35
May 2019 18101804-324364-3 / FS 30/5/1/2/3/2/1 (10050) EM APPENDIX S Closure Plan and Rehabilitation Assessment

APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

May 2019 18101804-324364-3 / FS 30/5/1/2/3/2/1 (10050) EM

APPENDIX S

Closure Plan and Rehabilitation Assessment

Page 2: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

REPORT

Preliminary closure cost determination for the

proposed Metsimaholo underground operation Seriti Coal (Pty) Ltd

Submitted to:

Seriti Coal (Pty) Ltd New Vaal Colliery

Heilbron Road

Viljoensdrift

1935

Submitted by:

Golder Associates Africa (Pty) Ltd.

Podium at Menlyn, Second Floor, 43 Ingersol Road, Menlyn, Pretoria, 0181, South Africa

P O Box 6001, Halfway House, 1685

+27 11 254 4800

18101804-321416-1

October 2018

Page 3: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

i

Distribution List 1 x electronic copy Seriti Coal (Pty) Ltd

1 x [email protected]

Page 4: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

ii

Table of Contents

1.0 INTRODUCTION ......................................................................................................................................... 4

1.1 Background information .................................................................................................................... 4

1.2 Mine contact details .......................................................................................................................... 5

1.3 Closure assessment practitioner ....................................................................................................... 5

2.0 MINE SITE CONTEXT ................................................................................................................................ 6

2.1 Locality .............................................................................................................................................. 6

2.2 Legal status ....................................................................................................................................... 6

2.3 Life of mine ........................................................................................................................................ 6

2.4 Mining reserves ................................................................................................................................. 7

2.5 Mining operations .............................................................................................................................. 7

2.6 Battery limits ...................................................................................................................................... 8

3.0 APPROACH AND METHODOLOGY ....................................................................................................... 11

4.0 KEY ASPECTS AND ASSUMPTIONS ..................................................................................................... 14

4.1 General ............................................................................................................................................ 14

4.2 Infrastructural aspects ..................................................................................................................... 14

4.3 Mining aspects ................................................................................................................................ 15

4.4 General surface rehabilitation ......................................................................................................... 15

4.5 Post-closure aspects ....................................................................................................................... 15

4.6 Preliminaries and general, contingencies and additional allowances ............................................. 16

5.0 CLOSURE COSTS, AS AT SEPTEMBER 2018 ...................................................................................... 16

6.0 CONCLUSION .......................................................................................................................................... 17

TABLES

Table 1: Contact details of Seriti Coal (Pty) Ltd ................................................................................................... 5

Table 2: Contact details for Closure Assessment Practitioners ........................................................................... 5

Table 3: Details of specialists ............................................................................................................................... 5

Table 4: Metsimaholo preliminary closure cost battery limits ............................................................................... 9

Table 5: Battery limits: shaft infrastructure, measurements and assumptions ................................................... 12

Table 6: Scheduled closure costs for the proposed Metsimaholo shaft complex .............................................. 17

Page 5: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

iii

FIGURES

Figure 1: Locality map and mining rights boundary .............................................................................................. 6

Figure 2: Top seam (“TMH”) mine design map .................................................................................................... 7

Figure 3: Middle seam (“MLMH”) mine design map ............................................................................................. 8

Figure 4: Planned infrastructure general arrangement plan for the proposed Metsimaholo shaft complex ...... 10

APPENDICES

APPENDIX A Document Limitations

APPENDIX B Curricula Vitae

Page 6: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

4

1.0 INTRODUCTION

Seriti Coal (Pty) Ltd (Seriti) acquired the remaining Metsimaholo reserves as part of a purchase agreement

that involved Seriti taking ownership of several Anglo-American Thermal Coal (AATC) mines supplying

thermal coal to Eskom. Seriti plans to access the remaining reserves through the development of Metsimaholo

Colliery. Golder Associates (Golder) is currently engaged in a process to compile and submit the following:

Application to graduate the prospecting rights (FS30/5/1/1/2/10383PR and FS30/5/1/1/2/10292PR) into a

consolidated Mining Right (MR) to the Department of Mineral Resources (DMR) in terms of the Mineral

and Petroleum Resources Development Act No. 28 2002 (MPRDA); and

An Environmental Impact Assessment (EIA) in support of an application for environmental authorisation

to the Department of Environmental Affairs (DEA) in terms of the National Environmental Management

Act, No. 107 of 1998 (NEMA).

As part of the package of work, Golder was appointed to compile the preliminary closure costs for the

proposed project. The closure costs are, as far as possible, aligned to the National Environmental

Management Act, 1998: GN R.1147 (Regulations Pertaining to the Financial Provision for Prospecting,

Exploration, Mining or Production Operations). Furthermore, it is noted that the proposed amendments to the

financial provisioning regulations for mines have been published for public comment. Cognisance was taken

of these proposed amendments, to ensure that these can be incorporated into the 2019 closure costs update

ensuring a stepped approach to compliance once the new Regulations are promulgated. Indications are that

mines will have to be compliant by February 2020.

1.1 Background information

The closure costing is based on the available information as at 30 September 2018 and will require annual

updates as per GN R.1147 or as required by amended financial regulations promulgated in future. The annual

updates should also incorporate the outcomes of the specialist studies to improve the resolution of the closure

cost determination. The following information was provided for this closure cost assessment:

Locality plan indicating the locality and extent of the prospecting right and boundary within which the

shaft complex will be established (Figure 1);

Initial mine design planning by Ukwazi (Pty) Ltd (Ukwazi) indicated in Figure 2 and Figure 3 (Ukwazi

2018);

A general arrangement drawing of the proposed shaft and the related infrastructure (Figure 4; Ukwazi

2018);

Draft scoping report (Golder, 2018); and

Correspondence with Ukwazi regarding the type of infrastructure to be established on site to inform the

demolition costing components (Table 5).

Page 7: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

5

1.2 Mine contact details Table 1: Contact details of Seriti Coal (Pty) Ltd

Name of company Seriti Coal (Pty) Ltd

Name of project Preliminary closure cost determination for Metsimaholo

Postal address 1st floor, 3 on Glenhove, crn Glenhove and Tottenham roads,

Johannesburg 2196

E-mail address [email protected]

Telephone number (011) 047 7025

1.3 Closure assessment practitioner

This closure costing was compiled by Golder, under the technical lead of Anthony Lamb. Contact details are

provided below.

