Upload
carina-amor-david-claveria
View
222
Download
0
Embed Size (px)
DESCRIPTION
JJJ
Citation preview
ARBITRATION PANEL DECISION
Complainant: Pampanga Energy Company (PEC)
Respondent: Construction Company (CC)
Case Number: Case No. 15-NNNNN
Panel Members: Claveria, Carina Amor D.
Pineda, Paul Christopher G.
Rogel, Angeline P.
The dispute involved in this case relates to an alleged breach of a construction contract
entered into by the parties. The complainant avers that respondent committed various defects in
the technical design and construction of their power station. On the other hand, respondent
claims it was owed large sums of money by complainant under the contract. In addition, the
respondent raises an issue which threatens the very core of the present arbitral process—that the
Tribunal has no jurisdiction over the matter at hand.
The Tribunal shall now resolve the issues presented before it.
I. THE PARTIES
Pampanga Energy Company (“PEC”), a Philippine company, is the owner of a power
station in Pampanga. Sometime in October 2012, PEC employed Construction Company (“CC”),
1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
also a Philippine company, to design, construct, commission, test, complete and hand over the
power station to it.
In mid-2013, disputes arose between the parties. PEC claimed that it is entitled to
liquidated damages while CC claimed numerous extensions of time which the complainant
refused to allow. It was alleged by CC that it was owed large sums of money by PEC under the
contract. As a counterclaim, complainant PEC claimed that there were many technical design
and construction defects in various parts of the project.
II. PROCEDURAL HISTORY
On November 4, 2013 PEC commenced arbitration proceedings against CC and filed a
Notice of Arbitration with the Hong Kong International Arbitration Centre (“HKIAC”). Fourteen
days later, on November 18, CC commenced its own arbitration proceedings against PEC and
submitted its Request for Arbitration to the Construction Industry Arbitration Commission
(“CIAC”).
On the same day, CC applied for an anti-suit injunction against the HKIAC proceedings
before the Regional Trial Court (“RTC”) of Manila. Such application was granted and
consequently, the injunction was issued on November 25, 2013.
CC subsequently served its answer before the HKIAC on November 29, 2013. CC
contended that this Arbitral Tribunal has no jurisdiction and that the RTC of Manila has issued
an anti-suit injunction which deserves utmost “respect” from us on the ground of equity.
III. PARTIES’ CONTENTIONS
1. The Respondent
Construction Company (CC) contends that since the case involves dispute arising from a
construction industry contract entered into by parties relating to constructions in the Philippines,
2
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
CIAC has original and exclusive jurisdiction. CC noted that jurisdiction is conferred by law and
cannot be defeated by the agreement of the parties. Since the jurisdiction of CIAC is conferred
by law, it cannot be subjected to any condition; nor can it be waived or diminished by the
stipulation, act or omission of the parties, as long as the parties agreed to submit their
construction contract dispute to arbitration, or if there is an arbitration clause in the construction
contract.
CC cites Section 4 of Executive Order No. 1008 which provides:
Sec. 4. Jurisdiction. The CIAC shall have original and exclusive
jurisdiction over disputes arising from, or connected with,
contracts entered into by parties involved in construction in the
Philippines, whether the dispute arises before or after the
completion of the contract, or after the abandonment or breach
thereof. These disputes may involve government or private
contracts. For the Board to acquire jurisdiction, the parties to a
dispute must agree to submit the same to voluntary arbitration.
CC stressed that in effect, this provision makes it clear that the only requirement for
CIAC to acquire jurisdiction is for the parties to agree to submit their dispute to voluntary
arbitration. Thus, when the parties agreed to be bound by the arbitration agreement, they were
deemed to have submitted themselves under the CIAC.
In its answer, CC also alleged that the waiver by the parties of applicable Philippine laws
such as Executive Order No. 1008 and Republic Act No. 9285 is invalid. According to CC, if the
parties have expressly agreed that the substantive law of the Philippines shall govern, they shall
not be permitted to divest the laws specifically mandated to govern them.
