Upload
vuongtuong
View
223
Download
3
Embed Size (px)
Citation preview
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 318
Annexe - 4
Status Report on Compliance with Directives
The directives earlier given by the Commission were addressed to KPTCL in its
capacity both as Transmission Licensee as well as Supply (Bulk & Retail) Licensee.
Subsequent to Tariff Order 2002, the Distribution & Retail Supply Business has now
been vested with the ESCOMs. Some of the Directives pertain exclusively to the
Transmission Licensee while others pertain to the Distribution & Retail Supply
Licensees. There are some Directives that are to be complied with by both KPTCL as
well as the ESCOMs. The following analysis compliance in this background.
1.0 Management Information System
1.1 Summary of Directive as in Tariff Order 2000 (page No. 145)
The KPTCL shall improve its management information system in the next filing to give
greater details and explain the basis for all the projections indicating the sources of
data and the method of estimating projected values.
1.2 Gist of Comments of KERC in Tariff order 2002 (Page 32)
The Commission concluded that the pace of computerization till then had been
very slow. The Commission identified certain functionalities out of the several that
are included in the computerization modules as being important for the work of the
Commission and asked KPTCL to commit itself to specific dates for their
implementation. Such dates had been specified in a few cases and were yet to be
committed in other cases. The Commission said that it would continuously follow up
with the Licensee on this matter.
1.3 Reply of KPTCL in the Current filing:
1. The work is entrusted to the ISP consultants M/s PWC. On transmission input
formats, draft is yet to be finalised by M/s PWC. The MIS is being developed to
capture information on issues like financial impact of both the Bulk Supply Tariff and
the various power purchase agreements. The development of MIS is in ToR of ISP
consultants and the consultants have been requested to expedite the report within
March 03.
2. The status of other modules is as follows:
i) Maintenance (MNS): 220KV Yerandanahally station is selected as pilot site. The
module is tested and some minor modifications are requested with TCS. The module
will be implemented in Yerandanahally shortly.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 319
ii) Project Management (PMS): Testing of the module at pilot site in CEE
(Transmission), Bangalore is in progress. Certain changes are being requested, by
Chief Engineer Electricity (Transmission) to adopt to field conditions. The
implementation will be taken up after testing.
iii) Material Management (MMS): Testing of Stores sub module at pilot site in East
Division stores is completed. The package is running in parallel with manual system.
The purchase sub module is under testing and would be completed by 30th
November 2002. After this, testing of scrap sub module will be taken up. The
complete roll out plan is planned to be completed by March 2003.
iv) Personnel & Pay Roll (PPR): Testing at pilot site in Central Division is under
progress. It is likely to be completed by end of November 2002. Certain changes
have to be made by TCS.
v) Finance & Accounting (FAS): The testing of FAS module is yet to be started as
implementation of other modules is being pursued. The testing will be taken up
shortly.
1.4 Replies of ESCOMs:
1.4.1 Reply of BESCOM
1. Billing and collection software prepared by M/s. TCS is being implemented at 39
urban sub-divisions and 13 rural sub-divisions of Bangalore district. Reports such as
Bill generation status, Number of MNR installations, Number of DC, Door lock
installations, abnormal & subnormal consumption, All cash counter -related reports,
Ledger-wise consumption reports, Disconnection and Reconnection lists, Days
demand and collection Tariff wise, Rebate provided for installations with solar water
heater facilities are being generated.
2. Bids for outsourcing the Data Base administration and Data warehousing is under
evaluation.
3. Software regarding payroll management and Material Management is being
tested at Pilot sites by KPTCL. Maintenance Module and Finance Modules will be
provided by KPTCL.
1.4.2 Reply of MESCOM
1. MESCOM commenced its operations from June 1, 2002 and till then preparatory
efforts had been initiated in implementing the Billing & Collection module of TCS.
MESCOM is acutely aware that a strong and robust monitoring system in
conjunction with a performance management system is extremely important for
improving efficiency, improving performance and enhancing consumer service.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 320
Such a system is extremely onerous to implement without computerisation of the
basic processes. Therefore, roll out of the B&C package in Mysore and Mangalore
divisions, closely followed by Udupi and Mandya, has been taken up at a high
priority. The action plan for B&C module rollout in these divisions is as below:
MIS Roll out Plan
Division Data Entry
& Validation
Generation of
Pilot Bills
Switchover
from
Manual Bills to
Computer Bills
Plan for
Manpower
redeployment
Mysore Completed In progress Jul-03 Oct -03
Mangalore Dec-02 Jan-03 Aug-03 Nov-03
Udupi Mar-03 Apr-03 Nov-03 Feb-04
Mandya Mar-03 Apr-03 Nov-03 Feb-04
2. We intend to put in place a robust and flexible system that would permit
meaningful analysis by the management for evolving business strategies and to
comply with regulatory requirements. In respect of Mysore division, the trial bills
have been generated and the first copy of all computerized bills is being distributed
among customers starting 1st November, 02. In respect of Mangalore, the
consumer database is being created. Computerized bill processing would be
undertaken soon. A workshop had been organized in Mangalore where the
Computer Centre Personnel from KPTCL familiarized the Field Officers viz., AEEs and
AAOs to familiarize them with the computerization of B&C software. A High Level
Team of MESCOM consisting of MD, DT and other Officers visited BSES Mumbai and
studied the system functioning there. Preliminary correspondence with BSES has
been taken up to assist MESCOM for setting up similar system and totally
implementing computerized billing. These initiatives and others would be continued
to take up computerised billing and collection system in the urban areas and
thereafter in rural areas.
3. Finalisation of New MIS Design: The MIS submitted by ISP after rationalizing the
131existing formats was reviewed. ISP Consultants were requested to present to the
field officers the revised MIS on the 4-5th October. Detailed review of the revised
MIS has been undertaken thereafter and performance measure is being finalized
for Management Review. On the MIS, several suggestions have been made and
detailed implementation requirements have been identified. For instance to
introduce slab-wise analysis, changes to the DCB reporting format from the sub-
division are required. The Sub-Division will be required to compile slab-wise
consumption while reporting the Demand Collection and Balance. ISP Consultants
also visited Udupi division to draw out other implementation issues so that key
regulatory information requirements can be met and a prioritised plan of
implementing the revised MIS can be developed. MESCOM has finalized plans to
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 321
implement the Revised MIS at a pilot location in March 2003 and rollout in the other
sub-division after a 2-month implementation cycle.
4. In the meantime, action has already been initiated to standardize reporting
formats, use of email to receive periodicals reports, and data compilation and
collation being done with the mailed in data leading to faster compilation of
reports, particularly for DCB reports. The monthly DCB figures are now available by
the 10th of the month at the corporate level, and exception reports generated and
sent to the field units by the different revenue monitoring cells to push them into
remedial action. Automatic compilation of data at corporate level with
simultaneous entry of data at the divisions is being taken up with the involvement of
an experienced private agency. MESCOM plans to set-up a MIS Cell within the
Corporate Headquarter, which will receive all the MIS reports and will carry out the
analysis centrally. Exception reports on pre-defined triggers will be generated for
Management action and furnished to the field office. By introducing such a
scheme, we expect to improve availability of MIS for regulatory oversight and to
relieve the field offices from the onerous task of compiling information formats.
5. MESCOM is also working on strategy of outsourcing the billing activities on a pilot
basis in areas where there is dearth of meter readers and meter reading is difficult
due to logistic reasons. This strategy of outsourcing would be finalised by March
2003. Discussions have been held at various levels on working out the details and 20
of the 74 sub-divisions have been identified for outsourcing of the meter reading
work, which is expected to lead to better efficiencies in the billing and thereby in
revenue collection.
6. While outsourcing, strict requirements on generating MIS for the sub-division will
be enforced, which will greatly improve the information quality.
7. Training of manpower: We have identified manpower to be given reorientation
training for attitudinal change to service the consumers better. Proposal has been
sent to the BSES Institute. Another proposal is also taken up to train some staff in
Computer operations, for which APTECH as an agency has been identified.
8. Financing Computerization Projects: We are preparing a proposal to approach
PFC for funding the computerization projects. CPRI has been contacted for assisting
in identifying projects suitable for the needs of the MESCOM.
1.4.3 Reply of HESCOM
1. A Management Information System Cell has been created with CEE, HESCOM as
the Chairman of the Cell, DGM, Corporate Office of HESCOM as the Convener of
the Cell and all the EEEs at HESCOM’s Corporate Office as its members.
Computerisation of collection is started and billing will be started shortly at
Belgaum, Dharwad and Hubli.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 322
1.4.4 Reply of GESCOM
1. GESCOM is planning a two-pronged strategy for computerization of its billing
activity:
(1) To introduce the in-house computerized system of billing and collection plan in
select divisions. GESCOM plans to computerise five Divisions namely Bidar, Koppal,
Raichur, Bellary and Gulbarga for billing and collection. This process shall be carried
out in three steps.
The first is to enter data into specified formats, which in itself requires considerable
effort and time. This will be followed by rectification and verification of the data.
The final introduction and implementation is expected around January 1, 2003. The
pilot implementation shall be made in the towns of Bellary, Bidar, Raichur,
Gangavati and Yadgir. Currently the GESCOM is in the first stage of the process.
(2) To outsource billing activities on a pilot basis
To initiate the process GESCOM has also called for bids from organisations
interested in providing packages for implementing computerizing billings and
revenue management information system in CSD-1, Gulbarga Sub-Division. It is
expected that this pilot computerization project could be implemented by March
2003. Based on the experience from pilot implementation, the process would be
extended to other regions after evaluating the cost and benefit of the
implementation.
