122
APPLICATION OF JUST-IN-TIME TECHNIQUE OF TOTAL QUALITY MANAGEMENT IN OIL FLOW STATIONS BY UTAZI, JOHN. O PG/M.ENG/07/42599 DEPARTMENT OF MECHANICAL ENGINEERING FACULTY OF ENGINEERING UNIVERSITY OF NIGERIA NSUKKA NOVEMBER 2009

APPLICATION OF JUST-IN-TIME TECHNIQUE OF … WORKS.pdf · 2015-09-16 · ALCON NIG. Ltd to satisfy the client and enhance its productivity, economic performance and to satisfy all

Embed Size (px)

Citation preview

APPLICATION OF JUST-IN-TIME TECHNIQUE OF

TOTAL QUALITY MANAGEMENT IN OIL FLOW

STATIONS

BY

UTAZI, JOHN. O

PG/M.ENG/07/42599

DEPARTMENT OF MECHANICAL ENGINEERING

FACULTY OF ENGINEERING

UNIVERSITY OF NIGERIA

NSUKKA

NOVEMBER 2009

2

APPLICATION OF JUST-IN-TIME

TECHNIQUE OF TOTAL QUALITY

MANAGEMENT IN OIL FLOW STATIONS

BY

UTAZI, JOHN .O PG/M.ENG/07/42599

A PROJECT WORK PRESENTED IN PARTIAL FULFILMENT OF THE REQUIREMENT FOR THE

AWARD OF THE DEGREE OF MASTER OF ENGINEERING IN MECHANICAL ENGINEERING

OPTION: INDUSTRIAL ENGINEERING AND MANAGEMENT

TO THE

DEPARTMENT OF MECHANICAL ENGINEERING

FACULTY OF ENGINEERING

UNIVERSITY OF NIGERIA

NSUKKA

3

CERTIFICATION

Utazi, John. O., a postgraduate student in the Department of

Mechanical Engineering and with the registration number

PG/M.ENG/07/42599, has satisfactorily completed the requirement for

courses and research work for the degree of Master of Engineering in

Mechanical Engineering with option in Industrial Engineering and

Management. The work embodied in this project is original and has not

been submitted in part or full for any other diploma or degree of this or

any other university.

……………… ………… ..………………… ………… UTAZI JOHN, O. DATE ENGR PROF.C.I EZEKWE DATE

(STUDENT) (PROJECT SUPERVISOR)

………………………. ..…… ……………….. ………. ENGR.PROF. S.O. ONYEGEGBU DATE EXTERNAL EXAMINAR DATE

(HEAD OF DEPARTMENT)

4

DEDICATION

I dedicate this work to the Almighty God for His guidance and protection

through out the period of this research work. It is also dedicated to firms,

individuals wishing to enhance JIT of total quality management.

5

ACKNOWLEDGEMENT

I give glory to the Almighty God for the enablement and guidance, for He

alone is the source of all knowledge embodied in the mystery of the Trinity.

Unique appreciation goes to my project supervisor, Prof. C.I. Ezekwe, for

the excellent supervisory skills provided during the planning and review of

every phase of this work. My sincere thanks goes to my sub-supervisor Engr.

C.I. Ezema for his total commitment in actualizing this noble task. My

unique and sincere appreciation goes to Prof. Agunwamba of Civil Engr.

Dept. UNN, Prof. Uche of Statistics Dept., UNN and in a greater way to

Nwosu Christian (Prof. Emeritus) of Statistics Dept. UNN for their

wonderful academic contributions at the difficulty stages of this research

work. Special thanks also goes to some of my post-graduate course mates for

their wonderful encouragement rendered to me at some difficult stages of

this work. I am deeply indebted to my immediate family who made all

necessary sacrifices in the course of this study. I also wish to express my

deep gratitude to the management and staff of ALCON NIG. Ltd, Noble

Engineering Nig Ltd and EXPRO TECH OIL AND GAS NIG. LTD for

their immense cooperation given to me especially in obtaining their

individual data.

It is my fervent hope that every reader of this work will be motivated

to pursue or adopt JIT of Total Quality, which will be the driver of all

economies in this century.

6

ABSTRACT

This work examines the concept of just-in time technique through reorder

point of total quality management with a view to understanding and appreciating

how its principles, techniques and model can be used to successfully manage flow

station’s project of variable demands and lead times.

Flow stations and its facilities, operated by multinational corporations, dot the land

scape of the entire Niger Delta region are not well managed. Some of these were

built over 25 years ago with little regard for safety, continuous service and the

environment. Due to internal and external pressure, the Shell Petroleum

Development Company (SPDC) among other flow stations embarked on major

upgrade of these flow stations to meet international standard, optimize production,

enhance plant safety, ensures streamlined production, maintainability and reduce

impact of its operation on the environment. To achieve these goals, TQM

strategies were deliberately developed and adopted by the contracting company,

ALCON NIG. Ltd to satisfy the client and enhance its productivity, economic

performance and to satisfy all stakeholders in the immediate environment where

these plants are located.

This work also identifies principles and techniques for building quality into all the

stages of a project cycle.

Information and data from field experience and survey are critically examined and

necessary findings presented.

The ROP model formulated to handle cases of variable demands and lead times of

selected flow stations were also tested using the data obtained from the field.

Recommendations that will hopefully encourage managers of flow stations project

to embrace the principles of Just-in-time of TQM are discussed with a view to

enabling them use its benefits to enhance productivity, continuous service,

acceptability by various stakeholders and economic performance in the face of

increasing competition amongst firms.

7

TABLE OF CONTENTS

Title page - - - - - - - - - - - - - - - - - - - - - - -- - - - - - i Certification - - - - - - - - ii Dedication - - - - - - - - - iii Acknowledgement - - - - - - - iv Abstract - - - - - - - - - v Table of contents - - - - - - - - vi List of tables - - - - - - - - vii List of figures - - - - - - - - viii CHAPTER ONE-INTRODUCTION 1.1 Background - - - - - - - - 1 1.2 Importance of the study - - - - - - 1 1.3 Basis of the study - - - - - - - 3 1.4 Research objectives - - - - - - 4 1.5 Significance of the study - - - - - - 5 1.6 Research methodology - - - - - - 5 1.7 Model formulation - - - - - - 6 CHAPTER TWO-LITERATURE REVIEW 2.1 Historical review - - - - - - - 7 2.2 Concept of just-in-time technique of TQM - - - 9 2.3 Other tools of total quality management (TQM) - - 10 2.4 Total quality – its meaning, significance and composition - 12 2.5.0 The ISO 9000 Bench mark for quality - - - - 17 2.5.1 Basic system design for JIT of TQ in project management 20 2.5.2 Management policy decision and planning - - - 23 2.5.3 Configuration management and work breakdown structures in JIT

project quality planning - - - - - - 24 2.5.4 Organizing the Just-in-time TQM structure - - - 28 2.5.5 Quality consideration in human resources - - - 31 2.5.6 Quality consideration in Engineering design using JIT project

management - - - - - - - - 33 2.5.8 Design inputs - - - - - - - 34 2.5.9 Design outputs - - - - - - - 35 2.6.0 Quality consideration in managing materials and project inputs 37

8

2.6.1 Procurement data processing - - - - 38 2.6.2 Material control - - - - - - - 41 2.6.3 Building quality into project execution processes - - 41 2.6.4 Procedures and instructions - - - - - 43 2.6.5 Process control - - - - - - - 44 2.6.6 Final inspection - - - - - - - 44 2.6.7 Quality records - - - - - - - 45 2.6.8 Non-conformances - - - - - - - 46 2.6.9 Corrective action - - - - - - - 47 2.7.0 Measurement and testing - - - - - - 47 2.7.1 Audits and field feed back - - - - - 48 2.7.2 Audit scheduling - - - - - - - 49 2.7.3 Audit planning - - - - - - - 49 2.7.4 Audit personnel - - - - - - - 50 2.7.5 Audit reporting - - - - - - - 50 2.7.6 Audit follow-up 2.7.7 Integration and enculturization of JIT of TQM programme 51 2.7.8 Other Aculturized tools and techniques for total quality - 52 2.7.9 When to reorder with EOQ - - - - - 60 2.8.0 Inventory control - - - - - - - 61 2.8.1 Inventory control model 62 CHAPTER THREE -PROBLEM FORMULATION/RESEARCH

METHODOLOGY 3.0 Chapter overview - - - - - - - 71 3.1 Data collection method - - - - - - 71 3.2 Model notations - - - - - - - 72 3.3 Model formulation - - - - - - - 73 3.4 Model assumptions - - - - - - 75 3.5 Result specification - - - - - - 75 CHAPTER FOUR - DATA PRESENTATION AND ANALYSIS 4.1 Chapter over view - - - - - - - 76 4.2 General analysis of survey - - - - - 76 4.3 The questionnaire - - - - - - - 78 4.4 Analysis of questionnaires field data - - - - 80 4.5 Employees’ awareness level of company performance statistics 80 4.5.1 Availability of specific company goals, policies and objectives 81 4.5.2 Assessment of documented quality system - - - 83 4.5.3 Assessment of specific quality plans and practices - - 84

9

4.5.4 Assessment of available other total quality tools and techniques 85 4.5.5 Availability and scope of quality audit system - - 86 4.5.6 Frequency of auditing - - - - - - 87 4.5.7 Assessment of scope of quality assurance - - - 87 4.5.8 Assessment of assurance records - - - - 88 4.5.9 Quality personnel authority - - - - - 89 4.6.0 Assessment of availability and type of formal and informal

association amongst workers - - - - - 89 4.6.1 Availability of reward for quality - - - - 90 4.6.2 Assessment of length of education and experience of workers 91 4.6.3 Availability of procedures for evaluating quality cost - 92 4.6.4 Responsibility for quality management - - - 93 4.6.5 Acceptability of quality functions - - - - 95 4.6.6 Testing of model formulation - - - - - 97 CHAPTER FIVE – DISCUSSION, CONCLUSION AND

RECOMMENDATION 5.1 Discussion - - - - - - - - 103 5.2 Summary of finding - - - - - - 103 5.3 Recommendation - - - - - - - 104 5.4 Conclusion - - - - - - - 105 References - - - - - - - - 108 Bibliography - - - - - - - 110 Appendix - - - - - - - 112

10

LIST OF TABLES

Table 1.1 The IAO 900 family of standards. Table 2.1 Tools and techniques used for quality improvement Table 4.1 Survey response Table 4.2 Response by category Table 4.3 Summary of questionnaire structure Table 4.4 Employee’s awareness level of company’s information Table 4.5 Availability of specific company goals, policies and objectives Table 4.6 Assessment of availability and awareness of the documented

quality system. Table 4.7 Assessment of availability and awareness on quality plans,

procedures, codes and standards. Table 4.8 Assessment of available TQ tools and techniques in use. Table 4.9 Span of Quality Audit. Table 4.10 Frequency of project audit. Table 4.11 Frequency of implementation of audit findings. Table 4.12 Scope of quality assurance. Table 4.13 Span of quality control Table 4.14 Availability and retrieval of quality records. Table 4.15 Availability of authority to quality personnel. Table 4.16 Management tolerance of workers association. Table 4.17 Type of association encouraged by management. Table 4.18 Availability o reward for quality Tale 4.19 Average length of formal education of workforce. Table 4.20 Average experience of workers. Table 4.21 Availability of procedures for evaluating cost of quality per

project. Table 4.22 Approximate cost of quality per project. Table 4.23 Responsible focal point for quality. Table 4.24 Acceptance of quality department’s work by top management. Table 4.25 Acceptance of quality department’s work amongst workers. Table 4.26 Flow station (A1) with variable demands, service level and lead

time. Table 4.27 Flow station (A2) with variable demands service level and lead

time. Table 4.28 Flow station (A3) with variable demands, lead time and service

level.

11

LIST OF FIGURES

Figure 2.1 Relationship between QC, QA and TQ

Figure 2.2 Basic system design requirements for a TQM project.

Figure 2.3 Configuration management Activities.

Figure 2.4 A typical TQM project organization chart.

Figure 2.5 Typical design schematic sequence.

Figure 2.6 Typical procurement schematic sequence.

Figure 2.7 Skilled man power loading histogram

Figure 2.8 ROP at safety stock.

Figure 2.9 Economic order quantity with safety stock.

Figure 2.10 Economic order quantity when there is shortages.

Figure 2.11 Similar triangles for determining economic order quantity.

Figure 2.12 Economic lot size when supply is continuous.

12

CHAPTER ONE

INTRODUCTION

1.1 BACKGROUND OF THE STUDY

In the past one decade or so, managers of engineering projects world –

wide are increasingly coming under market pressure to reform their quality

management practices, as it is being done by their counterparts in

manufacturing sector, service sector, the marketing sector etc.

1.2 IMPORTANCE OF THE STUDY

In Nigeria, most engineering firms especially flow stations have learnt

through the hard way that only those with efficient and effective systems and

techniques for managing quality in all stages of production including the

inventory control can survive in the sector. This is due to increased

competition amongst firms, leading to capacity under – utilization and out

right bankruptcy of many firms with the consequent social effect of

unemployment and under development. Most affected are wholly indigenous

firms whose fortunes have dwindled over the last few years due to

liberalization of the economy. Some have lost out right patronage from their

traditional clients due to mainly inability or unwillingness to embrace even

elementary principles of quality in their practices. According to American

production and inventory control society (APICS), Just-in –time is “ A

philosophy of manufacturing based on planned elimination of all waste and

continuous improvement of productivity. It also encompasses successful

execution of all manufacturing activities required to produce a final product,

from engineering to delivering and including all the stages of conversion

from raw material to finished product. On that note, it is believed to be a

track which follows the path/route of continuous improvement vis-à-vis

identification of bottlenecks and problems, attacking waste of all kinds and

13

the achievement of streamlined production. The fact is that issues of quality

management are fast becoming central to both professional and business

success. Thus, an engineering firm flow station that delights in profiteering

at the expense of quality, will soon discover itself isolated by clients and

more often places itself at the risk of being openly criticized by third party

stakeholders who are directly or indirectly impacted in the environment

where its activities are being undertaken.

This then is the basis of the renewed quest by project managers for

better techniques of managing quality issues in engineering projects such as

flow stations.

In most establishments in Nigeria today especially in flow stations,

and in both private and public sector, project quality management is often

not seen beyond the narrow precincts of traditional control mechanisms

which places emphasis on inspection as the only tool for ensuring

compliance with some stated standards and specifications. The result is high

failure rate and outright abandonment of projects, monumental waste of

scarce resources, transfer of avoidable defects, doubling of project execution

costs, low return on investment by clients and general dissatisfaction with

engineering activities in Nigeria (Hajek and Victor, G,1984).

Furthermore, many firms see quality as mere routine tasks and

activities which are peripheral to main project objectives, the aim being only

to satisfy some minimum specifications pre set by the client.

But, yet the concept of project quality is much wider and even more

so, Total Quality Management (TQM). The effect of Total Quality

Management (TQM) when properly employed and assimilated will be felt in

all areas of the project cycle.

14

Just – In – Time technique must be recognized as a total quality

management tool for attaining the firm’s objectives and must be one of the

cardinal responsibilities of top leaders of the engineering firms especially

flow stations. Just – in – time technique of total quality management (TQM)

provides a frame work around which the five Universal functions of

management namely; planning, organizing, directing, controlling and co-

ordination should revolve. This process involves that quality is scheduled

into all the factors of production (men, budget, materials, information, plant

and equipment) and properly blended to work harmoniously to achieve set

project objectives by encouraging the work force to participate in various

programmes relevant for increasing profits and leading to work

improvement through cost reduction, inventory reductions/eliminations and

quality improvements.

1.3 BASIS OF THIS STUDY

This study is an investigation of how Just – In – Time technique of

Total Quality management principles were used in flow stations through Re

– Order point to successfully manage their project (a turn key project by

shell flow stations upgrade) among other flow stations.

The flow stations project are spanned through all key engineering,

disciplines Viz; mechanical, Civil, structural, instrumentation, electrical and

environmental.

Also, to investigate the relevance of J I T. technique through Re –

order point model in solving practical Variable problems in demand and

production lead time in flow station’s project. For instance, one of the flow

station’s projects (the shell flow stations upgrade project) was executed in

three phases (I, II and III) over a period of seven years, 1992 to 1999.

Twenty-five (25) flow stations sited in land and remote Swamp Locations

15

were involved in the project. In the first phase of the project, ALCON (the

contracting firm) adopted the traditional “test and Fix” quality practices. In

phases II and III, it introduced J I T of T Q M, which encompasses

teamwork and used it as a model for managing subsequent projects.

The results obtained with the phases II and III quality models were out

standing compared with phase I.

At it acme (highest stage of development) the Just–In–Time technique

of Total Quality model, more than doubled production; achieved near zero

defect in all disciplines, reduced supervisory workload, greater capacity

utilization, cost reduction, Inventory reduction and maximum reduction in

plant down time as well as production lead time and set up times leading to

increased patronage from clients.

