43

Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd
Page 2: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

1

Application for Environmental Clearance Form – 1

(I) Basic Information: S. No. Item No. Details

1 Name Of the Project/s The Melia, Village Mohammadpur Gujar ,Sector -35 of Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd.

2 S. No. in the schedule The Project falls under S.No. 8 (a) Building and Construction Projects but as the built up area of the project is >1,50,000 sq.m therefore will be appraised as category B(B1) Clause 8(b) township and area development project

3 Proposed capacity / area / length/ tonnage to be handled / command area / lease area / number of wells to drilled

The project is a residental complex and involves construction of 912 Dewelling units, 169 EWS units, 2 Community Centre, 1 Primary school and 1 Nursery school. The plot area of the project 17.41 acres /70455.77 sqm. The Letter of intent has been granted by directorate of Town & country planning Haryana vide Letter No. LC-2761-JE(VS)-2013/37379 dated 23/4/13. Copy attached at Annexure-1. The License vide no. 77of 2013. Copy attached at Annexure-1A. NOC for construction has also been obtained from the adminstrator, HUDA, Gurgaon- vide Memo No. 910 dated 7/11/14. copy attached at Annexure-1B. The total cost of project is Rs 430 crores. Project report is attached atAnnexure-2. The area details are given below in Table:1. The receipt of letter for the approval of building plan is attached at Annexure-3 A-1: Letter of Intent A-1A: License A-1B: NOC for construction A-2: Project Report A-3: Receipt for letter for approval of layout plans A-4: Letter for verification of ownership of Land A-4A: Collaboration Agreement A-5: Authority letter A-6: Undertaking A-7: Soil Investigation report A-7A: Hydro geological report A-8: Receipt of Letter for assurance of water supply from HUDA

A-9: Water calculations A-9A: Schematic treatments details of STP. A-10: Receipt of Letter submitted for power requirement to Director General Town & Country

Page 3: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

2

Planning, Haryana. A-10A:Solar Architectural features A-10B: R & U value for Wall, Roof & Glass A-11: PERT/CPM chart A-11A: Demographic Details A-12: Test Reports A-13: Photographs of Project site A-14: NOC from Airport Authority of India A-15: Affidavit for no construction at site along with resolution of authorized director A-16: NOC from tehsildar for Aravali Notification A-17: Undertaking as per SEIAA checklist A-18: Authorization for consultant A-19: Copy of stay order of Consultant The following drawings are enclosed: D-1: Topographic sheet D-2: Panoramic view D-2A: Prospective view D-3: Location Plan D-4: Key features within 500m radius D-4A: Master Plan D-4B: Khasra Plan D-5: Layout Plan D-6: Contour Plan D-7: Zoning Plan D-8: Services Plan D-8A: RWH Design Detail D-9: Dual Plumbing Plan D-10 Parking Plan D-11: Landscape Plan D-12: Fire Fighting Plan D-13: Upper Ventilation Plan D-13A: Lower Ventilation Plan D-14: Electrical Pathway Diagram D-15: Solar Pathway Diagram D-16 Elevation Plan

Table: 1

Description Area covered (%)

Area in Sq.ft Area in Sq.m Area in Acres

Plot area -- 758379.6 70455.77 17.41 Built-up/ covered area -- 1806238.49 167805.04 -- Ground coverage 15.5% 121400.22 11278.45 2.7 Green area 25.84% 196093.7 18217.71 4.5 Upper Basement area 21.2% 162396.9 15087.17 3.7 Lower Basement area 21.2% 163845.2 15221.72 3.7

Page 4: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

3

4 New/Expansion / Modernization New 5 Existing capacity/ Area etc N.A 6 Category of the project „ A‟, „B‟ , „C‟ Category „B‟ – B1 7 Does it attract the general conditions? If

Yes, Please Specify. No

8 Does it attract the specific conditions? If Yes, Please Specify

Not Applicable

9 Location Topographic sheet showing location of project site enclosed as Drawing:1. Panoramic view enclosed as Drawing:2. Location Plan enclosed along as Drawing:3. Drawing showing key features within 500m radius enclosed as Drawing:4.

Plot/ Survey/Khasra No. .Letter for verification of ownership of land as Annexure-4 has been granted by Director General of Town and country Planning ,Haryana, chandigarh vide letter No. 855/S.K2 dated 22.3.2013 ..The collaboration agreement between the Owner and M/S DSS buildtech Pvt. Ltd. Properties Pvt. Ltd.. is attached at Annexure-4A.

Village Mohammadpur Tehsil Gurgaon District Gurgaon State Haryana

10. Nearest railway station / Airport along with Distance in kilometers.

Basai Dhankut Railway Station 29 Km IGI Airport 41 Km

11 Nearest town/District headquarters along with distance in kilometers

Gurgaon District Court 29 Km

12 Village Panchayat, Zilla Parishads, Municipal corporation , local Bodies (Complete Postal address with telephone No. to be given)

Municipal corporation, Civil Lines,Officers Colony (Gurgaon)

13 Name of the applicant Mr. Paras Kumar Jain Authorized Representative M/S D.S.S Buildtech Pvt. Ltd 506, Time Square Building, B block , Sushant Lok, Phase-I, Gurgaon Authority Letter is enclosed along as Annexure-5

14 Registered address

M/S D.S.S Buildtech Pvt. Ltd 506, Time Square Building, B block , Sushant Lok, Phase-I, Gurgaon

15 Address for correspondence : M/S D.S.S Buildtech Pvt. Ltd 506, Time Square Building, B block , Sushant Lok, Phase-I, Gurgaon

Name : Mr. Paras Kumar Jain Designation(owner/ Partner/CEO) Authorized Representative

Page 5: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

4

Address M/S D.S.S Buildtech Pvt. Ltd 506, 5th Floor, Time Square Building, B block , Sushant Lok, Phase-I, Gurgaon

Pin Code 122002 E- Mail [email protected] Telephone No. 0124-4550300, 9810605575 Fax No. 0124-4550399

16 Details of alternative Sites examined, if any. Location of these sites should be shown on the topo Sheets.

No

17 Interlinked Projects No

18 Whether separate application of interlinked project has been submitted?

Not Applicable

19 If Yes, date of submission. Not Applicable 20 If No, reason Not Applicable 21 Whether the Proposal involves approval

/ Clarence under : If Yes , details of the same and their to be given . (a) The Foerest Conservation , Act,1980 (b) the wild life Protection Act, 1972 (c) The C.R.Z Notification, 1991.