Table 2: Contact details for Closure Assessment Practitioners

Name of company Golder Associates Africa (Pty) Ltd

Name of Mine The proposed Metsimaholo Colliery

Name of project Preliminary closure cost determination for Metsimaholo

Postal address Podium at Menlyn, 43 Ingersol Road Menlyn, Pretoria 0181

Telephone number +27 (0) 11 254 4839

The core specialists who contributed to the closure planning process, and their relevant professional

registrations and experience, are listed in Table 3. Curriculum Vitae for the specialist team are provided in

APPENDIX B.

Table 3: Details of specialists

Specialist Task Professional registrations/experience

Tashriq Naicker Project manager BSc Hons (Environmental geology),

10 years’ experience

Anthony Lamb Closure costing BSc Hons (Environmental management),

21 years’ experience

Johan Bothma Project reviewer PrLArch (SACLAP), BL, ML

14 years’ experience

Page 8: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

6

2.0 MINE SITE CONTEXT

The following information is based on the Draft Scoping Report (Golder 2018) and the various planning maps

provided by Ukwazi (2018).

2.1 Locality

The project area is situated within the Metsimaholo Local Municipality, in the magisterial district of Sasolburg,

in the northern part of the Free State Province in South Africa. The nearest towns are Refengkgotso, which

straddles the northeast corner of the project area, and Deneysville which lies a further 3 km to the east as

shown in Figure 1. The area is gently undulating at 1 525 metres above mean sea level. The perennial

Taaibosspruit River meanders from south to north, through the western side of the project area. The Vaal

Dam, in part, forms the eastern edge of the project. Grazing dominates agriculture with limited areas of dry

land farming, predominantly maize. The climate is typical of the Northern Free State with warm to hot and wet

summers and cool to cold, dry winters.

Figure 1: Locality map and mining rights boundary

2.2 Legal status

Seriti Coal currently holds the prospecting mining/exploring coal rights (FS30/5/1/1/2/10383PR and

FS30/5/1/1/2/10292PR) for the Metsimaholo area which covers approximately 34 378 ha, which they propose

to graduate into a mining right. The proposed site was awarded a prospecting mining right in 2008 which was

renewed till 12 November 2018 for the primary purpose of exploring coal.

2.3 Life of mine

The Metsimaholo project pre-construction and construction phase is planned to commence in 2023. It is

expected that the construction period for the Metsimaholo project would last approximately 12 months. Mine

establishment and access development are scheduled to commence in quarter 3 of 2023. The access

Page 9: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

7

development is anticipated to take an additional 12 months. The project is planned to begin its operational

phase and commence initial production in 2025, depleting in 2055.

2.4 Mining reserves

Based on preliminary studies surrounding the Metsimaholo remaining reserves, there is potential for a 30-year

life-of-mine (LoM), until 2055. The mine is envisaged to deliver an average of 2.8 to 3.0 million tonnes per

annum of coal at steady state production. The total saleable product is estimated at approximately 80 million

tons over the LoM with an average calorific value of 19 megajoules per kilogram.

2.5 Mining operations

Metsimaholo colliery is proposed to be an independent underground mine producing thermal coal from one

operational decline shaft. The Metsimaholo coal resource (top and middle seams) will be mined by

underground methods. Conventional bord and pillar mining techniques with Continuous Miners (CM) are

selected as the primary coal extraction method. Access to the orebody is planned through a box-cut

development, with a twin decline shaft system to intersect the top seam (“TMH”) floor as shown in Figure 2

and the middle seam (“MLMH”) floor as shown in Figure 3 from which the shaft bottom development and main

primary development would be initiated. MLMH will be accessed from underground via a developed decline.

Figure 2: Top seam (“TMH”) mine design map

Page 10: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

8

Figure 3: Middle seam (“MLMH”) mine design map

In bord and pillar mining, parallel roads ways are developed in the mining direction. Perpendicular roads,

called splits, are developed at predetermined intervals to the parallel roads. These roads interlink, creating

pillars. The roads that are mined concurrently are determined by the size of the pillars required to support the

overburden above the coal seam and the length of the production equipment’s trailing cables. The road widths

would be designed at 7.2 m wide with an average mining height of 3 m. The pillar size is determined by the

safety factor formula that result in the pillar strength divided by the pillar load. The main access development

and production sections will be planned from the decline shaft floor consisting of either seven or nine road

development which constitutes a mining panel.

2.6 Battery limits

The planned infrastructure for the proposed Metsimaholo shaft complex is indicated in Figure 4. The itemised

infrastructure and mining components are summarised in Table 4 and constitute the battery limits for this

closure cost determination.

Page 11: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

9

Table 4: Metsimaholo preliminary closure cost battery limits

Map No. Inventory item Map No. Inventory item

1 Mine Offices 15 Incline Shaft

2 Change House & Laundry 16 Surge Silo and Conveyor belt

3 Stores 17 Lamp Room

4 Workshops 18 Stormwater Cut-off Drain

5 Security 19 Substations

6 Bus Shelter 20 Waste/overburden Stockpile

7 Shaft Offices 21 Bulk/Raw Water Storage

8 Parking 22 Fire Water Storage

9 Pollution Control Dam 23 Fence

10 Main Access Road (Surfaced) 24 Topsoil Stockpile

11 Maintenance Road (Gravel) 25 Waste Separation

12 Polluted Water Drain 26 Ventilation Fan

13 Sewage Treatment Plant 27 Brake test Ramp

14 Light Vehicle Refuel Bay

Page 12: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

10

Figure 4: Planned infrastructure general arrangement plan for the proposed Metsimaholo shaft complex

Page 13: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

11

3.0 APPROACH AND METHODOLOGY

The approach followed to compile the preliminary closure costs can be summarised as follows:

The Metsimaholo project is a green fields project, this preliminary costing is for inclusion in the MRA

application. The cost estimate is based on preliminary mine planning information and the project

description contained in the draft scoping report;

The battery limits of the assessment were based on the conceptual layout plans and general

arrangement plans provided by Ukwazi;

The rehabilitation and closure assumptions are based on the premise that all infrastructure will be

decommissioned and demolished, all disturbed areas will be rehabilitated to achieve a post mining land

use of grazing (assumed end land use for costing purposes);

With regard to the delineation and measurement of the future planned infrastructure and mining areas,

the following approach was followed:

▪ Site orientation and naming of facilities were obtained from the associated layout maps provided; and

