty
with any DG set, DG sets will be manually
interchangeable to cater only to the critical
loads. HSD requirement will be 300 Litres.
9.3 What are the characteristics of the
glass you plan to use? Provide
specifications of its characteristics
related to both short wave and
long wave radiation?
The type of glass proposed to be used will be
plain glass with have low conductance and
high insulation properties so that heat ingress
into the inside of the building will be
minimized. This will help to reduce the heat
gain in the building.
9.4 What passive solar architectural
features are being used in the
building? Illustrate the applications
made in the proposed project.
Passive solar cooling is incorporated in the
building design. Buildings are suitably
oriented for ensuring natural ventilation and
day lighting.
Building design and envelope may be
optimized through selection of appropriate
wall and roof construction and through
adoption of solar passive measures after
studying the sun path analysis to provide
shading devices for windows and roof which
would reduce energy demand.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 17
9.5 Does the layout of streets &
buildings maximise the potential for
solar energy devices? Have you
considered the use of street
lighting, emergency lighting and
solar hot water systems for use in
the building complex? Substantiate
with details.
Solar power facilities shall be used for
external lightning.
Paving onsite (open area surrounding
building premises) is reduced to the extent
possible to minimize the imperviousness of
the site and shade will be provided on hard
paved surfaces to minimize heat island
effect.
Passive solar cooling will be incorporated in
the building design. Building will suitably
orient for ensuring natural ventilation and
day lighting.
Solar panels will be used for the common
area lighting load.
9.6 Is shading effectively used to
reduce cooling/heating loads?
What principles have been used to
maximize the shading of Walls on
the East and the West and the
Roof? How much energy saving
has been effected?
Walls.
East and West Elevations.
Walls that face the east and west will be well
insulated as possible, to prevent summer
heat gain from the low morning and evening
sun.
Roof:
Brickbats will be placed on the flat roof to
give a slope and then grouting the same
with cement mortar admixed with some
water proofing compounds.
9.7 Do the structures use energy-
efficient space conditioning,
lighting and mechanical systems?
Provide technical details. Provide
details of the transformers and
motor efficiencies, lighting intensity
and air-conditioning load
assumptions? Are you using CFC
and HCFC free chillers? Provide
specifications.
Automatic power factor compensating
multiple capacitor units are provided for
maintaining of average power factor of
0.99 to have effective savings in energy
cost. All capacitors are provided with
Harmonic Filters to avoid distortion in
Voltage i.e. Clean Power is available to
building.
An APFC relay based on thyristerised
switching is proposed to effect the power
factor correction /improvement within a
few cycles of deviation from the setting &
also to reduce inrush currents.
All cables shall be derated to avoid
heating during use. This also indirectly
reduces losses and improves reliability.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 18
Lighting System:
The recommended illumination levels (in
Lux) as per the National Building Code of
India (2005) will be applied
9.8 What are the likely effects of the
building activity in altering the
micro-climates? Provide a self-
assessment on the likely impacts of
the proposed construction on
creation of heat island & inversion
effects?
Heat emission from the project can be from
the following sources:
Heat absorbed and radiated from the
paved and concrete structures.
Increased population for a particular
stretch of land.
Any building activity would alter the
microclimate of a site and it is inevitable that
wind patterns and thermal gain patterns on
a site would be changed. But the proposed
building has been carefully designed to
modify the microclimate so as to improve
overall thermal comfort and reduce energy
consumption.
Shade giving trees are planted near the east
and west side which affect the microclimate
and provide cooling effect in summers.
9.9 What are the thermal
characteristics of the building
envelope? (a) roof; (b) external
walls; and (c) fenestration? Give
details of the material used and the
U-values or the R values of the
individual components.
The building materials will be selected with
characteristics that limit heat ingress into the
inside of the building will be minimized.
U value
(W/m2-°C)
R value
(m2-°C/W)
Roof 0.261 3.5
Wall 0.352 2.35 Source: ECBC CODE 2005
9.10 What precautions & safety
measures are proposed against fire
hazards? Furnish details of
emergency plans.
Essential fire safety measures will be installed
into the building to ensure the safety of the
occupants within the building in the event of
fire or other emergency.
The entire building will be designed as per
NBC-2005 of India pertaining to fire hazards.
Safety measures:-
Proper fire exits and exit signs in case of
any emergency will be made available.
Fire extinguishers of appropriate type will
be placed on a readily accessible place
and will be maintained accordingly.
M/s. SMR Builders Pvt. Ltd.- SY.NO’S. 113 to 119, 121 & 126 Kondapur (V) Seri Lingampally (M) RANGA REDDY (DIST), TELANGANA STATE
PRIDHVI ENVIROTECH (P) LIMITED Page 19
9.11 If you are using glass as wall
material provides details and
specifications including emissivity
and thermal characteristics.
The type of glass proposed used have low
conductance and high insulation properties
so that heat ingress into the inside of the
building will be minimized. This will reduce the
air conditioning load.
9.12 What is the rate of air infiltration into
the building? Provide details of how
you are mitigating the effects of
infiltration.
The design is based on maintaining positive
pressure in the conditioned areas. As such
there shall be no outdoor air filtration into the
conditioned areas. However measured
amount of outdoor air will be introduced in
the HVAC system to maintain “INDOOR AIR QUALITY” as per international standards.
9.13 To what extent the non-
conventional energy technologies
are utilized in the overall energy
consumption? Provide details of the
renewable energy technologies
used.
The solar energy will be utilized efficiently for
Solar light for external lighting.
10. Environment Management Plan
The Environment Management Plan would consist of all mitigation measures for each
item wise activity to be undertaken during the construction, operation and the entire
life cycle to minimize adverse environmental impacts as a result of the activities of the
project. It would also delineate the environmental monitoring plan for compliance of
various environmental regulations. It will state the steps to be taken in case of
emergency such as accidents at the site including fire. A total of Rs. 1.5 Crore is
allocated for implementation of EMP
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 1
EXCUTIVE SUMMARY
M/s. SMR Builders (P) Limited is one of the leading construction group
is in existence over 2 decades. It has executed several residential and
commercial complexes in Hyderabad and Bangalore.
M/S SMR Builders proposed to develop a residential project at Sy No.
