APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT STORMWATER MANAGEMENT SYSTEM DESIGN

ATTACHMENT A.1 SWM Model Development

December 2014 Report No. 12-1125-0045/4500/vol IV

Page 3: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

ATTACHMENT A.1 SWM Model Development

December 2014 Project No. 12-1125-0045/4500/vol IV 1/2

A.1 Hydrologic Model Input Summary Tables Hydrological Parameter Selection

The existing Site conditions were determined to have five significant land use types: Scrubland; Woods; Pavement; Gravel; and Grasslands. The Manning’s n coefficient, depression storage depth and SCS Curve Number values assigned for each of these land use types are summarized in Table A.1.2.

In addition to the five significant land use types identified for the pre-development scenario, Vegetated Slope, and Gravel land use types have also been incorporated into the post-development hydrologic parameter selection for the Site sub-catchment Municipal Drain areas and recommended stormwater conveyance channels, respectively, in SWMM5. Table A.1.3 identifies post-development input parameters identified for each land use type.

Tables A1.2 to A.1.5 summarize the pre-development and post development hydrological input parameters for representing the Site conditions. Subsurface investigations performed by Golder were also utilized to identify the general silty sand soil type for the Site. The Site visit, aerial photography and GIS topography were also utilized to define the hydrological parameters such as the curve number, depression storage, Manning’s n coefficient and the land use. These parameters were defined based on published literature values and Site investigations.

Hydrologic Model Input Summary Tables

Table A.1. 1: 24-Hour Rainfall at City of Ottawa, CDA RCS Weather Station

Return Period (yrs) Rainfall Depth (mm)

2 33.0 5 72.1 25 103.9 100 115.8

Note: The total depths were distributed over a 24-hour time period using 15-minute intensity intervals and a SCS Type II rainfall distribution.

Table A.1. 2: Pre-Development Land Use Hydrologic Input Parameters

Scrubland Woods Paved Road Gravel Grassland

Manning’s n 0.15 0.4 0.012 0.024 0.035 Depression Storage (mm) 5 8 2 2 4 SCS Curve Number 77 70 98 89 71

Page 4: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

ATTACHMENT A.1 SWM Model Development

December 2014 Project No. 12-1125-0045/4500/vol IV 2/2

Table A.1. 3: Post-Development Land Use Hydrologic Input Parameters

Scrubland Woods Paved Road Gravel Grassland Landfill

Slope

Manning’s n 0.15 0.4 0.012 0.024 0.035 0.013 Depression Storage (mm) 5 8 2 2 4 5 Curve Number 77 70 98 89 71 82

Table A.1. 4: Pre-Development Sub-Catchment Hydrologic Input Parameters

Sub Catchment

Area (ha)

Width (m)

Slope (%)

Impervious (%) N Pervious

Dep. Stor. Pervious

(mm) Curve

Number

E101 21.0 200 0.1 10 0.133 4 86.8 E201 42.3 330 0.125 7.5 0.165 4 85.1 E202 33.3 150 0.343 0 0.213 6 76.7 E301 95.1 250 0.167 7.5 0.184 5 80.6

Table A.1. 5: Post-Development Sub-Catchment Hydrologic Input Parameters

Sub Catchment

Area (ha)

Width (m)

Slope (%)

Impervious (%) N Pervious

Dep. Stor. Pervious

(mm) Curve

Number

P101 14.74 125 0.05 70 0.012 5 88.9 P102 9.51 125 0.076 70 0.012 5 88.9 P201 12.6 250 0.4 75 0.012 4 91.9 P202 4.2 100 0.5 90 0.012 4 95.3

P203 1. 16.34 250 0.4 75 0.012 4 91.9 P204 48.2 640 4.3 0 0.012 5 72.6 P301 41.8 670 4.2 0 0.012 5 72.6 P302 27.9 430 4.2 0 0.012 5 72.6 P303 13.94 300 5.4 0 0.012 5 72.6

Note: Leachate Treatment Ponds (1.9 ha Equalization Pond and 0.66 ha Effluent Pond) are not included in the P203 Drainage Area.

n:\active\2012\1125 - environmental and civil engineering\12-1125-0045 crrrc ea eastern on\phase 4500_final_easr\vol 4 - d&o\appendices\app a_stormwater\attachments\attach-a\attachment a.1_crrrc_hydrologic-input_dec2014.docx

Page 5: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT STORMWATER MANAGEMENT SYSTEM DESIGN

ATTACHMENT A.2 Existing and Proposed SWMM5 Schematics Figures: Figure A-1 – Existing Scenario SWMM5 Schematic Figure A-2 – Proposed Scenario SWMM5 Schematic

December 2014 Report No. 12-1125-0045/4500/vol IV

Page 6: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

Regimbald Municipal Drain - Site Drainage Area

Simpson Municipal Drain - Site Drainage Area

Wilson-Johnston Municipal Drain - Site Drainage Area

Figure A-1: Existing Scenario SWMM5 Schematic

PROJECT: 12-1125-0045DATE: December 2013

DRAWN: JSA

Sub‐Catchment 

Sub‐Catchment

E101

Storage RetentionStorageSubcatchment

Flow LinkLegend

E101DS1‐Storage Culvert 1a 

Under Frontier Rd.

