Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
May 2019 18101804-324364-3 / FS 30/5/1/2/3/2/1 (10050) EM
APPENDIX S
Closure Plan and Rehabilitation Assessment
REPORT
Preliminary closure cost determination for the
proposed Metsimaholo underground operation Seriti Coal (Pty) Ltd
Submitted to:
Seriti Coal (Pty) Ltd New Vaal Colliery
Heilbron Road
Viljoensdrift
1935
Submitted by:
Golder Associates Africa (Pty) Ltd.
Podium at Menlyn, Second Floor, 43 Ingersol Road, Menlyn, Pretoria, 0181, South Africa
P O Box 6001, Halfway House, 1685
+27 11 254 4800
18101804-321416-1
October 2018
October 2018 18101804-321416-1
i
Distribution List 1 x electronic copy Seriti Coal (Pty) Ltd
October 2018 18101804-321416-1
ii
Table of Contents
1.0 INTRODUCTION ......................................................................................................................................... 4
1.1 Background information .................................................................................................................... 4
1.2 Mine contact details .......................................................................................................................... 5
1.3 Closure assessment practitioner ....................................................................................................... 5
2.0 MINE SITE CONTEXT ................................................................................................................................ 6
2.1 Locality .............................................................................................................................................. 6
2.2 Legal status ....................................................................................................................................... 6
2.3 Life of mine ........................................................................................................................................ 6
2.4 Mining reserves ................................................................................................................................. 7
2.5 Mining operations .............................................................................................................................. 7
2.6 Battery limits ...................................................................................................................................... 8
3.0 APPROACH AND METHODOLOGY ....................................................................................................... 11
4.0 KEY ASPECTS AND ASSUMPTIONS ..................................................................................................... 14
4.1 General ............................................................................................................................................ 14
4.2 Infrastructural aspects ..................................................................................................................... 14
4.3 Mining aspects ................................................................................................................................ 15
4.4 General surface rehabilitation ......................................................................................................... 15
4.5 Post-closure aspects ....................................................................................................................... 15
4.6 Preliminaries and general, contingencies and additional allowances ............................................. 16
5.0 CLOSURE COSTS, AS AT SEPTEMBER 2018 ...................................................................................... 16
6.0 CONCLUSION .......................................................................................................................................... 17
TABLES
Table 1: Contact details of Seriti Coal (Pty) Ltd ................................................................................................... 5
Table 2: Contact details for Closure Assessment Practitioners ........................................................................... 5
Table 3: Details of specialists ............................................................................................................................... 5
Table 4: Metsimaholo preliminary closure cost battery limits ............................................................................... 9
Table 5: Battery limits: shaft infrastructure, measurements and assumptions ................................................... 12
Table 6: Scheduled closure costs for the proposed Metsimaholo shaft complex .............................................. 17
October 2018 18101804-321416-1
iii
FIGURES
Figure 1: Locality map and mining rights boundary .............................................................................................. 6
Figure 2: Top seam (“TMH”) mine design map .................................................................................................... 7
Figure 3: Middle seam (“MLMH”) mine design map ............................................................................................. 8
Figure 4: Planned infrastructure general arrangement plan for the proposed Metsimaholo shaft complex ...... 10
APPENDICES
APPENDIX A Document Limitations
APPENDIX B Curricula Vitae
October 2018 18101804-321416-1
4
1.0 INTRODUCTION
Seriti Coal (Pty) Ltd (Seriti) acquired the remaining Metsimaholo reserves as part of a purchase agreement
that involved Seriti taking ownership of several Anglo-American Thermal Coal (AATC) mines supplying
thermal coal to Eskom. Seriti plans to access the remaining reserves through the development of Metsimaholo
Colliery. Golder Associates (Golder) is currently engaged in a process to compile and submit the following:
Application to graduate the prospecting rights (FS30/5/1/1/2/10383PR and FS30/5/1/1/2/10292PR) into a
consolidated Mining Right (MR) to the Department of Mineral Resources (DMR) in terms of the Mineral
and Petroleum Resources Development Act No. 28 2002 (MPRDA); and
An Environmental Impact Assessment (EIA) in support of an application for environmental authorisation
to the Department of Environmental Affairs (DEA) in terms of the National Environmental Management
Act, No. 107 of 1998 (NEMA).
As part of the package of work, Golder was appointed to compile the preliminary closure costs for the
proposed project. The closure costs are, as far as possible, aligned to the National Environmental
Management Act, 1998: GN R.1147 (Regulations Pertaining to the Financial Provision for Prospecting,
Exploration, Mining or Production Operations). Furthermore, it is noted that the proposed amendments to the
financial provisioning regulations for mines have been published for public comment. Cognisance was taken
of these proposed amendments, to ensure that these can be incorporated into the 2019 closure costs update
ensuring a stepped approach to compliance once the new Regulations are promulgated. Indications are that
mines will have to be compliant by February 2020.
1.1 Background information
The closure costing is based on the available information as at 30 September 2018 and will require annual
updates as per GN R.1147 or as required by amended financial regulations promulgated in future. The annual
updates should also incorporate the outcomes of the specialist studies to improve the resolution of the closure
cost determination. The following information was provided for this closure cost assessment:
Locality plan indicating the locality and extent of the prospecting right and boundary within which the
shaft complex will be established (Figure 1);
Initial mine design planning by Ukwazi (Pty) Ltd (Ukwazi) indicated in Figure 2 and Figure 3 (Ukwazi
2018);
A general arrangement drawing of the proposed shaft and the related infrastructure (Figure 4; Ukwazi
2018);
Draft scoping report (Golder, 2018); and
Correspondence with Ukwazi regarding the type of infrastructure to be established on site to inform the
demolition costing components (Table 5).
October 2018 18101804-321416-1
5
1.2 Mine contact details Table 1: Contact details of Seriti Coal (Pty) Ltd
Name of company Seriti Coal (Pty) Ltd
Name of project Preliminary closure cost determination for Metsimaholo
Postal address 1st floor, 3 on Glenhove, crn Glenhove and Tottenham roads,
Johannesburg 2196
E-mail address [email protected]
Telephone number (011) 047 7025
1.3 Closure assessment practitioner
This closure costing was compiled by Golder, under the technical lead of Anthony Lamb. Contact details are
provided below.