Not Applicable. Undertaking from the project proponent is enclosed along as Annexure-6

22 Ether their is any government Order / policy relevant / relating to the site?

Not Applicable. Undertaking from the project proponent is enclosed along as Annexure-6

23. Forest land Involved (hectare) Not Applicable 24. Whether there is any litigation pending

against the project and /or land in which the Projects is proposed to be set up? (a) Name of the court (b) Case no. (c) Orders / Directions of the Courts , if any and its relevance with the Project

Not Applicable. Undertaking from the project proponent is enclosed along as Annexure-6

Page 6: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

5

b) I hereby give the Undertaking that the data and information given in the application and enclosure are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. Date: ___________ Place: Gurgaon

Paras Kumar Jain Authorized Representative

M/s D.S.S Buildtech Pvt. Ltd. (Project Proponent/Authorized Signatory)

NOTE: 1. The project involving clearance under Coastal Regulation zone Notification, 1991 shall submit with the application a C.R.Z map duly demarcated by one of the authorized agencies, showing the project activities, w.r.t. C.R.Z (at the stage of TOR) and the recommendation of the state coastal zone Management Authority (at the stage of EC). Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the C.R.Z Notification, 1991 for the activities to be located in the CRZ. 2. The project to be located within 10 km of the National parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of wild Animals, the project proponent shall submit the map duly authenticated by chief wildlife warden showing these features vis-à-vis the project location and the recommendation or comments of the Chief wildlife warden thereon (at the stage of EC). 3. All correspondence with the Ministry of Environment & Forests including submission of application for TOR/Environmental Clearance, subsequent clarification, as may be required from time to time, participation in the authorized signatory only. The authorized signatory should also submit a do ment in support of his claim of being an authorized signatory for the specific project."

Page 7: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

6

(II) Activity 1. Construction, Operation or Decommissioning of the Project involving actions, which

will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

S.No. Information/Checklist confirmation

Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)

Yes The project “The Melia ” is a residential project. The project falls in residential zone as per the approved master plan. Master Plan showing location of project site is enclosed along as Drawing: 4A. Letter of intent is enclosed along as Annexure-1. License is attached as Annexure - 1A. The construction shall be done as per layout plan (Drawing-5).

1.2 Clearance of existing land, vegetation and buildings?

No Vacant land

1.3 Creation of new land uses? Yes The land use is changed but the project is approved by town & Planning department , Haryana. License is granted us and attached at Annexure-1A

1.4 Pre-construction investigations e.g. bore houses, soil testing?

Yes The pre-construction activity for the project is done and the soil investigation report is attached at Annexure-7. The depth of water level is 31 mt below the existing ground level . The hydrogeological report is attached at Annexure-7A .

1.5 Construction works?

Yes The construction shall be as per proposed land use plan. See S.No.3 of (I) Basic information, Table:1 & Drawing-5: Layout Plan.

1.6 Demolition works? No Not Applicable 1.7 Temporary sites used for

construction works or housing of construction workers?

Yes The manpower required during construction period shall be around 150. The most of the workers shall be local or from nearby areas. Only 30 workers shall reside at the site during peak construction period of 3 years. Temporary hutments and sanitation facilities shall be provided for these workers within the project site.

1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations

Yes See Land Use details in Drawing: 5 (Layout Plan)Also see S.No.3 of (I) Basic information and Table:1

Page 8: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

7

1.9 Underground works including mining or tunneling?

No 66000 CUM of earth will be excavated Excavation shall be done for the purpose of laying foundation & basements. Soil excavated will be stored within project site and will be used for cut & fill & landscaping.

1.10 Reclamation works? No Not Applicable

1.11 Dredging? No Not Applicable 1.12 Offshore structures? No Not Applicable 1.13 Production and manufacturing

processes? No Not Applicable

1.14 Facilities for storage of goods or materials?

Yes Cement and other construction materials shall be stored at site for which temporary sheds shall be constructed.

1.15 Facilities for treatment or disposal of solid waste or liquid effluents?

Yes The total design population of the project is 5605 out of which 5405is residential population for Dwelling and EWS units [11081x 5 person /units] and 200 flotation population for schools. The water supply will be from HUDA . Letter in this regard has been submitted to Executive engineer , HUDA . Recept of letter for assurance of water supply is attached at Annexure-8. The total water requirements of the project is 910 KLD out of which 728 KLD sewage @ 80% of the total water consumption shall be generated. The water calculations is attached at Annexure-9. An STP of 1 KLD capacity based on SBR technology will be installed at site. The Schematic treatment details of S.T.P is attached at Annexure-9 A. Solid waste of about 2202 Kg/day shall be generated @0.4 Kg/capita/Day from residential colony (Dwelling units and EWS units )and @0.2Kg/capita/Day from Floating population (Schools).A separate area is earmarked for segregation of solid waste. The biodegradable waste will be converted into compost using mechanical composter. Recyclable waste will be sold to local kabaris The left inert waste will be dumped to MC dumping site.

Page 9: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

8

Water Balance

216 KLD

Municipal Supply

Rain Water Recharging

Roof Top & Storm water

Domestic Demand

910 KLD Horticulture Demand - An area of 18217.71 sqmt. is available Summer- 100 KLD @ 5.5 lit/sq.m Winter- 32 KLD @ 1.2 lit/sq.m Monsoon – 9 KLD @ 0.5 lit/sq.m

To recharge aquifer

Flushing demand for The Melia 216 Kl/day

Domestic demand 694 Kl/day

(Flow to Sewer 80%)

555 KLD

Sewage Load 771KLD (Treated in STP of capacity 1 MLD based on SBR technology)

95% recovery

Excess will be disposed to MC sewer. Treated Sewage 732 KLD

Page 10: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

9

1.16 Facilities for long term housing of operational workers?

No Not Applicable

1.17 New road, rail or sea traffic during construction or operation?

Yes During construction phase movement of 10-12 vehicles shall be there. During operation, the gestation period for occupation is 2-3 years. The vehicles as four/two wheelers shall be used by the occupants,staffs and floating population.

1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc

No No new infrastructure for this purpose shall be required. The Sector will be Developed by Dept. of Town and Country Planning, Haryana and roads will be developed by them. Only internal circulation road to be made.

1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?

No Not Applicable

1.20 New or diverted transmission lines or pipelines?

No Not Applicable

1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers?

No

Not Applicable

1.22 Stream crossings?

No Not Applicable

1.23 Abstraction or transfers of water form ground or surface waters?

Yes During Construction period a water demand of 273 KLD (30% of the demand during operation) may be there depending upon phases of construction. This will include domestic demand for150 workers during peak period i.e. 7 Kl /day (@ 45 lpcd).See S.No.1.15, (II) Activity Form 1.Rainwater harvesting will be done from rooftop. For the roof top area @ 11278.45 Sq.m, with annual average rainfall of 596 mm and assuming runoff coefficient 0.8, total runoff available is 5377 KL/annum.The ground water shall be recharged by providing_ No. rain water harvesting pits to tap roof top water .Plan showing RWH structures is enclosed along as Drawing: 8. The RWH design is attached at D-8A.

