60
APPENDIX A CONNECTION ASSESSMENT

APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

APPENDIX A CONNECTION ASSESSMENT

Page 2: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System
Page 3: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Page 1

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

Executive Summary

Project Overview

EPCOR Distribution & Transmission Inc. (EDTI), in its capacity as the legal owner of the electric

distribution system (DFO) in the City of Edmonton, submitted a request for system access

service to the Alberta Electric System Operator (AESO) to reliably serve growing demand for

electricity in southwest (SW) Edmonton. The DFO informed the AESO that this growing demand in SW Edmonton is currently served by its 25 kV distribution system.

The DFO’s request includes a Rate DTS, Demand Transmission Service, contract capacity of 24 MW, and a request for transmission development in SW Edmonton (collectively, the Project). Specifically, the DFO requested a new 240/25 kV point of delivery (POD) substation with two 240/25 kV transformers, four 240 kV breakers and associated equipment in SW Edmonton.

The scheduled in-service date for the Project is October 1, 2019.

This report details the engineering studies undertaken to assess the impact of the Project on the

performance of the Alberta interconnected electric system (AIES).

Existing System

Geographically, the Project is located in the AESO planning area of Edmonton (Area 60), which

is part of the AESO Edmonton Planning Region. Edmonton (Area 60) is surrounded by the

AESO planning areas of Athabasca/Lac La Biche (Area 27), Fort Saskatchewan (Area 33),

Wetaskiwin (Area 31), and Wabamun (Area 40).

From a transmission system perspective, Edmonton (Area 60) consists of 500 kV, 240 kV,

138/144 kV, and 69/72 kV transmission systems. The existing 25 kV distribution system in SW

Edmonton is currently served by the Summerside and Poundmaker POD substations, which

are supplied through the 240 kV transmission system in Edmonton (Area 60).

Existing constraints in the Edmonton Planning Region are managed in accordance with the

procedures set out in Section 302.1 of the ISO rules, Real Time Transmission

Constraint Management.

Study Summary

Study Area

The Study Area for the Project consists of all 240 kV transmission facilities in Edmonton (Area

60) and the tie lines connecting Edmonton (Area 60) to the rest of the AIES. All transmission facilities rated at 240 kV and above within the Study Area were studied and monitored to assess the impact of the Project on the performance of the AIES, including any violations of the Reliability Criteria (as defined in Section 2.1.1).

Studies Performed

2018 winter peak (WP) and 2019 summer peak (SP) scenarios were studied.

Page 4: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

Page 2

Power flow studies were performed for the 2018 WP and 2019 SP pre-Project and post-Project

study scenarios.

Voltage stability studies were performed for the 2018 WP post-Project study scenario.

Results of the Pre-Project Studies

Under the Category A and Category B conditions studied, no Reliability Criteria violations were

observed.

Connection Alternatives Examined for the Project

The DFO informed the AESO that it intends to request system access service to address

capacity and reliability concerns on its 25 kV distribution system in southeast (SE) Edmonton in

the near future. For the sake of ensuring transmission system planning efficiency, given the

proximity of the 25 kV distribution system in SW Edmonton to SE Edmonton, six transmission

alternatives were examined that address the current request for system access service (i.e.,

distribution system concerns in SW Edmonton), as well as the DFO’s capacity and reliability

concerns in SE Edmonton.

The AESO examined these six transmission alternatives in consultation with the DFO and the

legal owners of transmission facilities (TFOs) that own facilities in the area.

Alternative 1 – Upgrade the existing Petrolia substation and add a new POD substation in SE Edmonton

This alternative involves the following transmission development:

upgrading the existing Petrolia substation including adding two 240/25 kV

transformers, two 240 kV circuit breakers, and eight 25 kV feeder breakers and

associated equipment; and

adding a new POD substation in SE Edmonton, including adding two 240/25 kV

transformers, four 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment; and connecting the new POD to the AIES.

Alternative 2 – Upgrade the existing Jasper substation and add a new POD substation in SE Edmonton

This alternative involves the following transmission development:

upgrading the existing Jasper substation including the addition of two 240/25 kV

transformers, two 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment; and

adding a new POD substation in SE Edmonton including two 240/25 kV transformers,

four 240 kV circuit breakers, and eight 25 kV feeder circuit breakers and associated

equipment ;and connecting it to the AIES.

Alternative 3 – Upgrade the existing Summerside and Poundmaker substations and add a new POD substation in SE Edmonton

This alternative involves the following transmission development:

Page 5: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

Page 3

upgrading the existing Summerside substation including adding one 240/25 kV

transformer, one 240 kV circuit breaker, and four 25 kV feeder circuit breakers and

associated equipment ;

upgrading the existing Poundmaker substation including adding one 240/25 kV

transformer, one 240 kV circuit breaker, and four 25 kV feeder circuit breakers and

associated equipment; and

adding a new POD substation in SE Edmonton, including two 240/25 kV

transformers, four 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment ; and connecting it to the AIES.

Alternative 4 – Add a new POD substation in SW Edmonton, to be called the Riverview substation and upgrade the existing Summerside substation

This alternative involves the following transmission development:

adding a new POD substation in SW Edmonton, to be called the Riverview

substation, including two 240/25 kV transformers, four 240 kV circuit breakers, and

eight 25 kV feeder circuit breakers and associated equipment;

connecting the proposed Riverview substation to the existing 240 kV transmission

line 1043L (future 1139L) using an in-and-out configuration, between the approved

Harry Smith 367S substation and the Petrolia substation, by adding two new 240 kV

transmission circuits, each approximately 70 metres in length; and

upgrading the existing Summerside substation, including adding one 240/25 kV

transformer, one 240 kV circuit breaker, and four 25 kV feeder circuit breakers and

associated equipment.

Alternative 5 – Add the proposed Riverview substation and add a new POD to SE Edmonton

This alternative involves the following transmission development:

adding the proposed Riverview substation, including two 240/25 kV transformers, four

240 kV circuit breakers, and eight 25 kV feeder circuit breakers and associated

equipment;

connecting the proposed Riverview substation to the existing 240 kV transmission

line 1043L (future 1139L) using an in-and-out configuration, between the approved

Harry Smith 367S substation and the Petrolia substation, by adding two new 240 kV

transmission circuits, each approximately 70 metres in length; and

adding a new POD substation in SE Edmonton, including two 240/25 kV

transformers, four 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment and connecting it to the AIES.

Alternative 6 – Upgrade the existing Summerside and Poundmaker substations

This alternative involves the following transmission development:

upgrading the existing Summerside substation, including replacing the two existing

240/25 kV transformers with two 240/25 kV transformers of higher capacity and adding a

Page 6: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

Page 4

third 240/25 kV transformer, one 240 kV circuit breaker, and eighteen 25 kV feeder

circuit breakers and associated equipment; and

upgrading the existing Poundmaker substation, including adding one 240/25 kV

transformer, one 240 kV circuit breaker, and four 25 kV feeder circuit breakers and

associated equipment.

Alternatives Not Selected for Further Examination

Alternative 1 and Alternative 2 were not selected for further study because the TFO advised that

expanding the existing Petrolia and Jasper substations are not viable.

Alternative 3 and Alternative 6 were not selected for further study because the total costs are

estimated to be higher than the total costs of Alternative 4 and Alternative 5.1

Alternatives Selected for Further Examination

Alternative 4 and Alternative 5 were selected for further study. Both Alternative 4 and Alternative

5 involve adding the proposed Riverview substation to meet the request for system access

service.

Alternative 4 and Alternative 5 include different transmission facilities to address the capacity

and reliability concerns in SE Edmonton, which the DFO has indicated will be the subject of a

forthcoming request for system access service. Therefore, the selection of the preferred

transmission development to address the DFO’s capacity and reliability concerns in SE

Edmonton will be assessed as a part of a separate project, and is not within the scope of this

study.

For the purpose of responding to the DFO’s current request for system access service,

Alternative 4 and Alternative 5 are equivalent in scope. Therefore, only the addition of the

proposed Riverview substation, connected to the existing 240 kV transmission line 1043L

(future 1139L) in an in-and-out configuration, and including two 240/25 kV transformers, four

240 kV circuit breakers, and eight 25 kV feeder circuit breakers and associated equipment, will

be examined further.

Results of the Post-Project Studies

The post-Project studies were performed for the proposed Riverview substation with a Rate

DTS request of 24 MW.

Under the Category A and Category B conditions studied, no Reliability Criteria violations were observed. The voltage stability margin was met for all studied conditions.

Conclusions and Recommendations

1 Cost estimates for Alternative 3, Alternative 4, Alternative 5, and Alternative 6 are provided under a

separate cover.

Page 7: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

Page 5

The connection assessment did not identify any pre-Project or post-Project system performance

issues. The connection assessment indicates that the Project will not adversely impact the

performance of the AIES.

Based on the connection assessment, adding the proposed Riverview substation to address the

request for system access service is technically acceptable.

Based on the connection assessment, adding the proposed Riverview substation and the

associated DTS is technically acceptable. The connection assessment did not identify any pre-

Project or post-Project system performance issues. The connection assessment indicates that

the Project will not adversely impact the performance of the AIES. No mitigation measures are

required as no Reliability Criteria violations were observed.

It is recommended to proceed with the Project by adding a new POD substation in SW

Edmonton as the preferred option to respond to the DFO’s request for system access service.

This includes: adding a new POD substation, to be designated the Riverview substation,

including two 240/25 kV LTC transformers, four 240 kV circuit breakers, and eight 25 kV feeder

circuit breakers and associated equipment; and adding two 240 kV circuits, approximately 70

metres in length, to connect the Riverview substation to the existing 240 kV transmission line

1043L (future 1139L) using an in-and-out configuration between the approved Harry Smith 367S

substation and the existing Petrolia substation.

A minimum rating equal or greater than the rating of the existing 240 kV transmission line 1043L

is recommended for the two new 70 metres 240 kV circuits.

The 240/25 kV LTC transformers at the Riverview substation are recommended to have a rating

of 75 MVA.

Page 8: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

Page 6

Contents

Executive Summary .................................................................................................................................... 1 1. Introduction ......................................................................................................................................... 8

1.1. Project ........................................................................................................................................... 8 1.1.1. Overview ................................................................................................................................ 8 1.1.2. Load Component ................................................................................................................... 8 1.1.3. Generation Component ......................................................................................................... 8

1.2. Study Scope .................................................................................................................................. 8 1.2.1. Study Objectives .................................................................................................................... 8 1.2.2. Study Area ............................................................................................................................. 9 1.2.3. Studies Performed ............................................................................................................... 12

1.3. Report Overview .......................................................................................................................... 12 2. Criteria, System Data, and Study Assumptions ............................................................................. 13

2.1. Criteria, Standards, and Requirements ....................................................................................... 13 2.1.1. Transmission Planning Standards and Reliability Criteria ................................................... 13 2.1.2. ISO Rules and Information Documents ............................................................................... 14

2.2. Study Scenarios .......................................................................................................................... 14 2.3. Load and Generation Assumptions ............................................................................................. 15

2.3.1. Load Assumptions ............................................................................................................... 15 2.3.2. Generation Assumptions ..................................................................................................... 15 *Unit Net Generation refers to Gross Generating unit MW output less Unit Service Load. ............. 15 2.3.3. Intertie Flow Assumptions and HVDC Assumptions ........................................................... 16

2.4. System Projects ........................................................................................................................... 16 2.5. Customer Connection Projects .................................................................................................... 16 2.6. Facility Ratings and Shunt Elements ........................................................................................... 17 2.7. Voltage Profile Assumptions ....................................................................................................... 18

3. Study Methodology ........................................................................................................................... 19 3.1. Connection Studies Carried Out .................................................................................................. 19 3.2. Power Flow Analysis ................................................................................................................... 19

3.2.1. Contingencies Studied ......................................................................................................... 19 3.3. Voltage Stability Studies .............................................................................................................. 19

3.3.1. Contingencies Studied ......................................................................................................... 20 4. Results of Pre-Project Studies ......................................................................................................... 21

4.1. Pre-Project Power Flow Studies .................................................................................................. 21 4.1.1. Scenario 1 (2018 WP pre-Project) ....................................................................................... 21 4.1.2. Scenario 2 (2019 SP pre-Project) ........................................................................................ 21

5. Connection Alternatives ................................................................................................................... 22 5.1. Overview ...................................................................................................................................... 22 5.2. Transmission Alternatives Identified ............................................................................................ 22

5.2.1. Transmission Alternatives Selected for Further Examination.............................................. 24 5.2.2. Transmission Alternatives Not Selected for Further Examination ....................................... 24

6. Results of Post-Project Studies ....................................................................................................... 26 6.1. Post-Project Power Flow Studies ................................................................................................ 26 6.1.1. Scenario 3 (2018 WP post-Project) ............................................................................................. 26 6.1.2. Scenario 4 (2019 SP post-Project) .............................................................................................. 26 6.2. Post-Project Voltage Stability Studies ......................................................................................... 26

7. Project Dependencies ....................................................................................................................... 27 8. Conclusions and Recommendations .............................................................................................. 28

Page 9: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

Page 7

Attachments

Attachment A Power Flow Diagrams – 2018 WP Pre-Project

Attachment B Power Flow Diagrams – 2018 WP Post-Project and 2019 SP Post-Project

Attachment C Voltage Stability Diagrams - 2018 WP Post-Project

Figures

Figure 1-1: Transmission System in vicinity of the Project ........................................................................................... 10

Tables

Table 2-1: Post-Contingency Voltage Deviations Guidelines for Low Voltage POD Busses ........................................ 14

Table 2-2: List of the Connection Study Scenarios ...................................................................................................... 14

Table 2-3: Forecast Area Load (2016 LTO at Edmonton Region Peak) ....................................................................... 15

Table 2-4: Key System Generation Dispatch Conditions ............................................................................................. 15

Table 2-5: Summary of Included Customer Projects in Edmonton (Area 60) ............................................................... 16

Table 2-6: Key Transmission Circuits in the vicinity of the Study Area ......................................................................... 17

Table 2-7: Summary of Key Transformer Ratings in the Study Area ............................................................................ 17

Table 2-8: Summary of Shunt Elements in the Study Area .......................................................................................... 17

Table 2-9: Bus Voltages of Key Substations in the Study Area .................................................................................... 18

Table 3-1: Summary of Studies Performed .................................................................................................................. 19

Table 6-1: Voltage Stability Study Results for the 2018 WP post-Project Scenario ..................................................... 26

Page 10: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

8

1. Introduction

This report details the engineering studies undertaken to assess the impact of the Project (as defined below) on the performance of the Alberta interconnected electric system (AIES).

1.1. Project

1.1.1. Overview

EPCOR Distribution & Transmission Inc. (EDTI), in its capacity as the legal owner of the electric distribution system (DFO) in the City of Edmonton, submitted a request for system access service to the Alberta Electric System Operator (AESO) to reliably serve growing demand for electricity in southwest (SW) Edmonton.

The DFO’s request includes a Rate DTS, Demand Transmission Service, contract capacity of 24 MW, and a request for transmission development in SW Edmonton (collectively, the Project). Specifically, the DFO requested a new point of delivery (POD) substation with two 240/25 kV transformers, four 240 kV breakers, two 25 kV busses with a total of eight 25 kV feeder breakers and associated equipment in SW Edmonton.

The scheduled in-service date for the Project is October 1, 2019.

1.1.2. Load Component

New Rate DTS contract capacity: 24 MW in SW Edmonton

Load type: Residential and Commercial

Power Factor (PF) assumed for studies: 0.9 pf (lagging)

Future expansion plans: EDTI has requested provisions to allow for future expansion.

1.1.3. Generation Component

There is no generation component associated with the Project.

1.2. Study Scope

1.2.1. Study Objectives

The objectives of the study are as follows:

Assess the impact of the Project on the performance of the AIES.

Identify any violations of the relevant AESO criteria, standards or requirements, bothpre-Project and post-Project.

Page 11: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

9

Recommend the preferred Project alternative and mitigation measures, if required, toreliably connect the Project to the AIES.

1.2.2. Study Area

1.2.2.1. Study Area Description

Geographically, the Project is located in the AESO planning area of Edmonton (Area 60), which is part of the AESO Edmonton Planning Region. Edmonton (Area 60) is surrounded by the AESO planning areas of Athabasca/Lac La Biche (Area 27), Fort Saskatchewan (Area 33), Wetaskiwin (Area 31), and Wabamun (Area 40).

From a transmission system perspective, Edmonton (Area 60) consists of 500 kV, 240 kV, 138/144 kV, and 69/72 kV transmission systems. The existing 25 kV distribution system in SW Edmonton is currently served by the Summerside and Poundmaker POD substations, which are supplied through the 240 kV transmission system in Edmonton (Area 60).

The Study Area for the Project consists of all 240 kV transmission facilities in Edmonton (Area 60) and the tie lines connecting Edmonton (Area 60) to the rest of the AIES.

Figure 1-1 shows the existing and approved transmission system in the vicinity of the Project.