113 to 119, 121 & 126 in Kondapur (V), Serilingampally (M), Ranga
Reddy (D) and obtained TOR vide File No. F.No.21-54/2015-IA. III dated
18.06.2015. As there are changes from the original plan, this application
is made for amendment of previous TOR
Following changes are proposed from the previously approved TOR
S.NO DISCRIPTION PREVIOUS PROPOSED
1 Total area of the plot 47,825.36 Square
meters
47,825.36 Square
meters( No change)
2 Total Built up area
including parking
3,95,849.3 Square meters
5,21,969.53
Square meters
3 Number of blocks 7 Blocks 7 Blocks (No
Change)
4 Total No. of flats 1699 1956
As the total area proposed to be developed is more than 1, 50,000
Square Meters, as per the EIA notification 2006, this comes under B1
category. Now this application is submitted for TOR approval for the
changes in the project for conducting necessary EIA Studies for
clearance of the project.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 2
1. 0 ABOUT PROMOTERS
Over the years SMR Holdings' flagship company SMR Builders Pvt. Ltd.
has perfected the art of building dreams. A pioneer and expert in the
construction of residential/housing projects, it takes pride in its project
management and quality control expertise. The quality control team
ensures topnotch quality while the project management team makes
sure schedules are met and promises kept.
The company has always created wonderful homes, excellent shopping
complexes and functional office spaces. Breathtaking landscaped
gardens, awe inspiring elevations and Vaastu compliant interiors make
every venture an architectural marvel.
SMR Holdings has been developed 7.5 million sq.ft. of commercial and
residential spaces. Further 4.5 million sq.ft. of premium living spaces
across Bangalore and Hyderabad is on its way. First SMR Holdings has
always set benchmarks and will now raise the bar in providing quality
construction
Some of the prestigious projects executed by SMR Builders are
Hyderabad Projects
SMR VINAY PRANGAN
Residential Apartments Madhapur
SMR VINAY ACROPOLIS
Residential Apartments Madhapur
SMR VINAY METROPOLIS Residential Apartments
Miyapur
SMR SRUJANA Residential Apartments
Sanjiva Reddy Nagar
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 3
SMR VINAY VISION
Residential Apartments
West Marredpally
SMR ARCADE
Shopping/Offices/Residences
Chikkadpally
EXCELLENCY APARTMENTS Residential Apartments
Malakpet
PRUTHVI MANSIONS Residential Apartments
Domalguda
SMR SARTAJ PLAZA
Commercial cum Residential Complex Sikh Road
SMR EMPIRE
Residential Complex West Marredpally
SMR RAM RESIDENCY Residential Apartments
West Marredpally
SMR HABITAT Residential Apartments
West Marredpally
DAYASHANKAR'S SMR SQUARE
Residential Apartments New Boiguda
SMR SOWMYA
Residential Apartments West Marredpally
Bangalore Projects
SMR VINAY REGENCY Commercial & Residential Apartments
Horamavu Ring Road
SMR VINAY ESTATES Commercial Complex
Horamavu Ring Road
SMR CASTLE Residential Apartments
Dhodda Banaswadi
SMR VINAY CASCADES Residential Apartments
Bangalore
SMR HEIGHTS
Residential Apartments Dr.C.V.Raman Road
SMR HERITAGE
Residential Apartments Thippasandra
SMR VINAY HARMONY
Residential Apartments Banaswadi, Main Road
SMR VINAY SAPPHIRE
Residential Apartments Banaswadi, Main Road
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 4
SMR VINAY VATIKA
Residential Apartments
Maruthi Seva Nagar
The Vision and Mission of SMR Builders
Vision, Mission & Values
Vision
To deliver high value and good quality construction coupled with on time delivery schedules. Qualified professionals and self directed teams work relentlessly towards elevating customer satisfaction levels.
Mission
To retain its position as one of the leading construction houses in South India by continuously innovating and constructing quality eco-friendly
structures.
Values
At First SMR Holdings every customer is valued and every effort is
directed to deliver beyond all expectations. Fulfilling promises, providing affordable housing solutions, delivering honest results and transparency
have always been the company’s prime strengths. The company also takes up a number of social service and community building activities.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 5
2. 0 ABOUT THE PROJECT
2.1 SALIENT FEATURES OF THE PROJECT
M/S SMR Builders acquired a semi developed site with an area of 86,401
Square meters of land at Sy. NO. 113 to 119, 121 & 126 in Kondapur
(V), Serilingampally (M), RR District, Telangana.
M/S SMR Builders proposed to develop a residential project at Sy No.
113 to 119, 121 & 126 in Kondapur (V), Serilingampally (M), Ranga
Reddy(D) and obtained TOR vide File No. F.No.21-54/2015-IA. III
dated 18.06.2015. As there are changes from the original plan, this
application is made for amendment of previous TOR
TABLE 2.1 PROJECT AT A GLANCE
Feature Details
Total Area of development in Phase II 47,825.36 Square meters
Total Project cost Rs. 525 Crores
Total No.of flats 1956 Flats
Total Built up area including parking 5,21,969.53 Square meters
Location Sy. No. 113 to 119, 121 & 126,
Kondapur (V), Serilingampally(M),
RR District, Telangana
Longitude 170 28’ 02.3” N & 170 28’ 13.8” N
Latitude 780 20’ 0.6” E & 780 20’ 14.0” E
Distance from Nearest Air Port Shamshabad Airport – 40
kms
Distance from Nearest Village Part of Kondapur Village
Total water requirement 1352.0KLD
Source of water 70% from HMWS & SB & Bore well and 30% recycled
Total Area for greenbelt 7280.52 Sq.mts
Total investment for environmental Infrastructure and Green belt
development
Rs 1.5 Crores
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 6
2.2 ABOUT THE SITE
2.2.1 LOCATION DETAILS:
Features of the site:
The area comes under residential zone as per the Master Plan of HMDA
GO MS NO. 288, MA dated 03.04.2008. Copy of the certificate confirming
the same is enclosed at Annexure I
The site is adjacent to Hitech city to Atapur road. The geographical co-
ordinates of Residential complex are between 170 28’ 02.3” & 170 28’
13.8” N latitude and 780 20’ 0.6” E & 780 20’ 14.0” longitude. Mean
Elevation above MSL is varying between 573 meters to 580 Meters
2.2.2. Accessibility & Existing Road network
The proposed site is in Sy. No. 113 to 119, 121 & 126, in Kondapur (V),
Serilingampally (M), RR District, state of Telangana The Site is
connected to Old Mumbai Highway (36 Meters Road) in the Western side
at a distance of 0.21 KM and Kothapeta – Gachibouli Road in Eastern
side. The site is adjacent to Majid Banda Road which is currently 24
Meters Road but expanding to 36 Meters Road.
2.2.3 .Topography & Surrounding features of the site
The Land is undulated area with elevation difference of about 7 meters.