Page 11: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

10

1.24 Changes in water bodies or the land surface affecting drainage or run-off?

No Not Applicable

1.25 Transport of personnel or materials for construction, operation or decommissioning?

Yes Clause-1.17, Section-II (Activity)

1.26 Long-term dismantling or decommissioning or restoration works?

No Not Applicable

1.27 Ongoing activity during decommissioning which could have an impact on the environment?

No Not Applicable

1.28 Influx of people to an area in either temporarily or permanently?

No There shall be no influx but routine movement of people. The maximum number of workers engaged in construction at any time shall not be more than 200, during peak Construction activity over 3 years. Of these more than half of the work force shall be local only and only about 80 workers shall reside at site. The project is a residental complex and involves construction of 912 Dewelling units, 169 EWS units, 2 Community Centre, 1 Primary school and 1 Nursery school. The expected population of the Project on full occupation will be5605. This will also have a gestation period of at least -2-3 years after the construction is over. So there will be no sudden influx but gradual occupation.

1.29 Introduction of alien species? No Not Applicable 1.30 Loss of native species or genetic

diversity? No Not Applicable

1.31 Any other actions? No Not Applicable

Page 12: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

11

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

S.No. Information/Checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information data

2.1 Land especially undeveloped or agricultural land (ha)

No The area is lying vacant and will be developed by M/s DSS Buildtech Pvt. Ltd for the construction of residential colony.

2.2 Water (expected source & competing users) unit: KLD

Yes See section 1.23 of Section-II (Activity). This is a planned construction and there are no competing users. The water supply will be provided by HUDA and letter inthis regard has already been submitted.

2.3 Minerals (MT) No Not Applicable 2.4 Construction material – stone,

aggregates, sand/s oil (expected source – MT)

Yes These materials shall be procured from authorized outlets in and around Gurgaon. The approximate quantities of material to be used is : Cement-6792 tonn, Fly ash- 2100 tonn, Jamuna Sand-825 tonn, Coarse sand-16415 tonn, Stone aggregates-24372 tonn, Bricks-38.88 lacs, TMT steel-2580 tonn, Structural Steel-10 tonne

2.5 Forests and timber (source – MT) No The Project shall not involve any use of timber for construction purpose. All material required for shuttering purpose shall be that of mild steel. In the serviced apartments also, a mix of MDF (e.g For Cupboards and Door Panels), Aluminium (e.g For Window shutters) shall be used to make minimum use of wood. At the most chowkets may be of wood.

2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW)

Yes Total Energy requirement of 6063 KW will be supplied by State Electricity Board. Letter in this regard has been submitted to Director General, Town and Country Planning , Haryana. The letter in this regard has been attached at Annexure-10 . -Generators of 625 KVA capacity & -Generator of 1010 KVA capacity are proposed for standby use for operating lifts etc. Electrical Pathway drawing is attached at D-14.

2.7 Any other natural resources (use No Not Applicable

Page 13: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

12

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

S.No. Information/Checklist confirmation

Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)

No The project is a residential complex and involves construction of 912 Dwelling units, 169 EWS units, 2 Community Centre, 1 Primary school and 1 Nursery school .There will not be any hazardous waste from the project site except for the used Oil from DG set (Hazardous Waste category 5.1). The same shall be stored in HDPE tanks and sold to the authorized recyclers in the region.

3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)

No Not Applicable

3.3 Affect the welfare of people e.g. by changing living conditions?

Yes The project involve area to local people. It shall also provide employment during construction period as well as later in activities like security, operation and maintenance of pollution control equipments, landscaping etc.

3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.

No Not Applicable

3.5 Any other cause No Not Applicable

appropriate standard units)

Page 14: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

13

4. Production of Solid Wastes during construction or operation or decommissioning (MT/month)

S.No. Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

4.1 Spoil, overburden or mine wastes

No The contour plan is attached as Drawing-6. The project area is plain thus not much of the land will be excavated.

4.2 Municipal waste (domestic and or commercial wastes)

Yes The construction waste shall be used in making the internal roads/floors. Solid waste of about 2202 Kg/day shall be generated @0.4 Kg/capita/Day from residential population ( dwelling and EWS units) and @0.2Kg/capita/Day from Floating population ( school) . A separate area is earmarked for segregation of solid waste. The biodegradable waste will be converted into compost using mechanical composter. Recyclable waste will be sold to local kabaris The left inert waste will be dumped to MC dumping site.

4.3 Hazardous wastes (as per Hazardous Waste Management Rules)

Yes Category 5.1, used oil from DG set

4.4 Other industrial process wastes No Not Applicable

4.5 Surplus product No Not Applicable

4.6 Sewage sludge or other sludge from effluent treatment

Yes See-Clause 4.2, Section-II (Activity) of Form-I

4.7 Construction or demolition wastes

Yes See-Clause 4.2, Section-II (Activity) of Form-I

4.8 Redundant machinery or equipment

No Not Applicable

4.9 Contaminated soils or other materials

No Not Applicable

4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No Not Applicable

Page 15: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

14

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.No. Information/Checklist

confirmation Yes/No Details thereof (with approximate quantities

/rates, wherever possible) with source of information data

5.1 Emissions from combustion of fossil fuels from stationary or mobile sources

Yes The unit shall install _ Gensets of 625 KVA & -_Gensets of 1010 KVA capacity which shall run on Diesel. These are to be used only as Standby and shall comply with emission limits as given in G.S.R. 520 (E), Environment (Protection) Amendment Rules 2003 at the manufacturing stage itself. The DG sets shall further be procured from agencies complying the noise emission standards at the manufacturing stage itself as per G.S.R. 371(E), the Environment (Protection) second Amendment Rules, 2002.

5.2 Emissions from production processes

No Not Applicable

5.3 Emissions from materials handling including storage or transport

No Not Applicable

5.4 Emissions from construction activities including plant and equipment

Yes Dust may be generated during activities as excavation of foundation & basement. These foundation shall be excavated in a minimum time as per PERT and CPM Chart using machines. PERT/CPM Chart attached along at Annexure-11.The vehicles which ferry construction material as sand are to be covered from top and made wet before movement and thus no dust is generated. The area involved is small and further construction activity shall be done in phases to avoid any significant generation of dust.

5.5 Dust or odours from handling of materials including construction materials, sewage and waste

Yes The construction material involved shall not provide any odour. An STP, based on SBR technology shall be provided. No odour shall be generated from the operation of STP. Details of Schematic treatments details of STP at Annexure-9A.