Table 2: Contact details for Closure Assessment Practitioners
Name of company Golder Associates Africa (Pty) Ltd
Name of Mine The proposed Metsimaholo Colliery
Name of project Preliminary closure cost determination for Metsimaholo
Postal address Podium at Menlyn, 43 Ingersol Road Menlyn, Pretoria 0181
Telephone number +27 (0) 11 254 4839
The core specialists who contributed to the closure planning process, and their relevant professional
registrations and experience, are listed in Table 3. Curriculum Vitae for the specialist team are provided in
APPENDIX B.
Table 3: Details of specialists
Specialist Task Professional registrations/experience
Tashriq Naicker Project manager BSc Hons (Environmental geology),
10 years’ experience
Anthony Lamb Closure costing BSc Hons (Environmental management),
21 years’ experience
Johan Bothma Project reviewer PrLArch (SACLAP), BL, ML
14 years’ experience
October 2018 18101804-321416-1
6
2.0 MINE SITE CONTEXT
The following information is based on the Draft Scoping Report (Golder 2018) and the various planning maps
provided by Ukwazi (2018).
2.1 Locality
The project area is situated within the Metsimaholo Local Municipality, in the magisterial district of Sasolburg,
in the northern part of the Free State Province in South Africa. The nearest towns are Refengkgotso, which
straddles the northeast corner of the project area, and Deneysville which lies a further 3 km to the east as
shown in Figure 1. The area is gently undulating at 1 525 metres above mean sea level. The perennial
Taaibosspruit River meanders from south to north, through the western side of the project area. The Vaal
Dam, in part, forms the eastern edge of the project. Grazing dominates agriculture with limited areas of dry
land farming, predominantly maize. The climate is typical of the Northern Free State with warm to hot and wet
summers and cool to cold, dry winters.
Figure 1: Locality map and mining rights boundary
2.2 Legal status
Seriti Coal currently holds the prospecting mining/exploring coal rights (FS30/5/1/1/2/10383PR and
FS30/5/1/1/2/10292PR) for the Metsimaholo area which covers approximately 34 378 ha, which they propose
to graduate into a mining right. The proposed site was awarded a prospecting mining right in 2008 which was
renewed till 12 November 2018 for the primary purpose of exploring coal.
2.3 Life of mine
The Metsimaholo project pre-construction and construction phase is planned to commence in 2023. It is
expected that the construction period for the Metsimaholo project would last approximately 12 months. Mine
establishment and access development are scheduled to commence in quarter 3 of 2023. The access
October 2018 18101804-321416-1
7
development is anticipated to take an additional 12 months. The project is planned to begin its operational
phase and commence initial production in 2025, depleting in 2055.
2.4 Mining reserves
Based on preliminary studies surrounding the Metsimaholo remaining reserves, there is potential for a 30-year
life-of-mine (LoM), until 2055. The mine is envisaged to deliver an average of 2.8 to 3.0 million tonnes per
annum of coal at steady state production. The total saleable product is estimated at approximately 80 million
tons over the LoM with an average calorific value of 19 megajoules per kilogram.
2.5 Mining operations
Metsimaholo colliery is proposed to be an independent underground mine producing thermal coal from one
operational decline shaft. The Metsimaholo coal resource (top and middle seams) will be mined by
underground methods. Conventional bord and pillar mining techniques with Continuous Miners (CM) are
selected as the primary coal extraction method. Access to the orebody is planned through a box-cut
development, with a twin decline shaft system to intersect the top seam (“TMH”) floor as shown in Figure 2
and the middle seam (“MLMH”) floor as shown in Figure 3 from which the shaft bottom development and main
primary development would be initiated. MLMH will be accessed from underground via a developed decline.
Figure 2: Top seam (“TMH”) mine design map
October 2018 18101804-321416-1
8
Figure 3: Middle seam (“MLMH”) mine design map
In bord and pillar mining, parallel roads ways are developed in the mining direction. Perpendicular roads,
called splits, are developed at predetermined intervals to the parallel roads. These roads interlink, creating
pillars. The roads that are mined concurrently are determined by the size of the pillars required to support the
overburden above the coal seam and the length of the production equipment’s trailing cables. The road widths
would be designed at 7.2 m wide with an average mining height of 3 m. The pillar size is determined by the
safety factor formula that result in the pillar strength divided by the pillar load. The main access development
and production sections will be planned from the decline shaft floor consisting of either seven or nine road
development which constitutes a mining panel.
2.6 Battery limits
The planned infrastructure for the proposed Metsimaholo shaft complex is indicated in Figure 4. The itemised
infrastructure and mining components are summarised in Table 4 and constitute the battery limits for this
closure cost determination.
October 2018 18101804-321416-1
9
Table 4: Metsimaholo preliminary closure cost battery limits
Map No. Inventory item Map No. Inventory item
1 Mine Offices 15 Incline Shaft
2 Change House & Laundry 16 Surge Silo and Conveyor belt
3 Stores 17 Lamp Room
4 Workshops 18 Stormwater Cut-off Drain
5 Security 19 Substations
6 Bus Shelter 20 Waste/overburden Stockpile
7 Shaft Offices 21 Bulk/Raw Water Storage
8 Parking 22 Fire Water Storage
9 Pollution Control Dam 23 Fence
10 Main Access Road (Surfaced) 24 Topsoil Stockpile
11 Maintenance Road (Gravel) 25 Waste Separation
12 Polluted Water Drain 26 Ventilation Fan
13 Sewage Treatment Plant 27 Brake test Ramp
14 Light Vehicle Refuel Bay
October 2018 18101804-321416-1
10
Figure 4: Planned infrastructure general arrangement plan for the proposed Metsimaholo shaft complex
October 2018 18101804-321416-1
11
3.0 APPROACH AND METHODOLOGY
The approach followed to compile the preliminary closure costs can be summarised as follows:
The Metsimaholo project is a green fields project, this preliminary costing is for inclusion in the MRA
application. The cost estimate is based on preliminary mine planning information and the project
description contained in the draft scoping report;
The battery limits of the assessment were based on the conceptual layout plans and general
arrangement plans provided by Ukwazi;
The rehabilitation and closure assumptions are based on the premise that all infrastructure will be
decommissioned and demolished, all disturbed areas will be rehabilitated to achieve a post mining land
use of grazing (assumed end land use for costing purposes);
With regard to the delineation and measurement of the future planned infrastructure and mining areas,
the following approach was followed:
▪ Site orientation and naming of facilities were obtained from the associated layout maps provided; and
▪ Quantification and measurement (areas, heights, volumes and load and haul distances) were based
on infrastructure general arrangement plans and assumptions regarding the construction of each
building/component discussed with Ukwazi (Table 5);
The amount of material required to backfill the decline shaft (voids) is based on an estimate provided by
Ukwazi, as with all other aspects this will require verification and updating as the project is developed in
more detail;
The above infrastructure and areas were captured in the Golder GN R. 1147 closure cost template;
Individual unit rate tables were developed based on the latest third-party rates;
Closure measures and associated quantifications were devised, incorporating the information described;
The scheduled closure costs were computed as if the infrastructure has been constructed as planned,
and narratives provided describing key assumptions/qualifications and other considerations made with
each item;
The scheduled and unscheduled closure cost components of the costing spreadsheet have been
completed for ease of future updating;
A summary sheet providing aggregated costs for the proposed shaft complex was compiled; and
A dedicated closure cost report (this report) was compiled.
