Appendix E
MCC Work Procedures
Surface Sweeping
Earth & Concrete Drain Cleaning
Herbicide Spraying
Cleaning Culverts, Pipes and Pits
Erosion & Sediment Control
Treatment of Acid Sulfate Soils
Integrated System Procedure (Environment)EROSION AND SEDIMENTATION CONTROL
Doc. Code: IS-ISPR-48
Version: 1.000
M:\Infrastructure Services\Quality Control\Env. Procedures\IS-ISPR-48na.igx 20/11/02 © Mackay City Council 2002 (IS-ISPR-48) Page 1
START
INSTALL EROSION AND/OR SEDIMENTATION CONTROL DEVICES WHERE REQUIRED
Controls devices are required where
sediment can wash into watercourses,
stormwater etc.
Control devices include:
straw bales, sediment fences, sandbags
or other propriety products
as identified in Project Management
Plan, or as determined by Supervisor
�
�
�
�
Resp: Supervisor, Work Staff
3
MONITOR EFFECTIVENESS OF INSTALLED EROSION AND/OR SEDIMENTATION CONTROL
DEVICES
• continuously during rain events
Resp: Supervisor
4
END
ACTION ANY INCIDENT IN ACCORDANCE WITH PROCEDURE "IS-ISPR-46"
Resp: Supervisor
8IDENTIFY POTENTIAL FOR SILT RUNOFF INTO
WATERWAYS AND STORMWATER SYSTEMS
as part of Preconstruction Meetings
(construction projects)
ongoing (maintenance)
�
�
Resp: Construction Co-ordinator, Maintenace Co-ordinator, Supervisor
1
CLEAN SEDIMENT CONTROL DEVICES (e.g.. SEDIMENT FENCES)
immediately (where sediment has
escaped control devices)
as often as necessary to retain
effectiveness in other cases
�
�
Resp: Supervisor, Work Staff
5
USE REMOVED SEDIMENT ON PROJECT
if feasible
if not feasible, remove sediment and
dispose of at an approved landfill dump
�
�
Resp: Work Staff
6
SITE MATERIAL STOCKPILES (SAND, GRAVEL ETC.) AWAY FROM SENSITIVE AREAS
Sensitive areas include:
watercourses
kerb and channel
gully pits
stormwater drains
�
�
�
�
Resp: Supervisor, Work Staff
2
REHABILITATE WORK SITE IF DIRECTED
Rehabilitation strategies include:
topsoiling
turfing or seeding
�
�
Resp: Work Staff
7
Integrated System Procedure (Environment)EROSION AND SEDIMENTATION CONTROL
Doc. Code: IS-ISPR-48
Version: 1.000
M:\Infrastructure Services\Quality Control\Env. Procedures\IS-ISPR-48na.igx 20/11/02 © Mackay City Council 2002 (IS-ISPR-48) Page 2
Sand Bag Check Dam - place regularly
along invert of drain
Sediment Fence - lower portion of fence
must be buried in a 200mm trench or
buried under a layer of aggregate
Straw Bales - effective for short periods
only
Sand Bags at Gully Pit Entrance -
sediment should be controlled before
it reaches this point
Staked Wire Mesh Surrounded By
Clean Aggregate
Reinforced Check Weir - ensure
silt can't flow around outside
edges
A Sediment Trap That Urgently Needs Cleaning
Integrated System Procedure (Maintenance)MOWING OF GRASS USING HANDMOWERS
Doc. Code: WK-ISPR-40
Version: 1.001
28/04/03 © Mackay City Council 2003 (WK-ISPR-40) Page 1
SET CUTTING HEIGHT
� QUALITY �refer to Table 1 "Restoration Standards"�
Resp: Work Staff
6
PERFORM PRESTART INSPECTION OF MOWERS
� SAFETY �disconnect spark plug lead before working
on mower
ensure that all guards are in place and are
operating correctly
check condition of all blades, bolts and
cutter assembly
clean filler cap area of dirt, grass etc.
