Upload
phamduong
View
219
Download
2
Embed Size (px)
Citation preview
9435370_1
INSTALLATION OF THE MARINA ROSE BAY MARINA
CONSTRUCTION MANAGEMENT PLAN
For Environmental Management
September 2008
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
CONTENTS
1.0 Introduction 2.0 Definitions and Abbreviations 3.0 Philosophy
3.1 Statement 3.2 Environmental Management Policy
4.0 Aims and Objectives
4.1 Description of the Project 4.2 Aims of EMP
5.0 Management
5.1 Scope 5.2 Compliance, Regulations, Approvals 5.3 Management Process
6.0 Environmental Impacts 7.0 Work Instructions 8.0 CMP Reporting 9.0 Conclusion Appendices 1. Locality map 2. Program of works 3. Environmental Incident/Complaint Report Form 4. Site Walkover Check 5. Site personnel register ATTACHMENT A - Environmental Management Plan
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
1. INTRODUCTION This CMP describes the environmental planning issues related to the installation of a floating marina. The CMP relates to the design and construction of a new floating concrete marina, pile installation, gangways, services and fittings. This plan describes the nature and scope of anticipated environmental impacts, addresses relevant legislation and approval conditions and outlines action to be taken to ensure compliance and to mitigate the environmental impacts identified before and throughout the execution of the construction contract. This plan incorporates details of proposed sediment control, waste management, noise management and traffic management. A Environmental Management Plan, comprising a summary table developed from this document suitable for use by site contractors, is included as Attachment A. 2. DEFINITIONS & ABBREVIATIONS RBM Rose Bay Marina CMP Construction Management Plan ESD Ecologically Sustainable Development EIS Environmental Impact Statement DECC Department of Environment & Climate Change NTU Nephelometric Turbidity Units TSS Total Suspended Solids
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
3. PHILOSOPHY 3.1 STATEMENT RBM’s vision for our marinas is the completion of a project that will provide an excellent marina facility for clients and the boating public and to demonstrate during the construction process, commitment to optimum environmental performance. The environmental outcome should be a completed project, which has not permanently, adversely impacted on the air or water quality, the flora and fauna, their habitat or the surrounding community of the marina site during construction, successful measures will be implemented to minimise any temporary, adverse effects on the environment. RBM wishes to be associated with a marina facility, which will improve the amenity for marina users and the community and complement the foreshore with low profile design. The marina pontoon units will provide sanctuary for rapid colonisation by marine life and have positive implications for marine colonies. 3.2 ENVIRONMENTAL MANAGEMENT POLICY RBM aims to ensure the environment is not harmed in any way on any of its projects. It is our objective that the environment is to be enhanced in areas where our products are installed. RBM has the financial and human resources to formulate and implement environmental strategies in their offices and at worksites. Subcontractors are expected to meet RBM environmental standards and are encouraged by example and familiarisation with sensitive environmental issues at particular worksites to ensure that RBM’s policy is successful.
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
4. AIMS AND OBJECTIVES 4.1 DESCRIPTION OF THE PROJECT ⇒ Integrated design floating marina, associated gangways.
⇒ Supply design documentation for approval.
⇒ Fabricate pontoons for the floating marina.
⇒ Supply and install piling to secure the pontoons.
⇒ Install marina, complete with pile guide systems, timber walers, thru-bolts, infill panels,
cleats, and fendering.
⇒ Supply and install all associated gangways to the marina.
⇒ Install the associated services to the marina
4.2 AIMS OF CMP
⇒ To establish ESD framework. (Guidelines for ESD as applied to building materials are
addressed elsewhere in the CMP.)
⇒ To establish the environmental management process involving co-operation between RBM
staff, other contractors at the site and subcontractors, to ensure understanding of the key
environmental issues for this project so that objectives and targets are met. Standard and
site specific procedures and equipment for mitigation of environmental damage will be
implemented and used.
⇒ To satisfactorily manage contaminated sediments during the construction phase of the
marina.
⇒ To realise optimum performance in the key areas of piling (noise, disturbance to seabed,
water quality) and waste minimisation/disposal to complete this project and achieve a ‘nil’
recording of environmental incident. To achieve these objectives all site workers will be
inducted at site and instructed in their responsibilities of care and reporting and familiarised
with environmental safeguards.
⇒ Identify statutory and non-statutory responsibilities.
⇒ To document the environmental management process.
