7/30/2019 api510-closedbook http://slidepdf.com/reader/full/api510-closedbook 1/22 FAST TRACK TECHNICAL TRAINING Part 2 Practice Exam A 281-482-2253 Question 36 begins the closed book portion of this exam! It is recommended that you take this portion without referring to the ASME Code or API books on your first attempt, to assess your strengths and concentrate your studies on the most needed subject areas.

api510-closedbook

Embed Size (px)

Citation preview

Page 1: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 1/22

FAST TRACK TECHNICAL TRAINING

Part 2 Practice Exam A

281-482-2253

Question 36 begins the closed book portion of this exam!

It is recommended that you take this portion without referring to the

ASME Code or API books on your first attempt, to assess your

strengths and concentrate your studies on the most needed subjectareas.

Page 2: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 2/22

36. What is the greatest allowed time between the testing of pressure relieving devices per API 510?

1. 5 years.

2. Pressure relief valves shall be tested at intervals that are frequent enough to verify that the valves perform reliably.

3. 10 years.4. Pressure relief devices must be tested at every shutdown.

37. Who is responsible for the rerating calculations of a vessel?

1. The manufacturer or an owner-user engineer (or his designated representative).

2. The chief inspector and the unit engineer.3. The API authorized inspector 

4. A professional engineer only, is allowed to perform these calculations.

38. If the requirements of API 510 are met who determines if a temporary fillet weld patch may be used in

a repair?

1. The API authorized inspector.

2. An engineer competent in pressure vessel design and the API authorizedinspector.

3. A repair concern which holds a valid NBIC R stamp.

4. Any of the above.

39. The maximum carbon content of weldable steel per ASME Code is?

1. .35 %

2. .035 %

3. .0035 %

4. 3.5 %

40. Per API 510 what is the recommended shell temperature during a hydrostatic test of a vessel 1” thick?

1. 30 o F above ambient.2. 65 o F above ambient.

3. 10 o F above MDMT.

4. 30 o F above testing liquids temperature.

41. If you were looking for the last date that a pressure relief valve was set, where should this information

always be?

1. In the product literature from the valve company.

2. The API 510 mandatory computer inspection records.

3. Relief valve’s tag.4. In the records of the repair shop.

Page 3: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 3/22

42. In what two ways may the probable corrosion rate for a new vessel be determined before the first

internal inspection?

1. Corrosion tabs and UT readings.

2. Consult Psychic Hot Line and Mr. Wizard.3. Ask a more experienced inspector or engineer 

4. From data collected on vessels providing the same or similar service or from published data onvessels providing comparable service.

43. A vessel is to undergo a hydrostatic test after an alteration, the test pressure will be 785 psi. Using

standard commercially available gauges what is the minimum and maximum gage pressure range

acceptable for this test?

1. 0-1000 to 0-3000 psi

2. 0-1500 to 0-3000 psi

3. 0-1000 to 0-2500 psi

4. 0-850 to 0-1500 psi

44. Which of the following should a progressive record for a pressure vessel contain?

1.  The exact location on a plot plan. 2. The piping schedule for the vessel.3. A complete weld map from the original construction plans.

4. Construction and design information, operating and inspection history.

45. If performing an external inspection of a vessel what consideration need be given the external

insulation?

1. It shall always be removed to inspect underneath.

2. If insulation is in good condition and the vessel operates within the high and low temperaturesstated in API 510, removal of insulation is not necessary for inspection of the vessel.

3. Select portions must be removed for inspections.

4. You may not use any plug locations used for UT thickness reading to inspect the vessel.

46. What must be considered important in the inspection of a metallic lining?

1. That there are no dissimilar welds.

2. That the linings made of pure alloy only.

3. That vent holes exist in all liners.

4. That there are no holes or cracks present in the lining.

47. What must be done prior to using special inspection procedures after an alteration to a vessel in place

of a hydrostatic test?

1. Check with the NBIC Authorized inspector.

2. Consult with the chief inspector of the jurisdiction.

3. Make certain it is permitted by any jurisdictional rules that may exist and consult with an engineer 

experienced in pressure vessel design and the Authorized Pressure Vessel Inspector.

4. Review all NDE procedures prior to commencement of the NDE used to waive the hydrostatic test

requirement.