Page 12: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Con

nect

ion

Engi

neer

ing

Stud

y R

epor

t for

AU

C A

pplic

atio

n: E

PC

OR

Riv

ervi

ew S

ubst

atio

n N

ew P

OD

10

Figu

re 1

-1: T

rans

mis

sion

Sys

tem

in v

icin

ity o

f the

Pro

ject

909L

908L

1056L

(Nor

mal

ly O

pen

Poi

ntw

ithin

Sub

stat

ion)

(Nor

mal

ly O

pen

Poi

ntw

ithin

Sub

stat

ion)

(Nor

mal

ly O

pen

Poi

ntw

ithin

Sub

stat

ion)

POU

ND

MA

KE

R

1045

L/90

9L(to

Sun

danc

e 31

0P)

739L

(to

Car

vel

432S

)

792L

898L (toClyde150S)

174L

(to

Bar

do19

7S)

746L

700L

(to

Wes

twoo

d

422S

)

1043

L (to

Kee

phills

320

P)

1139

L

BILB

Y10

5S

STO

NY

PLA

IN43

4S

739AL

LED

UC

325S

838L

632L

858L (toWetaskiwin

40S)

Saun

ders

Lake

289

S

780L

Har

rySm

ith36

7S

174L

(to

Bard

o19

7S)

Clo

verb

ar#1

-3 (E

NC

1-3)

Uni

vers

ity o

f Alb

erta

(UO

A1-U

AO

2)

DO

ME

YAS

A28

6SJA

SP

ER

805S

NAM

AO

BER

NE

SE

293S

VIC

TOR

IA51

1S

LAM

BTO

N

CLO

VE

RBA

R 9

87S

GA

RN

EA

U

BELL

AM

Y

NO

RTH

CAL

DE

R37

S

PETR

OLI

A

EA

ST

ED

MO

NTO

N38

S

HAR

DIS

TY

RO

SS

DA

LE

KEN

NE

DA

LE

WO

OD

CR

OFT

STEL

CO

EDM

ON

TON

133S

STR

ATH

CO

NA

ME

AD

OW

LAR

K

IMPE

RIA

L O

ILED

MO

NTO

N 9

5S

CAS

TLE

DO

WN

S

INLA

ND

CEM

EN

T

ATPL

AS

TIC

5RS

ATPL

AS

TIC

4RS

ARG

YLL

EA

ST

IND

US

TRIA

L

726L

(to

Lam

oure

ux 7

1S)

920L

761L

(to

Lam

oure

ux71

S)

72LH8

908L

72C

N10

1058L

215L

898L

72C

H9

930L

946L947L

1055

L240CV5

72C

K13

72C

K12

1056L

72RS5

72C

H11

905L

(to

Wab

amun

19S

)

72RW3

1059

L

72JM18

780L897L

72VN21

915L947L

711L

72JW19

240BA2

921L

1044

L90

9L

1098

L

72N

W15

72RV6

72RG1

915L

1044L

920L

/921

L(to

Lam

oure

ux71

S)

1045

L10

44L

908L909L

908L

908L

909L

1055L

1059

AL

822A

L

908A

L1059L908L

72N

K23

72M

G16

738A

L

72RG7

72RV2

72RV4

72LS

24

738L737L

240BA3

736L

947L

822L

1202

L (to

Keep

hills

320

P)

1209

L (to

Gen

esee

330

P)

1206L/1212L (toHeartland 12S)

910L914L (toBigstone

86S)

1057L10

57L

908L

SUM

ME

RSI

DE

657S

ELLE

RS

LIE

89S

DEV

ON

14S

NIS

KU

149S

BRE

TON

A45

S

ACH

ES

ON

305S

VIS

CO

UN

T92

S

BLA

CK

MU

D15

5S

BA

SELI

NE

317S

BRO

ADM

OO

R42

0S

BRE

TVIL

LE18

5S

SPR

UC

EG

RO

VE

595S

N.W

. CA

RD

IFF

191S

CO

OK

ING

LAK

E 5

22S

FIB

ER

GLA

SS

SH

ER

WO

OD

PAR

K74

6S

KN

IGH

TSB

RID

GE

216S

NO

RTH

ST.A

LBE

RT

99S

CA

NA

DA

LIQ

UID

AIR

337

S

PE

TRO

-CA

NA

DA

ED

MO

NTO

N 1

84S

739L

746L

700L

731L

897L

712L

605L

747L

677L

606L

632L(toBuford538S)

865L

874L

604L

746B

L

741L

739L

739L

838L

712L

667L

761L

636L

705L

746A

L

60 -

Edm

onto

n

40 -

Wab

amun

33 -

Fort

Sas

k.

31 -

Wet

aski

win

P169

5 - A

rea

Tran

smis

sion

Sys

tem

This

dia

gram

con

tain

s a

sim

plifi

ed v

ersi

onof

the

syst

em c

onfig

urat

ion.

Tec

hnic

alde

tail

has

been

sim

plifi

ed fo

r illu

stra

tion

purp

oses

. It

does

not

indi

cate

geo

grap

hica

llo

catio

ns o

f fac

ilitie

s.

Gas

Gen

erat

or

Futu

re 2

40 k

V Su

bsta

tion

69 o

r 72

kV S

ubst

atio

n13

8 or

144

kV

Sub

stat

ion

240

kV S

ubst

atio

n50

0 kV

Sub

stat

ion

Futu

re 1

38/1

44 k

VFu

ture

138

/144

kV

Dou

ble

Circ

uit

Futu

re 2

40 k

V D

oubl

e C

ircui

t

Nor

mal

ly O

pen

Line

69/7

2 kV

138/

144

kV13

8/14

4 kV

Dou

ble

Circ

uit

240

kV24

0 kV

Dou

ble

Circ

uit

500

kV50

0 kV

Dou

ble

Circ

uit

P16

95 P

roje

ct A

rea

AE

SO

Pla

nnin

g A

reas

Cur

renc

y D

ate:

201

7-01

-24

Page 13: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

11

1.2.2.2. Existing Constraints

Existing constraints in the Edmonton Planning Region are managed in accordance with the

procedures set out in Section 302.1 of the ISO rules, Real Time Transmission Constraint

Management (TCM Rule).

1.2.2.3. AESO Long-Term Transmission Plans

The approved South and West Edmonton Area Transmission Development (SWEATD) will be in

the Study Area.2 The Harry Smith 367S substation, which was approved as a part of SWEATD,

is shown in Figure 1-1. The 240 kV transmission line between the Keephills 320P and the

Petrolia substations is currently designated the 1043L. As Figure 1-1 shows, once the approved

Harry Smith 367S substation is in service, the 240 kV transmission line between the Harry

Smith 367S and the Petrolia substations will be designated the 1139L. The Harry Smith 367S

substation is scheduled to be in-service December 5, 2017.

In addition to the approved SWEATD, the AESO 2015 Long-term Transmission Plan (2015

LTP)3 provides a plan for system developments in the City of Edmonton in the near-term,

medium-term, and long-term. According to the 2015 LTP, the following transmission system

enhancements were identified and were considered to be needed in the near-term (by 2020):

Convert Hardisty substation in east Edmonton to 240/15 kV from 72/15 kV

Add new 240 kV loop from Lambton substation in southeast Edmonton to Hardistysubstation and onto Bellamy substation at Rossdale

Discontinue use of 72 kV lines from Rossdale substation (Bellamy) to Strathconasubstation to Lambton substation

Replace existing 240/72 kV transformers at Clover Bar substation in northeastEdmonton with larger units

Add new 240/72 kV substation near Namao in northeast, cut into 240 kV line betweenCastle Downs substation and Victoria substation on north edge of downtown Edmonton

Add new 72 kV line from new substation to existing Namao substation

Add new 240/72 kV transformer at Castle Downs substation in northeast

Add new 72 kV transmission lines from Castle Downs substation to Kennedalesubstation, and onto Namao substation

Discontinue use of 72 kV lines between Clover Bar and Hardisty substations, andHardisty and Lambton substations

Discontinue use of existing 72 kV lines that connect Clover Bar, Victoria, Namao,Kennedale, and Woodcroft substations

Convert Victoria substation from 240/72/15 kV to 240/15 kV

Add new 240 kV line from Victoria substation to Bellamy substation

Discontinue use of 72 kV lines between Rossdale and Victoria substations

2 The South and West of Edmonton Area Transmission Development Needs Identification Document was

originally approved by the Alberta Utilities Commission on May 5, 2014 in Approval No. U2014-183 and Decision 2014-126. 3 The 2015 LTP document is available on the AESO website.

Page 14: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

12

1.2.3. Studies Performed

The following studies were performed for the pre-Project scenarios:

Power flow

The following studies were performed for the post-Project scenarios:

Power flow

Voltage stability

1.3. Report Overview

The Executive Summary provides a high-level summary of the assessment and its conclusions. Section 1 provides an introduction of the Project. Section 2 describes the criteria, system data,and other study assumptions used in this study. Section 3 presents the methodology used forthe studies. Section 4 presents the pre-Project study results. Section 5 presents the transmission alternatives examined. Section 6 provides the post-Project study results for the alternative that was selected for further study. Section 7 presents any dependencies the Project may have on other AESO plans to expand or enhance the transmission system, if any. Section 8 presents the conclusions and recommendations of this assessment.

Page 15: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

13

2. Criteria, System Data, and Study Assumptions

2.1. Criteria, Standards, and Requirements

2.1.1. Transmission Planning Standards and Reliability Criteria

The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability Standards, and the AESO’s Transmission Planning Criteria – Basis and Assumptions 4 (collectively, the Reliability Criteria) were applied to evaluate system performance under Category A system conditions (i.e., all elements in-service) and following Category B contingencies (i.e., single element outage), prior to and following the studied alternatives. Below is a summary of Category A and Category B system conditions.

Category A, often referred to as the N-0 condition, represents a normal system with no contingencies and all facilities in service. Under this condition, the system must be able to supply all firm load and firm transfers to other areas. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages.

Category B events, often referred to as an N-1 or N-G-1 with the most critical generator out of service, result in the loss of any single specified system element under specified fault conditions with normal clearing. These elements include a generator, a transmission circuit, a transformer or a single pole of a DC transmission line. The acceptable impact on the system is the same as Category A. Planned or controlled interruptions of electric supply to radial customers or some local network customers, connected to or supplied by the faulted element or by the affected area, may occur in certain areas without impacting the overall reliability of the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of contracted firm (non-recallable reserved) transmission service electric power transfers.

The TPL standards, TPL-001-AB-0 and TPL-002-AB-0, have referenced Applicable Ratings when specifying the required system performance under Category A and Category B events. For the purpose of applying the TPL standards to the studies documented in this report, Applicable Ratings are defined as follows:

Seasonal continuous thermal rating of the line’s loading limits.

Highest specified loading limits for transformers.

For Category A conditions: Voltage range under normal operating condition follows the

AESO Information Document ID# 2010-007RS, General Operating Practices - Voltage

Control (ID #2010-007RS). ID#2010-007RS relates to Section 304.4 of the ISO rules,

Maintaining Network Voltage. For the busses not listed in ID #2010-007RS, Table 2-1 in

the Transmission Planning Criteria – Basis and Assumptions applies.

For Category B conditions: The extreme voltage range values per Table 2-1 in the

Transmission Planning Criteria – Basis and Assumptions.

Desired post-contingency voltage change limits for three defined post event timeframes

as provided in Table 2-1.

4 Filed under a separate cover

Page 16: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

14

Table 2-1: Post-Contingency Voltage Deviations Guidelines for Low Voltage POD Busses

Parameter and reference point

Time Period

Post-Transient (up to 30 sec)

Post-Auto Control (30 sec to 5 min)

Post-Manual Control (Steady State)

Voltage deviation from steady state at POD low voltage bus

±10% ±7% ±5%

2.1.2. ISO Rules and Information Documents

AESO ID# 2010-007RS was applied to establish pre-contingency voltage profiles in the Study Area. The TCM Rule was followed in setting up the study scenarios and assessing the study results. The Reliability Criteria is the basis for planning the AIES. In addition, due regard was given to the AESO’s Connection Study Requirements Document and the AESO’s Generation and Load Interconnection Standard.

2.2. Study Scenarios

At the time of study, the scheduled ISD for the Project was October 1, 2018. As a result, the studies were performed using 2018 winter peak (WP) and 2019 summer peak (SP) study scenarios. The scheduled ISD has since been revised from October 1, 2018 to October 1, 2019. The shift in the scheduled ISD does not materially impact the results of this connection assessment, and does not change the conclusions and recommendations contained in the report.

Table 2-2 provides a list of the study scenarios. The post-Project scenarios include the DFO-requested Rate DTS contract capacity of 24 MW. This connection assessment will assume a 0.9 lagging power factor for the load associated with the Project.

Table 2-2: List of the Connection Study Scenarios

Scenario Year/Season

Load pre-Project/ post-

Project Project Load

(MW)

Project Generation

(MW)

System Generation Dispatch

Conditions

1 2018 Winter Peak (WP)

pre-Project 0.0 0 Market Dispatch

2 2019

Summer Peak (SP)

pre-Project 0.0 0 Market Dispatch

3 2018 WP post-Project 24.0 0 Market Dispatch

4 2019 SP post-Project 24.0 0 Market Dispatch

Page 17: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

15

2.3. Load and Generation Assumptions

2.3.1. Load Assumptions

The Study Area load forecast used for this connection study is shown in Table 2-3 and corresponds to the forecasted area load during the forecasted Edmonton Region seasonal peak load, which was based on the AESO 2016 Long-term Outlook (2016 LTO). As part of its planning responsibilities, the AESO updates its corporate forecasts routinely to ensure they reflect the latest economic projects, factors and timing. While the AESO has updated its regional forecasts since the connection studies were performed, the use of the current AESO forecast, the AESO 2017 Long-term Outlook, would not materially alter the connection study results or affect the conclusions and recommendations in this report.

For the studies, when loads are modified to align with the load forecast in the 2016 LTO, the active power to reactive power ratio in the base case scenarios were maintained.

Table 2-3: Forecast Area Load (2016 LTO at Edmonton Region Peak)

Area Name Year/Season Forecast Peak

Load (MW)

Edmonton (Area 60) 2018 WP 2024

2019 SP 2114

Edmonton Region 2018 WP 2367

2019 SP 2428

2.3.2. Generation Assumptions

The key generation dispatch conditions for the study scenarios are described in Table 2-4. The Cloverbar #3 generating unit was identified as the critical generating unit, and was considered to be out-of-service to represent the N-G condition for all studies.

Table 2-4: Key System Generation Dispatch Conditions

Unit Name Unit No.

Bus Number

AESO Planning

Area

Pmax (MW)

2018 WP

Unit Net Generation

* (MW)

2019 SP

Unit Net Generation (MW)

Clover Bar

G1 25516 60 44 0 0

G2 26516 60 100 0 0

G3 27516 60 101 N-G**

N-G

University of Alberta

Cogeneration

G1 25352 60 39 14 2

G2

*Unit Net Generation refers to Gross Generating unit MW output less Unit Service Load.

** “N-G” indicates the critical generating unit that is assumed by the AESO to be offline to test the N-G contingency

condition

Page 18: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

16

2.3.3. Intertie Flow Assumptions and HVDC Assumptions

The Alberta-BC, Alberta-Montana, and Alberta-Saskatchewan intertie points are deemed to be too far away from the Study Area to have any material impact on the results of the studies. Therefore, the AESO planning base case intertie flow assumptions were used for the study scenarios.

The Western Alberta Transmission HVDC Line (WATL) and the Eastern Alberta Transmission HVDC Line (EATL) assumptions were expected to have minimal impact for the results of the studies. Therefore, the AESO planning base case HVDC assumptions were used for the study scenarios.

2.4. System Projects

The approved transmission developments that are a part of the SW Edmonton project are assumed to be in service for the studies. This includes the approved Harry Smith 367S substation and its connection to the existing 240 kV transmission line 1043L, which will be designated the 1139L (between the Harry Smith 367S and the Petrolia substations) after the Harry Smith 367S is connected.

The remaining of the AESO long term plans described in Section 1.2.2.3 were not included in the study scenarios.

2.5. Customer Connection Projects

Customer connection projects within the Study Area that have passed Gate 2 of the AESO

Connection Process as of October 2017 were modelled in the study scenarios based on their

positions in the AESO Connection Queue. Table 2-5 summarizes the customer connection

projects in Edmonton (Area 60) that were included in the studies.

Table 2-5: Summary of Included Customer Projects in Edmonton (Area 60)

Queue Position* Scheduled In-Service Date

AESO Project Name AESO

Project No. Gen (MW)

Load (MW)

32 Feb 1, 2019

Fortis New Anthony Henday Substation P1442 0.0 21.0

37 Feb 1, 2020

CP Genesee Generating Units 4 and 5 P1440 1010.0 50.0

51 Dec 12, 2017

Fortis Cooking Lake 522A Capacity Increase

P1674 0.0 3.7

53 Nov 30, 2019

EPCOR Garneau Area Upgrade – Phase 2

P1649 0.0 0.0

54 Feb 28, 2019

EPCOR Garneau Area Upgrade – Phase 1

P1649 0.0 20.9

56 Dec 21, 2018 EPCOR Strathcona Capacity Increase

P1659 0.0 14.2

*Per the AESO Connection Queue posted in October 2017. The projects in the Study Area, if any, that have queuepositions after the Project (AESO Project P1695) are not listed in this table and were not included in the studyscenarios.

Page 19: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

17

2.6. Facility Ratings and Shunt Elements

The legal owners of transmission facilities (TFOs) in the area provided the facility ratings for the existing transmission lines in the vicinity of the Study Area. The ratings of the key transmission lines are shown in Table 2-6 and the ratings of key transformers are shown in Table 2-7.

Table 2-6: Key Transmission Circuits in the vicinity of the Study Area

Line ID Line Description Voltage Class (kV)

Seasonal Continuous Rating

(MVA)

Short-term Emergency Rating

(MVA)

Summer Winter Summer Winter

1055L Petrolia-Argyll 240 419 517 503 620

1056L Ellerslie 89S-Argyll 240 419 517 503 620

1058L Summerside-Lambton 240 578 711 694 853

1139L* Petrolia-Approved Harry Smith 367S 240 831 831 831 831

1043L Approved Harry Smith 367S-Keephills

320P 240 989 1225 1187 1470

1044L Petrolia-Jasper 240 481 581 577 697

1045L Jasper-Sundance 310P 240 481 581 577 697

930L Poundmaker-Jasper 240 481 581 577 697

1098L Jasper-Poundmaker 240 481 581 577 697

*1139L is currently named the 1043L. It will be named the 1139L after the approved Harry Smith 367S substation isin service.

Table 2-7: Summary of Key Transformer Ratings in the Study Area

Substation Name and Number Transformer ID Transformer Voltages (kV)

Rating (MVA)

Heartland 12S T1 500/240 1200

Ellerslie 89S T1 500/240 1200

Ellerslie 89S T2 500/240 1200

Table 2-8 below provides summary of shunt elements in the Study Area.

Table 2-8: Summary of Shunt Elements in the Study Area

Substation Name and Number*

Voltage Class (kV)

Number of Switched Shunt

Blocks

Total at Nominal

Voltage (MVAr)

East Edmonton 38S 138 2 x 48.91 MVAr 97.82

Leduc 325S 138 1 x 30 MVAr 30.0

Page 20: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

18

Substation Name and Number*

Voltage Class (kV)

Number of Switched Shunt

Blocks

Total at Nominal

Voltage (MVAr)

Nisku 149S 138 1 x 30 MVAr 30.0

Acheson 305S 138 1 x 24.46 MVAr 24.46

Jasper 240 1 x 105.31 MVAr 105.31

Rossdale 69 2 x 47.76 95.51

Cloverbar 69 1 x 31.57 31.57

Stelco Edmonton 133S

34.5 1 x 16.8 + 1 x 30

MVAr 46.8

2.7. Voltage Profile Assumptions

The AESO ID# 2010-007RS is used to establish the pre-contingency voltage profiles for key area busses prior to commencing any studies. Table 2-1 of the Transmission Planning Criteria – Basis and Assumptions applies for all the busses not included in the ID# 2010-007RS. These voltages will be utilized to set the voltage profile for the study base cases prior to power flow analysis. A list of operating voltages for the key busses in the Study Area is shown in Table 2-9.