2. GESCOM has also taken steps to ensure that its own employees are skilled and
equipped with basic computer skills. Training initiatives has been taken up and
employees of Bellary Urban Sub-divisions have been trained on computer usage in
October 2002. There is a program to train 150 personnel in basic computers skills
and billing and collection software with the assistance of APTECH.
3. GESCOM is committed to improving its MIS and would like to assure the Hon’ble
Commission that this work is being carried out on a priority basis. However, given
the fact that the existing systems are particularly inadequate, it would require
significant effort, time and resources to be able to reach the expected level.
1. 5 Comments of KERC
1.The Commission notes that there are two aspects covered under MIS. One is the
development of MIS by PWC and the other is the application modules developed
by TCS.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 323
2. With respect to the former, KPTCL has replied that the mandate to develop the
transmission MIS is in the terms of reference with ISP consultants and PWC has been
requested to expedite report within March 03.
It is noted that in the earlier replies furnished to the Commission, KPTCL had
identified 131 formats out of which 19 were exclusively covering Generation and
Transmission. In order to minimise the number of formats, PWC was entrusted to
prepare MIS strategy and the MIS implementation was to be effective from 1st June
2002 as committed by KPTCL in Tariff Order 2002. Further the dates have been
revised as per the action plan of GOK as per which PWC had to submit
implementation plan within 45 days from reckoned from 14th June 02. However in
the current reply it is stated that the PWC report will be available in March –03 and
no commitment is made for implementation. The Commission notes that the
implementation dates are being changed frequently indicating the lack of
commitment in MIS implementation.
3. Regarding the TCS modules, the Commission had several meetings with
KPTCL/BESCOM & TCS officials as a follow up action. The Commission has noted
that the implementation schedule has been changed by KPTCL frequently without
any valid reasons. The Commitments made by KPTCL on various occasions on
various modules excluding Billing & Collection software [BNC is discussed in the
relevant section of ESCOMs] is indicated in the table below:
Letter/order
date
PMS module MNS module MMS
module
FRS
module
PPR
module
Tariff Order
2002
15-7-02 15-7-02 15-7-02 15-3-02 15-7-02
No. KPTCL/B-
36/4539/4015
dated 11-3-02
January
2003
onwards
after pilot
testing
January 03
onwards
after pilot
testing
- - -
17-6-02 report
on
“arrangements
on formation
of NEW
DISCOMs.
Under
testing
Delivered to
BESCOM for
implementa
tion
Under
testing
Under
testing
Under
testing
27-6-02
meeting on
MIS
December
2002
December
2002
December
2002
Decem
ber
2002
Decembe
r 2002
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 324
Letter no.
KPTCL/B-
36/2001-
2002/MIS/1049
dated 4-7-02
30-10-02
testing will
be
completed
15-9-02
testing will
be
completed
30-12-02 15-11-02
testing
will be
complet
ed
30-11-02
29-7-02
meeting on
MIS
Testing will
be
Completed
by the end
of Sept-02
Testing will
be
completed
by 10-8-02
Successfully
tested &
ready for
implement
ation
6-9-02 meeting
on MIS
Testing
Completed
Testing
Completed
Testing
Completed
- -
ERC FY04 Testing in
progress
after
modification
Ready for
implementa
tion
Only stores
sub module
tested.
Other
modules
will be
tested
latest by
Nov-02.
Testing
yet to
be
done
Testing
will be
Complete
d latest
by Nov-02
4. It is noted that the schedules furnished for the implementation have been
frequently changed and are inconsistent. Further, in the Advisory Committee
meeting held on 29-1-03, KPTCL has informed that agreement with TCS has been
terminated. In view of the above the Commission opines that none of the modules
envisaged by KPTCL has fructified and the entire computerization program has
perhaps become infructuous. A lot of time and money has been spent since 1996
on software development with TCS. The Commission is not yet aware of the
alternatives that are worked by KPTCL.
5. The Commission has noted that as per the GOK action plan furnished to KERC
vide letter dated 18-6-02, KPTCL had to Completely test all the modules and deliver
to the ESCOMs for implementation. Except for Billing & Collection (BNC) package
none of the other packages are implemented. The status of other packages has
been already discussed in the relevant section of KPTCL’s MIS. In view of the
contract with TCS being terminated, the alternative action plan envisaged has to
be to be provided to the Commission.
6. The Commission notes the efforts initiated by ESCOMs with respect to
Computerisation & MIS. The Commission does not wish to comment on the specifics
of the Action Plan worked out by the ESCOMs in this regard, but would keep the
progress under continues review.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 325
2.0 Energy Audit.
2.1 Summery of Directives as in Tariff Order 2000 (Page No. 217)
These covered the planning and implementation of metering in KPTCL grid system
voltage wise, reduction of transmission and distribution losses, creation of
responsibility centres for energy audit, a scientific procedure for estimation of IP set
consumption etc.
2.2 Comments of KERC in Tariff Order 2002 (page No. 34)
The Commission noted that compliance was very delayed, without any satisfactory
explanations. KPTCL stated that the metering of the KPTCL grid system voltage level
wise would be completed by January 03. Commercial losses were reportedly being
reviewed regularly at RBC meetings. The distribution losses in 46 towns and cities
observed to be high and the Commission concluded that there was no substantial
compliance on this directive. Regarding DC/MNR and sealing of meters the
Commission noted the increase in numbers from the ones in March 2000. Further the
Commission observed that sealing of meters was pending for a long time.
Regarding the distribution losses the Commission observed that even though the
Transmission losses decreased there was increase in distribution losses.
2.3 Reply of KPTCL in the current filing
Metering in Transmission system of KPTCL at 400 KV, 220 KV and 11 KV Banks is in
place. The CTs & PTs required for metering at 33 KV level are being installed and the
completion of the work is fixed as March 03. Soon after this loss level at 33 KV can
be measured.
Division wise Energy Balance statement up to March 2002 has already been
furnished to the Commission vide this office letter No.KPTCL/B-36/D/4533/1857-59
dated 17-10-2002. Energy Balance statement for April and May 2002 will be sent
shortly. From 1st of June 2002, ESCOMs have to furnish Division wise Energy Balance
statement.
2.4 Replies of ESCOMs
2.4.1 BESCOM Reply:
Special teams are sent from Corporate planning Wing to validate the energy audit
figures as month-to-month variation is noticed due to incorrect Computation of
metered & un-metered sales.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 326
As agreed during the meeting on 8-10-2002 with the commission, validation of
energy loss figures of all cities & towns will be completed and report will be
submitted to the Hon’ble Commission before December 2002.
2.4.2 Reply MESCOM:
1) MESCOM is fully committed to reducing the losses and introducing energy
accounting at all levels. For ensuring the same as a first step, it is intended to
continuously collect information and analyse the same. This process has already
been initiated and it is decided to take the assistance of private participants in this
regard and a tender has already being floated on an experimental basis.
2) The Chief Engineer of MESCOM has been made in charge of identifying the high
loss making feeders and to formulate schemes for reduction of loss.
3) MESCOM has already completed the analysis of the energy audit reports of
June, July and August for ten towns and cities.
4) Some of the measures contemplated for reduction of commercial losses include
providing of additional distribution transformers, provision for additional link lines
and express lines, and replacement of DC/MNR meters, and ensuring 100% billing.
Intensive metering programme has been taken up for replacement of meters of
MNR installations, because of which 2,12,934 meters have been provided. To target
theft and pilferage of power, a vigilance action plan has also been formulated and
targets have been set to convert commercial losses into revenue demand. Out of
the nine Vigilance Police Stations, four are already functional and efforts are made
to operationalize the others.
5) Energy Balance Sheet is prepared at the Division level. The Chief Engineer of
MESCOM is taking up supervision of data collection for the purpose.
6) A proposed incentive scheme based on performance measure has been
prepared in consultation with GoK and Institutional Strengthening Consultants. The
Energy Audit details of 11KV system of MESCOM Division-Wise have been furnished
to the Commission on a regular basis.
7) Distribution loss of 46 towns (10 towns in MESCOM) : In the cities of Mangalore,
Udupi, Shimoga, Badravathi and Sagar the losses have been brought under 15%. In
the cities of Chikkamagalur, Mysore, Hassan and Mandya it is in the range of 15 to
20% and in the city of Chamarajanagara it is 29.13%. Analysing the loss figures and
developing action plan to address the same has been a continuous process and
efforts are on to bring the losses in all these cities to less than 15%.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 327
8) MNR installations in the identified cities have been replaced as a part of the
general programme of replacing DC/MNR meters. This effort would continue to
keep the MNR figure below the figure stipulated by the Commission.
9) Efforts are being made to reduce the technical losses by properly directed
capital expenditure and reduction of commercial losses by effective checking of
installations with the assistance of Vigilance Wing.
10) The issues like having accurate interface metering with KPTCL and other
ESCOMs is being dealt with utmost urgency. Further, in order to have a more
accurate assessment of IP set Consumption, action is being taken to install energy
meters to all the IP sets connected to the DTCs involved in the estimation of IP set
consumption. This is expected to be completed by March 2003.
2.4.3 Reply of HESCOM:
1) HESCOM is making sincere efforts to reduce such losses. Action has already been
taken to reduce the distribution losses at 11 kV and below by taking up system
improvement works, APDRP works. In addition to these works, improvement works to
reduce the losses in 12 selected towns in HESCOM is under progress. Further 11 kV
Town feeders with high losses have been identified for intensive Vigilance activity.
2) An Energy Audit Cell comprising of CEE (Hubli Zone) as its Chairman, SEE (MRT)
and SEE (TL & SS) and AEE (E) at Corporate Office as its members, while EEE, Energy
Audit at Corporate Office will be its Convenor.
