35
APPLICATION FOR THE RENEWAL OF ENVIRONMENTAL CLEARANCE CERTIFICATE FOR EPL 3540 LOCATED IN THE AREA BETWEEN OTAVI, and GROOTFONTEIN OTJOZONDJUPA REGION CONSULTANT: PROPONENT Mr. Ipeinge Mundjulu (BSC, MSc) Gazania Investments 9 (Pty) Red-Dune Consulting CC P O Box 87100 P O Box 27623 Windhoek Eros Cell: +264 81 147 7889 Windhoek

APPLICATION FOR THE RENEWAL OF ENVIRONMENTAL …eia.met.gov.na/screening/899_renewal_application...2 Executive Summary Gazania Investments 9 (Pty) Ltd is a holder of the Exclusive

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • APPLICATION FOR THE RENEWAL OF ENVIRONMENTAL

    CLEARANCE CERTIFICATE FOR EPL 3540 LOCATED IN THE AREA

    BETWEEN OTAVI, and GROOTFONTEIN OTJOZONDJUPA REGION

    CONSULTANT: PROPONENT

    Mr. Ipeinge Mundjulu (BSC, MSc) Gazania Investments 9 (Pty)

    Red-Dune Consulting CC P O Box 87100

    P O Box 27623 Windhoek Eros

    Cell: +264 81 147 7889 Windhoek

  • Proponent Gazania Investments 9 (Pty)

    License Number EPL 3540

    Location Between Otavi and Grootfontein ,15 Km North east of Grootfontein

    Stage Final

    Author Ipeinge E. Mundjulu

    Aim RENEWAL of Environmental

    Clearance Certificate

    DOCUMENT INFORMATION

  • Table of Contents Acknowledgements ......................................................................................................................... 1

    Executive Summary ........................................................................................................................ 2

    1. Introduction ............................................................................................................................. 3

    2. Overview of the project .......................................................................................................... 3

    2.1.1. Location .................................................................................................................... 3

    2.1.2. Exploration activities ................................................................................................ 5

    2.1.3. Period 2011-2017 ...................................................................................................... 5

    2.1.4. Period 2017-2019 ...................................................................................................... 6

    3. The Environmental Management Plan.................................................................................... 7

    3.1. Purpose of the EMP.......................................................................................................... 7

    3.2. Compliance to the EMP ................................................................................................... 7

    3.3. Roles and Responsibilities ............................................................................................... 7

    3.3.1. Proponent .................................................................................................................. 7

    3.3.2. Environmental Compliance Officer (ECO) .............................................................. 8

    3.3.3. Site Manager ............................................................................................................. 8

    3.3.4. Employees ................................................................................................................. 8

    3.4. Disciplinary Action .......................................................................................................... 8

    3.4.1. Proponent .................................................................................................................. 8

    3.4.2. Workers ..................................................................................................................... 8

    4. The EMP Tables Mitigation Measure and Commitments ...................................................... 9

    5. Conclusion and Recommendations ....................................................................................... 23

    5.1. Conclusion ...................................................................................................................... 23

    5.2. Recommendations .......................................................................................................... 23

    6. Reference .............................................................................................................................. 24

    7. Appendixes ........................................................................................................................... 25

    7.1. Previous and Current Environmental Clearance Certificate .......................................... 25

    7.2. Curriculum of the Environmental Assessment Practitioner ........................................... 26

  • List of Figures

    Figure 2-1. Location of EPL 3540 ................................................................................................. 4

    List of Tables

    Table 4-1 Field Mapping, Geophysical Surveys And Soil Sampling ............................................ 9

    Table 4-2 Drill Site Establishment ............................................................................................... 12

    Table 4-3. Drilling ........................................................................................................................ 14

    Table 4-4. Relevant to All Exploration Activities........................................................................ 17

    Table 4-5. Closure and Rehabilitation.......................................................................................... 20

  • ACRONYMS

    AIDS Acquired Immune Deficiency Syndrome

    DEA Department of Environmental Affairs

    ECC Environmental Clearance Certificate

    EIA Environmental Impact Assessment

    EMA Environmental Management Act (No. 7 of 2007)

    EMP Environmental Management Plan

    HIV Human Immune Virus

    MET Ministry of Environment and Tourism

    MME Ministry of Mines and Energy

    RC Reverse Circulation

    RDC Red-Dune Consulting CC

  • 1

    Acknowledgements

    The renewal of an Environmental Clearance Certificate follows an existing Environmental