Table 2-9: Bus Voltages of Key Substations in the Study Area

Substation Nominal Voltage (kV) Minimum Operating

Limit (kV)

Desired Range

(kV)

Maximum Operating Limit

(kV)

Genesee 330P 500 518 525 – 540 550

138 124 124 – 152 152

Lambton 240 240 245 – 254 255

East Edmonton 38S 240 240 240 – 253 255

138 139 139 – 144 145

Jasper 240 240 245 – 254 255

Petrolia 240 240 245 – 254 255

Clover Bar 240 240 245 – 254 255

Page 21: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

19

3. Study Methodology

The studies performed in this connection assessment were completed using PTI PSS/E version 33.

3.1. Connection Studies Carried Out

The studies to be carried out for this connection study are identified in Table 3-1.

Table 3-1: Summary of Studies Performed

Study Scenario System Conditions Power Flow

Voltage Stability

1 2018 WP pre-Project Category A and Category B X -

2 2019 SP pre-Project Category A and Category B X

3 2018 WP post-Project Category A and Category B X X

4 2019 SP post-Project Category A and Category B X -

3.2. Power Flow Analysis

Pre-Project and post-Project power flow studies were conducted to identify and compare study scenario thermal and voltage criteria violations as per the Reliability Criteria, and to identify any POD low voltage bus deviations that are outside the guidelines, shown in Table 2-1. The purpose of the power flow analysis is to quantify any violations in the Study Area, for both pre-Project and post-Project study scenarios. For the Category B power flow studies, the transformer taps and switched shunt reactive compensation devices such as shunt capacitors and reactors were locked and continuous shunt devices were enabled.

POD low voltage bus deviations were assessed by both the pre-Project and post-Project networks by first locking all tap changers and area capacitors to identify any post-transient voltage deviations above 10%. Second, tap changers were then allowed to adjust, while shunt reactive compensating devices capacitors remained locked; to determine if any voltage deviations above 7% would occur in the area. Third, all taps and shunt reactive compensating devices were adjusted and voltage deviations above 5% would be reported.

3.2.1. Contingencies Studied

The power flow studies included the Category A and all Category B contingencies (240 kV facilities only) within the Study Area.

3.3. Voltage Stability Studies

The objective of the voltage stability studies is to determine the ability of the transmission system to maintain voltage stability at all busses in the system under Category A and B

Page 22: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

20

conditions. The power-voltage (PV) curve is a representation of voltage change as a result of increased power transfer between two systems. The incremental transfers are reported to the collapse point.

For load connection projects, the load level modelled in post-Project scenarios are the same or higher than in pre-connection scenarios. Therefore, voltage stability studies for pre-Project scenarios would only be performed if the post-Project scenarios show voltage stability criteria violations.

The voltage stability analysis was performed according to the Western Electricity Coordinating Council (WECC) Voltage Stability Assessment Methodology. WECC voltage stability criteria states, for load areas, post-transient voltage stability is required for the area modelled at a minimum of 105% of the reference load level for Category A and Category B conditions. For this standard, the reference load level is the maximum established planned load.

Typically, voltage stability analysis is carried out assuming worst case loading scenarios. For the Project’s worst case scenario, load was increased in Edmonton (Area 60) and the corresponding generation was increased in Fort McMurray (Area 25).

3.3.1. Contingencies Studied

The voltage stability studies were performed for the Category A condition and all Category B contingencies (240 kV facilities only) in the Study Area for the 2018 WP post-Project scenario.

Page 23: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

21

4. Results of Pre-Project Studies

4.1. Pre-Project Power Flow Studies

This section provides the results of the pre-Project power flow studies. The pre-Project power

flow diagrams are provided in Attachment A.

4.1.1. Scenario 1 (2018 WP pre-Project)

No Reliability Criteria violations were observed under the Category A condition.

No Reliability Criteria violations were observed under Category B conditions.

4.1.2. Scenario 2 (2019 SP pre-Project)

No Reliability Criteria violations were observed under the Category A condition.

No Reliability Criteria violations were observed under Category B conditions.

Page 24: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

22

5. Connection Alternatives

5.1. Overview

The DFO informed the AESO that it intends to request system access service to address

capacity and reliability concerns on its 25 kV distribution system in southeast (SE) Edmonton in

the near future.5 For the sake of transmission system planning efficiency, given the proximity of

the 25 kV distribution system in SW Edmonton to SE Edmonton, six transmission alternatives

were examined that address the current request for system access service, as well as the

DFO’s SE Edmonton capacity and reliability concerns.

The AESO examined these six transmission alternatives in consultation with the DFO and the

legal owners of transmission facilities (TFOs) that own facilities in the area.

5.2. Transmission Alternatives Identified

Alternative 1: Upgrade the existing Petrolia substation and add a new POD substation in SE Edmonton

Alternative 1 involves the following transmission development:

upgrading the existing Petrolia substation including adding two 240/25 kV

transformers, two 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment; and

adding a new POD substation in SE Edmonton, including adding two 240/25 kV

transformers, four 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment and connection the new POD to the AIES

The DFO has advised that Alternative 1 would also require the addition of ten new 25 kV distribution circuits, with a total length of approximately 97 km.

Alternative 2: Upgrade the existing Jasper substation and add a new POD substation in SE Edmonton

Alternative 2 involves the following transmission development:

upgrading the existing Jasper substation including adding two 240/25 kV

transformers, two 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment; and

adding a new POD substation in SE Edmonton, including adding two 240/25 kV

transformers, four 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment and connecting the new POD to the AIES.

The DFO has advised that Alternative 2 would also require the addition of ten new 25 kV

distribution circuits, with a total length of approximately 162 km.

5 See the EPCOR Distribution & Transmission Inc. Distribution Deficiency Report (DDR) for Riverview

Service Area, which is attached under a separate cover.

Page 25: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

23

Alternative 3: Upgrade the existing Summerside and Poundmaker substations and a new POD substation in SE Edmonton

Alternative 3 involves the following transmission development:

upgrading the existing Summerside substation including adding one 240/25 kV

transformer, one 240 kV circuit breaker, and four 25 kV feeder circuit breakers and

associated equipment;

upgrading the existing Poundmaker substation including adding one 240/25 kV

transformer, one 240 kV circuit breaker, and four 25 kV feeder circuit breakers and

associated equipment; and

adding a new POD substation in SE Edmonton, including two 240/25 kV

transformers, four 240 kV circuit breakers, and eight 25 kV feeder circuit breakers

and associated equipment and connecting it to the AIES.

The DFO has advised that Alternative 3 would also require the addition of ten new 25 kV distribution circuits, with a total length of approximately 97 km.

Alternative 4: Add a new POD substation in SW Edmonton, to be called the Riverview substation, and upgrades to the existing Summerside substation

Alternative 4 involves the following transmission developments:

adding a new POD substation in SW Edmonton, to be called the Riverview

substation, including two 240/25 kV transformers, four 240 kV circuit breakers, and

eight 25 kV feeder circuit breakers and associated equipment;

connecting the proposed Riverview substation to the existing 240 kV transmission

line 1043L (future 1139L) using an in-and-out configuration, between the approved

Harry Smith 367S substation and the Petrolia substation, by adding two new 240 kV

transmission circuits, each approximately 70 metres in length; and

upgrading the existing Summerside substation, including adding one 240/25 kV

transformer, one 240 kV circuit breaker, and four 25 kV feeder circuit breakers and

associated equipment.

The DFO has advised that Alternative 4 would also require the addition of ten new 25 kV

distribution circuits, with a total length of approximately 72 km.

Alternative 5: Add the proposed Riverview substation and add a new POD substation in SE Edmonton

Alternative 5 involves the following transmission development:

adding the proposed Riverview substation, including two 240/25 kV transformers,

four 240 kV circuit breakers, and eight 25 kV feeder circuit breakers and associated

equipment;

connecting the proposed Riverview substation to the existing 240 kV transmission

line 1043L (future 1139L) using an in-and-out configuration, between the approved

Page 26: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

24

Harry Smith 367S substation and the Petrolia substation, by adding two new 240 kV

transmission circuits, each approximately 70 metres in length; and

adding a new POD substation in SE Edmonton, including two 240/25 kV

transformers, four 240 kV circuit breakers and eight 25 kV feeder circuit breakers

and associated equipment and connecting it to the AIES.

The DFO has advised that Alternative 5 would also require the addition of ten new 25 kV distribution circuits, with a total length of approximately 59 km.

Alternative 6: Upgrade the existing Summerside and the Poundmaker substations

Alternative 6 involves the following transmission developments:

upgrading the existing Summerside substation, including replacing the two existing

240/25 kV transformers with two 240/25 kV transformers of higher capacity and adding a

third 240/25 kV transformer, one 240 kV circuit breaker, and eighteen 25 kV feeder

circuit breakers and associated equipment; and

upgrading the existing Poundmaker substation, including adding one 240/25 kV

transformer, one 240 kV circuit breaker, and four 25 kV feeder circuit breakers and

associated equipment.

The DFO has advised that Alternative 6 would also require the addition of ten new 25 kV distribution circuits, with a total length of approximately 110 km.

5.2.1. Transmission Alternatives Not Selected for Further Examination

Alternative 1 and Alternative 2 were not selected for further study because the TFO advised that

expansion of the Petrolia and Jasper substations is not viable, as explained further below.

The TFO has advised that Alternative 1 is not acceptable from an environmental and a

stakeholder impact perspective. From an environmental perspective, the TFO advised that there

was a spill on the Petrolia substation site in the early 1980s, which the TFO may not be able to

manage if transmission facilities are added to the substation. The TFO has also advised that

expanding the Petrolia substation would have an adverse impact to local residents, specifically

because the expanded substation site would encroach on an existing community park and

baseball diamond. As a result, Alternative 1 was not selected for further study.

Alternative 2 was not selected for further studies because the TFO has advised that there is

insufficient space within and around the Jasper substation to accommodate the addition of the

required transmission facilities. As a result, Alternative 2 was not selected for further study.

Alternative 3 and Alternative 6 were not selected for further study because the total combined

costs of the distribution and transmission developments were estimated to be higher than the

total combined costs of the distribution and transmission developments associated with

Alternative 4 and Alternative 5.6

6 Cost estimates for Alternative 3, Alternative 4, Alternative 5, and Alternative 6 are provided under a

separate cover.

Page 27: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

25

5.2.2. Transmission Alternatives Selected for Further Examination

Alternative 4 and Alternative 5 were both considered technically feasible and were selected for

further study. Both Alternative 4 and Alternative 5 involve adding the proposed Riverview

substation to address the DFO’s request for system access service.

Alternative 4 and Alternative 5 include different transmission facilities7 to address the capacity

and reliability concerns in SE Edmonton, which the DFO has indicated will be the subject of a

forthcoming request for system access service. Therefore, the selection of the preferred

transmission development to address the DFO’s capacity and reliability concerns in SE

Edmonton will be assessed as a part of a separate project, and is not within the scope of this

study.

For the purpose of responding to the DFO’s current request for system access service,

Alternative 4 and Alternative 5 are equivalent in scope; both alternatives address the current

request for system access service by adding a proposed Riverview substation in SW Edmonton

and connecting it to the existing 240 kV transmission line 1043L (future 1139L) in an in-and-out

configuration. Therefore, only this scope will be examined further in this report.

7 Alternative 4 includes adding a new POD substation in SE Edmonton and Alternative 5 includes

upgrading the existing Summerside substation.

Page 28: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

26

6. Results of Post-Project Studies

This section provides the results of the post-Project power flow and voltage stability, which includes the proposed Riverview substation with a Rate DTS request of 24 MW.

6.1. Post-Project Power Flow Studies

This section provides the results of the post-Project power flow studies. The post-Project power flow diagrams are provided in Attachment B.

6.1.1. Scenario 3 (2018 WP post-Project)

No Reliability Criteria violations were observed under the Category A condition.

No Reliability Criteria violations were observed under Category B conditions.

6.1.2. Scenario 4 (2019 SP post-Project)

No Reliability Criteria violations were observed under the Category A condition.

No Reliability Criteria violations were observed under Category B conditions.

6.2. Post-Project Voltage Stability Studies

Voltage stability analysis was performed for the 2018 WP post-Project scenario. The minimum incremental load transfer for the Category B conditions is 5.0% of the reference load or 105.7 MW to meet the voltage stability criteria. The table below summarizes the voltage stability study results for Category A and Category B conditions. The voltage stability diagrams are provided in Attachment C.

The voltage stability margin is met for all studied conditions.

Table 6-1: Voltage Stability Study Results for the 2018 WP post-Project Scenario

Contingency From To Maximum

incremental transfer (MW)

Meets 105% transfer criteria?

Category A 1153 Yes

908L Ellerslie 89S Petrolia 1152 Yes

1164L Riverview Petrolia 1148 Yes

1139L Riverview Harry Smith 367S 1147 Yes

1044L Jasper Petrolia 1152 Yes

1098L Poundmaker Jasper 1148 Yes

Page 29: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

27

7. Project Dependencies

The Project does not require the completion of any other AESO plans to expand or enhance the

transmission system prior to connection.

Page 30: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

28

Connection Engineering Study Report for AUC Application: EPCOR Riverview Substation New POD

8. Conclusions and Recommendations

The connection assessment did not identify any pre-Project or post-Project system performance

issues. The connection assessment indicates that the Project will not adversely impact the

performance of the AIES. No mitigation measures are required as no Reliability Criteria

violations were observed.

It is recommended to proceed with the Project by adding a new POD substation in SW

Edmonton as the preferred option to respond to the DFO’s request for system access service.

This includes: adding a new substation, to be designated the Riverview substation, including

two 240/25 kV LTC transformers, four 240 kV circuit breakers, and eight 25 kV feeder circuit

breakers and associated equipment; and adding two 240 kV circuits, each approximately 70

metres in length, to connect the Riverview substation to the existing 240 kV transmission line

1043L (future 1139L) using an in-and-out configuration between the approved Harry Smith 367S

substation and the existing Petrolia substation.

A minimum rating equal or greater than the rating of the existing 240 kV transmission line 1043L

is recommended for the two new 240 kV circuits.

Transformer Sizing Recommendation

EDTI DFO has advised that it foresees a need for 6 feeders in SW Edmonton in the near term

(within 10 years). EDTI DFO has also advised that provisions need to be made to eventually

enable the connection of 8 feeders in the medium term at the Riverview substation. EDTI TFO

has also advised that because it plans to install a 25 kV switchgear that will be gas-

insulated (GIS), it is not practical to install 6 feeder breakers now and 2 additional feeder

breakers in the future.

Since EDTI’s transformers have an average life of 50 years, EDTI DFO has requested that,

should the Riverview substation be chosen as the preferred alternative to address the Project

need, provisions be made to enable the connection of 8 feeders in the medium term at the

Riverview substation. EDTI DFO foresees that these feeders will eventually be loaded to their

design load rating of 12 MVA each.

EDTI TFO has advised that it sizes transformers based on their ability to serve all substation

load under an N-1 contingency of a transformer. For the proposed Riverview substation, that

would mean that two transformers would be needed. Each transformer should be capable of

serving all 8 feeders, given a diversity factor of 0.78 as per the EDTI DFO input; therefore based on the above information provided by EDTI, the AESO recommends that each transformer at the proposed Riverview substation have a rating of 75 MVA.

Page 31: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Attachment A

Power Flow Diagrams 2018 WP-2019SP Pre-Project

Page 32: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

PREP

RO

JEC

TBA

SE C

ASE

FIG

A-1

TUE,

OC

T 31

201

7 1

0:30

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W25

0.6

-18.

851

8AR

GY

LL E

-76.2-31.8

-172.838.7

172.8

250.

5-1

8.8

128

ELL

ER

SLI

250.

1-1

8.4

512

DO

ME

4

250.

5-1

8.4

135

SU

ND

ANC

4

260.

4-1

5.2

-74.9

76.2

250.

4-1

8.7

513

LAM

BTO

N4

248.

8-1

9.3

764

1058

JOIN

249.

0-1

9.2

891

904A

L TP

248.

9-1

9.4

250.

1-1

8.5

136

E E

DM

ON

424

9.0

-19.

5

186.3-185.7-13.0

514

CLO

VER

B4

249.

1-1

9.8

785

1059

A_TP

893

908

TP24

9.1

-19.

3

89.7-18.817.9

-48.729.2

48.7-30.1

-157.9-4.1

158.03.7

156.1-155.5

-79.818.5

14.5-189.1-15.3

-89.6

248.

9-1

9.5

2.6

519

CAS

TLE

DN

250.

1-2

0.6

520

VIC

TOR

IA24

9.9

-20.

7

57LA

MO

UR

E4

137

N C

ALD

E4

250.

7-2

0.1

75.6-9.2

-75.6-38.6

143.222.7

-143.0-23.1

-61.

89.

7

61.8-14.2

249.

4-2

0.4

521

PE

TRO

LIA

250.

6-1

8.6

92H

S_2

40

250.

9-1

6.7

505

JAS

PE

R 4

251.

7-1

9.5

420

KE

EP

HIL

4

255.

6-1

0.4

955

PD

MAK

ER

125

1.5

-19.

6

-110.1-28.9 27.7

110.2

133

WAB

AMU

N4

258.

0-1

6.5

138.338.3

-136.9-42.0

79.8-18.9

511

SU

MM

ER

S1

11.7

-4.1

185.024.8

-184.5-25.7

-184.4-25.8 25.7

79.8-19.4

-79.818.9

184.5 263.635.5

-263.6-35.4

-143

.467

.0

143.

9-6

9.4

-76.24.1

76.2

-5.0

-56.3-40.8

56.3

39.7

-75.1-172.8

74.9

-374.2-27.3 1 1.

025

374.650.6

-374.2-27.3 1 1.

025

374.650.6

189.6

173.0

39.5-42.5

-39.

540

.1

149.

935

.1

-149.8-35.2

186.

941

.4-1

84.0

-48.

3

143.

457

.8

-141

.4-6

9.5

-451

.9-1

6.0

456.

454

.1

421

KEEP

HIL5

256.

7-1

1.5

155

BENA

LTO

4

254.

5-1

0.5

122.