Following are the surrounding features of the proposed site
South Direction - State Bank Institute of Rural Development premises
North Direction - Sudarsan Nagar (Residential Colony)
Eastern Direction - Neighbor’s Vacant Residential plots
Western Direction – Sudarshan Nagar (Residential Colony
Topo sheet of the area is given at Figure 2.1. Base map of the Area is
given at Figure 2.2, photographs of the site are given at Figure 2.3
and Location map is given at Figure 2.4
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 7
2.2.4. Water Bodies & other features of the site and 10 KM radius
The major surface water bodies within the 10 kms radius are Osman
Sagar at about 8.4 KM in the upstream of the site in the South Western
Direction, Durgam Cheruvu is at about 8.0 KM in the North Eastern
direction of the site.
Kothaguda RF is at about 2.3 KM from the proposed site in the North
Eastern direction
2.2.5 Ecologically sensitive Areas
Kasu Brahmananda Reddy National Part is at about 9.6 KM from the site.
However no eco sensitive zone was declared around the Park and no
restrictions are in place on developmental activities
The Salient features of site and surroundings are given in the table
below
TABLE 2.1: SALIENT FEATURES OF PROJECT SITE
Village
Mandal
District
Kondapur
Seri Lingampally
Ranga Reddy
Longitude 170 28’ 02.3” N & 170 28’ 13.8”
Latitude 780 20’ 0.6” E & 780 20’ 14.0”
Ambient Temperature Minimum 100 C
Maximum 430C
Humidity 55 – 65 %
Rainfall 800 – 1100 mm per Annum
Climate Tropical & Semi-Arid
Type of soil Hard Morum soil with outcraps
Distance from Urban area Within the urban area
Distance from nearest Air
Port
Shamshabad Airport – 40 kms
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 8
Distance from nearest
village
Part of Kondapur Village
Distance from nearest
surface water source
Osman sagar – 8.4 kms
upstream
Reserve Forest Kottaguda RF – 2.3 kms
Any historical monuments
within 10 KM radius
None
Any ecologically sensitive
areas within 10 KM radius
Kasu Bhramananda Reddy
National Park - 9.6 kms
Topography Plain and land locked
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 9
FIGURE NO: 2.1 – TOPO SHEET OF THE AREA – 10 KM RADIUS
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 10
Figure 2.2 Base Map of the Area
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 11
Figure 2.3 Site photographs
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 12
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 13
FIGURE 2.4
LOCATION MAP OF THE SITE
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 14
3.0 Conceptual Plan
3.1 Total Plot Area
SMR Builders acquired a total of 21.35 Acres of land in residential zone.
After leaving area for Road widening of t he adjacent road from current
24 Meters to 36 Meters, the site is proposed to be developed in two
phases. In the first phase 37,989.59 Square meters are proposed to be
developed for which an application for getting Environmental Clearance
is already filed. In the second phase it is proposed to develop rest.
Below table gives overall area statement of the site
Table 3.1
Overall Area statement of the plot
S.No Land use Area in Square Meters
1 Total Plot area 86,401.00
2 Area affected for road widening
1,192.76
3 Net Area available for
development
85,208.24
4. Net area proposed to be
developed in 1st Phase ( EC application is under
process in MOEF)
37,989.59
5 Net area proposed to be
developed in Phase II
47,825.36
3.2 Development plan for Phase II:
This application is made for environmental clearance for the
development plan in Phase II activities. It is proposed to develop 7
residential blocks, and Amenities block. Total green belt area proposed
in this phase is 7280.52 Square Meters which is about 15.20 % of total
area which almost more than the statutory requirement in the State of
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 15
Telangana. Overall area statement of plot in Phase II is presented in
the Table 3.2 below
Table 3.2 Development Plan of the Phase II
S.NO Land Use Plinth Area in square meters
1 Residential block
( Plinth Area)
13252.03
2 Amenities 2510.26
3 Utilities 1920.44
4 Green belt 7280.52
5 Roads 10438.39
6 Vacant Areas (Set backs & other vacant space)
12123.72
Total area 47,825.36
3.3 Details of Residential Blocks & Flats:
It is proposed to develop 7 Residential blocks and amenities as detailed
below
TABLE 3.3 – NUMBER OF FLOORS AND AREA
S.
No
Block Details No. of Floors Area
(Sq.Mts)
1 Block-I A 25 44094.24
2 Block-I B 20 40245.6
3 Block-II A 25 33281.25
4 Block-II B 20 25656.80
5 Block-III 28 39226.6
6 Block - IV 28 96701.36
7 Block - V 40 80291.2
Total Main
Block
3,59,497.05
8 Amenities Blocks 9 20000.0
Total 3,79,497.05
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 16
Below Table gives block wise flats details proposed in Phase II
Table 3.4
Block wise Flats
Sl Description Block
IA Block
IB Block-
IIA Block IIB
Block - III
Block IV
Block - V
Total
1 No of floors 25 20 25 20 28 28 40
2
No of 2 BHK
flats
150 60 125 40 56 84 -- 515
3 No of 3 BHK flats
100 160 100 80 140 308 -- 888
4 No of 4 BHK flats
25 20 -- 20 28 28 80 201
5
No of 5BHK
flats
-- -- -- -- -- 112 240 352
Total 2BHK,
3 BHK ,4 BHK ,5 BHK
Flats
1956
3.4 PARKING AREA:
The total area allocated for parking is 1, 42,472.48 Sq.Mts, which can
accommodate 3600 four wheelers and 2000 two wheelers. The total
parking area is being proposed in the proposed project is given below.
TABLE 3.5 – PARKING SPACE PROVISION
BASMENT – 1
SQ.MTS
BASMENT – 2
SQ.MTS
BASMENT – 3
SQ.MTS
BLOCK I 10184.58 10184.58 10519.62
BLOCK II 8774.68 8774.68 9065.25
BLOCK III 4544.98 4544.98 4702.12
BLOCK IV 11688.48 11688.48 12070.95
BLOCK V 9620.62 9620.62 9937.87
Amenities Block
2183.33 2183.33 2183.33
TOTAL 46996.67 46996.37 48479.14
The conceptual Plan for the Phase II is given at Annexure II
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 17
3.5 ROADS & SET BACKS
As it is seven blocks of residential complex with amenities block and
parking area is provided in cellars, direct paved road from gate to cellar
areas would be provided. 12 Meter internal peripheral road is proposed
in the development of the site. Set backs as per the Building Norms in
the state would be left as detailed in the below table for free
movement of fire tender which is more than the Telangana state Fire
services directorate guidelines.