Page 4: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 4/22

48. If the corrosion rate of a vessel is determined to be less than a given amount per year, it is possible to

exempt the vessel from internal inspections. What is the value of the corrosion rate that cannot be

exceeded?

1. 0.001”per year 2. 0.001” between inspections not to exceed 5 years between inspections.

3. 0.005” per year.4. 0.005” between inspections not to exceed 3 years between inspections

49. What may happen if vessels are subjected to temperatures above design?

1. The relief device may fail.

2. The rupture disk may implode.3. Phosphoric granulation at the grain boundaries.

4. Creep of the vessel’s material may occur.

50. The definition of pressure vessels is;

1. A vessel for the containment of process fluids with or without internal pressure.

2. A container designed to operate below atmospheric pressure.3. A container no greater than 6” in cross section.

4. A container designed to withstand internal or external pressure.

51. Which is the most severe stress caused by internal pressure in a cylindrical shell?

1. Circumferential stress acting along the longitudinal axis.

2. Longitudinal stress acting along the longitudinal axis.

3. Circumferential stress acting along the circumferential axis.

4. Longitudinal stress acting along the circumferential axis.

52. Of the following heads; which is normally required to be the thickest all things being equal?

1. Hemispherical2. Flanged and dished

3. 2 to 1 elliptical

4. Forged flat heads

53. The maximum interval between external visual inspections for an above the ground vessel is;

1. Three years

2. Ten years

3. Five years

4. There is no maximum interval.

Page 5: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 5/22

54. What is the maximum inspection interval for a vessel with a remaining safe operating life of less than

four years?

1. The full remaining safe operating life up to a maximum of 4 years.

2. The full remaining safe operating life up to a maximum of 2 years.3. The full remaining safe operating life up to a maximum of 1 year.

4. The full remaining life of the vessel.

55. What do construction codes mean, as it regards repairs to a pressure vessel?

1. The current ASME Code edition.

2. The NBIC

3. The Code the vessel was constructed to including non-standard and jurisdictional special vessels.4. The API 510 Code.

56. What Code is used to evaluate a vessel after it has been placed in service?

1. ASME Section VIII

2. ASME Section V

3. API 510

4. RP 572

57. When a vessel is to be entered for inspection which of the following precautions should be observed?

1. The area should be roped off and no one else is to be working in the area.

2. Inspect the vessel for proper electrical grounding if a thunderstorm is in the area.

3. All hot work permits in the immediate area must be revoked until the inspection is complete

4. OSHA rules should be reviewed and followed where applicable.

58. Liquid penetrant inspection can find which type of discontinuity?

1. Internal cracking of welds.

2. Cracks open to the surface.3. Subsurface porosity.

4. Laminations on the surfaces of plate.

59. For proper internal or external visual inspection surfaces must be:

1. Wire brushed.

2. Walnut shell blasted.

3. Hydro blasted.

4. The type of surface preparation depends on individual circumstances and could be any of the

above.

60. Who normally performs welder certification test, that is, which organization is responsible for 

 performance and acceptance?