7-2

7.3

1

1

-122

.629

.9

-1.9

-24.

81.

9-1

5.3

-1.9

-24.

91.

9-1

5.3

-88.

125

.2

89.6

-59.

7

-88.

025

.5

89.6

-60.

1

SW -0.0

313

JOSE

PH1

249.

0-2

0.4

443

BANN

_240

249.

4-2

0.1

9.7

17.5

-9.7

-19.

5

-51.

751

.8-5

.2

13.4

-17.

8

-13.412.1

-5.2

341

HEAR

TLAN

252.

1-1

8.4

143.

940

.3-1

43.6

-44.

21.

7

T10.

00.

0

SW -115

.9

259.

6-1

0.8

-258

.913

.2

258

ELLE

RSLI

537.

8-1

4.9

Page 33: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

PREP

RO

JEC

TEL

LER

SLIE

T1

FIG

A-2

TUE,

OC

T 31

201

7 1

0:30

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

9.6

-19.

351

8AR

GY

LL E

-95.6-34.4

-147.442.0

147.4

249.

5-1

9.3

128

ELL

ER

SLI

249.

1-1

9.0

512

DO

ME

4

249.

5-1

8.9

135

SU

ND

ANC

4

260.

4-1

5.4

-78.0

95.6

249.

4-1

9.2

513

LAM

BTO

N4

247.

9-1

9.8

764

1058

JOIN

248.

0-1

9.7

891

904A

L TP

247.

9-1

9.9

249.

1-1

9.0

136

E E

DM

ON

424

8.0

-20.

0

173.3-172.8-11.7

514

CLO

VER

B4

248.

2-2

0.2

785

1059

A_TP

893

908

TP24

8.2

-19.

8

66.6-20.919.8

-38.630.3

38.6-31.2

-145.2-2.7

145.32.2

140.0-139.6

-69.719.6

12.7-176.4-13.9

-66.6

247.

9-1

9.9

0.8

519

CAS

TLE

DN

249.

4-2

0.8

520

VIC

TOR

IA24

9.2

-21.

0

57LA

MO

UR

E4

137

N C

ALD

E4

250.

1-2

0.4

81.5-6.9

-81.5-40.6

131.625.7

-131.4-26.2

-22.

912

.9

22.9-18.0

248.

8-2

0.4

521

PE

TRO

LIA

249.

7-1

9.0

92H

S_2

40

250.

2-1

6.8

505

JAS

PE

R 4

251.

1-1

9.8

420

KE

EP

HIL

4

255.

6-1

0.0

955

PD

MAK

ER

125

0.8

-20.

0

-95.4-28.1 26.7

95.5

133

WAB

AMU

N4

257.

9-1

6.8

138.342.0

-136.8-45.6

69.7-20.0

511

SU

MM

ER

S1

9.9

-1.3

174.823.5

-174.3-24.6

-174.3-24.8 24.6

69.7-20.5

-69.720.0

174.3 253.534.3

-253.5-34.2

-125

.972

.2

126.

3-7

5.0

-95.61.3

95.7

-2.0

-66.7-46.5

66.7

45.5

-78.4-147.4

78.0

1 1.02

5

-606.9-31.9 1 1.

025

607.693.2

176.8

147.6

6.0-46.6

-6.0

44.1

135.

234

.1

-135.1-34.3

189.

847

.2-1

86.8

-53.

3

154.

165

.5

-151

.8-7

5.3

-490

.7-1

9.0

496.

166

.5

421

KEEP

HIL5

256.

7-1

0.5

155

BENA

LTO

4

254.

4-1

0.5

59.6

-28.

5

1

1

-59.

529

.4

-12.

1-2

3.7

12.1

-16.

3

-12.

1-2

3.7

12.2

-16.

3

-91.

926

.9

93.5

-60.

6

-91.

927

.2

93.5

-61.

0

SW -0.0

313

JOSE

PH1

248.

5-2

0.4

443

BANN

_240

248.

8-1

9.8

-12.

814

.712

.8-1

6.6

-90.

991

.0-6

.3

30.9

-18.

4

-30.912.9

-4.0

341

HEAR

TLAN

251.

8-1

7.7

183.

442

.0-1

82.8

-43.

23.

5

T10.

00.

0

SW -115

.2

295.

2-6

.7-2

94.2

11.7

258

ELLE

RSLI

537.

9-1

3.3

Page 34: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

PREP

RO

JEC

T90

8L (E

LLER

SLIE

TO

PET

RO

LIA)

FIG

A-3

TUE,

OC

T 31

201

7 1

0:30

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W25

0.6

-18.

851

8AR

GY

LL E

-48.6-60.3

-200.667.4

200.7

250.

5-1

8.8

128

ELL

ER

SLI

250.

0-1

8.4

512

DO

ME

4

250.

3-1

8.3

135

SU

ND

ANC

4

260.

4-1

5.2

-103.5

48.6

250.

4-1

8.7

513

LAM

BTO

N4

248.

7-1

9.3

764

1058

JOIN

248.

9-1

9.2

891

904A

L TP

248.

7-1

9.4

249.

9-1

8.4

136

E E

DM

ON

424

8.8

-19.

5

187.1-186.4-12.2

514

CLO

VER

B4

248.

9-1

9.7

785

1059

A_TP

893

908

TP24

9.0

-19.

3

91.1-20.319.4

-49.329.9

49.3-30.8

-158.7-3.3

158.82.9

157.0-156.5

-80.419.1

13.7-189.8-14.5

-91.0

248.

7-1

9.4

1.6

519

CAS

TLE

DN

250.

1-2

0.6

520

VIC

TOR

IA24

9.9

-20.

8

57LA

MO

UR

E4

137

N C

ALD

E4

250.

8-2

0.2

75.4-9.0

-75.4-38.8

139.925.6

-139.7-26.0

-64.

112

.4

64.2-16.8

249.

3-2

0.4

521

PE

TRO

LIA

251.

0-1

8.7

92H

S_2

40

251.

1-1

6.8

505

JAS

PE

R 4

251.

9-1

9.6

420

KE

EP

HIL

4

255.

6-1

0.5

955

PD

MAK

ER

125

1.7

-19.

7

-105.6-33.3 32.1

105.7

133

WAB

AMU

N4

258.

1-1

6.5

139.037.4

-137.5-41.1

80.4-19.6

511

SU

MM

ER

S1

10.9

24.3

185.524.2

-185.1-25.1

-185.0-25.2 25.1

80.4-20.1

-80.419.6

185.1 264.234.9

-264.2-34.8

-137

.060

.5

137.

4-6

3.3

-48.6-24.3

48.6

23.3

-54.2-42.7

54.2

41.6

-103.3-200.7103.5

-372.3-30.3 1 1.

025

372.753.4

-372.3-30.3 1 1.

025

372.753.4

190.4

200.9

145.

439

.5

-145.3-39.6

188.

839

.3-1

85.9

-45.

9

141.

259

.6

-139

.3-7

1.4

-455

.7-1

2.3

460.

351

.1

421

KEEP

HIL5

256.

6-1

1.5

155

BENA

LTO

4

254.

5-1

0.5

119.

8-2

7.2

1

1

-119

.729

.7

-1.4

-25.

01.

4-1

5.2

-1.4

-25.

01.

5-1

5.2

-88.

325

.4

89.9

-59.

8

-88.

325

.7

89.8

-60.

2

SW -0.0

313

JOSE

PH1

249.

0-2

0.4

443

BANN

_240

249.

3-2

0.1

9.4

17.5

-9.4

-19.

4

-52.

252

.2-5

.4

16.5

-20.

4

-16.514.8

-4.2

341

HEAR

TLAN

252.

1-1

8.4

144.

440

.2-1

44.1

-44.

11.

9

T10.

00.

0

SW -116

.1

265.

0-1

6.1

-264

.318

.8

258

ELLE

RSLI

537.

7-1

4.9

Page 35: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

PREP

RO

JEC

T11

39L

(HAR

RY

SMIT

H T

O P

ETR

OLI

A)FI

G A

-4TU

E, O

CT

31 2

017

10:

30

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

9.9

-20.

251

8AR

GY

LL E

4.0-35.4

-246.442.7

246.5

249.

9-2

0.2

128

ELL

ER

SLI

249.

6-1

9.6

512

DO

ME

4

250.

0-1

9.5

135

SU

ND

ANC

4

260.

4-1

5.9

-78.4

-4.0

249.

9-2

0.0

513

LAM

BTO

N4

248.

4-2

0.5

764

1058

JOIN

248.

6-2

0.4

891

904A

L TP

248.

4-2

0.6

249.

6-1

9.6

136

E E

DM

ON

424

8.5

-20.

7

181.5-180.9-12.8

514

CLO

VER

B4

248.

6-2

0.9

785

1059

A_TP

893

908

TP24

8.7

-20.

5

82.0-19.218.3

-44.929.5

44.9-30.3

-153.2-3.8

153.23.4

150.4-149.8

-76.018.7

14.1-184.3-15.0

-82.0

248.

4-2

0.6

2.2

519

CAS

TLE

DN

249.

6-2

1.6

520

VIC

TOR

IA24

9.4

-21.

8

57LA

MO

UR

E4

137

N C

ALD

E4

250.

3-2

1.1

82.2-8.0

-82.1-39.6

147.123.1

-146.9-23.4

-48.

510

.3

48.5-15.1

249.

0-2

1.4

521

PE

TRO

LIA

249.

9-2

0.2

92H

S_2

40

252.

1-1

3.5

505

JAS

PE

R 4

251.

2-2

0.7

420

KE

EP

HIL

4

255.

6-9

.3

955

PD

MAK

ER

125

1.0

-20.

8

-70.9-30.4 28.8

70.9

133

WAB

AMU

N4

258.

0-1

7.1

152.639.9

-150.9-41.6

76.0-19.1

511

SU

MM

ER

S1

11.3

-0.4

181.124.6

-180.7-25.5

-180.6-25.7 25.5

76.0-19.6

-76.019.1

180.7 259.835.3

-259.8-35.2

-83.

264

.1

83.4

-68.

0

4.00.4

-4.0

-1.5

-74.4-40.2

74.5

39.2

-77.8-246.5

78.4

-416.2-29.5 1 1.

025

416.658.4

-416.2-29.5 1 1.

025

416.658.4

184.8

246.8

157.9-49.3

-157

.748

.3

110.

636

.0

-110.6-36.3

208.

543

.7-2

05.0

-46.

9

162.

059

.9

-159

.6-6

9.0

-303

.0-2

5.3

305.

135

.5

421

KEEP

HIL5

256.

5-1

1.2

155

BENA

LTO

4

254.

4-1

0.6

216.

0-2

2.5

1

1

-215

.829

.9

-27.

6-2

1.0

27.7

-18.

5

-27.

7-2

1.0

27.8

-18.

6

-99.

328

.9

101.

2-6

1.3

-99.

329

.2

101.

2-6

1.7

SW -0.0

313

JOSE

PH1

248.

7-2

1.4

443

BANN

_240

249.

0-2

1.0

3.6

16.3

-3.6

-18.

2

-57.

557

.5-5

.2

16.1

-16.

8

-16.111.1

-5.0

341

HEAR

TLAN

251.

8-1

9.3

149.

740

.7-1

49.4

-44.

21.

8

T10.

00.

0

SW -115

.4

258

ELLE

RSLI

537.

2-1

5.7

Page 36: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

PREP

RO

JEC

T10

44L

(JAS

PER

TO

PET

RO

LIA)

FIG

A-5

TUE,

OC

T 31

201

7 1

0:30

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

9.9

-18.

551

8AR

GY

LL E

-128.4-9.1

-142.420.6

142.5

249.

9-1

8.6

128

ELL

ER

SLI

249.

6-1

8.2

512

DO

ME

4

250.

0-1

8.2

135

SU

ND

ANC

4

260.

4-1

5.7

-56.8

128.5

249.

8-1

8.5

513

LAM

BTO

N4

248.

4-1

9.2

764

1058

JOIN

248.

6-1

9.1

891

904A

L TP

248.

4-1

9.3

249.

6-1

8.3

136

E E

DM

ON

424

8.5

-19.

4

196.3-195.6-9.3

514

CLO

VER

B4

248.

7-1

9.7

785

1059

A_TP

893

908

TP24

8.7

-19.

2

107.5-25.524.8

-56.432.2

56.4-33.1

-167.7-0.4

167.80.1

168.4-167.7

-87.521.4

11.2-198.9-11.7

-107.4

248.

4-1

9.3

-1.7

519

CAS

TLE

DN

250.

8-2

1.4

520

VIC

TOR

IA25

0.6

-21.

5

57LA

MO

UR

E4

137

N C

ALD

E4

251.

7-2

1.2

53.7-2.3

-53.7-45.8

75.447.7

-75.4-48.8

-91.

722

.7

91.8-26.3

249.

4-2

0.7

521

PE

TRO

LIA

249.

8-1

8.2

92H

S_2

40

250.

5-1

6.4

505

JAS

PE

R 4

253.

4-2

1.1

420

KE

EP

HIL

4

255.

6-1

0.3

955

PD

MAK

ER

125

3.1

-21.

2

-7.0-72.8 71.1

7.0

133

WAB

AMU

N4

258.

2-1

7.1

153.430.1

-151.7-32.1

87.5-21.8

511

SU

MM

ER

S1

8.3

-26.5

192.722.2

-192.2-22.9

-192.1-23.0 22.9

87.5-22.3

-87.521.8

192.2 271.432.9

-271.4-32.9

-128.526.5

128.

6-2

7.0

-29.4-51.2

29.5

50.0

-57.2-142.5

56.8

-365.4-36.1 1 1.

025

365.858.5

-365.4-36.1 1 1.

025

365.858.5

199.5

142.6

-26.2-9.8

26.2

7.2

46.7

78.2

-46.7-78.6

228.

321

.6-2

24.2

-22.

2

116.

165

.8

-114

.6-7

9.8

-442

.0-2

4.6

446.

360

.7

421

KEEP

HIL5

256.

6-1

1.4

155

BENA

LTO

4

254.

5-1

0.6

121.

8-2

6.9

1

1

-121

.629

.5

-6.3

-24.

46.

3-1

5.7

-6.3

-24.

46.

3-1

5.7

-96.

927

.9

98.6

-60.

8

-96.

828

.2

98.6

-61.

2

SW -0.0

313

JOSE

PH1

249.

1-2

0.7

443

BANN

_240

249.

4-2

0.2

3.8

19.4

-3.8

-21.

4

-60.

160

.2-7

.4

59.2

-35.

9

-59.131.0

-0.3

341

HEAR

TLAN

252.

1-1

8.5

152.

438

.7-1

52.0

-42.

14.

0

T10.

00.

0

SW -117

.4

233.

72.

3-2

33.1

-1.5

258

ELLE

RSLI

537.

5-1

4.8

Page 37: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

PREP

RO

JEC

T10

43L

(HAR

RY

SMIT

H K

EEPH

ILLS

)FI

G A

-6TU

E, O

CT

31 2

017

10:

30

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

8.8

-21.

851

8AR

GY

LL E

44.4-28.6

-290.634.9

290.8

248.

7-2

1.8

128

ELL

ER

SLI

248.

6-2

1.2

512

DO

ME

4

249.

1-2

1.1

135

SU

ND

ANC

4

260.

4-1

7.4

-70.1

-44.4

248.

8-2

1.6

513

LAM

BTO

N4

247.

4-2

2.1

764

1058

JOIN

247.

6-2

1.9

891

904A

L TP

247.

4-2

2.1

248.

6-2

1.2

136

E E

DM

ON

424

7.5

-22.

2

183.4-182.8-11.2

514

CLO

VER

B4

247.

7-2

2.5

785

1059

A_TP

893

908

TP24

7.7

-22.

1

84.0-21.320.4

-46.430.8

46.4-31.7

-155.1-2.2

155.11.8

152.3-151.8

-77.520.0

12.7-186.2-13.5

-84.0

247.

4-2

2.2

0.6

519

CAS

TLE

DN

248.

7-2

3.5

520

VIC

TOR

IA24

8.4

-23.

6

57LA

MO

UR

E4

137

N C

ALD

E4

249.

3-2

3.0

78.3-6.3

-78.3-40.9

124.722.1

-124.6-22.7

-52.

415

.1

52.4-19.7

248.

2-2

3.0

521

PE

TRO

LIA

248.

6-2

1.9

92H

S_2

40

247.

4-2

2.7

505

JAS

PE

R 4

250.

1-2

2.5

420

KE

EP

HIL

4

255.

6-6

.8

955

PD

MAK

ER

124

9.9

-22.

7

-88.1-25.4 24.0

88.2

133

WAB

AMU

N4

257.

6-1

9.0

155.444.8

-153.6-45.8

77.5-20.4

511

SU

MM

ER

S1

9.8

-6.8

182.623.5

-182.2-24.3

-182.1-24.5 24.3

77.5-20.9

-77.520.4

182.2 261.334.2

-261.3-34.2

-90.

074

.0

90.2

-77.

5

44.46.8

-44.

4-7

.9

-74.6-48.2

74.7

47.2

-68.8-290.8

70.1

-483.7-34.4 1 1.

025

484.273.6

-483.7-34.4 1 1.

025

484.273.6

186.7

291.2

222.3-38.6

-221

.739

.0

127.

931

.4

-127.9-31.6

219.

452

.7-2

15.4

-53.

4

162.

368

.5

-159

.8-7

7.0

421

KEEP

HIL5

256.

1-1

0.2

155

BENA

LTO

4

254.

0-1

0.8

385.

4-6

.4

1

1

-385

.029

.3

-84.

3-1

1.1

85.2

-23.

2

-84.

5-1

1.0

85.5

-23.

3

-126

.138

.5

129.

1-6

5.0

-126

.139

.0

129.

1-6

5.5

SW -0.0

313

JOSE

PH1

248.

0-2

3.0

443

BANN

_240

248.

3-2

2.5

-4.3

11.9

4.3

-13.

9

-74.

174

.2-5

.6

34.6

-14.

2

-34.68.8

-3.2

341

HEAR

TLAN

251.

2-2

0.6

166.

541

.5-1

66.0

-43.

92.

5

T10.

00.

0

SW -114

.4

-97.

4-2

9.9

97.6

25.1

258

ELLE

RSLI

536.

0-1

6.6

Page 38: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

REP

RO

JEC

TBA

SE C

ASE

FIG

A-7

TUE,

OC

T 31

201

7 1

0:30

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

7.9

-19.

251

8AR

GY

LL E

-97.7-54.5

-198.2-41.4

198.2

247.