    Management Plan (EMP) that was approved by the approving authority. The EMP for the

    Exclusive Prospecting License 3540 was developed by SLR Consulting Namibia. Red-Dune

    consulting has reviewed the EMP for purposes of renewing the Environmental Clearance

    Certificate as requested by Gazania Investment 9 Ltd. Red-Dune Consulting hereby acknowledge

    the great work done by SLR Consulting. This document remains the property of Gazania

    Investment 9 Pty Ltd and the Copyright, especially the EMP remains for SLR Consulting Company

  • 2

    Executive Summary

    Gazania Investments 9 (Pty) Ltd is a holder of the Exclusive Prospecting: License (EPL) 3540.

    The EPL was granted in 2011, exploration is a listed activity under the Environmental

    Management Act (Act No. 7 of 2007) that may not be undertake without an Environmental

    Clearance Certificate (ECC). The company was issued with an ECC in 2014. The following

    exploration activities took place; Geological studies and field mapping, Soil surveys, Geophysical

    surveys and Drilling (Reverse Circulation) between 2014 and 2017. The ECC was renewed in

    January 2017 where bi-annual and rehabilitation reports report detailing undertaken activities were

    submitted, which formed the basis of the ECC renewal.

    For the period between 2017 to 2019 no exploration activities took place, hence the state of the

    environments remained the same since the renewal of the ECC in 2017. Because of this, there were

    no bi-annual reports produced. The renewed ECC is now due to expire in January 2020, hence the

    company is hereby applying for the renewal of the ECC.

    Exploration activities are not necessarily detrimental to the bio-physical environment because of

    less evasive activities. The drilling holes shall be covered up, access road shall be restricted to the

    existing roads if new roads are established to the target site, they shall be rehabilitated after use.

    With adequate implementation of the EMP, the project operation would not have adverse impacts.

    Water is a scarce resource in Namibia, the project is not expected to use significant amount of

    water in a sense that, there would be no water abstraction. The area between Otavi and

    Grootfontein area is rich in water resource, ground water in the area is found at 60m and drilling

    is expected to intersect groundwater. Drilling of boreholes for water abstraction requires a permit

    from Ministry of Agriculture, Water and Forestry (MAWF). In an event where the farm owner

    would want a drill site to become a water borehole, all necessary permits should be obtained. At

    this moment, all holes shall be filled up completely.

  • 3

    1. Introduction

    Gazania Investments 9 (Pty) Ltd was granted the Exclusive Prospecting License EPL 3540 as per

    the Mineral Resource Act 1992 in September 2011 which valid until August 2021 (Appendix 7.1).

    Exploration activity is a listed under Environmental Management Act (Act No. 7 of 2007) (EMA),

    that may not be undertaken without an Environmental Clearance Certificate (ECC). The company

    was initially issued with an ECC in 2014 (Appendix 7.2). In accordance with EMA, the ECC is

    valid for a period of three years and Section 56 of EMA provides for the renewal of the ECC. In

    accordance with this provision, the ECC was renewed in 2017 and due to expire in January 2020

    (Appendix 7.2). Accordingly, the company is hereby applying for the second renewal of the

    Environmental Clearance for EPL 3540.

    2. Overview of the project

    2.1.1. Location

    The EPL 3540 is located in the area between Otavi, Grootfontein and Tsumeb (Figure 1). The

    western boundary is located at 19.63166667 S, 17.53694444 E and the eastern boundary at

    19.70305556 S, 17.85000000 E. It covers several commercial farms, whose main land use is

    agriculture, predominantly cattle farming.

  • 4

    Figure 2-1. Location of EPL 3540

  • 5

    2.1.2. Exploration activities

    2.1.3. Period 2011-2017

    Since the granting of the EPL in 2011, the following exploration activities took place between

    2014 and 2016.

    Geological studies and field mapping

    o During this stage, various geological data for the area were collected from

    different sources to analyses and study available information of the area.

    Information are derived from aerial photo. These geological photos were studied

    to generate target point where geochemical soil sampling were taken.

    Soil surveys

    o Soil survey was the process used to classify soil types and other soil properties in

    target area which is used for geo-encoding. The collection of information of the

    substrata, by air or ground, through sensors such as radar, magnetic and

    electromagnetic to detect any mineralization in the area. This is a non-evasive

    process that does not have impact on the environment.