The tasks involved are:
Developing Energy Audit Manual in co-ordination with counterpart team of
KPTCL
Listing objectives and common errors in Energy Audit
Developing Network map and assessing the correct input,
Estimating the un-metered consumption scientifically
Preparation of feeder wise accounts of energy delivered
Evolving appropriate methodology for shared feeders and (g) Carrying out
transformer failure analysis.
2.4.4 Reply of GESCOM:
1) GESCOM is fully committed to reducing the losses and introducing accounting at
all levels for ensuring the same. As a first step, it is intended to continuously collect
information and analyse the same. This process has already been initiated and a
core team under Chief Engineer (Corporate Planning) has been constituted to
analyse the energy audit reports on a continuous basis. In order to monitor the
energy losses more closely and to identify contributory factors it has also been
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 328
decided to conduct a sub-division level analysis. Instructions have been issued to
field offices to identify high loss feeders and to calculate the losses in feeders
supplying to IP sets.
GESCOM has already completed the analysis of the energy audit reports of June,
July and August of ten towns and cities. Following trends have been noted:
There has been an increase in energy losses in Gulbarga, Yadgir, Bidar and
Raichur towns.
Metered sales have come down in Gulbarga, Yadgir, Bidar, Raichur,
Koppal and Gangavathi towns.
Unmetered sales has gone up in Yadgir, Bidar and Bellary towns where as it
remained more or less the same in Gulbarga, Shahabad, Raichur,
Sindhanoor, Gangavathi and Hospet towns.
Input energy as measured in 11 KV feeders has increased in almost all the
towns except Sindhanoor, Hospet, Koppal and Gangavathi towns.
The trend during recent months indicates a decline in the performance. Transitional
issues and related constraints may have resulted in some slippages but GESCOM is
committed to reducing the losses and has already initiated a number of steps to
control them. These include 100% metering of urban feeders, metering of IP sets &
street lights, providing ETV meters, MNR replacement, sealing of meters,
improvement to distribution system, intensified vigilance raids, regularization and
physical verification drives etc.
2.5 Comments of KERC
2.5.1 Comments On KPTCL Reply:
There has been substantial delay in compliance with this directive of metering.
During several meetings in the last 2 years it was assured that the work would be
completed and voltage level wise losses would be provided from Jan 03. It was also
assured that all 11 KV feeder meters would be read using MRIs from April 02. But so
far the MRIs are not used for reading the ETV meters of the feeders. During the
meeting held with KPTCL on 24.01.03 it was reported to the Commission that the
work of metering at other voltage levels would be completed by March 03 and
voltage level wise loss figures based on meter readings would be furnished
thereafter. Further it is observed that several meters at interface points with ESCOMs
are faulty due to MNR, CT/PT failure etc.
There is no specific reply from KPTCL on the directive of transmission losses. For FY 03
the loss up to 11 KV is said to be estimated at 8.33% out of which the 33kV segment
loss is 1.94%, there by the Transmission loss is said to be 6.39%. The same loss level is
projected for FY 04. There is no proper and satisfactory reply for keeping the same
loss level for FY 03 and FY 04.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 329
2.5.2 Comments of KERC on Replies of ESCOMs:
The reply of ESCOMs is inadequate. ESCOMs have reported that the vigilance
activities have been increased. But even then the loss in the distribution system has
increased in the recent times.
The ESCOMs have furnished break up of losses at different levels. These are not
based on a sound basis.
The ESCOMs should take focused action in the matter of reduction of commercial
loss by increased vigilance activities. The task of sealing consumer energy meters is
pending for a long time.
There is delay in creation of responsibility centres and allocation of targets and
responsibilities to these centres. Even though ESCOMs have reported that the
responsibility centres at Division level have been created, the activities of these
centres are not satisfactory. To evaluate the performance of these centres and the
ESCOMs the Commission has issued reporting formats in November 02 with a
request to furnish the reports by 15th of every succeeding month starting from the
month of November 02. Even though the reports are received belatedly the
reporting seems to be not satisfactory.
The Commission issued directive on 4.10.2000 to reduce the losses to 15 % in 46
selected tons/cities. But there is no effective action in bringing down the losses.
The distribution loss levels in these towns/cities reported till November during FY03are
as follows:
ESCOM No. of
Towns
Monitored
Towns with loss %age
35-40% 30-35% 25-30% 20-25% 15-20% < 15%
BESCOM 14 -- 1 1 2 7 3
MESCOM 10 -- -- -- 1 5 4
HESCOM 12 -- -- 3 1 5 3
GESCOM 10 2 5 -- 2 1 --
Total 46 2 6 4 6 18 10
The IP sets in the town limits of the towns enjoy uninterrupted power supply. In spite
of several assurances to the Commission, they are not yet metered.
Further, even after three years of continuous persuasion by the Commission, the HT
metering cubicles to all the semi urban feeders to measure and segregate the
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 330
consumption outside the town limits in order to assess the loss accurately are yet to
be provided.
Further, metering and conversion of BJ installations in town limits, is not yet
completed. It is reported that the consumption by BJ installations within the town
limits is far more than the specific consumption by domestic lighting installations.
The Commission had directed ESCOMs to take up energy audit of at least three
DTCs in each urban sub division. Even though it is reported that the DTC energy
audit is taken up in some Sub Divisions the reports are not furnished.
Regarding DC and MNR installations there is no compliance with this directive by
the ESCOMs. There is an increase in the percentage of DC/MNR during FY 03 as
against FY 02.
The situation in GESCOM is alarming. It is reported that the meters are not supplied
in adequate quantities.
Regarding Survey of Unauthorised IP Sets the ESCOMs have not reported
specifically on this point and there seems to be no substantial compliance with this
directive. Even though about 79,000 unauthorised IP sets are reported to be
regularised during anti theft drive during March-April 2002 it has come to the
knowledge of the Commission that several un-authorised IP sets are getting added
even now and no action is taken on this matter due to law and order problem.
The Commission has issued a revised procedure for estimation of IP set consumption
by deducting LT line losses and taking account of the unauthorized IP sets
connected to the system. The revised procedure is not yet implemented.
Regarding Survey of IP sets with classification such as bore well; open well etc.,
along with capacity of pump there is no compliance with this directive by any of
the ESCOMs.
3.0 Directions in respect of Quality of Service as in Tariff Order 2000. (Page No. 219 )
3.1 The directives under Quality of Service contained the items like the reduction of
interruptions, maintenance of good voltage & frequency, earmarking of capital
expenditure for improvement of quality of power supply in rural areas, monitoring of
interruptions, identifying & improving low voltage pockets, maintenance of EHT & HT
capacitor banks, complaint handling machinery, reduction of accidents etc.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 331
3.2 Comments of KERC in Tariff Order 2002 (page No. 40)
The Commission has no information on the review of interruptions that is being taken
up in the RBC meetings. Consequently the Commission is not able to arrive at a
conclusion whether all possible steps in this regard are being taken by KPTCL or not.
Failure rate of transformers in rural divisions is on the increase.
KPTCL could have furnished 11 kV feeder interruption data (number of trips and
hours) for each MUSS monthly to assess the improvement in the power supply
conditions.
Regarding interruptions monitored by the Zonal Chief Engineers the Commission has
not been provided with any data. Monthly MIS may be evolved and the data in
that format may be made available to the Commission.
Systematic identification of division wise low voltage pockets has not been done.
The Commission notes that the licensee has not provided any specific and time
bound action programme to improve the low voltage conditions and has not
committed itself to any such programme.
The standard data MIS formats are not yet developed for monthly monitoring.
Several capacitor banks are out of service/are in service at reduced capacities.
It is observed that the complaint registers are not maintained uniformly at all
responsibility centres.
Due to the inadequacy of basic information as explained above, the Commission
has not been able to conduct the hearings on quality of supply as had been
originally planned.
Fatal accidents have increased. The fatal electrical accidents are more due to
snapping of conductors, non-observance of line clear procedure, ignorance on the
part of the public, un-authorised persons meddling with KPTCL power lines.
Though KPTCL has stated that it has taken remedial action, the Commission is
unable to agree with KPTCL since the accidents have actually increased.
3.3 Reply of KPTCL in current filing
Information regarding Quality of Service in respect of Transmission system of KPTCL
as per formats QoS T1, QoS T2, QoS T3 and QoS T4 of the Commission from April 2002
are being compiled and sent to the Commission.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 332
The status of the Quality of Service on month to month basis can be reviewed by
this information and the respective Transmission wings are directed to take
corrective steps in order to improve the same.
The total amount earmarked for FY03 in Budget for Transmission and sub-stations is
Rs.247.66 crores, out of which, Rs.199.71 crores is earmarked for Rural Areas, i.e., 81%
of total amount is earmarked for Rural Areas.
3.4 Reply of ESCOMs
3.4.1 Reply of BESCOM:
Due to poor monsoon and low reservoir levels the state’s total consumption is limited
to 80 MU per day. The above energy is rationed among all the ESCOMs and the sub
stations, thereby BESCOM is able to supply only 5 to 6 hours of 3 phase power supply
and 10 hours of single phase supply by rostering to the Rural Areas. There will be no
power supply for the balance period. Even in cities/towns (outside Bangalore) load
shedding to an extent of about 1½ to 3 hours per day is being done due to
generation limitation.
Due to constrains in allocation of the budgets by the Government all the planned
E&I Works cannot be taken up.
The H.T lines added in the first half of the current year is about 82% of the total of last
year indicating improvement of distribution system particularly the rural areas.
The quality of services regarding Transformers failure, Interruptions & Accident
Analysis is also being monitored.
Bench marking & Safety Audit is being taken up as per the directions of the
Commission to monitor the quality of service.
Comprehensive schemes have been prepared under APDRP programme works for
Tumkur & Kolar Circles for improvement of distribution network and submitted to
GOI.