Sub‐Catchment 

E201 Simpson‐Drain DS_Storage Culvert 2a 

Under Frontier Rd.

Sub‐Catchment 

E301 Culvert 3a Under Frontier Rd.

E101DS2‐Storage

Culvert 1bUnder Hwy 417 W

E101OUT

E201OUT

E301OUTE301

DS1‐Storage

CHECK: DVK

Spillway

Spillway

Spillway

Weir Spillway/Overflow

Culvert/Pipe

Conduit

Outfall

Outfall

Page 7: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

Regimbald Municipal Drain - Site Drainage Area

Simpson Municipal Drain - Site Drainage Area

Wilson-Johnston Municipal Drain - Site Drainage Area

Figure A-2: Proposed Scenario SWMM5 Schematic

PROJECT: 12-1125-0045DATE: December 2013

Sub‐Catchment

P101 P101_US‐RET

Culvert 1a Under Frontier Rd.

Sub‐Catchment 

P301

Culvert 3a Under Frontier Rd.

P‐1_DS‐2‐RET Culvert 1bUnder Hwy 417 W

P‐1OUT

P‐3OUT

P‐3DS1‐RET

DRAWN: JSA

CHECK: DVK

Legend Sub‐Catchment 

Storage/SWM Feature Retention

StorageSubcatchment Flow Link

OutfallChannelOutfall Conduit

Weir Spillway/Overflow Culvert/Conduit

Sub‐Catchment

P102P101_US‐RET

P101US‐Ditch

P102US‐Ditch

SWMP‐5a

SWMP‐5b

OrificeOrifice

Outlet Spillway

Outlet

Spillway

P‐1_DS‐1‐RET

P‐1_DS1Ditch

Spillway

P‐1_DS2Ditch

Sub‐Catchment

P201

Sub‐Catchment

P202

P201US‐Ditch

SWMP‐3

SWMP‐4a

Outlet

Spillway

Storm Servicing

Storm ServicingOutlet

Spillway

P‐2_SD‐1‐RET

SDSegment1

SDSegment2

SDSegment3

P‐2_SD‐2‐RET

Sub‐Catchment

P203 SWMP‐4b

Outlet

SpillwayP203US‐Ditch P‐2_SD‐3‐RET

Culvert 2a Under Frontier Rd.

P‐2OUT

Sub‐Catchment

P204P204

US‐DitchSWMP‐1

Outlet

Spillway

Spillway

SWMP‐2

Outlet

SpillwayP301US‐Ditch

Orifice

P‐3_DS1Ditch

Spillway

Spillway

P‐2_SD‐4‐RET

P‐3DS2‐RET

P303

P302

Page 8: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT STORMWATER MANAGEMENT SYSTEM DESIGN

ATTACHMENT A.3 Proposed CRRRC SWMPs Hydrographs Figures: Figure A-3 – 1 in 2 yr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs Figure A-4 – 1 in 5 yr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs Figure A-5 – 1 in 25 yr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs Figure A-6 – 1 in 100 yr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs

December 2014 Report No. 12-1125-0045/4500/vol IV

Page 9: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

Notes:1. Depths above Normal Water Level for Each SWMP.

1 in 2 yr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs Figure A-3

PROJECT: 12-1125-0045DATE: December 2013

DRAWN: JSACHECK: DVK

Page 10: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

1 in 5 yr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs Figure A-4

PROJECT: 12-1125-0045DATE: December 2013

DRAWN: JSACHECK: DVK

Page 11: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

1 in 25 yr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs Figure A-5

PROJECT: 12-1125-0045DATE: December 2013

DRAWN: JSACHECK: DVK

Page 12: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

1 in 100 yr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs Figure A-6

PROJECT: 12-1125-0045DATE: December 2013

DRAWN: JSACHECK: DVK

Page 13: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT STORMWATER MANAGEMENT SYSTEM DESIGN

ATTACHMENT A.4 24 hr Detention Time Assessment / Verification Hydrographs Figure: Figure A-7 – 25mm – 4 hr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs

December 2014 Report No. 12-1125-0045/4500/vol IV

Page 14: APPENDIX A, VOL IV DESIGN AND OPERATIONS REPORT

25 mm - 4 hr, City of Ottawa Design Storm Hydrographs for CRRRC SWMPs Figure A-7

PROJECT: 12-1125-0045DATE: December 2013

DRAWN: JSACHECK: DVK