    Geophysical surveys

    o Geophysical ground surveys used various method to gather geological information

    such as magnetic and electromagnetics. Magnetic surveying measure local

    magnetic field characteristic of the generated targets from geological mapping. This

    activity was used to detect minerals that respond to magnetic field. It provided

    information of a sub-surface area without physically opening the ground and is able

    to detect metal ore in the ground. The activity was done from air and on ground.

    On ground, a Magnetometer was carried by a person on the surveyed areas to collect

    samples. While in aerial magnetic data was collected using a helicopter where the

    Magnetometer is mounted and this was used on difficult terrain and on large

    terrains. This activity does not pose significant impact to the environment

  • 6

    Drilling (Reverse Circulation)

    o Reverse Circulation drilling often referred to as ‘RC’ drilling uses rods (shafts) with

    inner and outer tubes with drill bit attached to an air-filled interchanging piston

    known as a hammer. The hammer produces drill cuttings that are returned to surface

    inside the rods. RC drill are carried on drill rigs, which are mostly powerful heavy

    truck. World over, RC drilling is the most preferred method because it is less costly

    and produces liable materials that are free from contamination. In an arid place like

    Namibia, RC Drilling would be advantageous because it does not require water for

    rock drilling unlike Diamond core drilling that requires water for lubrication. Once

    the proposed exploration has been concluded, the impacted sites will be

    rehabilitated in accordance with the requirements of the EMP.

    The Bi-annual report and rehabilitation repots of evasive activities that took place were submitted

    to the Ministry of Environmental and Tourism and it was these reports which formed the basis of

    the ECC renewal in January 2017.

    2.1.4. Period 2017-2019

    There were no exploration activities during the period of 2017 – 2019. The status of the

    environment remains as it was reported during the period of 2011-2017. MET is in position of

    these reports.

  • 7

    3. The Environmental Management Plan

    3.1. Purpose of the EMP

    The Environmental Management Plan (EMP) is a risk strategy that contains logical framework,

    monitoring programme, mitigation measures, and management control strategies to minimize

    environmental impacts. It further stipulates the roles and responsibility of persons involved in the

    project. These strategies are developed to reduce the levels of impacts for the projects.

    3.2. Compliance to the EMP

    This EMP is a legally binding document as given under the provisions of the Environmental

    Management Act, 2007 (Act No. 7 of 2007). The proponent and its contractors must adhere to

    the framework of this document.

    3.3. Roles and Responsibilities

    3.3.1. Proponent

    The proponent, shall take overall responsibility for proper implementation of the EMP. It remains

    the responsibility of the proponent to appoint key personnel for the implementation of the EMP.

    The proponent must therefore;

    Appoint a site Manager;

    Ensure employees understand the guidelines of the EMP;

    Ensure the EMP is well explain to Contractors;

    Ensure safer working environment;

    Provide workers with Personal Protective Clothing;

    Ensure the environment is protected and;

  • 8

    In events where the proponent hires or subcontract contractors for the job, the proponent must

    ensure that the contractor is in position to execute the mandate of the EMP;

    3.3.2. Environmental Compliance Officer (ECO)

    Compliance to EMP is enforce by the environmental inspector as provided for under

    Environmental Management Act (No. 7 of 2007) (EMA). Hence the Environmental Compliance

    Officer (ECO) is an individual appointed as an environmental inspector under EMA. Depending

    on his/her work schedule, the ECO shall visit the site at any time for environmental inspection and

    monitoring.

    3.3.3. Site Manager

    The Site Manager (SM) represents the proponent on site. He/she shall be responsible for daily

    activities in ensuring environmental protection. All communication with regard to the

    implementation of EMP must be channeled through the SM.

    3.3.4. Employees

    It shall be responsibility of employees to adhere to the provision of EMP. At all times when on

    site, employees are expected to ensure their safety by wearing personal protective equipment

    clothing, report worn out PPE and request for replacement.

    3.4. Disciplinary Action

    3.4.1. Proponent

    The EMP is a legally binding document, non-compliance to the EMP is punishable upon

    conviction under EMA. Amongst others, legal action, fines and suspension of work or both.

    3.4.2. Workers

    Workers found contravening the EMP must be disciplined by the proponent such as written

    warning

  • 9

    4. The EMP Tables Mitigation Measure and Commitments

    This EMP table is not altered as provided from the proponent. The EMP was developed by SLR Consulting. Red-Dune reviewed the EMP and the

    gaps /comments are provided in red.