7-1

9.3

128

ELL

ER

SLI

248.

2-1

8.9

512

DO

ME

4

248.

5-1

8.7

135

SU

ND

ANC

4

260.

4-1

4.3

6.0

97.7

247.

9-1

9.2

513

LAM

BTO

N4

246.

3-1

9.8

764

1058

JOIN

246.

5-1

9.7

891

904A

L TP

246.

2-1

9.9

248.

1-1

8.9

136

E E

DM

ON

424

6.3

-20.

0

200.6-199.8-37.4

514

CLO

VER

B4

246.

6-2

0.3

785

1059

A_TP

893

908

TP24

6.5

-19.

8

84.0-36.235.4

-55.222.9

55.2-23.7

-170.5-24.9

170.624.6

163.9-163.3

-87.98.1

40.2-203.3-40.2

-84.0

246.

2-2

0.0

14.9

519

CAS

TLE

DN

248.

2-2

1.0

520

VIC

TOR

IA24

8.2

-21.

2

57LA

MO

UR

E4

137

N C

ALD

E4

248.

5-2

0.4

93.0-35.6

-93.0-11.4

168.9-2.4

-168.72.6

-67.

332

.0

67.4-36.1

247.

9-2

1.0

521

PE

TRO

LIA

248.

2-1

9.0

92H

S_2

40

249.

0-1

7.0

505

JAS

PE

R 4

249.

1-1

9.8

420

KE

EP

HIL

4

255.

6-1

0.8

955

PD

MAK

ER

124

8.9

-19.

9

-110.5-8.7 7.6

110.6

133

WAB

AMU

N4

257.

5-1

5.9

170.949.4

-168.7-47.7

87.9-8.5

511

SU

MM

ER

S1

36.9

19.4

198.249.9

-197.7-50.1

-197.6-50.1 50.1

87.9-9.0

-87.98.5

197.7 271.666.6

-271.6-66.5

-123

.554

.7

123.

8-5

7.7

-97.7-19.4

97.7

18.7

-95.1-29.2

95.1

28.3

5.9-198.2

-6.0

-368.3-118.3 1 1.

01

368.7143.5

-368.3-118.3 1 1.

01

368.7143.5

203.9

198.4

35.5-12.7

-35.

510

.2

155.

721

.0

-155.6-21.0

232.

860

.9-2

28.3

-58.

6

192.

070

.6

-188

.7-7

4.5

-450

.7-4

6.6

455.

385

.7

421

KEEP

HIL5

256.

5-1

1.9

155

BENA

LTO

4

254.

0-1

0.0

130.

0-2

2.0

1

1

-129

.924

.9

15.2

-29.

9-1

5.1

-10.

0

15.2

-29.

9-1

5.2

-9.9

-80.

725

.7

82.0

-61.

1

-80.

726

.0

82.0

-61.

5

SW -0.0

313

JOSE

PH1

248.

1-2

1.0

443

BANN

_240

247.

9-2

0.7

-5.8

-17.

45.

815

.5

-48.

148

.1-4

.5

0.2

-9.6

-0.23.9

-16.9

341

HEAR

TLAN

250.

6-1

9.1

138.

740

.0-1

38.3

-44.

01.

0

T10.

00.

0

SW -113

.5

262.

43.

6-2

61.7

-0.8

258

ELLE

RSLI

533.

7-1

5.4

Page 39: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

REP

RO

JEC

TEL

LER

SLIE

T1

FIG

A-8

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

5.8

-19.

851

8AR

GY

LL E

-116.6-64.0

-173.2-29.9

173.3

245.

7-1

9.8

128

ELL

ER

SLI

246.

0-1

9.4

512

DO

ME

4

246.

4-1

9.3

135

SU

ND

ANC

4

260.

4-1

4.7

-5.0

116.6

245.

8-1

9.7

513

LAM

BTO

N4

244.

2-2

0.4

764

1058

JOIN

244.

4-2

0.2

891

904A

L TP

244.

2-2

0.4

245.

9-1

9.5

136

E E

DM

ON

424

4.3

-20.

6

187.6-186.9-32.5

514

CLO

VER

B4

244.

7-2

0.7

785

1059

A_TP

893

908

TP24

4.5

-20.

4

61.6-43.742.8

-45.026.9

45.0-27.7

-157.8-20.0

157.919.7

148.0-147.5

-77.712.1

34.9-190.5-35.4

-61.6

244.

2-2

0.5

9.0

519

CAS

TLE

DN

246.

9-2

1.3

520

VIC

TOR

IA24

6.9

-21.

5

57LA

MO

UR

E4

137

N C

ALD

E4

247.

3-2

0.8

99.1-29.6

-99.1-16.9

157.71.4

-157.5-1.4

-29.

246

.0

29.2-50.4

246.

7-2

1.1

521

PE

TRO

LIA

246.

3-1

9.5

92H

S_2

40

247.

7-1

7.2

505

JAS

PE

R 4

247.

7-2

0.2

420

KE

EP

HIL

4

255.

6-1

0.4

955

PD

MAK

ER

124

7.5

-20.

3

-95.9-4.1 2.7

95.9

133

WAB

AMU

N4

257.

2-1

6.3

171.057.3

-168.7-55.1

77.7-12.5

511

SU

MM

ER

S1

31.6

29.5

188.045.9

-187.5-46.3

-187.4-46.4 46.3

77.7-13.0

-77.712.5

187.5 261.362.8

-261.3-62.7

-105

.969

.0

106.

2-7

2.1

-116.6-29.5

116.

729

.1

-105.1-43.8

105.

143

.0

-5.2-173.3

5.0

1 1.01

-596.5-161.5 1 1.

01

597.2226.5

191.1

173.4

2.6-28.3

-2.6

25.8

141.

016

.0

-141.0-16.2

236.

073

.7-2

31.2

-69.

8

202.

688

.6

-198

.7-8

9.4

-488

.5-5

9.9

494.

010

8.9

421

KEEP

HIL5

256.

5-1

1.0

155

BENA

LTO

4

253.

8-1

0.1

68.1

-24.

5

1

1

-68.

025

.5

5.1

-29.

4-5

.0-1

0.6

5.1

-29.

4-5

.1-1

0.6

-84.

927

.9

86.4

-62.

5

-84.

928

.2

86.3

-62.

8

SW -0.0

313

JOSE

PH1

247.

2-2

1.0

443

BANN

_240

247.

0-2

0.5

-27.

8-2

7.1

27.8

25.2

-87.

087

.1-0

.0

17.5

-7.3

-17.51.7

-11.6

341

HEAR

TLAN

250.

2-1

8.4

177.

847

.3-1

77.3

-48.

6-2

.8

T10.

00.

0

SW -112

.2

296.

918

.1-2

96.0

-12.

5

258

ELLE

RSLI

534.

7-1

3.8

Page 40: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

REP

RO

JEC

T90

8L (E

LLER

SLIE

TO

PET

RO

LIA)

FIG

A-9

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

7.8

-19.

351

8AR

GY

LL E

-72.6-62.3

-223.4-33.5

223.5

247.

7-1

9.3

128

ELL

ER

SLI

248.

1-1

8.8

512

DO

ME

4

248.

4-1

8.7

135

SU

ND

ANC

4

260.

4-1

4.4

-1.8

72.6

247.

8-1

9.2

513

LAM

BTO

N4

246.

2-1

9.8

764

1058

JOIN

246.

5-1

9.7

891

904A

L TP

246.

2-1

9.9

248.

1-1

8.8

136

E E

DM

ON

424

6.2

-20.

0

201.3-200.5-37.1

514

CLO

VER

B4

246.

5-2

0.2

785

1059

A_TP

893

908

TP24

6.5

-19.

8

85.3-36.635.8

-55.823.1

55.8-23.9

-171.2-24.7

171.324.4

164.8-164.2

-88.48.3

39.9-204.0-40.0

-85.2

246.

2-1

9.9

14.7

519

CAS

TLE

DN

248.

2-2

1.0

520

VIC

TOR

IA24

8.2

-21.

2

57LA

MO

UR

E4

137

N C

ALD

E4

248.

5-2

0.5

92.9-35.5

-92.8-11.5

165.9-1.7

-165.71.8

-69.

532

.9

69.6-36.9

247.

8-2

1.0

521

PE

TRO

LIA

248.

2-1

9.1

92H

S_2

40

249.

0-1

7.1

505

JAS

PE

R 4

249.

1-1

9.8

420

KE

EP

HIL

4

255.

6-1

0.8

955

PD

MAK

ER

124

9.0

-20.

0

-106.3-9.8 8.6

106.4

133

WAB

AMU

N4

257.

5-1

6.0

171.549.3

-169.2-47.6

88.4-8.7

511

SU

MM

ER

S1

36.6

27.2

198.849.7

-198.2-49.9

-198.1-49.9 49.9

88.5-9.2

-88.48.7

198.2 272.166.4

-272.1-66.4

-117

.653

.2

117.

9-5

6.4

-72.6-27.2

72.7

26.3

-93.2-30.2

93.2

29.3

-1.5-223.5

1.8

-366.8-119.4 1 1.

01

367.2144.4

-366.8-119.4 1 1.

01

367.2144.4

204.6

223.7

151.

521

.9

-151.5-22.0

234.

660

.7-2

30.0

-58.

0

190.

071

.3

-186

.7-7

5.5

-453

.7-4

6.1

458.

485

.8

421

KEEP

HIL5

256.

5-1

1.9

155

BENA

LTO

4

254.

0-1

0.0

127.

7-2

2.1

1

1

-127

.624

.8

15.6

-29.

9-1

5.5

-9.9

15.6

-30.

0-1

5.6

-9.9

-81.

025

.8

82.3

-61.

1

-80.

926

.1

82.3

-61.

5

SW -0.0

313

JOSE

PH1

248.

1-2

1.0

443

BANN

_240

247.

9-2

0.7

-6.0

-17.

66.

015

.6

-48.

548

.5-4

.5

3.0

-10.

2

-3.04.5

-16.6

341

HEAR

TLAN

250.

6-1

9.0

139.

140

.0-1

38.7

-44.

01.

0

T10.

00.

0

SW -113

.5

267.

02.

7-2

66.2 0.5

258

ELLE

RSLI

533.

7-1

5.4

Page 41: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

REP

RO

JEC

T11

39L

(HAR

RY

SMIT

H T

O P

ETR

OLI

A)FI

G A

-10

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

7.0

-20.

751

8AR

GY

LL E

-16.7-53.7

-272.3-41.4

272.5

246.

9-2

0.7

128

ELL

ER

SLI

247.

5-2

0.1

512

DO

ME

4

247.

8-1

9.9

135

SU

ND

ANC

4

260.

4-1

5.1

6.6

16.7

247.

1-2

0.5

513

LAM

BTO

N4

245.

6-2

1.1

764

1058

JOIN

245.

9-2

0.9

891

904A

L TP

245.

6-2

1.1

247.

4-2

0.1

136

E E

DM

ON

424

5.6

-21.

2

195.6-194.9-36.6

514

CLO

VER

B4

245.

9-2

1.5

785

1059

A_TP

893

908

TP24

5.9

-21.

1

76.4-37.236.4

-51.323.5

51.3-24.3

-165.7-24.2

165.823.9

158.1-157.5

-84.08.7

39.3-198.4-39.5

-76.4

245.

6-2

1.2

14.0

519

CAS

TLE

DN

247.

6-2

2.1

520

VIC

TOR

IA24

7.6

-22.

3

57LA

MO

UR

E4

137

N C

ALD

E4

248.

0-2

1.5

99.9-33.4

-99.9-13.3

173.1-1.8

-172.92.1

-54.

034

.0

54.1-38.4

247.

4-2

2.1

521

PE

TRO

LIA

247.

2-2

0.6

92H

S_2

40

250.

8-1

3.9

505

JAS

PE

R 4

248.

4-2

1.1

420

KE

EP

HIL

4

255.

6-9

.7

955

PD

MAK

ER

124

8.3

-21.

2

-70.9-8.0 6.4

70.9

133

WAB

AMU

N4

257.

4-1

6.6

185.452.5

-182.8-48.2

84.0-9.1

511

SU

MM

ER

S1

36.0

18.8

194.349.2

-193.8-49.5

-193.7-49.6 49.5

84.0-9.6

-84.09.1

193.8 267.766.0

-267.7-65.9

-62.

755

.0

62.8

-59.

2

-16.7-18.8

16.7

17.7

-113.3-29.7

113.

428

.9

7.5-272.5

-6.6

-410.4-123.2 1 1.

01

410.9154.2

-410.4-123.2 1 1.

01

410.9154.2

199.0

272.8

155.4-13.0

-155

.111

.8

116.

019

.6

-116.0-19.8

254.

865

.6-2

49.4

-58.

4

210.

974

.7

-206

.9-7

5.2

-301

.8-4

5.9

303.

856

.5

421

KEEP

HIL5

256.

3-1

1.7

155

BENA

LTO

4

253.

9-1

0.2

223.

6-1

6.8

1

1

-223

.424

.7

-10.

5-2

6.4

10.5

-13.

5

-10.

6-2

6.5

10.6

-13.

5

-92.

129

.4

93.8

-62.

8

-92.

129

.7

93.8

-63.

2

SW -0.0

313

JOSE

PH1

247.

7-2

2.0

443

BANN

_240

247.

4-2

1.7

-11.

9-2

0.0

11.9

18.1

-53.

953

.9-4

.2

2.9

-7.8

-2.92.1

-16.2

341

HEAR

TLAN

250.

2-2

0.0

144.

540

.7-1

44.1

-44.

40.

8

T10.

00.

0

SW -112

.8

258

ELLE

RSLI

533.

0-1

6.3

Page 42: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

REP

RO

JEC

T10

44L

(JAS

PER

TO

PET

RO

LIA)

FIG

A-1

1TU

E, O

CT

31 2

017

10:

31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

7.3

-19.

051

8AR

GY

LL E

-142.6-35.6

-172.3-56.3

172.4

247.

2-1

9.0

128

ELL

ER

SLI

247.

7-1

8.7

512

DO

ME

4

248.

1-1

8.6

135

SU

ND

ANC

4

260.

4-1

4.8

21.0

142.7

247.

4-1

8.9

513

LAM

BTO

N4

245.

9-1

9.7

764

1058

JOIN

246.

1-1

9.5

891

904A

L TP

245.

8-1

9.8

247.

7-1

8.7

136

E E

DM

ON

424

5.9

-19.

9

209.1-208.3-34.3

514

CLO

VER

B4

246.

2-2

0.2

785

1059

A_TP

893

908

TP24

6.2

-19.

7

99.1-41.640.9

-61.825.4

61.8-26.2

-178.9-21.9

179.021.7

174.4-173.7

-94.510.5

37.5-211.6-37.3

-99.0

245.

8-1

9.8

11.4

519

CAS

TLE

DN

248.

8-2

1.7

520

VIC

TOR

IA24

8.8

-21.

8

57LA

MO

UR

E4

137

N C

ALD

E4

249.

3-2

1.3

74.0-30.2

-73.9-17.1

110.817.4

-110.7-18.2

-92.

742

.8

92.9-46.0

247.

9-2

1.2

521

PE

TRO

LIA

247.

6-1

8.6

92H

S_2

40

248.

7-1

6.8

505

JAS

PE

R 4

250.

5-2

1.2

420

KE

EP

HIL

4

255.

6-1

0.7

955

PD

MAK

ER

125

0.2

-21.

2

-21.8-44.4 42.5

21.8

133

WAB

AMU

N4

257.

6-1

6.5

183.842.9

-181.3-39.5

94.5-10.9

511

SU

MM

ER

S1

34.1

0.7

204.947.7

-204.3-47.8

-204.2-47.8 47.8

94.5-11.4

-94.510.9

204.3 278.264.5

-278.2-64.5

-142.7-0.7

142.

80.

5

-72.0-38.5

72.0

37.5

20.7-172.4-21.0

-360.7-125.3 1 1.

01

361.1149.9

-360.7-125.3 1 1.

01

361.1149.9

212.3

172.5

-21.014.6

21.0

-17.

1

66.9

55.5

-66.9-55.9

268.

745

.5-2

63.0

-36.

6

168.

476

.7

-165

.6-8

3.7

-442

.2-5

3.6

446.

791

.1

421

KEEP

HIL5

256.

4-1

1.8

155

BENA

LTO

4

254.

0-1

0.1

129.

1-2

1.7

1

1

-129

.024

.6

11.4

-29.

5-1

1.4

-10.

4

11.4

-29.

6-1

1.4

-10.

4

-88.

328

.0

89.9

-62.

1

-88.

328

.2

89.8

-62.

4

SW -0.0

313

JOSE

PH1

248.

2-2

1.2

443

BANN

_240

247.

9-2

0.8

-10.

8-1

5.9

10.8

13.9

-55.

255

.3-6

.3

39.2

-24.

6

-39.119.3

-12.9

341

HEAR

TLAN

250.

6-1

9.1

145.

938

.6-1

45.5

-42.

32.

9

T10.

00.

0

SW -114

.7

240.

014

.4-2

39.4

-13.

0

258

ELLE

RSLI

533.

4-1

5.3

Page 43: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

REP

RO

JEC

T10

43L

(HAR

RY

SMIT

H K

EEPH

ILLS

)FI

G A

-12

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

5.5

-22.

451

8AR

GY

LL E

21.7-43.6

-314.8-52.7

315.0

245.

4-2

2.4

128

ELL

ER

SLI

246.

2-2

1.7

512

DO

ME

4

246.

6-2

1.6

135

SU

ND

ANC

4

260.

4-1

6.8

18.6

-21.7

245.

7-2

2.2

513

LAM

BTO

N4

244.

3-2

2.7

764

1058

JOIN

244.

6-2

2.6

891

904A

L TP

244.

3-2

2.8

246.

1-2

1.8

136

E E

DM

ON

424

4.4

-22.

9

197.7-196.9-34.6

514

CLO

VER

B4

244.

7-2

3.1

785

1059

A_TP

893

908

TP24

4.6

-22.

7

78.6-39.939.0

-52.925.3

52.9-26.1

-167.7-22.1

167.821.8

160.3-159.6

-85.610.4

37.4-200.4-37.5

-78.6

244.

3-2

2.8

11.9

519

CAS

TLE

DN

246.

3-2

4.1

520

VIC

TOR

IA24

6.3

-24.

3

57LA

MO

UR

E4

137

N C

ALD

E4

246.

6-2

3.5

95.8-30.7

-95.8-15.5

150.6-3.8

-150.43.7

-58.