3
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
In the matter of the anti-suit injunction secured by CC before the RTC of Manila, CC
would want this Tribunal to respect said relief and dismiss respondent’s claim lodged before the
HKIAC. CC interposes the defense of equity that where the proceeding merely intended to
oppress and vex the other party, an anti-suit injunction must be recognized. CC emphasized that
in the principle of comity and reciprocity, an anti-suit injunction that has been granted by a court
of competent jurisdiction must be respected.
2. The Complainant
Meanwhile, in its submission before the Arbitral Tribunal, Pampanga Energy Company
(“PEC”) contended that CC made a distorted interpretation of the rulings of the Supreme Court
of the Philippines when it stated that only the CIAC has exclusive and original jurisdiction over
the dispute presented herein.
Citing the Philippine jurisprudence of China Chang Jiang Energy Corporation vs. Rosal
Infrastracture Builders1, PEC refuted respondent’s claims by stating that the CIAC does not
possess sole jurisdiction over construction disputes where parties have stipulated and filed for
arbitration in another forum. In said case, the Philippine High Court held that notwithstanding
the validity of Section 1, Article III, such does not mean that the parties may no longer stipulate
to submit their disputes to a different arbitral body. Instead, the law gives the parties an
alternative forum before whom they may submit their controversies.
PEC claims that for filing a Notice of Arbitration before the HKIAC several days before
the respondent filed for arbitration before the CIAC, this Tribunal has first acquired jurisdiction
on the matter. Also, the claimant submitted that under the doctrine of Kompetenz/Kompetenz,
the arbitral tribunal may rule on its own jurisdiction, including any objections with respect to the
existence or validity of the arbitration agreement.
1 G.R. No. 125706, 30 September 1996
4
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
1
As to the matter of anti-suit injunction issued by the RTC of Manila, the claimant argues
that such injunction may be validly disregarded by this Tribunal as the same is not a court of the
seat of arbitration. According to PEC, only the courts of Hong Kong may issue such order since
the seat of arbitration is Hong Kong, and not the Philippines.
IV. FINDINGS OF THE ARBITRAL TRIBUNAL
1. The tribunal has jurisdiction over the dispute
In resolving this dispute at hand, the tribunal must first answer the question whether it has
jurisdiction over the case since the other substantive issues raised in the pleadings are dependent
to whether or not jurisdiction lies in this tribunal.
True to the contentions of the respondent, the tribunal, based on the existing laws and
jurisprudence, must answer the question on jurisdiction in the affirmative.
In claiming that the tribunal has no jurisdiction in this case, the respondents cited
Philippine laws and jurisprudence. One of this is E.O. 1008, Creating an Arbitration Machinery
in the Construction Industry of the Philippines. The respondent pointed out Section 4 which
states:
The CIAC shall have original and exclusive jurisdiction over
disputes arising from, or connected with, contracts entered into by
parties involved in construction in the Philippines, whether the
dispute arises before or after the completion of the contract, or
after the abandonment or breach thereof. xxx
To further support their allegations that only the CIAC has original and exclusive
jurisdiction over all construction disputes in the Philippines, the respondents relied on the CIAC
Rules of Procedure Governing Construction Arbitration, particularly Section 1, Article III, (as
5
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
cited in China Chang Jiang vs. Rosal Infrastracture Builders, HUTAMA-RSEA Joint Operations,
Inc. v. Citra Metro Manila Tollways Corporation) to wit:
Effect of the Agreement to Arbitrate
Section 1. Submission to CIAC Jurisdiction – An arbitration clause
in a construction contract or a submission to arbitration of a
construction dispute shall be deemed an agreement to submit an
existing or future controversy to the CIAC jurisdiction,
notwithstanding the reference to a different arbitral institution or
arbitral body in such contract or submission. xxxx
However, the law should be reconciled with the existing jurisprudence governing
substantial issues involving jurisdiction in arbitral processes. It must be in the forefront of
everyone’s minds that in relying on jurisprudence, it must be accentuated that pronouncements of
the Court should not be served in a piece-meal fashion and that the parties should not single out
parts of the decision favorable to their position.