In the first step proposals are submitted under APDRP to take up improvement works
at Taluk level. In these schemes all the 11KV lines having more than 9% Voltage
Regulation are bifurcated into Additional feeders to bring the voltage regulation
below 6% which infrastructure is sufficient to meet the load growth in the 10th Plan
period. More nos. of 25KVA DTs are provided to reduce the LT Distribution Loss.
150 Nos. of 15 KVA capacity three-phase distribution transformers have been
installed in BMAZ & BRAZ areas exclusively feeding to water supply installations.
Hon’ble Commission is aware that community involvement in Rural distribution is
being experimented in 3 O&M Units in BESCOM area and in this area 42nos. of 15
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 333
KVA Transformers are being installed to improve voltage regulation and benefited
consumers have agreed to clear all the IP dues.
Procurement of 15KVA 3 phase and 15KVA single phase DTs is also planned to
bifurcate village and IP loads so as to increase hours of single phase supply to
villages.
The Govt. of India under APDRP has approved Rs. 372.21 Crores for distribution
system in the areas of Roberts pet/KGF, Bangalore, Tumkur, Davanagere.
Any change in the ‘Capital Investment’ will be placed before the Hon’ble
Commission for revision of Capital Works Programme in regard.
3.4.2 Reply MESCOM:
APDRP Works has been taken up in respect of five divisions in Mysore Circle at a
cost of Rs. 95 Cr. Work in progress has been of the order of Rs. 53 Cr. and the
balance is expected to be achieved by the January 2003.
The divisional officers are taking up new capital works. Prioritising the capital works
has been in progress lately since resources have been a constraint. Works that show
faster payback period are being emphasized.
All efforts are being made for improvement of quality of power supply in rural areas
by proper and periodic maintenance of distribution lines, DTCs and jungle
clearance and undertaking pre-monsoon inspection. The field officers have been
directed to identify the low voltage pockets in their area and draw up action plan
to over come this.
3.4.3 Reply HESCOM:
The earlier allotment of 14.562 MU per day to HESCOM has been revised to 17.02
MU per day from Septermber 23, 2002. At present power supply to rural feeders is
being regulated to 6 hours per day instead of 8 hours of 3 phase supply per day
and 12 % of the rural feeders feed 3 phase supply for less than 6 hours due to (a)
Over loading of stations (b) Inadequate switchgear (c) Unscheduled load shedding
by KPTCL. However, steps are being taken for up-gradation of 33 kV sub-stations to
110 kV stations, providing additional power transformers, augmentation of power
transformer capacity, providing additional switchgear etc in order to improve the
quality of supply. Most of the above works are taken up by KPTCL and works are
under progress.
3.4.4 Reply GESCOM:
To prove its commitment on improving the quality of supply and service to its
consumers GESCOM has also set ambitious targets for itself for FY 2002-03. At the
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 334
outset it would be prudent to emphasise that to improve the quality of supply from
a level so inadequate to what is desirable needs significant effort, investment and
time. Results too will not be very forthcoming in the initial phases although the
efforts will reap rich dividends in the near future.
As many initiatives would require significant investments and hence depend on the
resources available to GESCOM. While some of the resources can be raised from
the outside agencies, internal resources would be important and hence tariff
increase and rationalization process has to proceed in conjunction with the
investments for improving quality of supply. GESCOM has established targets on a
division-wise basis for FY 2002-03
GESCOM intends to install additional transformers to manage the problem of
overloading and for improving voltage profile.
Significant efforts have been made by GESCOM in improving the quality of supply
and related infrastructure. GESCOM would like to ensure the Commission that
intensive efforts would continue in this direction in the future.
It is planned to take two feeder i.e. Yergera feeder (Raichur Division) and Srinivas
Saradgi feeder (Gulbarga division) for complete standardization on a turnkey basis.
Initiatives are being undertaken to improve the voltage profile in several divisions
including Gulbarga, Koppal, Hospet and Bellary .A comprehensive proposal has
been prepared under the APDRP scheme for improvement in quality of supply in
rural areas.
GESCOM has 24-hour complaint centers functioning in cities of Gulbarga, Bellary
and Raichur. It is envisaged to operationalize complaint centers in cities of Bidar
and Koppal. GESCOM has also initiated preventive measures to reduce accidents.
3.5 Comments of KERC on the Replies:
3.5.1 Comments of KERC on the Replies of KPTCL
In order that it will be easy for KPTCL to submit the data, the commission evolved,
four formats for furnishing data in respect of line interruptions, major equipment
failure details, Accidents and Bus voltage in select locations.
There is delay in furnishing the information by KPTCL. Only after continuous follow up
KPTCL has started furnishing the data in the specific formats. However the formats
are not properly completed. The Commission is analysing these reports.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 335
3.5.2 Comments of KERC on the Reply of ESCOMs
In all the public hearings in connection with tariff filing, the consumers are
expressing their dis-satisfaction at the number of interruptions, low voltages and
poor quality of supply. The efforts made by ESCOMs to improve the quality of
supply are not satisfactorily. The rural consumers especially the IP set consumers are
vociferous in their representation that they are not getting continuous three phase
power supply at least for 4 to 5 hours per day. The ESCOMs have expressed that
the rationing of energy has played a great role in the increased number of
interruptions and consumer dissatisfaction. The ESCOMs have expressed their
difficulty in completion of planned works in distribution system due to fund crunch
and constraint in budget allocation. The improvement works have suffered to a
great extent. The Commission notes that there is no substantial improvement in
reduction of LT to HT ratio, which would play a great role in reduction of
interruptions, improvement in voltage and loss reduction. As per the details
available in the Commission, the progress made in FY03 is marginal. Even now, the
LT to HT ratio is more than 2.5% and is nearly 4% in some ESCOMs. Even though the
improvement works are reported to have been taken up in some Circles under
APDRP proper implementation/monitoring in terms of agreement under APDRP
needs to done. The compliance/replies of MESCOM and HESCOM to the directions
are very inadequate. GESCOM has set some targets for easing of over loaded
conditions of distribution transformers. But while the transformers over loaded are
about 1650 the target for FY03 is a dismal 415 and achievement till August 02 is 374.
The targets are very inadequate compared to the number of over loaded
transformers.
A directive was issued to all the ESCOMs on 8.8.02 to monitor and work out the
interruption level initially in 46 towns and cities by down loading data from ETV
meters of 11 KV feeders through MRIs and the same has not been complied with.
Even though BESCOM has reported that they have taken action to out source the
task, further details are not available. Subsequently, during the month of November
02, the Commission has issued formats for performance evaluation and bench
marking to all the ESCOMs. These formats encompass most of the directives under
quality of service issued in Tariff Order 2000 such as interruptions, duration of
interruption, etc. The Commission has directed ESCOMs to furnish the details
starting from the month of November 02 to be reported by 15th of succeeding
month. The time schedule has not been maintained by the ESCOMs. But the
details worked out seem to be not in order and the base line parameter are yet to
be finalised.
Regarding EHT & HT capacitor banks, the same shall be maintained in working
condition at full capacity for better voltage maintenance. Regarding complaint
handling, the consumers in some hearings objected for not keeping up with the
standards laid down in Standards of Performance.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 336
Even though there is fall in number of accidents in BESCOM, the number of fatal
accidents have increased from 47 in November 01 to 58 in the corresponding
period in FY03. MESCOM has accounted for 45 fatal accidents in FY03 till
November. In case of HESCOM the total number of accidents and also the number
of fatal accidents have increased. In GESCOM the number of accidents has
increased, the number of persons met with fatal accidents is 33 as at the end of
Nov 02 when compared 30 fatal accidents during corresponding month of the
previous year. The Commission notes that the remedial action to minimise
accidents by ESCOMs is inadequate.
In conclusion, Commission observes that there is no compliance in this directive by
the ESCOMs. The low voltage packets shall be identified and specific time bound
action programme shall be provided to the Commission.
4.0 Directive on Distribution Transformer Failure (as in Tariff Order 2000)
4.1 The directive is about reducing the distribution transformer failures and restricting
the same to 5% in urban areas and to 12% in rural areas and to reward the staff who
perform better and to take action on officials/officers who disregard this work
leading to higher failure.
4.2 Comments of KERC in Tariff Order 2002 (Page No. 47)
The Commission is happy to note that the failure rate of distribution transformers has
come down in the State as a whole to 19% in FY02 in comparison with 22.3% in the
previous year. KPTCL shall take action to reduce the failure rate by 4 % during FY03.
4.3 Replies of ESCOMs in the Current Filing:
4.3.1 Reply of BESCOM:
The Transformer failure rate in Bangalore City is Zero, but there is no reduction in
failure of transformers in rural areas in spite of maintenance works being carried out.
As per the above analysis, the main reason for the same is the IP sets regularized
under ATL, reduced hours of 3phase supply leading to no diversity and use of
condensers during rostered supply.
Failures are also due to short circuit of LT distribution lines and failures due to
overload and other reasons. To bring down the failures due to these reasons, the
following measures are taken.
The BESCOM has issued instructions to all EEE’s to submit action plan for reduction of
failure of DT’s identifying worst sub-division and worst feeder. All divisions have
submitted estimates for maintenance of DT centres like providing DOLO/HG Fuse
units / LTP Kits / Grounding / Las / Topping of oil / New lugs / Lead wires / spacers /
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 337
Intermediate poles etc. The materials are being supplied and T.C. maintenance is
being insisted. Shortage of skilled staff like Section Officers/mechanics is also a
deterrent factor. Additional T.C’s are also being installed to reduce the over
loading.
The maintenance of 11 KV feeders where the DT failures rate is high is taken on
priority.
In order to address the problem, numbers of feeders have been selected per sub-
division where failure rate is high and needful remedial measures are taken up.