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
5. MANAGEMENT
5.1 SCOPE
The indicative site boundaries for the contract are to be as shown in the plan of the site locality attached in Appendix 1. The CMP covers the whole of the design and construction process including fabrication, demolition, piling, transportation, assembly, utilities and site maintenance. 5.2 MANAGEMENT PROCESS
It is proposed to manage the CMP by identifying a number of distinct phases and to arrange consultation and reporting to coincide with specific stages of the contract. These specific phases will be design/certification, fabrication, demolition, piling, transport and installation. At the design/certification phase consultation will be between the Principal, Project Engineers, RBM and Consulting Engineers. Upon completion of this phase, RBM will ensure that documents for the final design that is submitted for approval incorporate specific environmental considerations and comply with AS 3962- 2001 – Guidelines for the Design of Marinas. The fabrication phase involves production of the marina pontoons, gangways, timber and bracket components at the Pontoon construction factory. At the plant, raw materials and components are purchased to plant scheduling to minimise waste. Any concrete waste from the casting process is fabricated into ‘environmental blocks’ and incorporated into anchoring systems or abutments. Noise reduction has been achieved by selecting immersion vibrators. Runoff from cleaning operations is contained at site. The plant does not create pollutants, being in the main a casting facility with separate areas for drilling and docking of timber and metal fabrication. Sub-assembly of pontoons will be completed at the factory to minimise on-site construction. No hazardous chemicals are used in the manufacturing process. Construction materials are environmentally inert. Plantation timber is to be used wherever possible, rubbing blocks made from regranulated waste will be purchased for pile fixing assemblies, the bulk of transport dunnage will be back-loaded for re-use. During the piling phase, notification to neighbours will be made prior to piling phase and the recommendations of the noise impact assessment and noise management plan will be incorporated. Operations will be monitored with consultation between the piling operator and the RBM Project Manager. All vessels used at site for demolition and piling works will be in current survey. The hours of operation will be checked and the progress of installation for each pile will be recorded. Any complaints from the public or any authority and all details of any complaint will be noted and reported to the Principal, investigated and acted upon as appropriate.
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
Delivery and transport of materials to and from site will be by water. Deliveries of marina pontoons and fittings will be by semi-trailer to a suitable wharf area for unloading and pushed into position on site. Travel to the wharves will be undertaken only on designated trucking routes. Deliveries will be timed to avoid peak traffic periods and within specified times for movement according to RTA regulations for truck and load sizes. Cranes used in the unloading operation will also travel during RTA regulated hours. There is little waste generated by these operations. Delivery of pontoons will be monitored as dunnage is to be back-loaded on the final delivery truck each day and sub-assembly adjacent to the wharf will generate some waste. Packing material such as metal banding will be disposed of in appropriate bins maintained at site or within designated areas for recycling at a Waste Transfer Station. The amount of waste is expected to be minimal. Piles will be delivered to suitable wharves and transported by barge to site. All transport on water will be by barge or towage. The Port Authority will be advised of towage movements. All vessels used for transport will be in current Survey. The Superintendent will be informed of the timing of deliveries to site. Marina construction/ installation will be by an approved sub-contractor under the supervision of the RBM Project Manager. Site induction of all sub-contractors will be compulsory and induction will include familiarisation with incident forms, common-sense environmental measures to avoid spillage, provision for waste disposal and the particular environmental issues at the site. All sub-contractors will review relevant management plans for their section of the works at the site induction. There will be daily consultation between sub-contractors and RBM’s Project Manager. All construction activities must be undertaken during daylight hours. 5.3 RESPONSIBILITY STRUCTURE The Project Team and responsibilities follow: The RBM Project Manager Role is to:
Deal directly with the Principal’s appointed Superintendent Liaise with all involved in the design process Liaise with the Production and Quality Assurance teams Oversee transport of materials and supervise all unloading Conduct site induction and site inspections Oversee the piling operations Oversee all sub-contract work including installation and services works and to ensure EMP
procedures are followed Distribute RBM Safety Manual Complete Environmental Incident Report (appendix 3), Site Walkover Check (appendix 4)
and Site Personnel Register (appendix 5) The RBM Administrative Assistant Role is to:
Compile documentation pertinent to the contract including CMP documentation and reporting.
Register, report and respond to public inquiry or complaints on environmental or other construction matters.
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
The Construction Team Structure is to be compiled and advised subsequent to confirmation of the date for commencement at site. 6. ENVIRONMENTAL IMPACTS The possible environmental impacts identified for the works under this project, mitigation and amelioration measures are: Contaminated sediments and possible disturbance to the seabed during pile installation Contaminated sediments exist within part of the area occupied by Rose Bay Marina. The approximate extent of the contaminated sediments is shown together within the existing facilities and an outline of the proposed new facilities on Figure 1. The contaminants of concern are copper, mercury, lead, Polycyclic Aromatic Hydrocarbons (PAHs) and Tributyltin (TBT). The sources of contamination are considered to comprise a combination of estuary wide sources (diffuse source urban runoff entering the Parramatta River and Sydney Harbour upstream), atmospheric sources, and local sources comprising nearby stormwater outlets the former slipway at Rose Bay Marina. It is important that activities undertaken during construction of the marinas do not cause significant disturbance of the contaminated sediments. Such activities could potentially include demolition, particularly extraction of piles, and installation of new piles. While any disturbance of the seabed is expected to be minimal, localised and temporary, the following measures and procedures shall be adopted for contaminated sediment management:
Extraction of piles in the area of Rose Bay Marina slipway, as generally defined by the shading on Figure 1 and to be confirmed on site by an experienced environmental consultant, shall be undertaken within a metal sleeve placed over the pile prior to extraction.
Driving of new piles in the area described above shall also be undertaken within a metal
sleeve.
In addition, whilst any demolition or construction activities are being carried out in the area described above this area shall be completely contained by a turbidity curtain that extends fully to the seabed and is suitably weighted on the seabed.
