Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
Tunnel and Bridge AssessmentsEastern ZoneForm BA: Certificate of Assessment and Checking ‘Brunel Thames Tunnel’- Preliminary Impact AssessmentDoc Ref: 9.15.119
Folder 111 September 2013DCO-DT-000-ZZZZZ-091500
Form
BA
: Bru
nel T
ham
es T
unne
l
Thames Tideway Tunnel Thames Water Utilities Limited
Application for Development ConsentApplication Reference Number: WWO10001
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
Thames Tunnel
Form BA: Certificate of Assessment and Checking for ‘Brunel Thames Tunnel’
– Preliminary Impact Assessments
List of contents:
1 Part 1: Assessment Details ............................................................................. 4
2 Part 2: Acceptance by London Overground/ Network Rail Civil Asset Engineer ............................................................................................... 5
3 Appendices .........................................................................................................
4 Bibliography .......................................................................................................
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
2 Part 2: Acceptance by London Overground/ Network Rail Civil Asset Engineer
I accept that so far as can reasonably be ascertained from the information submitted, the relevant procedures for Assessment and Check as specified in Network Rail Company Standard NR/SP/CIV/035: Assessment of Structures have been followed properly.
I have considered the Assessment Check statement given in accordance with NR/SP/CIV/035 Clause 9.4.3, and confirm that the method of checking specified was a suitable method to be used.
Signed: Title: Civil Asset Engineer
Name (Print): Mahesh Jethwa Date:
To be signed on behalf of London Overground by the Civil Asset Engineer.
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
3 Appendices
Appendix A: Assessment Results
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
Appendix A: Assessment Results
The appendix forms part of Form BA which has been produced to certify that the
assessments identified in the Form AA has been undertaken. This appendix presents
the assessment results set out in the method of assessment as described in Form
AA for the Brunel Thames Tunnel.
The following four assessments have been undertaken:
An assessment of the change in track geometry, including an assessment of
the absolute settlement of the tracks and an assessment of the track twist as
the new Thames Tideway: Thames Tunnel is constructed.
An assessment of the twist caused to the track slab and the induced shear
strains.
An assessment of the longitudinal strains in the tunnel caused by the
settlement of the tunnel
An assessment of the impact of the different ground movements on the
stability and stresses in the Brunel Thames Tunnel as the settlement „bow
wave‟ passes through the tunnel.
This document is meant to be a Preliminary Impact Assessment. It is recognised that
a CAT III check will be required at a later stage of the project, but a check is
considered inappropriate at this pre-planning stage when a number of aspects of the
proposed scheme could change. The check is most appropriate once a contractor
has been nominated and assessments have been updated to reflect the specific
proposed method of working.
Note:
The sub-surface ground movement predictions were based on the assumption of a
Ribbon Sink settlement trough (New & Bowers, 1994).
The volume loss (VL) parameter used in the prediction of ground movements at this
stage have been determined based on the context of this assessment. A moderately-
conservative value of 1.0% has been used in the assessments and reflects the
assumed closed-face construction technique. These values should be readily
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
achievable provide good construction methods are put in place to ensure good
tunnelling practice (Moss & Bowers, 2005).
The 1% volume loss does not include an allowance for any particular stringent
control of movement caused by the tunnelling at this location. The value is also
expected to have conservatism because the Thames tideway: Thames Tunnel is
founded in Chalk at this location. For the purpose of this assessment, a volume loss
of 1.0% is proposed, which is considered to be moderately conservative as the
settlement caused by tunnelling in Chalk is likely to be less.
The trough width parameter (K) used in the assessment of ground movements has
been based on tunnel construction in cohesive soil (eg. Lambeth Group). Experience
in London reveals that „K‟ is seldom less than 0.40 (O'Reilly & New, 1982), and also
indicates that where VL values of less than 1.0% are achieved, a „K‟ value above 0.50
may be appropriate. The „K‟ value of 0.50 has been adopted for ground movement
predictions, and is a conservative assumption.
Following discussions with London Overground (London Overground, 2011), it is
agreed that the 1% volume loss parameter may be considered “moderately
conservative” provided that the specification and management of the TBM tunnelling
confirms to current best practice. However, London Overground will expect to review
both the TBM specification and tunnelling methodology and method statements.