Table 3.6
Setbacks for the blocks Norms Vs Actual Proposed
S.No Block Height of
block In meters
Set back as
per Building
Norm in Meters
Set Back
proposed in Meters
1 Block IA 77.0 18.5 18.5
2 Block IB 62.0 17.0 18.5
3 Block IIA 77.0 18.5 18.5
4 Block IIB 62.0 17.0 18.5
5 Block III 86.0 19.5 19.5
6 Block IV 86.0 19.5 19.5
7 Block V 122.0 23.0 23.0
8 Amenities
Block
30.0 10.0 10.0
3.6 STORM WATER DRAINS:
All along the block of the housing complex, storm water drains would
be provided to collect water during rains. They would adequately sized
to prevent over flooding of the site. Storm water collection sump is
proposed before discharging to municipal sewers.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 18
4.0 RESOURCE REQUIREMENTS
4.1 WATER REQUIREMENT:
As per National Building Code, 2005 (NBC), water requirement for
occupants is 135 litres/day/ person and for visitors the requirement is
15 litres/day/person. The total population likely to be accommodated
would be around 9800 people. Another 20 people would be there like
security and other support staff. Thus total water requirement for
inmates is estimated at 1320 KLD. Quantity estimated for guests and
visitors is estimated at another 10 KLD. Considering washings of floors
and other requirement, a total requirement is estimated at 1330 KLD.
Out of this, it is estimated that 440 KLD of water would be required for
toilet flushing’s and rest for other uses. Also it is estimated that about
22.0 KLD of water is required for landscaping and plantation purposes.
Thus total water requirement would be 1352 KLD.
It is proposed to source water from HMWS & SB & Borewell and the
treated waste water would be recycled for toilet flashings and green
belt. Any additional treated waste is there, same will be connected to
municipal sewer.
The total sewage water generated is 1150 KLD. It is proposed to treat
the sewage in STP of capacity of 1300 KLD. The treated waste water is
used for Flushing & gardening (462 KLD). Rest of the 688 KLD of
treated water would be send to municipal sewer. Thus the total fresh
water requirement during occupational stage is would be 890 KLD as
detailed below
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 19
TABLE 2.6 – WATER REQUIREMENT
S.N
o
Stream Quantity
(KLD)
Fresh/
Recycled
Waste
water generated
in KLD
Method of
treatment
1 Domestic
Water
890.0 Fresh 710.0 STP
2 Toilet Flushing water
440.0 Recycled 440.0 STP
3 Gardening 22.0 Recycled - -
Losses 202.0
Total 1352.0 1352.0
4.2 POWER REQUIREMENT:
The power requirement for the proposed project is estimated as
11195 KVA which will be sourced from the TSCPDL
4.3 BACK-UP POWER DETAILS:
It is proposed to provide emergency power back up for lifts, water
pumping and common area lighting with two DG sets of 6 X 500
KVA capacities.
4.4 FUEL REQUIREMENT:
The fuel requirement for 6 x 500 KVA is 900 Liters/day for 8 hours
operation of DG sets due to power outage. The fuel used in DG sets is
High Speed Diesel (HSD).
4.5 MAN POWER REQUIREMENT:
The maximum man power required for the development of proposed
project during construction phase is 100 persons. And during
occupational phase it would be around 20 people
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 20
5.0 POLLUTION SOURCES – CHARACTERISTICS &
QUANTIFICATION
5.1 POLLUTION SOURCES
Pollutants generated due to project activities during both the
construction and operation phase are solid, liquid and gaseous in
nature. Also the generation of pollution could be continuous, periodic or
accidental. Sources of pollutants and their characteristics during the
construction and operation phase are given below in Table 5.1.
TABLE 5.1: POLLUTANT SOURCES AND CHARACTERISTICS
S.
No
Activity/Area Pollutant Pollutant
Characteristics
Frequency
CONSTRUCTION PHASE
1. Ground
working and leveling
Air emissions
– PM, NOx, SO2, CO
Dust from
construction activities and
excavation. Particulate
matter, NOx and CO from
vehicle exhaust
Temporary
during construction
phase only- bulk of the
emissions are expected from
ground working and leveling
activities.
Earth / solid waste
Solid waste from
construction activity and
excavation.
Periodic.
Noise Noise generated
from
construction equipment and
Machinery
Temporary
during initial
construction phase
2. Labour Camps Sewage Sewage
generated from temporary labor
Temporary –
during the initial
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 21
S.
No
Activity/Area Pollutant Pollutant
Characteristics
Frequency
camps on site construction phase
Solid Waste Solid Waste
generated from temporary
labour camps on
site
Temporary –
during the initial
construction
phase
OPERATION PHASE
1. Vehicular movement
Air emissions and noise
Vehicle exhaust emissions
Continuous / Periodic
2. Diesel power
generators
Air emissions SO2, NOx, SPM,
CO from fuel burning
Periodic, only
during power failure
Noise Noise due to running of
equipment
Periodic
Waste Used Oil Generation
Periodic, during oil changes
3. Residential Wastewater Wastewater containing
food matter
Continuous / Periodic
Domestic Solid waste
Garbage / Food waste
Continuous
4. Raw water treatment
Wastewater Backwash water discharge
Continuous
Solid waste Sludge from
coagulation process
Continuous
5. S.T.P Solid waste Settled and stabilized sludge
Continuous
Treated
water
Treated sewage
water used for
Greenbelt
Continuous
6. Diesel Storage Solid waste Settled sludge
during tank
cleaning
Occasional
Oil Oil spillage –
Accidental large spills due to
pipe rupture Oil Spillage -
Small quantities
Accidental /
Only due to poor
housekeeping
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 22
S.
No
Activity/Area Pollutant Pollutant
Characteristics
Frequency
due to small pipe leaks
7. Maintenance /
housekeeping
Wastewater Floor washing Continuous
Solid waste Used equipment parts and
garden wastes
Continuous
8. Vehicle Parking
Area
Oil Spills Minor oil leaks
in parking lot
Continuous –
small Quantities
9. Storm water
drains
Wastewater Contamination
discharge from site – Mainly
suspended solids
During rainy
season
5.2 AIR EMISSION SOURCES
Air emissions have no boundaries and can migrate between areas
depending upon the wind direction and speed.
5.2.1 PREDICTED AIR EMISSIONS FROM THE SITE
CONSTRUCTION PHASE
During the construction phase, PM is expected to be the main pollutant
associated with on-site roads (paved and unpaved), stockpiles and
material handling. In this case, pollution emission sources shall be
distributed throughout the project site and shall fall under the category
of area source. The land acquired is fairly flat, so extensive formation
work is not expected during this phase. It is assumed that most of the
excavated material shall be used within the project, with minimal cut
and fill material to come from outside the site.