▪ Quantification and measurement (areas, heights, volumes and load and haul distances) were based

on infrastructure general arrangement plans and assumptions regarding the construction of each

building/component discussed with Ukwazi (Table 5);

The amount of material required to backfill the decline shaft (voids) is based on an estimate provided by

Ukwazi, as with all other aspects this will require verification and updating as the project is developed in

more detail;

The above infrastructure and areas were captured in the Golder GN R. 1147 closure cost template;

Individual unit rate tables were developed based on the latest third-party rates;

Closure measures and associated quantifications were devised, incorporating the information described;

The scheduled closure costs were computed as if the infrastructure has been constructed as planned,

and narratives provided describing key assumptions/qualifications and other considerations made with

each item;

The scheduled and unscheduled closure cost components of the costing spreadsheet have been

completed for ease of future updating;

A summary sheet providing aggregated costs for the proposed shaft complex was compiled; and

A dedicated closure cost report (this report) was compiled.

Page 14: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

12

Table 5: Battery limits: shaft infrastructure, measurements and assumptions

No Infrastructure Area (m2)

Stockpile

areas

(m2)

Shaft

area (m2)

Estimated

volume(m3) Length (m) structure type - assumptions

1 Mine Offices 2,331.33 portable cabins

2 Change House & Laundry 3,210.17 single story brick and mortar building

3 Stores 1,669.05 light shed type structure 0-5 m high with concrete slab <250

mm thick

4 Workshops 2,599.81 light shed type structure 0-5 m high with concrete slab <250

mm thick

5 Security 239.13 small portable cabin and fixed boom

6 Bus Shelter 61.50 typical car port with IRB roof

7 Shaft Offices 847.22 portable cabins

8 Parking 6,797.38 paving bricks with typical car port (IRB roof)

9 Pollution Control Dam 8,836.00 dam with concrete liner 150 mm thickness

10 Main Access Road

(Surfaced)

30,902.00 tarred road

11 Maintenance Road (Gravel) 1,938.00 gravel road

12 Polluted Water Drain 733.02 concrete lined drain 150 mm thickness

13 Sewage Treatment Plant 439.62 mostly medium concrete between 250-500 mm

14 Light Vehicle Refuel Bay 72.00 steel rented unit comes with bund walling. Varies in size

probably around 5 000 L

15 Incline Shaft 44,739.48 1,000,000.00 concrete decline, volume provided by ukwazi

16 Surge Silo (3 000 t

Provisional)

514.60 heavy concrete 500 - 750 mm

17 Lamp Room 188.60 portable cabins

18 Stormwater Cut-off Drain 2,734.00 v-drain unlined

19 Substations 423.29 Mobile sub-station

20 Waste Stockpile 42,406.20 subsoil/overburden stockpile from the shaft boxcut

Page 15: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

13

No Infrastructure Area (m2)

Stockpile

areas

(m2)

Shaft

area (m2)

Estimated

volume(m3) Length (m) structure type - assumptions

21 Bulk/Raw Water Storage 1,413.72 concrete overhead structure

22 Fire Water Storage 920.51 overhead Fresh water Reservoir will be used

23 Fence 3,392.25 security fence

24 Topsoil Stockpile 31,184.39 volume included in shaft boxcut 1 million m3

25 Waste Separation 3,056.19 concrete slab <250 mm no reinforcing

26 Ventilation Fan 286.71 medium concrete footing 250-500 mm with small steel

structure?

27 Brake test Ramp 381.75 earth ramp - subsoils from shaft excavation

Totals 70,595.60 73,590.59 44,739.48 1,000,000.00 3,392.25

Hectares 7.06 7.36 4.47

Page 16: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

14

4.0 KEY ASPECTS AND ASSUMPTIONS

Key aspects and assumptions considered in the determination of closure costs are outlined below.

4.1 General

The following general assumptions have been applied:

The overall closure costs for the site could comprise a number of cost components. This report only

addresses surface rehabilitation, decommissioning of infrastructure and the final closure and control of

the site that will ensure attainment of the predetermined post mining land use with acceptable

environmental and socio-economic effects. This equates to an outside (third party) contractor(s)

establishing on-site and conducting the suite of closure related work, ranging from surface rehabilitation

to the monitoring/control and corrective action to ensure the desired rehabilitation related outcomes.

Other components of the overall costs such as staffing of the site after decommissioning, the

infrastructure and support services (e.g. power supply, etc.) for this staff as well as workforce matters

such as separation packages, re-training /re-skilling, etc. are outside the scope of this report;

Based on the above, dedicated contractors would be commissioned to conduct the surface rehabilitation,

demolition and closure related work on the site. This would inter alia require establishment costs for the

contractors and hence, the allowance for preliminary and general (P&Gs) in the closure costs;

Allowance has also been made for third party contractors and consultants to conduct post-closure care

and maintenance work as well as performance and compliance monitoring;

Potential handover of infrastructure to third parties at closure will be considered in the closure costing if

an agreement is in place with the relevant third party; should no such agreement be in place, it has been

assumed that the infrastructure will be demolished at closure;

In accordance with international accounting practices and GN R.1147, no cost off-sets due to possible

salvage of dismantled infrastructure has been considered;

Due to the board and pillar method of mining planned for the operations, surface subsidence has been

deemed to be an insignificant risk and hence measures to rehabilitate land/watercourses affected by

subsidence have not been included; and

It has been assumed that most infrastructure in underground workings will remain underground at

closure and will not be brought to surface for salvaging, therefore no costs have been allowed for the

removal of underground infrastructure.

4.2 Infrastructural aspects

The following assumptions apply to all infrastructure:

It has been assumed that concrete, decontaminated and inert demolition waste and building rubble will

be disposed of into the shaft portal. An allowance has been made for crushing and screening the

concrete demolition waste prior to backfilling;

It has been assumed that a temporary salvage yard and decontamination bay will be established during

the demolition of the infrastructure utilising the exiting dirty water management areas during

decontamination and sorting;

It has been assumed that recoverable steel will be sent to the salvage yard;

Page 17: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

15

Closure costing makes provision for a nominal amount of hazardous material/waste to be disposed at

Holfontein, based on the volume of asphalt recovered during the rehabilitation of the tar access roads as

well as emanating from the PCDs and sewage plant sludge; and

It has been assumed that all internal roads and paved surfaces, including tar and gravel access roads

associated with the mine infrastructure, will be rehabilitated accordingly.