1. Inspection department2. Company employing the welder 

3. OSHA

4. The company safety department.

Page 6: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 6/22

61. What is the definition of a construction code?

1. Any standard used to repair vessel

2. Any technique of construction.

3. Any standard used to build a vessel.4. The Code or standard to which a vessel was originally built.

62. Of the following tools which should the inspector have on hand for vessel inspections?

1. Pencil and note pad, flash light and scraper.

2. Social security card.

3. Clean fire retardant clothing.

4. Electrical conductivity testing equipment to test liners.

63. The purpose of a Welding Procedure Specification and its Procedure Qualification Record is:

1. To make sure every one involved in the repair process has a listing of nonessential variables

2. Make sure the welder follows the essential variables

3. To prove the weld will provide the required properties

4. Keep testing labs in business

64. Many of the problems that develop in operating vessels may be traced to;

1. Cold winters

2. On-Stream inspections

3. Electrical shorts

4. Faulty materials and workmanship

65. The maximum content of iron in a nonferrous metal is

1. 35%2. 50%

3. 75%

4. 45%

66. Which of the following types of over pressure protection is not found on a pressure vessel?

1. Safety Relief 

2. Pilot Operated3. Rupture Disk 

4. Pressure/Vacuum Vent

67. If steel of a vessel has exceeded its yield point upon the removal of pressure and heat it will;

1. return to its original shape

2. contain a permanent deformation

3. split or rupture4. be oblong

Page 7: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 7/22

68. Of the types of stresses placed on a thin walled cylinder the most severe is;

1. Circumferential

2. Longitudinal

3. Compressive4. Radial

69. The report for qualifying a welder is:

1. WPS

2. PQR  

3. WPQ

4. WQR  

70. Which of the following inspection techniques requires direct visual examination of the test specimen?

1. Radiography testing

2. Ultrasonic testing

3. Magnetic particle

4. Eddy current

71. A welding procedure is a detailed plan developed by whom to ensure sound welds.

1. API-510 Inspector 

2. Welder  

3. Quality Control Manager 

4. Fabricator  

72. The primary cause of deterioration in pressure vessels is:

1. Corrosion

2. Operating conditions

3. Improper installation

4. Water damage

73. High pressure may develop in a vessel as a result of::

1. Rapid venting of a vessel’s pressure source

2. Lowering heat below normal operating conditions

3. Thermal contraction of trapped fluids

4. Blocking off against a pressure source

74. Which of the following techniques is considered the primary means to determine the minimum

thickness of a vessel’s components?

1. A boat sample remove from a thin area

2. Measuring from a corroded area

3. Any suitable destructive method of examination4. Ultrasonic thickness measurements.

Page 8: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 8/22

75. The rules for impact testing of carbon steel in Section VIII vessel materials require what kind(s) of 

impact test.

1. Brinell & Rockwell

2. Izod & Charpy V-notch3. Charpy V-notch only is acceptable.

4. Brinell only is acceptable

76. You have measured undercut on a girth weld during the repair to a vessel, it was found to be 1/32 inch

in depth. The base metal is 2 inches thick, and you should?

1. Reject the weld.

2. Accept the weld.3. Consult the API 510 Code for accept/reject criteria before making a decision.

4. Consult with the Chief Inspector or Engineer.

77. What is the minimum length of weld metal to be radiographed for a Welder’s Performance

Qualification using an NPS 6 inch pipe coupon made of P No 5 materials utilizing the SMAW process?

1. Six inches of weld metal

2. The entire circumference of the pipe coupon3. Stops and starts only

4. None, not allowed by Section IX

78. The API authorized pressure vessel inspector may give prior authorization for repairs that do not

involve;

1. Pressure tests

2. Radiography

3. Pneumatic testing

4. Final visual inspections

79. The two types of impact tests required by Section VIII Div. 1 are;

1. Izod and Drop Weight

2. Brinell and Rockwell

3. Charpy and Drop Weight

4. Weld metal and Base metal

80. In Section VIII Div. 1 acceptance of a radiograph is based on;

1. the speed of the film used.

2. the geometric unsharpness of the image.

3. the absence of backscatter.

4. the ability to see the essential hole or wire, if a wire type IQI is used.

Page 9: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 9/22

81. A spot radiograph of a butt weld in a 1 inch thick shell of a vessel marked RT-3 was found to have a

rounded indication, the dimension of such an indication according to Section VIII Div. 1 is;

1. 1/32 of an inch.

2. 1/3 of an inch.

3. 2/3 of an inch

4. None, rounded indications are not a consideration with spot radiography.

82. Section VIII Div. 1, is very specific about the number of spot radiographs required when applying it

for quality control, the basic premise is to;

1. insure that all welds are made perfectly.

2. make sure someone is held responsible for any poor welding.

3. apply the radiographs immediately after welding in order to take corrective steps if needed.4. fire as many welders as possible.

83. A P No. 1 material that is plate has been rolled into a cylinder and butt welded. The cylinder is exactly1-1/4” thick, and it is used in the repair of a pressure boundary on a U stamped vessel, the following is a

true statement.

1. It must receive full radiography.

2. It may be not spot radiographed.3. It may not be fully radiography.

4. It may receive either spot, full, or no radiography depending on original the original U1 form.

84. Charpy impact tests are intended to prove that a material is;

1. tough at the desired MDMT of the vessel to be constructed using that material.