    Table 4-1 Field Mapping, Geophysical Surveys And Soil Sampling

    Activity Potential Impact

    Management and Mitigation Measures Action Plan Frequency Responsible

    Parties

    Air survey Noise Discuss flight plans and schedule with land owners prior to air

    surveys.

    Avoid residences, game and livestock enclosures where possible.

    Prior to

    air

    surveys

    Project Manager

    Pilots

    Ground survey,

    mapping and soil

    sampling

    Socio-

    economic

    Honour agreements set out in the site-access contracts

    Consult and provide feedback regarding activities on the

    individual properties

    Provide contact details to a designated Gazania Investment

    person, who will serve as liaison between landowners and the

    exploration teams

    Land owners to be provided with a list of all people working on

    site

    All staff operating on site will be provided with identification

    and proof that they are working for the applicant

    Ensure gates are closed after entry and exit.

    Duration

    of

    mapping

    and

    surveying

    Project

    Manager

    Site

    supervisor

  • 10

    Activity Potential Impact

    Management and Mitigation Measures Action Plan Frequency Responsible

    Parties

    Biodiversity The footprint of the area to be disturbed for surveying/mapping

    and for providing access to survey sites will be minimised as far

    as is practically possible.

    Gazania Investment will implement a zero tolerance policy with

    regards to the killing or collecting of any biodiversity. This

    applies to people directly employed by Gazania Investment as

    well as any contractors working on their behalf.

    Employees and contractors will be shown the value of

    biodiversity and the need to conserve the species and systems that

    occur within the project area.

    No open fires will be permitted on site.

    Speed limits will be enforced so as to prevent road kills.

    Permits will be required for the removal of protected tree species.

    Duration

    of

    mapping

    and

    surveying

    Project

    Manager

    Site

    supervisor

    Air quality Vehicle speeds will be limited to 40km/h on access routes to limit

    dust.

    Duration

    of

    mapping

    and

    surveying

    Project

    Manager

    Site

    supervisor

  • 11

    Activity Potential Impact

    Management and Mitigation Measures Action Plan Frequency Responsible

    Parties

    Heritage In the event that archaeological resources are discovered, a

    chance find emergency procedure will be implemented which

    includes the following:

    All work at the find will be stopped to prevent damage;

    An appropriate heritage specialist will be appointed to assess

    the find and related impacts; and

    Permitting applications will be made to the necessary

    authorities, if required.

    In the event that any graves are discovered during the

    exploration activities, these will be avoided and preserved as

    a first priority. If damage is unavoidable, prior to damaging

    or destroying any identified graves, permission for the

    exhumation and relocation of graves must be obtained from

    the relevant descendants (if known) and the relevant local

    and provincial authorities

    Duration

    of

    mapping

    and

    surveying

    Project

    Manager

    Site

    supervisor

  • 12

    Table 4-2 Drill Site Establishment

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    - Access the drill site

    using a new access

    track where

    necessary

    - Set-up drilling

    machine with drip

    trays and

    groundsheets

    - Strip vegetation

    and topsoil (up to

    300mm where

    available)

    - Temporarily store

    topsoil adjacent to

    drill site

    - Set-up ablution

    Air quality –

    dust and

    gaseous

    emissions

    The movement of drilling related vehicles on the unpaved

    access track will be on a small scale

    Vehicle speeds will be limited to 30km/h on site

    Vehicles and the drilling rig will be maintained in good

    working order

    Minimize new access route development (routes to be

    approved by land owners prior to development)

    On-going Project

    Manager

    Site

    supervisor

    Noise Vehicles will travel maximum 30 km/hour near

    houses/settlements

    Ongoing Project Manager

    Site supervisor

    Biodiversity Refer to biodiversity management measures relating to

    ground surveying, mapping and sampling (Table 4-1).

    Honour agreements set out in the site-access contracts,

    specifically relating to the areas utilized for game and

    livestock farming. Special consideration should be given to

    the sensitive hunting season.

    Ongoing Project

    Manager

    Site

    supervisor

  • 13

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    facilities

    - Set-up fuel and

    lubricants storage

    area

    - Waste management

    Provide appropriate toilet facilities for the exploration

    workers on the site or agree with landowner to use certain

    facilities on the farm.

    Land use Access agreements to be prepared and approved prior to drill

    site establishment.

    The footprint of the area to be disturbed will be minimised as

    far as is practically possible.