4.3 Mining aspects

The rehabilitation and closure assumptions regarding the mining areas include:

Coal will be loaded into trucks from the silos and transported off site for processing or directly to an end

user, any resulting discard or slurry management is excluded from this assessment;

It has been assumed that the shaft portal voids will be backfilled with overburden and topsoil stripped

and stored onsite during the development phase. An average load and haul distance of approximately

500 m was assumed for this purpose based on the available shaft complex drawings. This assumption

should be revised based on actual haul distance requirements once construction of the shaft complex

has been completed;

Costing has made provision for rehabilitation (sealing, plugging, etc.) of the decline shaft and the

ventilation shaft indicated in Figure 4; and

For the dirty water impoundment (pollution control dam, sewage plant dams and dirty water separation

trench), it has been assumed that the concrete will be demolished, removed decontaminated and

screened with the other concrete. A nominal allowance has been made to transport and dispose of

hazardous waste at Holfontein.

4.4 General surface rehabilitation

The following assumptions apply to general surface rehabilitation:

An allowance has been made for rehabilitation of disturbed areas, including: general levelling and

shaping all disturbed areas, ripping to alleviate compaction, scarifying the footprints and hydroseeding

with a mixture of soil ameliorants and grassland species, and

Dedicated soil sampling, fertility analysis and results interpretation will inform the soil amelioration

program.

4.5 Post-closure aspects

The post-closure aspects have been costed according to the following:

Provision has been made for surface water and groundwater monitoring for five (5) years;

Provision has been made for rehabilitation monitoring for five (5) years;

Care and maintenance of rehabilitated land has been allowed for over a period of five (5) years;

Identified potential latent and residual risks were not included in the closure costs; input data will be

refined during the EIA process for consideration during the next closure costs update; and

Allowance has been made for alien invasive plant control over areas where vegetation has been

established during and after closure, this action is included in the overall rehabilitation monitoring and

maintenance provision.

Page 18: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

16

4.6 Preliminaries and general, contingencies and additional allowances

Preliminaries and general were assumed to be 6%;

Contingencies were assumed to be 10%;

Closure costing has made provision for several additional studies and integrated environmental

authorisations (Environmental Impact Assessment/basic Assessment process, Integrated Waste Water

Management Plan (IWWMP) and a Water Use Licence Application (WULA)) that will likely be required in

the event of closure.

5.0 CLOSURE COSTS, AS AT SEPTEMBER 2018

The costs are structured according to the format routinely used for the presentation of closure costs for mine

sites as per the following categories:

Infrastructural areas;

Mining areas;

General surface rehabilitation;

Post-closure aspects:

▪ Surface water monitoring;

▪ Ground water monitoring;

▪ Rehabilitation monitoring and Care and maintenance;

▪ Contingencies for post-closure aspects; and

Additional allowances:

▪ Preliminary and general;

▪ Contingencies; and

▪ Additional studies.

The summary of the scheduled closure costs as at September 2018 are included in Table 6.

Page 19: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

17

Table 6: Scheduled closure costs for the proposed Metsimaholo shaft complex

Metsimaholo Mine Closure Costs, as at September 2018

Closure components Scheduled Closure

(2055)

1 Infrastructural aspects R 18,003,320.46

2 Mining aspects R 32,001,591.85

3 General surface rehabilitation R 2,215,097.43

Sub-Total 1 R 52,220,009.74

5 Post-Closure Aspects

5.1 Surface water monitoring R 1,142,270.05

5.2 Groundwater monitoring R 815,907.15

5.3 Rehabilitation monitoring R 44,387.71

5.4 Care and maintenance R 650,630.91

5.5 Contingencies for post-closure aspects R 265,319.58

Sub-Total 2 R 2,918,515.40

6 Additional Allowances

6.1 Preliminary and general R 3,133,200.58

6.2 Contingencies R 5,222,000.97

6.3 Additional studies R 1,179,032.26

Sub-Total 3 R 9,534,233.82

Grand Total

Excl. VAT. (Sub-total 1 +2 +3) R 64,672,758.96

6.0 CONCLUSION

The preliminary closure costs compiled within the battery limits described is based on limited information as

expected during the early stages of the project planning phase. The assessment provides a robust costing

framework for future annual updates and a basis for a step-based approach to aligning the closure planning

and costing with GN R.1147 and the anticipated update.

Golder Associates Africa (Pty) Ltd.

Anthony Lamb Johan Bothma

Land use and closure Land use and closure

AL/JB/nbh

Reg. No. 2002/007104/07

Directors: RGM Heath, MQ Mokulubete, SC Naidoo, GYW Ngoma

Golder and the G logo are trademarks of Golder Associates Corporation

g:\projects\18101804 - seritinewvaal ncvmra\6. deliverables\final client deliverables\18101804-321416-1_metsimaholo_cc.docx

Page 20: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

APPENDIX A

Document Limitations

Page 21: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

DOCUMENT LIMITATIONS

This Document has been provided by Golder Associates Africa Pty Ltd (“Golder”) subject to the following

limitations:

i) This Document has been prepared for the particular purpose outlined in Golder’s proposal and no

responsibility is accepted for the use of this Document, in whole or in part, in other contexts or for any

other purpose.

ii) The scope and the period of Golder’s Services are as described in Golder’s proposal, and are subject to

restrictions and limitations. Golder did not perform a complete assessment of all possible conditions or

circumstances that may exist at the site referenced in the Document. If a service is not expressly

indicated, do not assume it has been provided. If a matter is not addressed, do not assume that any

determination has been made by Golder in regards to it.

iii) Conditions may exist which were undetectable given the limited nature of the enquiry Golder was

retained to undertake with respect to the site. Variations in conditions may occur between investigatory

locations, and there may be special conditions pertaining to the site which have not been revealed by the

investigation and which have not therefore been taken into account in the Document. Accordingly,

additional studies and actions may be required.

iv) In addition, it is recognised that the passage of time affects the information and assessment provided in

this Document. Golder’s opinions are based upon information that existed at the time of the production of

the Document. It is understood that the Services provided allowed Golder to form no more than an

opinion of the actual conditions of the site at the time the site was visited and cannot be used to assess

the effect of any subsequent changes in the quality of the site, or its surroundings, or any laws or

regulations.