October 2018 18101804-321416-1
12
Table 5: Battery limits: shaft infrastructure, measurements and assumptions
No Infrastructure Area (m2)
Stockpile
areas
(m2)
Shaft
area (m2)
Estimated
volume(m3) Length (m) structure type - assumptions
1 Mine Offices 2,331.33 portable cabins
2 Change House & Laundry 3,210.17 single story brick and mortar building
3 Stores 1,669.05 light shed type structure 0-5 m high with concrete slab <250
mm thick
4 Workshops 2,599.81 light shed type structure 0-5 m high with concrete slab <250
mm thick
5 Security 239.13 small portable cabin and fixed boom
6 Bus Shelter 61.50 typical car port with IRB roof
7 Shaft Offices 847.22 portable cabins
8 Parking 6,797.38 paving bricks with typical car port (IRB roof)
9 Pollution Control Dam 8,836.00 dam with concrete liner 150 mm thickness
10 Main Access Road
(Surfaced)
30,902.00 tarred road
11 Maintenance Road (Gravel) 1,938.00 gravel road
12 Polluted Water Drain 733.02 concrete lined drain 150 mm thickness
13 Sewage Treatment Plant 439.62 mostly medium concrete between 250-500 mm
14 Light Vehicle Refuel Bay 72.00 steel rented unit comes with bund walling. Varies in size
probably around 5 000 L
15 Incline Shaft 44,739.48 1,000,000.00 concrete decline, volume provided by ukwazi
16 Surge Silo (3 000 t
Provisional)
514.60 heavy concrete 500 - 750 mm
17 Lamp Room 188.60 portable cabins
18 Stormwater Cut-off Drain 2,734.00 v-drain unlined
19 Substations 423.29 Mobile sub-station
20 Waste Stockpile 42,406.20 subsoil/overburden stockpile from the shaft boxcut
October 2018 18101804-321416-1
13
No Infrastructure Area (m2)
Stockpile
areas
(m2)
Shaft
area (m2)
Estimated
volume(m3) Length (m) structure type - assumptions
21 Bulk/Raw Water Storage 1,413.72 concrete overhead structure
22 Fire Water Storage 920.51 overhead Fresh water Reservoir will be used
23 Fence 3,392.25 security fence
24 Topsoil Stockpile 31,184.39 volume included in shaft boxcut 1 million m3
25 Waste Separation 3,056.19 concrete slab <250 mm no reinforcing
26 Ventilation Fan 286.71 medium concrete footing 250-500 mm with small steel
structure?
27 Brake test Ramp 381.75 earth ramp - subsoils from shaft excavation
Totals 70,595.60 73,590.59 44,739.48 1,000,000.00 3,392.25
Hectares 7.06 7.36 4.47
October 2018 18101804-321416-1
14
4.0 KEY ASPECTS AND ASSUMPTIONS
Key aspects and assumptions considered in the determination of closure costs are outlined below.
4.1 General
The following general assumptions have been applied:
The overall closure costs for the site could comprise a number of cost components. This report only
addresses surface rehabilitation, decommissioning of infrastructure and the final closure and control of
the site that will ensure attainment of the predetermined post mining land use with acceptable
environmental and socio-economic effects. This equates to an outside (third party) contractor(s)
establishing on-site and conducting the suite of closure related work, ranging from surface rehabilitation
to the monitoring/control and corrective action to ensure the desired rehabilitation related outcomes.
Other components of the overall costs such as staffing of the site after decommissioning, the
infrastructure and support services (e.g. power supply, etc.) for this staff as well as workforce matters
such as separation packages, re-training /re-skilling, etc. are outside the scope of this report;
Based on the above, dedicated contractors would be commissioned to conduct the surface rehabilitation,
demolition and closure related work on the site. This would inter alia require establishment costs for the
contractors and hence, the allowance for preliminary and general (P&Gs) in the closure costs;
Allowance has also been made for third party contractors and consultants to conduct post-closure care
and maintenance work as well as performance and compliance monitoring;
Potential handover of infrastructure to third parties at closure will be considered in the closure costing if
an agreement is in place with the relevant third party; should no such agreement be in place, it has been
assumed that the infrastructure will be demolished at closure;
In accordance with international accounting practices and GN R.1147, no cost off-sets due to possible
salvage of dismantled infrastructure has been considered;
Due to the board and pillar method of mining planned for the operations, surface subsidence has been
deemed to be an insignificant risk and hence measures to rehabilitate land/watercourses affected by
subsidence have not been included; and
It has been assumed that most infrastructure in underground workings will remain underground at
closure and will not be brought to surface for salvaging, therefore no costs have been allowed for the
removal of underground infrastructure.
4.2 Infrastructural aspects
The following assumptions apply to all infrastructure:
It has been assumed that concrete, decontaminated and inert demolition waste and building rubble will
be disposed of into the shaft portal. An allowance has been made for crushing and screening the
concrete demolition waste prior to backfilling;
It has been assumed that a temporary salvage yard and decontamination bay will be established during
the demolition of the infrastructure utilising the exiting dirty water management areas during
decontamination and sorting;
It has been assumed that recoverable steel will be sent to the salvage yard;
October 2018 18101804-321416-1
15
Closure costing makes provision for a nominal amount of hazardous material/waste to be disposed at
Holfontein, based on the volume of asphalt recovered during the rehabilitation of the tar access roads as
well as emanating from the PCDs and sewage plant sludge; and
It has been assumed that all internal roads and paved surfaces, including tar and gravel access roads
associated with the mine infrastructure, will be rehabilitated accordingly.