    Areas used as laydown areas are to be raked and/or ploughed

    to encourage re- vegetation

    Agree on relevant compensation with land-owners where

    land uses are impacted

    Ongoing Project

    Manager

    Site

    supervisor

    Heritage Refer to heritage management measures relating to ground

    surveying, mapping and sampling (Table 4-1)

    Ongoing Project Manager

    Site supervisor

    Socio-economic Refer to socio-economic management measures relating to

    ground surveying, mapping and sampling (Table 4-1)

    Ongoing Project Manager

  • 14

    Table 4-3. Drilling

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    - Drill borehole

    - Contain all

    drilling water in

    the sump and

    allow to settle

    - Log the drill core

    and place on core

    trays

    - Maintain ablution

    facilities

    Contamination

    of

    soil/Hydrocarbo

    n spillages

    In all areas where there is storage of hazardous substances

    (i.e. hydrocarbons), there will be containment of spillages on

    impermeable floors and bunded trays that can contain 110%

    of the volume of the hazardous substances.

    All refueling and any maintenance of vehicles will take place

    on impermeable surfaces.

    Pollution will be prevented through basic infrastructure

    design and through maintenance of equipment.

    Spill kits will be readily available on site. Employees and/or

    contractors will be shown to use the spill kits to enable

    containment and remediation of pollution incidents.

    Environmental awareness training of contractor

    Gazania Investment will establish environmental awareness

    in employees and contractors

    On-going

    for all

    drilling

    activities

    Project

    Manager

    Site

    supervisor

  • 15

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    A PVC lined sump will be used for collection of oils and silt

    contained in the drilling water

    Any spills will be contained and cleaned up immediately

    Non-toxic and biodegradable drilling lubricant will be used

    Groundwater

    contamination

    Refer to management measures relating to contamination of

    soils.

    Licenses in terms of the Water Resource Management Act

    (Act No. 11 of 2013) will be obtained for all drilled holes

    (not just boreholes).

    Provide appropriate toilet facilities for the exploration

    workers on the site or agree with landowner to use certain

    facilities on the farm.

    On-going

    for all

    drilling

    activities

    Project

    Manager

    Site

    supervisor

    Air quality

    deterioration

    Vehicle speeds will be limited to 40km/h on access routes to

    limit dust.

    The movement of drilling related vehicles on unpaved access

    track will be on a small scale.

    Water sprays can be used around the lay-down area when a

    drill-site is located

    On-going

    for all

    drilling

    activities

    Project

    Manager

    Site

    supervisor

  • 16

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    near settlements (or sensitive land-use areas, i.e. horticultural

    areas).

    Noise generation Drilling will only be conducted during the day when drill

    sites are located close to inhabited homesteads.

    Drilling plans and schedules will be discussed and agreed

    upon with land owners prior to initiation.

    Vehicles will travel maximum 30 km/hour near

    houses/settlements.

    On-going

    for all

    drilling

    activities

    Project

    Manager

    Site

    supervisor

    Land use Refer to land use management measures relating to drill site

    establishment (Table 4-2)

    On-going

    for all

    drilling

    activities

    Project Manager

    Site supervisor

    Water abstraction Groundwater

    quantity

    Water use licenses in terms of the Water Resource

    Management Act (Act No. 11 of 2013) will be obtained for

    all boreholes.

    Water levels will be measured prior to abstraction, during

    abstraction (daily) and after completion. Levels will be

    reported to land owners.

    On-going

    for all

    drilling

    activities

    Project

    Manager

    Site

    supervisor

  • 17

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    Should water be reached during drilling the landowners will

    be informed. Should the landowners wish it; the holes will

    be cased and left for use by the farmers (liability relating to

    the boreholes will then be transferred to the landowners).

    Table 4-4. Relevant to All Exploration Activities

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible Parties

    All exploration

    activities

    Social –

    provision of

    toilet facilities

    and other

    Socio

    Economic

    Impacts

    (Employment,

    Alcohol and

    Drug Abuse,

    Provide appropriate toilet facilities for the exploration

    workers on the site or agree with landowner to use certain

    facilities on the farm.

    Employment

    Recruit locals for unskilled labour

    Where possible, procure materials from local suppliers

    Alcohol and Drug Abuse

    Ban the use of alcohol and drugs at work place

    On-going

    for all

    exploration

    activities

    Project Manager

    Site supervisor

  • 18

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible Parties

    HIV and AID Teach employees about dangers alcohol and substance

    abuse

    All employees must be screen with the breathalyser to

    avoid intoxicated personnel on site

    HIV and AIDS

    Provide HIV / AIDS awareness at induction

    Avail Condoms at the mine site

    Waste

    Management

    Waste generated will be handled in accordance with the

    contract signed with the landowner.