ensure fuel tank is filled with correct
fuel - avoid spillage
check and top up oils as necessary
grease machine as required
check and clean/replace air filters as
necessary
check pull cord and have replaced if frayed
adjust handle to waist height for general
mowing reconnect spark plug
ENVIRONMENT
clean up any fuel/oil spills immediately
refer to Procedure "IS-ISPR-55"
�
�
�
�
�
�
�
�
�
�
�
�
Resp: Work Staff
3
SET UP TRAFFIC CONTROL, IF REQUIRED
� SAFETY �use appropriate figure from "Works on
Roads" (Part 3 "MUTCD")
�
Resp: Work Staff
4
START
START THE MOWER
� SAFETY �turn on fuel tap
prime carburettor
set throttle control
stand to side of mower or behind mower
(depending on location of starter cord)
ensuring feet are well clear of blades
brace mower with one hand while pulling
starter cord with other
repeat if necessary
allow cold engine to "warm up" for
approximately 30 seconds before use
ensure mower is operated in well
ventilated areas
ENVIRONMENT
inform workshop of mowers which have
smoky or faulty exhausts
�
�
�
�
�
�
�
�
�
Resp: Work Staff
7INSPECT THE WORK AREA
� SAFETY �free of objects that may injure the operator
/ public, or damage the brush cutter
dispose of found objects correctly - if in
doubt contact Supervisor
exercise particular caution in known
"sharps" areas
refer to Procedure "IS-ISPR-89
conduct risk assessment before using
mowers on steep, uneven, rocky or sandy
ground
ENVIRONMENT
check area for the presence of noxious
weeds
refer to Procedure "IS-ISPR-53"
�
�
�
�
�
�
�
Resp: Work Staff
5REFER TO RELEVANT PROCEDURE BELOW FOR GENERAL MAINTENANCE REQUIREMENTS
"WK-ISPR-80" - MCC maintenance
"WK-ISPR-108" - RMPC maintenance
�
�
Resp: Work Staff
1
PERFORM PRESTART PLANNING
GENERAL
establish the work area
from Job Sheet/Works Order and/or
Supervisor's instructions
ensure requirements of documents listed
in Table 1 are followed
� SAFETY �ensure correct PPE is available and used:
safety footwear
long pants
safety glasses or goggles
ear muffs or ear plugs
wide brim hat
gloves, if necessary
dust mask, if necessary
�
�
�
�
�
�
�
�
�
�
�
Resp: Work Staff
2
Integrated System Procedure (Maintenance)MOWING OF GRASS USING HANDMOWERS
Doc. Code: WK-ISPR-40
Version: 1.001
28/04/03 © Mackay City Council 2003 (WK-ISPR-40) Page 2
MOW THIS SECTION
� SAFETY �mow in the direction of traffic, if applicable
cease operations until members of the
public and other operators are clear
[maintain a 15 metre "clear zone"]
exercise extreme caution when mowing
on slopes - mow across slopes
where possible
push mower away from body where
possible
use appropriate engine speeds
ENVIRONMENT
leave grass clippings on ground where
possible
avoid soil compaction
�
�
�
�
�
�
�
Resp: Work Staff
8
RETRIEVE HAZARDOUS OBJECTS THROWN ONTO ROADWAY
� SAFETY �• immediately
• dispose of correctly - if in doubt contact
Supervisor
Resp: Work Staff
9
END
CHECK WORK AGAINST RESTORATION STANDARDS
refer to Table 1 for requirements�
Resp: Work Staff
10
REMOVE TRAFFIC CONTROL DEVICES, IF USED
� SAFETY �clean / repair as necessary
store correctly
�
�
Resp: Work Staff
12
SHUTDOWN MOWER
� SAFETY �do not leave mower running if unattended
turn fuel tap off
allow mower to cool then wash down and
store in correct location
notify Supervisor if repairs are necessary
ENVIRONMENT
wash down in designated wash-down bay
�
�
�
�
�
Resp: Work Staff
11
COMPLETE JOB SHEET / WORKS ORDER AND RETURN TO SUPERVISOR
if applicable�
Resp: Work Staff
14
CLEAN DOWN MOWER
Resp: Work Staff
13
Integrated System Procedure (Maintenance)MOWING OF GRASS USING HANDMOWERS
Doc. Code: WK-ISPR-40
Version: 1.001
28/04/03 © Mackay City Council 2003 (WK-ISPR-40) Page 3
1 MCC Road Maintenance Process WK-ISPR-80 Safety
1 RMPC Road Maintenance Process WK-ISPR-108 Using Mobile Plant IS-ISBK-01
3 Handling of Liquid Spills IS-ISPR-55 Using Hazardous Substances IS-ISPR-58
4 Works on Roads Using PPE IS-ISPR-93
5 “Sharps” Safety IS-ISPR-89 Manual Handling IS-ISPR-104
5 Flora and Fauna Protection IS-ISPR-53 Working in the Sun IS-ISPR-94, IS-ISBK-03
Using Hand Tools IS-ISPR-113
� work area left safe and tidy
� grass to be less than 75mm high for RMPC work [for allother situations, vegetation height to be at or belowlevel set by supervisor]
� cut grass will not block drains
Environmental
Noise Generation IS-ISPR-49
Performance Target:
Integrated System Procedure (Maintenance)HERBICIDE SPRAYING
Doc. Code: WK-ISPR-30
Version: 1.000
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-30na.igx 18/06/03 © Mackay City Council 2003 (WK-ISPR-30) Page 1
CHECK WEATHER AND WIND
� SAFETY �do not spray if rain is likely within 2 hours
do not spray if wind will blow spray
towards non-targeted vegetation or if wind
speed is greater than 12 knots
�
�
Resp: Work Staff
4
START
Do not spray if rain is likely
within 2 hours.