Further, apart from increased turn over and profits, an astonishing

discovery was made that workers in JIT technique of total quality

management team were more motivated by the work they do than the

monetary benefits they derive due to a kind of “ESPRIT DE CORPS” that

seem to blind the team (JIT of TQM). It was discovered, as a sure way/

technique of motivating a work force company–wide.

1.4 RESEARCH OBJECTIVES

The Objectives of this study are;

To investigate the principles of Just-in-time of Total Quality

Management (TQM) among other tools and techniques Vis–a–vis

Current international practices with particular reference to

management of engineering projects (flow stations).

To present, solve and analyze flow stations practical field data of

Variable cases of demand and production lead times with the JIT of T

Q M model through Re–order point.

16

To establish if there are indeed significant benefits accruable from the

application of J I T of T Q M and its model through Re-order point in

handling engineering projects (flow stations).

To make recommendations for improvement strategies in the

management of flow stations project using Just–in–time of TQM

principles and techniques.

1.5 SIGNIFICANCE OF THE STUDY

It is hoped that at the end of this research work, the information obtained

will;

Serve as a readily available reference document for engineering

firms (flow stations) as well as potential investors who want to take

advantage of Just–In–Time of TQM principles and techniques to

improve project management.

To encourage engineering firms especially flow stations to

embrace the concept of Just–In–Time of TQM among other tools and

techniques to enhance their productivity and acceptability in the

market, especially the indigenous ones.

That the formulated model will provide the best approach to

Variable Cases of demand and production lead time of JIT (Re–order

point) in handling flow stations project.

To guide future researchers, operators and managers of

engineering projects (flow stations) the concept of Just–In–Time of

Total Quality in project Management.

17

1.6 RESEARCH M ETHODOLOGY

To accomplish the defined objectives of this study, a survey was carried out

in some flow stations in Port-Harcourt which offer similar production and

services. The following methods were used to obtain the relevant

information from the companies (ALCON ENGR OIL AND GAS LTD,

NOBLE ENGR DRILLING COMPANY LTD AND EXPRO TECH OIL

AND GAS DRILLING COMPANY LTD) Viz;

(i) During visits to these flow stations, direct observations were made by

the researcher with respect to Variable Cases of demand and production lead

time of their products. How the operational tasks are organized and

implemented in the flow stations, are also surveyed.

(ii) The system documents of the companies were also sighted and

recorded by the researcher.

(iii) During visits to these companies (flow stations), interviews and

discussions were held with respondents in the course of administering and

retrieving the research questionnaires. Information obtained from this source

was recorded.

(iv) Data were also gathered from the companies with the aid of a research

questionnaire. Questions structured using ISO 9000 principles, were used to

explore the factors that collectively address the quality culture and practices

of the firms (flow stations).

1.7 MODEL FORMULATION.

A model on Just–In–Time of TQM through Re–order point was

formulated to address the Various Cases of Variability in demands and

production lead times of the said flow stations to ensure Just–in–time of

their products. The model formulated and analyzed provided the basis for

making empirical judgments, conclusions and recommendations.

18

CHAPTER TWO

LITERATURE REVIEW

2.1 HISTORICAL REVIEW

Quality dates back to medieval times from when man in his quest for

meeting his basic needs began to engage in some form of manufacture. To

create better articles of trade, man invented the idea of quality so as to

enhance the Value of these articles in exchange. The medieval Craftsman for

instance, who casted temple bells knew when a bell had been properly cast

by striking the bell–a bell the “rang true” when struck was accepted as being

without casting defects, while the one that produced “false note” was

rejected.

In project management, the origin of quality can be traced to ancient

structures like temples, tombs, pyramids etc. the desire for human safety,

durability and aesthetics in these projects, spurred the idea of specialization

of craftsmen and eventual enforcement of some rigid rules to regulate

construction activities. Kings appointed more experienced craftsmen to

oversee the implementation of these rules. These craftsmen therefore acted

as both supervisors and inspectors. Initially, the rules were mostly unwritten,

but as time went by and as the science of metrology became developed,

learned craftsmen began to write down their experiences and expectations,

thus leading to the development specifications, and much later standards.

According to Feigenbaum[1991:P.15], the first step in the

development of modern quality predated 1900 during which every worker

could take control of the quality of his personal work, since only one worker

or every small number of workers were involved in the entire production

process. This led to the period when foremen assumed responsibility for a

group work, some time prior to the First World War due to the advent of the

19

modern factory concept. About World War I, full time inspectors were

appointed to handle quality matters as production systems became more

complex. Then followed, the concept of statistical quality control, which

emerged during world war II and which, continued to be improved upon

until in the early 80’s when the idea of Just–in–time of Total Quality

management emerged.

About this time, the work of the international Organization for

standardization (shortened ISO) – a voluntary body of quality organizations

in several countries around the world, began to develop quality models

which have revolutionized the concept of total quality. Its ISO/TC 176

technical committee which was commissioned in 1978 produced a document

in 1987 on quality models, now popularly known as the ISO 9000 series,

thus harmonizing quality practices on an international scale. In this series,

demonstrating conformance to one of three quality management models viz;

ISO 9001, ISO 9002 and ISO 9003, becomes the “easiest” means by which

an organization can provide objective evidence that it has in place an

effective system for quality management. The ISO 9000 models radically

changed management thinking in many organizations the world over, which

led to a major revival in the application of the universal principles of quality

management, application of the universal principles of quality management,

first by the big corporations and soon by many smaller firms as a managerial

philosophy for survival. The ISO 9000 models, thus laid the foundation of

what is today called Total Quality Management (TQM) or Total Quality

(TQ) and by mid 80’s following the collapse of communist Russia, many

firms saw JIT of TQM as the “cheapest” route to internationalize their

market opportunities.

20

The history of a formal, national effort in the development of quality

management system for Nigeria, began in 1971, when the them Federal

Military Government enacted the Decree No 56 of 1971, called the Nigerian

standards Organization Decree [Laws of the FGN: 1990, p.155]. This Decree

led to the formal national consciousness towards matters related to quality

management, but has however done little to change the culture of some

enterprises, especially indigenous engineering firms, thus affecting their

ability to compete even in the domestic market. The standard organization of

Nigeria (SON) is a member and subscribes to the character of establishing

the International Organization for standardization (ISO).

2.2 CONCEPT OF JUS-IN-TIME TECHNIQUE OF TOTAL

QUALITY MANAGEMENT (TQM)

According to American production and inventory control society

(APIC), JIT is “A philosophy of manufacturing based on planed elimination

of all waste and continuous improvement of productivity”. It encompasses

successful execution of all manufacturing activities required to produce a

final product, from engineering to delivery all states of conversion from raw

material onward. It is also believed to be a track which follows the

path/route of continuous improvement. Just-In-time is believed to; Attacks

Wastes of all kinds may be inventory time or scrap etc, identifies bottle

necks and problems and also helps in achievement of streamlined

production.

Just-In-time is also required in the following factors; (i) adoption of

TQC so as to achieve the target of quality (ii) participation of employees at

various levels (iii) small lot size processing so as to attack all wastes and

also in production, it utilizes the pull system ratter than traditional push

21

system which focuses on the end of the production line and pulls work

through from preceding operations.

2.3 OTHER TOOLS OF TOTAL QUALITY MANAGEMENT

(TQM)

(i) PARATO ANALYSIS: This provides one of the most powerful

ways of looking at data for the purpose of quality improvement. It

is based on the 80/20, rule. 80 percent of the problems can be

attributed to 20 percent of the causes. Hence, it identifies the cause

of the majority of the problems. It helps the user to quickly and

visually identify the most frequently occurring type of defects so

that the causes of these defects should be probably be identified

and attacked first. It is an investigatory tool that enables the quality

assurance service to assign priorities to the possible sources of

quality defects. This leads to PARETO PRINCIPLE, which says

that there are many unimportant problems but only a few serious

ones. The diagram which is drawn with the aid of HISTOGRAM

enables us objectively to identify the serious problems we are

currently facing and take up the really important ones as a matter

of policy.

(ii) CAUSE-AND-EFFECT DIAGRAM: This is nick-named the

“fish bone diagram”. This is because of its skeletal structure which

resembles the skeleton of a typical fish. It illustrates the

relationship between characteristics (the results of a process) and

those causes considered for technical reasons to exert an effect on

the process. When used with other statistical tools such as pareto, it

is useful for promoting process improvement on a priority basis,

accumulating and organizing knowledge and technology,

22

consolidating the ideas of all employees for control–related

activities, and facilitating discussions, education a variety of other

aspects of human relations. It is mostly used to illustrate the

various sources of non conformities in products and

interrelationships. It is also used in focusing the attention of

operators, manufacturing Engineers, and managers on quality

problems.

(iii) HOUSE OF QUALITY (Quality function development): This is a

graphic tool for defining the relationship between customer desires

and the firm/product capabilities. It is part of QFD and it utilizes a

planning matrix to relate what the customer wants to, how a firm

(that produces the products) is going to meet those wants. The

basic structure is a Table with “what” as the labels on the left and

“How” across the top. The roof is a diagonal matrix of “How vs

How” and the body of the house is a matrix of “what vs How”.

Both of these matrices are filled with indicators of whether the

interaction of the specific item is a strong positive, a strong

negative or somewhere in between.

iv TAGUCHI TECHNIQUE: Genichi Taguchi developed in

interesting quality cost model that is today called Taguchi technique

or taguchi’s loss function. The basic philosophy is that, when ever

something is produced, a cost is imposed on society. Part of that cost

is borne by the producer and part is borne by the customers as a result

of using the product or service. If these cost are plotted as a function

of “quality”, producer cost tend to increase with increased quality;

customer costs, tends to decrease because of greater efficiency, less

breakdown and so forth. The total cost or loss to society is the sum of

23

these two cost functions it tends to decrease over some range of

increasing “quality”, until a minimum is reached and then increased

beyond that point. Hence, the focus is on minimizing deviations in

parameter settings (Xo) and reducing process variability. The

parabolic loss function equation proposed by Taguchi for two sided

specifications is L = K (δ2 + ∂2) = K (M S D); where δ = the current

best estimate of process standard deviation, ∂ = (μ-T) where; µ = the

current best estimate of process centering, T = the target or nominal

dimension. K=A constant used to convert M S D = (δ2 + ∂2) into

monetary unites. MSD = Mean – Square Deviations.

(v) QUALITY CONTROL PROCESS CHARTS (PROCESS

CHART):

This is a graphic representation of the sequence of events or steps that

occur in the work method or procedure, classifying them by symbols

according to the nature of the event. It is a device for visualizing a procedure

for the purpose of improving it. It is used in process analysis by

investigating what is happening in practice, and revises the process chart on

the basis of the results of the analysis so as to facilitate process chart. Some

symbols are used eg; O operation, Inspection,

Transport, D delay etc.

2.4 TOTAL QUALITY – ITS MEANING, SIGNIFICANCE AND

COMPOSITION

According to Lockyer [1983:P.88], four main factors that determines

the acceptability of a product by a consumer Viz; Quality, reliability,

availability (delivery) and reliability price, but to much larger extent, quality

and reliability play much more significant roles in most situations. The

ISO/TC No. 176 [1994:P.2], emphasized the importance of quality thus;

24

“today, all industrial enterprises are finding that their principal market place

competitors include companies headquartered in other countries,

consequently, quality continues to grow in importance as a factor in market

place success”.

The primary purpose of business is to make profit in the process of

satisfying customers’ needs and requirements. In contractual situations such

as in engineering projects, these needs and requirements are usually

described in the service specifications often, the specifications by the client

may fail to meet part or all of his requirements due to deficiencies in the

specifications used or in the organization itself. Also, in a project situations,

it is often not possible for the client to state all his requirements in an order,

it therefore behaves on the contractor, as a specialist, to develop ways of

meeting the minimum specifications set by his client and ‘work’ quality into

the entire stages of the project cycle.

In doing this, the contractor will have to rely on standards with which

specifications can be compared. A standard is a document or physical.

Specimen defining or giving examples of parameters, properties of

professional performances of work. It is also a set of specifications for parts,

materials, product or processes intended to achieve uniformity, efficiency

and a specified quality [ Shigley and Mischke 1989,p.10]. Standards defined

specifications and any standard is a minimum requirement for a defined

situation or process which provides a basis for comparing current practices

with established parameters.

Another use of standard is in the process of standardization, which seeks to

place a reasonable limit on the number of items in the specifications so as to

provide uniform inventory of tooling, sizes, shapes, spares and varieties.

25

In certain situations, the aim might be to drew a set of specifications to

assure that some specified degree of “safety parameters” are built into the

product (or project). This type of standard is called a CODE. It is a set of

specifications for the analysis, design, manufacture and construction of

something [Shigley and Mischke 1989,p.10]. The overall aim here in the use

of codes is to produce things, which are operationally safe without end-

angering the life of the user, reliable and functionally satisfactory to the user

and third party who may be impacted by its use.

A procedure is a laid down and previously agreed route to achieving a

defined project objectives. Procedures are project control tools to

ensure and assure that activities leading to the manufacturer or

installation of something are done systematically according to an

agreed pattern and to pre-set specifications [Weihrich and Koontz

1993,p.125]. Procedures may cover both administrative and technical

activities and is usually administered at the middle level management.

Examples are; project costing and evaluation procedures

(administrative) and non-destructive testing procedure (technical).

Practices are documented actions based on experience acquired over

the years from often repeated operations which have come to be

regarded as part of the culture of the firm, for instance, design and

Engineering practice (D.E.P). It is not standard parse, but documented

evidence that certain processes will produce a desired end-result.

Project guidelines, instructions and statements are a body of rules

developed by a firm to guide its member at the working level while

carrying out their routine functions. Instructions and statements

particularly, give details of actions that are required by the sender

from the recipient.

26

A policy e.g. company’s quality policy, shows the overall intentions

and direction of that company expressed formally by top management.

Quality is all about doing things right the first time and in project

management situations, a client will judge the contractor by his ability to

follow relevant specifications, codes, procedures, practices and denied

polices, project guidelines and instructions, including a documentary

evidence that indeed every phase of the project has had the level of quality

requirements built into it. The ISO standard No. 8402 [1994:p.6], has

defined quality as the “totality of characteristics of an entity that bear on its

ability to satisfy stated and implied needs”. An entity in this context is tat

which can be individually described and could be an activity, a process, a

product, an organization or combination of all these.

In project management, therefore it follows that the intention of quality must

include meeting, satisfying, conforming to prior agreed and negotiated client

needs, requirements and expectations, including the expectations of all

stakeholders in the project.

The operational techniques and activities that are used to fulfill

requirements for quality is termed quality control, while quality

assurance implies all planned and systematic activities implemented

within the quality system and demonstrated as needed to produce

adequate confidence that an entity will fulfill requirements of quality.

The quality system of a firm include its organizational structure,

available standards, specifications, procedures, processes and

resources needed to implement quality management [The ISO

standard No 8402, 1994: p.16].

Modern quality management and hence its implementation is not just

mere quality control, as widely misunderstood, but includes all

27

activities of the overall management function that determine the

quality control and the quality system. Since the mid 80’s, the global

trend has been the conscious realization that a management oriented

quality system is necessary to achieve and sustain good economic

performance. This than is the underlying basis for the wider concept

called Total Quality Management (TQM).

The ISO 8402 [1994:p.17], has defined TQM as the “management

approach of an organization centered on quality, based on the

participation of all its members and aiming at long-term success

through customer satisfaction and benefits to all members of the

organization and to society”. This brings to fore, the four vital

principles on which TQ is anchored viz:

Total quality must be the higher priority of the firm and all individuals

in the team.

The TQ team must have an aim, a goal which is properly

communicated, generally understood and accepted by every team member.

The concept of client is broader than just the purchaser (investor), but

includes all employees, suppliers, stakeholders, the community and every

interface that could be possibly impacted by a defined activity. It is this

broadness that accommodates the needs and expectations of every

stakeholder and makes the team responsible in the eye of every body.

There are some values which every member of the team holds dear

integrity, honesty, commitment, active participation and a sense of

ownership. To meet these principles, the TQ practitioner must appreciate

that JIT of TQ is a working philosophy, it is a management journey, not a

destination and it calls for continuous measurable improvements at all levels

of the organization [Akanya, p.13]. the just-In-Time of TQM concept

28

applied to project management would mean a management approach that

would centre on quality, with the participation of all team members aiming

at client and stakeholders’ satisfaction at every phase of the project life

cycle.

The relationship between quality control, assurance and TQ is shown is fig

2.1 to provide clearer understanding of each concept

Fig 2.1: RELATIONSHIP BETWEEN QC, QA AND TQM

Management policies and

actions cent red on quality

All activities associated

with the attainment of quality

Actions and systems to

measure and regulate quality

SOURCE. Adopted, with modifications, from standards organization of

Nigeria (SON), lectures slide an quality (1994).