    Suitable receptacles for waste disposal will be provided at

    appropriate locations on site. These receptacles will be clearly

    marked for different waste types.

    Employees and contractors will be shown the importance of

    correct waste disposal as well as waste minimization and

    recycling.

    Waste will be removed from site and disposed of at a suitable

    licensed waste disposal facility.

    Project

    Manager

    Site

    supervisor

  • 19

    Activities Potential Impact Management and Mitigation Measures Action Plan

    Frequency Responsible Parties

    Hazardous waste (including hydrocarbon contaminated

    material/soil) will be disposed of at a licensed hazardous

    waste disposal facility.

  • 20

    Table 4-5. Closure and Rehabilitation

    Activities Potential

    Impact

    Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    General closure

    activities:

    - Close drill holes

    (unless otherwise

    agreed with farmers)

    - Remove water from

    the sump and drip

    trays

    - Remove oils and silt

    from drip trays and

    store until disposal to

    permitted hazardous

    landfill site

    - Backfill the sump

    once it has dried out

    (dome to allow for

    Groundwater

    and

    surface

    water

    contaminat

    ion

    In all areas where there is storage of hazardous substances

    (i.e. hydrocarbons),

    There will be containment of spillages on impermeable floors

    and bunded trays that can contain 110% of the volume of the

    hazardous substances.

    All refueling and any maintenance of vehicles will take place

    on impermeable surfaces.

    Pollution will be prevented through basic infrastructure

    design and through maintenance of equipment.

    Spill kits will be readily available on site. Employees and/or

    contractors will be shown how to use the spill kits to enable

    containment and remediation of pollution incidents.

    Any spills will be contained and cleaned up immediately

    Once- Closure

    of

    drill site

    Project Manager

    Site supervisor

    Noise pollution Vehicles will travel maximum 30 km/hour near

    houses/settlements.

    On-going Project Manager

    Site supervisor

  • 21

    Activities Potential

    Impact

    Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    subsidence) and plug

    borehole (unless an

    agreement is in place

    with landowner for

    alternative uses)

    - Move drill core trays,

    ablution facilities,

    water bowser, stores

    and drill rig from the

    site

    - Dispose of any general

    waste to a permitted

    landfill site

    - Remove temporary

    fencing

    - Rip and plough

    compacted areas

    Contaminati

    on of soils

    Refer to management measures relating to contamination of

    water

    On-going

    and

    closure

    Project

    Manager

    Site

    supervisor

    Air

    quality

    deteriorati

    on

    Vehicle speeds will be limited to 40km/h on access routes to

    limit dust.

    The movement of drilling related vehicles on unpaved access

    track will be on a small scale.

    On-going Project

    Manager

    Site

    supervisor

    Soil erosion Impacted footprints are to be raked and/or ploughed to

    encourage re- vegetation

    Access routes will be ripped unless the land owners wish for

    them to remain.

    A monitoring program will be implemented to establish re-

    vegetation progress

    Agree on relevant compensation with land-owners where

    land used for hunting

    purposes is impacted

    Starts at

    closure,

    continues for

    a pre-

    determined

    time (as

    stated in

    agreements)

    Project

    Manager

    Site

    supervisor

  • 22

    Activities Potential

    Impact

    Management and Mitigation Measures Action Plan

    Frequency Responsible

    Parties

    - Replace topsoil over

    disturbed area

    - Rehabilitate access

    track by ripping

    - GPS marker to

    identify

    - drill site

    Waste

    management

    Decommission ablution facilities

    Ensure that all waste generated during activities is removed

    from the site and

    disposed of appropriately

    Once off Project

    Manager

    Site

    supervisor

    Land use Land owners will be invited to carry out site inspections

    following rehabilitation in order to ensure that it has been

    carried out suitably.

    Post-closure Project

    Manager

    Site

    supervisor

  • 23

    5. Conclusion and Recommendations

    5.1. Conclusion

    The following are points of consideration;

    The review of the Environmental Management Plan found it be adequate, practical and

    efficient towards the improvement of environmental sustainability;

    No exploration activities took place between the period of 2017 and 2019;

    The ECC is due for renewal in January 2020;

    In accordance to the submitted bi-annual report in 2017, there were no red-flags or

    complaints from farmers about environmental performance;

    With adequate implementation of the EMP, the project is not expected to pose harm to

    the environment.