5.6 Emissions from incineration of waste

No Not Applicable

5.7 Emissions from burning of waste in open air (e.g. slash materials, constructiondebris)

No Not Applicable

5.8 Emissions from any other sources

No Not Applicable

Page 16: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

15

6. Generation of Noise and Vibration, and Emissions of Light and Heat: S.No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

6.1 From operation of equipment e.g. engines, ventilation plant, crushers

Yes Unit shall install - gensets of KVA and - genset of 1010 KVA capacity for standby use. The DG sets shall be of in-built acoustic enclosure as approved by CPCB and conforming to MoEF Notification GSR 371 (E).

6.2 From industrial or similar processes

No Not Applicable

6.3 From construction or demolition

No Normal construction is there without using any heavy machinery. The noise if any shall be contained within the area. No construction at night shall be there. No demolition is involved.

6.4 From blasting or piling No Not Applicable 6.5 From construction or

operational traffic

Yes The traffic during construction phase may be around 10-12 vehicles in a day. This shall not have any significant impact. During the operational phase only personnel vehicles as cars/ two wheelers shall be used by the flat owners. The parking plan is enclosed at Drawing 10 & 10 A. Parking details are given in the table 2 below. In addition adequate green area is given, so that noise impact is minimized. The project shall plant trees along the boundary @ 10-15 feet c/c in two or three rows), road sides and parking areas as per landscape plan enclosed at Drawing 11.

6.6 From lighting or cooling systems

No Not Applicable

6.7 From any other sources No - Table 2: S.No Parking Type No. of cars 1. Stilt Parking @30 sq.mt/ECS 67 2. Surface Parking @25 sq.mt/ECS 390 3. Basement Parking @35 sq.mt/ECS 1301

Total cars provided 1758 Total ECS required @1.5 ECS /units(1.5 X 912) 1368

Page 17: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

16

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

S.No. Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

7.1 From handling, storage, use or spillage of hazardous materials

No Not Applicable

7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)

Yes About 728 KLD of sewage shall be generated that shall be recycled for the purpose of irrigation and in toilets within the project. The wastewater shall be treated to BOD < 5 mg/l and shall be discharged after disinfection. The water being discharged after tertiary treatment shall not add to any pollutant load.

7.3 By deposition of pollutants emitted to air into the land or into water

No Not Applicable

7.4 From any other sources No Not Applicable

7.5 Is there a risk of long term build up of pollutants in the environment from these sources?

No Not Applicable

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

S.No.

Information/Checklist confirmation

Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances

No Not Applicable

8.2 From any other causes

No The Building shall comply with the requirements of National Building Code towards Fire Safety for multistory structures. Fire fighting plan attached at Drawing:12

8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)?

No The Building is designed against Earthquakes for Zone-IV requirements as laid down in NBC.

Page 18: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

17

9. Factors which should be considered (such as consequential development) which could

lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

S.No. Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information data

9.1 Lead to development of supporting. utilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: •Supporting infrastructure (roads,

power supply, waste or waste water treatment, etc.)

• housing development • extractive industries • supply industries • other

No The project is a residental complex and involves construction of 912 Dewelling units, 169 EWS units, 2 Community Centre, 1 Primary school and 1 Nursery school and the related impacts are discussed .There shall not be any further consequential cumulative impacts.

9.2 Lead to after-use of the site, which could have an impact on the environment

No Not Applicable

9.3 Set a precedent for later developments

No Not Applicable

9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects

No Not Applicable

Page 19: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

18

(III) Environmental Sensitivity

S.No. Areas Name/ Identity

Aerial distance (within 15 km.) Proposed project location boundary

1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value

No -

2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests

- __

3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

No --

4 Inland, coastal, marine or underground waters No -- 5 State, National boundaries - Delhi Boundary – 45 Km 6 Routes or facilities used by the public for

access to recreation or other tourist, pilgrim areas

No --

7 Defence installations -- Military Area, New Delhi- 41.8 Km

8 Densely populated or built-up area No The demographic details are attached at Annexure- 11.

9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)

-- See location plan (Drawing: 3) and 500 m Plan (Drawing: 4)

10 Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

-- --

11 Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded)

No The area is not subjected to environmental damage. Test reports enclosed along as Annexure-12.

12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

-- The area has not faced any natural hazard so far.

Page 20: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

19

(IV) Project Brief

M/s DSS Buildteach are coming up with a residential colony in the name and style of “ The Melia " at Village Mohammadpur Gujar, Sector 35 ,Sohna, District Gurgaon .The project is over a plot area of 17.41 with built up area (1866238sq.m). The residential complex consists of The residential colony which will have dwelling units, EWS units, Commercial units and schools..The total cost of the project is Rs. 430crores. The approved layout plan for the project is enclosed. The design population is 5605 persons. Total Plot Area: 70455.770sq.m. Built up Area: 167805.04 sq.m. Ground Coverage: 11278.45sq.m Green Area: 18217.71sq.m The project falls in Category-B (B2) Clause 8(a) construction projects

It is submitted that project be granted clearance subject to compliance of proposals as laid down in EMP that include:

1. The total water requirement of the project is 910 KLD. The water demand shall be met through HUDA water supply.

2. Total sewage 728 KLD shall be generated for which a STP of 1 KLD shall be installed. The water will be recycled for flushing and excess shall be used for horticulture (4.5 acres) and remaining shall be discharged into public sewer.

3. Provision of parks over 18217.71 sq.m and trees along the boundary as per landscape plan are suggested.

4. _ No. DG set of 625 and _ No. of 1010 KVA capacity are proposed. Gen-sets for standby use only with in-built acoustic enclosures in compliance MoEF notification GSR 371 (E) and emission levels as per GSR G.S.R. 520 (E), Environment (Protection) Amendment Rules 2003

5. _No. rain water harvesting structures are proposed for recharging ground water.

6. Provision of Fire-fighting Measures for multistory buildings and an Earthquake resistant structure as laid down in National Building Code shall be provided

7. Provision of parking for 1758 cars shall be there.

Page 21: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

20

8. Maximum power demand of 6063 KW with energy saving that will include providing (1) CFL fixtures (2) Use of Low-pressure sodium lamps for the most energy-efficient outdoor lighting along the road and security lighting with Solar mix Street Lights. It shall be ensured that outdoor light fixtures have reflectors, deflectors, or covers to make more efficient use of the light source.

9. Environmental Monitoring during the Construction and Operational Phase as per terms and Conditions imposed by regulatory authorities and compliance to EMP as provided.

Page 22: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

21

“I hereby given undertaking that the data and information given in the application and

enclosures are true to the best of my knowledge and belief and I am aware that if any part of

the data and information submitted is found to be false or misleading at any stage, the project

will be rejected and clearance given, if any to the project will be revoked at our risk and cost”.