The scheme of incentives prepared by M/s. PWC for the performance of entire sub-
division is being examined
4.3.2 Reply of MESCOM:
As observed by the Commission, the failure rates of certain divisions in Mescom was
more than 30% - Channarayapatna, Sagar and Chamarajanagara.
The existing systems and procedures in the Company do not capture the
information regarding the Distribution Transformer Failure rates, as the Corporate
Office would like it to be.
A plan has been devised to capture information, report them in the proper format,
and then analyse the reasons for the same.
In some division the failure rate of less than 10%, in some divisions it is in the range of
10-15%. C.R. Patna is with a high figure of 18%. However all out efforts are being
made to ensure the failures are kept to bare minimum.
At the end of year the distribution failure rates will be reviewed and suitable cash
award will be thought of for the outstanding divisions.
4.3.3 Reply of HESCOM:
There are 44938 DTCs in HESCOM. The Corporate Office is regularly monitoring the
failures division-wise and action is taken to analyse the reason for failures. The
analysis reveals that most of the failures are caused due to single phasing,
overloading during peak hours ad unscheduled load shedding on the rural feeders.
In order to curtail the failure rates remedial measures are being taken.
4.3.4 Reply of GESCOM:
GESCOM has inherited a high transformer failure rate caused due to overloading of
transformers, maintenance practices, purchase procedures etc. It would however
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 338
like to bring to the attention of the Hon’ble Commission the fact that improvement
would be gradual and also require measures such as investments, discipline in
consumers on managing their demand etc. GESCOM has established ambitious
targets for itself for FY 2002-03 and is measuring failure rate on a monthly basis and
making efforts to reduce the failure rate.
GESCOM intends to put a transformer information monitoring system in place to
track down the reasons for failure of transformers. It is also intended to take-up a
drive for repair of transformers.
4.4 Comments of KERC
With the data furnished to the Commission by the ESCOMs till the end of November
2002, it is found that there is no failure of transformers in BMAZ of BESCOM. But the
over all reduction in failure rate in BESCOM is very marginal. It is 11.33% as against
11.96% found during the corresponding month of previous year. In MESCOM and
HESCOM the failure rate has gone up by about 0.6% and it is at 13.1% and 12.7%
respectively. In GESCOM even though there is fall in failure rate as at the end of
November 2002 in comparison with the corresponding month of previous year. The
rate of failure is high @15%. This may be because of more number of over loaded
transformers in GESCOM. It is stated that the failure is contributed by ATL
installations also. The installations added in ATL especially the IP sets are yet to be
provided with infrastructure even though the development charges have been
collected. KPTCL had assured to complete the infrastructure work within six months
in April 02. In the Tariff Order 2002, the Commission had directed that the
transformer failures should be brought down by another 4% from 19% found during
FY02 for the entire state. It is obvious that this is not complied with. The failure
analysis is to be taken up seriously by the ESCOMs and necessary MIS is to be
developed to monitor and minimise the failures.
5.0 Directive on Capital works programme: (as in Tariff Order 2000 Page No. 84)
5.1 The directive covered earmarking of funds for improving the T&D system, time
bound action plan for improving T&D in rural areas, prioritising the capital works,
realistic project cost estimates, benchmarking of system parameters, interest
charging, maintenance of cost registers, preparation of completion reports, action
plan for enhancing safety etc.
5.2 Comments of KERC in Tariff Order 2002 (Page No. 50)
There is no improvement in preparation of realistic estimates, benchmarking and
also the physical progress of works is very much less when compared to the targets.
KPTCL should address the issues impeding the progress as substantial investment is
involved lest the T&D loss reduction and quality improvement programmes suffer a
setback.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 339
5.3 Reply of KPTCL in the Current Filing:
Technical Co-ordination Committee (TCC) which was constituted as per
Government Order DE 33 PSR 2002 dated 12-07-2002 has approved Power System
Study Report prepared by M/s. PRDCL on 9th August 2002
As TCC has approved the PRDCL report, the new works will be prioritised as per the
report and will be taken up for execution based on earmarked Capital expenditure
as per FRP. KERC vide letter No.X/02/01/1432 dated 04-09-2002 has indicated that
works are to be prioritised even when budget is restricted and that the works with
higher BCR and Energy Savings is taken up on priority after approval by the
Commission.
As PRDCL report has been approved during the month of August 2002, action will
be taken to prepare the priority list of new works to be taken up for future years to
match the FRP.
Further, in this regard Capital expenditure and Budget provision for 2003-04 has to
be provided for all on-going works so as to complete the same.
The DPR’s are prepared on realistic basis for establishing stations for which lands are
available after duly conducting the survey for Transmission line from Date of Issue of
Circular by Corporate Office. DPR’s prepared prior to 25-08-2002 and for which
already the work is in progress, action is taken to revise the DPR as per actuals on
completion of the work, if there is any variation / deviation in estimated / DPR cost.
Circular instructions have been issued to field staff for documenting the system
parameters to arrive at benefits derived due to commissioning of new sub-stations.
DPR’s approved for Transmission works by Corporate Office includes IDC and in this
regard necessary circulars are issued.
It is intimated by the Major Works Units that 43 completion reports are to be
received from the field. Instructions are being issued in this regard to prepare the
completion reports immediately.
Further, all the Major Works units have intimated that the Cost Registers have been
posted up to September 2002.
As explained in para No.3 on the directive of Quality of Service, the status of the
Quality of Service including the details of accidents occurred, etc., on month to
month basis can be reviewed by the information and the respective Transmission
wings are directed to take corrective steps in order to enhance safety.
Power System Studies are conducted by M/s. PRDCL and has identified new
stations, Transmission lines, Augmentation of station and strengthening of existing
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 340
Transmission Network and has furnished the yearly phased implementation up to
2007 as a need based programme to achieve the parameters as envisaged by the
KERC. Due to restriction in the fund availability for Capital Expenditure, execution of
works as per system study report will have to be deferred / postponed and hence, it
will not be possible to achieve the desired results as per the study report.
5.4 Reply of ESCOMs in Current Filing:
5.4.1 Reply of BESCOM:
The budget allocation for 2002-03 in respect of ESCOM’s was furnished by KPTCL.
The allocated budget for BESCOM for the year 2002-03 was Rs.163.58 crores. As per
the directions of GOK vide MTFB 2003-06, due to the limitations of Borrowings the
budget allocation has been reduced to Rs.108.71 crores.
Considering the procurement action already taken, materials on stock and
metering materials required, there is very little Capital budget for major initiatives
under E&I.
Project cost will be on realistic basis in distribution sector.
Documentation of Bench Marking of parameters is being done & will be submitted
to the Commission after validating the Data received from the field units.
Instructions have been issued to update cost Registers & to submit CRs as soon as
the works are completed.
BESCOM has taken note of Commission’s directive that no work estimated to cost
more than 1.00 lakh will be awarded without going through a process of
competitive bidding.
There is continuous efforts & commitment of BESCOM to improve T&D system in Rural
Areas by providing additional TCs, reconductoring, New 11KV lines etc. and the
data provided earlier indicates the increase quantum of 11KV lines added in the
current year
5.4.2 Reply of MESCOM
MESCOM in its endeavour to provide quality supply to its consumers seeks to make
prudent capital investments.
GoK as part of FRP has approved investment plan especially the size of investment
for various activities. Mescom will provide a perspective plan on investments
covering information required by the Commission.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 341
The Capital Works Programme is being drawn up for all the Divisions so that
regulation of 6% is maintained at the distant LT point from DTC end. Further works for
energisation of Hamlets, Harijan Basthies, Tribal Colonies, Water Works etc., is being
taken up on priority.
Works to reduce energy loss of the feeders to be below 15% is also being planned.
The priority area for Mescom is loss reduction and rural electrification and metering.
Documentation of Bench Marking of parameters is being carried out and will be
submitted to the Hon’ble Commission after validating the Data received from the
field units.
Instructions have been issued to update cost registers & to submit cost registers as
soon as the works are completed.
MESCOM has taken note of Hon’ble Commission’s directive that no work estimated
to cost more than Rs.1.00 lakh should be awarded without going through a process
of competitive bidding.
5.4.3 Reply of HESCOM:
The steps taken by HESCOM have been as follows:
The budget allocation for 2002-03 in respect of ESCOMs was furnished by KPTCL to
the Hon’ble Commission. The allocated budget for HESCOM for the year 2002-03
was Rs.124.81 Cr. As per the directions of GOK vide MTFB 2003-06, due to the
limitations of Borrowings the budget allocation has been reduced to Rs.120.75 Cr.
Capital works are prioritized based on the requirement of such works for
improvement of the distribution system. The prioritization of capital works shall be
submitted to the KERC for approval.
The sub station works in the circles of Belgaum, Hubli, Bijapur are to be taken up on
priority in order to improve the quality of power supply:
Further 24 Nos.additional 33 KV sub stations are under construction and are
targeted for commissioning by March, 2003.
The estimated cost for distribution works is always being arrived at based on field
survey and application of the latest schedule of rates.
1. HESCOM is making efforts to prepare Project cost estimates on a realistic
basis
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 342
2. Documentation of Bench Marking of parameters is being done & will be
submitted to the Hon’ble Commission after validating the Data received
from the field units.
3. Efforts are being initiated to update and submit cost registers as soon as the
works are completed.
4. HESCOM has taken note and will follow Hon’ble Commission’s directive that
no work estimated to cost more than Rs.1.00 lakh should be awarded
without going through a process of competitive bidding.
5. There is continuous effort and commitment of HESCOM to improve T&D
system in Rural Areas by providing additional TCs, reconductoring, new 11KV
lines etc.