Monitoring of turbidity outside the turbidity curtain at a distance of 2m from the curtain and
at a control location(s) shall be undertaken on a daily basis during the works. The number of monitoring locations, the depth(s) in the water column at which monitoring takes place and trigger values for any corrective action shall be approved by the Department of Environment and Climate Change prior to commencement of construction.
If the levels of turbidity established by the monitoring exceed the trigger value, the
Contractor shall immediately investigate the exceedance and implement corrective measures. These measures shall include, but not necessarily be limited to, inspection of the turbidity curtain for any damage or defect and the carrying out of repairs if required, continuous monitoring of turbidity levels until such time as turbidity levels at the monitoring locations outside the curtain fall below the trigger level or construction activity is ceased, modification of the construction methodology to ensure exceedances do not persist
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
including ceasing work if required, and notification of the exceedance to the Superintendent.
The results of all monitoring activities shall be included in a monthly report submitted to the
Superintendent. The report shall note any non-compliances and corrective actions.
9435
370_
1
9435370_1
Noise of piling works
Equipment will be maintained in good working order.
Multiple use of items of equipment will be limited to avoid aggregation of noise levels.
Construction site working hours will be strictly observed ie. 8.00 am to 5.00 p.m., on weekdays and 8.00 am to 1.00 PM on Saturdays.
Further restrictions to hours of operation will apply to piling and specifically piling is to be
carried out using a piling rig with a L10 15 minute sound power level no greater than 105 dB(A) (as specified in the EIS). Piling is not to occur before 8 am or after 5 pm on any weekday or before or before 8 am or after 1 pm on a Saturday, and there must be a 15 minute break every hour.
During the piling stage of the works noise will be generated and the amenity of local residents could be affected. Previous experience showed that the noise generated by piling activity cannot be noticed within buildings in the immediate vicinity of the works. Previously, no complaint has been recorded at any work sites. Several mitigation measures will be taken to minimise the impact of piling noise. Noise impacts are detailed in the EIS and will be managed through standard piling techniques such as acoustically treated driving heads. The proposed piling contractor has worked successfully on several projects to satisfy goals of lowest possible noise and inconvenience. Piling shall be generally undertaken in accordance with the following:
The method of piling to be used is the drop hammer method.
Acoustic packing will be used between the base of the driving helmet and the hammer.
Piling time limits will be strictly observed except in cases where safety may be compromised. The general hours of piling operations will be from 8.00 am to 12.00 pm and 2.00 pm to 5.00 pm. Monday to Friday, and on Saturdays between 8.00 am and 1.00 pm.
Complaints will be entered in a logbook. Where possible, residents’ concerns will be
addressed. A copy of the logbook will be available to the DECC. Noise during construction of the marina Sub-assembly will be completed off-site to minimise construction time on site. There will be no tools used for construction of the new marina that could cause unacceptable noise levels. Compressors will be of a size to operate hand power tools and will be used intermittently only until power is established on the marina. Localised traffic pressure during construction
It is unlikely that construction works will contribute to traffic pressure. There will be visits to site usually daily by the RBM Project Manager during the piling and construction phase. During this period it is anticipated that a maximum of six vehicles per day will visit the worksite. These will be the work vehicles of RBM’s appointed surveyor, installation personnel and sub-contractors.
Semi trailers will deliver loads of pontoons and associated materials to a commercial wharf,
avoiding peak hour traffic and within RTA regulated times pertaining to load sizes. All deliveries will be to the area at the commercial wharf and then barged to site.
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
Crane will remain barricaded off until all unloading is completed.
Piles will be delivered to site by barge. The Supervisor will co-ordinate water-based activity with all other users. RBM, due to the very manoeuvrable nature of the piling and assemble work, will not require an exclusion zone on the water during construction.
Pollution of sea or seabed from construction works
Sub-contractors will be instructed to keep tools and materials contained and to maintain good housekeeping to ensure that wrappings, nuts, bolts, flex/conduit off-cuts etc. do not fall into the water. Timber off-cuts and shavings are to be cleaned from the pontoon surfaces and placed in bags as soon as possible to prevent them from entering the water. Metal hardware such as bolts and washers will leave rust marks on the decks - these are to be kept in containers. Any unnecessary cleaning is to be avoided and the best preventive measures will be implemented. Waste bins will be provided on-shore.
Any material that does fall into the water will be removed immediately.
The pile barge is to be kept clean and clear of unnecessary waste materials. Operational
oil or fuel cans will be stored appropriately, containers are securely fastened and all pile barges are equipped with oil absorbent pads.
Workboats are to be refuelled off-site and bilge water will not be discharged.
Waste generated by construction work Pre-assembly will ensure that on-site waste is minimal. All waste from construction works will be placed in bins appropriate to the material. Bins will be provided on-shore for recyclables and putrescible/mixed waste and emptied regularly. Any waste at wharf loading/unloading sites or brought to wharf sites by barge will also be placed in appropriate recycling bins to limit the use of landfill tips. Any treated timber off-cuts should not be burnt. These will be disposed of in bins. No materials are to be burnt. Where appropriate, all material that can be recycled will be taken to merchants specialising in the particular material. Marine ecology The commitments made in the EIS must be carried out including carrying out a final field survey prior to commencement of construction to accurately locate current seagrass beds and Caulerpa patches to be used in a Marine Vegetation (Seagrass and Caulerpa) Management Plan. The NSW DPI Caulerpa Management Plan is to be implemented.