SOURCE: Adapted, with modifications, from standards organization of

Nigeria (SON), lectures slides on quality (1994).

2.5 THE ISO 9000 BENCH MARK FOR QUALITY

TOTAL QUALITY MANAGEMENT (TQM)

QUALITY ASSURANCE (QC)

QUALITY CONTROL (QC)

Effective QC confirms that QA is working An understood QA system confirms that TQM is working TQM ensures that QA and QC works effectively

29

The ISO 9000 family of international standards provides a kind of

model, detailing minimum requirements for achieving the TQ goal. It

prescribes what elements quality systems should encompass but not how a

specific organization should implement these elements. The objective is to

ensure that quality is assured at every stage of the production or service

process.

The international Organization for standardization (ISO) was

established on February 23, 1947, having metamorphosed from the

international standardizing Association (ISA), itself having been founded in

1926. ISO has since issued numerous standards and models covering many

fields of human endeavor. However, as ubiquitous as some of these

standards have become, none has matched the rapid rise to world wide

application of the ISO 9000 series of standards, which is recognized

internationally as a bench mark for measuring quality in a trade context

[Akanya, p.8]. The series provides criteria for evaluating quality assurance

and quality management within an enterprise and between its customers or

public. It contains generic guide lines for quality systems covering every

conceivable field of human activity from manufacturing to servicing. Table

1.1 gives a brief description of standards in the ISO 9000 series.

30

TABLE 1.1 THE ISO 9000 FAMILY OF STANDARDS

STD No. DESCRIPTION USES REMARKS

ISO 9000 Quality Systems-

Quality Manage-

ment and Quality

Standards-

Guide Lines for

selection and Use.

* For non – contractual

situation

* Guides management in

selecting and using the

appropriate quality model

(s).

ISO 9001 Quality systems-

model for quality

assurance in Design /

Development,

production,

installation and

servicing

* Model for use in

contractual situations

when conformance to

specified requirements is

to be assured by the

supplier during design,

development, production,

installation and servicing.

Good for EMPIC

contracts ie Engineering,

manufacturing,

procurement, installation

and commissioning

projects.

ISO 9002 Quality systems –

model for quality

assurance in

production and

installation.

* For contractual

situations where

conformance to specified

requirements is to be

assured by the supplier

during production,

installation and servicing

Good model for project

management.

ISO 9003 Quality systems –

model for quality

assurance in final

inspection and Test.

* for contractual

situations when

conformance to specified

requirements is to be

assured by the supplier

solely at the final

Good for third party

inspection, services, and

for service providers.

31

inspection and testing

phase.

ISO 9004 Quality management

and quality system

Elements guidelines.

*For non – contractual

situations.

* Used in the

development and

implementation of in-

house quality system with

a view to ensuring

customer satisfaction

* Used with ISO 9000

SOURCE. Constructed from ISO 9000 series; International standards for Quality

management, 4th Edition, (1994. p. 71 - 124).

2.5.1 BASIC SYSTEM DESIGN FOR JIT OF TQ IN PROJECT

MANAGEMENT

Like any other organization effort, total quality must be properly

design to suite the requirements of the project in contractual situations,

within the ambit of the organization’s mission and business goals. An

effective TQ design must ensure that there are mechanisms of identification

and control of all sub-elements in the project cycle, in a way that enhances

quality at every stage with adequate documentary evidence that all defined

acceptance criteria have been met and are traceable.

In the case study project, the just-in-time of TQ was designed as

shown in fig 2.2. The ISO 9001 provided the basis for the design. It is

important to note the feed forward and feed back effort and the

consideration given to the impacted environment, in the quality loop.

32

Eight main steps were taken to achieve the objectives of the design

namely;

(1) Firm management policy and a proper plan

(2) Organizing an effective project structure

(3) Emphasis on quality consideration in employee selection,

training and motivation.

(4) Total quality consideration in engineering design and project

technical specifications.

(5) Effective control and deliverance of purchased materials, as

well as third party inputs.

(6) Proper control of project execution processes

(7) Adequate audit and field back programmes.

(8) Integration and enculturization of gains of the programme.

The discussion that follows gives details of how and why these steps

were taken, including the theoretical basis underlying each step.

33

FIG 2.2 A BASIC SYSTEM DESIGN REQUIREMENTS FOR A TQM PROJECT

SOURCE. TQM DESIGN FOR FLOW STATIONS UPGRADE PHASE II ALCON, 1995

Available An Appropriate Quality Model Quality Policy Decision Quality Planning Quality Procedures Task and work instructions Document control system Adequate human resources.

DESIGN PURCHASING

PROJECT EXECUTION PROCESSES

VENDOR

QUALITY AUDIT

FINAL INSPECTION AND TESTING

REPAIRING WORK

FEED FORWARD Ѕ FEED BACK EFFORT FEED FORNARD EFFORT ONLY

POST COMMISSIONING ENGINEERING SERVICES

PROJECT COMMISSIONING AND HANDOVER

CLIENT

ENVIRONMENTAL IMPACT BY PROJECT

SCRAP PAILED PROJECT

PROJECT GUARANTEE PERIOD

34

2.5.2 MANAGEMENT POLICY DECISION AND PLANNING

Weihrich and Koontz [1993, p. 199], have defined decision as the

selection of a course of action from among alternatives, while planning

involves objectives and the actions required to achieve them. A plan can

therefore not be said to exist unless a decision has been made. Juran et al

[1993, p.119] defined a policy as a broad guide to action or a statement of

principles that guide mangers’ thinking in decision making. In project

management, the decision to apply TQ principles must be evaluated on the

basis of some deliberate policies with the aim of transforming the

organization into a quality company within the framework of its mission

and business goals. It follows therefore that only those who are equipped

with the necessary authority (at the top most management level) can decide

on the ways and means of committing the company’s resources in a TQ

policy.

In this case study, for instance, the decision to adopt JIT TQ, the

model to be adopted, the investment requirements etc; were taken

during the technical and commercial proposal stages of the project

which allowed the cost elements to be built into the project at the

tendering stages. A quality route selection scheme as already seen in

fig 2 was developed during the front end planning of the project. The

decision to adopt Just-in-time of TQ was taken based on its

experience and to give it competitive advantage ever other builders,

reduce field problems (post Commissioning failures, client complaints

etc.), offer some production cost reduction, increases profit yield and

reduce down time associated with repairs, retesting etc. prior to phase

II of the project ALCON’S concept of quality was still traditional

characterized by a mere programme keyed to assure conformance to

35

client specifications and without sufficient budgetary cover to permit

preventive efforts. In phase II and III, when it decided to introduce

Just-in-time of T Q, the project objectives became more centrally

defined and properly structured to minimize problems in delivery and

service. “Fire fighting” approaches usually adopted for correcting

defects became unnecessary, since the new techniques effectively

closed the loop holes that created the problems in the first place.

2.5.3 CONFIGURATIONMANAGEMENT AND WORK

BREAKDOWN STRUCTURES IN JUST-IN-TIME PROJECT

QUALITY PLANAING

According to the ISO 9004 part 7 [1994: p.405], configuration

management (CM) is a management discipline that applies technical and

administrative direction to the configuration, production and support life

cycle of a configuration item (CI) and aggregation of a project discrete

portions which can be treated as a single entities in the management process.

CM can be seen as the implementation of a formal management and

technical direction and controls definition of the functions and physical

characteristics of each item, to control the adoption of changes and to

maintain continuous accounting of the design and all equipment

configuration item of a CM are usually selected, by a process of

decomposition which divides the project structure into logically related

aggregates. CM helps in monitoring technical documentation to ensure

complete visibility of the products and consistency between the

documentation and the completed project itself.

A typical Configuration management plan (CMP) comprises five

phases – concept formation, definition execution, commissioning and post

commissioning which must be tailored to the project by the project manager.

36

A typical flow diagram of the CMP used for the case study is shown in fig.

2. 3. In our CM model, configuration base lines were established separating

the different phases and stages of the project. These represented points in the

project, which provided a precise identity of the results of the proceeding

phase and the objectives of the following phase. The effort on a project

could not be allowed to proceed until the documents consists of each base

line were verified as complete and accurate, and accepted by all parties. In

this way the client was carried along and assured that requirements were

being met. These base line documents, consisted of design documents,

approved for construction drawings, material take-off documents,

specifications, quality manuals and plans, project quality audit reports,

inspection and

37

Table 30

FIG. 2.3 CONFIGURATION MANAGEMENT ACTIVITIES

SOURCE: CM DESIGN FOR FLOW STATIONS UPGRADE, PHASE II, ALCON (1995)

─ Contract Award ─ Pre-qualification of personnel ─ Arrange plans and equipment

Stop 9 2

3 4 5

6 7 8 10 1

GENERAL MOBILIZATION PHASE

ENGINEERING PHASE

PROCUREMENT PHASE

YARD FABRICATION PHASE

MOVEMENT TO SITE

SITE PREINSTALLATION PHASE

SHUT DOWN WORKS PHASE

COMMISSIONING PHASE

POST COMMISSIONING PHASE

DEMOBILIZATION

CONFIGURATION MANAGEMENT PLAN

─ Detailed engineering ─ Design review ─ AFC Drawings ─ Approval of specifications ─ Materials acquisition ─ Detailed CMP ─ Detailed WBS

-Order material ─ Purchasing ─ Expediting ─ Shipment ─Forwarding ─Customs clearance ─ Delivery to site

─ Spool fabrication ─ NDT ─ Painting ─ Records ─ Package ready for shipment to site

─Shipment to site ─ Erect temporary site facilities ─ Ready to start inst work ─ Settle with communities

─Decommission ─Redundant system ─ Pre-install pipe work and new equipment ─ Civil works ─Inst./Electpre-shut down works

─Decommission producing system ─ Inst. new pipe work and tie-in to equipment ─ Tie-in all pre-installed items ─ Mach; instr/Elect ─ Carry out pre- commissioning cheeks

─ Start-up new and existing equipment ─ Carry out operating parameters check ─ Ensure all parameters are recorded

─ Paint entire facilities ─ clean-up site

─ settle all communities ─Demobilize all resources from site ─Reconcile materials ─ Hand over all works with certificates of completion ─ Produce project documentation and reports ─ close –out contract

Base line Base line Base line Base line Base line Base line Base line Base line Base line Base line

Start

LEGEND

Project effort

38

testing records, Operating Manuals etc. All documents included revision

information and traceability indexes. The CM base lines thus, provided a

stop gap opportunity to assure and reassure that the project quality objectives

were being met.

Closely related to CM is the concept of work Breakdown structure

(WBS), whereby the work items in the project were decomposed or broken

down into specific work packages with each package containing its budget, a

schedule, some performance evaluation criteria and information relating to

effort [Hajek: 1984 p.20]. The benefit of this is that it allows quality inputs

to be recognized and planned into every phase and activity in the project.

The Overall objectives of using configuration Management and work

breakdown structures is to avoid:

(i) Delays on decisions affecting optimal changes.

(ii) Undirected flaws requiring corrective actions.

(iii) Excessive cost of changes.

(iv) Documentation of those are inconsistent with actual site situations,

(v) Project objectives which are not clearly stated and understood by

every member of the T Q team.

39

2.5.4 ORGANIZING THE JUST-IN-TIME T Q M STRUCTURE

Heinz Weihric et al [1993: p. 20] have defined organizing, as that part of

managing that involves establishing an intentional structure of roles for

people to fill in an organization. It is intentional in the sense that all tasks

necessary to accomplish pre-selected goals are assigned to people who can

to them best and with clearly defined boundary of actions, its purpose being

to help create an environment for human performance. Therefore, the

effectiveness of a Just-in-time of a TQM programmed in a project depends

largely on an efficient and suitable human structure carefully deigned to

meet the project objectives.

In this case study, prior to kick-off, a project organization structure

(see fig. 2.4) was designed to allows flexibility in meeting JIT of TQM

objectives within all project disciplines, as well as allow for accountability

for action by all. Roles were assigned to all projects key personnel in the

team. Which was designed in line with requirements of the ISO 9001

model. The project manager was assigned the additional responsibility as the

leader of the TQM team, thus making him the TQM focal point, apart from

his primary duty for steering the technical and financial aspects of the

project. Similarly, every sectional head was assigned the additional task of

being responsible for quality in his area of Jurisdiction with all workers in

his team being accountable for their responsibility was that of the integrative

role of co-coordinating the programme amongst and within the various

disciplines. For effectiveness, the top echelon of the project was constituted

into the JIT of TQM committee as follows; project manager (team leader),

Quality manager (secretary),

40

Fig. 2.4: A TYPICAL TQM PROJECT ORGANIZATION C HART

SOURCE: ORGANI GRAM FOR FLOW STATIONS UP GRADE PROJECT, PHASE II, ALCON (1995)

MANAGING DIRECTOR

SAFETY MANAGER PROJECT MANAGER (TQM TEAM LEADER)

QUALITY MANAGER PROGRAMMED CO-ORDINATION

ENGINEERING MANAGER

PROCUREMENT MANAGER

PLANNING AND COST CONTROL MANAGER

ADMINISTRATIVE AND FINANCIAL MANAGER

CONSTRUCTION MANAGER

PROCESSЅ BASIC ENGINEERING

PURCHASING PLANNING AND SCHEDULING

ACCOUNTING FIELD ENGINEERING

DETAILED ENGINEERING

DRAFTING

EXPEDITING

SHIPPING AND TRANSPORT

ESTIMATING

COST CONTROL

PERSONNEL ADMINISTRATION

BANK AND FINANCING

FIELD CONSTR CREWS

GENERAL CINSTR

SERVICES

FIELD ADMINISTRATION

41

Construction, Engineering, Procurement, cost ,and planning, safety,

financial and Admin. Managers as members. Meetings were held by

monthly to specially discuss the progress and problems of the TQ effort.

Based in field reports, serious problems were diagnosed and remedy sort to

prevent recurrence. In this way, top management became aware of areas

where management action was required such as making equipment

replacement decisions, hiring of more competent personnel, introduction of

better equipment, out right change in procedures etc.

To facilitate the work of the TQ committee, quality review meetings

were held with the participation of the entire project term of about 350.

These meetings provided opportunity to further sensitize the workforce,

review the implementation of the TQ programme, high light critical quality

problem areas and allow workers to proffer solutions. It was discovered that

this 45 minutes, once – a – month meeting changed the thinking and

orientation of the lower level work force, boosted their morale and reduced

not only human induced defects, but also increased the volume of production

geared towards the positive impact of Just – in – time technique. Also,

workers became more conscious of their actions and efforts such as timely

reporting of equipment and process failures, changes in atmospheric

conditions (eg humidity) which can adversely affect the quality of their

work. Twice yearly, the managing director attended the quality review

meetings in order to have first hand information on the conduct of the

meeting.

As discussed above, three organization mechanisms were used to

achieve the desired TQ objectives namely. A formal project structure using

the cross- functional TQ committee and the quality review meetings. There

42

is other known tested mechanism-both formal and informal-which an

organization can use to achieve its objective. One of these is the use of

QUALITY CIRCLES which is a group of volunteers made up of workers

and managers who meet frequently to discuss quality problems in their work

bits with a view to finding solutions to these problems. The circle members

select the problems and are given training in problem solving techniques.

Juran et al [1993: p. 147] have identified a three fold powerful beneficial

effect of Quality circles thus;

(i) Effect on the workers’ individual characteristics – it improves

personal capabilities, increases the individual self respect and changes

certain negative personality characteristics.

(ii) Effect on workers’ individual relations with each other - it increases

the respect of management and supervisors for their workers and creates

workers understanding of the difficulties faced by the supervisors.

(iii) Effect on workers attitudes to the company – it allows for re –

orientation of negative attitudes towards the company goals, reduces

interface conflicts and creates general understanding of the TQ programme

amongst employees.

2.5.5 QUNLITY CONSIDERATION IN HUMAN RESOUCES

For JIT of TQ programme to be successful, careful consideration must

be given to the selection, training and motivation of the employee. It entails

aligning the team members to imbibe the culture of quality with a focus on

the customer, because only qualitative workers can produce quality results.

Selection is the process of choosing from among candidates, from

within the organization or outside it, the most suitable persons for available

positions in an established structures on the basis of some pre – determined

criteria such as the level and quality of training, relevant experience,

43

personal attitudes etc. It has been established that the quality of staffing

affects the quality of leadership and control necessary to achieve the

enterprise objectives, preventing many desirable deviations which can

adversely affect the quality of human output in a production process

[Weihrich et al. 1993: p.359].