    5.2. Recommendations

    It is recommended to the approving authority to approve the renewal of the

    Environmental Clearance Certificate.

    It is further recommended to the approving authority conduct site inspection of site,

    especially the drilled site and establish cordial relationship with farmers’ associations

    whom are crucial at monitoring the exploration activities in order to ensure compliance to

    the law and the EMP.

  • 24

    6. Reference

    Dr. Martin Pickford and Dr Brigitte Denut 2010., Memoir 21 Karst Geology and

    Palaeobiology of Northern Namibia, Ministry of Mines and Energy Geological Survey

    of Namibia

    Enviro Dynamics 2014., Environmental Assessment for the exploration of base metals on

    exclusive prospecting licenses 5606, 4934, 5712 & 5713), Kavango East Region,

    Namibia.

    Greg Christelis and Wilhelm Struckmeier 2011., Groundwater in Namibia; An Explanation

    to the Hydrogeological Map, Ministry of Agriculture Water and Forestry

    J.E. Misiewicz 1988., The Geology and Metallogeny of the Otavi Mountain land, Damara

    Orogen, Swa/Namibia, with particular reference to the Berg Aukas zn·pb-v Deposit - A

    Model of Ore Genesis

  • 25

    7. Appendixes

    7.1. Previous and Current Environmental Clearance Certificate

  • 26

    7.2. Curriculum of the Environmental Assessment Practitioner

  • Master of Science Degree International Fisheries Management, TROMSO, NORWAY

    Bachelor of Science Degree Natural Resource: Fisheries and Aquatic Sciences, UNAM

    CURRICULUM VITAE FOR IPEINGE E. MUNDJULU

    PERSONAL INFORMATION

    First names: Ipeinge Etuwete

    Surname: Mundjulu

    Identity Number: 840805 1009 8

    Citizenship: Namibian

    Membership in Professional Bodies: None (There is no established existing Regulatory Body for

    Environmental Practitioners under any Act of Parliament in

    Namibia).

    EDUCATION / ACADEMIC QUALIFICATIONS

    Year: Institution/school Qualification obtained

    2018 -2018 Center of Environment Institute Certificate, Environmental

    (India) Management and its Compliances in Mine

    2017-2017 Center of Environment Institute Certificate of Mining Inspection and

    (India) Compliance Assurance

    2007-2009 University of Tromsø Master of Science Degree, International Fishery

    (Norway) Management

    2003-2006: University of Namibia Bachelor of Science Degree, Natural Resources;

    Fisheries and Aquatic Sciences

    2001-2002: Oshakati Senior Secondary School Grade 12 IGCSE certificate

    1997-2000: Oshatotwa combined school Grade 10 JSC certificate

    1990-1996: John Shekudja combined school Primary education

    EMPLOYMENT RECORD;

    Period Institution Position Core Functions

    Nov 2018-

    Todate

    Red-Dune

    Consulting CC

    Director and

    Lead Consultant

    Conducting Environmental Impact Assessment

    and Developing Environmental Management

    Plans

    Environmental Inspections and Auditing

    Natural Resource Management

  • CURRICULUM VITAE FOR IPEINGE E. MUNDJULU

    Master of Science Degree International Fisheries Management

    Bachelor of Science Degree Natural Resource: Fisheries and Aquatic Sciences

    Period Institution Position Core Functions

    01 August 2016-

    November 2018

    Ministry of

    Environment

    and Tourism

    Senior

    Conservation

    Scientist (DEA)

    Reviewing of Environmental Impact Assessment

    and Environmental Management Plans Reports

    Make Recommendations to Environmental

    Commissioner for the issuing of the

    Environmental Clearance Certificates

    Carrying out Environmental Inspections at new

    and old development sites around the country

    Raising awareness on the implementation and

    procedures of the Environmental Management

    Act 2007 (Act No. 7 of 2007) to various

    Institutions.

    Technical Person for Sand Mining in the Country

    Member of the technical committee that

    developed the National Solid Waste

    Management Strategy.

    01 July 2012 –

    30 July 2016

    01 Jan 2010 –

    29 June 2012

    Ministry of

    Fisheries and

    Marine

    Resources

    Senior Fisheries

    Biologist

    Fisheries

    Biologist

    Technical Focal Person for the review of

    Environmental Impact Assessment under which

    the Ministry of Fisheries is a Competent

    Authority. Amongst the reviewed EIA project;

    - EIA Application for Namibian Phosphate

    Project

    - EIA Application for various Oil and Gas

    Offshore prospecting

    - EIA Application for Desert Rose Project

    - EIA Application for the Proposed Cape

    Cross Salt Project

    - EIA Application for Solar Power at Henties

    Bay etc.