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
7. WORK INSTRUCTIONS At the time of placement of order, all sub-contractors and site workers will be instructed in the level of best environmental practice expected at the Site. Instruction will be given at induction on the location of waste bins and RBM’s expectation that the worksite be maintained in a tidy manner at all times. Workers will be advised that waste and construction materials are not to fall into the water and that if they are, they are to be removed immediately. All equipment will be inspected and properly maintained. 8. CMP REPORTING
Report weekly on piling operations to Principal. This will document any complaints, incidents or evidence of non-compliance.
Report weekly once installation commences to the Superintendent, covering outcomes of
pollution control and waste management.
Environmental incident reports (appendix 3) Completed at site or office (source of incident report). Promptly notified to the Project
Manager in the case of environmental incident or complaint. All complaints will be noted and reported to the Principal and the relevant authority notified if appropriate. Where appropriate, the incident will also be investigated and action taken to minimise any adverse environmental effects wherever possible.
Site walkover check (appendix 4)
This document checks compliance and records corrective measures taken. Completed weekly by or submitted to the Project Manager.
Site personnel register (appendix 5)
Completed at induction and returned to office to be kept on file.
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
9. CONCLUSION The CMP has set goals for optimum environmental outcome for the design and construction work associated with the new Marina. Any environmental impacts will be short-term over a construction period on site of approximately 21 weeks with piling over approximately 9 weeks. It has been shown that resources and action will be applied to ensure that RBM’s role in the construction delivers a project with exemplary environmental management. Design considerations have produced a marina with low visual profile which while serving the requirements of the marina owners, occupiers and visitors and providing safer berthing, will provide an extended sanctuary for new colonisation of marine flora and fauna. Maintenance requirements for the new marina will be minimal. The overall outcome will be a long-lasting positive contribution to the marina industry and the locality.
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
APPENDIX 1
LOCALITY MAP
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
APPENDIX 2 PROGRAM OF WORKS
TIVITC
AMETI
YN
OTE
STY
PIC
AL
PLA
NT
AN
D E
QU
IPM
ENT
Wee
k1
23
45
67
89
1011
1213
1415
1617
1819
2021
2223
241
Site
est
ablis
hmen
tB
arge
s, li
ght c
omm
erci
al v
ehic
les
and
hand
hel
d po
wer
tool
s
shtreb 64 shtreb gnitaolf fo noitallatsnI
2yad rep selip 2 gnilip gir 1 - seli
P 83gnili
P1.2
Pili
ng b
arge
whi
h w
ill s
crew
pile
s in
to s
ea b
edA
mrA ta sregnif
m01 x 4 dna C
mrA no shtreb
m51 x 73snootnop gnitaolf fo noitallatsnI
2.2B
arge
s, li
ght c
omm
erci
al v
ehic
les
and
hand
hel
d po
wer
tool
sslee
R esoH eriF kcal
B dna anihC - stao
B yhganoCc
M yb tliub slatsedeP
motsuC
sleeR eso
H eriF dna slatsedeP fo noitallatsnI
3.2Li
ght c
omm
erci
al v
ehic
les
and
hand
hel
d po
wer
tool
s2.
4In
stal
l CC
TV C
amer
a sy
stem
and
oth
er c
utom
ele
men
tsLi
ght c
omm
erci
al v
ehic
les
and
hand
hel
d po
wer
tool
s
3Se
rvic
es
3.1
Con
nect
ion
to e
xist
ing
Pow
er a
nd W
ater
Ser
vice
sE
xist
ing
serv
ices
hav
e ex
cess
cap
acity
to s
ervi
ce p
ropo
sed
expa
nsio
nLi
ght c
omm
erci
al v
ehic
les
and
hand
hel
d po
wer
tool
s
4Si
te re
stor
atio
n/cl
eanu
pB
arge
s, li
ght c
omm
erci
al v
ehic
les
and
hand
hel
d po
wer
tool
s
RED
EVEL
OPM
ENT
OF
RO
SE B
AY
AN
D P
OIN
T PI
PER
MA
RIN
AS
- PR
ELIM
INA
RY
CO
NST
RU
CTI
ON
PR
OG
RA
M -
Febr
uary
201
2
DU
RA
TIO
N O
F A
CTI
VITI
ES
Pag
e 1
App
endi
x Q
9435370_1
APPENDIX 3 ENVIRONMENTAL INCIDENT/COMPLAINT REPORT Any accident or incident, which may impact on the environment, MUST be reported Any complaint MUST be recorded and reported Accident/Incident/Complaint ..................................... Date: ............................. Time: ................................ LOCATION AND DURATION/SOURCE OF INCIDENT/COMPLAINT
...........................................................................................................................................................................
...........................................................................................................................................................................
PERSON REPORTING
........................................................................................................................................................................... NATURE/DETAILS OF INCIDENT/COMPLAINT/QUANTITY OF POLLUTANTS ETC.
...........................................................................................................................................................................
...........................................................................................................................................................................
ACTUAL OR SUSPECTED CAUSE
...........................................................................................................................................................................
...........................................................................................................................................................................