4.3 Mining aspects
The rehabilitation and closure assumptions regarding the mining areas include:
Coal will be loaded into trucks from the silos and transported off site for processing or directly to an end
user, any resulting discard or slurry management is excluded from this assessment;
It has been assumed that the shaft portal voids will be backfilled with overburden and topsoil stripped
and stored onsite during the development phase. An average load and haul distance of approximately
500 m was assumed for this purpose based on the available shaft complex drawings. This assumption
should be revised based on actual haul distance requirements once construction of the shaft complex
has been completed;
Costing has made provision for rehabilitation (sealing, plugging, etc.) of the decline shaft and the
ventilation shaft indicated in Figure 4; and
For the dirty water impoundment (pollution control dam, sewage plant dams and dirty water separation
trench), it has been assumed that the concrete will be demolished, removed decontaminated and
screened with the other concrete. A nominal allowance has been made to transport and dispose of
hazardous waste at Holfontein.
4.4 General surface rehabilitation
The following assumptions apply to general surface rehabilitation:
An allowance has been made for rehabilitation of disturbed areas, including: general levelling and
shaping all disturbed areas, ripping to alleviate compaction, scarifying the footprints and hydroseeding
with a mixture of soil ameliorants and grassland species, and
Dedicated soil sampling, fertility analysis and results interpretation will inform the soil amelioration
program.
4.5 Post-closure aspects
The post-closure aspects have been costed according to the following:
Provision has been made for surface water and groundwater monitoring for five (5) years;
Provision has been made for rehabilitation monitoring for five (5) years;
Care and maintenance of rehabilitated land has been allowed for over a period of five (5) years;
Identified potential latent and residual risks were not included in the closure costs; input data will be
refined during the EIA process for consideration during the next closure costs update; and
Allowance has been made for alien invasive plant control over areas where vegetation has been
established during and after closure, this action is included in the overall rehabilitation monitoring and
maintenance provision.
October 2018 18101804-321416-1
16
4.6 Preliminaries and general, contingencies and additional allowances
Preliminaries and general were assumed to be 6%;
Contingencies were assumed to be 10%;
Closure costing has made provision for several additional studies and integrated environmental
authorisations (Environmental Impact Assessment/basic Assessment process, Integrated Waste Water
Management Plan (IWWMP) and a Water Use Licence Application (WULA)) that will likely be required in
the event of closure.
5.0 CLOSURE COSTS, AS AT SEPTEMBER 2018
The costs are structured according to the format routinely used for the presentation of closure costs for mine
sites as per the following categories:
Infrastructural areas;
Mining areas;
General surface rehabilitation;
Post-closure aspects:
▪ Surface water monitoring;
▪ Ground water monitoring;
▪ Rehabilitation monitoring and Care and maintenance;
▪ Contingencies for post-closure aspects; and
Additional allowances:
▪ Preliminary and general;
▪ Contingencies; and
▪ Additional studies.
The summary of the scheduled closure costs as at September 2018 are included in Table 6.
October 2018 18101804-321416-1
17
Table 6: Scheduled closure costs for the proposed Metsimaholo shaft complex
Metsimaholo Mine Closure Costs, as at September 2018
Closure components Scheduled Closure
(2055)
1 Infrastructural aspects R 18,003,320.46
2 Mining aspects R 32,001,591.85
3 General surface rehabilitation R 2,215,097.43
Sub-Total 1 R 52,220,009.74
5 Post-Closure Aspects
5.1 Surface water monitoring R 1,142,270.05
5.2 Groundwater monitoring R 815,907.15
5.3 Rehabilitation monitoring R 44,387.71
5.4 Care and maintenance R 650,630.91
5.5 Contingencies for post-closure aspects R 265,319.58
Sub-Total 2 R 2,918,515.40
6 Additional Allowances
6.1 Preliminary and general R 3,133,200.58
6.2 Contingencies R 5,222,000.97
6.3 Additional studies R 1,179,032.26
Sub-Total 3 R 9,534,233.82
Grand Total
Excl. VAT. (Sub-total 1 +2 +3) R 64,672,758.96
6.0 CONCLUSION
The preliminary closure costs compiled within the battery limits described is based on limited information as
expected during the early stages of the project planning phase. The assessment provides a robust costing
framework for future annual updates and a basis for a step-based approach to aligning the closure planning
and costing with GN R.1147 and the anticipated update.
Golder Associates Africa (Pty) Ltd.
Anthony Lamb Johan Bothma
Land use and closure Land use and closure
AL/JB/nbh
Reg. No. 2002/007104/07
Directors: RGM Heath, MQ Mokulubete, SC Naidoo, GYW Ngoma
Golder and the G logo are trademarks of Golder Associates Corporation
g:\projects\18101804 - seritinewvaal ncvmra\6. deliverables\final client deliverables\18101804-321416-1_metsimaholo_cc.docx
October 2018 18101804-321416-1
APPENDIX A
Document Limitations
October 2018 18101804-321416-1
DOCUMENT LIMITATIONS
This Document has been provided by Golder Associates Africa Pty Ltd (“Golder”) subject to the following
limitations:
i) This Document has been prepared for the particular purpose outlined in Golder’s proposal and no
responsibility is accepted for the use of this Document, in whole or in part, in other contexts or for any
other purpose.
ii) The scope and the period of Golder’s Services are as described in Golder’s proposal, and are subject to
restrictions and limitations. Golder did not perform a complete assessment of all possible conditions or
circumstances that may exist at the site referenced in the Document. If a service is not expressly
indicated, do not assume it has been provided. If a matter is not addressed, do not assume that any
determination has been made by Golder in regards to it.
iii) Conditions may exist which were undetectable given the limited nature of the enquiry Golder was
retained to undertake with respect to the site. Variations in conditions may occur between investigatory
locations, and there may be special conditions pertaining to the site which have not been revealed by the
investigation and which have not therefore been taken into account in the Document. Accordingly,
additional studies and actions may be required.