Date: 25-05-2015

Place: Gurgaon

Page 23: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

21

FORM 1A

FORM-1A

(Only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS (Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme)

1. LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity) Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.

Reply: Panoramic view of the project site and the vicinity is attached as Drawing-2. See Drawing- 3 and Drawing- 4 for location and 500 m key plan respectively. The development activity shall be done as per the approved layout plan attached as Drawing:5. Also see Form 1, (I) Basic information S.No.3 & Table:1

1.2 List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc.

Reply: See Form 1, (I) Basic information S.No.3, Table: 1 and Drawing:8. For water consumption, sewage generation, solid waste details see Form 1, (II) Activity, and S.No. 1.15

1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities, details of the existing landuse, disturbance to the local ecology).

Reply: No likely impact on adjacent facilities. 1.4 Will there be any significant land disturbance resulting in erosion, subsidence &

instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given).

Reply: No. The project site falls under Seismic Zone IV. Contour plan is attached along as Drawing:6. The ground is almost leveled.

1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site)

Reply: No, Contour map of site is given as Drawing-6. The ground is almost leveled.

1.6 What are the quantities of earthwork involved in the construction activity-cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc.)

Reply: The soil excavated will be from excavation of foundations and Basements. The excavated soil will be used for landscaping and cut & fill purpose within the project.

Page 24: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

22

1.7 Give details regarding water supply, waste handling etc during the construction period

Reply: See Clause-2.2 of Section-II (Activity) of Form-1 and See section 1.23 of Section-II (Activity) of Form-1 regarding water supply. For waste handling See 4.2 of Section- II (Activity) of Form-1.

1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity)

Reply: No.

1.9 Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)

Reply: No. The waste generated during construction shall include material as broken brick, dry plaster pieces, broken sanitary items which shall be used within as in lying down floors, internal road. The pieces of iron shall be sold to Kabadis. For sewage handling from labour hutments, proper toilets with Septic tank shall be provided.

Page 25: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

23

2. WATER ENVIRONMENT 2.1 Give the total quantity of water requirement for the proposed project with the

breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement.

Reply: See Clause-2.2 of Section-II of Form-1 regarding water supply. Water Balance Diagram is given in Form 1

2.2 What is the capacity (dependable flow or yield) of the proposed source of water?

Reply: Water supply will be provided by HUDA.

2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality)

Reply: The water quality confirms to required standards. Test reports enclosed as Annexure: 12.

2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage)

Reply: The water balance for The Melia is attached at Annexure:9. Attempt is to recycle maximum amount of water either in irrigation or flushing. Excess will be discharged to MC sewer.

2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption)

Reply: No

2.6 What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity)

Reply: Minimum, the wastewater shall be reused within project site to the maximum possible extent and shall be treated to tertiary level.

2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created.

Reply: _ No. rain water harvesting wells will be provided. The Services Plan is enclosed along as Drawing:8.

2.8 What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long term basis? Would it aggravate the problems of flooding or water logging in any way?

Reply: Nil. The proposed development does not interfere with any natural drainage.

2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any)

Reply: Any impact on ground water due to abstraction shall be balanced through rainwater harvesting. See 1.23, Section II of Form 1. The Services Plan is attached at Drawing: 8.

Page 26: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

24

2.10 What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts)

Reply: The Construction Planning shall be done so that the excavation is prior to monsoon and all loose material is lifted to earmarked site so that there are no chances of soil flowing along with run-off and clogging the storm system. Further during the construction an agreement shall be there with the contractor to store all material as aggregates, sand and bricks in proper earmarked stacks. The material like cement or any material that can lead to generation of leachate shall be stored under sheds. The construction shall be further taken in phases so that at one time only a portion is being handled.

2.11 How is the storm water from within the site managed?(State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels

Reply: For details on storm water management see S.No. 1.23 Form I and Drawing: 8 (Services Plan)

2.12 Will the deployment of construction labourers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation)

Reply: No. At the time of peak construction activity @ 200 workers shall be employed. ,out of this @ 80 workers shall reside at the site and rest of workforce shall be local that shall commute daily. A temporary common toilet and bathroom facility shall be provided for this workforce with a connection to septic tank. The temporary housing for this workforce shall be within the plot and no hutments shall be allowed outside. The workforce shall also be provided with kerosene to use stoves for cooking and burning of wood shall not be allowed.

2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal)

Reply: About728 KL/day of sewage shall be generated that shall be treated to BOD < 5 mg/l in a sewage treatment plant of capacity 1 MLD. An STP based on SBR technology shall be provided. The water being discharged will be tertiary treated and shall not add to any pollutant load.

2.14 Give details of dual plumbing system if treated waste used is used for flushing of toilets or any other use

Reply: Dual plumbing system shall be provided for recycling of treated waste water for flushing. See Drawing: 9.

Page 27: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

25

3. VEGETATION 3.1 Is there any threat of the project to the biodiversity? (Give a description of the

local ecosystem with it’s unique features, if any)

Reply: No. 3.2 Will the construction involve extensive clearing or modification of vegetation?

(Provide a detailed account of the trees & vegetation affected by the project)

Reply: No. 3.3 What are the measures proposed to be taken to minimize the likely impacts on

important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale

Reply: See Drawing-11 for Landscape Plan

4. FAUNA 4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or

creation of barriers for their movement? Provide the details.

Reply: No 4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

Reply: No 4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse

impacts on fauna

Reply: Not Applicable

Page 28: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

26

5. AIR ENVIRONMENT 5.1 Will the project increase atmospheric concentration of gases & result in heat

islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions)

Reply: No. The proposed project does not have any permanent operating source of fossil fuel burning as Boiler or Furnace being a commercial colony project. The generators to be provided shall only act as standby and shall comply by standards as laid down in MoEF Notifications GSR 371E and GSR 520 E for compliance at manufacturing stage for noise and emission levels. The Project only involves construction of residential colony. The design population is5608 . This will also have a gestation period of 2-3 years. Thus the project shall not alter the traffic composition to an extent to cause a measurable impact.

5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters.

Reply: There shall not be generation of hazardous gases or odorous fumes. The dust generation during the construction activity shall be controlled as given in EMP.

5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

Reply: The project shall have adequate space for parking. Parking plan is attached at Drawing:10.

5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category.

Reply: See Drawing:10 for traffic movement. 5.5 Will there be significant increase in traffic noise & vibrations? Give details of

the sources and the measures proposed for mitigation of the above.

Reply: See 5.3, Green Belt shall be provided to mitigate noise pollution from road traffic.

5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details.

Reply: See Clause-6 of Section-II of Form-1.

Page 29: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

27

6. AESTHETICS 6.1 Will the proposed constructions in any way result in the obstruction of a view,

scenic amenity or landscapes? Are these considerations taken into account by the proponents?

Reply: No

6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?

Reply: No

6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out.

Reply: The architecture shall suit the local development.

6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.