6. HESCOM wishes to invest an amount of Rs. 186 Cr for the year FY03 under
APDRP, the 50% of the amount will be provided by the GoI and the
remaining 50% will be borne by HESCOM. HESCOM requests the Hon’ble
Commission to allow the debt servicing cost on borrowings to fund such
capital investments.
5.4.4 Reply of GESCOM:
The process of evolving independent priorities and capital works programme for
each of the ESCOM’s is not yet completed and the targets and amount available is
provided by the KPTCL. For FY 2002-03, KPTCL had initially indicated a budget
provision of Rs. 94.18 Cr. for the GESCOM. However, on October 1, 2002, the KPTCL
has indicated a revised budget provision of Rs. 57.97 Cr, after considering the
limitation of borrowings to Rs. 650 Cr.
The actual capital expenditure till September 2002 is Rs. 30.16 Cr. The balance
budget provision available to GESCOM is Rs. 27.83 Cr. While GESCOM is in process
of evolving a proper allocation for the remaining months considering the substantial
reduction, an indicative programme is as provided below.
GESCOM has understood the concerns of the Hon’ble Commission provided under
this directive and would accordingly internalise them when it is able to formulate an
independent capital works programme. In order to minimize the cost of inventory
build-up and to reduce delays in procuring material, it is proposed to execute
projects on a turnkey basis to the extent possible.
5.5 Comments of KERC On Replies: KPTCL reply:
In spite of the specific directives from the Commission, prioritisation of works are not
being done, the estimates in respect of works are not being done, the estimates in
respect of the projects continue to be prepared unrealistically, project reports
continue to be prepared without being based on the field survey, bench marking
of important parameters in the project areas is not being adhered to. Thus no
serious efforts are being made to comply with the directives.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 343
5.6 Comments of KERC on the Replies of ESCOMs
ESCOMs have furnished replies in a very general way and have expressed that the
budget constraints for FY03 were preventing taking up major initiatives. There is no
such constraint for FY04.
6.0 Directive on Metering in Tariff Order 2000 (Page No. 132)
6.1 The directive is on the metering programme of Un-metered installations BJ/KJ, IP
sets and Streetlights.. Regarding metering of BJ/KJ installations the Commission
directed KPTCL to first examine the options available in order to identify possible
alternatives to universal metering of all BJ installations and on metering of IP sets
and street lights and provision of pre-paid meters to domestic consumers.
6.2 Comments of KERC in Tariff Order 2002 (page No. 51)
KPTCL has not complied with the Commission's directives to examine the options
available in respect of metering BJ/KJ installations. The actual progress in metering
is very poor.
KPTCL has not taken any action so far on the provision of pre-paid meters for
domestic consumers.
6.3 Replies of ESCOMs in the Current Filing:
6.3.1 Reply of BESCOM:
The metering programme has been reviewed and a revised programme has been
sent to GoK, for their kind perusal keeping in view the universal metering policy
already approved by GoK.
Metering of Bhagyajyothi/ Kutirajyothi: The number of Bhagyajyothi and Kutirajyothi
(BJ/KJ) installations as on June 1, 2002 is 5,33,328 and the amount required to meter
all these installations is expected to be Rs.56 Cr. It is proposed to take up this work
during next three and half years and complete by 2006. In the current year since
procurement action has just been initiated, meters can be provided to only 50,000
BJ/KJ connections, which are likely to be serviced.
Metering of Public Lighting: The total number of Streetlight Circuits to be metered in
BESCOM area is 29,918 and the approximate cost for providing the same will be
Rs.5.39Cr. Experience shows that metering to public streetlights is required more for
energy audit than for revenue improvement and even on undertaking an intensive
energy audit of these installations, the assessment will not make a substantial
impact on the total loss as street consumption comprises about 2 % of the total
sales.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 344
BESCOM proposes to give priority first to metering of public lighting circuits for
proper energy audit in the 13 Towns and Cities and in Bangalore City and to take
up metering in other rural areas later on so that correct energy audit can be done.
It is therefore planned to complete the entire activity over a period of three years.
Metering of IP sets: BESCOM is reviewing whether metering of all IP sets is to be
carried out to accurately to account for the consumption by IP sets considering the
huge investment of about Rs.140 Cr., which would be required. The sample
metering of distribution transformers predominantly feeding the IP sets is an
inexpensive method to accurately estimate the IP set consumption and to arrive at
the total losses in the system. The earlier methodology of IP consumption estimation
has been reviewed by the Hon’ble Commission with proper accounting of
distribution system losses in the LV network between DTC and IP Sets while
estimating IP set consumption and this procedure will be adopted in current year.
The recent experience of fixing meters to IP sets in some of the ESCOMs has shown
that the farmers resist the installation of meters to IP sets particularly in the dry
districts where deep well pump sets are more and IP set consumptions are high. The
survey done by CSMR, Hyderabad, has also indicated that consumer will resist the
installation of meters. Further, with the present flat rate per HP and metered IP set
tariff, there is no incentive for the farmers to accept metering. There is also a
suggestion that the metered tariff has to be constant for a period of 2 to 3 years, in
order to incentivise the metering programme as farmers are apprehensive that the
metered tariffs or policy of billing may get modified in the next tariff revision. Reports
have also indicated that the farmers have no paying capacity to pay the cost of
electricity supply. Some pilot studies are being undertaken in some Rural Distribution
pockets to assess the feasibility of having Grama Panchayats or Transformer user
associations.
In the backdrop of the above, the immediate necessity to meter all IP sets needs to
be reviewed and an action plan of metering of all IP sets will be drawn up
separately. Further metering of all IP sets connected to the urban feeders i.e.
coming under the categories LT -4a(ii), LT-4(c) (above 10 HP) and LT-4 (d)
(Agricultural and Plantation) will be taken up and provided with meters in the year
2003-04.
The metering programme will be finalized after receiving the views of GoK.
6.3.2 Reply of MESCOM:
Providing meter to BJ/KJ Installations in all the five divisions of Mysore Circle has
been taken up and so far, 49268 meters for BJ/KJ have been installed. Metering for
IP Sets has also been taken up for identified 9 out of 14 divisions in the jurisdiction of
MESCOM, and 63,086 nos. for IP sets have been installed. The entire process of IP set
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 345
metering will be completed in two more years’ time. However providing meters to
BJ/KJ Installations in other circles will be taken up in due course.
6.3.3 Reply of HESCOM:
As on July 15,2002 there were 22,1320 DC/MNR installations. HESCOM has replaced
138,536 meters till August 20,2002. Replacement of meters for balance 82,784
installations will be done after supply of new meters. Orders for purchase of 140,000
meters is already placed and the supply will commence from November 2002.
6.3.4 Reply of GESCOM:
GESCOM intends to conduct a careful analysis of the proposal for metering of
Bhagyajyothi/ Kutirajyothi installations as suggested by the Hon’ble Commission. In
the meanwhile, new Bhagyajyothi / Kutirajyothi installations, are being provided
connection with meters. GESCOM has also proposed to convert Bhagyajyothi /
Kutirajyothi installations with more than one bulb into domestic category. During the
current financial year 16,583 installations have been converted from Bhagyajyothi /
Kutirajyothi to domestic category.
The metering programme for street light circuits and urban IP sets has been
formulated. Presently, there are about 11,639 IP sets fed from urban feeders that
remain to be metered. It is proposed to provide meter to these consumers by the
end of December 2002. Currently, only 348 street light circuits out of 1,023 are
metered. It is proposed to meter all the remaining by the end of March 2003. There
are 5,159 street light circuits in rural area and majority of them are not metered. It is
proposed to meter all the remaining by the end of June 2003.
GESCOM would analyse the suggestion for introduction of prepaid meters and as a
first step may like to initiate a pilot before adopting the same on a large scale.
6. 4 Comments of KERC
The Commission observes that there is no substantial compliance to the directive.
ESCOMs have not studied the options available to identify the possible alternatives
to universal metering of all BJ/KJ installations. GESCOM have stated that they intend
to analyse the proposal for metering the BJ/KJ installations.
Regarding metering programme of IP sets and Streetlights the progress achieved as
on 15.2.2003 is as follows.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 346
Category MESCOM HESCOM GESCOM
Target Progress Target Progress Target Progress
IP sets 81960 73170 98185 37916 6186 4647
BJ/KJ 188483 109853 309627 194136 42200 36804
Streetlight 7000 8 0 0 1958 1958
Total 277443 183031 407812 232052 50344 43409
Regarding prepaid meters for domestic consumers GESCOM has stated that they
would analyse the suggestion and intend to initiate a pilot scheme. Other ESCOMs
have not come out with any response.
BESCOM has stated that they have submitted proposal on the metering
programme to the GoK and would finalize after receiving the views of GoK. They
have not furnished the progress made. The ESCOMs have to take a focused action
on metering the Urban IP sets on priority.
7.0 Directive on Codes and toll free telephone numbers (Page No.138 of Tariff Order
2000)
7.1 The directive is on several codes of practice, providing toll free telephones and
formulating a scheme to compensate the consumers put to loss by deficient supply.
7.2 Comments of KERC in Tariff Order 2002 (Page No. 53)
The Commission has approved the code of practice for payment of bills and the
same is sent for notification in Gazette.
Only BMAZ has been provided with Toll Free telephone.
The Commission has examined the entire issue of compensating the consumers put
to loss by deficient service in the light of the opinion expressed by KPTCL. The
Commission notes, however, that customers have complained bitterly about the
poor quality of service and the losses caused to them. The customers have to
patiently endure all the planned and unplanned load shedding and other
uncertaintities of the KPTCL and even pay penal charges for all lapses, deliberate or
otherwise, on the part of the Licensee. The Commission therefore reiterates its earlier
stand that the Licensee has to formulate a scheme for compensating consumers
put to loss by deficient supply and present the same to the Commission within one
month from the date of this Order.