SET UP TRAFFIC CONTROL IF NEEDED
� SAFETY �Use appropriate figure from "Works on
Roads" (Part 3 "MUTCD")
�
Resp: Work Staff
6
OBTAIN RELEVANT PERMITS, IF NECESSARY
ENVIRONMENT
Refer to Notes�
Resp: Supervisor
2
PERFORM PRESTART PLANNING
GENERAL
Establish the work area
from Job Sheet/Works Order and/or
Supervisor's instructions
Ensure requirements of documents listed
in Table 1 are followed
Determine appropriate herbicide for
vegetation type
� SAFETY �Ensure all applicable Material Safety Data
Sheets (MSDS) are available
Ensure the availability and use of, all PPE
required by the applicable MSDSs
Note that the amount and type of PPE is
determined by the type of chemical(s),
degree and duration of exposure,
weather conditions and application
equipment used.
ENVIRONMENT
Ensure appropriate spill clean up material
is on hand
�
�
�
�
�
�
�
�
Resp: Supervisor
3
MIX HERBICIDE
� SAFETY �Before mixing the product, check for leaks
and operative problems on the spray
equipment.
Read the label thoroughly before opening
pesticide containers.
Work in a well-ventilated area and
accurately measure out the amount of
active ingredient required.
Do not attempt to pour concentrates
above shoulder height (e.g. into a spray
tank), as spillage is likely.
Rinse measuring containers three times,
adding the rinse water to the tank.
Never siphon herbicides with your mouth.
Wash hands with soap and water
immediately after mixing.
Refer also to Procedure "IS-ISPR-58"
ENVIRONMENT
Clean up any spills and dispose of
according to relevant MSDS
Refer to Procedure "IS-ISPR-55"
�
�
�
�
�
�
�
�
�
�
Resp: Work Staff
5
SPRAY VEGETATION
� QUALITY �Spray neatly and consistently
Ensure that only targeted vegetation is
sprayed
� SAFETY �Work in the direction of traffic where
practicable
Spray only the specified vegetation
Spray at distributor's specified rate
If nozzles become blocked, clean them
with a soft brush - do not suck or blow
into them using your mouth.
Minimise exposure when fixing or
adjusting equipment
�
�
�
�
�
�
�
Resp: Work Staff
7
REFER TO RELEVANT PROCEDURE BELOW FOR GENERAL MAINTENANCE REQUIREMENTS
"WK-ISPR-80" - MCC maintenance
"WK-ISPR-108" - RMPC maintenance
��
Resp: Work Staff
1
Integrated System Procedure (Maintenance)HERBICIDE SPRAYING
Doc. Code: WK-ISPR-30
Version: 1.000
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-30na.igx 18/06/03 © Mackay City Council 2003 (WK-ISPR-30) Page 2
RECORD SPRAY DETAILS
� QUALITY �note on spray sheet or MCC spray diary
record on Form "WK-ISFM-125" (Drain
Spraying)
return form to supervisor at year's end
�
�
�
Resp: Work Staff
8
END
Do not spray if wind will blow
spray towards other vegetation.
CHECK WORK AGAINST RESTORATION STANDARDS
refer to Table 1 for requirements�
Resp: Work Staff
9
REMOVE TRAFFIC CONTROL DEVICES, IF USED
� SAFETY �clean / repair as necessary
store correctly
�
�
Resp: Work Staff
10
COMPLETE JOB SHEET / WORKS ORDER AND RETURN TO SUPERVISOR
if applicable�
Resp: Work Staff
13CLEAN UP AND CHECK SPRAY EQUIPMENT
� QUALITY �Check and make any necessary repairs or
adjustments
� SAFETY �Inform relevant people of re-entry period
restrictions on the sprayed area if
applicable
ENVIRONMENT
Wash out only in designated areas
(ensure no waste materials enter
waterways)
Dispose of used herbicide, cleaning agent
etc., according to relevant MSDS
�
�
�
�
Resp: Work Staff
11
REMOVE PROTECTIVE CLOTHING
� SAFETY �Change out of protective clothing and
shower as soon as possible after spraying
and clean up
Wash before eating, drinking or smoking
Wash or dispose of all personal protective
equipment after each use
Wipe respirators with a damp cloth and
store in a sealed container.
�
�
�
�
Resp: Work Staff
12
Integrated System Procedure (Maintenance)HERBICIDE SPRAYING
Doc. Code: WK-ISPR-30
Version: 1.000
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-30na.igx 18/06/03 © Mackay City Council 2003 (WK-ISPR-30) Page 3
Step No.