2. some what prone to brittle fracture.

3. acceptable for use in high temperature service.

4. not required to be heat treated.

85. According to Section IX, all welders must be re-tested for a process;

1. if they have not been tested before.

2. if they have not used a process in the past 9 months or longer.3. if they have not used a process for the past 12 months or longer and have not been welding with

other processes.4. if the welder’s ability to make sounds welds with process is in doubt.

86. The testing apparatus used, and the techniques for performing Charpy impact tests are found in;

1. Section VIII Div. 1 Paragraph UG-84

2. SA-270

3. SA-370

4. Section IX paragraph 401.32

87. An above the ground vessel is required to receive an external inspection;

1. Every 4 years.

2. At the half corrosion-rate life.

3. Every 10 years.

4. Every five years or at the same interval as the internal inspection whichever is less.

Page 10: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 10/22

88. Before starting the inspection of a pressure vessel, especially one in severe service, the inspector 

should determine;

1. The pressure and temperature conditions under which the vessel has been operated since the first

inspection.2. The pressure and temperature conditions under which the vessel has been operated during the

 period since the last two inspections.3. The pressure and temperature conditions under which the vessel has been operated since the

current inspection.

4. The pressure and temperature conditions under which the vessel has been operated since the last

inspection.

89. The inability to draw the products of fractionation or distillation from certain trays may

1. indicate fouling or loss of tray parts in a process tower.

2. indicate that instrumentation is giving false readings.

3. prove that the piping diameter is too small.

4. indicate that the trays have lost all bubble caps or tray valves, or possibly the tray has collapsed.

90. Prior to witnessing a pneumatic test of a pressure vessel, which has been repaired by welding, the

inspector should;

1. Determine if the vessel has had all relief devices removed.2. Observe that the digital pressure gage to be used for the test is of the proper range.

3. Check that the personnel conducting the test have been properly trained to perform hazardous

tests.

4. Make sure that the analog pressure gage is of the proper range for the test pressure.

91. Widely scattered pits may be ignored as long as the following are true:

a. No pit depth is greater than one half the vessel’s wall thickness exclusive of the corrosion allowance. b. The total area of the pits does not exceed 7 square inches (45 square centimeters) within any 8-inch (20-

centimeter) diameter circle.

c. The sum of their dimensions along any straight line within the circle does not exceed 2 inches (5centimeters).

d.?

What is the missing item in d above is?

1. The pit depths must be measured from the side the pit is located on.

2. The 8 inch diameter is to be measured from the center of the deepest pit.

3. There are no missing item there are only 3 items listed for this rule.

4. The total area of the pits cannot exceed 3.5 square inches in a 4-inch diameter circle.

92. The surface remote from a welded joint is determined as follows;

1. 1 inch on either side of the weld or twice the minimum thickness which ever is greater.2. 1 inch on either side of the weld or twice the minimum thickness which ever is less.

3. For vessels with inside diameters less than 60 inches 20 inches or ½ the vessel diameter.4. 2 inches on either side of the weld.

Page 11: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 11/22

93. Before any repair to a pressure vessel in accordance with its code of construction, what if any

additional requirements for inspection may need to be considered?

1. Jurisdictional requirements that might override the API 510 Code.

2. Who is doing the repair?3. The quality of the repair materials.

4. The need for qualified welding procedures.

94. Some jurisdictions require that welded repairs to a pressure vessel be documented by the completion

and filing of;

1. A detailed report of the location and extent of repairs.

2. A qualifications record of all repair personnel.3. A permit issued by the jurisdiction.

4. The National Board of Boiler and Pressure Vessel Inspectors Form “R-1”.

95. While inspecting an operating vessel you observe that cracks are present in the connecting welds for a

gauge glass, you also notice vibrations are occurring in the assembly. Before you recommend corrective

actions you should;

1. Re-evaluate the materials used in the fabrication of the gauge glass.2. Write a report of the location with a recommendation for the type of repairs needed.

3. Research the inspection records for previous failures of this type.4. Check with a pressure vessel engineer to see if the cracks are caused by fatigue failure.