Reply: No

7. SOCIO-ECONOMIC ASPECTS 7.1 Will the proposal result in any changes to the demographic structure of local

population? Provide the details. Reply: The project is of small nature with a population of 5605 persons. No significant

impact shall be there on demographic structure. 7.2 Give details of the existing social infrastructure around the proposed project.

Reply: See Annexure-11A for Demographic details

7.3 Will the project cause adverse effects on local communities, disturbance to

sacred sites or other cultural values? What are the safeguards proposed? Reply: No

Page 30: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

28

8. BUILDING MATERIALS 8.1 May involve the use of building materials with high-embodied energy. Are the

construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency)

Reply: The proposed construction shall involve use of concrete and brick using PPC cement, which is fly ash, based. All interior partitions shall be made on half brick wall to save quantum of bricks and to reduce structural load and thus less consumption of steel. The wood shall be replaced with MDF wherever possible. In concrete work admixtures shall be used to reduce water cement ratio, which saves both cement and water.

8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?

Reply: See clause-5.4/5.5 of section-II of Form-1. 8.3 Are recycled materials used in roads and structures? State the extent of savings

achieved? Reply: The construction debris shall be used in building the road and floors. 8.4 Give details of the methods of collection, segregation & disposal of the garbage

generated during the operation phases of the project Reply: See Clause 4.2 of Section-II of Form-1. 9. ENERGY CONSERVATION 9.1 Give details of the power requirements, source of supply, backup source etc.

What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption?

Reply: Total Energy requirements of 6063 KW to be provided by State Electricity Board. ____ generators of 650 KVA and 1 Generator of 1010 KVA capacity shall be provided for Standby power to run lifts and other emergency uses. Use of energy efficient devices like light sources such as LED . Solar water heater and Solar panel will be provided . the details on solar architectural feature is attached at Annexure-10A and Drawing showing Solar pathway is attached at D-15.

9.2 What type of, and capacity of, power back-up to you plan to provide? Reply: The back-up source is __ generators of 625 KVA and __ Generator of 1010

KVA capacity with inbuilt acoustic enclosure will be installed see 9.1, Form 1A.

9.3 What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation

Reply: Details given in Annexure-10B. 9.4 What passive solar architectural features are being used in the building?

Illustrate the applications made in the proposed project. Reply: Solar Architectural features are considered in the design of Building, See

Annexure-10A.. The Drawing showing Solar pathway is attached at D-14 . 9.5 Does the layout of streets & buildings maximize the potential for solar energy

devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.

Page 31: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

29

Reply: Solar mix street light shall be used for street lighting 9.6 Is shading effectively used to reduce cooling/heating loads? What principles

have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

Reply: West area is the hottest area according to the sun movement in the afternoon keeping this in the mind less openings are proposed in this area for saving the electricity in the terms of lighting and at the roof brick bet-coba has to be provided which acts as a thermal insulation.

9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications.

Reply: Transformer of 90% efficiency will be used. No central Air Conditioning proposed.

9.8 What are the likely effects of the building activity in altering the micro-climates? Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?

Reply: This Project is going to be a Eco Friendly residential colony. The project is designed as a low density project. The green belt plan shall ensure that trees and shrubs of different varieties and sizes are planted. This will cut-off any local heat island generation or inversion effects and provide dilution effect.

9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R values of the individual components.

Reply: Details given in Annexure-10B. 9.10 What precautions & safety measures are proposed against fire hazards? Furnish

details of emergency plans. Reply: The Drawing showing fire fighting plan is attached at D-12. 9.11 If you are using glass as wall material provides details and specifications

including emissivity and thermal characteristics. Reply: No glass is provided as wall material.

9.12 What is the rate of air infiltration into the building? Provide details of how you

are mitigating the effects of infiltration

Reply: Not Applicable

9.13 To what extent the non-conventional energy technologies are utilized in the overall energy consumption? Provide details of the renewable energy technologies used.

Reply: Solar mix street light shall be used for street lighting, solar water heaster and solar panel will be used.

Page 32: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

30

10. Environment Management Plan(Conceptual Plan) Reply: The Conceptual Plan cum Environment Management Plan consists of all

mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire. The Conceptual Plan is enclosed along.

Page 33: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

31

CONCEPTUAL PLAN

1. INTRODUCTION________________________________________ “The Melia ” is a residential colony project proposed at Village Mohammadpur Gujar , Sector 35 of Sohna, Dist. Gurgaon The total plot area of the project is 17.41 acres with built-up area 167805.04 Sq.m. The specific measures that shall be put to practice to minimize the impact on the environment are discussed below: 2. MITIGATING IMPACTS ON AIR ENVIRONMENT_________ Construction phase

The construction shall be completed within 5 years using PERT and CPM techniques. No construction will be done at night.

All excavation work shall be done mechanically in minimum time to reduce dust

generation. There shall be provision of sprinklers so as to suppress the fugitive emission of dust. Also the nuisance dust generated due to wind at construction site will be taken care of by immediate removal and recycling of the debris and unutilized construction material and earth.

The vehicles employed by the developers shall be checked for vehicular

emissions and PUC certificates. The developers shall also impress upon the service agencies to get vehicles regularly checked for vehicular emission.

The mitigation measures shall include regular maintenance of machinery and

provision of personnel protective equipments to workers where needed.

The steps shall be taken to reduce the impact of noise by taking to plantations from the very beginning. Construction Activities shall not be carried out at night.

The work shall be undertaken in phases over specific areas so that effective

material management is possible. Operation phase

A sewage treatment plant of 1 KLD based on SBR technology is proposed , thus there are no chances of odour pollution from the untreated domestic sewage from the project. Extensive plantation is planned to mitigate the impact of noise and to improve the ambient air in general.

The standby generators shall be installed with enclosures as per guidelines of

Central pollution Control Board and after taking consent from State Pollution Control Board under Air (Prevention and Control of Pollution) Act, 1981. The

Page 34: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

32

generators installed shall comply with emission limits as given in G.S.R. 520 (E), Environment (Protection) Amendment Rules 2003 at the manufacturing stage itself. The DG sets shall further be procured from agencies complying the noise emission standards at the manufacturing stage itself as per G.S.R. 371(E), the Environment (Protection) second Amendment Rules, 2002. These Rules say that the maximum permissible sound pressure level for new diesel generator (DG) sets with rated capacity up to 1000 KVA, manufactured on or after the 1st July, 2003 shall be 75 dB(A) at 1 meter from the enclosure surface. The diesel generator sets should be provided with integral acoustic enclosure at the manufacturing stage itself. Installation of a DG set shall be strictly in compliance with the recommendations of the DG set manufacturer. A proper routine and preventive maintenance procedure for the DG set should be set and followed in consultation with the DG set manufacturer which would help prevent noise levels of the DG set from deteriorating with use. The DG Set area shall also be attenuated using green belt as laid down in Environment Management Plan. Extensive plantation is planned to mitigate the impact of noise and to improve the ambient air in general.