The tribunal finds solace in the case of China Chang Jiang vs. Rosal Infrastracture
Builders as cited by the petitioner.
In the abovementioned case, the Philippine Supreme Court enunciated:
“Now that Section 1, Article III, as amended, is submitted to test in
the present petition, we rule to uphold its validity with full
certainty. However, this should not be understood to mean that the
parties may no longer stipulate to submit their disputes to a
different forum or arbitral body. Parties may continue to stipulate
as regards their preferred forum in case of voluntary arbitration,
6
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
but in so doing, they may not divest the CIAC of jurisdiction as
provided by law. xxx
xxx When the law provides that the Board acquires jurisdiction
when the parties to the contract agree to submit the same to
voluntary arbitration, the law in effect, automatically gives the
parties an alternative forum before whom they may submit their
disputes. That alternative forum is the CIAC. This, to the mind of
the Court, is the real spirit of E.O. No. 1008, as implemented by
Section 1, Article III of the CIAC Rules.
While both parties made reference to the case of China Chang Jiang, said case must be
read in its entirety and not in a part and parcel form. While we agree with the respondent’s
contention that a mere agreement to arbitrate vests CIAC the jurisdiction to take over the case,
such is only true when parties have not previously agreed to submit their dispute in a particular
forum.2
Thus, the respondent’s reliance on HUTAMA-RSEA Joint Operations, Inc. vs. Citra
Metro Manila Tollways Corporation case is misplaced. In that case, the arbitration agreement in
the contract did not provide for an institution where parties may submit their construction
disputes. Said absence of a specific agreement on the appropriate institution/tribunal to handle
the case automatically vests CIAC of original and exclusive jurisdiction over the matter.
The factual milieu in the case of HUTAMA is not present in the issue submitted before
this Tribunal. In this case, it is clear that both parties agreed to submit their disputes to another
forum, particularly the HKIAC. Therefore, when CC and PEC previously agreed to submit
before the HKIAC tribunal, in effect, they have made CIAC as an alternative forum.
2 CHINA CHANG JIANG
7
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
2
At this point, it may be relevant to define the Doctrine of Adherence of Jurisdiction. This
rule states that once the jurisdiction of a court attaches, the court cannot be ousted by subsequent
happenings or events, although of a character that would have prevented jurisdiction from
attaching in the first instance; the court retains jurisdiction until it finally disposes of the case.3
In the normal course of proceedings, a court or tribunal acquires jurisdiction over the
person of the plaintiff through the submission of complaints or any initiatory pleading. When the
claimant first submitted its Notice of Arbitration before the Tribunal, in effect, HKIAC being the
agreed venue, already acquired jurisdiction. Applying the doctrine laid down in the China Chang
case, CIAC becomes merely an alternative forum.
In the same note, since HKIAC was first vested the authority to hear and determine the
case, under the Doctrine of Adherence of Jurisdiction, it shall retain the authority to hear such
until its final disposition. The mere objection of the respondents on jurisdiction is an event which
would not oust the HKIAC tribunal of the power to render proper resolution of this controversy.
Moreover, to further bolster this Tribunal’s jurisdiction in the present case, it is
noteworthy to examine the very arbitration agreement entered into by PEC and CC. The records
of this case provide:
By clause 31 of the engineering procurement and construction
contract, the parties agreed to the following:
“31.1 Any unresolved dispute shall be referred to and finally
resolved by arbitration administered by the Hong Kong
International Arbitration Centre under the Rules, except as
the Rules may be modified herein. The arbitration proceedings
3 REGINA ONGSIAKO REYES, Petitioner, vs. COMMISSION ON ELECTIONS and JOSEPH SOCORRO B. TAN
8
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
3
shall be conducted, and the award shall be rendered, in the English
language. The seat of arbitration shall be Hong Kong .