ACTION TAKEN OR PROPOSED ACTION – MANAGEMENT & PREVENTION
...........................................................................................................................................................................
...........................................................................................................................................................................
CONTRACTOR ........................................................................................................................................................................... REPORTED TO DECC 13 1555 ................................................................................................... Client ................................................................................................... SIGNATURE......................................................................................................................................................
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
APPENDIX 4 ENVIRONMENTAL MANAGEMENT PLAN
SITE WALKOVER CHECK Waste Sorted Bin Required/Changeover Required? Construction Materials Stacked/Contained Equipment secured and operating correctly Workboat (if used) – Fuel tank removed and stored each night Check Work Site & Car Park – Clean of Rubbish, General Housekeeping Corrective Measures Date: ___________________________ Name: ___________________________ Signature: _____________________
CONSTRUCTION MANAGEMENT PLAN
ROSE BAY MARINA
APPENDIX 5 SITE PERSONNEL REGISTER EMPLOYEE NAME: EMPLOYEE ADDRESS: DATE OF BIRTH: NEXT OF KIN: PHONE NO: RELATIONSHIP: ADDRESS BLOOD GROUP: (Optional)
ALLERGIES: HEALTH DETAILS: (i.e. diabeties, colour blindness, deafness, asthmatic etc)
EMPLOYER’S NAME: EMPLOYER’S ADDRESS: EMPLOYER’S PHONE №: CERTIFICATES/TICKETS SIGHTED: First Aid
Crane Operator Dogman Ticket Other
I have been inducted by my employer on the relevant safe work procedures for my works on the project. Yes / No I agree to wear safety shoes and safety helmets whilst working on the project at all times. Yes / No I agree to abide by the requirements of Rose Bay & Point Piper Marinas and/or any direction by them in relation to the health and welfare for the site generally. Yes / No Employee’s signature ________________________________ Date: ___________________
9435370_1
ATTACHMENT A
9435
370_
1
Pr
elim
inar
y Si
te E
nviro
nmen
tal M
anag
emen
t Pla
n
Proj
ect:
Ros
e B
ay M
arin
a
Pr
inci
ple:
Add
enbr
ooke
Pty
Ltd
N
omin
ated
Env
ironm
enta
l Offi
cer r
espo
nsib
le fo
r Env
ironm
enta
l Iss
ues
K
ey Is
sues
: Mai
ntai
n aw
aren
ess
of th
e en
viro
nmen
tally
sen
sitiv
e as
pect
s of
the
site
dur
ing
all w
ork
func
tions
. Ite
m
Pote
ntia
l Im
pact
Pr
even
tativ
e / R
emed
ial A
ctio
n 1.
CO
NSE
RVA
TIO
N O
F PL
AN
TS &
W
ILD
LIFE
•
Pos
sibl
e di
stur
banc
e of
Pla
nts
and
Wild
life
lead
ing
to e
nviro
nmen
tal i
ncid
ent
and
disr
uptio
n of
wor
k
• P
rote
ct e
xist
ing
trees
and
pla
nts
at a
nd a
roun
d th
e S
ite
from
dam
age
and
do n
ot re
mov
e flo
ra w
ithou
t app
rova
l fro
m th
e P
rinci
pal
• P
rote
ct b
irds,
fish
and
ani
mal
s at
and
aro
und
the
Site
from
ha
rm a
nd d
o no
t rem
ove
faun
a fro
m th
e S
ite w
ithou
t ap
prov
al fr
om th
e P
rinci
pal
• E
nsur
e th
at a
nim
als
and
plan
ts a
re n
ot b
roug
ht o
nto
the
Site
with
out t
he w
ritte
n ag
reem
ent o
f the
Prin
cipa
l •
Use
site
road
s or
app
rove
d ac
cess
rout
es fo
r veh
icul
ar a
nd
equi
pmen
t acc
ess
• P
ark
all v
ehic
les
and
equi
pmen
t in
desi
gnat
ed a
reas
•
Use
app
rove
d ac
cess
rout
es fo
r all
pede
stria
n an
d go
ods
mov
emen
ts to
veh
icle
s, e
quip
men
t, an
d fa
cilit
ies
2.