96. Witch of the following describes a type/s of rupture disks?

1. Multiple layer of graphite impregnated Kevlar fibers

2. Various metals - usually flat except steel.

3. Impervious graphite – un-bulged

4. Various metals, usually pre-bulged or impervious graphite, usually flat.

97. The two types of graphitization are;

1. Localized and random graphitization.

2. Ferritic and martensite graphitization.

3. Austenitic and martensitic graphitization.

4. Circular or globular graphitization.

98. The main reason(s) for inspecting heat exchanger bundles after removal and prior to cleaning is/are;

1. Location of scale on tubes can reveal non-operational problems.

2. Deposits on the tubes can reveal acid contamination problems.

3. Color of the tube ends can reveal de-zincification.

4. Color of deposits and scale can reveal corrosion problems.

Page 12: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 12/22

99. Hydrogen chloride becomes a problem when;

1. Exposed to air, it will thermally react and result in a fire.

2. Exposed to water, it forms hydrochloric acid.

3. Exposed to water, it becomes unstable and can form an explosive compound.

4. Exposed to water and air it produces formic acid.

100. Which one of the following types of coating failures may not easily detected?

1. Film lifting.

2. Rust.

3. Blisters.

4. Film dispersions.

101. Are nondestructive procedures allowed in lieu of hydrostatic testing, if so what must be done?

1. Engineer experienced in pressure vessel design and the API inspector must be consulted.

2. The API inspector and NBIC inspector must be consulted.3. The API inspector must be consulted.

4. An experienced engineer must be consulted.

102. A new vessel has been installed, what must be done in order accept the vessel for operation?

1. A first internal inspection.

2. A first internal inspection, however if a manufactures’ data report (U1) assuring that the vessel is

satisfactory for its intended service is available the first internal may be waived.

3. Base line thickness readings must be taken per OSHA 1920 (j).

4. Base line thickness reading must be taken per OSHA 1910(j).

103. A vessel is in a service that subjects it to acidic fluids, what is a major concern for this type of 

service?

1. Graphitic induced corrosion.

2. Caustic blistering

3. Caustic embrittlement and cracking.4. Accelerated corrosion, Hydrogen blistering, and Hydrogen induced cracking

104. Ordinarily non-metallic coatings and linings can be most effectively inspected by what technique?

1. Law holiday tester 

2. Radiography

3. Hammer testing

4. Using a high voltage low current brush type electrode device. (Spark Tester)

105. A relief valve has been shipped lying down on its side; this is a problem because;

1. Relief valves are often heavy and are sometimes difficult to upright.

2. Flange faces may be damaged during shipment.3. Springs in the valve may shift and distort and as a result not exert the same force on stems and

seats.

4. Springs may slip out and be lost during shipment.

Page 13: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 13/22

Page 14: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 14/22

113. Above what temperature must hydrogen attack be considered a concern in an operating carbon steel

vessel?

1. above 650 oF

2. below 650 oF

3. below 450 oF

4. above 450 oF

114. After removing an exchanger bundle you find a prussian blue coating on the tubes, what do you

suspect causes this coating?

1. Amino acid.

2. Cyanide.

3. Ferri-ferrocyanide.4. Phosphoric acid.

115. One major area of concern when inspecting guy wires for a vessel is crevice corrosion, where doesthis occur?

1. On the free end of the turn buckle.

2. In the threaded areas

3. On the guy wires.4. Where the wires contact the ground.

116. You are inspecting a failure in a vessel wall, what conditions would you look for if it was believed

that the fracture was brittle?

1. There is almost a no lack of ductility.

2. The fractured surfaces has a smooth surface

3. The surface of the crack would have jagged edges.

4. There is an almost complete lack of ductility and the failure site will have a faceted surface.

117. What is the ideal time to inspect pressure relief valves?

1. When the unit is in operation.

2. When the unit is out of operation.3. For relief valves when the boiler is undergoing Jurisdictional Inspections.

4. When the inspection least interferes with the process and maintenance manpower is readilyavailable.

118. Temper embrittlement is best described as;

1. Cracking due to operating at high temperatures above 700 degrees F.

2. Loss of ductility and notch toughness due to exposure above 700 degrees F.3. Flaking of the metal surfaces, causing dip pits.