Due to the confined nature of heavy construction activity during this
limited period, tailpipe emissions from construction equipment are
assumed to be essentially negligible.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 23
OPERATIONAL PHASE
During the operational phase, the diesel generator sets to be operated
for back-up power supply are the major source of air pollution. From
this point source, the following pollutants are expected;
PM, SO2, NOx and CO
Diesel Generator Set Fuel Combustion - Point Source
To serve as a emergency power back-up, 6 diesel generators of 500
KVA connected to individual stacks shall be installed. The diesel
generator sets are operated only during power failure thus conserving
fuel and reducing the pollution.
As a worst-case scenario, emissions were predicted assuming an
operation time of 24 hours. The emissions from the diesel generators
are provided in the following table:
TABLE 5.2 – DIESEL GENERATOR SET EMISSIONS
Capacit
y of DG
Set
No. of
DG Sets
Stack
Height
(m)
Diame
ter of Stack
(m)
Temp.
of exhaust
gases (0C)
Exit
velocity
(m/sec)
Pollutant
Emission rate (g/sec)
SPM SO2 NOx
500 KVA 6 5 mts 0.4 250 12.5 0.04 0.08 0.32
5.3 NOISE EMISSIONS SOURCES
The assessment of the impacts of noise on the surrounding community
depends upon:
Characteristics of noise source (instantaneous, intermittent, or
continuous in nature, with the latter contributing the least to
noise pollution);
Time of day at which noise occurs; and
Location of noise source with respect to noise sensitive receptor.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 24
CONSTRUCTION PHASE
The description of construction activity as detailed in Section 4.2.1
(with regards to spatial phasing and type of sources) is also pertinent
to the noise emissions emitted in the construction phase. Sources of
noise emissions are expected from various types of construction
equipment.
General noise levels generated from the operation of equipment and
machinery are provided in Table 5.3 below:
TABLE 5.3: NOISE LEVELS GENERATED FROM CONSTRUCTION
EQUIPMENT
Name of the source
Noise Level at 16 m (50 ft)from Source
in dB (A)
Noise Level at 1 m from Source (calculated)in
dB(A)
Air Compressor 87 111
Back Hoe/Loader 81 105
Concrete Mixer Truck 85 109
Concrete Pumper 70 94
Concrete Vibrators 77 101
Cranes - mobile 81 105
Dump Truck 83 107
Generator Not Considered 75 (CPCB)
Hammering 86 110
Jackhammer 88 112
Pile Driver 100 124
Radial Arm Saw 80 104
Source:www.gvrd.bc.ca/education/pdf04/ColumbiaWorkshop1-
ConstructionNoise.pdf
The MoEF has not yet prescribed noise emission specifications for
construction equipment. However, the limited information available is
provided in Table 5.4.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 25
TABLE 5.4 – NOISE LIMITS FOR APPLIANCES AND
CONSTRUCTION EQUIPMENT AT MANUFACTURING STAGE
Equipment Noise Limit dB
(A)
Window Air Conditioner(1ton -1.5
tons)
68
Air Coolers 60
Diesel Generators 85-90
Compactors (rollers), Front Loaders, Concrete Mixers, Cranes(movable),
Vibrators, and Saws
75
Source: http://dpcc.delhigovt.nic.in/pdf/Pollution_Control_Law.pdf
OPERATIONAL PHASE
During the operational phase, the diesel power generators will be the
major source of noise.
Diesel Generator Sets
Noise Limit for Generator sets run with Diesel
Noise limit for diesel generator sets (6 X 500 KVA) manufactured on or
after the 1st January, 2005.
The maximum permissible sound pressure level for new diesel
generator (DG) sets with rated capacity 6 X 500 KVA, manufactured on
or after the 1st January, 2005 shall be 75 dB(A) at 1 meter from the
enclosure surface.
Noise control for diesel generator will be as follows:-
Noise from DG set shall be controlled by providing an acoustic
enclosure or by treating the room acoustically, at the users end.
The acoustic enclosure or acoustic treatment of the room shall be
designed for minimum 25 dB (A) insertion loss or for meeting the
ambient noise standards, whichever is on the higher side ( if the actual
ambient noise is on the higher side, it may not be possible to check the
performance of acoustic enclosure/ acoustic treatment. Under such
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 26
circumstances the performance may be checked for noise reduction
upto actual ambient noise level, preferably, in the night time).The
measurement for Insertion Loss may be done at different points at 0.5
m from the acoustic enclosure/ room. The DG set shall be provided
with proper exhaust muffler with insertion loss of minimum 25 dB
(A).These limits shall be regulated by the State Pollution Control Boards
and the State Pollution Control Committees.
Source: www.cpcb.nic.in
5.4 WATER AND WASTEWATER MANAGEMENT
5.4.1 WATER REQUIREMENTS
Water requirement during the construction phase will be met from Bore
well water tankers. The required water during the operational phase will
be sourced from HMWS & SB. However, in the event of non availability
of water or for any excess requirement of water during the operational
phase, the proponents are proposing backup with the aid of rainwater
collection in the reservoirs which will be duly treated, water recycling
and water tankers (in case of water supply failure). It is also
emphasized that at any stage of the project, groundwater reserves
would not be exploited for the water requirement. The water
requirements during various phases of the project are discussed below:
A) CONSTRUCTION PHASE
The project implementation would involve various construction
activities. The following section summarizes the water requirement, its
sources and management of wastewater.
Site development:
Development of site for the proposed development involves excavation,
leveling of the ground surface and stock piling. However as the project
site is flat with no vegetation cover, the leveling activities would result
in very less water usage. Water requirement for any use at this stage
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 27
would be provided from water tankers. Similarly, the generation of
domestic wastewater can be managed on site.
Construction of building infrastructure:
The construction of building infrastructure that includes residential and
other units, Offices, restaurants and multiplex would require water and
may generate waste water too. Water demand during construction
phase would be for:
Construction activities.
Domestic use.
Construction phase may last for a period of approximately two years in
order to complete the earthwork, foundation lying, superstructure
development, service provision and finishing. The water requirement
during construction phase would be around 200 KLD. The water
requirement is being met from the water tankers.
B) OPERATIONAL PHASE
Daily Water Requirement and Sources:
It has been mentioned before that the domestic water requirements will
be met from the Bore well & HMWS&SB Water supply scheme. The
water requirement for Flushing, Gardening, Landscaping and other
purposes would be met from duly treated recycled water. However, in
case of failure of HMWS&SB, water requirements are planned to be met
partly by ground water & through private tankers. Rain water will be
recharged to the ground to augment the water table in the area. Water
tankers will be used only in case of any emergency or failure of water
supply by HMWS & SB or insufficiency of the water reservoir.