iv) In addition, it is recognised that the passage of time affects the information and assessment provided in
this Document. Golder’s opinions are based upon information that existed at the time of the production of
the Document. It is understood that the Services provided allowed Golder to form no more than an
opinion of the actual conditions of the site at the time the site was visited and cannot be used to assess
the effect of any subsequent changes in the quality of the site, or its surroundings, or any laws or
regulations.
v) Any assessments made in this Document are based on the conditions indicated from published sources
and the investigation described. No warranty is included, either express or implied, that the actual
conditions will conform exactly to the assessments contained in this Document.
vi) Where data supplied by the client or other external sources, including previous site investigation data,
have been used, it has been assumed that the information is correct unless otherwise stated. No
responsibility is accepted by Golder for incomplete or inaccurate data supplied by others.
vii) The Client acknowledges that Golder may have retained sub-consultants affiliated with Golder to provide
Services for the benefit of Golder. Golder will be fully responsible to the Client for the Services and work
done by all of its sub-consultants and subcontractors. The Client agrees that it will only assert claims
against and seek to recover losses, damages or other liabilities from Golder and not Golder’s affiliated
companies. To the maximum extent allowed by law, the Client acknowledges and agrees it will not have
any legal recourse, and waives any expense, loss, claim, demand, or cause of action, against Golder’s
affiliated companies, and their employees, officers and directors.
viii) This Document is provided for sole use by the Client and is confidential to it and its professional advisers.
No responsibility whatsoever for the contents of this Document will be accepted to any person other than
the Client. Any use which a third party makes of this Document, or any reliance on or decisions to be
made based on it, is the responsibility of such third parties. Golder accepts no responsibility for
damages, if any, suffered by any third party as a result of decisions made or actions based on this
Document.
GOLDER ASSOCIATES AFRICA (PTY) LTD
October 2018 18101804-321416-1
APPENDIX B
Curricula Vitae
Curriculum Vitae ANTHONY LAMB
1
Education
University of South Africa: BSc Honours Geography & Environmental Management
University of Johannesburg: BSc Geography & Environmental Management
Tshwane University of technology: Certificate in Environmental Chemistry
Eco-Training: Higher Diploma in Game ranging.
Various short courses, including: ▪ Finance for non-financial
managers - The Gordon Institute for Business (GIBS) 2012;
▪ Tools for Wetland Assessment - Rhodes University 2011;
▪ Pollution and Rehabilitation - University of the Free State;
▪ Basic Principles of Ecological Rehabilitation - University of North West;
▪ NOSA auditors course;
▪ Understanding ISO14001 – South African Bureau of Standards;
▪ Foundation course in Environmental Auditing – Aspects International; and
▪ Various Game Ranging Practical courses at Klaserie, Moholoholo and Sabi Sands game reserves.
Internal course attended at Golder Associates include:
▪ Introduction to the Upstream Petroleum Industry (Oil and Gas School);
▪ Tailings and Mine Waste Management; and
▪ Manager Excellence;
Internal Courses completed while at Fraser Alexander:
▪ Tailings Management and Design - 201
Golder Associates Africa (Pty) Ltd. – Pretoria
Land Use and Closure: Senior Rehabilitation and Closure Consultant
Anthony Lamb has 21 years’ experience in rehabilitation and closure planning, design
and implementation across the mining and industrial sectors. Anthony worked on
various opencast and underground coal mining operations in the Mpumalanga highveld
of South Africa as a Research Assistant, Scientific Officer, Land Rehabilitation Officer
and an Environmental coordinator. The latter roles had a specific emphasis on
managing land rehabilitation activities within the mining operations. After 10 years of
gaining operational experience he moved to consulting. The last 11 years he has
focused on closure planning, liability determination and integrated mine and
rehabilitation planning to help companies understand, directly address and reduce their
environmental liabilities.
PROFESSIONAL SUMMARY
Golder associates Africa (2018 - current)
Anthony rejoined the Land use and Closure Division within Golder Associates Africa as
a Snr mine rehabilitation and closure consultant. He brings 21 years of experience to the
team and will focus on progressing closure planning, costing and integrated
rehabilitation planning for clients across mining and industrial industries.
Wrink Environmental engineers (2016-2018)
Anthony was a co-founder of WRINK environmental engineers (PTY) Ltd. The company
was established in 2016 and provided land rehabilitation, closure, waste management
and waste engineering services to the mining and industrial industries. Successful
projects include:
▪ Designing and modelling the post-mining landform and quantifying the mass
earthworks required at closure for on opencast pit at Royal Baphokeng
Platinum;
▪ Developing the Final Rehabilitation, Decommissioning and Closure Plan
(FRDCP), Annual Rehabilitation Plan (ARP) and Environmental Risk
Assessment Report (ERAR) with accurate quantification of annual and closure
rehabilitation costs for a planned opencast operation at Anglo Platinum (aligned
with the NEMA GN 1147 requirements);
▪ Compiling the FRDCP, ARP and ERAR according to the NEMA GN 1147
minimum requirements for a gas extraction operation by Tetra4 Gas;
▪ Developing a closure route map for AngloGold Ashanti; and
▪ Determining the closure liability for an underground expansion at Samancor.
Anthony also Presents the Landform Modelling and Planning module for the Ecological
Rehabilitation and Mine Closure course offered at the Centre for Environmental
Management (North West University).
Fraser Alexander tailings (2012-2015)
Anthony held the position of Business Development Lead: Rehabilitation within the
Business Development Division of Fraser Alexander Tailings situated in Jet Park.
Responsibilities included technical support to the operations in South Africa, within other
African countries and South America; and the development of new products and new
business within the rehabilitation domain.
Curriculum Vitae ANTHONY LAMB
2
Languages
English – Fluent
Afrikaans - Fluent
Professional Affiliations
IAIAsa
Golder associates Africa (2008-2011)
As Divisional Leader of the Rehabilitation and Closure Division of Golder Associates
Africa (Golder purchased African EPA in 2008), he was responsible for the day-to-day
operations of the division as well as marketing and providing technical expertise. The
role required close liaison across various Golder divisions for integrated projects, as well
as developing and maintaining key relationships with clients. Anthony was responsible
for the implementation and project management of several closure liability determination
projects in South Africa, notably the following:
▪ Determining the decommissioning and closure liability for all ESKOM coal fired
Power Stations in South Africa, the wind farm at Sere, open cycle gas turbines
in the Western and Eastern Cape and the pump storage scheme in the
Drakensburg;
▪ Planning and quantifying the decommissioning and rehabilitation required for
closure of Namaqualand mines (De Beers), and subsequently updating the
reporting for inclusion into the sale of the mine;
▪ Calculating the decommissioning and closure liability for Saldhanha Steel in the
Western Cape; and
▪ Devising the rehabilitation and closure liability for several coal mines in South
Africa including Exxaro, Xstrata and Anglo operations.