31.2 This clause and the parties’ agreement to arbitrate herein
shall be governed by the laws of Hong Kong.”
It is well emphasized that in arbitration proceedings, various laws, rules, and guidelines
in the arbitral proceedings are observed in an order of hierarchy4 as follows:
I. Arbitration Agreement
II. Arbitration Rules
III. National Laws
IV. International Arbitration Practice
V. International Treaties
It is submitted that this hierarchy guidelines will help the arbitration tribunal to determine
the existence and validity of arbitration agreements, jurisdiction, and granting the reliefs prayed
for by the parties.
As exemplified in the above enumeration, the top of the hierarchy is the Arbitration
Agreement, followed by Arbitration Rules, then by the National Laws, the International
Arbitration Practice and the International Treaties.
The Arbitration agreement is the underpinning for the regulatory framework governing
the private dispute resolution process5 and it is the law between the parties. The agreement, as a
binding stipulation between them, shall be followed by said parties in good faith. Since the
arbitration agreement between PEC and CC clearly provided that “Any unresolved dispute shall
4 Moses, The Principles and Practice of International Commercial Arbitration (2012), Second Ed., p. 6
5 Supra Note 4
9
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
456
be referred to and finally resolved by arbitration administered by the Hong Kong International
Arbitration Centre under the Rules, except as the Rules may be modified herein”, this stipulation
validly consented by the parties, is dictated not only by public policy and also by law that it be
faithfully recognized in any court to which this case is pending.
2. DOCTRINE OF SEPARABILITY IN RELATION TO ANTI-SUIT INJUNCTION
In reality, the present controversy actually involves two distinct contract in one
document. This is in conformity to the “Doctrine of Separability,” which treats an arbitration
agreement contained in a contract as a separate agreement from the contract itself.6
When the parties enter to a contract stipulating an agreement to arbitrate, they are in
effect concluding two separate agreements.7 Both the Laws of Philippine and Hong Kong
recognize this doctrine and are uniform in accepting and implementing this principle. This is
elucidated in the case of Gonzales vs. Climax Mining Ltd8 which held:
“The doctrine of separability, or severability as other writers call it,
enunciates that an arbitration agreement is independent of the main
contract. The arbitration agreement is to be treated as a separate
agreement and the arbitration agreement does not automatically
terminate when the contract of which it is part comes to an end.
The separability of the arbitration agreement is especially
significant to the determination of whether the invalidity of the
main contract also nullifies the arbitration clause. Indeed, the
doctrine denotes that the invalidity of the main contract, also
6 Greenberg, et al. International Commercial Arbitration – An Asia-Pacific Perspective (2010). First Ed. Par. 4.36, p. 155.7Id at Par. 4.47, p. 158.8 G.R. No. 161957, 22 January 2007.
10
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
789
10
referred to as the "container" contract, does not affect the validity
of the arbitration agreement. Irrespective of the fact that the main
contract is invalid, the arbitration clause/agreement still remains
valid and enforceable.
The separability of the arbitration clause is confirmed in Art. 16(1)
of the UNCITRAL Model Law and Art. 21(2) of the UNCITRAL
Arbitration Rules.”
In the same way the High Court of Hong Kong ruled:
“The problem with this argument is that it does not take into
account that the arbitration agreement contained in another
written agreement has a life of its own. The doctrine of
separability has now been enshrined in the Model Law and has
been fully accepted in case law in England and Hong Kong. x x x”
In effect, the arbitration clause contracted by the party is separate from the document
which it is contained, the law that will govern the arbitration and the contract must be separate. 9
The two agreements having different purpose, it is very clear that different law applies to each.10
Considering the premises, the agreement entered and expressly stipulated by the parties,
it can be now deduced that the engineering and procurement contract (EPC), which is the main
(construction) contract is governed by the Philippine law; while Clause 31, another separate and
distinct contract pertaining to the arbitration agreement, is governed by the law of Hong Kong.