The proposed assessment methodologies have not intended to be undertaken using
detailed soil structure interaction modelling and therefore parameters such as soil
stiffness have not be considered.
Table 1: Assumed modelling parameters
Modelling Parameters Value
Volume Loss (VL) % 1.0%
Trough width parameter (K) 0.50
Track geometry and track slab
The absolute settlement and change in track geometry were calculated based on the
Ribbon Sink trough assumptions with no stiffening effect of the existing structures
and no soil-structure interaction, as described in Section 1.9.1 in Form AA.
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
The change in track geometry was calculated by assessing the difference in ground
movements for points 3m apart along the line of the tracks (track twist).
The limit criteria have been based on values set out in Network Rail Track Geometry
and Gauge Clearance (Network Rail, 2009). We understand that the criteria set out in
the Network Rail Standard assumes perfect track condition which is seldom the case,
and a Clearance and Track Survey will be required prior to the TBM entering the
zone of influence. If London Overgound has a recent survey for this section of the
line, we recommend that this is used. The condition of the track based on the survey
will then inform the track movement trigger levels and tolerance.
The effects of the ground movements causing a twist in the track slab was
considered without taking into account the beneficial effect of the stiffness of the
track slab. Higher rates of rotation are analogous to higher torsional stresses in the
slab. The stress was calculated using the rate of change of rotation and by assuming
the track slab is a simple rectangular beam.
Table 2: Results of Track Geometry and Shear Stress in Track Slab
Settlement Predictions Assessed
Value
Limit
Criteria
(Network Rail, 2009)
Action
Absolute settlement at invert level of Brunel Thames Tunnel
13.0mm 20mm No mandated action
Trough width (2 x 3Kz) 110.6m - -
Track Geometry
Maximum track twist (per 3m) 0.03 mm /3m 12mm /3m No mandated action
Track Slab
Maximum ground movement induced shear stress
0.03N/mm2 - -
The resultant shear stress in the track slab caused by the predicted ground
movements is small and is considered to be insignificant.
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
Longitudinal strains
The longitudinal assessment of the effects on the Brunel Thames Tunnel due to the
transverse settlement trough caused by driving the Thames Tideway: Thames
Tunnel has been determined from the Greenfield settlement predictions. The bending
strains derived from the instantaneous radius of curvature, and the instantaneous
axial strains are calculated from the change in length, reduced by an axial tensile
reduction factor of 0.20 (Bracegirdle et al., 1996).
The limiting tensile strain category (Burland & Wroth, 1974) was taken as „Very
Slight‟ with a limiting tensile strain value of 750με, which is one category below the
normal limiting category of „Slight‟ to reflect the sensitivity of the listed status of the
Brunel Thames Tunnel
Table 3: Longitudinal Tensile Strains
Assessed Value Limit Criteria
(Burland & Wroth, 1974)
Longitudinal tensile strain 147με 750με
Damage Category “Negligible” “Very Slight”
As the assessment predicts a damage category within the acceptance limits, a more
detailed assessment of the predicted damage has not been pursued.
Transverse deformation
The transverse deformation of the Brunel Thames Tunnel has been assessed based
on a multi stage process to account for the distortion of the tunnel as the Thames
Tideway: Thames Tunnel is constructed beneath.
The impact of the ground movements on the Brunel Thames Tunnel have been
assessed by considering the difference in ground movements either side of the base
slab. If the differential ground movements are nominal (<5mm) and the existing
structure is shown to have significant residual capacity (37%) then no additional
assessments have been undertaken.
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
Table 4: Existing condition check
Assessed Value Limit Criteria
Maximum compressive stress (Mean High Water Spring)
1.4N/mm2 1.92N/mm2
Maximum compressive stress (Mean Low Water Spring)
1.0N/mm2 1.92N/mm2
Table 5: Transverse Assessment Results
Assessed Value Limit Criteria
Differential settlement of base slab 3.3 mm 5 mm
Conclusion
The results indicate that the damage impact of the construction of the Thames
Tideway: Thames Tunnel on the Brunel Thames Tunnel is within the design criteria
adopted in these assessments.