4. Cracking due to low temperature service.

119. Carbon dioxide considered corrosive when?

1. When combined with glycol.2. When combined with water.

3. When combined with ethylene.

4. When combined with water and high temperatures.

Page 15: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 15/22

120. If white salts are found at cracks in a vessel;

1. it is an indication that the vessel contains an alkaline based chemical

2. it is an indication that the vessel contains an acidic based chemical

3. it is an indication that the vessel contains a low pH chemical4. it is an indication that the vessel had been operated above normal temperatures

121. The first consideration that must be given when the half bead temper bead technique of repair is

 proposed should be;

1. Consultation with the jurisdiction.

2. Time required to do the repair, and personnel safety.

3. Suitability for a given fluid service and any corrosion resistance required.4. Close monitoring of the welding operation.

122. A poor choice of material for ammonia service would be;

1. Stainless steels.

2. Copper based alloys.

3. Carbon steels.

4. Carbon Molybdenum steels.

123. When manufacturing lubricating oils and aromatics the following chemical is used;

1. phenol

2. ammonia

3. hydrogen cyanide

4. glycol

124. Aluminum chloride can affect stainless steel in which of the following ways?

1. Severe pitting corrosion only

2. Intergranular cracking only

3. Stress corrosion cracking only4. Stress corrosion cracking and/or intergranular cracking can occur 

125. The low temperature corrosion of gray cast irons is called;

1. graphitic corrosion

2. temper embrittlement

3. brittle fracture

4. incipient melting

Page 16: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 16/22

126. A bulged metal rupture disk with the pressure on the concave side has life expectancy of ;

1. 5 years.

2. 2 years.

3. 1 year.4. Indefinite length.

127. Most active of sulfur compounds found in refinery service is;

1. Mercaptans.

2. Organic sulfur compounds.

3. Hydrogen sulfide.

4. Polymorphic sulfides when combined with polymer products.

128. Which of the following are the materials could be expected to produce reliable magnetic particle

examination results?

1. Monels.

2. Cupro-Nickels.

3. Austenitic Stainless Steels.

4. Common Carbon Steels.

129. Which of the following is an example of a microstructural change in metal?

1. Graphitization.

2. Interstitial corrosion.

3. Debrittlement.

4. Embossing.

130. A common corrosive compound found in crude oil is;

1. Nitrogen compounds.

2. Phenolic acid.

3. Napthinic acid.4. Carbonic acid.

131. Dezincification occurs by attacking metals which contain;

1. Copper - zinc alloys containing less than 95% of copper used in water service2. Copper - zinc alloys containing less than 85% of copper used in water service

3. Copper - zinc alloys containing less than 85% of copper used in caustic service

4. Copper - zinc alloys containing less than 95% of copper used in acidic service

132. Which of the following describes a physical change in metal?

1. Intergranular corrosion.

2. Sensitization.3. Banite solution .

4. Amphoric layering.

Page 17: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 17/22

133. When looking for surface cracks in a vessel made of ferrous material which of the following is the

most capable of detection?

1. Fluorescent Penetrant Method.

2. Radiography.3. Fluorescent Magnetic Particle Method.

4. Close visual Inspection with good lighting.

134. The majority of vessel foundations are constructed using;

1. High grade (load bearing) concrete compounds.

2. Structural steel fireproofed with concrete.

3. Concrete reinforced with polymers.4. Structural steel overlaid with refractory.

135. Which of the following is considered a construction code?

1. ASME B 31.23

2. ASME B 33.2

3. ASME Section V

4. ASME Section VIII Div. 1

136. Vanadium Oxide corrosion is not known to occur below;

1. 1,050 oF

2. 1,100 oF

3. 950 oF

4. 800 oF

137. Under which of the following condition(s) should you require to the removal of safety relief 

device(s)?

1. If a pressure test is being conducted in which the test pressure will exceed the set pressure of the

safety relief valve with the lowest setting.2. The safety relief device was opening on a regular, unexplainable basis.

3. Seepage had been discovered and operators have been consulted.

4. Surface corrosion on the body of the device.

138. The rerating of vessel involves the;

1. Calculations from only a manufacturer experienced in pressure vessels.

2. Use of Non-Code requirements as established in accordance with the alternative rules of B31.3.

3. Review Inspection records verify the pressure vessel has been in the proposed service previously.

4. Calculations from either the manufacturer or an owner-user engineer experienced in pressure

vessels.