African EPA (2005-2008)
Fulfilling the role of Environmental Scientist for African EPA, Anthony was specifically
focused on the modelling of post mining landforms, integration of mining and
rehabilitation planning and the optimization of mass earth works for the opencast coal
mining industry. He completed surface water specialist studies, closure cost estimates
and rehabilitation planning for the following:
▪ all Eskom coal fired Power Stations,
▪ BHP Billiton operations including all pits at Middleburg Mines, Khutala and
Klipspruit,
▪ Anglo Coal Kleinkopje and Isibonello Colliery,
▪ Glencore Xstrata Impunzi and Tweefontein operations;
▪ Sasol Coal Syferfontein Colliery; and
▪ Optimum Colliery West pit.
Anglo Coal (1997-2005)
Anthony started his career working for Anglo Coal Central Environmental Services
(ACES) and subsequently as Scientific and Rehabilitation Officer at Kriel Colliery and
then Environmental Coordinator: Rehabilitation at New Vaal Colliery.
The role at ACES included maintaining the surface and ground water quality database
for all Anglo Coal operations and developing monthly/annual reports. The
responsibilities also included soil, surface and ground water monitoring for greenfields
and closure sites.
Key aspects during the period at Kriel Colliery included the implementation of an
ISO14001 system, developing monitoring systems to inform corporate sustainability
reporting and managing rehabilitation and farming activities.
Curriculum Vitae ANTHONY LAMB
3
The position at New Vaal Colliery included managing the pre-strip fleet, dozing
operations, placement of pre-strip material on reshaped spoils, revegetation and post-
rehabilitation pasture management.
All roles included cross operational involvement in Environmental, Health and Safety
auditing and engaging in various rehabilitation and environmental planning initiatives
and forums.
1
Education
MLArch Landscape Architecture, University of Pretoria, Pretoria, 2004
BL Landscape Architecture, University of Pretoria,
Pretoria, 2001
Certifications
South African Council for the Landscape Architectural
Profession (SACLAP 20163)
Institute of Landscape Architecture in South Africa
(ILASA)
Languages
English – Fluent
Afrikaans – Fluent
Professional Affiliations
Institute of Landscape
Architecture of South Africa (ILASA)
South African Council for the Landscape Architectural Profession (SACLAP)
Johan Bothma Senior Land Use and Closure Consultant
PROFESSIONAL SUMMARY
Mine Environment
Johan is the service lead for Closure Planning and Costing in the Land Use and Closure Team based in the Pretoria, South Africa office. He has 13 years
consulting experience and is currently advancing closure costing and planning for mining and industrial sites, with a focus on next land use planning and latent
risk mitigation. Johan has completed many closure related projects for a wide
variety of different commodity mines throughout Africa and abroad.
He also specialises in visual assessment and technical direction of graphic
representation of project impacts and mitigation. He furthermore has considerable experience in impact assessment, environmental management
plans and auditing for mining, industrial, commercial and property development
and projects.
Johan is a professionally registered Landscape Architect and completed his
Master's Degree in 2004, focusing on climate responsive design and energy efficiency for residential developments. He has previously worked on various
landscape planning and design projects, including large scale open space
management plans, as well as landscape architectural design for prestige governmental projects including the Presidential residence in Bryntirion Estate
in Pretoria.
RELEVANT EXPERIENCE
KEY REHABILITATION AND CLOSURE PROJECTS
Sasol Secunda - Mpumalanga, South Africa (2015; 2017) Project manager for the 2015 and 2017 closure costs update for the
Sasol Secunda Synfuels and Chemicals operations (including the
Polymers, Explosives and Fertiliser facilities and all waste disposal facilities in the Secondary Areas), including waste disposal, post-
closure water treatment and cash flows.
Mafube Coal - Mpumalanga, South Africa (2017) Development of detailed closure plan; and GN 1147 compliant closure
costs spreadsheets for bio-physical closure aspects. Qualitative and quantitative risk assessments to inform residual and latent risk
mitigation and quantification of costs. Detailed water treatment costs
and financial discounting.
Exxaro Arnot Coal Mine - Mpumalanga, South Africa (2016 - ongoing)
Project manager of comprehensive closure plan and costs for final closure of Arnot Coal mine. Development of GN 1147 compliant
closure costs spreadsheets. Qualitative and quantitative risk
assessments to inform residual and latent risk mitigation and quantification of costs. Detailed water treatment costs and financial
discounting.
Resume – Name of Person Proposal #
2
Sibanye Gold Mines - Gauteng, Free State, and Mpumalanga, South Africa (2013 - ongoing)
Project manager for ongoing closure costs updates and transitional planning towards GN 1147 for the Beatrix, Kloof, Driefontein, Cooke,
Ezulwini and RUSO operations including operational rehabilitation
planning and closure costs determinations, as well as scheduled, residual costs quantifications. Scheduled and unscheduled closure
cost updates for financial reporting and auditing purposes.
Sibanye Platinum operations - Northwest Province, South Africa
(2017 - ongoing)
Project manager for transitional planning towards GN 1147 compliance, including operational rehabilitation and closure planning as well as related rehabilitation costs, scheduled and residual closure
costs. Scheduled and unscheduled closure costs for financial reporting
and auditing purposes.
Gold Fields South Deep Mine - Gauteng, South Africa (2013-2017) Project manager operational rehabilitation planning and costing,
scheduled, residual and latent costs determination as well as related
rehabilitation and closure planning towards GN 1147 compliance (2016). Project management, scheduled and unscheduled closure cost updates for South Deep gold mine for financial reporting and
auditing purposes. Compilation of detailed next land use plan,
rehabilitation and closure plans (2014-2015).
Morupule thermal power station - Morupule area, Botswana (2016) Project manager scheduled closure costs determination and closure
framework for Phase 2 expansion of the Morupule thermal coal power
station.
Kenmare Moma Mine Sofala, Mozambique (2015)
Project manager for scheduled and unscheduled closure cost updates
for Moma sand mine in Mozambique.