    Research

    Supervised scientific sampling programs

    Supervised research onboard the vessel for

    Sardine survey

    Prepare and present research findings for in-

    house reports and discussions and for scientific

    publications and presentations.

    Present research findings for in-house

    discussions and to the Marine Advisory Council

    as was as Ministerial Management and to the

    small pelagic Industry.

    Participate in relevant regional and international

    research initiatives

  • CURRICULUM VITAE FOR IPEINGE E. MUNDJULU

    Master of Science Degree International Fisheries Management

    Bachelor of Science Degree Natural Resource: Fisheries and Aquatic Sciences

    Period Institution Position Core Functions

    Conduct in-house training for technical staff

    within the section

    02 Apr 2007-

    31 July 2007

    Walvis Bay Salt

    Refiners

    Oyster

    Supervisor

    In charge of oyster farm administration such as

    employees leave and Overtime claims

    On Job Training

    Dec 2005-Feb

    2006

    Namsov Fishing

    Company

    Student

    (Onboard the

    Vessel)

    Sorting of Fish on conveyer belts and Fish

    packaging

    Biological data collection and analysis

    Dec 2004-Feb

    2005

    Seagull Abalone

    Farm (Lüderitz)

    Student Management of Aquaculture operation

    CONSULTANCY EXPERIENCE

    Period Institution Position Assignments

    Nov 2018-

    todate

    Red-Dune

    Consulting CC

    Lead Consultant 1. Environmental Impact Assessment and

    Environmental Management Plan for UNAM’s

    proposed Solar Powered Desalination Plant at Sam

    Nuyoma Campus, Henties Bay Campus (March

    2. Environmental Management Plan for the Brick

    Making at Epalela

    3. Environmental Management Plant for the Seal

    Processing Factory at Henties Bay

    4. Development Environmental Management Plan and

    Decommissioning Plan of existing Waste Disposal

    site (C2 – Waste Disposal site) (UNAM Neudamm

    Campus)

    5. Development of Environmental Management Plan

    Experimental Farming Waste Disposal site (UNAM

    Neudamm Campus)

    6. Development of Environmental Management Plan

    for the Incinerator (UNAM Neudamm Campus)

    7. Undertake Environmental Impact Assessment and

    develop an Environmental Management Plan for the

    New Waste Disposal Site (UNAM Neudamm

    Campus)

    8. Development of an Environmental Management Plan

    for the Sewerage water treatment (Sewerage pond)

    (UNAM Neudamm Campus)

    9. Undertake Environmental Impact Assessment and

    develop an Environmental Management Plan for the

    New Waste Disposal Site for Eenhana Town Council

    10. Development of Environmental Management Plan

  • CURRICULUM VITAE FOR IPEINGE E. MUNDJULU

    Master of Science Degree International Fisheries Management

    Bachelor of Science Degree Natural Resource: Fisheries and Aquatic Sciences

    Period Institution Position Assignments

    and Decommissioning Plan of existing Waste

    Disposal site for Eenhana Town Council

    11. Undertake Environmental Impact Assessment and

    develop an Environmental Management Plan for the

    New Waste Disposal Site for Eenhana Town Council

    12. Development of an Environmental Management Plan

    and Rehabilitation plan of existing gravel burrow pits

    for Eenhana Town Council

    13. Undertake Environmental Impact Assessment and

    develop an Environmental Management Plan for

    Sand Mining Site for Eenhana Town Council

    LANGUAGES

    Language Speak Write Read

    Oshiwambo Excellent

    English Excellent Excellent Excellent

    Afrikaans Good Fair Fair

    REFERENCES

    Mr. Teofilus Nghitila,

    EXECUTIVE DIRECTOR,

    Ministry of Environment and Tourism,

    Tel: +264 61 284 2111,

    Email. [email protected]

    Mrs. Graca D’Almeida,

    DIRECTOR;

    Ministry of Fisheries and Marine

    Resources Resource Management,

    Tel: +264 61 2053911,

    Email: Graca.D'[email protected]

    CERTIFICATION

    I, the undersigned certify that to the best of my knowledge and belief, these data correctly describe me,

    my qualification, and experience.

    Signature of Consultant

    Full Name of Consultant: MUNDJULU IPEINGE ETUWETE