1 MCC Road Maintenance Process WK-ISPR-80 Safety
1 RMPC Road Maintenance Process WK-ISPR-108 Using Mobile Plant IS-ISBK-01
3 Relevant MSDS Using PPE IS-ISPR-93
5 Handling of Liquid Spills IS-ISPR-55 Working Near O/head Services IS-ISPR-238
� all targeted vegetation killed
� no other vegetation sprayed
5 Hazardous Substances Management IS-ISPR-58 Manual Handling IS-ISPR-104
6 Works on Roads Working in the Sun IS-ISPR-94, IS-ISBK-03
8 Drain Maintenance Record WK-ISFM-125 Entry to MCC Quarries IS-ISPR-98
Action which triggers apermit
Name of permit/approval AdministeringAuthority
8 Spray Sheet or Spray Diary
Environmental
Plant Operation IS-ISPR-54
Spraying of herbicide ontovegetation within the roadreserve
Commercial OperatorsLicence
Agricultural ChemicalsDistribution ControlBoard
Use of herbicides indesignated HazardousArea
Commercial OperatorsLicence
Hazardous Area Permit
Agricultural ChemicalsDistribution ControlBoard
Use of a registeredagricultural and veterinarychemical in a manner thatis not included on the label
Off-label Permit National RegistrationAuthority
Performance Target:
Integrated System Procedure (Maintenance)MOWING / SLASHING OF GRASS USING TRACTORS
Doc. Code: WK-ISPR-29
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-29na.igx 28/04/03 © Mackay City Council 2003 (WK-ISPR-29) Page 1
SET CUTTING HEIGHT
� QUALITY �refer to Table 1�
Resp: Work Staff
6
MOW THE SECTION
� SAFETY �mow in the direction of traffic, where
possible
cease operations until passing traffic or
members of the public are clear (where
there is a danger of objects being
thrown by mower)
maintain a "safe zone" of 10 metres
between working tractors
exercise extreme caution when mowing
on slopes
ENVIRONMENT
arrange collection of shredded roadside
litter if required
�
�
�
�
�
Resp: Work Staff
7
RETRIEVE HAZARDOUS OBJECTS THROWN ONTO ROADWAY
� SAFETY �• immediately
Resp: Work Staff
9
TRIM AROUND OBSTRUCTIONS, IF INSTRUCTED
� QUALITY �use brush cutter and / or hand tools
� SAFETY �refer to Procedure "IS-ISPR-41"
�
�
Resp: Work Staff
8 INSPECT MOWERS
� SAFETY �ensure that all guards are in place and are
operating correctly
check condition of all blades, flails etc.
complete "Plant Operator's Daily Pre-Start
Checklist Record Book"
�
�
�
Resp: Work Staff
3
INSPECT THE WORK AREA
� SAFETY �check for washouts, unmarked culverts
and any other objects that may cause
personal or property damage
take appropriate action to minimise risks
from any found hazards
�
�
Resp: Work Staff
4
END
CHECK WORK AGAINST RESTORATION STANDARDS
refer to Table 1 for requirements�
Resp: Work Staff
10
SET UP TRAFFIC CONTROL
� SAFETY �use appropriate figure from "Works on
Roads" (Part 3 "MUTCD")
�
Resp: Work Staff
5
REMOVE TRAFFIC CONTROL DEVICES
� SAFETY �clean / repair as necessary
store correctly
�
�
Resp: Work Staff
11
START
COMPLETE JOB SHEET / WORKS ORDER AND RETURN TO SUPERVISOR
if applicable�
Resp: Work Staff
14
RECORD MOWING DETAILS (DRAIN MOWING ONLY)
� QUALITY �record on Form "WK-ISFM-125"
return form to supervisor at year's end
�
�
Resp: Work Staff
12
REFER TO RELEVANT PROCEDURE BELOW FOR GENERAL MAINTENANCE REQUIREMENTS
"WK-ISPR-80" - MCC maintenance
"WK-ISPR-108" - RMPC maintenance
�
�
Resp: Work Staff
1
PERFORM PRESTART PLANNING
GENERAL
establish the work area
from Job Sheet/Works Order and/or
Supervisor's instructions
ensure requirements of documents listed
in Table 1 are followed
ensure the availability and use of, all
activity relevant PPE
�
�
�
�
Resp: Work Staff
2
CLEAN DOWN TRACTOR AND MOWER
Resp: Work Staff
13
Integrated System Procedure (Maintenance)MOWING / SLASHING OF GRASS USING TRACTORS
Doc. Code: WK-ISPR-29
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-29na.igx 28/04/03 © Mackay City Council 2003 (WK-ISPR-29) Page 2
1 MCC Road Maintenance Process WK-ISPR-80 Safety
1 RMPC Road Maintenance Process WK-ISPR-108 Using Mobile Plant IS-ISBK-01
3 Plant Operator Daily Prestart Record Using Hazardous Substances IS-ISPR-58
5 Works on Roads Using PPE IS-ISPR-93
8 Trimming of Vegetation - Brushcutters IS-ISPR-41 Manual Handling IS-ISPR-104
12 Drain Maintenance Record WK-ISFM-125 Working in the Sun IS-ISPR-94, IS-ISBK-03
7 Litter Collection WK-ISPR-33 Using Slings IS-ISPR-112
Using Tractors IS-ISPR-91
Work in “Sharps” Location IS-ISPR-89
� work area left safe and tidy
� slashed vegetation less than 75 mm high in urban areasor 100 mm high in rural areas for RMPC work [for allother situations, vegetation height to be at, or belowlevel, determined by supervisor]
� road furniture / signs to be clearly visible
� vegetation does not obstruct visibility at intersections orcurves
� cut vegetation will not block drains
Environmental
Plant Operation IS-ISPR-54
Dust Generation IS-ISPR-50
Flora/Fauna Disturbance IS-ISPR-53
Noise Generation IS-ISPR-49
Liquid Spills IS-ISPR-55
Performance Target:
Integrated System Procedure (Maintenance)CLEANING CULVERTS, PIPES AND PITS
Doc. Code: WK-ISPR-27
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-27na.igx 28/04/03 © Mackay City Council 2003 (WK-ISPR-27) Page 1
CLEAN CULVERT, PIPE OR PIT
� QUALITY �remove silt and debris
ENVIRONMENT
dispose of waste material at an approved
landfill dump, or as directed by supervisor
�
�
Resp: Work Staff
5
END
START
OBTAIN RELEVANT PERMIT, IF NECESSARY
ENVIRONMENT
refer Notes�
Resp: Supervisor
1
SET UP TRAFFIC CONTROL
� SAFETY �refer to appropriate figure from "Works on
Roads" (Part 3 "MUTCD")
�
Resp: Work Staff
4
CHECK WORK AGAINST RESTORATION STANDARDS
refer to Table 1 for requirements�
Resp: Work Staff
6
REMOVE TRAFFIC CONTROL DEVICES
� SAFETY �• clean / repair as necessary
• store correctly
Resp: Work Staff
7
COMPLETE JOB SHEET / WORKS ORDER AND RETURN TO SUPERVISOR
if applicable�
Resp: Work Staff
8
REFER TO RELEVANT PROCEDURE BELOW FOR GENERAL MAINTENANCE REQUIREMENTS
"WK-ISPR-80" - MCC maintenance
"WK-ISPR-108" - RMPC maintenance
�
�
Resp: Work Staff
2
PERFORM PRESTART PLANNING
GENERAL
establish the work area
from Job Sheet/Works Order and/or
Supervisor's instructions
ensure requirements of documents listed
in Table 1 are followed
ensure the availability and use of, all
activity relevant PPE
�
�
�
�
Resp: Work Staff
3
Integrated System Procedure (Maintenance)CLEANING CULVERTS, PIPES AND PITS
Doc. Code: WK-ISPR-27
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-27na.igx 28/04/03 © Mackay City Council 2003 (WK-ISPR-27) Page 2
Step No.
1 MCC Road Maintenance Process WK-ISPR-80 Safety
1 RMPC Road Maintenance Process WK-ISPR-108 Using Mobile Plant IS-ISBK-01
3 Works on Roads Using Hazardous Substances IS-ISPR-58
� work area left safe and tidy
� all material that could block drains removed
Using PPE IS-ISPR-93
Manual Handling IS-ISPR-104
Working in the Sun IS-ISPR-94, IS-ISBK-03
Using Ladders IS-ISPR-83Action which triggers a
permitName of permit/approval Administering
Authority
Using Hand Tools IS-ISPR-113
Using Slings IS-ISPR-112
Using Hand Tools IS-ISPR-113
Spraying of herbicide ontovegetation within the roadreserve
Commercial OperatorsLicence
Agricultural ChemicalsDistribution Control Board
Working Near U/ground Services IS-ISPR-84
Working Near O/head Services IS-ISPR-238
Entry to MCC Quarries IS-ISPR-98, IS-ISPR-56
Use of herbicides indesignated HazardousArea
Commercial OperatorsLicenceHazardous Area Permit
Agricultural ChemicalsDistribution Control Board
Working at Heights IS-ISPR-109
Work Needing Inoculations MCC-ISPR-123
Work Needing First Aider MCC-ISPR-114
Working in Sharps Locations IS-ISPR-89
Use of a registeredagricultural and veterinarychemical in a manner thatis not included on the label
Off-label Permit National RegistrationAuthority
Environmental
Burning of clearedvegetation
Permit to Burn Qld Fire and RescueAuthority
Plant Operation IS-ISPR-54
Noise Generation IS-ISPR-49
Acid Sulphate Soil Disturbance IS-ISPR-57
Erosion/Sedimentation Control IS-ISPR-48
Carrying out works with thepotential to result in theremoval, destruction ordamage of marine plants
Permit to remove, destroy ordamage marine plants
Dept. of PrimaryIndustries
Flora/Fauna Disturbance IS-ISPR-53
Liquid Spills IS-ISPR-55
Cultural Heritage Disturbance IS-ISPR-47
Maintenance activitieswithin protected areas
Take, use, keep orinterfere with a cultural ornatural resource of aprotected area
Qld Parks & WildlifeService
Clearing vegetationcontaining protected plants
Take, use a protected plant Qld Parks & WildlifeService
Undertaking works in awatercourse which willdestroy vegetation orrequire excavation
Permit to destroyvegetation, excavate orplace fill in a watercourse
Department of NaturalResources
Performance Target:
Integrated System Procedure (Maintenance)EARTH AND CONCRETE DRAIN CLEANING
Doc. Code: WK-ISPR-26
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-26na.igx © Mackay City Council 2003 (WK-ISPR-26) Page 1
CLEAN CONCRETE SURFACE DRAINS (IF APPLICABLE)
� QUALITY �remove deposited material from concrete
drain
ENVIRONMENT
dispose of waste material at an approved
landfill tip, or as directed by your
supervisor
�
�
Resp: Work Staff
8
EXCAVATE THE DRAIN
� QUALITY �peg location and level, if specified
fill scours and depressions with suitable
material, if required
ENVIRONMENT
dispose of waste material at an approved
landfill dump, or as directed by your
supervisor
�
�
�
Resp: Work Staff
7
OBTAIN RELEVANT PERMITS, IF NECESSARY
ENVIRONMENT
refer to Notes�
Resp: Supervisor
1
END
CHECK WORK AGAINST RESTORATION STANDARDS
refer to Table 1 for requirements�
Resp: Work Staff
10
START
SET UP TRAFFIC CONTROL
� SAFETY �use appropriate figure from "Works on
Roads" (Part 3 "MUTCD")
�
Resp: Work Staff
5
REMOVE OBSTRUCTIONS (IF NECESSARY)
� QUALITY �• guide posts, signs etc.