In this case study, practical steps were taken to ensure that workers

selected to constitute part of the team were the best available within the

organization, 20% of the work force were also brought in from out side

using very strict pre – employment criteria. Training for selected personnel

was also given the necessary importance. Engineers and other technical staff

were sent on refresher courses within and out side the company, while

skilled and unskilled workers were given periodic tutorials and practical

training sessions to enhance the quality of their outputs. This arrangement

provided the opportunity for the project personnel to interact with expert

resource persons within the industry, thus broadening their own expertise

and helping to adapt new techniques and technologies. Further, periodic bi –

annual award with some monetary component was instituted and given to

the best member of the team who consistently maintain quality conscious

approach to his work for six months. The managing director during the

quality review meetings presented the awards. Apart from the monetary

package equivalent to the winner’s one – month basic salary, a souvenir, a

certificate and a letter of recognition was issued to the award winning

personnel.

One major discovery was that, these made the workers in the TQ Team to

take more pride in their work, boosted their morale, increase their

productivity and encouraged a higher team spirit within the TQ team. It is

not the intent of this work to study the various theories of motivation as

44

these are studied in existing literature [see Weihrich et al . 1993: p.462–488],

but suffice it to state here that motivation is a widely accepted factor in

human performance.

2.5.6 QUALITY CONSIDERATION IN ENGIVEERING DESIGN IN

JUST – IN – TIME PROJECT MANAGEMENT

By far one of the most important factors that bears directly on the

quality of any project, product, and system or for that matter any engineering

task, is the quality of input into the design and technical appraisal process.

Juran et al [1993. p.25] states that there is dramatic evidence that many

quality problems encountered by both internal and external customers can be

traced to design. These quality problems are easily traceable to deficiencies

arising from use of obsolete specifications, poor selection of processes, out

right technical errors due to limited experience and knowledge of the

designer etc. The severity of quality problems caused by design related

factors, if not detected early in the project life cycle, can totally derail an

otherwise laudable project leading to out right project abandonment, hence

the need to have necessary safe guards to identify impending problems,

before they become impossible to solve. One method is by design review

which is a formal, documented, comprehensive and systematic examination

of a design to evaluate the design requirement and the capacity of the design

to meet these requirements and to identify problems and propose solutions.

Design Review is usually done by specialist personnel with many years’

relevant design and field experience who meet as necessary to consider the

project concept, its function, its preliminary design, feasibility, main

trainability, operation ability etc. The purpose is to discover critical features

of the project design that may give rise to problems during the production,

material sourcing, maintenance, operations etc. and to consider the tests and

45

quality evaluation needed for reliability, safety, environmental, customer and

project life cycle demands.

In the case study, a design review method called Hazard and operational

analysis (HAZOP analysis for short) was used to identify design deficiencies

at the early stages of the project life. HAZOP analysis is a helpful qualitative

tool for design assurance and is similar to the so called failure mode, effect

and criticality (FMEC) analysis [Juran et al 1993: p.266]. During the design

review, a number of potential safety, environmental, operational and quality

problems which could have marred the project were discovered. In some

cased, designs were completely changed and scope of work revised on the

basis of the studies. Expectedly, on completion of the project, only routine

complaints were received from client and third party stakeholders who were

solved within the project guarantee period.

Once the design and other technical specifications have been reviewed

and approved for implementation, there is still need to monitor, account and

control its circulation and use, and ensure that only the initial approved or

approved variations of it, is transmitted into the project execution processes.

Therefore, there must be a defined process for managing design inputs and

out puts, design changes, document control procedures etc. This is because

mismanagement of engineering information can impact very negatively on

the project quality even though all designs, specifications etc are right. In the

case study project, the designs and technical documents were managed as

discussed below.

2.5.7 DESIGN INPUTS

Distribution of the applicable information from the client’s contract

and technical specifications was recognized as the start point of each design

activity in the project. Where contractual rules and regulations were being

46

complied or a third party certifying authority involved, the project team

made itself aware of the requirements of the body and relevant approval

needs. Based on the identified technical data, the engineering team defined

the basic parameters of the systems to meet functional, safety, reliability and

operational requirements. The Quality Assurance function ensured that the

design inputs, were clearly identified, documented, reviewed and that the

quality requirements provided for proper flow of technical information, its

control and revision as needed.

2.5.8 DESIGN OUTPUTS

Design documents (such as drawings, specifications, calculations,

procedures etc). We are prepared by specialist engineers in the project team.

Each design document was checked by another senior specialist engineer

who verified compliance with the contractual data, interface constraints,

safety, layout etc.

The Quality Assurance function ensured that all design criteria

imposed by the client were clearly identified, documented and that a system

of technical information retrieval by numbering, indexing, filing etc., was

available for every out going document. It also ensured that the design

review and verifications processes were completed prior to issuance. The

project manager had the ultimate responsibility for approving and issuing

technical documents to the client and third party certifying authorities, where

required.

47

A typical design Sequence Schematic is shown in Fig 2.5

CONTRACT SPECIFICATIONS

PROJECT ENGINEERING

ENGINEERING DEPARTMENT

LIST OF DESIGN DOCUMENT

DESIGN DOCUMENTS

DESIGN DOCUMENTS

INTERNAL VERIFICATION

Q. A VERIFICATION

PROJECT INTERNAL APPROVAL

CLIENT APPROVAL / CERT. AUTHORITY

PROJECT CONCRETION DEPARTMENT

SITE

FIG. 2.5: A TYPICAL DESIGN SCHEMATIC SEQUENCE SOURCE: DESIGN MANAGEMENT FOR FLOW STATIONS UPGRADE, PHASE II

ALCON (1995)

48

2.6.0 QUALITY CONSIDERATIONS IN MANAGING MATERIALS

AND PROJECT INPUTS

A company’s quality programme, no matter how carefully designed,

will not yield optimum result, except there is a defined process to ensure that

in-coming materials and inputs by other parties, especially sub contractors

are subjected to the same rigorous quality management as with the internal

processes. One method to achieve this is by in-coming materials control and

sub-contractor/vendors whose activities have impact on the quality of the

project.

[Feigeribaun 1993: p.681] defines material control from quality

management perspective as involving the receiving and stocking, at the most

economical level of quality of only those parts whose quality conform to the

specification requirements, with emphasis upon the fullest vendor

responsibility. Sub-contracts on the other hand, are those services given out

to others which in the opinion of the prime contractor will help to achieve

the objectives of the project in terms of quality, as well as optimize the use

of specialized resources which are better manage by the specialists in certain

aspects of the project.

In the case study, project materials were widely varied such as heavy

duty machinery, valves, pipes, fittings, structural steel, instruments,

electrical machines, cement, aggregates etc. Therefore the co-ordination of

quality of inputs posed challenges to the TQ team. For instance, in phase I of

the project, a particular batch of concrete for vibrating equipment foundation

(export pump) was found to have very low crushing test results. On

investigation of the causes, it was discovered that from a sample of 100 bags

taken from a batch of 1000 bags supplied (ie. 10%), the port land cement

averaged 42.8kg per bag instead of 50kg. The design was for 8 bags (400kg)

49

per m3 of concrete, thus implying that every m3 of concrete cast fell short by

57.6kg. Further investigation showed that the shortages were in fact

committed at the bagging section of a local cement bagging plant. There

were other similar situations whereby suppliers used body fillers to build up

late thickness to meet specifications in their purchase orders. To prevent re-

occurrence of such problems in phase II of the project, a proactive quality

management approach was adopted to ensure proper verification of all

project inputs as discussed below.

2.6.1 PROCUREMENT DATA PROCESSING

Material list requisition and inquiry list of materials to be purchased,

as well as subcontracts were finalized prior to project kick-off which were

then included in the overall project planning. The main aim was to ensure

that an effective system was put in place for planning quality into

procurement and vendor activities. The project procurement function was

responsible for issuing inquiries, based on requisitions from the various

functions while QA ensured that applicable quality requirements were built

into such inquires. Inquires were issued only to qualified suppliers and

contractors who were assessed on the basis of their objective evidence of

ability to comply with specified requirements and previous experience.

Every inquiry documentation included: a correct description of the item to

be purchased or the scope of work to be subcontracted, drawings and

specifications which established what codes and standards to be fulfilled,

QA system requirements, inspection and testing requirements, certification

by an accepted inspection entity, list of documentation and certificates

requirements for packing, handling, storage and transportation.

On receipt of response to inquires, the responses were reviewed on the

basis of certain criteria such as the ability to meet preset quality

50

requirements, economic view points, delivery terms etc. The winning bid

then gets a firm order.

A procurement flow scheme involving quality consideration is shown

in fig 2.6

51

REQUISITION DOCUMENTATION

PROJECT ENGINEERING

PROCUREMENT

INQUIRY TO QUALIFIED SUPPLIERS

BID

PROCUREMENT

COMMERCIAL EVALUATION

MATERIAL LIST

Q. A VERIFICATION

ADMINISTRATIVE FINANCIAL EVALUATION

Q. A AND Q. C EVALUATION

TECHNICAL EVALUATION

P. O REGISTER PURCHASE ORDER APPROVAL

SUPPLIER P. O ACCEPTANCE

P. O FILES

PROJECT ENGINEERING

QUALITY ASSURANCE

MATERIAL CONTROL

FINANCE

52

FIG: 2.6 TYPICAL PROCUREMENT SCHEMATIC SEQUENCE

SOURCE: QUALITY CONSIDERATION IN MATERIAL

/SUBCONTRACT MANAGEMENT FOR FLOW STATIONS UPGRADE,

PHASE II, ALCON (1995)

2.6.2 MATERIAL CONTROL

All materials to be used in a project should be subjected to strict

quality control at manufacturer site and to inspection by the material control

personal at their receipt at every location.

The quality plan should establish method of acceptance of material in

manufacturer site according to the following process:

- Acceptance by certificate of conformance method

- Acceptance by receiving inspection method

- Acceptance by surveillance method

Dedicated project procedures should be available detailing how materials are

to be received, handled, identified, stored and issued to production to allow

for full traceability. The subject of materials control is wide and poses

special challenges in terms of quality, economics, Usage etc. The discussion

on material management and control is outside the scope of this study,

however a large body of knowledge can be found in existing literature [see

Feigenbaum 1991: p. 677 – 735].

2.6.3 BIULDING QUALITY INTO PROJECT EXECUTION

PROCESSES

A process has been defined as some unique combination of machines,

tools, methods, materials and people engaged in production of something

53

[Juran et al. 1993, p.393]. For total quality to be built into the execution of

any project, it requires that all processes, which directly or indirectly affect

quality be identified and that these processes are carried out knowledgeably

by all and under controlled conditions via documented procedures defining

every possible task that could be encountered, the amount of knowledge

required of the personnel performing the task, the type of suitable

equipment, compliance with requirements of all reference codes, standards,

specifications, monitoring and control of process parameters to meet some

pre set acceptance criteria for workmanship, aesthetics, maintainability,

operation ability and reliability. [see Lockyer, et al. 1983, p.20].

When a quality system is being developed for a project, one of the

first decisions to be taken is that of defining the activities to be covered by

the system. The activity definition must have a mechanism for controlling all

inputs – both hardware and software, including information -that goes into

every process throughout process throughout the project life cycle also, there

must be a way of verifying that each process has an acceptable out put that

meets the stated needs of the immediate client, as well as the implied needs

and expectation of other stakeholders who may be impacted by the process

being implemented.

In the case study project, the following methods were adopted by the

JIT of TQM team to achieve a satisfactory delivered project.

Generally, project production processes were properly planned and

organized before work break down structures previously discussed.

Technological processes to be adopted were evaluated not only from the

production performance point of view, but from the quality consideration.

Resources, facilities and materials were provided timely to avoid

delays which usually lead to rework. The production personnel were trained

54

and qualified to acceptable codes for the operations they were employed to

do. Responsibility for project quality was placed on those managing,

supervising, planning the work, as well as those performing the work, with

additional provision for in – process surveillance during installation to

ensure that the required level of quality was being attained and that deficient

items or systems were found and prevented from further processing.

Inspections of work – in – progress were performed to verify that items

being installed, assembled or constructed complied with requirement of the

contract, latest revisions of approved specifications, drawings, procedures,

standards and codes.

2.6.4 PROCEDURES AND INSTRUCTIONS

Procedures provide the fulcrum around which quality surveillance

revolves. In JIT of TQM, the rule of the thumb is; “if it is not written down,

it does not exist, but when it is written, it must be done”. This underscores

the importance of documented way of executing every project activity. For

the case study project, each project activity was covered by adequate

instructions in form of drawings, specifications, work procedures, method

engineering statements etc, with the project manager ensuring timely issue

of such instructions to all personnel and forwarding of Subsequent revisions

to ensure that personnel were updated adequately.

Special processes were covered by detailed procedures which were

qualified by tests prior to work commencement. Such processes included,

welding procedures, non destructive and destructive examination

procedures, heat treatment procedures, coating and hydrostatic testing

procedures etc. Also, apart from testing the procedures to ensure that they

will meet the required services, the operators assigned to execute the

55

procedures were subjected to performance qualification tests before being

allowed to make production input [Hajek et al. 1984, p.85].

2.6.5 PROCESS CONTROL

All project activities were subjected to inspection on the basis of the

requirements of the contract and all associated codes, standards and

specifications. These inspections were detailed in the quality control plans

and procedures which were developed at the planning stages of the project

containing as a minimum, control activity against process description,

process document references, verifying document references and

intervention required for all organizations involved in the process execution.

Specialist inspectors were responsible for the inspection activities specified

in the relevant control plans and were provided with all necessary technical

data, drawings, specifications, procedures etc.

2.6.6 FINAL INSPECTION

Final inspections to verify that the completed systems and items were

in conformance with specified requirements were carried out. These

inspections verified the operational readiness of systems and items. The

inspection techniques selected were determined by considering the

characteristic or parameter to be measured on the operations being

performed. The basic criteria for the selection of inspection techniques and

processes were based on requirement of the applicable specifications, codes

and standards.

When the physical inspection of completed items was impossible or

disadvantageous, in direct control by monitoring of the processing methods,

equipment and personnel were performed. Inspection and process

monitoring were also performed were control was inadequate without both.

56

2.6.7 QUALITY RECORDS

A good Quality Assurance programme ensures that there is objective

evidence of the quality of the work being done via quality records. For this

purpose, a system of records to document the internal control on all project

processes must be developed.

Records should be easily retrievable and traceable to the processes

which they were produced for, provided with identification, date, signature,

activity reference. At the beginning of the works, an indexing system should

be established for all record to be produce on a project index. Generally,

quality records should have adequate provision at all intervention points of

the production processes, as discussed below.

(i) Inspection Records. Documentation of inspection results is important

for evaluation purposes and to provide evidence that the inspected item or

systems are acceptable. For the case study project, checklists, which list each

inspection criteria, were prepared to document the results of the various

inspections. As a minimum, they identified the date of the inspection, the

inspector, reference appropriate drawings and specifications, and note the

type of observation, the results, the acceptability of the results, and the

action taken in document with any deficiencies noted.

(ii) Monitoring inspection results: The inspection results for the various

processes should be monitored to keep a track of the processes, which were

producing deficiencies. This monitoring is often called trend analysis. In this

case study, this trend analysis’s were performance by complex methods (e.g.

statistical evaluation) and simple methods (e.g. plotting the percentage of

rejects on weekly basis). The trend analysis provided a much more objective

and systematic appraisal than that achieved by simply relying upon the

memory of the inspection or construction personnel (Spiegel 1972).

57

When an analysis revealed some problems, the first step was to

determine the cause of the problem and then take steps to correct the causes.

It was not sufficient to simply increase inspection, since this will only

separate the good from the bad. Increased inspections usually increase costs

because the money spent on work which was rejected cannot be retrieved

and the increased volume of inspection costs more money. The greater

amounts of rework also affect the schedule, since less acceptable work is

completed.

(iii) Final data book: All project records should be collected in a final

data book, which documents the complete history of the work, performed. In

the case study project, the detailed list of the records included was finalized

under the responsibility of the project Q.A. function.

2.6.8 NON CONFORMANCES

Any non-compliance with approved plans, drawings, procedures or

specifications is a non-conformance. Therefore, non-conformances may be

related to materials, documents and activities. Two examples of non-

conformances are described below:

(1) PROCUREMENT NON-CONFORMANCE: Procurement non-

conformances are deviations from procurement document

requirements. It is essential to correct these non-conformances to

prevent further processing, and completion or delivery of material

and equipment items to incorrect procurement requirements.

(2) CONSTRUCTION PROCESS NON-CONFORMANCE: It is

important to present the use or installation of items which have

been determined to be unacceptable. An effective and positive

system for controlling these items included procedures for the

identification, segregation, and disposition of the non-conforming

58

items. Non-conforming items should be identified by the use of

tags or other markings, or the placement of these items in

containers, which are so marked.

The responsibility and authority for the disposition of non-

conforming items must be defined to assure that these important

decisions are controlled.

2.6.9 CORRECTIVE ACTION

The aim of a corrective action in project management is to rectify

non-conformances and prevent their reoccurrence. The project Q.A. function

should be responsible for initiating all corrective actions. The corrective

actions could be generated by an audit or an inspection as result of

evidenced deficiency.