7.3 Replies of ESCOMs
Toll free telephones are provided in some selected towns.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 347
The issue of formulating a scheme for compensating consumers who suffered loss
because of deficient supply is highly contentious. The question of whether there
was deficient supply, quantum of loss sustained, the machinery to adjudicate these
aspects is complicated and cannot be formulated in a scheme. A scheme that will
suit each case of loss sustained by the consumers is difficult to be formulated as it
depends on various factors. Each case has to be decided independently on its
own merit and based on the facts and circumstances of each case. The question
of payment of compensation arises only in case of proved negligence on the part
of ESCOMs or its officials and on proof of loss. Further, due to poor power availability
and system constraints it is practically not possible to adhere to the standard of
supply as the grid is operated in a closely-knit way and the grid condition is not
always stable and dependent upon power conditions within and outside the state
of Karnataka. However, ESCOMs are examining this issue.
7.4 Comments of KERC
Several codes have been issued by the Commission for implementation by the
ESCOMS.
Toll free telephones have been provided in some of the towns. The ESCOMs have to
provide the same in other towns also.
The Commission in Tariff Order 2002 had once again reiterated its earlier stand that
the licensees have to formulate a scheme for compensating consumers put to loss
by deficient supply and present the same with in one month and the same has not
complied with. The ESCOMs have not formulated the scheme for compensating the
consumers.
8.0 Direction in respect of power purchase plan (Merit Order Power
purchase page 71 of Tariff Order 2000)
8.1 The Commission directed that a plan for purchasing power on a merit order
basis must be prepared for each month at least 15 days before the
commencement of the month and got approved by the Commission.
8.2 Comments of KERC in Tariff Order 2002 (Page No.57)
The power purchase plan is usually received during the last week of the preceding
month.
8.3 Reply of KPTCL in the present filing
The monthly details of reservoirs capacity, schedules, etc. up to March 2003 are
submitted to the Commission vide this office letter No.KPTCL/B-36/4505/T/8/ 1883
dated 25-10-2002.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 348
Karnataka is facing bad monsoon and the availability from all Hydro reservoirs as on
1st October 2002 is reduced by 3211 MU. Therefore, there is difficulty in meeting the
energy sale indicated in ERC for the year 2002-03. Hence, priority is given to keep
the Hydro generation to the lowest permissible limits.
Further, the highest purchase cost is paid to the energy supplied by KAPS and mini
IPPs. However, it is difficult to regulate the generation from these units.
Merit order despatch is followed for purchase of power from major IPPs, such as,
Tannirbavi, Tata Power and Rayalseema. In case of JTPCL, even though their rates
(variable cost) are slightly higher that Tannirbavi, preference is given to JTPCL, since
it is a captive power plant and treated as co-generation. However, when the total
state demand is less than total availability including CGS share, JTPCL is requested
to back down (particularly between 00 hrs to 06 hrs).
8.4 Comments of KERC
The scheduled plan of power purchase from various sources for each month which
are supposed to be submitted on the 15th of the preceding month have not been
received regularly and of late, the monthly plan for power purchase are not at all
received in the Commission even though it has been stated in the ERC for FY 04
that monthly power purchase plan are being submitted regularly to the
Commission.
9.0 Directive on Disconnection of all unauthorised IP sets (As in Tariff Order 2000)
9.1 The Commission notes that KPTCL has been continuously extending the last date
for regularisation of unauthorised IP sets. This policy would lead to such IP set
holders not taking the KPTCL seriously at all. The continuance of unauthorised IP
sets would seriously affect the KPTCL’s efforts to recover the stipulated charges from
IP set consumers. The Commission, therefore, directs KPTCL not to extend the dead
line beyond that already announced. Once the dead line is over, KPTCL must
proceed to disconnect all unauthorised IP set connections that exist beyond that
date. Unauthoirsed IP set connections represent theft of energy that needs to be
dealt with accordingly. KPTCL should report to the Commission latest by 31st March,
2001 confirming that all unauthorised IP sets have been disconnected.
9.2 Comments of KERC in Tariff Order 2002 (Page 59)
The Commission notes the steps taken for regularisation of IP sets in terms of the
GOK policy. Now that the period for regularisation as per that policy is over, the
Commission directs that unauthorised IP sets be disconnected and action taken
under the anti-theft law.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 349
9.3 Replies of ESCOMs in the present Filing:
9.3.1 Reply of BESCOM:
Unauthorized IP sets have been disconnected during regularization drive held
between March and April 2002. The dead line for regularization was extended by
the GoK upto June 30, 2002. The Vigilance Wing has been strictly instructed to
conduct raids to create awareness among the unauthorized IP sets owners and the
services of NSS volunteers is being availed in this regard.
9.3.2 Reply of MESCOM:
Unauthorized IP sets have been disconnected during regularization drive held
between March and April 2002. The dead line for regularization was extended by
the GoK upto June 30, 2002. The Vigilance Wing has been strictly instructed to
conduct raids to create awareness among the unauthorized IP sets owners.
Vigilance Wing has prepared a plan of action for booking the cases under anti
theft low. Unauthorized IP sets are being regularized by following positive approach
of convincing the IP set owners of the provisions of Anti Theft Law.
9.3.3 Reply of HESCOM:
As on November 30,2001 10, 465 unauthorised IP sets were identified. 10,315 IP sets
were regularised as on November 30,2001. Further, during the ATL drive, 22,987 IP
sets were regularised between March 11, 2002 and April 9, 2002 and 3069 IP sets
were regularized from April 10, 2002 to June 30, 2002. Vigilance activities are being
carried out on a regular basis to check all categories of consumers for unauthorised
abstraction of power. A number of cognisable and non-cognisable cases have
been booked and back-billed.
9.3.4 Reply of GESCOM:
The GESCOM will further gear up its administrative and vigilance machinery for
disconnection of unauthorized IP set installations.
9.4 Comments of KERC:
It is learnt that the unauthorised IP Sets are coming up in large numbers in all the
ESCOMs even after the ATL came into force. The unauthorised IP Sets menace
should be dealt under the provisions of ATL. These unauthorised installations are
causing over loading of transformers, leading to transformer failures and large
interruptions.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 350
10.0 Directives on Studies to Taken Up (Page No. 145 of Tariff Order 2000)
10.1 The directive was to take up studies on Cost of service, Paying capacity of
subsidised categories, Manpower study, and Census of IP sets.
10.2 Comments of KERC in Tariff Order 2002 (Page No. 59)
KPTCL has given its comments on the methodology suggested by MECON in
respect of cost of service. They have been asked to propose a methodology that
should be adopted, in their opinion. However, the Commission has not received
any reply in this regard.
The results of the Studies on Paying capacity, Manpower study are yet to be
received by the Commission.
The copy of the report of the Survey conducted to identify open wells, bore wells,
defunct wells along with the study of no. of un-authorised IP sets said to have been
conducted by Dept. of Mines & Geology is yet to be submitted to the Commission.
In any event, the Commission had directed KPTCL to conduct the study based on
their own records. The total number of water sources identified by the Dept. of
Mines & Geology is much smaller than the number of even authorised IP
connections. Hence, reliance on such a survey defeats the very objective for which
the same has been ordered.
KPTCL survey should encompass the following information requirement:
i) No.of IP sets Transformer Centre-wise, O&M Section-wise, Sub-Division-wise along
with capacity, classifying the IP sets as bore wells, open wells, river bed, etc.
Unauthorized IP sets shall be identified.
ii) The survey should identify the transformer center, no.of IP sets connected to
transformer centers and identifying of the transformers and poles with distinct
codes.
KPTCL shall inform the Commission the Action Plan within two months.
10.3 Reply of KPTCL in the present filing
a) Cost of service : The report of M/s MECON on cost of service is examined in
depth and it is felt that further studies are required to determine the correctness of
certain parameters like load factor, co-incidence factor, etc. considered by the
Consultants. These issues are being discussed with the ESCOMs and the Consultants.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 351
On a preliminary examination of the report submitted by the consultants M/s
MECON in this regard, it is observed that the data collected for the study report is at
variance with actuals. Further, it is also observed that the methodology adopted by
the Consultants in assuming peak load, load factor are not agreeable by KPTCL.
Hence, comments of ESCOMs are sought on this issue vide letter No.KPTCL/B-
36/D/4533/ 1377-80 dated 09-08-2002.
b) Paying capacity: It is learnt that the study has been completed by the
Consultants, M/s CMSR, Hyderabad. The draft report has been received and
reviewed by Energy Department of Government of Karnataka and comments have
been sent to the Consultants.
c) Man power study: Prior to unbundling of KPTCL, approval was given by the
Corporation to entrust study on this subject to M/s National Productivity Council
(NPC) and quotation was obtained. While the negotiations regarding terms of
reference of study were on, it was proposed to have sample study in couple of
Divisions in order to know the implications of the study to be taken up by NPC for
the entire Organisation. As NPC commenced its preliminary work of identifying the
sample offices, the unbundling of the distribution work of KPTCL was finalised and 4
new DISCOMs were formed with effect from 01-06-2002. M/s NPC was requested to
select sample offices of Bangalore Electricity Supply Company Limited and the
process of identification is completed. The Consultants have sought 8 weeks time
for sample study and 10-12 months for complete study of KPTCL and the 4 newly
formed ESCOMs.
In the meanwhile, it was understood that the ESCOMs desired to have their own
methodology of workload study and Manpower planning. The ESCOMs are
embarking on plans to outsource activities, which will have a major impact on
Manpower requirement. As the ESCOMs are desirous of taking up studies on
Manpower Planning independently, KPTCL has, in the changed scenario, decided
to set up an 'Internal workload study and Manpower requirement committee' to
finalise the Manpower requirement.