No further work is recommended to mitigate the potential damage to the Brunel
Thames Tunnel in the section of interest.
Atkins recommends that the appointed contractor of Thames Tunnel should
undertake a pre-construction and alignment survey prior to the construction of the
Thames Tideway: Thames Tunnel.
The monitoring of the Brunel Thames Tunnel during the construction of the Thames
Tideway: Thames Tunnel is a requirement of London Overground and agreement will
be sought for the proposed instrumentation and monitoring plan (London
Overground, 2011). Details of the monitoring strategy will be provided at a later
stage. We believe that the monitoring strategy is most appropriate once a contractor
has been nominated and assessments have been updated to reflect the specific
proposed method of working.
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
Appendix B: Extract from Calculations
Project: Thames Tunnel Job ref5100812
Part of structure: TU015 East London Calc sheet no rev4 AB
Calc ref Calc by Date Check by Date002 IN 07-07-2011 MY 07-07-2011
Ref Calculations Output
Greenfield Settlement, Radius of Curvature & Longitudinal StrainsReferences:1. Settlements above tunnel in the United Kingdom - their magnitude and prediction; O'Reilly MP, New BM; Tunneling '82; p.173-1812. " Tunneling in Soil" Ground Movements and their Effects on Structures., P.B.Atwell, R.K. Taylor, eds., Surrey University Press, Champman and Hall, New York, NY, 133-2153. London Overground ELL Thames Tunnel, Interface with Proposed Thames Tunnel, 100-DA-TPI-TU015-810000-AB
[4] Plan Angle between Existing Tunnel and Thames Tunnel β 70deg
Slope angle of Railway Line α 1.5deg
[3] External Diameter of Thames Tunnel Dext 8800mm
[4] Volume loss (%) VL 1.00%
[4] Trough width parameter K 0.5 Conservativelyassume track is atinvert level
[3] Invert Level of East London Line Tunnel (mATD) ILBT 82.265m
Axis Level of Thames Tunnel (mATD) ALTT 49.794m
[3] Invert Level of Thames Tunnel (mATD) ILTT ALTT 0.5 Dext ILTT 45.39 m
Depth to Thames Tunnel Invert(from Existing Tunnel Invert)
z ILBT ILTT 36.87 m
Volume loss Vs VL πDext
2
2
Vs 0.608 m2
8
Plan Section
Output:
S(x,y,z) : The settlement of each point
U(x,y,z) : The x direction-displacement of each point
V(x,y,z) : The y direction-displacement of each point
[1,2] s x y z( )Vs
Dext1 cnorm
x
K z
cnorm2y Dext
2 K z( )
cnorm2y Dext
2 K z( )
u x y z( )Vs K
Dext 2πexp
x( )2
2 K z( )2
cnorm2y Dext
2 K z( )
cnorm2y Dext
2 K z( )
v x y z( )Vs K
Dext 2πcnorm
x
K z
1
exp2y Dext( )
2
8 K z( )2
exp2y Dext( )
2
8 K z( )2
Maximum Radius of Curvature
Calculates maximum maximum radius of curvature (long term) by tracking 3 consecutive points
Setting out calculation points
ystart 6 K z yend ystart calculation length lcalc 10mm
intervalyend ystart
lcalc
interval 22122.60 i 0 interval Yi
ystart i lcalc
xstart
ystart
tan β( ) xstart 40.26 m xend
yend
tan β( ) xend 40.26 m
xinterval
xstart xend
interval X
ixstart i xinterval 500m The -500m considers long term settlement
when settlement trough has fully developed
zstart z ystart tan α( ) zstart 39.77 m zend z yend tan α( ) zend 33.97 m
zinterval
zstart zend
interval Z
izstart i zinterval
Si
s Xi
Yi
Zi
Ui
u Xi
Yi
Zi
Vi
v Xi
Yi
Zi
9
100 50 0 50 10010
0
10
20
Si
mm
Ui
mm
Vi
mm
Yi
m
Max settlement
max S( ) 13.04 mm
Bending Strains
Note:
lcalc is the distance between calculation points. Set this to very small to calculate instantaneous curvature.
H is the vertical offset between three consecutive calculation points.