Any residential area once occupied is also expected to bring vehicular traffic. Due consideration has been given to traffic management. The layout of the project is so done that traffic congestion is not there. A wide road shall run around all the blocks along the boundary with unidirectional entry and exit.

About 220 Kg/day of solid waste shall be generated from the proposed residential project. The solid waste area shall be further attenuated using green belt.

Sludge generated from the STP shall be used as manure for the green belt. The

solid waste shall be duly segregated into biodegradable, non-biodegradable and recyclable components. The recyclable components shall be sold to resellers for re-use. The biodegradable component shall be converted into compost using mechanical composter. The inert waste left will be dumped to authorized dumping site.

Page 35: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

33

3. MITIGATING IMPACTS ON WATER ENVIRONMENT______

Construction phase

As mentioned above the construction related solid waste as malba, loose soil etc. will be removed immediately thus controlling run-off during development/construction phase.

The land clearing activity shall be kept to the absolute minimum by working at the specific sites one by one where construction is to take place.

During Construction a Water demand of 273 KLD may be there depending upon phases of construction. This will include domestic demand for @150workers during peak period i.e. 7 KL/d (@ 45 lpcd).

There shall be no discharge as such from the water used for construction, as it will be consumed in the process. There shall thus be no impact on ground or surface water resources.

The surface water environment can be slightly affected if run-off over excavated material or construction material dumps during monsoons carries the materials along with. The excavation and other construction debris as construction material shall be kept in identified areas and used within the project so that it is not carried along with run-off. The site further does not interfere/ obstructs any natural drain.

A toilet facility for workers shall be provided at site and the same shall be connected to mobile STP or septic tank. Workers shall be discouraged from open defecation.

Operation phase

The rainwater harvesting shall be undertaken from rooftop area.

The total design population of the project shall be 5605 persons.

The total water demand is 910 KLD For a population of 5605 for the residential colony . The water demand shall be met through HUDA water supply.

Provision of a STP of 1 MLD based SBR technology shall be provided with

tertiary level of treatment i.e BOD < 5 mg/l and after disinfection to recycle the sewage for gardening and use in toilets for flushing as per water balance diagram. The remaining treated sewage shall be discharged into sewer line

Page 36: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

34

4. MITIGATING IMPACTS ON LAND ENVIRONMENT________ Construction phase

To avoid erosion of the top soil the development is planned in the shortest possible time and land-clearing activity shall be kept to the absolute minimum by working at the specific sites one by one where construction is to take place so as to increase detention and infiltration. These conditions shall be made a part of contract agreement.

The activities that result in soil being laid bare shall be scheduled in such a way

that some type of vegetative cover appropriate to the site shall be established prior to onset of monsoons.

The solid waste generated from the construction activities shall be effectively

recycled within the project.

The requirements of sand and aggregates for the construction works are met from authorized sources. The fly ash based cement shall be used for the purpose.

For the construction works the use of wood shall not be allowed (Timber Free

Construction) and all shuttering shall be of mild steel. The use of MDB, Mild Steel, Aluminium, Glass and Plastic shall be undertaken to the extent possible to reduce the use of wood.

The land use as proposed shall not be altered.

Operation phase

A storm water network and sewer system is designed for the project. There is no vegetation to remove. The land is earmarked for residential use and the development is proposed as per land use, thus there are minimum chances of effect on land environment; however, following points shall be taken care:

The landscaping shall be undertaken to aid the natural drainage.

About 2202 Kg/day of solid waste shall be generated from the proposed project

that shall be adequately handled. Thus there are no chances of solid waste interfering with land environment.

Page 37: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

35

5. ENERGY MANAGEMENT_____________________________

The land use is so planned that there is minimum adverse impact and maximum use of principles of eco design. A fundamental principle of solar design is to maximize the solar gain in the winter and minimize it in the summer and is used to the extent possible practically. The layout and green belt is planned taking care of principles of eco-design. Only surfaces facing South receive sun all year round. The dominant direction of the sun is from South, especially in winter. Building is oriented for optimum solar heat gain and reduce energy consumption.

Paved areas are kept to minimum thereby avoiding heat islands on site and

reducing temperatures. 6. LIGHTS_______________________________________________

An energy-efficient lighting system shall be provided to include the following:

More light is not necessarily better. Human visual performance depends on light quality as well as quantity, Match the amount and quality of light to the performed function, Install task lights where needed and reduce ambient light elsewhere, Use energy-efficient light components and systems, Maximize the use of day-lighting

Fluorescent Light Fixtures shall be installed for all ceiling and wall-mounted

fixtures that will be on for more than 2 hours each day.

LED shall be used, rather than CFL in incandescent fixtures, so that fluorescent bulbs continue to be used for the life of the house.

Light wall colors shall be used to minimize the need for artificial lighting.

Outdoor lighting generally serves one or a combination of three main purposes:

Aesthetic: illuminate the exterior of the building and landscape, Security: illuminate the grounds near the building or driveway, Utility: illuminate the porch and driveway to help people navigate safely to and from the building.

Energy-efficient outdoor lighting shall be achieved through:

Low-pressure sodium vapour lamps which provide the most energy-efficient

outdoor lighting shall be used along the road and security lighting. It shall be ensured that outdoor light fixtures have reflectors, deflectors, or covers to make more efficient use of the light source.

Page 38: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

36

7. EMERGENCY PLAN_________________________________

Since the projects may face fire hazards or other emergency situations an

emergency plan is provided to caution the people during any accidents. The fundamental approach, governing fire safety attempts to ensure that fires do not at all start in the first place and if they occur, to restrain their spread by quick detection and extinguishments.

Fire detection: Despite the many precautions taken, fires may breakout. Hence

the residential colony should have established measures to detect a fire and to extinguish it. Automatic fire detection has many advantages such as speed and reliability and is recommended.

Depending on the nature of the occupancy and the hazard, a variety of detection

systems are available. They are activated by one of the effects of fire such as temperature rise, smoke, flame or heat and can be coupled to an alarm system which would provide visual/ audible alarms at designed manned locations. They can also be designed to automatically activate fire-extinguishing systems. The selection/ installation of the detection system should conform to the applicable national standards.

Extinguishing system: Equipment for the fighting should be chosen with care

and suited to the task. Fires are classified depending on the materials involved and appropriate extinguishing agents are also recommended. Table-I gives the classification/ recommendation as per Indian Standard IS-2490. The extinguishing agents mentioned are applied to the fire using portable or fixed appliances. To fight fires at their incipient stage, portable extinguishers prove very useful. These must be provided in adequate numbers at appropriate locations and people pshould be thoroughly trained in their use.

