Applying the Pearl Rating System

Envelope Thermal Performance Compliance

Page 2: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Outline

• Introduction

• Site Audit Stages and Process

• Case Study – Envelope Thermal Performance

• Final Remarks

• Questions

Page 3: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Introduction

Page 4: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Pearl Rating System Process

Page 5: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Estidama Projects on the Ground

Abu Dhabi

Al Ain

Western Region

90

49

12

69

31

11

38

7

6

0

2

0

Completed

Under Construction

Awarded

Total Submitted

Page 6: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Sustainable Legacy

• Estidama is now part of Abu Dhabi’s Built Environment

• We now have over 100 projects with a Design Rating

• Of this, we have over 50 under construction and 2 completed

• The vision is now a reality with industry effort and delivery

• We continue to help Design & Development Teams in ensuring the Design

Rating will be realized at Construction.

Page 7: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Construction Rating Audits

Construction Site Audits are a process by which the UPC meet and

assist the Design and Development Team to track a project’s progress

in achieving the targeted Pearl Rating

IT IS NOT A CONSTRUCTION RATING ASSESSMENT

Construction

Rating

Award

Design

Rating

Award

Site Audit

Page 8: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Aims Offer

assistance

tool

Allow

corrective

action

Identify

‘high’ risk

credits

Construction

Site Audits

Reduce risk

of non-

compliance

Provide

Guidance

during

construction

Confirm

Compliance

Page 9: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Responsibility for Credit Compliance

Design & Development Team Government Organizations

UPC

Municipality

Auditor

PQP

Contractor

Suppliers

Designers

Audits are only an assistance tool

All responsibility for Estidama Credit Compliance lies

with the Design & Development Team

Page 10: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

10

Site Audit Stages and Process

Page 11: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

The Construction Rating Process

Design

Rating

Award

Construction

Rating

Award

Construction Credit Clarification Requests

PQP to Complete

Construction Rating

Questionnaire

PQP Complete initial

steps of audit form

Building Handover Stage 1 - 4 Audits PQP arrange for Site

Audit meetings

Construction Rating

Submission

Page 12: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Construction Rating Audit Stages

Stage 1

Site Set-Up &

Sub-Structure

Stage 2

Superstructure

& Envelope

Stage 4a & 4b

Commissioning &

Handover Docs

Stage 3

Internal Fit-Out

& MEP Works

Page 13: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Site Audit – Key Topics

• Estidama Awareness

• Procurement Process

• Natural Systems Strategy

• Construction Waste Management

• CEMP

• Sustainable Materials

• Envelope Verification

• Energy and Water Credits

• Legionella Risk Management

• Indoor Air Quality Management

• Commissioning

• Any relevant optional credits

Page 14: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Typical Site Audit Timeline

Meet at Pre-Allocated

Time on Site

Audit Meeting will take place

Stage Audit Form is completed “LIVE”

by PQP

Site Walk-Around

Contractor to issue PPE and advise on site regulations-

Sign-off and exit meeting

2 hours

PQP to prepare meeting

minutes and finalize Site Audit Form

PQP to issue final meeting minutes and Stage Audit Form to UPC

5 days

Page 15: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

15

Site Audit – Case Study

Page 16: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Site Audit – Envelope

• Envelope related Awareness

Questions are in Stage 1 and Stage 2

of the audit process

• Responses to all questions link to

minimum and improved energy

performance or building envelope

verification

• Team must demonstrate purchase of

materials with appropriate U-Value

• Contractor must demonstrate that

envelope elements have been installed

appropriately

• All gaps should be appropriate sealed Gap in Insulation

Page 17: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – Insulation

Incorrectly laid blocks / poor detailing

Insulation full length of wall

Page 18: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – Gaps

All gaps

need to be

appropriately

sealed

Page 19: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – U-Values

• Third-party test certificate

demonstrating thermal

properties of insulation

and other wall make-up

elements

Page 20: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – U-Values

• Shop drawings highlighting envelope elements with different U-Values

Page 21: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – U-Values

• Elemental U-Value

calculations

• PVRS U-Value calculator

Page 22: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – U-Values

Page 23: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – U-Values

Page 24: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – U-Values

Page 25: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Envelope – U-Values

• Area weighted average U-Value calculations

U-Value = (A1 x U1 + A2 x U2 + An x Un) / (A1 + A2 + An)

Page 26: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Estidama Villa Products Database

• Over 600 technically compliant products:

• Water Fittings & Fixtures

• Solar hot water systems

• Glazing

• Air Conditioning Units

• Insulation Products and Systems:

• Pre-Cast

• Insulated Block work

• AAC Blocks

• Insulated Concrete Form

• Rigid Insulation Board

• These are NOT certified products but rather products that comply with

technical requirements of water and energy performance.

• Only products are approved as compliant, NOT suppliers.

Page 27: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Final Remarks

• Design Rating is the beginning of the sustainability journey to

achieving a better built environment for Abu Dhabi

• Compliance with Estidama is demonstrated at Construction. PQP is

responsible for approving envelope compliance prior to submission to

UPC.

• Construction Audits help project teams maintain and improve the

achieved Design Rating.

• Thoughtful designs result in more sustainable buildings.

• UPC is always available to meet project teams and work together in

the most sustainable solution for your project.

Page 28: Applying the Pearl Rating System Envelope Thermal ... Thermal Performance Compliance . Outline ... in achieving the targeted Pearl Rating ... • Compliance with Estidama is demonstrated

Comments & Questions