v) Any assessments made in this Document are based on the conditions indicated from published sources

and the investigation described. No warranty is included, either express or implied, that the actual

conditions will conform exactly to the assessments contained in this Document.

vi) Where data supplied by the client or other external sources, including previous site investigation data,

have been used, it has been assumed that the information is correct unless otherwise stated. No

responsibility is accepted by Golder for incomplete or inaccurate data supplied by others.

vii) The Client acknowledges that Golder may have retained sub-consultants affiliated with Golder to provide

Services for the benefit of Golder. Golder will be fully responsible to the Client for the Services and work

done by all of its sub-consultants and subcontractors. The Client agrees that it will only assert claims

against and seek to recover losses, damages or other liabilities from Golder and not Golder’s affiliated

companies. To the maximum extent allowed by law, the Client acknowledges and agrees it will not have

any legal recourse, and waives any expense, loss, claim, demand, or cause of action, against Golder’s

affiliated companies, and their employees, officers and directors.

viii) This Document is provided for sole use by the Client and is confidential to it and its professional advisers.

No responsibility whatsoever for the contents of this Document will be accepted to any person other than

the Client. Any use which a third party makes of this Document, or any reliance on or decisions to be

made based on it, is the responsibility of such third parties. Golder accepts no responsibility for

damages, if any, suffered by any third party as a result of decisions made or actions based on this

Document.

GOLDER ASSOCIATES AFRICA (PTY) LTD

Page 22: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

October 2018 18101804-321416-1

APPENDIX B

Curricula Vitae

Page 23: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

Curriculum Vitae ANTHONY LAMB

1

Education

University of South Africa: BSc Honours Geography & Environmental Management

University of Johannesburg: BSc Geography & Environmental Management

Tshwane University of technology: Certificate in Environmental Chemistry

Eco-Training: Higher Diploma in Game ranging.

Various short courses, including: ▪ Finance for non-financial

managers - The Gordon Institute for Business (GIBS) 2012;

▪ Tools for Wetland Assessment - Rhodes University 2011;

▪ Pollution and Rehabilitation - University of the Free State;

▪ Basic Principles of Ecological Rehabilitation - University of North West;

▪ NOSA auditors course;

▪ Understanding ISO14001 – South African Bureau of Standards;

▪ Foundation course in Environmental Auditing – Aspects International; and

▪ Various Game Ranging Practical courses at Klaserie, Moholoholo and Sabi Sands game reserves.

Internal course attended at Golder Associates include:

▪ Introduction to the Upstream Petroleum Industry (Oil and Gas School);

▪ Tailings and Mine Waste Management; and

▪ Manager Excellence;

Internal Courses completed while at Fraser Alexander:

▪ Tailings Management and Design - 201

Golder Associates Africa (Pty) Ltd. – Pretoria

Land Use and Closure: Senior Rehabilitation and Closure Consultant

Anthony Lamb has 21 years’ experience in rehabilitation and closure planning, design

and implementation across the mining and industrial sectors. Anthony worked on

various opencast and underground coal mining operations in the Mpumalanga highveld

of South Africa as a Research Assistant, Scientific Officer, Land Rehabilitation Officer

and an Environmental coordinator. The latter roles had a specific emphasis on

managing land rehabilitation activities within the mining operations. After 10 years of

gaining operational experience he moved to consulting. The last 11 years he has

focused on closure planning, liability determination and integrated mine and

rehabilitation planning to help companies understand, directly address and reduce their

environmental liabilities.

PROFESSIONAL SUMMARY

Golder associates Africa (2018 - current)

Anthony rejoined the Land use and Closure Division within Golder Associates Africa as

a Snr mine rehabilitation and closure consultant. He brings 21 years of experience to the

team and will focus on progressing closure planning, costing and integrated

rehabilitation planning for clients across mining and industrial industries.

Wrink Environmental engineers (2016-2018)

Anthony was a co-founder of WRINK environmental engineers (PTY) Ltd. The company

was established in 2016 and provided land rehabilitation, closure, waste management

and waste engineering services to the mining and industrial industries. Successful

projects include:

▪ Designing and modelling the post-mining landform and quantifying the mass

earthworks required at closure for on opencast pit at Royal Baphokeng

Platinum;

▪ Developing the Final Rehabilitation, Decommissioning and Closure Plan

(FRDCP), Annual Rehabilitation Plan (ARP) and Environmental Risk

Assessment Report (ERAR) with accurate quantification of annual and closure

rehabilitation costs for a planned opencast operation at Anglo Platinum (aligned

with the NEMA GN 1147 requirements);

▪ Compiling the FRDCP, ARP and ERAR according to the NEMA GN 1147

minimum requirements for a gas extraction operation by Tetra4 Gas;

▪ Developing a closure route map for AngloGold Ashanti; and

▪ Determining the closure liability for an underground expansion at Samancor.

Anthony also Presents the Landform Modelling and Planning module for the Ecological

Rehabilitation and Mine Closure course offered at the Centre for Environmental

Management (North West University).

Fraser Alexander tailings (2012-2015)

Anthony held the position of Business Development Lead: Rehabilitation within the

Business Development Division of Fraser Alexander Tailings situated in Jet Park.

Responsibilities included technical support to the operations in South Africa, within other

African countries and South America; and the development of new products and new

business within the rehabilitation domain.

Page 24: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

Curriculum Vitae ANTHONY LAMB

2

Languages

English – Fluent

Afrikaans - Fluent

Professional Affiliations

IAIAsa

Golder associates Africa (2008-2011)

As Divisional Leader of the Rehabilitation and Closure Division of Golder Associates

Africa (Golder purchased African EPA in 2008), he was responsible for the day-to-day

operations of the division as well as marketing and providing technical expertise. The

role required close liaison across various Golder divisions for integrated projects, as well

as developing and maintaining key relationships with clients. Anthony was responsible

for the implementation and project management of several closure liability determination

projects in South Africa, notably the following:

▪ Determining the decommissioning and closure liability for all ESKOM coal fired

Power Stations in South Africa, the wind farm at Sere, open cycle gas turbines

in the Western and Eastern Cape and the pump storage scheme in the

Drakensburg;

▪ Planning and quantifying the decommissioning and rehabilitation required for

closure of Namaqualand mines (De Beers), and subsequently updating the

reporting for inclusion into the sale of the mine;

▪ Calculating the decommissioning and closure liability for Saldhanha Steel in the

Western Cape; and

▪ Devising the rehabilitation and closure liability for several coal mines in South

Africa including Exxaro, Xstrata and Anglo operations.