Page 18: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 18/22

139. Which of the following is a major concern when operating vessels that utilize the fluidized bed

 principle?

1. Overheating

2. Erosion3. Corrosion

4. Cracks

140. The inspection of a vessel to determine if a hydrogen blister is present is often best performed by;

1. Researching the inspection records.

2. Determine the vessels material to see if hydrogen attack is likely.

3. Shining a flash light parallel to the vessel’s surface.4. Recommending metallurgical tests for blisters in a laboratory.

141. When a crack is discovered in a vessel that is in a highly stressed area. What action should you

recommend be considered as a first step in any effort to correct the flaw?

1. Using an insert patch.

2. Removing the crack using by grinding and inspect using an NDE procedure before repair by

welding.3. Call in a pressure vessel engineer.

4. Design an overlay patch that has rounded corners.

142. Which of the following should be considered in determining the material to be used for pressure

relieving devices?

1. Temperature and pressure.

2. Pressure and corrosion resistance requirements.

3. Temperature, pressure, corrosion resistance requirements and atmospheric conditions.

4. Atmospheric conditions and temperature.

143. When preparing to inspect a vessel which has had previous inspections what is the initial step in

 preparation for the inspection?

1. Assemble all the required tools to perform the inspection.

2. Review previous inspection records.

3. Advice maintenance of any anticipated repairs.

4. Insure that all non-destructive examinations required have been scheduled.

144. When rerating a pressure vessel, one of the steps of the rerating is the documentation of the;

1. Calculations from the manufacturer or the owner-user’s engineer.

2. Approval of the operation’s engineering department.

3. Report from a professional engineer.

4. Approval of the ASME.

Page 19: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 19/22

145. Which of the following best describes a “Corrosion Button” as might be found in a pressure vessel?

1. Buttons made of highly corrosion resistant material from which corrosion loss can be measured.

2. Buttons which corrode at about the same rate as the vessel’s material and are used to estimate the

vessel’s corrosion losses.3. No such thing exists; there is however a corrosion tab used in vessels.

4. A form of corrosive product produced by certain chemicals in a vessel when is constructed of highchrome alloy material.

146. Why should weld probe or trepan inspection methods be avoided if at all possible?

1. The repair concern will normally charge more to repair these destructive tests sites in the vessel.

2. These types of destructive test site (holes) are difficult to repair and the weld quality of suchrepairs is likely to be poor.

3. Most jurisdictions prohibit such destructive tests.

4. NDE personnel are ill equipped to test such sites prior to repairs.

147. Pitting corrosion is usually found in a vessel by what means?

1. Thickness measurements at all the compass points at one foot intervals.

2. Scratching with a pointed scraper.3. Each shell course and head shall be subjected to abrasive blasting.

4. Each shell course and head shall be wire brushed thoroughly.

148. The thinned areas of a vessel are to be evaluated for continued service using the design by analysis

methods of Section VIII Division 2. When using this technique it is always true that:

1. The insurer of the vessel must be consulted with first.

2. Corporate engineering must approve this method of evaluation.

3. Consultation with a pressure vessel engineer is required.

4. You must determine the materials used in the fabrication of the vessel.

149. Heavy wall process hydro-carbon reactors operate at high pressures and have special inspection

requirements, chief among these requirements are inspections for what type of problem?

1. Laminations of the heavy wall plates used in construction.

2. Crack damage.

3. Upset trays and down comers.

4. Severe corrosion in the top head due to corrosive vapors generated in the process.

150. The number of Charpy impact specimens required for a 1-1/2" thick weld procedure test plate is;

1. 2 sets of 3.

2. 3 sets of 2.

3. 4 sets of 3.4. Dependent on the type of material to be used in the construction of the vessel.