2.7.0 MEASUREMENT AND TESTING

The accuracy and adequacy of measurement and testing is very vital

in a project to assure that quality requirements are being met. It provides

some level of confidence that quantity and quality as specified in design and

other engineering specifications are being followed and should be a routine

requirement in the project execution process.

In the case study, to ensure precision, tools, gauges, instruments and

other measuring and testing devices were calibrated to assure that they

produced accurate measurements. They were physically identified by unique

serial (or other) numbers, and calibrated according to reference standards.

The equipment were calibrated at scheduled intervals with each item

calibration interval being based on the type, required accuracy level, and the

frequency of use. Every,calibrated equipment had a label bearing the

equipment serial number, the date of calibration, the last date the equipment

could be used and the name of person or company performing the

59

calibration. The TQM team performed some of the calibrations, while it used

the services of independent laboratories for others. In some cases, the

equipment supplier performed the initial calibrations when it was stipulated

in the purchase order (certificate of calibration was requested from the

supplier or the records).

2.7.1 AUDITS AND FIELD FEED BACK

For a JIT of TQM programme to succeed there must be a visible

mechanism for self appraisal to show that the programme is indeed on

course. The ISO 8402, [1994: p. 26] defines quality audit as a systematic,

independent examination and evaluation to determined whether quality

activities and results comply with planned arrangements and whether these

arrangements are implemented effectively and are suitable for achieving

objectives. Juran et al [1993: p. 567] states that “independence” of the audit

team should be a critical consideration in the sense that the reviewer(s) is

neither the person responsible for the performance under review nor the

immediate supervisor of that person.

The purpose of audits on a project is to provide independent assurance

that;

(1) Plans for attaining quality are adequate, such that if followed the

intended quality objectives will be achieved.

(2) Relevant codes, standards, specifications and regulations in so far

as it affects the project are being followed.

(3) The data collection system is accurate and adequate.

(4) Non-conformances are identified and corrective actions

implemented.

The production process or its final product can be audited, but in project

management, the aim should be to audit the project processes right from

60

conception to commissioning and hand over. This is the only way audits can

be harnessed and built into the entire project.

2.7.2 AUDIT SCHEDULING

The audit should be regularly scheduled on the basis of the status of

work activities. They are normally conducted at the beginning of a project,

at three-month intervals during peak periods, and near the completion of

work.

Regularly scheduled audits can be supplemented by additional audits

when any of the following conditions occurs;

(a) When it is suspected that the quality of an item is in jeopardy due

to deficiencies in the quality management programme.

(b) When significant changes are made to the quality management

programme such as extensive reorganization or procedure

revisions;

(c) When independent assessment of programme effectiveness is

considered necessary;

(d) When it is necessary to verify implementation of required

corrective action.

2.7.3 AUDIT PLANNING

Audits are performed in accordance with checklists used by the

auditor to enter all pertinent areas in an orderly sequence and with a

minimum of wasted time and effort. Without a checklist, the auditor enters

an area with only the requirements or working procedures at hand. It is

difficult to leave through the requirements, documents, or procedure on the

spot and pick out the specific items that can be checked at the point it is all

too easy to live the area only to find, often when it is entirely too late to

remedy the over sight, that one or more significant points have been over

61

looked. The audit checklist provides a useful means of determining, at any

time what was actually done during the audit and what the auditor found.

2.7.4 AUDIT PERSONNEL

To avoid conflicts of interests, personnel who do not have direct

responsibilities in the areas being audited should perform audits. Personnel

performing audits should be competent and have sufficient authority and

organizational freedom to make the audit process meaningful and effective.

When specific technical expertises are required in the performance of an

audit, it is desirable to select appropriately qualified technical personnel to

participate in the audit.

2.7.5 AUDIT REPORTING

In the case study project, audit results were documented in an audit report

form which was transmitted to management personnel having responsibility

for the activity audited. The audit report included the following;

(a) Description of the audit scope;

(b) Identification of the auditors

(c) Personnel contracted during the audit;

(d) Summary of the audit results;

(e) Details of specific non – conformances observed;

(f) Recommendations for correcting quality programme non –

conformances or improving the program;

(g) Date of required response by the audited organization.

The report was distributed to management of both the audited and auditing

organization and issued within 5 working days after the audit.

2.7.6 AUDIT FOLLOW – UP

This is important for an effective TQ programme. Usually, the

management of the audited activity should scheduled appropriate corrective

62

action, to prevent recurrence (including, where necessary, changes to the

quality management programme). Follow – up actions are taken by the audit

team leader for the following reasons;

(a) To obtain a written response to the audit report, when a response is

required.

(b) To evaluate the adequacy of the response

(c) To ensure that corrective action and means of preventing reoccurrence

are identified and scheduled for each non – conformance,

(d) To verify that corrective actions are accomplished as scheduled.

2.7.7 INTEGRATION AND ENCULTURIZATION OF JIT OF TQM

PROGRAMME

The attitude of the people doing the job determines the level of quality

that can be attained – numerous quality problems is attitudinal; while

management should give the direction and vision; every member of the

organization should receive and drive the JIT of TQM objective of the firm.

Therefore, the TQ machinery of the firm must necessarily function Via the

co- operation of all members.

Juran et al [1993: p.158] have defined quality culture as the pattern of

human habits, beliefs and behaviour concerning quality. Thus, while all

variables discussed under the basic system design for TQ in this paper, are

management controllable, it will be fool hardy to think that a disoriented

work force which does not take these issues to heart can effectively produce

tangible results in terms of meeting the desired quality objectives. This then

is the reason for integrative approach to the subject of TQ, where by all men,

machines, tools, information and indeed all company resources are

integrated and harmonized for optimum quality performance. Thus, the top

and middle level management spends more time in teaching, counseling and

63

leading both individual employees and employee work teams on quality,

productivity and other related matters, which makes the entire work force

participation to become institutionalized in the quality programme. The TQ

concept must be sufficiently internationalized and appreciated by every

segment of the project team before it can be effective.

In this case study scenario, there was a dramatic discovery that the most hard

working employees, when given a little training on quality consciousness,

can also be the most quality minded, thus re – affirming that quality and

productivity is a habit and can be mutually integrated into production

without any operational conflicts. To enculturize quality habits, our

experience shows that there must be the “CARROT” and the “Stick” side by

side, to respectively encourage the determined employees and prevent the

never changing types from corrupting the programme.

2.7.8 OTHER ACCULTURIZED TOOLS AND TECHNIQUES FOR

TOTAL QUALITY

To successfully progamme TQ into a project as discusses in the

proceeding section, we need to appreciate what scientific tools and

techniques are available for quality Improvement in project processes from

conception up to commissioning and hand over. The ISO 9000 series has

identified and recommends a number of techniques for use in contractual

situations, such as project engineering. Table 2 shows list of both numerical

and non – numerical tools recommended by ISO 9004 – part 4 (1994: p. 6)

of these tools and techniques, shell Malaysia (petronas carigali) strongly

recommend the use of the following as primary or frequent application tools

for day to day management of quality in its engineering projects. These in

addition to other TQM tools discussed in this chapter.

64

Check sheets

Bench marking

Brain storming

Flow and control charts

Histograms

In this case study, the following tools and techniques were used:

(i) CHECK SHEETS: Check sheets were developed for every

conceivable aspect of the project like design review check sheet, procedure

review, specification, purchasing construction and reaction activities check

sheets. In all over 200 check sheets were developed for the project

(ii) BENCH MARKING: There was a deliberate attempt to improve in

quality by comparing the available process and performances to that of those

considered to be industry leaders. This led to management radical decisions

in such areas as equipment replacement decisions, personnel retraining and

outright changes in procedures and process. At commencement of the

programme, two companies were identified as industry leaders in TQ and

efforts were made to study their systems, most times by engaging their

strategic personnel through pay and other incentives.

(iii) BRAIN STORMING: This provided opportunities for every segment

of the company and within the TQ team to interact, thus tapping the creative

thoughts of every team member to generate and clarify ideas, problems and

issues. For example, all the decisions reached during the bench marking

processes were as a result of brain storming.

(iv) FLOW DIAGRAMS: Flow charts were used in the project as a

planning tool, either to describe an existing process or design entirely a new

one in order to gain precise understanding of how a selected process should

65

work. Flow charts were used extensively in TQ programming efforts as

already seen in the proceeding section.

(v) HISTOGRAMS AND TRENDS CURVES: Histograms were

developed for analysis of situations, when there were need to graphically

summarize some variations in a set of data. For instance, in phase I of the

project, it was discovered that the plant shutdown time approved for each

plant was being exceeded by an average of 18 hrs per station implying oil

deferment, increased supervision cost, loss of revenue to the client and

ultimately client dissatisfaction. After a careful study, it was discovered that

the root cause of the problems arose from under estimation of the scope of

tie in works and consequent impact on the production and service delivery.

To correct this problem in phase II, manpower histograms were constructed

to show weekly requirements of all description of manpower per flow

station, who were them matched with appropriate tools and equipment they

required to do their work effectively. Also, trends curves were developed by

trade, thus enabling the team to evaluate its readiness for that phase of the

work.

A typical manpower histogram used for the project is shown in fig

2.7. This approach enabled management to deploy enough resources as

required with a consequent reduction of plant down time from the approved

14 days to an average of 11.75 days per facility. Of course, this delighted the

client which rewarded the TQM team by awarding the phase III of the

project to it.

66

A TYPICAL MANPOWER HISTOGRAM USED FOR THE

PROJECT`

WEEKS

Fig 2.7: skilled manpower loading histogram

Source: manpower loading, flow stations upgrade phase II, alcon (1995)

(VI) CONTROL CHARTS: Generally, control chants are used

Fig 2.7: Skilled Manpower Loading Histogram

Source: Manpower loading, flow stations Upgrade Phase II, Alcon (1995)

No. of workers

140

120

100

80

60

40

20

0 1 2 3 4 5 6 7 8 9 10

Weeks

67

(vi) CONTROL CHARTS: Generally, control chants are used to show

the significance of an observed difference between a process actual

performance and some set goals. Process variations can be as a result of; (i)

A read difference due to some cause or (ii) An apparent difference arising

from random variation. According to Juran et al: [1993: p. 108], the former

is termed random (due mainly to chance), while the latter is called

Assignable causes. Random causes are allowed in a process while assignable

causes are not allowed. Control charts are used to distinguish random from

assignable causes in a process through choice of control Limits, which are

calculated from the laws of probability in such a way that highly improbable

random variations are presumed to be due not to random causes but

assignable causes. Thus, when the actual variations exceed the control

Limits, it signifies that some assignable causes have entered the process and

the process should be investigated, while variations within the control Limits

means that only random causes are present and the process is statistically

stable /okay and should be left intact. The control chart therefore, provides

an early warning of impending problems which could have a major

economic significance, if the process were allowed to continue on

uncontrolled. It is thus used as a preventive tool. There are three main types

of control chart namely;

Those that plot statistical mean X and range, R (called X- and R-

charts).

Those that plot percentages (called P- charts) and

Those that plot number of non – conformities (called C- charts). These

charts are used depending on what is being investigated.

In this case study project, control charts were used for evaluating process

stability, determine when a process needed to be adjusted, or rejected out

68

right and to confirm that some certain processes were responding to

improvement efforts. For example, every high importance was attached to

assuming the quality of parent metals and their fusion weld joining

processes, because of the safety, environmental, cost and operational

implications. It was therefore mandatory to carryout 100% Gamma ray

examination on all process equipment, as well as 24 hour hydrostatic testing.

These are two forms of non – destructive examination (NDE) to assure that

the systems will be able to with stand operational working pressures,

stresses, impacts etc. Hydrostatic testing was achieved using high pressure

pumps to raise the hydraulic pressure to 1.5 X design temperature for 24

hours within the design temperature develop. The test pressure was then

observed for the varying conditions; pressure, temperature and flow

recorders equipped with time mechanisms, were used to monitor these

conditions on a P – chart. A sudden drop in test conditions is immediately

noticed on the chart and if it drops further below a certain percentage, the

test is superadded and the system checked for faults, which are rectified

before continuing. If it is a long pipe for instance (eg.20kg), the entire length

is inspected physically to locate exact problem point. In this way, there is an

assurance that the pipeline will perform to design requirements when

commissioned. A pressure – flow circular chart is used to record the test

using a Bordon Spring of suitable range at atmospheric temperature. There

are other controls charts like, stress relief charts, differential pressure – flow

chart etc. for use depending on what is being controlled.

(vii) CAUSE AND EFFECT DIAGRAMS: Though, it has been

emphasized in this chapter but to go into details; Extensive use was made of

cause and Effect diagrams otherwise called the ISHIKAWA diagrams

named after Kaoro Ishikawa who first developed it. Though initially

69

designed for descriptive problem analysis, they have been improved for use

in effectively solving process problems, especially in system trouble

shooting. Example of a practical application is the typical cause and effect

Matrix for flow station logic system. This is use for safety and operational

shutdown devices in the plant. A typical flow station has between 10 and 20

surface processing and production units, including 5 to 10 heavy duty

rotating equipment and about over 50 electro pneumatic control instruments

that keeps the plant in unmanned mode. The cause and effect diagrams allow

for diagnosis of plant problems when they occur, since the plants are

unmanned.

TABLE 2.1 TOOLS & TECHNIQUES USED QUALITY

IMPROVEMENT

NO TOOLS AND TECHNIQUES

APPLICATION

1 GENERAL (i) Data Collection Firm To gather data systematically in order to

obtain picture of the facts (ii) Check List A simple data - recording from which

results can be readily interpreted from the firm itself

2 NON-NUMERICAL TOOLS AND TECHNIQUES FOR NON-NUMERICAL DATA

(i) Affinity Diagram To organize into groupings in large number of ideas, opinions or concerns about a particular subject

(ii) Bench Marking To compare a process against others to identify opportunities for improvements

(iii) Brain Storming To identify possible solutions to problems and potential opportunities for improvement

(iv) Cause and Effect Diagrams (Also known as ISHIKAWA

To communicate cause and effect To facilitate problem solving from

70

diagram) symptom to cause to solution (v) Flow Chart To design a new process

To describe an existing process (vi) Tree Diagram To show relationship between a subject

and its component elements 3 TOOLS & TECHNIQUES

FOR NUMERICAL DATA

(i) Control Charts Diagnosis: To evaluate process stability Control: To determine when a process

needs to be adjusted and when it needs to be left as it is

Confirmation: To confirm an improvement to a process

(ii) Histograms To display the pattern of variation of data To communicate visually, information

about process behaviour To make decisions about where to focus

improvement efforts (iii) Pareto Diagram To display, in order of importance, the

contribution of each item to the total effect

No TOOLS AND TECHNIQUES APPLICATION To rank Opportunities. Ranked Comparison

of factors related to problems separates vital few from useful many.

(iv) Scatter Diagram To discover and confirm relationships between two associated sets of data.

To confirm anticipated relationships between two associated sets of data.

SOURCE: ABRIDGED FORM 150 9004 PART 4:

GUIDELINES FOR QUALITY IMPROVEMENT, (1993: P2)

71

2.7.9 WHEN TO REORDER WITH EOQ ORDERING

EOQ models answer the question of how much to order, but not the

question of when to reorder (Stevenson 2006, 8th edition). The reorder

occurs when the quantity on hand drops to a predetermined amount. That

amount generally includes expected demand during lead time and perhaps

on extra cushion of stock, which services to reduce the probability of

experiencing a stock out during lead time.

In order to know when the reorder point has been reached, a perpetual

inventory is required. The goal in ordering is to place an order when the

amount of inventory on hand is sufficient to satisfy demand during the time

it takes to receive that order (ie lead time). There are four determinants of

the reorder point quantity.

The rate of demand (usually based on a forecast)

The lead time

The degree of stock out risk acceptable to management

The extent of demand and / or lead time variability

R OP = d x LT at constant demand and lead time where d = demand

rate (units per day or week), LT = lead time in days or weeks.

When Variability is present in demand or lead time, it creates the

possibility that actual demand will exceed expected demand. Consequently,

it becomes necessary to carry additional inventory, called safety stock, to

reduce the risk of stock out during lead-time. The reorder point in greases by

the amount of the safety stock ie ROP = expected demand during lead-time

+ safety stock, where SS = Zσdlt where SS = safety stock, Z = Number of

standard deviation of lead time demand, Zσdlt = the standard deviation of

lead time demand. The amount of safety stock for a particular situation

72

depends on * The average demand rate and average lead time, * Demand

and lead time variability * The desired service level. ROP AT SAFETY STOCK THAT REDUCES RISK OF STOCK OUT DURING

LEAD TIME

Figure 2.8 (R.O.P at safety stock)

2.8.0 INVENTORY CONTROL

This is defined as the scientific way of finding out the quantities to be

kept in stock to meet the production requirements and the systematic

location, storage and recordings of the goods/items in such a way that

desired degree of service can be provided at competitive prices or at

minimum ultimate cost.