Resp: Work Staff
6
REMOVE TRAFFIC CONTROL DEVICES
� SAFETY �• clean / repair as necessary
• store correctly
Resp: Work Staff
11
REINSTATE SIGNS, GUIDE POSTS ETC.
refer Procedures "WK-ISPR-34" and "WK-
ISPR-35"
�
Resp: Work Staff
9
SCHEDULE DRAIN MAINTENANCE
� QUALITY �schedule in accordance with the "Drain
Maintenance Programme"
�
Resp: Supervisor
2 COMPLETE JOB SHEET / WORKS ORDER AND RETURN TO SUPERVISOR
if applicable�
Resp: Work Staff
13
RECORD DRAIN CLEANING DETAILS
record on Form "WK-ISFM-125"
return form to supervisor at year's end
�
�
Resp: Work Staff
12
REFER TO RELEVANT PROCEDURE BELOW FOR GENERAL MAINTENANCE REQUIREMENTS
"WK-ISPR-80" - MCC maintenance
"WK-ISPR-108" - RMPC maintenance
�
�
Resp: Work Staff
3
PERFORM PRESTART PLANNING
GENERAL
establish the work area
from Job Sheet/Works Order and/or
Supervisor's instructions
ensure requirements of documents listed
in Table 1 are followed
ensure the availability and use of, all
activity relevant PPE
ENVIRONMENT
check for potential Acid Sulphate Soil
refer to Procedure "IS-ISPR-57"
�
�
�
�
�
�
Resp: Work Staff
4
Integrated System Procedure (Maintenance)EARTH AND CONCRETE DRAIN CLEANING
Doc. Code: WK-ISPR-26
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-26na.igx © Mackay City Council 2003 (WK-ISPR-26) Page 2
Step No.
2 Drain Maintenance Program Safety
3 MCC Road Maintenance Process WK-ISPR-80 Using Mobile Plant IS-ISBK-01
3 RMPC Road Maintenance Process WK-ISPR-108 Using Hazardous Substances IS-ISPR-58
4 Treatment of Acid Sulphate Soils IS-ISPR-57 Using PPE IS-ISPR-93
� work area left safe and tidy� all material that could block drains removed
� base evenly sloped to allow water to flow to outlet� loose material removed from work area
5 Works on Roads Manual Handling IS-ISPR-104
9 Sign Repairs WK-ISPR-34 Working in the Sun IS-ISPR-94, IS-ISBK-03
9 Repairing/Replacing Guide Markers WK-ISPR-35 Using Chainsaws IS-ISPR-95
12 Drain Maintenance Record WK-ISFM-125 Using Hand Tools IS-ISPR-113Action which triggers a
permitName of permit/approval Administering
Authority
Working Near U/ground Services IS-ISPR-84
Working Near O/head Services IS-ISPR-238
Entry to MCC Quarries IS-ISPR-98, IS-ISPR-56
Undertaking works withinthe Coastal ManagementControl Districts
"Permit required toundertake any workswithin control district"
Beach ProtectionAuthority
Work in “Sharps” Location IS-ISPR-89
Environmental
Plant Operation IS-ISPR-54
Liquid Spills IS-ISPR-55
Damage or removal ofground, stone or othermaterials in CoastalManagement ControlDistricts or erosion proneareas
Written approval fromBeach Protection Authorityrequired
Beach ProtectionAuthority
Carrying out of works withthe potential to result inthe removal, destruction ordamage of marine plants
"Permit to remove, destroyor damage marine plants"
Dept. of PrimaryIndustries
The undertaking of workswith within a declared FishHabitat Area
"Permit top perform workor related activity in adeclared fish habitat area"
Dept. of PrimaryIndustries
Undertake activities ontidal lands
"Permit to carry out workson tidal lands"
EnvironmentalProtection Agency
Performance Target:
Integrated System Procedure (Maintenance)SURFACE SWEEPING
Doc. Code: WK-ISPR-17
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-17na.igx 28/04/03 © Mackay City Council 2003 (WK-ISPR-17) Page 1
CHECK WORK AGAINST RESTORATION STANDARDS