Page 20: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 20/22

36. 3 API 510 6.6

37. 1 API 510 7.3

38. 2 API 510 7.2.7

39. 1 API 510 7.2.8

40. 3 API 510 6.5

41. 3 API 576 6.2.242. 4 API 510 5.3

43. 2 UG-102

44. 4 API 510 6.7

45. 2 API 510 6.3

46. 4 API 572 10.4.5

47. 3 API 510 7.2.10

48. 3 API 510 6.4

49. 4 API 510 5.2

50. 4 API 510 3.12

51. 1 UG-27&API 510

52. 4 Due to Geometry the flatter the thicker required

53. 3 API 510 6.3

54. 2 API 510 6.4

55. 3 API 510 1.1

56. 3 API 510 1.1

57. 4 API 510 5.1

58 2 API 510 5.5

59. 4 API 510 5.5

60. 2 IX QW-300.2

61. 4 API 510 3.5

62. 1 API 572 10.2.2

63. 3 IX QW-100.1

64. 4 API 572 8.4

65. 2 SEE ASME/NBIC Q&A

66. 4 API 576 4.8.167. 2 SEE ASME/NBIC Q&A

68. 1 VIII UG- 27

69. 3 IX QW-300.3

70. 3 ALL OTHERS USE O SCOPES

71. 4 IX QW-200.1

72. 1 API 572 8.2

73. 4 CHAPTER II 206.021 - .023

74. 4 API 572 10.5

75. 3 VIII UG-84

76. 2 VIII UW-35

77. 2 IX QW-302.2

78. 1 API 510 7.1.179. 4 VIII UG-84

80. 4 VIII UW-51(a)(3)

81. 4 VIII UW-52 (c) (3)

82. 3 VIII UW-52 header note.

83. 4 VIII UW-11(a)(3) & UCS -57 (table notes)

84. 1 VIII UG-84 definition of Charpy (notch toughness)!

85. 4 IX QW-322.1

86. 3 VIII UG-84 refers SA-370 for details

Page 21: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 21/22

87. 4 API 510 6.3

88. 4 API 572 10.1

89. 1 API 572 9.2

90. 4 VIII UG-100 & 102 & UW-50

91. 3 API 510 5.7(e)

92. 1 API 510 5.7(g)

93. 1 API 572 11.0 (see note in text body}94. 4 API 572 11.0 (see note in text body)

95. 4 API 572 10.3.10

96. 4 API 576 4.9.1à4.9.5

97. 1 CHAPTER 2 204.022

98. 4 API 572 A.9.1

99. 2 CHAPTER II 202.022

100. 1 API 572 10.3.11

101. 1 API 510 7.2.10

102. 2 API 510 6.1

103. 4 CHAPTER II 202.022

104. 4 API 572 10.4.6

105. 3 API 576 5.8.1106. 4 API 572 10.3.8

107. 1 CHAPTER II 202.042

108. 4 API 572 8.3.3

109. 4 API 572 8.3.7

110. 1 API 576 6.4.1.

111. 2 API 572 10.4.4

112. 3 API 572 10.4.4

113. 4 CHAPTER II 204.035

114. 3 API 572 A.9.2

115. 2 API 572 10.3.7

116. 4 CHAPTER II 205.01

117. 4 API 576 6.5.1

118. 2 API 510 5.2119. 2 CHAPTER II 202.024

120. 1 API 572 10.3.12

121. 3 API 510 7.2.3

122. 2 CHAPTER II 202.037

123. 1 CHAPTER II 202.033

124. 4 CHAPTER II 202.039

125. 1 CHAPTER II 202.063

126. 3 API 576 4.9.3

127. 3 CHAPTER II 202.23

128. 4 SECTION V T-720

129. 1 API 572 8.3

130. 1 CHAPTER II 202.021131. 2 CHAPTER II 202.66

132. 1 API 572 8.3

133. 3 API 572 10.4.4

134. 2 API 572 10.3.3

135. 4 B31.23&B33.2 nonexistent V is a support Code

136. 2 CHAPTER II 202.054

137. 1 API 510 6.5

138. 4 API 510 7.3

Page 22: api510-closedbook

7/30/2019 api510-closedbook

http://slidepdf.com/reader/full/api510-closedbook 22/22

139. 2 CHAPTER II 202.32

140. 3 API 572 10.3.13

141. 3 API 510 7.1.3

142. 3 API 576 5.6

143. 2 API 572 10.4.3

144. 1 API 510 7.3

145. 1 API 572 10.5146. 2 API 572 11.0

147. 2 API 572 10.4.4

148. 3 API 510 5.7(f)

149. 2 API 572 10.4.4

150. 1 VIII UG-84 (h)