CO
NSE
RVA
TIO
N O
F R
ESO
UR
CES
•
Nee
d to
con
trol m
ater
ials
use
d to
redu
ce
– re
sour
ce u
se
– oz
one
depl
etin
g ef
fect
s –
detri
men
tal e
ffect
s on
air,
wat
er,
qual
ity
• M
inim
ise
the
use
of im
porte
d to
psoi
l •
Reu
se a
ll to
psoi
l on
site
•
Max
imis
e th
e us
e of
mat
eria
ls fr
om a
sus
tain
able
sou
rce,
th
at a
re, a
nd/o
r can
be,
recy
cled
•
Min
imis
e th
e us
e of
sol
vent
s, g
lues
, pai
nts
and
othe
r m
ater
ials
whi
ch re
leas
e od
ours
or v
apou
r
3. P
OLL
UTI
ON
CO
NTR
OL
Item
Po
tent
ial I
mpa
ct
Prev
enta
tive
/ Rem
edia
l Act
ion
i) W
ater
Pol
lutio
n a)
Silt
Cur
tain
/Tur
bidi
ty B
arrie
r •
Pot
entia
l env
ironm
enta
l iss
ue d
ue to
in
abili
ty to
cap
ture
out
flow
and
di
stur
banc
e of
sed
imen
ts w
ithin
a d
efin
ed
area
• D
eter
min
e re
quire
men
ts fo
r Silt
Cur
tain
/Tur
bidi
ty B
arrie
r •
Ens
ure
silt
curta
in/T
urbi
dity
Bar
rier i
s es
tabl
ishe
d ar
ound
w
ork
perim
eter
and
sed
imen
ts w
here
nec
essa
ry
• In
spec
t silt
cur
tain
/Tur
bidi
ty B
arrie
r reg
ular
ly fo
r sig
ns o
f da
mag
e •
Wor
k to
cea
se im
med
iate
ly if
silt
cur
tain
/Tur
bidi
ty B
arrie
r is
dam
aged
•
Rep
air a
ny d
amag
e to
silt
cur
tain
/Tur
bidi
ty B
arrie
r bef
ore
wor
k re
com
men
ces
b) D
istu
rban
ce o
f Sea
bed
• P
oten
tial e
nviro
nmen
tal i
ssue
due
to
exis
ting
leve
l of c
onta
min
atio
n
• M
inim
ise
mot
oriz
ed m
ovem
ents
of c
rane
bar
ge a
nd
supp
ort v
esse
ls –
din
ghys
etc
•
Inst
all a
dditi
onal
turb
idity
cur
tain
s ar
ound
con
tam
inat
ed
sedi
men
ts fo
r dur
atio
n of
wor
ks
c) R
esid
ue F
rom
Exi
stin
g P
ipew
ork
•
Pos
sibl
e sp
illag
e in
to w
ater
bel
ow
resu
lting
in c
onta
min
atio
n or
dis
turb
ance
of
sea
bed
and
mar
ine
ecos
yste
m
• M
inim
ise
and
cont
rol f
alls
of o
ffcut
s an
d de
bris
into
wat
er
as id
entif
ied
belo
w
d) C
oncr
ete
Offc
uts
• P
ossi
ble
fall
into
wat
er b
elow
resu
lting
in
cont
amin
atio
n or
dis
turb
ance
of s
eabe
d •
Min
imis
e di
stur
banc
e to
fine
bed
sed
imen
ts, e
nsur
e tu
rbid
ity c
urta
in s
edim
ent c
onta
inm
ent a
nd c
onfin
emen
t is
in p
lace
. e)
Con
cret
e S
lurr
y
• P
ossi
ble
topp
ling
/ spi
llage
into
wat
er
belo
w re
sulti
ng in
con
tam
inat
ion
or
dist
urba
nce
of s
eabe
d
• C
onfir
m d
isco
ntin
uatio
n of
ser
vice
s be
fore
pip
es a
re
disc
onne
cted
. Flu
sh o
ut p
ipew
ork
and
capt
ure
any
back
was
h in
a c
onta
iner
•
Follo
w p
rope
r rul
es fo
r Cut
ting
of C
oncr
ete
and
Pile
s f)
Tim
ber D
ebris
• M
inim
ise
any
debr
is le
avin
g si
te v
ia
curta
ins
and
awar
enes
s
• E
nsur
e de
bris
cap
turin
g m
echa
nism
s ar
e in
pla
ce b
elow
de
ck b
efor
e co
ncre
te o
r tim
ber c
uttin
g co
mm
ence
s •
Mai
ntai
n aw
aren
ess
of im
pact
of t
imbe
r offc
uts
whe
n cu
tting
or l
iftin
g pi
les
g) S
tock
pile
d M
ater
ials
• M
anag
emen
t of o
nsite
mat
eria
l
• M
inim
ise
leve
l of b
ulk
mat
eria
ls b
ags
on s
ite
• C
arry
out
vis
ual i
nspe
ctio
n of
bag
s fo
r sig
ns o
f spl
ittin
g be
fore
lifti
ng c
omm
ence
s •
Ens
ure
all w
aste
mat
eria
ls a
re n
eatly
sta
cked
to a
void
to
pplin
g.