African EPA (2005-2008)

Fulfilling the role of Environmental Scientist for African EPA, Anthony was specifically

focused on the modelling of post mining landforms, integration of mining and

rehabilitation planning and the optimization of mass earth works for the opencast coal

mining industry. He completed surface water specialist studies, closure cost estimates

and rehabilitation planning for the following:

▪ all Eskom coal fired Power Stations,

▪ BHP Billiton operations including all pits at Middleburg Mines, Khutala and

Klipspruit,

▪ Anglo Coal Kleinkopje and Isibonello Colliery,

▪ Glencore Xstrata Impunzi and Tweefontein operations;

▪ Sasol Coal Syferfontein Colliery; and

▪ Optimum Colliery West pit.

Anglo Coal (1997-2005)

Anthony started his career working for Anglo Coal Central Environmental Services

(ACES) and subsequently as Scientific and Rehabilitation Officer at Kriel Colliery and

then Environmental Coordinator: Rehabilitation at New Vaal Colliery.

The role at ACES included maintaining the surface and ground water quality database

for all Anglo Coal operations and developing monthly/annual reports. The

responsibilities also included soil, surface and ground water monitoring for greenfields

and closure sites.

Key aspects during the period at Kriel Colliery included the implementation of an

ISO14001 system, developing monitoring systems to inform corporate sustainability

reporting and managing rehabilitation and farming activities.

Page 25: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

Curriculum Vitae ANTHONY LAMB

3

The position at New Vaal Colliery included managing the pre-strip fleet, dozing

operations, placement of pre-strip material on reshaped spoils, revegetation and post-

rehabilitation pasture management.

All roles included cross operational involvement in Environmental, Health and Safety

auditing and engaging in various rehabilitation and environmental planning initiatives

and forums.

Page 26: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

1

Education

MLArch Landscape Architecture, University of Pretoria, Pretoria, 2004

BL Landscape Architecture, University of Pretoria,

Pretoria, 2001

Certifications

South African Council for the Landscape Architectural

Profession (SACLAP 20163)

Institute of Landscape Architecture in South Africa

(ILASA)

Languages

English – Fluent

Afrikaans – Fluent

Professional Affiliations

Institute of Landscape

Architecture of South Africa (ILASA)

South African Council for the Landscape Architectural Profession (SACLAP)

Johan Bothma Senior Land Use and Closure Consultant

PROFESSIONAL SUMMARY

Mine Environment

Johan is the service lead for Closure Planning and Costing in the Land Use and Closure Team based in the Pretoria, South Africa office. He has 13 years

consulting experience and is currently advancing closure costing and planning for mining and industrial sites, with a focus on next land use planning and latent

risk mitigation. Johan has completed many closure related projects for a wide

variety of different commodity mines throughout Africa and abroad.

He also specialises in visual assessment and technical direction of graphic

representation of project impacts and mitigation. He furthermore has considerable experience in impact assessment, environmental management

plans and auditing for mining, industrial, commercial and property development

and projects.

Johan is a professionally registered Landscape Architect and completed his

Master's Degree in 2004, focusing on climate responsive design and energy efficiency for residential developments. He has previously worked on various

landscape planning and design projects, including large scale open space

management plans, as well as landscape architectural design for prestige governmental projects including the Presidential residence in Bryntirion Estate

in Pretoria.

RELEVANT EXPERIENCE

KEY REHABILITATION AND CLOSURE PROJECTS

Sasol Secunda - Mpumalanga, South Africa (2015; 2017) Project manager for the 2015 and 2017 closure costs update for the

Sasol Secunda Synfuels and Chemicals operations (including the

Polymers, Explosives and Fertiliser facilities and all waste disposal facilities in the Secondary Areas), including waste disposal, post-

closure water treatment and cash flows.

Mafube Coal - Mpumalanga, South Africa (2017) Development of detailed closure plan; and GN 1147 compliant closure

costs spreadsheets for bio-physical closure aspects. Qualitative and quantitative risk assessments to inform residual and latent risk

mitigation and quantification of costs. Detailed water treatment costs

and financial discounting.

Exxaro Arnot Coal Mine - Mpumalanga, South Africa (2016 - ongoing)

Project manager of comprehensive closure plan and costs for final closure of Arnot Coal mine. Development of GN 1147 compliant

closure costs spreadsheets. Qualitative and quantitative risk

assessments to inform residual and latent risk mitigation and quantification of costs. Detailed water treatment costs and financial

discounting.

Page 27: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

Resume – Name of Person Proposal #

2

Sibanye Gold Mines - Gauteng, Free State, and Mpumalanga, South Africa (2013 - ongoing)

Project manager for ongoing closure costs updates and transitional planning towards GN 1147 for the Beatrix, Kloof, Driefontein, Cooke,

Ezulwini and RUSO operations including operational rehabilitation

planning and closure costs determinations, as well as scheduled, residual costs quantifications. Scheduled and unscheduled closure

cost updates for financial reporting and auditing purposes.

Sibanye Platinum operations - Northwest Province, South Africa

(2017 - ongoing)

Project manager for transitional planning towards GN 1147 compliance, including operational rehabilitation and closure planning as well as related rehabilitation costs, scheduled and residual closure

costs. Scheduled and unscheduled closure costs for financial reporting

and auditing purposes.

Gold Fields South Deep Mine - Gauteng, South Africa (2013-2017) Project manager operational rehabilitation planning and costing,

scheduled, residual and latent costs determination as well as related

rehabilitation and closure planning towards GN 1147 compliance (2016). Project management, scheduled and unscheduled closure cost updates for South Deep gold mine for financial reporting and

auditing purposes. Compilation of detailed next land use plan,

rehabilitation and closure plans (2014-2015).

Morupule thermal power station - Morupule area, Botswana (2016) Project manager scheduled closure costs determination and closure

framework for Phase 2 expansion of the Morupule thermal coal power

station.

Kenmare Moma Mine Sofala, Mozambique (2015)

Project manager for scheduled and unscheduled closure cost updates

for Moma sand mine in Mozambique.

Anglo New Denmark, New Vaal, Union and Goedehoop Mines interim closure planning and costing - Mpumalanga, South Africa (2013-

2014)

Project manager/specialist for interim closure planning for respective Anglo Coal mines according to the Anglo Closure Toolbox, which included state of the environment, rapid strategic environmental

assessment, closure criteria, risk assessment, closure costing and end

land use planning.