From similar triangles, the rotation of the alignment over the three points is 2 γi
Assuming lcalc = lhor, the half angle of rotation γi can be calculated.The sensitivity of this assumption has
been checked and is considered negligible wrt H.
The radius of curvature Radi is then calculated from geometry.
Hi
Hi
Si
Si 1 S
i 1 2
1 i interval 1if
Hi
1 1020
m otherwise
Hi
Set non-zero
γi
asinH
i
lcalc
Radi
lcalc
sin 2 γi
Maxhogging A 109
km
A Radi
Radi
A Radi
0kmif
i 0 intervalfor
A
Maxhogging 55.58 km
Rad
0
01
2
3
4
5
6
7
8
9
12-5.00·106-5.32·106-5.31·106-5.30·106-5.28·106-5.27·106-5.26·106-5.25·106-5.23·10
...
km
Maxsagging A 109km
A Radi
Radi
A Radi
0kmif
i 0 intervalfor
A
Maxsagging 26.52 km
10
Bending strain
Assume bending about base of sewer
Diameter of existing tunnel DE 12ft 9in3
4in DE 3.905 m
εbending_hogging
DE
Maxhogging
7.025846 105
εbending_sagging
DE
Maxsagging
0.000147
εbendingi
DE
Radi
Axial Strains
Xfi
Xi
Ui
Yfi
Yi
Vi
Zfi
Zi
Si
Lfi
Lfi
Zfi
Zfi 1
2 Xfi
Xfi 1
2 Yfi
Yfi 1
2 1 i interval 1if
Lfi
1 1010
m otherwise
Lfi
Li
Li
Zi
Zi 1 2 X
iX
i 1 2 Yi
Yi 1 2 1 i interval 1if
Li
1 1010
m otherwise
Li
Compression Tension
εaxiali
Li
Lfi
Li
max εaxial 0.000306 min εaxial 0.000151
Combined Strains
Reduction Factor for axial tensile strains RF 0.20
εtotali
εtotali
εbendingi
RF εaxiali
εaxiali
0if
εtotali
εbendingi
otherwise
εtotali
100 50 0 50 1002 10
4
1 104
0
1 104
2 104
3 104
4 104
εtotali
εaxiali
εbendingi
Yi
mMaxstrain min εtotal 147.3 10
6
11
Project: Thames Tunnel Job ref5100812
Part of structure: TU015 East London Calc sheet no rev2 AB
Calc ref Calc by Date Check by Date005 IN 07-07-2011 MY 07-07-2011
Ref Calculations Output
Settlements of either side of base slabIn this calculation the difference in ground movements either sied of the base slab is calculated.Then if the maximum of the difference is less than 5mm, no additional assessments will be required forthe impact of the ground movements on Brunel's Thames Tunnel.
References:1. Settlements above tunnel in the United Kingdom - their magnitude and prediction; O'Reilly MP, New BM; Tunneling '82; p.173-1812. London Overground ELL Thames Tunnel, Interface with Proposed Thames Tunnel, 100-DA-TPI-TU015-810000-AB
Plan Angle between Existing Tunnel and Thames Tunnel β 70deg
External Diameter of Thames Tunnel Dext 8800mm
Tunnel excavated diameter of New tunnel D Dext 8.800 m
Width of Existing Tunnel segment D1 11.45m
VL 1.0%
Face loss (%) K 0.5
Trough factorInvert Level of Existing Tunnel IL 82.265m
Axis Level of Thames Tunnel AL 49.794m
Depth to Thames Tunnel Axis (from Existing Tunnel Invert) z IL AL 32.471 m
Volume loss Vs VL πD
2
2
Vs 0.608 m2
Maximum settlement Smax
Vs
2π K z Smax 14.95 mm
30
Plan
x1 x( ) xD1
2sin β( )
y1 y( ) yD1
2cos β( )
z1 zD
2
x2 x( ) xD1
2sin β( )
y2 y( ) yD1
2cos β( )
z2 zD
2
Output: Six(x,y) : The settlement of each point
S1x x y( )Vs
Dcnorm
2 y1 y( ) D
2 K z1
cnorm2 y1 y( ) D
2 K z1
1 cnormx1 x( )
K z1
*
S2x x y( )Vs
Dcnorm
2 y2 y( ) D
2 K z2
cnorm2 y2 y( ) D
2 K z2
1 cnormx2 x( )
K z2
*
DoS x y( ) S1x x y( ) S2x x y( )
Maximum Difference of S1 and S2
x 0m y 5 m
DoSmi Minimize DoS x y( )
DoSmi2.84
7.97
m
DoS DoSmi0
DoSmi1
3.3 mm
x 100 m y 15m
DoSma Maximize DoS x y( )
DoSma117.81
18.65
m
DoS DoSma0
DoSma1
1.7 mm
As is shown above, the maximum of the difference in ground movements either side of thebase slab is less than 5 mm. Therefore the additional assessments will not required.