Water conservation:
Water conservation is an important part of sustainable living and in
order to optimize the water requirement in the project, the developers
would incorporate the component of water conservation by means of
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 28
rainwater harvesting and water recycling using fixtures which are low
flow and water efficient models such as 3 litre capacity WC flushing
system, sensor operated urinals and taps to minimize the wastage of
water along with employee education and awareness programme and
selective use of dry type urinals. As per the approved plans from
GHMC, various mitigative measures shall be proposed to further
minimize the impacts.
Storm Water Management & Rain Water Harvesting Structures
It is proposed to channelizing the storm water by constructing water
drains leading to the storm water sump. In order to minimize the
surface runoff loss, groundwater recharging through groundwater
recharge pits at the project site has been planned. Appropriate design
considerations have been taken while designing the recharge pits.
5 .5 2 WASTEWATER QUANTIFICATION AND CHARACTERISTICS
The wastewater generation during construction and operational phase
is described below:
A) CONSTRUCTION PHASE
Waste water generation during construction period shall be from
construction labours and construction activities. Wastewater generation
due to construction activities would be very less. Since the project lies
in an urban stretch, preference would be given to the employment of
labours local to the area. This would result in settlement of less labour
colonies in the project site and hence less wastewater generation from
the transit labour settlements. Wastewater generation from labour
toilet shall not exceed 20 KLD. Temporary toilets are planned for labour
during construction phase and waste water would be disposed to
municipal drain
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 29
B) OPERATIONAL PHASE
During this phase, it has been assumed that 80 % of the water supplied
will be discharged as wastewater (Source: Manual on sewerage and
sewage treatment, published by Government of India). Hence
approximately 225.0 m3 per day of domestic effluent would be
generated.
Wastewater generated is expected to have characteristics and pollution
load as shown in Table 5.5
TABLE 5.5
EXPECTED WASTEWATER CHARACTERISTICS AND POLLUTION
LOAD
Parameter Unit Concentration
Quantity KLD 1150
pH -- 6.5 – 8.5
Oil & Grease Mg/l 20
TSS Mg/l 200
BOD Mg/l 300
COD Mg/l 500
The wastewater with the foresaid characteristics can neither be
discharged into in land surface water nor reused. Suitable treatment
would be given to the wastewater so as to meet CPCB requirements
depending upon the end use. It is proposed to install a sewage
treatment plant of capacity 1300 KLD, to recover the recycled water of
quality suitable for use in flushing and gardening. A sewage treatment
plant of 1300 KLD capacity based on Fluidized Aerobic Bio-Reactor
(FAB) technology is proposed to treat 1150 KLD of sewage water
generated in the proposed project. After treatment the water will be
used for Flushing & Gardening.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 30
The treated wastewater shall meet the standard required for discharge
on land for horticulture. Table 5.6 gives the comparison of the
standards that would be met by the treated wastewater and quality
norms prescribed for discharge on land by irrigation.
TABLE – 5.6: DISCHARGE NORMS FOR WASTE WATER
Parameters Quality
Norms Discharge On
land for irrigation
Quality
Norms for Discharge
in inland surface
water
Treated
standard For proposed
project
pH 5.5 – 9.0 5.5 – 9.0 6.5 to 8.5
Biological Oxygen
Demand (BOD3 at 27°C)
mg/l
100 30 <15
Chemical Oxygen Demand (COD)
mg/l
-- 250 <100
Suspended Solids 200 100 <30
Oil and Grease 10 10 <10
5.6 SOLID AND OTHER WASTES
Waste quantification and characterization exercise is being carried out
to estimate the quantum and type of waste that would be generated by
different activities due to proposed project during construction and
operation phase. The estimated quantity and quality of waste would
serve as a baseline for designing collection, transportation, treatment
and disposal options for solid waste generated due to proposed project.
5.6.1 WASTE SOURCES AND QUANTIFICATION
Description of solid and other wastes generated from the site during
construction and operation phases of the project is given in Table 5.7
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 31
TABLE 5.7: SOLID AND OTHER WASTES GENERATED
S.
No.
Activity/Area Waste
Generated
Waste
Characteristics
Frequency of
generation
CONSTRUCTION PHASE
1. Earth Working
and Construction
Construction
Wastes
Earth, Stones,
concrete, bricks, lumber etc.
Larger
quantities will be
generated in
construction phase.
2. Labour quarters
Domestic wastes
Mainly bio-degradable
wastes including food
wastes.
Temporary – during
construction phase.
OPERATIONAL PHASE
1. Residential
areas
Domestic
waste
Biodegradable
wastes (food waste) and non-
biodegradable wastes (paper,
plastics etc.)
Daily
2. Set back area sweepings dust, leaves etc. Daily
3. Utilities
including Power
generation
Waste from
oil
Waste oil Only during oil
changes – six monthly.
4. Sewage Treatment
Plant
STP Sludge Stabilized sludge – to be used as
manure for the landscaping.
Every week – after sludge
drying operation.
Waste quantification has been done based on the activities proposed in
the project master plan. The waste generation for each activity has
been estimated based on National and International standards
applicable in similar setting. The following section gives the details of
the type of waste generated by different activity, waste generation
factors and assumptions used for estimating waste generation.
Waste quantification and characterization exercise is being carried out
to estimate the quantum and type of waste that would be generated by
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 32
different activities due to the proposed project activity during the
construction and operation phase.
5.6.2 WASTE QUANTIFICATION
A) CONSTRUCTION PHASE
Construction activities create solid wastes that need to be disposed.
Such wastes include sand, concrete, gravel, stone, bricks, plastic,
paper, wood, metal and glass. According to a report prepared by the
Technology Information, Forecasting, and Assessment Council (TIFAC),
estimated waste generation during construction and demolition
operations is 60 kg/m2 and 500 kg/m2 respectively (TIFAC, 2001). This
waste after sorting can be used for backfilling in the basement and for
leveling purposes.
B) OPERATIONAL PHASE
Waste quantification has been carried out based on the activities
proposed in the project master plan. Waste generation factors for each
activity are as per the National and International standards applicable
in similar setting. Following section outlines details of the type of waste
generated by different activities.
Residential waste: Domestic garbage is anticipated from the
residential complex. Total solid waste estimated @ 0.5 Kg/day per head
or person. Thus total garbage anticipated from the complex will be
4900 kg/day which is proposed to be disposed to municipal solid waste
disposal facility of MCH through local municipal authorities. About 100
Kgs/Day of solid waste anticipated from sewage treatment plant and
same will be used as manure.