The functions of inventory control are as follows;

To develop policies, plans and standards required

To ensure effective running of stores

Technological responsibility for the state of different materials

Qua

ntity

LT

Maximum probable demand during lead time Expected demand

during lead time

ROP

Place order

Receive order

Safety stock Time

73

Stock control system

To ensure the timely availability of goods.

Inventory can be viewed as a descriptive list of items/goods which gives

quantity and money value of each item. Inventory has the following as its

functions;

It serves as cushions

It serves as a necessary evil for any enterprise

It provides production economies

Maintenance of smooth and efficient production flow

Creation of motivational effect in decision making.

Inventory has the following as it importance;

(i) Good consumer service can be provided and maintained in the

organization.

(ii) Enables smooth and efficient production flow of goods/items.

(iii) Provides protection against uncertainties regarding demand and

supply of materials and out put.

(iv) Ensure better utilization of men, machines and materials.

The various classification of inventory are as follows;

Production inventory

Work in process inventory

Finished goods inventory

Operating and maintenance inventory

Miscellaneous inventory

2.8.1 INVENTORY CONTROL MODELS

One of the problems of inventory management is to find out the

quantity (of items required as inventory) to be ordered for each of the

74

supplies or the lot size to be manufactured. So that it is most economical to

the enterprise or organizational aspects point of view (Stevenson 2006).

In inventory control, two conflicting costs come into picture which

finally decides how much is to be ordered or produce. This model integrates

the time, costs and quantity of items to be produced.

MODEL I; Harris formula for instantaneous supply, continuous

consumption and zero buffer stock (Relationship for EOQ and ELS).

Let Yc = total yearly cost (total annual investment)

Yc = material cost + Annual Inventory carrying or Holding cost of

Procurment or preparation or set up cost.

But;

Material cost = Unit cost x Annual production/usage

∴ Material cost = CD

Annual inventory carrying cost/Holding Cost = (Holding cost) x average

Inventories = CxHQ2

But D = annual production, C = unit cost of production

Q = economic lot size to be manufactured.

Preparation cost or set up cost = preparation cost per unit x D = P/Q x D.

Yc = C x D + (Hc) Q/2 + P/Q x D

Now, for economic ordering Quantity or lot size, differentiating Yc with

respect to, Q and equating it to zero, we have

220.

2)(0

QPDHC

DQPQ

HCCDdQd

dQdYc

OR

HC

DP.2 Note: No reserve stock has been kept

75

MODEL II; ECONOMIC ORDER QUANTITY OR ECONOMIC LOT

SIZE WITH RESERVE STOCK

Here when the supply is instantaneous and consumptions continuous and

there is reserve stock and for this model, the pattern of inventory is shown

below; ECONOMIC ORDER QUANTITY WITH SAFETY STOCK

Maximum level

Re – Order level

Figure 2.9 Economic order quantities with safety stock

Now following the previous notations and R as reserve stock, we have the

total annual costs (Yc) as:

Yc = material cost + Inventory carring or Holding cost + setup cost. But

material cost = C.D Inventory carrying cost = H x cost if inventory =

H(R+2Q ) C . Here we take the average of Q and zero plus safety stock setup

cost = P/Q x D

Yc = C.D + H . C (R + Q/2) + P/Q x D

Inve

ntor

y qu

antit

y

Q(yr)

Safety stock minimum level R

Time

76

Uc = C.D + Q

PD + HRC + H2Q .C

Let R/Q = F ie Let R be taken as a fraction of Q or R = fQ.

Yc = C.D + P/Q.D + H.Q.F.C + H.Q/2 .C

For economic order, quantity or economic lot size differentiating with

respect to Q and putting to zero, we have;

CHQCHQfDQ

PDCdQd

dQdYc .

2.....

2QP D + H.F.C +

2HC = O OR

P/Q2 D = HC [f + ½] = 2

)12( fCH

OR Q2 = )21.(.

2),21(

2fHC

PDQ

fCHPD

77

MODEL III; ECONOMIC ORDER QUANTITY OR ECONOMIC

LOT SIZE WHEN THERE IS SHORTAGES

See the illustration below; MAXIMUM INVENTORY LEVEL

MODEL FOR ECONOMIC

ORDERED QUANTITY

WITH SHORTAGES

Qm

SHORTAGE QUANTITY Time

Figure 2.10 economic order quantity when there is shortages

Following the previous notations with

C1 = penalty per unit shortages cost per unit time.

Q = order quantity or lot size, Qm = maximum Inventory level, n = Number

of Orders planed per year = D/Q Total time of the cycle t = t1 + t2. t1 is the

time during which demand is met from inventory stock and t2 = the time

when shortages occur. Now, using the geometrical relationship from these

similar triangles as shown below;

Inve

ntor

y Q

uant

ity

Q

t1 t2

78

SIMILAR TRIANGLES

We have Q

Qmtt1 from ∆s, CDB and CED

OR

t1 1egntQ

Qm And t2 = )2(egnt

QQmQ from ∆S,

COB and OFD or OAD

Now, the average number of units in inventory during time t1 = 2

Qm

Average Inventory cost during time t1 = 2

Qm C. t1 But, Average Inventory

Carrying cost during this period = H. 2

Qm C. t1; since n is the number of

orders placed annually. The annual inventory carrying cost will be = H. 2

Qm

C. t1 x n

Similarly, the average number of units short during

22

QmQt

The average shortage cost during time

22

QmQt

C1 t2

Annual Shortage Cost = 2QmQ C1 t2 n

C

Qm

Q B

E

t1 Q-Qm

t

O t2 A

F t2 D Time

Qua

ntity

79

So that yearly Cost (Yc) material cost + Inventory carrying cost + setup cost

+ shortage cost = C. H 2

Qm t1 n + CD + P/Q.D 2QmQ C1 t2. n

Substituting the value of t1 and t2 from equation (1) and (2)

Yc = CD + p/Q.D+C.H 2

Qm Q

Qm t. n + 2QmQ C1 Q

QmQ )( t. n

Putting n. t = 1 year;

Yc = CD + P/Q.D + C.H QmQ

2

2

+ 1

2

2)( C

QQmQ =

CD + QP .D+C.H

QmQ

2

2

+ 1

2

2)( C

QQmQ

CASE I; TO GET OPTIMUM Qm; differentiating Yc with respect to Qm

and putting it equal to zero;

1

2

2(

2. C

QQmQ

QmQ

CHDQP

DCdQ

d

m

OR

012

22

200 1

C

QQmQ

QQmCH

CHQm – QC1 + Qm C1 = 0); Qm (CH + C1) = Q C1

Qm = 1

1

CCHQC

Since the factor 1

1

CCHC

is always less than 1, so

The optimum Qm will always be less than Q.

CASE II; TO GET OPTIMUM Q

Put dQdyc = O And Qm = Q

1

1

CCHC

in the result dQdyc =

dQd

QQQ

QCHQ

DQP

CD mm

2)(

2

22

= O

80

On simplification, we get Qopt = CHPD2

1

1

CCHC

Since factor 1

1

CCHC is greater than 1, so, Q >

CHPD2

Figure 2.12 Economic lot size when supply is continuous

Here, the supply rate (s) is greater than the rate of consumption (p). There is

a gradual build up of inventory at the rate or (S-P) The rate of inventory

build up = (S-P). Model for economic lot sizes with supply and consumption

rates varying, no shortages, no buffer stock, rate of supply = r, rate of

consumption = p.

Inventory after time t1 = (S-P) t1 = St1(1-p/s) = Q (1-p/s) since Q = St1

∴Average inventory = Q/2 (1-p/s)

Then, the annual cost (Yc) = material cost + set up cost + inventory holding

cost OR Yc = CD + P/Q. D + Q/2 (1-P/S) CH

(S -

P)

(S -

P)

Inve

ntor

y Q

uant

ity

MODEL IV; ECONOMIC LOT SIZE WHEN SUPPLY IS CONTINUOUS (NOT INSTANTANEOUS), CONSUMPTION IS CONTINUOUS, NO SHORTAGES AND NO BUFFER STOCK.

TIME t1 t2

81

Form minimum total annual cost, put dQdyc = O =

dQd

CHSPQ

QPD

CD

1(

2

OR O = SPCH

DQP

122

OR Q = )/1(

2SPCH

PD

82

CHAPTER THREE

PROBLEM FORMATION/RESEARCH METHODOLOGY

3.0 CHAPTER OVERVIEW

This chapter explains the model formulation of Re-order point of

variable lead times and demand of Just-IN-time in flow stations. The various

model assumptions were also explained, the condition in which the model is

applicable and the statistics of some flow stations based on their variability

of quantity demands and lead times are also discussed.

3.1 DATA COLLECTION METHOD

To accomplish the defined objectives of this study, a survey was

carried out in some randomly selected flow stations in Port-Harcourt which

offer similar services. The following methods were used to obtain the

relevant information from the flow station Viz;

(i) During visits to these flow stations, direct observations were made by

the researcher with respect to how their products are being demanded

corresponding to their production lead time. Also how the operational tasks

are organized and implemented in the flow stations are surveyed.

(ii) The system document of the firms (flow stations) were also sighted

and recorded by the researcher.

(iii) During visits to these companies (flow stations), interviews and

discussions were held with respondents in the course of administering and

retrieving the research questionnaires. Information obtained from this source

was recorded.

(iv) Data were also collected from the companies with the aid of a

research questionnaire. Questions structured using ISO 9000 principles were

used to explore the factors that collectively address the quality culture and

83

practices of the firms (flow stations). Data on variability of quantity

demanded corresponding to their Lead times were also obtained.

3.2 MODEL NOTATIONS

The following notations were used in the model formulation below;

d = Average demand (weeks)

L = Average Lead time (days)

= Number of standard deviations

= Level of significance 2d = Variance of the demand 2L = Variance of the Lead time

dLS = Standard errors of the mean of the led time and mean of the demand.

N (0,1) = Follows normal distribution with zero mean and variance 1

Z = test statistic

P = Probability

Ss = Safety stock

(1 – α) = Confidence region

(1 – α) 100% = Shows that we are (1-α)100% confidence that the safety

stock will lie in the interval.

L = Lower Limits

U = Upper Limits

ROP = Re-order point

84

3.3 MODEL FORMULATION

The Re-order point (ROP) based on a normal distribution of variable

lead time and variable demand may be represented in the diagram below;

To establish the safety stock region, we employ the following test statistic

(Z)

ie meantheoferrordardS

meanPopulationmeanSampleZtan

dLS

dELEdLZ )(.)(

)1,0(222

NdL

SsLxd

Ld

…………….. (1) Satorra and Bentiler(2001).

where 222LddL

dLS

The confidence interval for the safety stock (Ss) is given by

1ZZZP 100% …………….. (2)

substituting for Z in equation (2) above, we have;

Service level (probability of no stockout)

Risk of stockout

ROPQty

Ss

Zα - Zα

2

(1 - α)

0

2

85

1

222Z

dL

SsLxdZPLd

100% __________ (3)

Multiply each term in the bracket by

)4(%1001

%1001

222222

222

222

222222

222

LdLd

Ld

Ld

LdLd

Ld

dLZSsLddLZP

dLZdL

SsLdXdLdLZP

havewedL

Subtract Ld from each term in the bracket, we have that;

)6.........(....................%1001

)5(.........%.........1001

222222

22222

LdsLd

LdLd

dLZLdSdLZLdP

dLZLdLdSsLddLZLdP

Now multiply each term in the bracket by – 1 to make Ss positive.

)7(...............%.1001222222

LdsLd dLZLdSdLZLdPie

Using the fact that if a ≥ x ≥ b ≡ b ≤ x ≤ a, we can write that

)8(................%1001222222

LdsLd dLZLdSdLZLdP

Let L and U denote Lower and Upper Limits respectively.

)10(........................................

).9.(........................................

222

222

Ld

Ld

dLZLdU

ndAdLZLdL

86

Since stock cannot be negative, equation (10) becomes useful. So, we use

the upper limit to find our Re-order point (ROP) ie

ie ROP = 222Ld dLZLd

3.4 ASSUMPTIONS OF THE MODEL

(i) One of the assumptions is that the test statistic Z, is normally

distributed with 0 mean and variance 1

(ii) The Interval of the safety stock is taken to be non-negative

(iii) The model assumes variable demands and variable lead time

(iv) Sample values were used to estimate the population values. Eg sample

means Ld , were used to estimate the population means of d and L and

sample variances 2L and 2

d were used to estimate their population

variances.

(v) The model is valid if the service level of the flow station is known

3.5 RESULTS SPECIFICATION

The results of the research/model formulated will be applied to flow

stations wishing to adopt Just-in-time through Reorder point model of total

quality management.

The model will also be suitable in solving problems of variability in

both the quantity demanded and as well the production lead times which is

aimed at knowing the proper time a firm (flow station) should Re-order or

their quantities to be always available for Work. This is also geared towards

having a good inventory level of their firm. It ensures Just-in-time of their

products there by avoiding risk of stock out or excess stock, to avoid

doubling of projects execution time. This also minimizes the cost of

production of any flow station’s project.

87

CHAPTER FOUR

DATA PREENTATION AND ANALYSIS

4.1 CHAPTER OVERVIEW

The objective of this chapter is to present and discuss the data

obtained from the flow stations mentioned. These data will be used in testing

and in computation of the developed model. This is done to see the

relevance of the model in approaching Just – in – time when variable

demand and production lead time are experienced in flow stations.

4.2 GENERAL ANLYSIS OF SURVEY

To effectively study the subject, three flow stations including the one

in the case study, were surveyed using the methods already discussed in

chapter three.

Sixthly questionnaires were administered to twenty respondents in

each of the firms, out of which fifty-one were properly filled and returned

representing 51%. For the purpose of this study, these flow stations are

coded AI (case study firm), (AlCON NIG LTD), A2 (NOBLE ENGR. NIG

LTD), and A3 (EXPRO TECH OIL GAS NIG LTD)

These companies (flow stations) were selected at random to asses how

they apply JIT technique as a measure of quality performance of their

products.

88

Table 4.1 SURVEY RESPONSE

COMPANY /

FLOW

STATION

CODE

NO.OF

QUESTIONNAIRES

ADMINISTERED

RESPONSE REMARKS

A1 20 19 Expatriate

A2 20 17 Expatriate + +

Indigenous

A3 20 15 Wholly

indigenous

TOTAL 60 51

The distribution in table 4.1 shows that while response from A1 (case study

firm) was 99%, others (A2 to A 3) were 97% and 95% respectively.

This may be suggestive of how these flow stations appreciate issues

concerning quality.

Respondents were chosen among project managers, supervisors and

skilled work force as show in Table 4.2 below.

89

Table 4.2 Response by Category

Company

code

No. of questionnaires administered by

category

Response per category

Managers Supervisors Skilled workers Managers Supervisors Skilled

workers

A1 3 8 9 3 8 8

A2 3 8 9 2 7 8

A3 3 8 9 2 6 7

Total 9 24 27 7 21 23

4.3 THE QUESTIONNAIRE

To capture the key issues in this research, the questionnaire was

structured into two parts in line with the ISO 9000 series of standards. Part

A, comprising 9 questions, dealt on the respondent, the company and some

performance indicators. Part. B, comprised 32 questions, spanning corporate

specific statements, project, structure, documentations and process

management system audit, training, record. Sample of the questionnaire is

attached as addendum to this project.

Specifically, the composition of the questions and intent is as

Summarized in table

90

TABLE 4.3 SUMMARY OF QUESTIONNAIRE STRUCTURE

QUESTIONS RESEARCH INTENT

PART A GENERAL INFORMATION

Q1 to Q3

Q4 to Q6

Q7

Q8 to Q9

To obtain brief personal data of respondent.

To obtain information on company age and ownership.

To obtain information on type of service offered by company.

To appreciate the size of company in terms of company’s trading

results and employee’s awareness of results.

PART B ASSESSMENT OF QUALITY MANAGEMENT SYSTEMS

Q10 to Q17

Q18 to Q19

Q20

Q21

Q22

Q23

Q24 to Q27

Q28 to Q30

Q31

To assess the availability of company’s specific mission, policy and

objectives in respect of JIT of TQM and spam of coverage of these

documents.

To assess the availability of a document quality system and

awareness level of the employees.

To assess the availability of the minimum system elements.

To assess the availability of documented process specific practices.

To assess the firms awareness of statutory industry codes and

standards.

Assessment of available tools and techniques apart from JIT for

quality improvement.

Assessment of the QA (quality assurance) audit programmed

including effectiveness and team work.

To assess the span of Quality assurance and control.

Assessment of authority level of quality personnel.

91

Q32 to Q33

Q35 to Q36

Q37 to Q38

Q39 to Q41

To provide insight into employee association within firm.

To assess the level of education and experience of company

operatives.

To assess the approximate cost of quality.