340

.2

58.4-44.3

246.

4-2

3.8

521

PE

TRO

LIA

245.

5-2

2.5

92H

S_2

40

244.

0-2

3.2

505

JAS

PE

R 4

247.

0-2

3.0

420

KE

EP

HIL

4

255.

6-7

.3

955

PD

MAK

ER

124

6.9

-23.

1

-89.0-3.3 1.8

89.0

133

WAB

AMU

N4

256.

9-1

8.6

187.958.8

-185.2-53.5

85.6-10.8

511

SU

MM

ER

S1

34.1

9.1

195.947.8

-195.4-48.0

-195.3-48.1 48.0

85.6-11.3

-85.610.8

195.4 269.364.7

-269.3-64.6

-70.

866

.5

71.0

-70.

4

21.7-9.1

-21.

78.

0

-113.2-39.9

113.

339

.1

20.2-315.0-18.6

-477.5-131.7 1 1.

01

478.0173.4

-477.5-131.7 1 1.

01

478.0173.4

201.1

315.4

217.03.0

-216

.4-2

.7

134.

115

.1

-134.1-15.3

265.

477

.8-2

59.5

-67.

4

210.

985

.9

-206

.8-8

5.5

421

KEEP

HIL5

255.

9-1

0.7

155

BENA

LTO

4

253.

5-1

0.4

392.

4-0

.1

1

1

-392

.023

.8

-67.

1-1

7.4

67.7

-19.

0

-67.

4-1

7.4

68.0

-19.

0

-119

.339

.0

121.

9-6

6.7

-119

.239

.4

121.

9-6

7.2

SW -0.0

313

JOSE

PH1

246.

9-2

3.7

443

BANN

_240

246.

5-2

3.3

-19.

6-2

6.8

19.6

24.9

-70.

470

.5-3

.9

21.3

-3.3

-21.3-2.2

-14.0

341

HEAR

TLAN

249.

4-2

1.4

161.

242

.2-1

60.7

-44.

70.

7

T10.

00.

0

SW -111

.5

-91.

4-3

9.9

91.6

35.3

258

ELLE

RSLI

531.

5-1

7.2

Page 44: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Attachment B

Power Flow Diagrams 2018 WP-2019SP Post-Project

Page 45: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

POST

PRO

JEC

TBA

SE C

ASE

FIG

B-1

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W25

0.4

-18.

751

8AR

GY

LL E

-72.1-31.6

-181.130.1

181.1

250.

3-1

8.8

128

ELL

ER

SLI

250.

0-1

8.4

512

DO

ME

4

250.

4-1

8.3

135

SU

ND

ANC

4

260.

4-1

5.1

-66.2

72.2

250.

3-1

8.6

513

LAM

BTO

N4

248.

8-1

9.2

764

1058

JOIN

249.

0-1

9.1

891

904A

L TP

248.

8-1

9.3

250.

0-1

8.4

136

E E

DM

ON

424

8.9

-19.

4

183.0-182.4-11.2

514

CLO

VER

B4

249.

0-1

9.7

785

1059

A_TP

893

908

TP24

9.1

-19.

2

88.5-19.018.2

-48.229.2

48.2-30.0

-155.1-2.5

155.22.1

153.4-152.9

-78.718.7

12.5-185.7-13.4

-88.5

248.

8-1

9.4

1.2

519

CAS

TLE

DN

249.

9-2

0.5

520

VIC

TOR

IA24

9.7

-20.

7

57LA

MO

UR

E4

137

N C

ALD

E4

250.

6-2

0.0

78.8-4.7

-78.8-43.0

143.525.0

-143.3-25.3

-61.

69.

3

61.6-13.9

249.

3-2

0.3

521

PE

TRO

LIA

250.

4-1

8.5

92H

S_2

40

250.

8-1

6.6

505

JAS

PE

R 4

251.

6-1

9.4

420

KE

EP

HIL

4

255.

6-1

0.4

955

PD

MAK

ER

125

1.4

-19.

6

-108.8-29.1 27.9

108.9

133

WAB

AMU

N4

258.

0-1

6.4

138.038.9

-136.5-42.7

78.7-19.1

511

SU

MM

ER

S1

9.7

-4.2

181.522.7

-181.0-23.6

-180.9-23.8 23.6

78.7-19.7

-78.719.1

181.0 258.632.9

-258.6-32.9

-138

.069

.6

138.

4-7

2.2

-72.24.2

72.2

-5.2

-57.9-42.2

57.9

41.1

-66.4-181.1

66.2

-374.2-28.7 1 1.

025

374.652.1

-374.2-28.7 1 1.

025

374.652.1

186.2

181.3

48.3-37.1

-48.

334

.6

147.

835

.2

-147.8-35.3

186.

842

.4-1

83.9

-49.

1

143.

358

.5

-141

.3-7

0.2

-453

.2-1

8.7

457.

757

.1

421

KEEP

HIL5

256.

7-1

1.4

155

BENA

LTO

4

254.

5-1

0.4

121.

6-2

7.2

1

1

-121

.529

.8

-1.8

-24.

91.

8-1

5.3

-1.8

-24.

91.

8-1

5.3

-87.

825

.2

89.3

-59.

7

-87.

825

.5

89.3

-60.

1

SW -0.0

313

JOSE

PH1

249.

0-2

0.3

443

BANN

_240

249.

3-2

0.0

9.4

17.1

-9.4

-19.

1

-51.

351

.3-5

.1

14.7

-16.

0

-14.710.3

-3.9

341

HEAR

TLAN

252.

1-1

8.3

143.

540

.4-1

43.1

-44.

31.

6

979

RIVE

RVIE

W1

250.

4-1

8.1

-239

.122

.123

9.3

-21.

826

3.9

-6.7

-263

.4 8.6

SW -115

.8

258

ELLE

RSLI

537.

7-1

4.9

2979

RIVE

RVIE

WS2

25.1

-20.

239

79RI

VERV

IEW

S3

26.1

-20.

1

12.0 6.6

1

0.9816

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 46: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

POST

PRO

JEC

TEL

LER

SLIE

T1

FIG

B-2

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

9.4

-19.

251

8AR

GY

LL E

-91.7-34.3

-156.133.4

156.2

249.

3-1

9.2

128

ELL

ER

SLI

249.

0-1

8.9

512

DO

ME

4

249.

4-1

8.8

135

SU

ND

ANC

4

260.

4-1

5.4

-69.3

91.7

249.

3-1

9.1

513

LAM

BTO

N4

247.

8-1

9.7

764

1058

JOIN

248.

0-1

9.6

891

904A

L TP

247.

9-1

9.8

249.

0-1

8.9

136

E E

DM

ON

424

8.0

-19.

9

169.8-169.3-9.8

514

CLO

VER

B4

248.

1-2

0.1

785

1059

A_TP

893

908

TP24

8.1

-19.

7

65.6-21.120.1

-38.430.2

38.4-31.1

-142.3-1.1

142.40.6

137.3-136.9

-68.919.7

10.7-172.8-11.9

-65.6

247.

9-1

9.8

-0.7

519

CAS

TLE

DN

249.

3-2

0.7

520

VIC

TOR

IA24

9.0

-20.

9

57LA

MO

UR

E4

137

N C

ALD

E4

250.

0-2

0.3

85.0-2.3

-84.9-45.1

132.128.0

-131.9-28.4

-22.

712

.7

22.7-17.8

248.

7-2

0.3

521

PE

TRO

LIA

249.

5-1

9.0

92H

S_2

40

250.

0-1

6.8

505

JAS

PE

R 4

251.

0-1

9.7

420

KE

EP

HIL

4

255.

6-1

0.0

955

PD

MAK

ER

125

0.7

-19.

9

-94.1-28.3 26.9

94.2

133

WAB

AMU

N4

257.

9-1

6.7

138.042.8

-136.5-46.3

68.9-20.2

511

SU

MM

ER

S1

7.9

-1.3

170.921.2

-170.5-22.4

-170.5-22.6 22.4

68.9-20.7

-68.920.2

170.5 248.131.6

-248.1-31.5

-120

.575

.0

120.

9-7

7.9

-91.71.3

91.8

-2.1

-68.2-48.0

68.2

47.0

-69.7-156.2

69.3

1 1.02

5

-606.8-34.0 1 1.

025

607.695.3

173.3

156.3

15.0-41.3

-15.

038

.7

133.

234

.1

-133.1-34.3

189.

848

.2-1

86.8

-54.

2

154.

066

.4

-151

.7-7

6.1

-492

.0-2

1.8

497.

469

.7

421

KEEP

HIL5

256.

7-1

0.5

155

BENA

LTO

4

254.

4-1

0.5

58.5

-28.

5

1

1

-58.

429

.3

-12.

0-2

3.8

12.0

-16.

3

-12.

1-2

3.8

12.1

-16.

3

-91.

726

.8

93.3

-60.

6

-91.

627

.1

93.3

-61.

0

SW -0.0

313

JOSE

PH1

248.

5-2

0.3

443

BANN

_240

248.

8-1

9.7

-13.

214

.213

.2-1

6.1

-90.

590

.5-6

.1

32.3

-16.

5

-32.311.0

-2.6

341

HEAR

TLAN

251.

7-1

7.6

182.

942

.2-1

82.3

-43.

43.

2

979

RIVE

RVIE

W1

249.

6-1

8.4

-274

.520

.527

4.7

-19.

529

9.5

-2.4

-298

.7 6.4

SW -115

.1

258

ELLE

RSLI

537.

8-1

3.2

2979

RIVE

RVIE

WS2

25.0

-20.

639

79RI

VERV

IEW

S3

26.0

-20.

5

12.0 6.6

1

0.9816

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 47: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

POST

PRO

JEC

T90

8L (E

LLER

SLIE

TO

PET

RO

LIA)

FIG

B-3

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W25

0.4

-18.

851

8AR

GY

LL E

-38.2-56.4

-214.954.8

215.0

250.

3-1

8.8

128

ELL

ER

SLI

249.

9-1

8.3

512

DO

ME

4

250.

3-1

8.2

135

SU

ND

ANC

4

260.

4-1

5.1

-90.8

38.2

250.

2-1

8.7

513

LAM

BTO

N4

248.

7-1

9.2

764

1058

JOIN

248.

9-1

9.1

891

904A

L TP

248.

7-1

9.3

249.

9-1

8.3

136

E E

DM

ON

424

8.8

-19.

4

184.0-183.4-10.5

514

CLO

VER

B4

248.

9-1

9.6

785

1059

A_TP

893

908

TP24

9.0

-19.

2

90.2-20.219.4

-48.629.6

48.6-30.4

-156.2-1.8

156.21.4

154.7-154.1

-79.119.1

11.8-186.7-12.7

-90.1

248.

7-1

9.3

0.3

519

CAS

TLE

DN

250.

0-2

0.5

520

VIC

TOR

IA24

9.7

-20.

7

57LA

MO

UR

E4

137

N C

ALD

E4

250.

7-2

0.1

78.4-4.4

-78.4-43.4

139.427.5

-139.2-27.9

-64.

411

.6

64.5-16.1

249.

3-2

0.3

521

PE

TRO

LIA

250.

7-1

8.7

92H

S_2

40

250.

9-1

6.7

505

JAS

PE

R 4

251.

8-1

9.5

420

KE

EP

HIL

4

255.

6-1

0.4

955

PD

MAK

ER

125

1.5

-19.

6

-103.2-32.9 31.7

103.3

133

WAB

AMU

N4

258.

0-1

6.5

138.838.2

-137.3-41.9

79.1-19.5

511

SU

MM

ER

S1

9.0

20.4

182.422.0

-182.0-22.9

-181.9-23.1 22.9

79.1-20.0

-79.119.5

182.0 259.632.3

-259.6-32.2

-130

.164

.0

130.

4-6

6.9

-38.2-20.4

38.2

19.4

-55.3-44.0

55.3

42.9

-90.5-215.0

90.8

-372.0-31.3 1 1.

025

372.454.4

-372.0-31.3 1 1.

025

372.454.4

187.2

215.3

142.

238

.9

-142.2-39.0

189.

240

.6-1

86.3

-47.

1

140.

660

.2

-138

.7-7

2.0

-457

.5-1

5.6

462.

255

.0

421

KEEP

HIL5

256.

6-1

1.4

155

BENA

LTO

4

254.

5-1

0.4

118.

3-2

7.2

1

1

-118

.229

.7

-1.3

-25.

01.

3-1

5.2

-1.3

-25.

01.

3-1

5.2

-88.

125

.3

89.6

-59.

8

-88.

125

.6

89.6

-60.

1

SW -0.0

313

JOSE

PH1

249.

0-2

0.3

443

BANN

_240

249.

3-1

9.9

9.1

17.0

-9.0

-19.

0

-51.

851

.8-5

.2

18.5

-18.

2

-18.412.6

-3.0

341

HEAR

TLAN

252.

1-1

8.3

144.

040

.3-1

43.7

-44.

21.

7

979

RIVE

RVIE

W1

250.

6-1

8.2

-245

.526

.924

5.7

-26.

527

0.3

-11.

1-2

69.7

13.4

SW -115

.9

258

ELLE

RSLI

537.

6-1

4.8

2979

RIVE

RVIE

WS2

25.1

-20.

339

79RI

VERV

IEW

S3

26.1

-20.

2

12.0 6.6

1

0.9816

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 48: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

POST

PRO

JEC

T11

39L

(HAR

RY

SMIT

H T

O R

IVER

VIEW

)FI

G B

-4TU

E, O

CT

31 2

017

10:

31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

9.7

-20.

151

8AR

GY

LL E

9.4-34.3

-255.633.3

255.8

249.

7-2

0.1

128

ELL

ER

SLI

249.

5-1

9.6

512

DO

ME

4

249.

9-1

9.4

135

SU

ND

ANC

4

260.

4-1

5.8

-69.0

-9.4

249.

7-2

0.0

513

LAM

BTO

N4

248.

3-2

0.4

764

1058

JOIN

248.

5-2

0.3

891

904A

L TP

248.

3-2

0.5

249.

5-1

9.6

136

E E

DM

ON

424

8.4

-20.

6

178.1-177.5-10.9

514

CLO

VER

B4

248.

5-2

0.8

785

1059

A_TP

893

908

TP24

8.6

-20.

4

80.7-19.618.7

-44.029.5

44.0-30.4

-150.4-2.2

150.41.8

147.7-147.1

-74.519.0

12.1-180.9-13.1

-80.6

248.

3-2

0.5

0.7

519

CAS

TLE

DN

249.

5-2

1.5

520

VIC

TOR

IA24

9.2

-21.

7

57LA

MO

UR

E4

137

N C

ALD

E4

250.

2-2

1.1

85.3-3.3

-85.3-44.1

147.425.4

-147.2-25.6

-48.

010

.2

48.0-15.0

248.

9-2

1.3

521

PE

TRO

LIA

249.

7-2

0.1

92H

S_2

40

252.

1-1

3.4

505

JAS

PE

R 4

251.

1-2

0.7

420

KE

EP

HIL

4

255.

6-9

.2

955

PD

MAK

ER

125

0.9

-20.

8

-68.9-30.2 28.5

68.9

133

WAB

AMU

N4

257.

9-1

7.1

152.540.8

-150.8-42.4

74.5-19.5

511

SU

MM

ER

S1

9.3

-1.4

177.822.4

-177.4-23.4

-177.3-23.6 23.4

74.5-20.0

-74.519.5

177.4 255.032.7

-255.0-32.6

-76.

767

.4

76.9

-71.

4

9.41.4

-9.4

-2.5

-76.3-41.9

76.4

40.9

-68.2-255.8

69.0

-416.8-31.5 1 1.

025

417.360.5

-416.8-31.5 1 1.

025

417.360.5

181.4

256.1

168.6-42.6

-168

.341

.7

107.

835

.6

-107.8-35.9

208.

845

.0-2

05.3

-48.

0

162.

260

.9

-159

.8-7

0.0

-302

.1-2

5.0

304.

135

.0

421

KEEP

HIL5

256.

5-1

1.1

155

BENA

LTO

4

254.

4-1

0.5

216.

3-2

2.3

1

1

-216

.129

.8

-27.

9-2

1.0

28.0

-18.

5

-28.

0-2

1.0

28.1

-18.

6

-99.

228

.9

101.

1-6

1.3

-99.

229

.2

101.

1-6

1.7

SW -0.0

313

JOSE

PH1

248.

6-2

1.3

443

BANN

_240

249.

0-2

0.9

3.2

15.7

-3.2

-17.

7

-57.

157

.1-5

.0

17.3

-14.

9

-17.39.3

-3.6

341

HEAR

TLAN

251.

8-1

9.2

149.

340

.9-1

49.0

-44.

41.

6

979

RIVE

RVIE

W1

249.

5-2

0.2

24.1

11.5

-24.

1-1

3.2

SW -115

.3

258

ELLE

RSLI

537.

1-1

5.7

2979

RIVE

RVIE

WS2

25.0

-22.

339

79RI

VERV

IEW

S3

26.0

-22.

3

12.0 6.6

1

0.9816

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 49: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

POST

PRO

JEC

T10

44L

(JAS

PER

TO

PET

RO

LIA)

FIG

B-5

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

9.7

-18.

451

8AR

GY

LL E

-122.1-8.0

-151.011.2

151.0

249.

7-1

8.5

128

ELL

ER

SLI

249.

5-1

8.2

512

DO

ME

4

249.

9-1

8.1

135

SU

ND

ANC

4

260.

4-1

5.6

-47.2

122.2

249.

7-1

8.4

513

LAM

BTO

N4

248.

3-1

9.1

764

1058

JOIN

248.

5-1

9.0

891

904A

L TP

248.

4-1

9.2

249.

5-1

8.2

136

E E

DM

ON

424

8.5

-19.

3

192.8-192.1-7.2

514

CLO

VER

B4

248.

6-1

9.6

785

1059

A_TP

893

908

TP24

8.6

-19.

1

105.4-25.925.2

-54.732.0

54.7-32.8

-164.81.4

164.9-1.8

165.4-164.7

-85.221.4

9.0-195.3

-9.6

-105.3

248.

4-1

9.2

-3.4

519

CAS

TLE

DN

250.

7-2

1.3

520

VIC

TOR

IA25

0.4

-21.

4

57LA

MO

UR

E4

137

N C

ALD

E4

251.

7-2

1.0

57.32.8

-57.3-50.9

78.251.2

-78.1-52.3

-90.

122

.8

90.3-26.4

249.

