Universitatea Politehnica Timisoara Facultatea de Constructii si Arhitectura ANTEMASURATOARE Nr . ANTEMASURATOARE cr t. Simbol Denumire articol Calculul cantitati explicit U.M. Cantita tea 1 2 3 4 5 6 1 TSG02A1 Curatirea terenului de frunze si crengi 35.00x45.00 100m p 15.75 2 TSC02D1 Sapatura mecanica cu excavat pe pneuri (2.0mx3.0mx2.10m)x12buc+(2.0mx3.0mx2.10m)x 6buc +(1.0mx1.0mx0.65m)x12buc=250mc +(1.09mc+0.82mc)18=280mc 100m c 2.80 3 TSA02B1 Sapatura manuala sub 1m latime 0.010x0.25x(15x4.0+8x4.3+8x3.0)=0.30mc mc 0.30 4 TRA01A04 P Transport rutier a lpamantului (280mc+0.30mc-130mc(umplutura))x1.2t/ mc=180t t 180 5 TSD01B1 Realizarea umpluturilor (2.025mcx2.0m+1.58mcx2.0m)x18buc=130mc mc 130 6 TSD04D1 Compactarea cu maiul Cf. art. 5: 130mc mc 130 7 TSD16A1 Strat de repartitie balast (42.32mx32.52mx0.20m)+ +(42.92mx2.0mx0.09m+32.52mx2.0mx0.15m)x2la turi=314mc mc 314 8 TRA01A10 Transport rutier ballast Cf. art. 7: 314mcx1.8t/mc=558t t 558 Coordonator proiect: Regep Zoe Candidat: Vidrighin-Bratu Gheorghe

Antemasuratoare

Embed Size (px)

DESCRIPTION

co

Citation preview

ANTEMASURATOARE

Universitatea Politehnica Timisoara

Facultatea de Constructii si Arhitectura

ANTEMASURATOARE

Nr.ANTEMASURATOARE

crt.SimbolDenumire articolCalculul cantitati explicitU.M.Cantitatea

123456

1TSG02A1Curatirea terenului de frunze si crengi35.00x45.00100mp15.75

2TSC02D1Sapatura mecanica cu excavat pe pneuri(2.0mx3.0mx2.10m)x12buc+(2.0mx3.0mx2.10m)x6buc+(1.0mx1.0mx0.65m)x12buc=250mc +(1.09mc+0.82mc)18=280mc100mc2.80

3TSA02B1Sapatura manuala sub 1m latime0.010x0.25x(15x4.0+8x4.3+8x3.0)=0.30mcmc0.30

4TRA01A04PTransport rutier a lpamantului(280mc+0.30mc-130mc(umplutura))x1.2t/mc=180tt180

5TSD01B1Realizarea umpluturilor(2.025mcx2.0m+1.58mcx2.0m)x18buc=130mcmc130

6TSD04D1Compactarea cu maiulCf. art. 5: 130mc mc130

7TSD16A1Strat de repartitie balast(42.32mx32.52mx0.20m)+

+(42.92mx2.0mx0.09m+32.52mx2.0mx0.15m)x2laturi=314mcmc314

8TRA01A10Transport rutier ballastCf. art. 7: 314mcx1.8t/mc=558tt558

9CB01A1Cofraje pentru beton in fundatii(1.0m+2.0m)x2buc=6mlx0.40m=2.40mpx12buc=28.8mp(1.0m+2.40m)x2buc=6.8mlx0.40m=2.72mpx6buc=16.32mp

Total: 45.12mp mp45.12

10CZ0301B1Confectionarea armaturilor OB37Cf. extras de armatura fundatii: 157kgkg157

11CZ0301E1Confectionarea armaturilor PC52Cf. extras de armatura fundatii: 625kgkg625