To appraise the quality function, service level of the firms and it’s

acceptance by management and employees. Also to get the variable

demands quantities in (weeks) and variable led times (days) of each

of the flow stations surveyed

4.4 ANLYSIS OF QUESTIONNAIRES FIELD DATA.

The field responses as summarized in table 4.3 above are analyzed in

tables 4.4 to table 4.27 below. Some inferences are drawn, where necessary,

based on interviews, discussions, observations etc made by the researcher

during the survey. The testing of the model formulated using the data

obtained from the surveyed flow stations was also done.

4.5.0 EMPLOYEE’S AWARENESS LEVEL OF COMPANY

PERFORMANCE STATISTICS

Table 4.4 Employee’s awareness level of company’s Indicators

Compan

y code

No. of

respondent

Age Service Ownership Size turn

over

Employee

awareness

level

Average

awareness

A1

10

25

Engr. design,

drilling,

construction

Expatriate

>300m

16

84.2%

92

A2

A3

12

9

19

12

/maintenance

Design, drilling

and installation/

maintenance

Engr. design,

construction/dril

ling and

maintenance

Expatriate

+

indigenous

Indigenous

Within

200-250m

<2oom

12

6

75%

50%

As seen in table 4.4, a relationship exists between the type of ownership and

level of awareness of the work force. This is because the ownership structure

influences the level of centralization of power at top level. For instance in

company A3 only the managers knew the company’s approximate turn-over

because the span of delegation is low, thus affecting team efforts which is a

main requirement in JIT of total quality management.

4.5.1 AVAILABILITY OF SPECIFIC COMPANY GOALS,

POLICEES AND OBJECTIVES

Table 4.5 Availability and awareness of documented mission, policies

and objective statements.

Code No of

respondents

Respondent’s Answers to awareness on: Mean%

Mission

statement

% Quality

policy

% Objective

documents

%

93

statement

A 1 19 13 68.4 17 89.47 15 78.9 78.9

A 2 16 10 62.5 12 75.0 10 62.5 66.7

A 3 12 5 41.7 6 50.0 4 33.3 41.7

From Table 4.5, it can be seen that A1 to A2, have higher number of

employees who know the company’s mission and what route it intends to

take to meet required organizational goals with respect to quality. In all the

companies, the researcher sighted these documents but the availability was

not transformed into awareness for company A3. These documents as earlier

discussed, when well managed are supposed to provide the inertia for

organizational performance be it in production, quality, and good will.

94

4.5.2 ASSESSMENT OF DOCUMENTED QUALITY SYSTEM

Table 4.6 Assessment of availability and awareness of the documented

quality system

Code No of

respondents

Respondent’s Answers To: Mean%

Mission

statement

% Quality

policy

statement

% Objective

documents

%

A 1 19 19 100 14 33.9 16 84.2 86.03

A 2 16 16 100 15 93.8 13 81.3 91.7

A 3 9 5 55 3 3.3 2 22.2 37.03

Table 4.6 shows that employees A1 and A2 have higher awareness

level of availability and contents of their quality assurance system. In A3,

only the managers with a few senior personnel knew of the existence of a

QA system for their company. As discussed in section 2.4, a basic TQ

design requires that an appropriate quality model is chosen, documented

with provisions for under standing by all members of the organization.

95

4.5.3 ASSESSMENT OF SPECIFIC QUALITY PLANS AND

PRACTICES

Table 4.7. Assessment of availability and awareness of quality plans,

procedures, codes ,and standards.

Code No of

respondents

Respondent’s Answers To: Mean%

Availability

of specific

project plans

% Availability

of method

of

statement

and

procedures

% Familiarity

with

statutory

codes and

standards

%

A 1 19 19 100 17 89.5 15 78.9 89.5

A 2 12 12 100 10 83.3 8 66.7 83.3

A 3 9 6 66.7 5 55.6 2 22.2 48.2

As, seen in table 4.7, again the availability and awareness of documented

plans and practices for executing processes were higher in A1 and A2 which

tended to be company – wide, while awareness is restricted in company A3

to senior managers only. In fact, in A3 only two managers knew what

statutory codes and standards were being used in their company, which

hinders effective team work and communications of technical specifications

down the line.

96

4.5.4 ASSESSMENT OF AVAILABLE OTHER TQ TOOLS AND

TECHNIQUES

Table 4.8 Assessment of availability of other quality tools in use.

CODE No. of

respondents

RESPONDENTS ANSWER TO.

Awareness of

tools in use

% Average

No. of tools

/tech in use

Complexity of tools/

techniques in use

A1 19 10 52.6 10 Simple to complex

tools

A2 16 8 50 10 Simple to complex

tools

A3 12 5 41.7 6 Simple and medium

tools

Awareness level of other tools and techniques in use was restricted to

managers and supervisors in company A1 and A2, while only the managers

knew one or more tools used in A3. Also, while the tools and techniques

available in A1 and A2 were varied and ranged from simple to complex,

company A3 has simple and medium tools / techniques.

97

4.5.5 AVAILABILITY AND SCOPE OF QUALITY AUDIT SYSTEM

Table 4.9 Span of Quality Audit

RESPONDENTS ANSWER TO SCOPE OF ADUIT AVAILBLE

Cod

e

Ava

ilabi

lity

of p

lan

%

STR

AC

TUR

E %

PER

SIO

NN

E

L %

DO

CU

MEN

T

%

EQU

IPM

EN

T %

PRO

CESS

%

WO

RK

ARE

A

%

MEA

N %

A1 12 63.3 6 31.6 5 26.3 12 63.2 16 84.2 18 94.7 18 94.7 65.4

A2 10 62.5 8 40.2 8 50 13 81.3 15 93.8 15 93.8 15 93.8 75.0

A3 6 50.0 4 0 0 0 4 33.3 6 50 8 66.7 8 66.7 42.9

Table 4.9 shows respondents awareness of the availability and scope of

quality audit system being adopted by their companies. The companies were

evaluated on a seven – point scale. While A1and A2 gives a demonstration

of an awareness of the availability, as well as the scope of quality audit in

these firms, A3 obtained low points. Field observation showed that only the

managers and few senior personnel know the importance and relevance of

audit in the pursuance of quality objective. Further analysis shows that A3

lack audit schemes in structure, and personnel and even, does not audit its

documentation during the survey also confirm observation.

4.5.6 FREQUENCY OF AUDITING

Table 4.10 Frequency of project audit

CO

DE

No.

O

F R

ESPO

ND

EN

TS

RESPONDENTS ANSWER TO FREQUENCY OF AUDIT ON PROJECTS

Mon

thly

%

2-

3 m

onth

s %

Q

uarte

rly

%

Bi-

annu

ally

%

A

NN

UA

LLY

%

IN

FREQ

UEN

TLY

%

CENTRAL TENDENCY

A1 18 5 27.8 5 27.8 8 44.4 0 0 0 0 0 0 QUARTERLY A2 15 0 0 12 80 3 20 0 0 0 0 0 0 2-3 months A3 10 0 0 1 10 4 40 5 5

0 0 0 0 0 Bi-

ANNUALLY

98

TABLE 4.11 FREQUENCY OF IMPLEMENTATION OF AUDIT

FINDINGS

FREQUENCY OF IMPLEMENTATION OF AUDIT FINDINGS

No

of

resp

onde

nts

BEL

OW

20%

%

BET

WEE

N

30%

& 5

0%

%

BET

WEE

N

60%

& 8

0%

%

UP

TO

100%

%

CENTRAL TENDENCY

A1 18 - - 3 16.7 8 44.4 7 38.9 B/W 6O% & 80%

A2 15 - - - - 10 66.7 5 33.3 B/W 60% & 80%

A3 14 - - 12 85.7 2 14.3 - - B/W 30% & 50%

Table 4.10 and 4.11 reveals that ,A1 and A2 audit their projects and

implement their audit findings more frequently. Company A3, audit their

projects bi-annually and has a lower percentage range on the frequency of

implementation of their audit findings.

4.5.7 ASSESSMENT OF SCOPE OF QUALITY ASSURANCE

Table 4.12. Scope of Quality Assurance

CO

DE

NO

OF

RESP

ON

DEN

TS

RESPONDENTS ANSWER TO SCOPE OF ASSURANCE

MA

NA

GEM

ENT

QC

AN

D

POST

INST

ALL

AT

ION

%

CO

NTR

OL

OF

PRO

CESS

%

INSP

ECTI

O

N

%

ZER

O

ASS

UR

AN

C

E %

QC

BY

CLI

ENT

INSP

ECTI

O

N

%

CEN

TRA

L

TEN

DEN

CY

A1 15 8 53.3 7 46.7 - - - - - - Through mgt, QC &

post installation

A2 14 9 64.3 5 35.7 - - - - - - Through mgt QC &

post installation

A3 7 - - - - - - 2 28.5 5 71.4 By client inspectors

TABLE 4.13 SPAN OF QUALITY CONTROL

99

COD

E

NO

OF

RES

PON

DEN

TS

RESPONDENS ANSWER TO WHAT IS CONTROLLED

CEN

TRA

L TE

ND

ENC

Y

SYST

EMS

RESS

OU

RCES

PR

OC

ESS

&

PRO

DU

CT

%

%

INSP

ECTI

ON

%

ZERO

A

SSU

RA

NC

E

A1 15 9 60 6 40 - - SYSTEMS, RESSOURCES PROCESS AND PRODUCT

A2 14 8 57.1 6 42.9 - - SYSTEMS, RESSOURCES, PROCESS AND PRODUCT

A3 7 2 - 2 28.6 5 71.4 PROCESS AND PRODUCT ONLY

Tables 4.12 and 4.13 show the scope of quality assurance and control. While

A1 and A2 adopt management system approaches, with a focus on systems,

resources, process and product. A3 relies on process approach where in only

the process and the product are controlled. A3 scope of quality assurance

efforts are not internalized, as only the client dictates the level of quality to

be built into its product.

4.5.8 ASSESSMENT OF ASSURANCE RECORDS

Table 4.14 Availability and retrieval of quality records.

COD

E

RESP

ON

DEN

TS

RESPONDENTS ANSWERS TO AVAILABILITY & EASE OF TRACE AND RETRIEVAL

LESS

TH

AN

10

%

%

B/W

20 &

50

%

%

B/W

50

&

80%

%

ALW

AY

S

%

CEN

TRA

L TE

ND

ENCY

A1 16 - - - - 7 43.8 9 56.2 RECORDS RETRIEVAL IS 100%

A2 13 - - 2 15.4 3 23.1 8 61.5 RECORDS RETRIEVAL IS 100%

A3 10 2 20 5 50 3 30 - - RECORDS ARE AVAILABILITY 20-50% OF THE TIME

100

Table 4.14 shows that A3 has low level ability to trace and retrieve quality

records, while A1 and A2 have 100% ability. It is worthy to note that this

culture is a function of the scope and span of quality assurance as already

discussed in section 4.3.8

4.5.9 QUALITY PERSONNEL AUTHORITY

Table 4.15 Availability of authority to quality personnel

CODE No. OF RESPONDENTS

Responses to availability of stop and resume authority

CENTRAL TENDENCY

YES % NO % A1 19 15 78.9 4 21.1 STOPAND RESUME

AUTHORITY IS HIGH A2 15 11 73.3 4 26.7 STOP AND RESUME

AUTHORITY IS HIGH A3 12 7 58.3 5 41.7 STOP S RESUME

AUTHORITY IS FAIR From the table 4.15, we see that the authority to stop and resume work, when

required, is available in A1 and A2 while in A3 it is fair. Infarct, in A3, only

the managers said the authority existed.

4.6.0 ASSESSMENT OF AVAILABILITY AND TYPE OF FORMAL

AND INFORMAL ASSOCIATION AMONGST WORKERS

Table 4.16 management Tolerance of workers association CODE No. OF

RESPONDENTS

Respondents Answer to management Tolerance of workers association

CENTRAL TENDENCY

YES % NO % A1 19 14 73.7 5 26.3 ASSOCIATION

WELL TOLERATED

A2 18 10 55.6 8 44.4 ASSOCIATION FAIRLY TOLERATED

A3 9 3 33.3 6 66.7 NOT TOLERATED

101

Table 4.17 TYPE OF ASSOCIATION ENCOURAGED BY MGT

CO

DE

No.

OF

RES

PON

DEN

TS

RESPONDENTS ANSWER TO TYPE OF ASSOCIATION ENCOURAGED CENTRAL TENDENCY U

NIO

N

%

QU

ALI

TY

CIR

CLE

%

WEL

FAR

E

ASS

OC

IATI

ON

%

CO

MM

ITT

EE

%

A1 19 4 21.1 - - 2 10.5 13 68.4 USE OF COMMITTEE TO

ACHIEVE TASKS IS MORE

ENCOURAGED

A2 18 3 16.7 - - 5 27.8 10 55.5 ,,

A3 9 - - - - 3 33.3 6 66.7 ,,

Management tolerance of workers association in the companies surveyed

seem to be encouraged in A1 and A2 as shown in table 4.16. However, the

type of association encouraged tended towards the use of committees in all

the companies (Table 4.17) with only A1 and A3 barely tolerating unionism.

None of the companies, even the case study flow station, uses the concept of

quality circles. The usual suspicion between management and workers may

be responsible for the Tendency towards the use of committees in handling

special tasks for specific problem solving. However, it is note worthy to

state that companies / flow stations have more to gain by allowing free and

responsible association amongst and between their workers.

4.6.1 AVAILABILITY OF REWARD FOR QUALITY

Table 4.18 availability of reward for quality

CO

DE

No

OF

RES

PON

DEN

TS Respondent to availability of Quality reward

Yes % No % CENTRAL TENDENCY

A1 19 17 89.5 2 10.5 There is some reward for quality A2 17 16 94.1 1 5.9 ” A3 9 1 11.1 8 88.9 There is no reward for quality

102

As seen in table 4.18, A1 and A2 have an incentive scheme which is under

stood by not only the managers but the work force as well. While A3 may

not necessarily be as a result of non – availability of reward schemes, but

the fact that the work forces are not aware and is not being practiced.

Observations during the survey shows that in this firm/flow station, only the

managers had full understanding of documented practices which is not good

enough for effective JIT of TOTAL QUALITY implementation.

4.6.2 Assessment of length of education and experience of workers.

Table 4.19. Average length of formal education of workforce. CODE No OF

RESPONDENTS

RESPONDENTS ANSWER TO AVAILABILITY OF QALITY

REWARD;

TOP

MGT

MIDDLE

MGT

SUPERVISORS SKILLED

WORKERS

MEAN

(YRS)

A1 19 12 16 12 8 12

A2 17 16 16 12 5 12.25

A3 9 12 12 8 5 9.25

TABLE 4.20 AVERAGE EXPERIENCES OF WORKERS

CODE No OF

RESPONDENTS

RESPONDENTS ANSWER TO AVAILABILITY OF QALITY

REWARD

TOP

MGT

MIDDLE

LEVEL

MGT

SUPERVISORS SKILLED

WORKERS

MEAN

(YRS)

A1 19 28 18 20 20 21.5

A2 17 30 20 25 22 24.25

A3 9 30 12 25 20 21.75

103

Table 4.19 and 4.20 respectively show the average length of formal

education and experience of all categories of members of each flow station.

While A1 and A2 have longer period formal education, A3 has lower

education at the top, but with much experience. The lower formal education

explains its inability to cope with the challenges of JIT of total quality

management. Education and experience when properly blended is a

stimulant for total quality, as already discussed in chapter 2.

4.6.3 AVAILABILITY OF PROCEDURES FOR EVALUATING

QUALITY COST.

Table 4.21 availability for procedures for evaluating cost of quality CODE No OF

RESPONDENTS

AVAILABILITY OF PROCEDURES FOR COST

EVALUATION

YES % NO % CENTRAL

TENDENCY

A1 8 8 100 - - Procedures for cost

evaluation strongly

exists

A2 10 10 100 - - Strongly exists

A3 7 4 57.1 3 42.9 Fairly exists

104

TABLE 4.22 APPROXIMATE COST OF QUALITY PER

PROJECT CODE No OF

RESPONDENTS

AVERAGE COST OF QUALITY PER

PROJECT

TOTAL

COST

% Preventive cost

(%)

Failure cost (%)

A1 8 10 1.75 11.75

A2 10 12 O.5 12.5

A3 7 3 10 13

Availability of means of evaluating the cost of quality is a necessary

incentive for companies / flow stations to appreciate how well their

programmes are doing. As seen in tables 4.21, A1 and A2 have procedures

for evaluating cost while such procedures exist fairly in A3. As shown in

table 4.22, (approximate cost), it is worthy to note that A1 and A2 have

massive expense on preventive costs and keeps its failure cost low, while the

failure cost in A3 is high due to low investment in preventive efforts.

105

4.6.4 RESPONSIBILITY FOR QUALITY MGT

Table 4.23 Responsible focal point for quality

As seen in Table 4.23, while A1 and A2 have senior managers in charge of

their quality Departments, A3 rely on QA/QC engineers, who are at

supervising level, hence the differential effect it has on their individual

programmes in their firms.