31
Transport for London
Form BA : Certificate of Assessment and Checking
Title of Scheme: Thames Tunnel Project
Location: Brunel Thames Tunnel – Rotherhithe to Wapping
ELR: ELL Mileage: N/A OS grid ref.:
TQ 35498 80339
Structure No.: TL163 (Down) /TL164 (Up)
Form BA: Certificate of Assessment and Checking for „Brunel Thames Tunnel‟ – Detailed Tunnel Assessment
Printed 23/09/2011
4 Bibliography
Bracegirdle, A., Mair, R., Nyren, R. & Taylor, R. A methodology for evaluating potential damage to cast iron pipes induced by tunnelling. Balkema, Rotterdam. (1996). pg 659-664.
Burland, J.B. & Wroth, C.P. Settlement of buildings and associated damage. State of the art review. (1974).
London Overground. Comments of Form BA - East London Line (Thames Tunnel Impact Assessment). London Overground, London. LO-IFM-306-5-0011 (2011).
Moss, N.A. & Bowers, K.H. The effect of new tunnel construction under existing metro tunnels. Proceedings of the 5th International Symposium TC28 (2005).
Network Rail. Inspection and Maintenance of Permanent Way - Track Geometry and Gauge Clearance (NR/L2/TRK/001/C01). Network Rail, London. (2009).
New, B.M. & Bowers, K.H. Tunnelling-induced ground movements; predicting their magnitude and effects. (1994).
O'Reilly, M.P. & New, B.M. Settlement above Tunnels in the United Kingdom - Their Magnitude and Prediction. (1982).
Thames Tunnel. Design Standard and Guidance: Impact Assessment of Construction Induced Ground Movements On Third Party Infrastructure And Buildings. 100-PS-DES-00000-000008 (2011).
Copyright notice Copyright © Thames Water Utilities Limited September 2013. All rights reserved. Any plans, drawings, designs and materials (materials) submitted by Thames Water Utilities Limited (Thames Water) as part of this application for Development Consent to the Planning Inspectorate are protected by copyright. You may only use this material (including making copies of it) in order to (a) inspect those plans, drawings, designs and materials at a more convenient time or place; or (b) to facilitate the exercise of a right to participate in the pre-examination or examination stages of the application which is available under the Planning Act 2008 and related regulations. Use for any other purpose is prohibited and further copies must not be made without the prior written consent of Thames Water. Thames Water Utilities LimitedClearwater Court, Vastern Road, Reading RG1 8DB The Thames Water logo and Thames Tideway Tunnel logo are © Thames Water Utilities Limited. All rights reserved.
Copyright notice Copyright © Thames Water Utilities Limited September 2013. All rights reserved. Any plans, drawings, designs and materials (materials) submitted by Thames Water Utilities Limited (Thames Water) as part of this application for Development Consent to the Planning Inspectorate are protected by copyright. You may only use this material (including making copies of it) in order to (a) inspect those plans, drawings, designs and materials at a more convenient time or place; or (b) to facilitate the exercise of a right to participate in the pre-examination or examination stages of the application which is available under the Planning Act 2008 and related regulations. Use for any other purpose is prohibited and further copies must not be made without the prior written consent of Thames Water. Thames Water Utilities LimitedClearwater Court, Vastern Road, Reading RG1 8DB The Thames Water logo and Thames Tideway Tunnel logo are © Thames Water Utilities Limited. All rights reserved.
10243-A4P-Copyright-imp-V01.pdf p1 12:03:39 September 21, 2013