INSTRUCTIONS FOR COMPLETING PRIVATE RECREATIONAL DOCK

PROGRAMMATIC GENERAL PERMIT (PGP0083) APPLICATION TO THE

GADNR COASTAL RESOURCES DIVISION

Use the checklist below to ensure you have submitted all of the required documents to complete your

application. Your Project Manager may request additional supporting information to help with the

processing of your application.

Dock Application Checklist

____ Programmatic General Permit (PGP) Application (2 pages) - This application is intended for

private residential, single-family, shared-family, noncommercial, recreational docks in Chatham,

Bryan, Liberty, McIntosh, Glynn, Camden, Long, Effingham, Wayne, Brantley, and Charlton

Counties. (All owners listed on the Deed of the property must sign the application)

____ Revocable License (RL) Request (1 page) - Please ensure that all of the requested information

at the top of the sheet is provided. (All owners listed on the Deed of the property must sign the

RL)

____ Adjacent Owner Notification Sheets - (1 page for each adjacent owner)

a) Applicant can submit sheets signed by both upstream and downstream property owners.

OR-

b) Applicant can submit Certified Mail (date stamped) receipts which were addressed to

upstream and downstream property owners.

OR-

c) Adjacent owners may submit their comments directly to your Project Manager.

____ Copy of the Warranty Deed and referenced Plat of the subject parcel. (the applicant must be

the current owner)

____ Drawing/Plans of the Proposed Dock - At least one clean, legible drawing on an 8 1/2”x 11”

sheet to include:

a) Dimensions for each component (i.e. walkway, fixed deck, float, ramp, hoist, catwalk, etc.) If

permit is being modified and components are being added, please indicate on the drawing

which components exist and which components are proposed. Please do not highlight or

color code. The drawing must indicate the exact configuration of the existing and proposed

structure components.

b) Waterway width at Mean Low Water (MLW). Indicate grass to grass or bank to bank

measurement if channel is dry or mostly dry at MLW.

c) Extent of dock into the channel from the MLW line.

d) Distance from each side of dock at the terminal end to extended property lines.

e) Any specific characteristic of the site should be identified with the proposed structure in place

(i.e. a bend in the channel, a tidal creek or slough in proximity of the proposed structure, and

dock corridors that have been approved by the GADNR)

f) When using previously submitted drawings or drawings from other sources, please ensure

that all information matches the request. (Professional drawings may be required

depending on the proposed structure)

PGP Application Instructions

Page 2 of 2

To fit within the Programmatic General Permit (PGP) size restrictions, your dock structure proposal must

adhere to the following:

____ Walkway is 6 ft. wide or less measured from outer handrail, with a max length of 1,000 ft., and

max area of 3,000 sq. ft. Any bracing or support structures must be clearly indicated on the

drawing.

____ Fixed deck is 300 sq. ft. or less. This includes landings for the sole purpose of accessing

the float. Please indicate if covered and give roof dimensions.

____ Floating dock is 600 sq. ft. or less for a single-family structure and 1,000 sq. ft. or less for a

shared-family structure. This includes all run-up, modular, and jet-ski floats.

____ Single boat hoist no larger than 16 ft. x 30 ft. measured from pilings. Please indicate if

covered and give roof dimensions.

____ Single catwalk, whose sole purpose is to service a boat hoist max is 3 ft. x 30 ft.

____ Dock extends less than 40’ or ¼ the channel measured at MLW, whichever is less.

If your dock structure does not fit within these restrictions and/or you are located on the Intra- Coastal

Waterway (ICW), you must submit an Individual Permit (IP) application in lieu of the PGP application as

well as all of the other previously listed required application documents to this Department and to the

U.S. Army Corps of Engineers. Applicants that do not wish or are not able to, adhere to the above

dimension restrictions will be required to provide justification as to why the restriction cannot be met.

Requests to exceed the PGP restrictions will be approved or denied on a case-by-case basis.

All documents must be submitted to the Permit Coordinator for your county before your application can

proceed through the process. The application is considered incomplete if all of the required documents

have not been submitted. If the requested information for your incomplete application is not received

within 90 days after the initial submittal, your application will be withdrawn unless other arrangements

have been made with your Project Manager. Within 10 days post-construction, you must complete and

submit a Construction Notification Form to your Project Manager.

Please mail all required dock application materials to:

PGP Dock Permit Coordinator

County of Proposed Dock:______________

Georgia Department of Natural Resources

Coastal Resources Division

One Conservation Way

Brunswick, GA 31520

For general questions about dock permits, the status of a pending application, see our web page at

http://coastalgadnr.org or call (912) 264-7218 to speak with the Permit Coordinator for your county.

STATE OF GEORGIA

REQUEST FOR A REVOCABLE LICENSE FOR THE USE OF TIDAL WATERBOTTOMS APPLICANT NAME(S): MAILING ADDRESS: (Street) (City) (State) (Zip) PROJECT ADDRESS/LOCATION: COUNTY: WATERWAY: LOT, BLOCK & SUBDIVISION NAME FROM DEED:

Georgia Department of Natural Resources Coastal Resources Division One Conservation Way Brunswick, Georgia 31520-8687

I am requesting that I be granted a revocable license from the State of Georgia to encroach on the beds of tidewaters, which are state owned property. Attached hereto and made a part of this request is a copy of the plans and description of the project that will be the subject of such a license. I certify that all information submitted is true and correct to the best of my knowledge and understand that willful misrepresentation or falsification is punishable by law.

I understand that if permission from the State is granted, it will be a revocable license and

will not constitute a license coupled with an interest. I acknowledge that this revocable license does not resolve any actual or potential disputes regarding the ownership of, or rights in, or over the property upon which the subject project is proposed, and shall not be construed as recognizing or denying any such rights or interests. I acknowledge that such a license would relate only to the property interests of the State and would not obviate the necessity of obtaining any other State license, permit, or authorization required by State law. I recognize that I waive my right of expectation of privacy and I do not have the permission of the State of Georgia to proceed with such project until the Commissioner of DNR or his/her designee has executed a revocable license in accordance with this request.

Sincerely, By: ______________________________________ Date: _________________________ Signature of Applicant

___________________________________ Title, if applicable

By: ______________________________________ Date: _________________________

Signature of Applicant

___________________________________ Title, if applicable

Attachments