Zincor detailed next land use plan - Gauteng, South Africa (2013) Detailed evaluation of post-closure next land use options for the

decommissioned Zincor zinc smelter complex, which includes

extensive industrial plant and two tailings storage facilities.

Letlhakane and Jwaneng land use plans and graphic modelling -

Botswana (2012-2014) Preliminary post-closure next land use plans for the Letlhakane and

Jwaneng open pit diamond mines in Botswana. Graphic modelling

Page 28: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

Resume – Name of Person Proposal #

3

direction for various waste rock disposal alternatives for Jwaneng

mine and end land use planning for Letlhakane Mine.

Thaba Metsi Coal Mine - Limpopo, South Africa (2012)

Scheduled and unscheduled closure cost determinations, preliminary

end land use plan for Thaba Metsi opencast and underground coal

mine.

Goedehoop Colliery - Mpumalanga, South Africa (2012) Scheduled and unscheduled closure cost determinations, preliminary

land use plan for Goedehoop North and South underground coal

mines.

KEY ENVIRONMENTAL ASSESSMENT, PERMITTING AND AUDITING

PROJECTS

Zululand Anthracite Colliery - Kwazulu-Natal, South Africa (2013,

2015) On-site assessment and environmental audits of EMP and ROD

Requirements for ZAC operations.

Menlyn Maine EMPs and environmental audits - Pretoria, South

Africa (2011-2013)

Compiled Environmental Management Plans for the Menlyn Maine Clinton Climate Change Initiative-endorsed Phase 1 infrastructure development as well as Falcon, Epsilon and Pegasus Buildings; and

conducted construction environmental compliance audits. All projects

are targeting a minimum Green Star SA four star rating; and LEED ND

certification.

Tubatse water treatment and pelletiser plant EMP audits - Limpopo Province, South Africa (2010-2013)

Six-monthly environmental compliance audits in terms of approved EMP and Environmental Authorisations for construction and operation

of new water treatment plant and pelletiser plant.

Rand Uranium TSF EIA - Gauteng, South Africa (2010) EIA lead for new long term tailings storage facility for disposal of up to

350 million tons of re-processed tailing from a number of tailing resources in the Randfontein area, including 40 km associated pipelines. Coordination of specialist assessment and public

participation in terms of overall EIA process.

Transnet New Multi-Products Pipeline (NMPP) EMP - Durban, Kwa

Zulu-Natal to Jameson Park Near Heidelberg, South Africa (2008) Compiled the Environmental Management Plan (EMP) for the design,

construction, operations and decommissioning phases of the NMPP

project. This consisted of a new multi-products liquid fuel pipeline (or "Trunkline") running from Durban, Kwa Zulu-Natal to Jameson Park

near Heidelberg in Gauteng, with a pump station at each terminal, and

eight pump stations along the route. A coastal fuel terminal either at the Durban International Airport or and inland fuel terminal at Jameson Park near Heidelberg. The EMP ensured that recommendations of

numerous specialists from a wide variety of fields were implemented.

Page 29: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

Resume – Name of Person Proposal #

4

Following the compilation of a draft version of the EMP, I also facilitated a detailed workshop between the Contractor and the Client

to establish that the mitigation measures proposed are feasible,

following which the EMP was amended as required.

Road D419 EIA - North West Province, South Africa (2005) EMP for the construction of road D419, including extensive addressing

of erosion prevention and mitigation. EIA Scoping report for the

proposed D419 Road between the two Lekgophung and Swartkopfontein in the Northwest Province. The distance between the

two termini of the road (approximately 15 km) required extensive

consideration of several alignment option and extensive public

participation.

The Hills and Sammy Marx lifestyle estates - Pretoria, South Africa

(2004) EIA Scoping Report, EMP and various Water Use Licence

Applications for large, exclusive mixed use developments in east of

Tshwane.

PUBLICATIONS

Hattingh, R and Bothma, J. 2013. Taking the risk out of a risky business: a land

use approach to closure planning, in Mine Closure 2013. Edited by M. Tibbett,

A.B. Fourie and C. Dogby. Australian Centre for Geomechanics: Perth.

Bothma, J. and Theron, G. 2012. Human comfort and the South African climate

design regions in terms of small-scale development design, in South African

Landscape Architecture - a Reader. Pretoria: Unisa Press.

Bothma, J., Crockett, D. and Southwood, J. 2012. Siting a building for human comfort, on SABMag homepage. [Online] Available:

www.sabmagazine.com/blog/2011/12/21/siting-a-building-for-human-comfort/

Bothma, J. 2011. Greening the building: Plants, planting and detailing, in Green

Building Handbook South Africa - the Essential Guide Volume 3. Edited by L. Van

Wyk, Capte Town. Alive2green (pp209-226)

Bothma, J. 2010. Siting a building for Human Comfort, in Green Building Handbook South Africa - The Essential Guide Volume 2. Edited by L.V.Wyk, Cap

Town Alive2green (pp57-72)

Theron, G. and Bothma, J. 2009. The Ecology of Building and Landscape Designin Green Building Handbook South Africa Volume 1: A Guide to Ecological

Design. Edited by L. van Wyk, Cape Town: Alive2green cc (pp61-75).

Bothma, J. 2004. “Landscape and Architectural Devices for Energy-Efficient Sout

African Suburban Residential Design” Submitted in partial fulfilment of the requirements for the degree Master of Landscape Architecture. Pretoria:

University of Pretoria.

Page 30: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

1

Curriculum Vitae TASHRIQ NAICKER

Education

BSc (Hons) Environmental Science, University of the Witwatersrand, Johannesburg, 2008

BSc Geology and Environment Conservation, University of the Witwatersrand, Johannesburg, 2007

Languages

English – Fluent

Afrikaans – Fluent

Golder Associates Africa (Pty) Ltd. – Pretoria

Environmental Practitioner

Tashriq is an Environmental Practitioner with more than nine years’ experience,

Tashriq specialises in the environmental management field.