Anglo New Denmark, New Vaal, Union and Goedehoop Mines interim closure planning and costing - Mpumalanga, South Africa (2013-
2014)
Project manager/specialist for interim closure planning for respective Anglo Coal mines according to the Anglo Closure Toolbox, which included state of the environment, rapid strategic environmental
assessment, closure criteria, risk assessment, closure costing and end
land use planning.
Zincor detailed next land use plan - Gauteng, South Africa (2013) Detailed evaluation of post-closure next land use options for the
decommissioned Zincor zinc smelter complex, which includes
extensive industrial plant and two tailings storage facilities.
Letlhakane and Jwaneng land use plans and graphic modelling -
Botswana (2012-2014) Preliminary post-closure next land use plans for the Letlhakane and
Jwaneng open pit diamond mines in Botswana. Graphic modelling
Resume – Name of Person Proposal #
3
direction for various waste rock disposal alternatives for Jwaneng
mine and end land use planning for Letlhakane Mine.
Thaba Metsi Coal Mine - Limpopo, South Africa (2012)
Scheduled and unscheduled closure cost determinations, preliminary
end land use plan for Thaba Metsi opencast and underground coal
mine.
Goedehoop Colliery - Mpumalanga, South Africa (2012) Scheduled and unscheduled closure cost determinations, preliminary
land use plan for Goedehoop North and South underground coal
mines.
KEY ENVIRONMENTAL ASSESSMENT, PERMITTING AND AUDITING
PROJECTS
Zululand Anthracite Colliery - Kwazulu-Natal, South Africa (2013,
2015) On-site assessment and environmental audits of EMP and ROD
Requirements for ZAC operations.
Menlyn Maine EMPs and environmental audits - Pretoria, South
Africa (2011-2013)
Compiled Environmental Management Plans for the Menlyn Maine Clinton Climate Change Initiative-endorsed Phase 1 infrastructure development as well as Falcon, Epsilon and Pegasus Buildings; and
conducted construction environmental compliance audits. All projects
are targeting a minimum Green Star SA four star rating; and LEED ND
certification.
Tubatse water treatment and pelletiser plant EMP audits - Limpopo Province, South Africa (2010-2013)
Six-monthly environmental compliance audits in terms of approved EMP and Environmental Authorisations for construction and operation
of new water treatment plant and pelletiser plant.
Rand Uranium TSF EIA - Gauteng, South Africa (2010) EIA lead for new long term tailings storage facility for disposal of up to
350 million tons of re-processed tailing from a number of tailing resources in the Randfontein area, including 40 km associated pipelines. Coordination of specialist assessment and public
participation in terms of overall EIA process.
Transnet New Multi-Products Pipeline (NMPP) EMP - Durban, Kwa
Zulu-Natal to Jameson Park Near Heidelberg, South Africa (2008) Compiled the Environmental Management Plan (EMP) for the design,
construction, operations and decommissioning phases of the NMPP
project. This consisted of a new multi-products liquid fuel pipeline (or "Trunkline") running from Durban, Kwa Zulu-Natal to Jameson Park
near Heidelberg in Gauteng, with a pump station at each terminal, and
eight pump stations along the route. A coastal fuel terminal either at the Durban International Airport or and inland fuel terminal at Jameson Park near Heidelberg. The EMP ensured that recommendations of
numerous specialists from a wide variety of fields were implemented.
Resume – Name of Person Proposal #
4
Following the compilation of a draft version of the EMP, I also facilitated a detailed workshop between the Contractor and the Client
to establish that the mitigation measures proposed are feasible,
following which the EMP was amended as required.
Road D419 EIA - North West Province, South Africa (2005) EMP for the construction of road D419, including extensive addressing
of erosion prevention and mitigation. EIA Scoping report for the
proposed D419 Road between the two Lekgophung and Swartkopfontein in the Northwest Province. The distance between the
two termini of the road (approximately 15 km) required extensive
consideration of several alignment option and extensive public
participation.
The Hills and Sammy Marx lifestyle estates - Pretoria, South Africa
(2004) EIA Scoping Report, EMP and various Water Use Licence
Applications for large, exclusive mixed use developments in east of
Tshwane.
PUBLICATIONS
Hattingh, R and Bothma, J. 2013. Taking the risk out of a risky business: a land
use approach to closure planning, in Mine Closure 2013. Edited by M. Tibbett,
A.B. Fourie and C. Dogby. Australian Centre for Geomechanics: Perth.
Bothma, J. and Theron, G. 2012. Human comfort and the South African climate
design regions in terms of small-scale development design, in South African
Landscape Architecture - a Reader. Pretoria: Unisa Press.
Bothma, J., Crockett, D. and Southwood, J. 2012. Siting a building for human comfort, on SABMag homepage. [Online] Available:
www.sabmagazine.com/blog/2011/12/21/siting-a-building-for-human-comfort/
Bothma, J. 2011. Greening the building: Plants, planting and detailing, in Green
Building Handbook South Africa - the Essential Guide Volume 3. Edited by L. Van
Wyk, Capte Town. Alive2green (pp209-226)
Bothma, J. 2010. Siting a building for Human Comfort, in Green Building Handbook South Africa - The Essential Guide Volume 2. Edited by L.V.Wyk, Cap
Town Alive2green (pp57-72)
Theron, G. and Bothma, J. 2009. The Ecology of Building and Landscape Designin Green Building Handbook South Africa Volume 1: A Guide to Ecological
Design. Edited by L. van Wyk, Cape Town: Alive2green cc (pp61-75).
Bothma, J. 2004. “Landscape and Architectural Devices for Energy-Efficient Sout
African Suburban Residential Design” Submitted in partial fulfilment of the requirements for the degree Master of Landscape Architecture. Pretoria:
University of Pretoria.
1
Curriculum Vitae TASHRIQ NAICKER
Education
BSc (Hons) Environmental Science, University of the Witwatersrand, Johannesburg, 2008
BSc Geology and Environment Conservation, University of the Witwatersrand, Johannesburg, 2007
Languages
English – Fluent
Afrikaans – Fluent
Golder Associates Africa (Pty) Ltd. – Pretoria
Environmental Practitioner
Tashriq is an Environmental Practitioner with more than nine years’ experience,
Tashriq specialises in the environmental management field.