refer to Table 1 for requirements�
Resp: Work Staff
6
SET UP TRAFFIC CONTROL, IF NEEDED
� SAFETY �use appropriate figure from "Works on
Roads" (Part 3 "MUTCD")
�
Resp: Work Staff
3
REMOVE TRAFFIC CONTROL DEVICES, IF USED
� SAFETY �• clean / repair as necessary
• store correctly
Resp: Work Staff
7
SWEEP THE AREA
� QUALITY �clean, dust free surface
� SAFETY �ensure sweeping plant is visually evident
at all times (use signs and / or lights)
ENVIRONMENT
minimise dust by use of water sprays
�
�
�
Resp: Work Staff
5
REMOVE LARGER DEBRIS BY HAND
� QUALITY �debris that may damage sweeper to be
removed by hand
�
Resp: Work Staff
4
START
END
RECORD STREET SWEEPING DETAILS
record on Form "WK-ISFM-126"
return form to supervisor at year's end
�
�
Resp: Work Staff
8REFER TO RELEVANT PROCEDURE BELOW FOR
GENERAL MAINTENANCE REQUIREMENTS
"WK-ISPR-80" - MCC maintenance
"WK-ISPR-108" - RMPC maintenance
�
�
Resp: Work Staff
1
PERFORM PRESTART PLANNING
GENERAL
establish the work area
from Job Sheet/Works Order and/or
Supervisor's instructions
program sweeping in accordance with the
"Street Sweeper Programme"
ensure requirements of documents listed
in Table 1 are followed
ensure the availability and use of, all
activity relevant PPE
�
�
�
�
�
Resp: Work Staff
2
Integrated System Procedure (Maintenance)SURFACE SWEEPING
Doc. Code: WK-ISPR-17
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-17na.igx 28/04/03 © Mackay City Council 2003 (WK-ISPR-17) Page 2
1 MCC Road Maintenance Process WK-ISPR-80 Safety
1 RMPC Road Maintenance Process WK-ISPR-108 Using Mobile Plant IS-ISBK-01
� all loose material removed from the sealed carriageway,kerb and channel etc.
2 Street Sweeper Programme Using Hazardous Substances IS-ISPR-58
3 Works on Roads Using PPE IS-ISPR-93
8 Street Sweeper Record WK-ISFM-126 Manual Handling IS-ISPR-104
Working in the Sun IS-ISPR-94, IS-ISBK-03
Work Needing Inoculations MCC-ISPR-123
Work in “Sharps” Location IS-ISPR-89
Environmental
Plant Operation IS-ISPR-54
Noise Generation IS-ISPR-49
Dust Generation IS-ISPR-50
Liquid Spills IS-ISPR-55
Performance Target:
Integrated System Procedure (Environment)TREATMENT OF ACID SULPHATE SOILS
Doc. Code: IS-ISPR-57
Version: 1.000
M:\Infrastructure Services\Quality Control\Env. Procedures\IS-ISPR-57na.igx 20/11/02 © Mackay City Council 2002 (IS-ISPR-57) Page 1
LOOK FOR ASS INDICATORS
mangroves, saltwater couch, tea trees,
she-oaks
stunted, sick or dead
vegetation - unexplained bare areas
presence of shells
water lilies
presence of Jarosite
dark gray and wet soil
hydrogen sulphide (rotten egg) odour from
disturbed soil
fish kills in nearby waterways
rust coloured scum on water
corroded concrete structures
�
�
�
�
�
�
�
�
�
�
Resp: Trained Work Staff
1B
CHECK IF WORK IS IN A TYPICAL ASS LOCATION
low lying areas near coast (below 5 AHD)
estuaries, flood plains, tidal mangrove flats
�
�
Resp: Trained Work Staff
1A
WEREANY OF THE ITEMS LISTED IN STEPS
1 & 2 OBSERVED?
ASS UNLIKELY, COMPLETE MAINTENANCE ACTIVITY
Resp: Trained Work Staff
OBTAIN SOIL SAMPLES FROM THE REGION IN WHICH WORK IS TO BE PERFORMED
refer "Notes" on page 2�
Resp: Trained Work Staff
WAS THE pH(f) <5 AND pH(fox) <4?
ASS LIKELY - STOP WORK IMMEDIATELY AND NOTIFY SUPERVISOR
Resp: Trained Work Staff
CALCULATE VOLUME OF SOIL INVOLVED
use Form "IS-ISFM-75"�
Resp: Supervisor
IS LESS THAN 100 m³ OF SOIL INVOLVED?