4-2

0.5

521

PE

TRO

LIA

249.

6-1

8.1

92H

S_2

40

250.

3-1

6.4

505

JAS

PE

R 4

253.

5-2

1.0

420

KE

EP

HIL

4

255.

6-1

0.3

955

PD

MAK

ER

125

3.1

-21.

0

-9.6-75.1 73.3

9.6

133

WAB

AMU

N4

258.

2-1

7.0

152.430.2

-150.8-32.5

85.2-21.9

511

SU

MM

ER

S1

6.1

-27.6

189.719.6

-189.2-20.3

-189.1-20.5 20.3

85.2-22.4

-85.221.9

189.2 266.829.9

-266.8-29.9

-122.227.6

122.

3-2

8.1

-32.1-52.5

32.1

51.3

-47.7-151.0

47.2

-365.7-37.9 1 1.

025

366.160.4

-365.7-37.9 1 1.

025

366.160.4

195.9

151.1

-15.2-3.0

15.2

0.4

48.5

80.3

-48.5-80.6

226.

621

.5-2

22.6

-22.

4

117.

166

.6

-115

.5-8

0.4

-443

.6-2

7.6

448.

064

.2

421

KEEP

HIL5

256.

6-1

1.3

155

BENA

LTO

4

254.

5-1

0.5

120.

8-2

6.9

1

1

-120

.629

.4

-6.1

-24.

56.

1-1

5.7

-6.1

-24.

56.

1-1

5.7

-96.

327

.8

98.0

-60.

8

-96.

228

.1

98.0

-61.

2

SW -0.0

313

JOSE

PH1

249.

0-2

0.5

443

BANN

_240

249.

4-2

0.1

3.7

19.1

-3.7

-21.

1

-59.

359

.4-7

.3

58.5

-34.

7

-58.529.9

1.3

341

HEAR

TLAN

252.

0-1

8.4

151.

638

.7-1

51.2

-42.

23.

9

979

RIVE

RVIE

W1

249.

7-1

7.7

-214

.3 7.0

214.

4-7

.023

8.9

7.0

-238

.5-6

.2

SW -117

.5

258

ELLE

RSLI

537.

4-1

4.7

2979

RIVE

RVIE

WS2

25.0

-19.

839

79RI

VERV

IEW

S3

26.0

-19.

8

12.0 6.6

1

0.9816

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 50: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

POST

PRO

JEC

T10

43L

(HAR

RY

SMIT

H K

EEPH

ILLS

)FI

G B

-6TU

E, O

CT

31 2

017

10:

31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

8.5

-21.

851

8AR

GY

LL E

48.9-27.5

-298.425.6

298.5

248.

5-2

1.7

128

ELL

ER

SLI

248.

5-2

1.1

512

DO

ME

4

248.

9-2

1.0

135

SU

ND

ANC

4

260.

4-1

7.4

-60.7

-48.9

248.

5-2

1.6

513

LAM

BTO

N4

247.

3-2

2.0

764

1058

JOIN

247.

5-2

1.9

891

904A

L TP

247.

3-2

2.1

248.

5-2

1.1

136

E E

DM

ON

424

7.5

-22.

2

180.3-179.7-9.4

514

CLO

VER

B4

247.

6-2

2.4

785

1059

A_TP

893

908

TP24

7.6

-22.

0

82.6-21.720.8

-45.031.0

45.0-31.8

-152.5-0.6

152.60.2

149.8-149.2

-75.520.4

10.6-183.1-11.6

-82.6

247.

3-2

2.1

-0.9

519

CAS

TLE

DN

248.

5-2

3.4

520

VIC

TOR

IA24

8.2

-23.

5

57LA

MO

UR

E4

137

N C

ALD

E4

249.

1-2

3.0

81.0-1.8

-81.0-45.3

124.724.2

-124.6-24.8

-52.

015

.0

52.0-19.7

248.

2-2

2.9

521

PE

TRO

LIA

248.

3-2

1.9

92H

S_2

40

247.

1-2

2.6

505

JAS

PE

R 4

250.

0-2

2.5

420

KE

EP

HIL

4

255.

6-6

.7

955

PD

MAK

ER

124

9.8

-22.

6

-86.6-25.4 24.0

86.7

133

WAB

AMU

N4

257.

5-1

8.9

155.145.7

-153.3-46.6

75.5-20.9

511

SU

MM

ER

S1

7.9

-7.8

179.921.4

-179.4-22.3

-179.3-22.4 22.3

75.5-21.4

-75.520.9

179.4 257.031.7

-257.0-31.7

-84.

377

.3

84.5

-80.

8

48.97.8

-48.

9-8

.9

-76.3-49.9

76.3

48.9

-59.3-298.5

60.7

-484.0-36.5 1 1.

025

484.575.9

-484.0-36.5 1 1.

025

484.575.9

183.6

299.0

231.3-31.8

-230

.732

.4

125.

631

.1

-125.6-31.3

219.

454

.1-2

15.4

-54.

7

162.

369

.7

-159

.8-7

8.1

421

KEEP

HIL5

256.

1-1

0.1

155

BENA

LTO

4

254.

0-1

0.7

385.

1-6

.3

1

1

-384

.729

.1

-84.

4-1

1.1

85.3

-23.

2

-84.

7-1

1.0

85.6

-23.

2

-126

.038

.5

128.

9-6

5.0

-126

.039

.0

129.

0-6

5.5

SW -0.0

313

JOSE

PH1

248.

0-2

2.9

443

BANN

_240

248.

2-2

2.4

-4.7

11.2

4.7

-13.

2

-73.

773

.7-5

.4

35.7

-12.

3

-35.76.9

-1.8

341

HEAR

TLAN

251.

1-2

0.5

166.

041

.7-1

65.6

-44.

12.

2

979

RIVE

RVIE

W1

247.

9-2

2.1

118.

236

.5-1

18.2

-37.

6-9

4.0

-28.

094

.124

.5

SW -114

.3

258

ELLE

RSLI

535.

9-1

6.5

2979

RIVE

RVIE

WS2

24.8

-24.

339

79RI

VERV

IEW

S3

25.8

-24.

2

12.0 6.6

1

0.9816

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 51: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2018

WP-

POST

PRO

JEC

T11

64L

(PET

RO

LIA

TO R

IVER

VIE

W)

FIG

B-7

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e B

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W25

0.0

-20.

051

8AR

GY

LL E

2.0-38.0

-248.936.8

249.0

249.

9-2

0.0

128

ELL

ER

SLI

249.

7-1

9.4

512

DO

ME

4

250.

1-1

9.3

135

SU

ND

ANC

4

260.

4-1

5.7

-72.6

-2.0

249.

9-1

9.8

513

LAM

BTO

N4

248.

5-2

0.3

764

1058

JOIN

248.

7-2

0.2

891

904A

L TP

248.

5-2

0.4

249.

7-1

9.4

136

E E

DM

ON

424

8.6

-20.

5

178.6-178.0-11.3

514

CLO

VER

B4

248.

7-2

0.7

785

1059

A_TP

893

908

TP24

8.8

-20.

3

81.4-19.018.1

-44.429.2

44.4-30.0

-150.8-2.6

150.92.1

148.2-147.7

-74.918.7

12.4-181.4-13.4

-81.4

248.

5-2

0.4

1.1

519

CAS

TLE

DN

249.

6-2

1.4

520

VIC

TOR

IA24

9.4

-21.

6

57LA

MO

UR

E4

137

N C

ALD

E4

250.

3-2

0.9

84.7-3.9

-84.7-43.6

147.125.4

-146.9-25.6

-49.

39.

1

49.3-13.9

249.

1-2

1.2

521

PE

TRO

LIA

250.

0-2

0.0

92H

S_2

40

251.

6-1

3.7

505

JAS

PE

R 4

251.

3-2

0.5

420

KE

EP

HIL

4

255.

6-9

.3

955

PD

MAK

ER

125

1.1

-20.

6

-72.6-31.9 30.2

72.6

133

WAB

AMU

N4

258.

0-1

7.0

151.239.7

-149.5-41.6

74.9-19.1

511

SU

MM

ER

S1

9.6

2.2

178.222.6

-177.7-23.7

-177.7-23.8 23.7

74.9-19.7

-74.919.1

177.7 255.332.9

-255.3-32.9

-82.

464

.7

82.6

-68.

5

2.0-2.2

-2.0 1.0

-74.6-40.6

74.6

39.6

-71.9-249.0

72.6

-413.2-28.8 1 1.

025

413.657.2

-413.2-28.8 1 1.

025

413.657.2

181.9

249.3

157.7-47.9

-157

.446

.8

111.

637

.3

-111.5-37.6

206.

743

.2-2

03.3

-46.

7

160.

559

.3

-158

.1-6

8.7

-315

.3-3

0.5

317.

542

.7

421

KEEP

HIL5

256.

5-1

1.1

155

BENA

LTO

4

254.

4-1

0.5

208.

1-2

3.0

1

1

-207

.929

.9

-25.

6-2

1.3

25.7

-18.

4

-25.

7-2

1.3

25.8

-18.

4

-98.

228

.5

100.

0-6

1.1

-98.

128

.8

100.

0-6

1.5

SW -0.0

313

JOSE

PH1

248.

8-2

1.2

443

BANN

_240

249.

1-2

0.8

3.8

16.5

-3.7

-18.

5

-56.

556

.6-5

.3

17.1

-15.

5

-17.19.9

-4.0

341

HEAR

TLAN

251.

9-1

9.1

148.

840

.5-1

48.4

-44.

11.

9

979

RIVE

RVIE

W1

251.

3-1

3.8

24.1

8.6

-24.

1-1

3.2

SW -115

.5

258

ELLE

RSLI

537.

3-1

5.6

2979

RIVE

RVIE

WS2

25.2

-15.

939

79RI

VERV

IEW

S3

26.2

-15.

8

12.0 6.6

1

0.9816

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 52: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

OST

PRO

JEC

TBA

SE C

ASE

FIG

B-8

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

7.8

-19.

251

8AR

GY

LL E

-92.7-54.8

-204.9-55.6

205.0

247.

6-1

9.3

128

ELL

ER

SLI

248.

2-1

8.8

512

DO

ME

4

248.

5-1

8.7

135

SU

ND

ANC

4

260.

4-1

4.3

20.2

92.7

247.

8-1

9.1

513

LAM

BTO

N4

246.

6-1

9.8

764

1058

JOIN

246.

8-1

9.7

891

904A

L TP

246.

5-1

9.9

248.

2-1

8.9

136

E E

DM

ON

424

6.5

-20.

0

197.6-196.9-32.5

514

CLO

VER

B4

246.

8-2

0.2

785

1059

A_TP

893

908

TP24

6.7

-19.

8

83.3-34.733.9

-55.714.2

55.7-15.0

-168.0-20.3

168.120.0

161.7-161.0

-87.9-0.3

35.1-200.3-35.3

-83.3

246.

5-1

9.9

11.8

519

CAS

TLE

DN

248.

1-2

1.0

520

VIC

TOR

IA24

8.1

-21.

2

57LA

MO

UR

E4

137

N C

ALD

E4

248.

5-2

0.4

95.0-28.7

-95.0-18.3

168.80.9

-168.5-0.7

-67.

129

.2

67.2-33.3

247.

9-2

1.0

521

PE

TRO

LIA

248.

1-1

9.0

92H

S_2

40

248.

9-1

7.0

505

JAS

PE

R 4

249.

1-1

9.8

420

KE

EP

HIL

4

255.

6-1

0.8

955

PD

MAK

ER

124

8.9

-19.

9

-109.1-10.1 9.0

109.2

133

WAB

AMU

N4

257.

5-1

5.9

170.649.7

-168.4-48.1

87.9-0.1

511

SU

MM

ER

S1

31.8

19.8

194.739.6

-194.2-40.0

-194.1-40.1 40.0

87.9-0.6

-87.90.1

194.2 266.955.9

-266.9-55.9

-118

.556

.0

118.

8-5

9.1

-92.7-19.8

92.7

19.0

-96.5-29.5

96.5

28.6

20.3-205.0-20.2

-368.4-117.5 1 1.

01

368.8142.6

-368.4-117.5 1 1.

01

368.8142.6

200.9

205.2

44.3-4.2

-44.

31.

7

153.

622

.1

-153.6-22.1

232.

861

.2-2

28.3

-58.

8

192.

070

.0

-188

.6-7

4.0

-452

.1-4

8.1

456.

887

.6

421

KEEP

HIL5

256.

5-1

1.9

155

BENA

LTO

4

254.

0-1

0.0

129.

1-2

2.1

1

1

-129

.024

.9

15.4

-29.

9-1

5.4

-10.

0

15.5

-29.

9-1

5.4

-9.9

-80.

625

.7

81.9

-61.

0

-80.

525

.9

81.8

-61.

4

SW -0.0

313

JOSE

PH1

248.

2-2

0.9

443

BANN

_240

247.

9-2

0.6

-6.1

-17.

26.

115

.2

-47.

647

.7-4

.7

1.2

-6.5

-1.20.8

-14.0

341

HEAR

TLAN

250.

7-1

9.0

138.

239

.8-1

37.9

-43.

91.

2

979

RIVE

RVIE

W1

248.

2-1

8.5

-241

.8 9.3

242.

0-8

.926

6.6

6.6

-266

.0-4

.3

SW -113

.4

258

ELLE

RSLI

533.

7-1

5.4

2979

RIVE

RVIE

WS2

25.1

-20.

739

79RI

VERV

IEW

S3

25.8

-20.

6

12.0 6.6

1

0.98927

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 53: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

OST

PRO

JEC

TEL

LER

SLIE

T1

FIG

B-9

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

5.8

-19.

751

8AR

GY

LL E

-111.7-64.4

-180.4-44.3

180.5

245.

6-1

9.8

128

ELL

ER

SLI

246.

0-1

9.4

512

DO

ME

4

246.

5-1

9.3

135

SU

ND

ANC

4

260.

4-1

4.7

9.5

111.7

245.

8-1

9.7

513

LAM

BTO

N4

244.

5-2

0.3

764

1058

JOIN

244.

7-2

0.2

891

904A

L TP

244.

5-2

0.4

246.

0-1

9.4

136

E E

DM

ON

424

4.5

-20.

5

184.4-183.8-27.6

514

CLO

VER

B4

244.

9-2

0.7

785

1059

A_TP

893

908

TP24

4.7

-20.

3

61.0-42.241.2

-45.918.1

45.9-18.9

-155.1-15.4

155.215.0

145.7-145.2

-78.13.5

29.8-187.4-30.4

-61.0

244.

4-2

0.5

5.9

519

CAS

TLE

DN

246.

8-2

1.3

520

VIC

TOR

IA24

6.7

-21.

5

57LA

MO

UR

E4

137

N C

ALD

E4

247.

2-2

0.7

101.3-22.5

-101.2-23.8

157.74.7

-157.4-4.7

-29.

043

.0

29.0-47.5

246.

8-2

1.0

521

PE

TRO

LIA

246.

3-1

9.5

92H

S_2

40

247.

5-1

7.2

505

JAS

PE

R 4

247.

7-2

0.2

420

KE

EP

HIL

4

255.

6-1

0.4

955

PD

MAK

ER

124

7.5

-20.

3

-94.6-5.5 4.2

94.7

133

WAB

AMU

N4

257.

2-1

6.2

170.757.7

-168.4-55.5

78.1-3.9

511

SU

MM

ER

S1

26.5

29.9

184.135.5

-183.6-36.2

-183.5-36.3 36.2

78.1-4.4

-78.13.9

183.6 256.352.0

-256.3-52.0

-101

.070

.2

101.

3-7

3.4

-111.7-29.9

111.

829

.4

-106.4-44.0

106.

543

.2

9.3-180.5

-9.5

1 1.01

-596.6-160.2 1 1.

01

597.4225.1

187.9

180.6

11.5-19.7

-11.

517

.1

139.

017

.2

-139.0-17.4

236.

073

.9-2

31.2

-70.

0

202.

687

.9

-198

.6-8

8.7

-489

.9-6

1.3

495.

411

0.7

421

KEEP

HIL5

256.

5-1

1.0

155

BENA

LTO

4

253.

8-1

0.1

67.3

-24.

6

1

1

-67.

125

.6

5.3

-29.

4-5

.3-1

0.6

5.3

-29.

4-5

.3-1

0.6

-84.

827

.8

86.2

-62.

4

-84.

728

.1

86.2

-62.

8

SW -0.0

313

JOSE

PH1

247.

3-2

0.9

443

BANN

_240

247.

0-2

0.4

-28.

1-2

6.8

28.1

24.9

-86.

686

.6-0

.2

18.6

-4.2

-18.6-1.4

-8.7

341

HEAR

TLAN

250.

2-1

8.4

177.

447

.0-1

76.8

-48.

4-2

.6

979

RIVE

RVIE

W1

246.

5-1

8.9

-276

.1-2

.327

6.3

3.4

301.

121

.0-3

00.4

-16.

6

SW -112

.2

258

ELLE

RSLI

534.

8-1

3.8

2979

RIVE

RVIE

WS2

24.9

-21.

139

79RI

VERV

IEW

S3

25.6

-21.

0

12.0 6.6

1

0.98927

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 54: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

OST

PRO

JEC

T90

8L (E

LLER

SLIE

TO

PET

RO

LIA)

FIG

B-1

0TU

E, O

CT

31 2

017

10:

31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

7.7

-19.

351

8AR

GY

LL E

-61.3-56.9

-236.2-53.5

236.3

247.

6-1

9.3

128

ELL

ER

SLI

248.

2-1

8.8

512

DO

ME

4

248.

5-1

8.7

135

SU

ND

ANC

4

260.

4-1

4.3

18.3

61.3

247.

8-1

9.2

513

LAM

BTO

N4

246.

5-1

9.8

764

1058

JOIN

246.

8-1

9.6

891

904A

L TP

246.

5-1

9.8

248.

2-1

8.8

136

E E

DM

ON

424

6.5

-20.

0

198.6-197.8-32.4

514

CLO

VER

B4

246.

7-2

0.2

785

1059

A_TP

893

908

TP24

6.7

-19.

8

84.8-34.834.0

-56.214.2

56.2-15.1

-169.0-20.3

169.120.0

162.8-162.2

-88.3-0.2

35.1-201.2-35.3

-84.7

246.

4-1

9.9

11.8

519

CAS

TLE

DN

248.

1-2

1.0

520

VIC

TOR

IA24

8.0

-21.

2

57LA

MO

UR

E4

137

N C

ALD

E4

248.