Key experience includes:
▪ Renewable Energy Applications
▪ Environmental Impact Assessments
▪ Specialist Assistance with regard to bio-monitoring
▪ Basic Assessments
▪ Scoping & EIAs
▪ Environmental Opinions
▪ Water Use Licence Applications
▪ Waste Management Licences
▪ Mining Right Applications
▪ Section 102 Applications
▪ Geotechnical Risk Assessments
▪ Dust and Water Monitoring
▪ Section 24G Applications
▪ Due Diligence reports
▪ Peer Review on External EAP’s
Employment History
Golder Associates Africa (Pty) Ltd – Pretoria
Environmental Practitioner (May 2018 to Present)
Project Management, including conducting assessment processes, ensuring
quality control and legal compliance. Involvement with the Client and technical
project team, oversight over specialist studies and management of specialists.
Extensive Authority liaison.
GIBB (Pty) Ltd – Pretoria
Senior Environmental Scientist, Environmental Services Sector (May 2013 to
April 2018)
Complete Project Management. Conducting the S&EIR & BA Processes,
oversight on the process and ensuring quality control and legal compliance.
Extensive involvement with the Client and technical project team, oversight over
specialist studies and management of specialists. Extensive Authority liaison.
Strategic Planning with client technical team to ensure successful roll out of
projects. Financial responsibility on the projects as well as minimising company
liability.
GIBB (Pty) Ltd – Pretoria
Environmental Scientist, Environmental Services Sector (August 2012 to April
2013)
Completed various BA & EIA processes, over saw public participation and
complied Assessment Reports, Envionmental Opinions, Due Diligence reports
2
Curriculum Vitae TASHRIQ NAICKER
etc.
Strategic Environmental Focus (Pty) Ltd – Pretoria
Environmental Assistant: Environmental Services Division (March 2010 to July
2012)
Conducting BA & EIA processes, including report compilation, reviewing and
interrogation of specialist studies, extensive Client Liaison, Authority Liaison, and
public participation involvement
Strategic Environmental Focus (Pty) Ltd – Pretoria
Environmental Assistant: Environmental Services Division (April 2009 to March
2010)
Assisting in BA & EIA processes, including report compilation, reviewing and
interrogation of specialist studies, extensive Client Liaison, Authority Liaison, and
public participation involvement
3
Curriculum Vitae TASHRIQ NAICKER
PROJECT EXPERIENCE – ENERGY
Eskom Nuclear-1 EIA Eastern and Western
Cape Provinces, South Africa
Scoping & EIR process for the construction of a Nuclear facility for the generation
of electricity to strengthen the electrical grid. Position of Senior Environmental
Scientist held. Responsibilities included finalisation of the EMP, and
Environmental Impact Report. Oversight and management of the public
participation process, extensive liaison with the specialist on the project team as
well as the Client and Authorities. Responding to I&AP’s and assisting with the
logistics and facilitation of the public meetings. Review and integration of the
specialist’s studies and peer reviewed specialist studies into the report.
Responding to appeals on the positive authorisation issued.
SEF: OLAM ENERGY PROJECT 11
Mpumalanga Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: OLAM ENERGY PROJECT 10
Free State Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 9
Mpumalanga Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 8
Free State Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 7
Northern Cape Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 6
Northern Cape Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 5
Free State Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 4
Northern Cape Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 3
Northern Cape Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
4
Curriculum Vitae TASHRIQ NAICKER
SEF: TRANSALLOYS ENERGY PROJECT 1
Northern Cape Province , South Africa
BA for the establishment of a solar farm. Environmental Scientist. Conducting the
BA process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, and public participation involvement
SEF: OLAM ENERGY PROJECT 10 - 22 Kv
Powerline Free State Province ,
South Africa
BA for the construction of a power line connecting the site to the nearest
substation. Environmental Scientist. Conducting the BA process, including report
compilation, reviewing and interrogation of specialist studies, Client Liaison,
Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 8 -
22Kv Powerline Free State Province ,
South Africa
BA for the construction of a power line connecting the site to the nearest
substation. Environmental Scientist. Conducting the BA process, including report
compilation, reviewing and interrogation of specialist studies, Client Liaison,
Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 3 –
132 KV POWER LINE Northern Cape Province
, South Africa
BA for the construction of a power line connecting the site to the nearest
substation. Environmental Scientist. Conducting the BA process, including report
compilation, reviewing and interrogation of specialist studies, Client Liaison,
Authority Liaison, and public participation involvement
SEF: TRANSALLOYS ENERGY PROJECT 1 –
132 KV POWER LINE Northern Cape Province
, South Africa
BA for the construction of a power line connecting the site to the nearest
substation. Environmental Scientist. Conducting the BA process, including report
compilation, reviewing and interrogation of specialist studies, Client Liaison,
Authority Liaison, and public participation involvement
Oasis - Taaipit 132 Kv powerline
Northern Cape Province , South Africa
Project Leader and EAP. Complete Project Management. Conducting the BA
process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, extensive involvement with the project
team, and public participation involvement and management
Olien – Karats 132 kv powerline
Northern Cape Province, South Africa
Project Leader and EAP. Complete Project Management. Conducting the BA
process, including report compilation, reviewing and interrogation of specialist
studies, Client Liaison, Authority Liaison, extensive involvement with the project
team, and public participation involvement and management
Zandkopsdrift 132Kv Powerline
Western and Northern Cape Province, South
Africa
BA for the construction of a 132kV powerline approximately 82 km long. EAP
and Project Leader. Conducting the BA process, including report compilation,
reviewing and interrogation of specialist studies, Client Liaison, Authority Liaison,
extensive involvement with the project team, and public participation involvement
Caledon Wind Farm Western Cape Province ,
South Africa
Community Wind Energy Facility. Environmental Scientist role. Responsible for
Authority and client liaison. Overseeing of additional public participation.
PROJECT EXPERIENCE – PROJECT MANAGEMENT
PPC Van Rhyns Dorp - Search and Rescue
Western Cape Province, South Africa
Complete Project Management. Oversight on the search and rescue process
and ensuring quality control and legal compliance with the Rehabilitation Audits.
Extensive involvement with the Client and technical project team, oversight over
specialist studies and management of specialists.
5
Curriculum Vitae TASHRIQ NAICKER
PROFESSIONAL AFFILIATIONS
South African Council for Natural and Scientific Professions (SACNASP)
International Association for Impact Assessment - South African Charter (IAIAsa)
golder.com