10.4 Replies of ESCOMs
a)The study of the cost of service to each category of consumers was entrusted to
M/s. MECON, Bangalore and they have submitted the reports. The same has been
received on August 9, 2002. For the cost of service study expenses are classified into
demand, energy, and customer components based on principle of cost causation.
The costs, which vary with the KW demand imposed by the customers, are known
as demand costs and fixed in nature. Similarly, costs changing with the increase or
decrease in energy consumption are treated as variable costs. Customer costs vary
with number of customers. The above components categorized into fixed and
variable components are classified as demand and energy components. In the
absence of details in the respect of fixed and variable components, approximate
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 352
percentages will be used as assured. Regarding customer related expenditure like
billing and metering expenses will be estimated and allocated to respective
customer classes. The above report is under examination.
b) Paying capacity: - This study is entrusted to M/s. CMSR by KPTCL.
c) Manpower study: - We are yet to take up this study and are planning to
outsource various activities based on which the manpower requirement will be
finalized.
d) Census of IP sets to identify the number of existing IP sets under the category of
bore wells, open wells Nala, river etc. and also defunct wells.
It is proposed to outsource the above details since the O&M staff is pre-occupied
with many works, since the details obtained by the Mines & Geology Departments is
not acceptable to the Hon’ble Commission.
10.5 Comments of KERC on KPTCL reply
KPTCL has replied that ESCOMs are desirous of taking up the studies independently
and KPTCL has decided to set up internal workload study and manpower
requirement Committee to finalise the requirement of manpower. The schedule for
the same has not been furnished.
10.6 Comments of KERC on ESCOM replies:
There is no compliance with this directive.
The Commission has requested the GOK to outsource the study in respect of Cost of
Service to consultants.
The survey of IP sets as pointed out in Tariff Order 2000 and Tariff Order 2002, which
are long delayed is to be taken up and compliance reported to the Commission
within 3 months of this order.
The Commission has considered the M/s. CMSR report in this Order.
11.0 Directive on Street light metering:
11.1 While the water supply installations are already metered, the Commission
directs KPTCL to implement metering of the streetlight installations within a period of
one year.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 353
11.2 Comments of KERC in Tariff Order 2002 (Page No. 61)
Even though KPTCL was directed to meter all the streetlights within one year from
the date of Tariff Order 2000, KPTCL intends to take up metering as per Metering
Policy. As per Metering Policy, streetlights are expected to be completely metered
by FY04. KPTCL has scheduled to provide 16,000 meters in FY02. Details of the
actual progress are not available.
11.3 Replies of ESCOMs:
The directive would be implemented but more time is required for the
implementation as the KPTCL, which had taken up the responsibility of procurement
of meters, has not been able to do it so far. Action would be taken at the level of
ESCOMs hereafter to ensure timely procurement and installation of meters.
11.4 Comments OF KERC:
The directive is partially complied by GESCOM. The other ESCOMs are yet to start
the metering of streetlights.
12.0 Directive on Solar water Heaters (Page No. 131)
12.1 KPTCL is directed to conduct a detailed study to estimate the actual quantity
of benefit to the system as a result of installation of solar water heaters.
12.2 Comments of KERC inTariff Order 2002 (Page No. 64)
KPTCL has submitted a report the Study is limited to only Bangalore city. The study is
incomplete and is not completely in line with the directions of the Commission. The
purpose of the study directed by the Commission was to determine the extent to
which installation of solar water heaters contribute to reducing the peak demand
and the study should provide a scientific basis for any rebate to be given to the
consumers with solar water heaters. The focus of the study should be more on the
technical issues of the directives issued by the Commission.
12.3 Reply of ESCOMs:
This study report of M/s. PRDCL is furnished to the Commission.
12.4 Comments of KERC:
The Commission notes the compliance with the directive.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 354
13.0 Directive on billing of LT 4(c) category IP sets:
13.1 Commission notes that though the earlier LT-4(C) category pertaining to
private horticultural nurseries, coffee, tea, coconut and areca nut plantations were
required to be charged on a metered per unit basis, KPTCL does not appear to
have implemented metered billing. The Commission directs KPTCL to ensure full
implementation of metered billing in all cases ordered by the Commission.
13.2 Comments of KERC in Tariff Order 2002 (Page No.65)
This directive appears to have not been implemented.
13.3 Replies of ESCOMs
13.3.1 Reply BESCOM:
There are 1823 private horticultural nurseries, Tea, Coconut and Arecanut
plantations earlier under LT 4(c) and now under LT 4(d) category and all these are
to be metered. This will be taken up on priority.
13.3.2 Reply of MESCOM: The task has been completed.
13.3.3 Reply of HESCOM: LT 4(c) metering is carried out.
13.3.4 Reply of GESCOM: The directions of the Hon’ble Commission have been
complied with.
13.4 Comments of KERC
While other ESCOMs have complied with the directive BESCOM is yet to initiate
action. The meters are to be read regularly and bills to be issued based on the
meter readings. Non-metering of this category of installations results in revenue loss.
14.0 Directive on IP sets under LT 4 (b)
14.1 The directed was to report to the Commission, within three months from the
date of the order, the number of consumers who have been classified as LT-4(b) in
terms of this order.
14.2 Comments of KERC in Tariff Order 2002 (Page No. 66)
Though KPTCL has reported the identification of these customers, there has been no
confirmation from KPTCL so far about whether all such consumers have been billed
as per the LT-4 (b) tariff and whether the sums so billed have been recovered.
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 355
14.3 Replies of ESCOMs:
14.3.1 Reply of BESCOM:
BESCOM has issued circulars to IP set consumers regarding self -declaration by the
farmers. Not all the consumers have returned the forms. A deadline was fixed to
obtain declarations before October 21,2002. As on the date of filing 406,183
numbers of declaration forms were issued, out of this only 1,21,856 numbers of
declarations forms have been received. It was found that 12,033 numbers of IP sets
could be classified under LT -4(b). Soon after the receipt of all the declaration,
necessary classification will be made and placed before the Hon’ble Commission.
14.3.2 Reply of MESCOM:
MESCOM has issued circulars to 1,87,450 IP set consumers regarding self-declaration
by the farmers. Out of which 68,079 have been received back duly filled. Based on
the declaration in the form, 3,767 consumers have been classified under LT – 4(b).
14.3.3 Reply of HESCOM:
HESCOM has issued circulars to IP set consumers regarding self -declaration by the
farmers. Not all the consumers have returned the forms. The exact numbers will be
known only after 31-12-2002 only.
14.3.4 Reply of GESCOM:
As on date, 492 consumers have been categorized under LT4 (b). GESCOM has
instructed all the field officers to issue declaration forms to IP set owners. At the
same time, the field staff has been asked to contact Income Tax and Commercial
Tax deportment to obtain a list of Income Tax and Commercial Tax payees.
Identification of IP set owners who are employees of State and Central
Government department / undertaking etc., is also in progress. The GESCOM feels
that it would in near future be able to complete the process of metered billing for LT
-4 (c).
GESCOM has also introduced an incentive scheme for linemen /assistant linemen
to motivate them to identify consumers falling under LT -4(B) category. The scheme
provides for payment of Rs.10 per installation identified and classified as LT-4 (b).
14.4 Comments of KERC:
The Commission feels that the identification of IP set consumers under LT 4(b) is not
properly handled by the ESCOMs. Necessary action is to be taken immediately and
billed accordingly
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 356
15.0 Directive on Remote meter reading of the 11KV feeder meters (Page No. 67 of
Tariff Order 2002):
15.1 The Commission has noted that there is no proper way of assessing the quality
of power supply at present. The Commission informed KPTCL during meeting held
on 12.10.2001 that since all the 11 kV feeders are installed with electronic load
survey meters, it should be possible to remotely read these meters to get the
parameters of numbers of hours of power supply and interruption, voltage, load,
etc., by installing modems, internet connections, etc. KPTCL has called for tenders
for this work. The Commission attaches great importance to this work and directs
KPTCL to complete the work in the shortest possible time.
15.2 Reply of KPTCL
There is a rethinking to incorporate SCADA features in the remote meter reading
mechanism and action is being taken accordingly.
15.3 Comments of KERC
KPTCL has been reporting differently on different occasions. Nothing has been
done to implement this directive. KPTCL is not committing a definite date for
implementation of the directive.
16.0 Directive on Time of the day metering (Page No. 99 of Tariff Order 2002):
16.1 Reply of KPTCL
Action is to be taken by the ESCOMs.
16.2 Comments of KERC
The directive is pending since December 00 and now KPTCL is stating that the
matter lies with the ESCOMs. The ESCOMs shall come up with the proposal within 3
months from the date of this Order.
17.0 Directive on Infrastructure Facilities to Installations regularised in the drive
before ATL: (Page No. 99 of Tariff Order 2002)
17.1 The Commission directs that infrastructure facilities for additional loads
regularised in regularisation drive in March-April 2002 before the ATL came into
force shall be brought on the system such as Changing of undersized conductor,
providing additional poles, installing additional transformers, installing meters to all
un-metered connections within six months.
17.2 Reply of ESCOMs: Nil
Karnataka Electricity Regulatory Commission Tariff Order 2003
Annexe-4 : Compliance with Directives Page 357
17.3 Comments of KERC:
Even though KPTCL in the 2002 Tariff hearings had committed to complete the work
of metering and providing infrastructure to the regularised installations with in 3
months the Commission allowed another 3 months time. In spite of this the work is
not completed though the necessary cost towards development of infrastructure
especially from IP set consumers. This was pointed out in the public hearings by the
objectors. The Commission directs that the work shall be completed within 3 months
and compliance reported to the Commission.