4-2

0.4

94.6-28.5

-94.6-18.4

165.01.0

-164.7-0.9

-69.

729

.5

69.8-33.6

247.

9-2

0.9

521

PE

TRO

LIA

248.

0-1

9.1

92H

S_2

40

248.

8-1

7.1

505

JAS

PE

R 4

249.

0-1

9.8

420

KE

EP

HIL

4

255.

6-1

0.8

955

PD

MAK

ER

124

8.9

-20.

0

-103.9-10.2 8.9

104.0

133

WAB

AMU

N4

257.

5-1

5.9

171.349.9

-169.0-48.2

88.3-0.2

511

SU

MM

ER

S1

31.8

21.8

195.639.6

-195.1-40.0

-195.0-40.0 40.0

88.4-0.7

-88.30.2

195.1 267.955.9

-267.9-55.9

-111

.255

.9

111.

4-5

9.2

-61.3-21.8

61.3

20.8

-94.1-30.3

94.2

29.4

18.7-236.3-18.3

-366.6-117.9 1 1.

01

367.0142.8

-366.6-117.9 1 1.

01

367.0142.8

201.9

236.6

148.

422

.0

-148.3-22.1

235.

061

.6-2

30.4

-58.

7

189.

670

.4

-186

.3-7

4.8

-455

.6-4

8.5

460.

488

.8

421

KEEP

HIL5

256.

5-1

1.9

155

BENA

LTO

4

254.

0-1

0.0

126.

4-2

2.2

1

1

-126

.324

.9

15.9

-29.

9-1

5.8

-9.9

15.9

-30.

0-1

5.9

-9.8

-80.

925

.7

82.2

-61.

1

-80.

826

.0

82.2

-61.

4

SW -0.0

313

JOSE

PH1

248.

2-2

0.9

443

BANN

_240

247.

9-2

0.6

-6.4

-17.

36.

415

.4

-48.

148

.1-4

.7

4.6

-6.5

-4.60.8

-13.9

341

HEAR

TLAN

250.

6-1

9.0

138.

739

.8-1

38.3

-43.

91.

2

979

RIVE

RVIE

W1

248.

2-1

8.6

-247

.2 9.3

247.

4-8

.827

2.1

7.0

-271

.5-4

.4

SW -113

.4

258

ELLE

RSLI

533.

7-1

5.4

2979

RIVE

RVIE

WS2

25.0

-20.

839

79RI

VERV

IEW

S3

25.8

-20.

7

12.0 6.6

1

0.98927

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 55: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

OST

PRO

JEC

T11

39L

(HAR

RY

SMIT

H T

O R

IVER

VIEW

)FI

G B

-11

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

6.9

-20.

751

8AR

GY

LL E

-10.3-53.5

-280.0-55.9

280.1

246.

8-2

0.7

128

ELL

ER

SLI

247.

5-2

0.1

512

DO

ME

4

247.

8-1

9.9

135

SU

ND

ANC

4

260.

4-1

5.1

21.2

10.3

247.

0-2

0.5

513

LAM

BTO

N4

245.

9-2

1.0

764

1058

JOIN

246.

1-2

0.9

891

904A

L TP

245.

8-2

1.1

247.

5-2

0.1

136

E E

DM

ON

424

5.8

-21.

2

192.6-191.9-31.7

514

CLO

VER

B4

246.

1-2

1.4

785

1059

A_TP

893

908

TP24

6.0

-21.

0

75.5-35.935.0

-51.515.0

51.5-15.8

-163.1-19.5

163.219.2

155.8-155.2

-83.60.5

34.2-195.4-34.5

-75.4

245.

8-2

1.2

10.8

519

CAS

TLE

DN

247.

5-2

2.1

520

VIC

TOR

IA24

7.4

-22.

3

57LA

MO

UR

E4

137

N C

ALD

E4

247.

9-2

1.5

101.8-26.4

-101.8-20.3

173.01.5

-172.7-1.2

-53.

531

.4

53.5-35.8

247.

4-2

2.0

521

PE

TRO

LIA

247.

1-2

0.7

92H

S_2

40

250.

8-1

3.8

505

JAS

PE

R 4

248.

4-2

1.1

420

KE

EP

HIL

4

255.

6-9

.7

955

PD

MAK

ER

124

8.2

-21.

2

-68.8-9.1 7.4

68.8

133

WAB

AMU

N4

257.

4-1

6.6

185.353.0

-182.7-48.7

83.6-0.9

511

SU

MM

ER

S1

30.9

18.6

191.039.0

-190.5-39.5

-190.4-39.6 39.5

83.7-1.4

-83.60.9

190.5 263.255.4

-263.2-55.3

-56.

756

.8

56.8

-61.

0

-10.3-18.6

10.3

17.5

-115.0-30.2

115.

129

.4

22.3-280.1-21.2

-411.2-122.7 1 1.

01

411.6153.8

-411.2-122.7 1 1.

01

411.6153.8

196.0

280.5

166.0-3.8

-165

.72.

8

113.

220

.3

-113.2-20.6

255.

166

.1-2

49.7

-58.

8

211.

274

.4

-207

.2-7

4.8

-301

.0-4

5.2

303.

155

.7

421

KEEP

HIL5

256.

3-1

1.7

155

BENA

LTO

4

253.

9-1

0.1

224.

2-1

6.8

1

1

-224

.024

.7

-10.

6-2

6.4

10.7

-13.

6

-10.

7-2

6.4

10.7

-13.

5

-92.

129

.4

93.8

-62.

8

-92.

129

.7

93.8

-63.

2

SW -0.0

313

JOSE

PH1

247.

8-2

2.0

443

BANN

_240

247.

5-2

1.7

-12.

3-1

9.9

12.3

18.0

-53.

553

.5-4

.3

3.8

-4.6

-3.8-1.1

-13.2

341

HEAR

TLAN

250.

2-2

0.0

144.

140

.6-1

43.7

-44.

30.

9

979

RIVE

RVIE

W1

247.

0-2

0.7

24.1

11.6

-24.

1-1

3.2

SW -112

.8

258

ELLE

RSLI

533.

0-1

6.3

2979

RIVE

RVIE

WS2

24.9

-22.

939

79RI

VERV

IEW

S3

25.7

-22.

8

12.0 6.6

1

0.98927

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 56: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

OST

PRO

JEC

T10

44L

(JAS

PER

TO

PET

RO

LIA)

FIG

B-1

2TU

E, O

CT

31 2

017

10:

31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

7.2

-19.

051

8AR

GY

LL E

-135.5-35.5

-179.4-70.9

179.4

247.

1-1

9.0

128

ELL

ER

SLI

247.

8-1

8.7

512

DO

ME

4

248.

2-1

8.6

135

SU

ND

ANC

4

260.

4-1

4.8

35.7

135.6

247.

3-1

8.9

513

LAM

BTO

N4

246.

2-1

9.7

764

1058

JOIN

246.

4-1

9.5

891

904A

L TP

246.

1-1

9.7

247.

8-1

8.7

136

E E

DM

ON

424

6.1

-19.

9

206.0-205.2-29.2

514

CLO

VER

B4

246.

4-2

0.2

785

1059

A_TP

893

908

TP24

6.3

-19.

7

97.5-40.239.5

-61.316.5

61.3-17.3

-176.2-17.1

176.316.9

171.8-171.1

-93.52.0

32.3-208.5-32.2

-97.4

246.

1-1

9.8

8.2

519

CAS

TLE

DN

248.

7-2

1.6

520

VIC

TOR

IA24

8.7

-21.

8

57LA

MO

UR

E4

137

N C

ALD

E4

249.

3-2

1.2

76.4-22.8

-76.4-24.5

112.921.4

-112.8-22.2

-91.

340

.2

91.5-43.5

248.

0-2

1.1

521

PE

TRO

LIA

247.

5-1

8.6

92H

S_2

40

248.

5-1

6.8

505

JAS

PE

R 4

250.

5-2

1.1

420

KE

EP

HIL

4

255.

6-1

0.7

955

PD

MAK

ER

125

0.3

-21.

2

-24.0-46.9 45.0

24.1

133

WAB

AMU

N4

257.

6-1

6.4

183.043.0

-180.5-39.7

93.5-2.3

511

SU

MM

ER

S1

28.9

0.6

201.737.2

-201.1-37.4

-201.0-37.4 37.4

93.5-2.8

-93.52.3

201.1 273.953.5

-273.9-53.5

-135.6-0.6

135.

70.

3

-74.4-38.6

74.4

37.6

35.5-179.4-35.7

-361.1-124.7 1 1.

01

361.5149.3

-361.1-124.7 1 1.

01

361.5149.3

209.2

179.6

-10.223.7

10.2

-26.

2

68.4

57.7

-68.4-58.1

267.

345

.1-2

61.6

-36.

6

169.

376

.1

-166

.5-8

3.1

-443

.9-5

5.3

448.

493

.3

421

KEEP

HIL5

256.

4-1

1.8

155

BENA

LTO

4

254.

0-1

0.1

128.

3-2

1.8

1

1

-128

.224

.6

11.8

-29.

5-1

1.8

-10.

4

11.8

-29.

6-1

1.8

-10.

3

-87.

927

.8

89.4

-62.

0

-87.

828

.1

89.4

-62.

4

SW -0.0

313

JOSE

PH1

248.

2-2

1.1

443

BANN

_240

247.

9-2

0.8

-10.

9-1

5.5

10.9

13.6

-54.

554

.5-6

.5

38.3

-21.

8

-38.316.5

-9.8

341

HEAR

TLAN

250.

6-1

9.1

145.

138

.4-1

44.7

-42.

13.

1

979

RIVE

RVIE

W1

247.

6-1

8.2

-220

.4-3

.222

0.5

3.3

245.

117

.8-2

44.6

-16.

5

SW -114

.8

258

ELLE

RSLI

533.

5-1

5.3

2979

RIVE

RVIE

WS2

25.0

-20.

439

79RI

VERV

IEW

S3

25.8

-20.

3

12.0 6.6

1

0.98927

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 57: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

OST

PRO

JEC

T10

43L

(HAR

RY

SMIT

H K

EEPH

ILLS

)FI

G B

-13

TUE,

OC

T 31

201

7 1

0:31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

5.4

-22.

451

8AR

GY

LL E

27.3-43.3

-321.0-67.0

321.2

245.

3-2

2.4

128

ELL

ER

SLI

246.

2-2

1.7

512

DO

ME

4

246.

6-2

1.6

135

SU

ND

ANC

4

260.

4-1

6.8

33.0

-27.2

245.

6-2

2.2

513

LAM

BTO

N4

244.

6-2

2.7

764

1058

JOIN

244.

8-2

2.6

891

904A

L TP

244.

5-2

2.8

246.

2-2

1.8

136

E E

DM

ON

424

4.5

-22.

9

194.9-194.2-29.7

514

CLO

VER

B4

244.

9-2

3.1

785

1059

A_TP

893

908

TP24

4.8

-22.

7

77.6-38.637.7

-52.517.0

52.5-17.8

-165.4-17.5

165.517.2

158.1-157.5

-84.72.4

32.4-197.7-32.6

-77.6

244.

5-2

2.8

8.8

519

CAS

TLE

DN

246.

2-2

4.0

520

VIC

TOR

IA24

6.1

-24.

2

57LA

MO

UR

E4

137

N C

ALD

E4

246.

5-2

3.5

97.3-23.8

-97.3-22.4

150.2-0.7

-150.00.5

-57.

937

.6

57.9-41.8

246.

4-2

3.8

521

PE

TRO

LIA

245.

4-2

2.5

92H

S_2

40

243.

8-2

3.2

505

JAS

PE

R 4

246.

9-2

3.0

420

KE

EP

HIL

4

255.

6-7

.3

955

PD

MAK

ER

124

6.8

-23.

1

-87.4-4.4 3.0

87.4

133

WAB

AMU

N4

256.

8-1

8.5

187.659.3

-184.9-54.1

84.7-2.8

511

SU

MM

ER

S1

29.0

8.8

193.237.8

-192.6-38.2

-192.5-38.2 38.2

84.7-3.3

-84.72.8

192.6 265.454.3

-265.4-54.2

-65.

568

.3

65.7

-72.

2

27.2-8.8

-27.

27.

8

-114.7-40.4

114.

739

.7

34.8-321.2-33.0

-477.9-131.3 1 1.

01

478.5173.1

-477.9-131.3 1 1.

01

478.5173.1

198.3

321.7

226.012.2

-225

.4-1

1.7

131.

816

.0

-131.8-16.2

265.

578

.4-2

59.5

-67.

9

211.

085

.6

-206

.9-8

5.2

421

KEEP

HIL5

255.

9-1

0.7

155

BENA

LTO

4

253.

5-1

0.4

392.

3-0

.2

1

1

-392

.023

.8

-67.

1-1

7.4

67.7

-19.

0

-67.

4-1

7.3

68.0

-19.

0

-119

.238

.9

121.

9-6

6.7

-119

.239

.3

121.

9-6

7.1

SW -0.0

313

JOSE

PH1

246.

9-2

3.7

443

BANN

_240

246.

5-2

3.3

-19.

9-2

6.7

19.9

24.8

-70.

170

.1-4

.0

22.1

-0.1

-22.1-5.4

-11.0

341

HEAR

TLAN

249.

4-2

1.4

160.

842

.1-1

60.3

-44.

60.

8

979

RIVE

RVIE

W1

244.

9-2

2.7

112.

546

.9-1

12.4

-48.

0-8

8.3

-38.

288

.434

.8

SW -111

.5

258

ELLE

RSLI

531.

6-1

7.2

2979

RIVE

RVIE

WS2

24.7

-25.

039

79RI

VERV

IEW

S3

25.5

-24.

9

12.0 6.6

1

0.98927

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 58: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

2019

SP-P

OST

PRO

JEC

T11

64L

(PET

RO

LIA

TO R

IVER

VIE

W)

FIG

B-1

4TU

E, O

CT

31 2

017

10:

31

Bus

- Bas

e vo

ltage

(kV)

Bran

ch -

MW

/Mva

rEq

uipm

ent -

MW

/Mva

r10

0.0%

Rat

e A

kV: <

=25.

000

<=69

.000

<=13

8.00

0<=

240.

000

<=50

0.00

0>5

00.0

00

506

BE

LLAM

Y4

509

ARG

YLL

W24

7.2

-20.

551

8AR

GY

LL E

-17.7-57.2

-273.2-52.5

273.4

247.

0-2

0.5

128

ELL

ER

SLI

247.

7-2

0.0

512

DO

ME

4

248.

1-1

9.8

135

SU

ND

ANC

4

260.

4-1

5.0

17.7

17.7

247.

3-2

0.4

513

LAM

BTO

N4

246.

1-2

0.9

764

1058

JOIN

246.

3-2

0.8

891

904A

L TP

246.

0-2

1.0

247.

7-2

0.0

136

E E

DM

ON

424

6.0

-21.

1

193.1-192.4-32.1

514

CLO

VER

B4

246.

3-2

1.3

785

1059

A_TP

893

908

TP24

6.2

-20.

9

76.2-35.334.4

-51.914.6

51.9-15.4

-163.6-19.9

163.719.6

156.4-155.8

-84.00.1

34.5-195.9-34.9

-76.1

246.

0-2

1.0

11.3

519

CAS

TLE

DN

247.

7-2

2.0

520

VIC

TOR

IA24

7.6

-22.

2

57LA

MO

UR

E4

137

N C

ALD

E4

248.

1-2

1.4

101.2-27.1

-101.1-19.6

172.61.4

-172.3-1.2

-54.

830

.2

54.8-34.6

247.

6-2

1.9

521

PE

TRO

LIA

247.

4-2

0.5

92H

S_2

40

250.

4-1

4.1

505

JAS

PE

R 4

248.

6-2

0.9

420

KE

EP

HIL

4

255.

6-9

.8

955

PD

MAK

ER

124

8.4

-21.

0

-72.5-10.8 9.2

72.6

133

WAB

AMU

N4

257.

4-1

6.5

184.051.8

-181.4-47.9

84.1-0.5

511

SU

MM

ER

S1

31.3

22.2

191.439.3

-190.8-39.8

-190.7-39.8 39.8

84.1-1.0

-84.10.5

190.8 263.655.6

-263.6-55.6

-62.

454

.0

62.5

-58.

2

-17.7-22.2

17.7

21.1

-113.3-28.9

113.

428

.1

18.6-273.4-17.7

-407.5-120.0 1 1.

01

407.9150.4

-407.5-120.0 1 1.

01

407.9150.4

196.5

273.7

154.9-9.2

-154

.78.

0

116.

922

.1

-116.9-22.3

253.

164

.2-2

47.8

-57.

5

209.

472

.6

-205

.5-7

3.6

-314

.1-5

0.7

316.

463

.4

421

KEEP

HIL5

256.

3-1

1.7

155

BENA

LTO

4

253.

9-1

0.1

215.

9-1

7.5

1

1

-215

.724

.9

-8.4

-26.

78.

4-1

3.3

-8.4

-26.

78.

4-1

3.3

-91.

129

.0

92.7

-62.

6

-91.

029

.2

92.7

-63.

0

SW -0.0

313

JOSE

PH1

247.

9-2

1.9

443

BANN

_240

247.

6-2

1.5

-11.

7-1

8.9

11.7

17.0

-52.

953

.0-4

.6

3.6

-5.3

-3.6-0.4

-13.6

341

HEAR

TLAN

250.

4-1

9.9

143.

540

.2-1

43.2

-43.

91.

2

979

RIVE

RVIE

W1

250.

0-1

4.2

24.1

8.7

-24.

1-1

3.2

SW -113

.0

258

ELLE

RSLI

533.

2-1

6.2

2979

RIVE

RVIE

WS2

25.2

-16.

439

79RI

VERV

IEW

S3

26.0

-16.

3

12.0 6.6

1

0.98927

-12.

0-6

.012

.06.

6

0.9816

1-12

.0-6

.099

12.0 6.0

9912

.06.

0

Page 59: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

Attachment C

Voltage Stability Diagrams 2018 WP Post-Project

Page 60: APPENDIX A CONNECTION ASSESSMENT - Alberta Electric System

0 200 400 600 800 1000 12000.92

0.94

0.96

0.98

1

1.02

1.04

1.06

1.08

1.1

Pincremental (MW)

Vol

tage

(p.u

.)

Voltage at Bus # 979

N−0: Base CaseN−1: 908LN−1: 1164LN−1: 1139LN−1: 1044LN−1: 1098L