12CC01A1Montarea armaturilor in fundatiiCf. art. 10+11: 157kg+625kg=782kgkg782

13CA12D1Betonarea buloanelor la fundatii4x18buc=72bucbuc72

14CA01B1Turnarea betonului simplu in fundatii(1.0mx1.0mx0.4m)=0.40mcx12buc=4.8mcmc4.8

15CA02B1Turnare beton armat in fundatii3.0mx2.0mx0.70m+2.0mx1.0mx0.40m=5mcx12buc=60mc3.40mx2.0mx0.70m+2.40mx1.0mx0.4m=5.72mcx6buc=34.3mc Total: 94.3mcmc94.3

16TRA06A05Transport rutier al betonuluiCf. art. 15: 100mcx2.5t/mc=250tt250

17CL01C1Montare stalpi marginali din otelCf. extras de material stalp: 27.3tt27.3

18CL09A1Montare ferme cu zabreleCf. extras de material ferma: 6.58tt6.58

19TRA01A14Transport rutier al materialelorCf. art. 17+18: 27.3t+6.58t=33.88tt33.88

20AUT6753Automacara 40oreore40

21CL09A1Montare grinzi de rulareCf. extras de material gr. rulare: 28.2t-3.55t(sina)=24.65tt24.65

22CL11A1Montare sine de rulare6.0mx3buc+7.2mx2buc=32.4mx4siruri=129.6mlml129.6

23TRA01A14Transport rutier al materialelorCf. art. 21+22: 28.2tt28.2

24AUT6753Automacara 32oreore32

25CL13A1Montare contravantuiri acoperisCf. extras de material contravantuiri: 2.17tt2.17

26CL16B1Montare pane metaliceCf. extras de material pane: 5.06tt5.06

27TRA01A14Transport rutier al materialelorCf. art. 25+26: 7.23tt7.23

28AUT6753Automacara 32oreore32

29CL05A1Montare gr. cu inima plina I1617.9kg/mx(42.0m+30.0m)x2laturi=2578kg=2.578tt2.578

30CL01A1Montare stalpi metalici fronton92.6kg/mx(12.20mx8buc+13.00mx4buc)=13853kg=13.85tt13.85

31TRA01A14Transport rutier al materialelorCf. art. 29+30: 16.428tt16.428

32AUT6753Automacara 16oreore16

33CG18E1Pardoseli din beton B30042.80mx32.40m=1387mpmp1387

34CZ0108E1Preparare beton B3001387mpx0.18m=249.7mcx1.008=251.7mcmc251.7

35TRA06A05Transportul rutier al betonului251.7mcx2.5t/mc=629.3tt629.3

36CD12B1Montare pereti din placi plane(42.92mx32.52m)x2siruri=150.9mx1095m=1652mpscad portile: (5.0mx5.0m)x4buc=100mp

Total: 1552mpmp1552

37CK15B1Usi si porti metalice(5.0mx5.0m)x4buc=100mpmp100

38CE05A1Invelitoare acoperis(11.90mx32.80m)x4buc=1561mpmp1561

39IZD10A1Vopsirea anicoroziva a stalpilor pana la cota 0.00Cf. art. 24: 2.578tCf. extras de material stalp: 1.85t

Total: 4.428tt4.428

40IZD04D1Vopsirea confectiilor metaliceCf. art. 17+18+21+25+26: 81.31tt81.31

41CE13A1Jgheaburi din tabla zincata(42.92mx32.52m)x2randuri=151mm151

42CE14A1Burlane din tabla zincata11.0mx6buc=66mm66

43CO01A1Trotuar din beton simplu B15042.92mx2.00mx2laturi+32.52mx2.00mx2laturi=302mpm302

44CZ0105A1Preparare beton B150Cf. art. 43: 302mpx0.10m=30.2mcx1.008=30.44mcmc30.44

45TRA06A10Transportul rutier al betonului Cf. art. 44: 30.44mcx2.5t/mc=76.1tt76.1

Coordonator proiect: Regep Zoe

Candidat: Vidrighin-Bratu Gheorghe