STOCKPILE REMOVED ASS IN A BUNDED AREA
Resp: Supervisor, Work Staff
DISPOSE OF TREATED SOIL
dump treated soil onto already cleared
land, at least 5m from any drain or
waterway
do not dump on tidal land or other wetlands
�
�
Resp: Work Staff
ARRANGE FOR LABORATORY TESTING TO BE UNDERTAKEN
Resp: Supervisor
PERFORM ASS SCREENING TESTS
refer "Notes"
record results on Form "IS-ISFM-75"
�
�
Resp: Trained Work Staff
NOTIFY MANAGER ENVIRONMENTAL SERVICES
Resp: Supervisor
DRAFT ASS MANAGEMENT PLAN
use test results as basis of plan�
Resp: Manager Environ. Services, Supervisor
FOLLOW REQUIREMENTS OF ASS MANAGEMENT PLAN
Resp: Supervisor, Work Staff
START
END
END
END
ACTION ANY INCIDENT IN ACCORDANCE WITH PROCEDURE "IS-ISPR-46"
Resp: Supervisor
1M
TREAT BY SPREADING AGRICULTURAL LIME OVER THE SOIL AND MIXING THOROUGHLY
use Form "IS-ISFM-75"�
Resp: Work Staff
Integrated System Procedure (Environment)TREATMENT OF ACID SULPHATE SOILS
Doc. Code: IS-ISPR-57
Version: 1.000
M:\Infrastructure Services\Quality Control\Env. Procedures\IS-ISPR-57na.igx 20/11/02 © Mackay City Council 2002 (IS-ISPR-57) Page 2
Integrated System Procedure (Maintenance)REPAIR INLET AND OUTLET SCOURS
Doc. Code: WK-ISPR-43
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-43na.igx 28/04/03 © Mackay City Council 2003 (WK-ISPR-43) Page 1
CHECK WORK AGAINST RESTORATION STANDARDS
refer to Table 1 for requirements�
Resp: Work Staff
6
REPAIR INLET/OUTLET STRUCTURE
� QUALITY �in accordance with details in Works Order
and relevant specifications
�
Resp: Work Staff
5
START
END
SET UP TRAFFIC CONTROL
� SAFETY �use appropriate figure from "Works on
Roads" (Part 3 "MUTCD")
�
Resp: Work Staff
4
REMOVE TRAFFIC CONTROL DEVICES
� SAFETY �• clean / repair as necessary
• store correctly
Resp: Work Staff
7
OBTAIN RELEVANT PERMITS, IF NECESSARY
ENVIRONMENT
refer to Notes�
Resp: Supervisor
1
COMPLETE JOB SHEET / WORKS ORDER AND RETURN TO SUPERVISOR
if applicable�
Resp: Work Staff
8
REFER TO RELEVANT PROCEDURE BELOW FOR GENERAL MAINTENANCE REQUIREMENTS
"WK-ISPR-80" - MCC maintenance
"WK-ISPR-108" - RMPC maintenance
�
�
Resp: Work Staff
2
PERFORM PRESTART PLANNING
GENERAL
establish the work area
from Job Sheet/Works Order and/or
Supervisor's instructions
ensure requirements of documents listed
in Table 1 are followed
ensure the availability and use of, all
activity relevant PPE
��
�
�
Resp: Work Staff
3
Integrated System Procedure (Maintenance)REPAIR INLET AND OUTLET SCOURS
Doc. Code: WK-ISPR-43
Version: 1.001
M:\Infrastructure Services\Quality Control\Maint. Procedures\WK-ISPR-43na.igx 28/04/03 © Mackay City Council 2003 (WK-ISPR-43) Page 2
1 MCC Road Maintenance Process WK-ISPR-80 Safety
1 RMPC Road Maintenance Process WK-ISPR-108 Using Mobile Plant IS-ISBK-01
4 Works on Roads Using Hazardous Substances IS-ISPR-58
Using PPE IS-ISPR-93
Manual Handling IS-ISPR-104
� work area left safe and tidy
� specified branches / trees removed / trimmed
� no regrowth
� no material left to block drains
Working in the Sun IS-ISPR-94, IS-ISBK-03
Using Hand Tools IS-ISPR-113
Working Near O/Head Services IS-ISPR-238
Working Near U/ground Services IS-ISPR-84
Action which triggers apermit
Name ofpermit/approval
AdministeringAuthority
Work Needing First Aider MCC-ISPR-114
Using Power Tools IS-ISPR-90
Work in “Sharps” Location IS-ISPR-89
Undertaking works within theCoastal Management ControlDistricts
"Permit required toundertake any workswithin control district"
BeachProtectionAuthority
Environmental
Plant Operation IS-ISPR-54
Noise Generation IS-ISPR-49
Damage or removal of ground,stone or other materials inCoastal Management ControlDistricts or erosion prone areas
Written approval fromBeach ProtectionAuthority required
BeachProtectionAuthority
Acid Sulphate Soils IS-ISPR-57, IS-ISBK-02
Liquid Spills IS-ISPR-55
Cultural Heritage Disturbance IS-ISPR-47
Carrying out of works with thepotential to result in theremoval, destruction or damageof marine plants
"Permit to remove,destroy or damagemarine plants"
Dept. of PrimaryIndustries
The undertaking of works withwithin a declared Fish HabitatArea
"Permit top performwork or related activityin a declared fishhabitat area"
Dept. of PrimaryIndustries
Undertake activities on tidallands
"Permit to carry outworks on tidal lands"
EnvironmentalProtectionAgency
Performance Target:
Undertaking works in awatercourse which will destroyvegetation or requireexcavation
"Permit to destroyvegetation, excavate orplace fill in awatercourse"
Dept. of NaturalResources