• S
ecur
e w
ith R
opes
or c
hain
s if
requ
ired
• M
inim
ise
stor
age
time
befo
re re
mov
al to
oth
er a
reas
or
was
te d
ispo
sal f
acili
ty
Item
Po
tent
ial I
mpa
ct
Prev
enta
tive
/ Rem
edia
l Act
ion
ii) V
ehic
les
and
Pla
nt
•
Pos
sibl
e da
mag
e to
site
aris
ing
from
m
alfu
nctio
ning
equ
ipm
ent
• P
oten
tial f
or s
pilla
ge in
to w
ater
•
Pot
entia
l fue
l spi
llage
dur
ing
refu
elin
g
• C
ondu
ct re
gula
r ins
pect
ions
of a
ll m
achi
nery
for
evid
ence
of l
eaks
or l
oose
con
nect
ions
on
hose
s or
pr
oduc
ing
exce
ssiv
e em
issi
ons
and
rect
ify im
med
iate
ly
• E
nsur
e sp
ill k
it is
read
ily a
vaila
ble
and
clos
e to
wor
k ar
ea
• U
se s
pill
kit t
o co
ntai
n an
y sp
illag
e •
Ens
ure
all f
uel s
tora
ge is
pro
perly
bun
ded
• E
nsur
e “C
ontro
lled
Han
d P
umpi
ng M
etho
d is
the
pref
erre
d m
etho
d of
refu
ellin
g w
hene
ver p
ossi
ble
iii) A
ir P
ollu
tion
from
dus
t and
em
issi
ons
min
imiz
ed
Pos
sibl
e da
mag
e to
env
ironm
ent a
risin
g fro
m
exce
ssiv
e om
issi
ons
or o
dors
from
pile
s •
Min
imis
e ar
eas
of e
xpos
ed e
arth
•
Use
wat
er s
pray
s an
d/or
oth
er m
eans
to c
ontro
l dus
t •
Kee
p em
issi
ons
with
in s
tatu
tory
or r
equi
red
limits
iv
) Noi
se im
pact
on
neig
hbou
rs,
occu
pant
s or
use
rs o
f fa
cilit
y m
inim
ised
H
ealth
Impl
icat
ions
for p
erso
nnel
on
site
and
su
rrou
ndin
g oc
cupa
nts
• K
eep
with
in E
PA
and
Cou
ncil
nois
e lim
its
• A
dher
e to
site
rule
s re
gard
ing
oper
atin
g tim
es a
nd
rest
rictio
ns
• U
se e
quip
men
t in
good
repa
ir an
d co
nditi
on
• U
se n
oise
sup
pres
sion
equ
ipm
ent (
eg. S
ilenc
ers
and
muf
flers
on
com
pres
sors
and
equ
ipm
ent)
• D
o no
t exp
ose
wor
kers
and
vis
itors
to e
xces
sive
noi
se
• S
ee A
ppen
dix
M o
f Env
ironm
enta
l Im
pact
Sta
tem
ent f
or
deta
ils o
f mea
sure
s.
4. D
ISPO
SAL
OF
WA
STE
• E
nsur
e w
aste
item
s ar
e di
spos
ed o
f in
acc
orda
nce
with
the
Was
te
Man
agem
ent P
lan.
• P
oten
tial e
nviro
nmen
tal i
ncid
ent a
risin
g fro
m in
effe
ctiv
e W
aste
Man
agem
ent P
lan
or fa
ilure
to a
dher
e to
pla
n
• P
rovi
de v
alid
dis
posa
l cer
tific
ates
for e
ach
appl
icab
le
item
. •
Sub
mit
was
te d
ispo
sal c
ertif
icat
es o
r cer
tific
atio
n of
ap
prop
riate
dis
posa
l to
the
Prin
cipa
l whe
re a
pplic
able
•
Was
te –
Con
cret
e
• P
ossi
ble
fall
into
wat
er b
elow
resu
lting
in
cont
amin
atio
n or
dis
turb
ance
of s
eabe
d •
Larg
e B
lock
s
• E
nsur
e pr
oper
sta
ckin
g on
dum
b ba
rge
•
Ens
ure
barg
e is
not
ove
rload
ed
• S
ecur
e lo
ad w
hen
trans
porti
ng fr
om s
ite
• Sm
all B
lock
s •
Ens
ure
bloc
ks a
re w
ithin
wei
ght c
apac
ity o
f col
es c
rane
•
Ens
ure
bloc
ks a
re p
rope
rly lo
aded
into
ded
icat
ed
disp
osal
bin
s
Item
Po
tent
ial I
mpa
ct
Prev
enta
tive
/ Rem
edia
l Act
ion
• W
aste
– T
imbe
r
• E
nsur
e pr
oper
sta
ckin
g on
dum
b ba
rge
•
Ens
ure
barg
e is
not
ove
rload
ed
• S
ecur
e lo
ad w
hen
trans
porti
ng fr
om s
ite
• R
emov
e to
land
bas
e •
Was
te ti
mbe
r to
be lo
aded
into
des
igna
ted
bins
and
tra
nspo
rted
to a
n “a
utho
rised
recy
clin
g de
pot”
5. E
MER
GEN
CIE
S •
Pos
sibl
e he
ight
ened
env
ironm
enta
l in
cide
nt a
risin
g fro
m fa
ilure
to a
dher
e to
em
erge
ncy
plan
• E
nsur
e em
erge
ncy
proc
edur
es a
re u
sed
to m
anag
e al
l re
ason
ably
fore
seea
ble
harm
, inc
ludi
ng s
pills
and
oth
er
envi
ronm
enta
l em
erge
ncie
s •
Ens
ure
all e
mpl
oyee
s / s
ub-c
ontra
ctor
s ar
e tra
ined
in s
ite
emer
genc
y pr
oced
ures
•
Doc
umen
t key
con
tact
s
6. IN
CID
ENT
REP
OR
TIN
G
• Fa
ilure
s to
pro
perly
repo
rt in
cide
nts
coul
d re
sult
in la
ck o
f fut
ure
prev
enta
tive
mec
hani
sms
and
lead
to m
ore
seve
re
inci
dent
s
• Im
med
iate
ly re
port
all e
nviro
nmen
tal i
ncid
ents
to th
e P
rinci
pal i
n ac
cord
ance
with
Rep
ortin
g P
roce
dure
s
7. C
OM
PLIA
NC
E
• C
ompl
ianc
e w
ith P
rinci
pal e
nviro
nmen
tal
requ
irem
ents
and
, whe
re b
reac
hes
are
dete
cted
, rec
tific
atio
n of
def
ects
with
in
the
time
perio
d se
t in
the
audi
t pro
cess
• In
spec
t the
Site
dai
ly to
ens
ure
the
appr
opria
te
envi
ronm
enta
l con
trols
are
in p
lace
and
are
ope
ratin
g ef
fect
ivel
y, a
nd to
ens
ure
all e
nviro
nmen
tal m
anag
emen
t re
quire
men
ts a
re b
eing
met
•
Coo
pera
te w
ith e
nviro
nmen
tal a
udits
by
othe
rs
• R
ectif
y an
y en
viro
nmen
tal b
reac
hes
iden
tifie
d w
ithin
the
time
fram
e sp
ecifi
ed in
an
audi
t or b
y th
e P
rinci
pal
8.