Key experience includes:

▪ Renewable Energy Applications

▪ Environmental Impact Assessments

▪ Specialist Assistance with regard to bio-monitoring

▪ Basic Assessments

▪ Scoping & EIAs

▪ Environmental Opinions

▪ Water Use Licence Applications

▪ Waste Management Licences

▪ Mining Right Applications

▪ Section 102 Applications

▪ Geotechnical Risk Assessments

▪ Dust and Water Monitoring

▪ Section 24G Applications

▪ Due Diligence reports

▪ Peer Review on External EAP’s

Employment History

Golder Associates Africa (Pty) Ltd – Pretoria

Environmental Practitioner (May 2018 to Present)

Project Management, including conducting assessment processes, ensuring

quality control and legal compliance. Involvement with the Client and technical

project team, oversight over specialist studies and management of specialists.

Extensive Authority liaison.

GIBB (Pty) Ltd – Pretoria

Senior Environmental Scientist, Environmental Services Sector (May 2013 to

April 2018)

Complete Project Management. Conducting the S&EIR & BA Processes,

oversight on the process and ensuring quality control and legal compliance.

Extensive involvement with the Client and technical project team, oversight over

specialist studies and management of specialists. Extensive Authority liaison.

Strategic Planning with client technical team to ensure successful roll out of

projects. Financial responsibility on the projects as well as minimising company

liability.

GIBB (Pty) Ltd – Pretoria

Environmental Scientist, Environmental Services Sector (August 2012 to April

2013)

Completed various BA & EIA processes, over saw public participation and

complied Assessment Reports, Envionmental Opinions, Due Diligence reports

Page 31: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

2

Curriculum Vitae TASHRIQ NAICKER

etc.

Strategic Environmental Focus (Pty) Ltd – Pretoria

Environmental Assistant: Environmental Services Division (March 2010 to July

2012)

Conducting BA & EIA processes, including report compilation, reviewing and

interrogation of specialist studies, extensive Client Liaison, Authority Liaison, and

public participation involvement

Strategic Environmental Focus (Pty) Ltd – Pretoria

Environmental Assistant: Environmental Services Division (April 2009 to March

2010)

Assisting in BA & EIA processes, including report compilation, reviewing and

interrogation of specialist studies, extensive Client Liaison, Authority Liaison, and

public participation involvement

Page 32: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

3

Curriculum Vitae TASHRIQ NAICKER

PROJECT EXPERIENCE – ENERGY

Eskom Nuclear-1 EIA Eastern and Western

Cape Provinces, South Africa

Scoping & EIR process for the construction of a Nuclear facility for the generation

of electricity to strengthen the electrical grid. Position of Senior Environmental

Scientist held. Responsibilities included finalisation of the EMP, and

Environmental Impact Report. Oversight and management of the public

participation process, extensive liaison with the specialist on the project team as

well as the Client and Authorities. Responding to I&AP’s and assisting with the

logistics and facilitation of the public meetings. Review and integration of the

specialist’s studies and peer reviewed specialist studies into the report.

Responding to appeals on the positive authorisation issued.

SEF: OLAM ENERGY PROJECT 11

Mpumalanga Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: OLAM ENERGY PROJECT 10

Free State Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 9

Mpumalanga Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 8

Free State Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 7

Northern Cape Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 6

Northern Cape Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 5

Free State Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 4

Northern Cape Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 3

Northern Cape Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

Page 33: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

4

Curriculum Vitae TASHRIQ NAICKER

SEF: TRANSALLOYS ENERGY PROJECT 1

Northern Cape Province , South Africa

BA for the establishment of a solar farm. Environmental Scientist. Conducting the

BA process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, and public participation involvement

SEF: OLAM ENERGY PROJECT 10 - 22 Kv

Powerline Free State Province ,

South Africa

BA for the construction of a power line connecting the site to the nearest

substation. Environmental Scientist. Conducting the BA process, including report

compilation, reviewing and interrogation of specialist studies, Client Liaison,

Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 8 -

22Kv Powerline Free State Province ,

South Africa

BA for the construction of a power line connecting the site to the nearest

substation. Environmental Scientist. Conducting the BA process, including report

compilation, reviewing and interrogation of specialist studies, Client Liaison,

Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 3 –

132 KV POWER LINE Northern Cape Province

, South Africa

BA for the construction of a power line connecting the site to the nearest

substation. Environmental Scientist. Conducting the BA process, including report

compilation, reviewing and interrogation of specialist studies, Client Liaison,

Authority Liaison, and public participation involvement

SEF: TRANSALLOYS ENERGY PROJECT 1 –

132 KV POWER LINE Northern Cape Province

, South Africa

BA for the construction of a power line connecting the site to the nearest

substation. Environmental Scientist. Conducting the BA process, including report

compilation, reviewing and interrogation of specialist studies, Client Liaison,

Authority Liaison, and public participation involvement

Oasis - Taaipit 132 Kv powerline

Northern Cape Province , South Africa

Project Leader and EAP. Complete Project Management. Conducting the BA

process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, extensive involvement with the project

team, and public participation involvement and management

Olien – Karats 132 kv powerline

Northern Cape Province, South Africa

Project Leader and EAP. Complete Project Management. Conducting the BA

process, including report compilation, reviewing and interrogation of specialist

studies, Client Liaison, Authority Liaison, extensive involvement with the project

team, and public participation involvement and management

Zandkopsdrift 132Kv Powerline

Western and Northern Cape Province, South

Africa

BA for the construction of a 132kV powerline approximately 82 km long. EAP

and Project Leader. Conducting the BA process, including report compilation,

reviewing and interrogation of specialist studies, Client Liaison, Authority Liaison,

extensive involvement with the project team, and public participation involvement

Caledon Wind Farm Western Cape Province ,

South Africa

Community Wind Energy Facility. Environmental Scientist role. Responsible for

Authority and client liaison. Overseeing of additional public participation.

PROJECT EXPERIENCE – PROJECT MANAGEMENT

PPC Van Rhyns Dorp - Search and Rescue

Western Cape Province, South Africa

Complete Project Management. Oversight on the search and rescue process

and ensuring quality control and legal compliance with the Rehabilitation Audits.

Extensive involvement with the Client and technical project team, oversight over

specialist studies and management of specialists.

Page 34: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

5

Curriculum Vitae TASHRIQ NAICKER

PROFESSIONAL AFFILIATIONS

South African Council for Natural and Scientific Professions (SACNASP)

International Association for Impact Assessment - South African Charter (IAIAsa)

Page 35: APPENDIX S Closure Plan and Rehabilitation Assessment...Figure 3: Middle seam (“MLMH”) mine design map In bord and pillar mining, parallel roads ways are developed in the mining

golder.com