CO

DE

No

OF

RES

PON

DEN

TS RESPONSBLE FOCAL POINT FOR QUALITY

SEN

IOR

MA

NA

GER

%

Com

mitt

ee

Cha

riman

%

Con

sulta

nts

%

QA

/QC

ENG

ING

EER

S %

NO

NE

%

CENTRAL

TENDENCY

A1 15 13 86.7 - - - - 2 13.3 SNR. MGR.

HEADES

THE QA

FUNCTION

A2 12 8 66.7 6 33.3 - - - - SNR. MGR.

HEADS

THE QA

DEPT.

A3 10 - - 4 40 - - 6 60 QA/QC

ENGINEER

S

106

4.6.5 ACCEPTABILITY OF QUALITY FUNCTION

TABLE 4.24 ACCEPTANCE OF QUALITY DEPARTMENT’S

WORK BY TOP MANAGEMENT

CO

DE

No

OF

RES

PON

DEN

ACCEPTANCE OF QUALITY DEPT’S WORK BY WORKERS

BEL

OW

30%

%

B/W

30&

50%

%

B/W

50^

80%

%

100%

AC

CEP

T

AN

CE

%

CENTRAL

TENDENCY

A1 19 - - - - 7 36.8 12 63.2 WORK OF

QUALITY

FUNCTION IS

STRONGLY

ACCEPTED

A2 16 - - - - 6 37.5 10 62.5 STRONGLY

ACCEPTED

A3 15 - - 7 41.7 8 53.3 - - WELL ACCEPTED

107

Table 4.25 Acceptance of quality Departments work amongst workers.

CO

DE

No

OF

RES

PON

DEN

T

BEL

OW

30%

%

B/W

30&

50%

%

B/W

50&

80%

%

100%

AC

CEP

T

AN

CE

%

CENTRAL

TENDENCY

A1 19 - - - - 10 52.6 9 47.4 WORK OF

QUALITY

FUNCTION IS

STRONGLY

ACCEPTED

A2 16 - - - - 12 75 4 25 WELL ACCEPTED

A3 15 - - 6 40 9 60 - - FAIRLY

ACCEPTED

Table 4.24 and 4.25 shows that the work of the Quality Assurance and

control function is strongly accepted by top management of A1 and A2. It is

fairly accepted in A3.

However, amongst the work force; the quality function is well

accepted in A1 and A2, while it is fairly accepted in A3 Several reasons

account for this, amongst which is the level of leadership in quality

Assurance Department, as well as the level of commitment by top

management, as workers cannot be accepted to be more committed to a

philosophy than its leadership.

108

4.6.6 TESTING OF MODEL FORMULATION

This model as formulated to know the reorder point when there are variable

demand and lead time of flow stations activities to ensure Just – in – time of

their products which prevents stock out or excess stock of their inventory

level.

Three flow stations data of variable demands and lead times were

obtained. The flow stations were coded A1, A2 and A3. The service level of

each of them was also recorded as shown below;

FLOW STATION A1 WITH SERVICE LEVEL OF 96%

Table 4.26 flow station A1 (ALCON Nig Ltd) with variable demands

lead times.

WEEKS 1 2 3 4 5 6 7 Mean( x ) Variance(σ2) Standard deviation

DEMANDS (WKS)

50 60 45 80 75 65 55 d = 61 2d = 141

87.112 d

LEAD TIMES (DAYS)

5 6 4 7 6 5 4 5L 2L = 1.14 07.12 l

DETAILS OF THE CALCULATION:

Mean of demand 7

55657580456050

nd

d

61)( d

Mean of lead time 57

4567465

nL

L

Variance of Demand 2d =

ndddddddd n

223

22

21 )(...)()()(

109

7)6155()6165()6175()6180()6145()6160()6150( 2222222

2 d

14179872 d

Variance of lead time 2L =

nLLLLLLLL n

223

22

21 )(....)()()(

7

)54()55()56()57()54()56()55( 22222222 L

14.1782 L

Standard Deviation of demand 87.111412 d

Standard Deviation of lead time 07.141.12 L

At service level of 96%=0.96, Zα=1.75 (from the table of normal distribution

Service level).

Applying the R O P Model, we have;

R O P = 222Ld dLZLd

R O P = 61 x 5 + 1.75 14.1611415 2 xx

R O P = 305 + 1.75 94.4241705

R O P = 305 + 1.75 94.4946

R O P = 305 +1.75 x 70.33 = 305 +123

R O P = 428 quantities

Hence, flow station A1 places an order at an inventory of 428 quantities of

pipes and other structural steel equipment to allow Just-In-time of their

products before a stock out is noticed.

FLOW STATION, A2 WITH SERVICE LEVEL OF 93%

Table 4.27; flow station A2 (Noble Engineering Nig. Ltd) with variable

quantities of demands and production lead times of their products

110

WEEKS 1 2 3 4 5 6 7 Mean

( X )

Variance

(σ2)

Standard

Deviation

DEMANDS

(Weeks)

30 20 50 45 60 70 65 ( d )

=4 9

( 2d ) =

291

172 d

LEAD

TIMES

(Days)

4 3 4 5 6 7 5 ( L )

= 4.9

( 2L ) =

1.6 3.12 L

Mean of demand ( d ) = 497

65706045502030

nd

Mean of lead-time ( L ) = 9.47

5765434

nL

Variance of demand ( 2d ) =

nddddxddd n

223

22

21 )(.....)()()(

2d =

7)4965()4970()4960()4945()4950()4950()4920()4930( 22222222

2d = 291

72037

Variance of lead time ( 2L ) =

nLLLLLL n

222

21 )(....)()(

2L =

7)9.45()9.47()9.46()9.45()9.44()9.43()9.44( 2222222

2L = 6.1

787.10

Standard Deviation of demand 172912 d

Standard Deviation of lead time 3.16.12 L

111

At service level of 93% = 0.93, Zα = 1.48 (from the table of normal

distribution service level).

Applying the Developed R O P model, we have that;

R O P = LdLZLd d222

R O P = 49 x 4.9 + 1. 48 6.1492919.4 2 xx

R O P = 240.1+1.48 6.38419.1425

R O P = 240.1+1.48 6.7248.11.2405.5267 x

R O P = 240.1+107.45 = 347.55

R O P 348 quantities

Thus, flow station, A2 reorders at an inventory of 348 quantities of pipes and

other flow stations equipment to ensure J I T of their products before a zero

stock is experienced.

FLOW STATION, A3 (EXPRO TECH OIL AND GAS NIG. LTD) with

SERVICE LEVEL OF 82%

Table 4.28; flow station, A3 with variable demands and lead times of

their products.

WEEKS 1 2 3 4 5 6 7 Mean

( X )

Variance

(σ2)

Standard

Deviation

DEMANDS

(WEEKS)

72 64 80 91 63 94 83 ( d )

= 78

( 2d ) =

130

4.112 d

LEAD

TIMES

(DAYS)

4 5 6 5 6 5 6 ( L ) =

5.3

( 2L ) =

0.49 7.02 L

112

DETAILS OF THE CALCULATION

Mean of demand ( d ) = 7

83946391806472

nd

d = 78

Mean of Lead time ( L ) = 7

6565654

nL

L = 5.3

Variance of demand ( 2d ) =

ndddddddd n

223

22

21 )(...)()()(

2d =

7)7883()7894()7863()7891()7880()7864()7872( 2222222

2d = 130

7911

Variance of lead time ( 2L ) =

nLLLLLL n

222

21 )(...)()(

2L =

7)3.56()3.55()3.56()3.55()3.56()3.55()3.54( 2222222

2L = 49.0

743.3

Standard Deviation of demand 2d = 130 = 11.4

Standard Deviation of lead time 49.02 L = 0.7

At service level of 82% = 0.82, Zα = 0.92

(From the table of normal distribution service level)

Applying the R O P Model, we have that;

R O P = LdLZLd d222

R O P = 78 x 5.3 + 0.92 49.0781303.5 2 xx

R O P = 413.4 + 0.92 16.2981689

113

R O P = 413.4 + 0.92 16.3670

R O P = 413.4 + 0.92 x 60.58 = 413.4+55.74

R O P = 469.14 ~ 469 quantities

Thus, flow station, A3 reorders at an inventory level of 469 quantities of

pipes and other structural steel equipment to allow J I T of their products

before zero stock is observed.

From the detailed calculations of all the three flows stations data

surveyed, it shows that the model formulated is relevant in determining the

point reorder of variable cases of demand and lead time of which this

project is designed to look into.

114

CHAPTER FIVE

DISCUSSION, CONCLUSION AND RECOMMENDATIONS

5.1 DISCUSSION

Having gone through the reviewed empirical literature on reorder

point model, it was discovered that ROP model of variable cases of demand

and lead time have not been adopted in some of our flow stations. This made

the researcher to analyze the formulated model using the data obtained from

the randomly selected flow stations operating in Port Harcourt, Rivers state.

The results obtained from these analyses and findings are presented and

necessary recommendations made.

5.2 SUMMARY OF FINDINGS

From table 4.26 to 4.28 for the testing of he formulated model, it was

found that;

(i) The model can be used to determine point of reorder irrespective

of the variability in the quantity demanded and the corresponding

Lead times of any flow station.

(ii) The service level of any flow station is one of the factors that help

in determining the quantity to be reordered so as not to have a zero

or excess stock at any inventory level.

(iii) Commitment of top management to the principles of JIT quality if

lacking, will in turn reduce the continuous production leading to

zero stock.

(iv) In other aspect of total quality, over centralization of responsibility

and authority at the top management level was also observed to be

one of the major impediments to the firm’s growth.

115

(v) Documentation, awareness, evaluating the cost of quality, the

scope and frequency of quality audits, the acceptance of the work

of quality personnel in the firms are factors that must be looked

into by any firm (flow station) wishing to adopt total quality.

(vi) It was also established that the success of the quality programme of

a firm is significantly determined by the type of model the firm

uses, availability and type of codes, standards, techniques and the

awareness level of employees in their use.

5.3 RECOMMENDATIONS

Based on the Discussion above, the followings are recommended;

(i) That project managers of any flow station should strongly consider

the option of adopting JIT of total quality at project planning

phases and as well as execution phases, as the shortest, economical

etc route to acceptability by client and third party that may be

impacted by their activities.

(ii) That project managers of any flow station should adopt the

Reorder point model of actualizing JIT in handling any cases of

variability in both the quantity demanded and their corresponding

lead times.

(iii) The management of project engineering companies (flow stations)

should re-orientate the thinking that investment in quality is a

waste and that only the minimum requirements should be done.

This is not true. JIT of total quality also implies that every process

in projects planning, designing, execution and implementation can

be done better leading to cost reduction, loss prevention and repeat

buying on the long run.

116

(iv) Clients (Investors) of engineering projects/flow stations project

should begin to specify that JIT of TQ principle, among other

tools, should be used in executing their projects as part of their

purchase/procurement system. Only in this way, that contracting

firms will begin to imbibe the culture of doing things in the right

way at first attempt.

(v) Managers and investors of different companies should embrace

Just-In-Time technique of Total Quality Management in achieving

their goals.

(vi) Just-In-time of total quality is good for the wider society and it is

in the interest of all, irrespective of occupation, to begin to imbibe

its principles which will help to reduce dependence on foreign

goods and services, and lead to eventual prosperity for all, if

carefully integrated into our national culture, especially by the

small scale enterprises. Our ability to compete in the face of rapid

globalization of our economy may well depend on JIT of Total

Quality management.

6.0 CONCLUSION

Just-in-time of Total quality is attitudinal and part of a firm’s over all

culture. Doing things the quality way does not negatively affect production,

in fact, it helps to prevent doing things a second time over with its associated

cost impact. This study revealed a positive, useful model of Just-in-time

through Reorder point of variable demands and variable lead time. In the

formulation of these models, the following assumptions were made: (i) The

test statistic, Z is normally distributed with 0 mean and variance 1

(ii) The interval of the safety stock is taken to be non-negative.

117

(iii) There is variability of the quantity of the firm and as well their

production lead times.

(iv) Sample values were used to estimate the population values.

(v) The model is valid if and only if the service level of the flow

station is known.

The study also revealed that documentation, awareness level, evaluating

the cost of quality, the scope and frequency of quality audits, the

availability and types of codes used, standards and techniques all

amounts to the overall “SUCCESS OF THE QUALITY PROGRAMME

OF A FIRM”. All these are important in the full attainment of any

meaningful effort geared at improving quality, be it in the private or

public sector.

118

REFERENCES

Akanya, J.N., (SON) (1999): “ISO 9000 Series Quality Management

standards – implementation and Route to Quality system

Certification”, A paper delivered at NSE Technical workshop on

Quality, Port Harcourt.

Bowersox ,C. and Cooper (2002): “ Supply Chain Logistics Management”,

1st edition, McGraw-Hill Inc. New York.

Cetinkanya, S, Mutlu, F, and Lee C.Y (2006): “A comparison of out bound

dispatch policies for integrated inventory and transportation decisions.

European journal of operational research 2006; 171(3): 1094-112.

Davis, Aquilano and Chase (2000): “Operations management for

competitive Advantage”, 4th edition, McGraw-Hill Inc New York

Feigenbaum and Armand V. (1991): “Total Quality control”, 3rd edition,

McGraw-Hill Inc. New York.

Hajek and Victor, G. (1984): “Management of Engineering projects”, 3rd

edition, McGraw-Hill Inc. New York.

ISO 8402 and 9000 series (1994): “International standards for Quality

Management”, 4th edition, international organization for

standardization, Switzerland.

Juran, J.M. , Gryna and Frank M. (1993): “Quality planning and Analysis”,

3rd edition, McGraw-Hill Inc. New York.

Lockyer and Keith (1983): “Production Management”, 4th edition, pitman

publishing Ltd., London.

Melnyk and Swink (1997): “Value-Driven Operations management””, 1st

edition, McGraw-Hill Inc. New York.

Nahmias (2005): Production and operations Analysis”, 4th edition, McGraw-

Hill Inc. Irwin.

119

Satorra, A and Bentiler, P(2001): “ A scaled difference chi-square test

statistic for moment structure analysis.

Silver E, Pyke D, and Speterson R. (1998): Inventory Management and

production planning and scheduling”, 3rd edition, McGraw-Hill Inc.

New York.

Shigley, J.E and Mischke, C.R. (1989): Mechanical Engineering Design”,

56th edition, McGraw-Hill Inc. New York.

Spiegel and Murray R. (1972): “Schaum’s outline of “Theory and problems

of statistics” in SI units, 2nd edition, McGraw-Hill Inc. New York.

Stevenson (2006): “Operations Management”, 8th edition, McGraw-Hill Inc

Irwin.

The Law Revision Committee (1990): “The Laws of the Federal Republic of

Nigeria”, (The SON Decree) Federal Government press, Lagos

Nigeria.

Weihrich, Henz, and Koontz; H. (1993): “Management-A Global

perspective”, 10th edition, McGraw-Hill Inc. New York.

120

BIBLIOGRAPHY

Abalaka, J.A., [SON] (1999): “Quality Assurance in Engineering Process: A

key note address delivered at NSE technical work shop on Quality”

Port Harcourt.

Axsater S.A. (2007): “A Heuristic for Triggering Emergency orders in an

Inventory System” A European journal of operational Research 2007;

176:880-91.

Awujo, A.C. (1994): “Elements of Management”, 1st edition, CAPIIC

publishers, Owerri, Nigeria.

Browne S and Zipkin P. (1990): “Inventory Models with continuous,

stochastic demands-Annals of applied probability”. 3rd edition,

prentice ~ Hall Ltd., New Delhi

Cakanyildirim M, Book binder J., and Gerchak Y. (2000): “Continuous

review inventory models where random lead time depends on lot size

and reserved capacity. International Journal of production economics

2000; 68(3): 217-28.

Ezema, I.C. (2007/08): Lecture Notes on “ quality control and reliability”

(ME 683), unpublished, University of Nigeria, Nsukka.

Fickelson, M. [Editor] (1990): “TEST QUALITY for construction, materials

and structure”, proceedings of the international Union of Testing and

Research Laboratories for materials and structures, and the

international laboratory Accreditation congress symposium, chapman

and Hall, London.

Luck, David J. and Rubin, R. (1987): “Marketing Research”, 7th edition,

prentice-Hall int. Inc., Englewood cliffs, New Jersey.

121

Marvin, C. J. and Golderhar, J. D., [editors] (1970): “The science of

managing Organise Technology”, volume 1 and 2, 1st edition Garden

and Breach Science publishers, New York.

Mcclain, J. O and Thomas, J. L. (1987): “Operations Management-

production of Goods and Services”, 2nd edition, prentice ~ Hall Ltd.,

New Delhi.

Parsons, C.J. (1976): “Theses and project Work-A Guide to Research and

writing”, 1st edition, George Allen and Unwin Ltd., London.

APPENDIX

Sample of table for normal distribution service level and unit loss

function.

Sample of the research questionnaire.