9 Supra note 19 at Par. 4.50, p. 159.10Supra note 22 at Par. 4.50, pp. 159-160.
11
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
1112
The contention of CC as to the invalidity of the arbitration clause supported by the cases
held by the Supreme Court is misplaced. Considering that Hong Kong Law is the governing
decree over the Arbitration Agreement (Clause 31) and Philippine Law applies only to the EPC
Contract. Since the agreement not to apply E.O. No. 1008 and R.A. No. 9285 is contained in
Clause 31, judicial pronouncement and Philippine laws are no longer controlling.
Furthermore, the Philippine cases cited by CC are not similar to facts and circumstances
of the instant case. None of these cases portray a fact wherein the parties have chosen two
different laws to separately govern their main contract and their arbitration agreement.
As evidenced by paragraph 31.1 of the arbitration clause, both parties have intended to be
governed and be bound by the rules of HKIAC. And, to further clarify their intentions, they even
agreed to submit to the domestic laws of Hong Kong, in case an arbitration proceeding is
commenced, as what actually transpired in this case.
Considering the principle of doctrine of separability and its effect to the contract, the
claim of the respondent regarding the applicability of certain Philippine Laws supposedly
conferring jurisdiction to the CIAC is untenable, since it is Hong Kong Law, not Philippine Law,
which governs the Arbitration Agreement.
As to the matter of the Anti-suit injunction ordered by the Manila Court on November 25,
2013, the tribunal is in the opinion that the said order cannot stay, much less, intervene with the
proceedings of this Arbitral Tribunal in determining jurisdiction and deciding upon the merits of
the case.
The respondent’s prayer to recognize said anti-suit injunction order issued by the Manila
Regional Court on the basis of the Arbitration Ordinance of Hong Kong (CAP 609) stating that
12
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
the relief granted by courts outside Hong Kong should be respected is a fact in which this
tribunal cannot agree.
Indeed, there is a clear misinterpretation of the Arbitration Ordinance in connection with
the facts prevailing in this dispute. PEC and CC, as evidenced by their arbitration agreement,
have clearly agreed to set Hong Kong as the seat of arbitration. Being the seat of arbitration it
actually serves as the legal domicile of the arbitration.11 Therefore, it is only the courts of Hong
Kong that could provide interim reliefs, as in this case, the anti-suit injunction sought by the
respondent.
On the final note, this Tribunal, in finding that it has jurisdiction in this case, is guided by
an established principle (Kompetenz-kompetenz)12 in arbitration proceedings that arbitrators are
vested with the ability to rule on their own jurisdiction and such is almost fully accepted as a part
of a long founded practice in international arbitration.13
V. CONCLUSION
PREMISES CONSIDERED, with the failure of the respondent Construction Company to
prove that this Tribunal lacks jurisdiction to hear the dispute, the members of this Honorable
Tribunal hereby grants the petitioner Pampanga Energy Company’s prayer to continue with the
arbitral proceedings. The tribunal rules in the negative as to the recognition of the anti-suit
injunction filed by the respondent before the RTC of Manila.
This Tribunal orders the petitioner and respondent to file their respective memoranda to
support their position as to the merits of the case.
11 Belohlavek, Importance of the Seat of Arbitration in International Arbitration: Delocalization and Denationalization of Arbitration as an Outdated Myth, 31 ASA BULLETIN 2/2013 (JUNE), at p. 263.12 This empowers an arbitral tribunal to decide on any and all objections as to its own jurisdiction. This doctrine, which is followed in most jurisdictions, provides that arbitrators are competent to determine their own competence.13 Greenberg, et al. International Commercial Arbitration – An Asia-Pacific Perspective (2010). First Ed. Par. 5.46, p. 214. Supra note at p. 91.
13
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
13141516171819
SO ORDERED.
Rogel, Angeline P.
Chairman
Pineda, Paul Christopher G. Claveria, Carina Amor D.
Arbitrator Arbitrator
26th September 2015
14
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309