Page 39: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

37

Table-I: Fires - Classification & Extinguishing Media Class of tire Description Extinguishing

medium Indian Standard

A Fires involving ordinary combustible materials, like woods, paper textiles, etc. where the cooling effect of water is essential for the extinction of fire.

Water 934 940 6234

B Fire in flammable liquids like oils, solvents, petroleum products, varnishes, pains etc. where a blanketing effects is essential

Foam Carbon dioxide Dry chemical

933 2878 2171 4308

C Fires involving gaseous substances under pressure where it is necessary to dilute the burning gas at a very fast ate with an inert gas or powder.

Carbon dioxide Dry Chemical powder The best way to extinguish such fires is by stopping the flow of fuel gas to the fire. Container is kept cool with water spray

2878 2171, 4308

D Fires involving metals like magnesium, aluminium, zinc, potassium, etc. where the burning metal is reactive to water and which requires special extinguishing media or technique.

Special dry powders 2171 4861

Page 40: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

38

The task of accident and emergency control can be simplified and made effective if pre-planned systems and procedures are available. Without these, important matters may be overlooked at the time of an emergency

Every management must survey the total operation to identify potential for fire losses and develop an action plan to put the business back to normal with minimum loss of time. A fire protection Manual should be prepared, preferably in 3-parts. The first part should outline the fire risks in terms of locations, equipment and facilities and indicate the ways in which risks have been minimized. The second part would set out operating procedures, standards of fire protection established, and maintenances of these standards action to betaken in the event of fire by every level of management responsibility for inspection and repair. It should also include instructions for staff responsible for building services. The third part should outline the training required for existing and new staff, the inspection schedules and check lists, sources of additional information and help.

The Management Cell of the project shall keep ready a plan to alert and take care of residents in case there is any fire. There shall be designated an Emergency Team that shall consist of staff of maintenance department, security supervisor representative of promoter.

During non-emergencies this team shall engage in activities as (1) Earmarking Area for Assembling during Emergencies (2) Awareness programme for the on fire, first aid and evacuation (3) Identification of Hospitals (4) Identification and Displaying Emergency Numbers and Contacts (5) Displaying Emergency Symbols (6) Updating First Aid Emergency Kit (7) Updating Fire Control Systems (8) Preparation and Updating of Standard Operating procedures (SOP)

In case member on duty spots the emergency like comes to know about any fire he will also try his best to find out about the exact location and nature of emergency. In accordance with the SOP the following activities will immediately begin (1) People will be informed, necessary Alarms shall be activated to direct the people to the emergency assembly area if needed (2) The external network of District Fire Station, Police and Hospital shall be intimated. Once the emergency situation is under control, the team will initiate step-by-step restoration of normal operation.

Page 41: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

39

8. ENVIRONMENT MONITORING PROGRAMME___________

Regular monitoring of all significant environmental parameters is essential to

check the compliance status vis-à-vis the environmental laws and regulation. The objectives of the monitoring will be as follows:

a. To verify the results of the impact assessment study with respect to the proposed

projects. b. To study the trend of concentrated values of the parameters, which have been

identified as critical and then planning the mitigating measures. c. To check and assess the efficacy of pollution control equipment. d. To ensure that any additional parameters, other than those identified in the impact,

do not turn critical after the commissioning of proposed project.

To implement the EMP, a structured Environment Management Cell (EMC) interwoven with the existing management system will be created. EMC will undertake regular monitoring of the environment and conduct yearly audit of the environmental performance during the construction of the project. It will also check that the stipulated measures are being satisfactorily implemented and operated. It shall also co-ordinate with local authorities to see that all environmental measures are well coordinated. A comprehensive environmental monitoring program as laid down by State Pollution Control Board shall be followed.

All the above observations will be complied and documented by the EMC to

serve the following purposes. a. Identification of any environmental problems that are occurring in the area. b. Initiating or providing solution to those problems through designed channels and

verification of the implementation status. c. Controlling activities inside the project, until the environmental problem has been

corrected. d. Suitably responding to emergency situations.

9. ENVIRONMENT MANAGEMENT CELL The Environment Management Cell shall include:

a. Representative of Management b. Representative of Project Management Consultants c. Process In-charge from STP/SWM and Water Works d. In-charge Maintenance Department e. A representative of Environmental Consultants f. A representative of local authority

Page 42: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

40

10. GREEN BELT_________________________________________

The landscaping and green belt will be designed and trees will be planted in open areas, around plot boundary along footpaths and dividers. Standard practice will be followed for planting of saplings in pits of substantial dimensions, 1m x 1m x 1m for big trees and almost half of these dimensions for smaller trees and shrubs. The pits shall then be filled with earth, sand, silt and manure in predetermined proportions. Saplings planted in the pits will be watered liberally. The growing plants will be cared for the first five years under favorable conditions of climate and drainage. Care will be taken for nutrient supplement (healthy growth), plant protection, absence of water stress (to maintain openness of stomata apertures and epidermal structures) and exposure to normal atmospheric conditions (free air flow). The guidelines as laid out in National Building Code of India shall be followed in the overall development of Green Belt. The plants shall be selected out of plants given in plant species guidelines by CPCB.

11. COST OF ENVIRONMENT PROTECTION_______________

The implementation of the pollution control and environmental monitoring and management programmes is the basis of mitigation of impacts. The development is essential for economic growth but at the same time the environment is to be preserved for future generations. The environmental expenditures show commitment of the management on environmental front. Details Capital Rs. Lac Operation Rs. Lac Sewage Treatment Plant: 200 10 Air & Noise Pollution Management:

12 2

Landscaping: 10 1 Rainwater harvesting: 15 1 Environmental Monitoring: 2 1 Waste Management: 10 1 Solar lighting: 20 1 TOTAL: 269 lac 19 Lac

Page 43: Application for Environmental Clearanceenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015-05-31 · Sohna, District Gurgaon Project by M/s DSS Buildtech Pvt. Ltd

41

12. CORPORATE SOCIAL RESPONSIBILITY (CSR)____

We will provide 1% of total project cost i.e. 4.3 crore for CSR which will be implemented in 5 years

Further, Mr. Pardeep Jain, Director, will be responsible for implementation of EMP (Environment Management plan) / CSR (Corporate Social Responsibility).

13. COMPLIANCE TO ENVIRONMENTAL LEGISLATIONS

All applicable environmental laws/legislation will be complied with including: 1. Compliance of conditions stipulated in NOC granted by HSPCB under Water and Air Act. 2. Compliance of environmental clearance as granted by SEIAA, Haryana. 3. Compliance of conditions imposed in consent to operate under Water & Air act . 4. The project proponent will abide by all other applicable rules/regulations as and when amended from time to time.