Garden and open spaces: Waste from open spaces and garden
comprise of horticultural waste that will be generated by periodical lawn
mowing and trimming of trees. Horticulture waste generated is based
on the experience in other projects with similar setting. Assumed waste
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 33
generation factor for horticulture waste is 15 kg/acre / day or .0037 kg/
sq m /day. Table 5.8 gives detail of the estimated waste generation
TABLE 5.8 : ESTIMATED WASTE GENERATION FROM DIFFERENT
ACTIVITIES
Facilities Provided
Waste generation norms per unit
No. Of units/Area
Total Waste
Generated (Kg /day)
Residential area 0.5 kg/day/person 1956 flats 4900
Garden &
Open space
15 kg/Acre/day or
0.0037kg/sq m/day
7280.52 27.0
Kgs/day
Total Waste Generated (kg/day) 4927
Kgs/day Say 4950
Kgs
5.6.3 WASTE CHARACTERIZATION
Waste characterization for the proposed project has been carried out on
the basis of waste characterization studies in similar settings. The
following section details the estimated waste generation for proposed
project during construction and operation phases.
A) CONSTRUCTION PHASE
During the construction phase, a considerable quantum (90%) of waste
generated at the project site would be inert waste, which largely
comprising of clay, sand, gravel, untreated wood (natural wood, no
paint), brick, concrete, concrete block, asphalt, pipes, conduits and
light steel material. A major portion of this waste will be used for
backfilling the basement and other leveling purposes.
Table 5.9 gives an estimate of the average composition of waste that
shall be generated from the onsite construction activities.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 34
TABLE 5.9 : WASTE COMPOSITION – CONSTRUCTION PHASE
S. No Constituents Percentage Composition
1. Soil, Sand and Gravel 34.99
2. Brick and Masonry 29.95
3. Concrete 24.98
4. Metal 4.97
5. Bitumen 2.04
6. Wood 2.04
7. Other 1.02
Total 100
Source: Derived from TIFAC Report “Utilization of Waste from
Construction Industry”, 2001
B) OPERATIONAL PHASE
Waste generated during operational phase can be broadly subdivided
into following.
a) Biodegradable
b) Recyclable
c) Non recyclable(Inert)
Table 5.10 shows the estimated composition of waste generated in
proposed project during operation phase.
TABLE 5.10: ESTIMATED WASTE COMPOSITION
S. No Characteristics of
Waste
Units Percentage
Composition
Physical
Characteristics
1. Paper and paper board % 40
2. Glass /ceramics % 5
3. Metals % 3
4. Plastics % 11
5. Rubber and Leather % 1
6. Textile % 2
7. Wood % 1
8. Food waste % 18
9. Others (Garden and
Inert)
% 19
Total 100
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 35
5.7 OTHER STRESSORS LEADING TO ENVIRONMENTAL IMPACTS
5.7.1 Change in Landscape of the site: The landscape of the area
will change with the coming up of proposed project. The large vista,
interconnected lawns and open green areas will change the aesthetics
of the local area.
5.7.2 Stress on Road Network
As it is anticipated about 5000 vehicles are likely to be added to road
net work, there is possibility of stress on road network due to be
implementation of the project
5.7.3 Energy utilization & Conservation :
The total energy load requirement for the site is 11191.26 KVA. Out of
this Energy load for common areas, Lifts, Water Motors, ETP, Cellars &
Basements and Roads and garden area requirement is 167.85 KVA. It
is proposed to adopt the following energy saving measures to save
20% of total load
LED Lighting
Energy Efficient 5 star rated Motors for water and ETP
Energy Efficient 5 star rated Motors for Lifts
Solar lighting for roads and Garden area
Solar water heating system for blocks
Other measures of natural ventilation & Lighting
5.7.4 Safety and Emergency handling system
Elaborate fire fighting system which include fire hydrant system,
portable fire extinguishers, smoke detection & Alarm systems are
proposed for all the residential blocks and cellars. Adequate fire water
is maintained as per the norms prescribed. Adequate set backs are
planed for easy movement of fire fighting vehicles in case of
emergencies
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 36
6.0 IMPACT ASSESSMENT & MITIGATION MEASURES
6.1 IMPACT ASSESSMENT:
The potential impacts on the surrounding environment in the 10km
radial distance of proposed project site along with the mitigation
measures during construction and operational stages are summarized
in Table 6.1 and Table 6.2.
The construction phase is for a period of 24 months. Considering this to
be a relatively short period, all construction impacts can be considered
to be short term and temporary.
As for the operational phase, the project proponent shall ensure that
impacts are minimized and are within applicable/ specified limits by
TSPCB & CPCB by providing relevant pollution control equipment and/
or mitigation measures discussed in the following tables.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 37
TABLE – 6.1 - CONSTRUCTION PHASE - POTENTIAL IMPACTS AND MITIGATION MEASURES
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
1. Water
resources
Minor negative
& temporary impact on
surface & ground water
resources.
Water requirement
of 50 - 70 KLD for construction
activities
Judicious use of water;
minimization of water consumption by use of
high-pressure hoses for dust suppression
Water requirement
will be sourced from the outside water
tanker.
2. Surface water
quality
No impact Erosion and run-off
due to excavation/ construction
activities, especially in
monsoon season;
Discharge of waste water, construction
as well as domestic.
Avoiding excavation in
monsoon season; providing appropriate measures for
erosion and sediment control; providing adequate
sanitation facilities for
workers at site; avoiding discharge of untreated
wastewater in the area.
-
3. Ground water quality
No impact Construction activities
Storage area for fuels, paints, thinners, etc. to be
such so as to avoid chances
of spillage. No discharge to
ground water body.
-
4. Air quality Temporary negative impact
Construction equipment;
operation of DG
Carrying out construction activity in temporary
enclosures, where feasible;
-
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 38
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
sets for construction power
requirement; vehicular traffic;
excavation; concreting; etc.
water sprinkling for dust suppression; regular
maintenance of construction equipment &
vehicles; use of fuel of proper quality; use of
state-of-the-art
construction equipment & methods
5. Noise Medium negative &
temporary
Various construction
activities; material and vehicular
movement
Use of low noise generating state-of-the-art
construction equipment and construction techniques;
providing personnel
protective equipment to workers; providing
temporary enclosure for DG set and other construction
activities, where feasible; avoiding construction work
in the night time
-
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 39
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
6. Land
(i) Land use/ requirement
No impact The total plot area is 86,401 Sq. m.