REC
OR
DS
Item
Po
tent
ial I
mpa
ct
Prev
enta
tive
/ Rem
edia
l Act
ion
Rec
ords
S
uffic
ient
doc
umen
tatio
n to
dem
onst
rate
: •
App
rove
d m
anag
emen
t pla
ns
• Tr
aini
ng re
cord
s •
Val
id d
ispo
sal c
ertif
icat
es a
nd/o
r co
mpa
ny c
ertif
icat
ion
of a
ppro
pria
te
disp
osal
as
appl
icab
le
• C
orre
spon
denc
e w
ith re
gula
tors
in
clud
ing
evid
ence
that
the
caus
e of
no
n-co
mpl
ianc
es h
as b
een
fixed
K
eep
train
ing
reco
rds
for i
nspe
ctio
n
Envi
ronm
enta
l Man
agem
ent S
tate
men
t Pre
pare
d by
___
____
____
____
____
____
____
____
__
Aut
horis
ed B
y __
____
____
____
____
____
____
____
_
Acc
epte
d B
y___
____
____
____
____
___
(Prin
t Nam
e)
____
____
____
____
____
____
___
(Sig
natu
re)
On
Beh
alf o
f Inf
inity
Con
stru
ctio
ns –
____
____
____
____
____
____
____
__
Dat
e __
____
____
____
___
PAR
T 5:
SU
PER
VISO
RS
SIG
N-O
FF
By
sign
ing
this
, I a
ckno
wle
dge
that
I am
aw
are
of a
nd a
gree
with
the
envi
ronm
enta
l iss
ues
desc
ribed
in th
is d
ocum
ent.
I ag
ree
to s
ee th
at th
e pr
even
tativ
e /
rem
edia
l act
ions
are
impl
emen
ted.
I w
ill co
mm
unic
ate
the
envi
ronm
enta
l iss
ues
to e
ach
mem
ber o
f the
wor
k cr
ew a
nd re
spon
d im
med
iate
ly to
any
non
-co
mpl
ianc
es.
I will
con
sult
with
the
wor
k cr
ew a
nd a
men
d th
is E
nviro
nmen
tal M
anag
emen
t Sta
tem
ent a
s ne
cess
ary
in th
e ev
ent o
f any
cha
nges
to th
e w
ork
met
hod,
eq
uipm
ent,
sequ
ence
, mat
eria
ls o
r the
like
and
in th
e ev
ent o
f any
env
ironm
enta
l inc
iden
t. S
uper
viso
r: __
____
____
____
____
____
____
____
____
____
/
/
PAR
T 6:
EN
VIR
ON
MEN
TAL
MA
NA
GEM
ENT
STA
TEM
ENT
REC
OR
D O
F C
ON
SULT
ATI
ON
AN
D IN
STR
UC
TIO
NS
INTO
SA
FE W
OR
K M
ETH
OD
S
By
sign
ing
this
reco
rd, I
ack
now
ledg
e I h
ave
been
pro
vide
d th
e op
portu
nity
to c
ontri
bute
to th
e id
entif
icat
ion
of e
nviro
nmen
tal h
azar
ds a
ssoc
iate
d w
ith th
is s
tate
men
t an
d to
the
form
ulat
ion
of w
ork
met
hods
that
will
enab
le th
e w
ork
activ
ity to
be
unde
rtake
n in
an
envi
ronm
enta
lly s
afe
man
ner.
I al
so a
ckno
wle
dge
I hav
e be
en
inst
ruct
ed in
the
safe
wor
k m
etho
ds. I
und
erst
and
and
will
com
ply
with
thes
e in
stru
ctio
ns.
DO
NO
T SI
GN
TH
IS R
ECO
RD
IF Y
OU
DO
NO
T U
ND
ERST
AN
D, D
O N
OT
AG
REE
OR
DO
NO
T IN
TEN
D T
O C
OM
PLY
WIT
H T
HE
SAFE
WO
RK
MET
HO
DS
PRES
CR
IBED
Fam
ily N
ame
Firs
t Nam
e Jo
b D
escr
iptio
n Si
gnat
ure
Dat
e of
Tra
inin
g Su
perv
isor
s Si
gnat
ure