No land conversion is required as land is a vacant
plot and is designated for Residential complex by
municipal corporation.
Site Premises is designated as
Residential area
(ii) Solid wastes &
land pollution
Temporary
minor negative
impact
Construction
material handling;
construction wastes handling and
disposal
Maintaining proper
inventory control for
reduced waste generation; substitution of hazardous
raw materials by non-hazardous materials, where
feasible; providing proper facility for storage and
handling of fuel oils; disposal of spent oils,
classified as hazardous waste by sale to authorized
third party; proper handling and disposal of construction
wastes; Contractor’s to assume full responsibility
for clearing off construction
wastes
-
(iii) Geology &
Seismicity
No impact Construction of the
Residential
No heavy structure planned
as part of the project
All civil structures
shall be constructed
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 40
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
complex as per earthquake zone classification
7. Ecology Minor positive
impact
Construction
activity causing impact on existing
ecosystem on-site and top soil;
cutting of existing vegetation, if
required;
No trees on the site shall
be cut. In fact green belt will be
developed all along the building boundary, roadside
and lane divider. water sprinkling during
dust generation activities; erosion and sediment
control; noise and fugitive dust control; restricting
construction activity during
night time
No ecologically
sensitive area such as forest/
agricultural land will be used for the
project. Presently, the sites have few
trees. 7280.52 Sq. m to be developed
as greenbelt
8. Socio-economic
(i) Population and literacy rate
Minor negative and temporary
Increase in population due to
possible temporary settling of
construction workers from
outside the study area for the project
Employing local people to the maximum extent
possible
About 50 construction workers
are expected to be employed
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 41
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
(ii) Employment Minor positive & temporary
impact
Availability of construction jobs
Employing local people to the maximum extent
possible
About 50 construction workers
are expected to be employed
(ii) Amenities such
as education, medical, water
supply, sanitation, etc.
No impact Needs of
construction workers;
Employing local people to
the extent possible for construction work; making
adequate provision through the contractors to handle
water, sanitary, medical and fuel requirement of
construction workers to ensure that the existing
infrastructure is not
strained
-
(iv) Transportation Temporary
negative impact
Increased traffic
load due to transportation of
construction materials and
workers
Ensuring that traffic is well
regulated. Use of non-peak hours for material
transportation
-
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 42
TABLE – 6.2 - OPERATIONAL PHASE – POTENTIAL IMPACTS AND MITIGATION MEASURES
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
1. Water
resources
Minor negative
impact on surface water resources
Moderate negative impact
on ground water resources due to
consumption.
Minor positive impact due to
recharge by rainwater
harvesting.
Total water
requirement for the proposed project is
1352 KLD.
(Fresh water 890
KLD & S.T.Precycle462
KLD)
Recycle water will be used
Flushing and Gardening
The fresh water
will be sourced from Bore well &
HMWS&SB.
2. Surface water quality
No impact Discharge of sewage and waste
water from utilities
Recycle water will be used Flushing and Gardening
-
3. Ground water
quality
No impact Discharge of
sewage and waste
water from utilities
No discharge of
wastewater to ground
water body; use of treated sewage water for Flushing,
Gardening
Rainwater from
the rain water
harvesting will be used to recharge
ground water.
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 43
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
4. Air quality Minor negative impact (for SO2,
NOX and HC emissions)
Fuel combustion in DG sets
All emissions will be well within the specified
emissions standards; stack height = building
height +5 mts. for safe dispersal of pollutants;
HSD with 0.25% sulfur content in DG sets;
periodic maintenance of DG sets for reduced
emissions
All emissions well within the
specified limits
5. Noise Minor negative
impact
Noise generating
rotating/ moving equipment
Proper equipment
selection; mandatory acoustic enclosure for DG
sets; regular maintenance of noise generating
equipment; providing personnel protective
equipment to persons
working in noisy areas;
suitable design and
location of utility block; development of suitable
green belt and landscaping
-
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 44
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
6. Land environment
(i) Land use /
requirement
No impact Requirement of land
for the proposed project
47,825.36 Sq.m of area
available for development
Once the project is
operational, no additional land will
be required.
(ii) Solid wastes & land pollution
Minor negative impact
Handling and disposal of
hazardous and solid wastes
Segregation of wet and dry garbage – disposal of
dry garbage through off-site recycling or to
municipal waste collection system and wet waste to
composting at site; disposal of waste lube oils
by sale to authorized third
party; buy-back arrangement for waste
lead acid batteries
Though no solid/ hazardous waste
will be disposed off on land,
chances of inadvertent
occasional spillage on land cannot be
ruled out
(iii) Geology &
Seismicity
No impact Improper building
design not adhering to specified codes;
improper building
maintenance
Regular maintenance of
the structures to withstand natural phenomena;
carrying out the structural
integrity testing
-
9. Ecology No impact Emissions and
discharges from project operations;
All emissions and
discharges including noise will be within specified
-
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 45
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
noise generation; improper disposal of
wastes
standards; all solid/ hazardous waste will be
disposed off in environmentally sound
manner
10. Socio-economic factors
(i) Population and
literacy rate
No impact Increase in
population due to settlement of
personnel and their families from
outside the study area for the
proposed project
Employing personnel from
within the study area to the extent possible, subject to
availability of skilled manpower requisite to the
job requirement
About 20
personnel would get direct
employment from the project
(ii) Employment Medium positive impact
Direct employment of personnel for
proposed project.
Employing personnel from within the study area to the
extent possible, subject to availability of skilled
manpower requisite to the job requirement
Approximately 20 persons Direct
employment and 20 persons
indirect employment are
expected to be employed for the
project
(ii) Amenities such as education,
No impact Requirement of various facilities
Employing personnel from within the study area to the
Various amenities in the study area
RESIDENTIAL COMPLEX – PHASE II SMR BUILDERS PVT LTD, Sy.No 113 to 119,121&126, Kondapur (V), Seri lingampally (M),Rangareddy(D), Telangana State.
Pridhvi Envirotech (P) Ltd Page 46
S.
No.
Environmenta
l components
Potential
impacts
Source of impacts Mitigation measures Remarks
medical, water supply,
sanitation, etc.
for the children of personnel
employed from outside the study
area
extent possible, subject to availability of skilled
manpower requisite to the job requirement
are adequate.
(iv) Transportation Medium negative impact
Burden on the existing road
infrastructure due to the increased
traffic from the proposed project
Ensuring that vehicular movement is controlled
during peak traffic hours; providing bus services from
the office to the nearest railway station; encouraging
car-pools for office employees
-
SMR Builders Private Limited
47 Pridhvi EnviroTech(P) Limited