266
Annex‐A 1  ef:  11091801S Annex –A Technical Specifications for Diesel Generator No #5 BEN-GURION AIRPORT Israel Airport Authority Technical Specifications for Diesel Generator No #5 and chiller absorption 16/05/15 Nir.Z IAA Rev Tender Date Created By Approved By              

Annex –A Technical Specifications for Diesel Generator No #5 · C.5.11. Load Sharing Control ----- 83 C.6. Upgrading Existing Generators Synchronization Routing ‐ Optional 84

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Annex‐A1  

ef:  11091801S 

Annex –A Technical Specifications for Diesel Generator No #5

BEN-GURION AIRPORT

Israel Airport Authority

Technical Specifications for Diesel Generator No #5 and chiller absorption

16/05/15 Nir.Z IAA

Rev Tender Date Created By Approved By

 

 

 

 

 

 

 

 

 

 

 

 

 

Annex‐A2  

Contents

A. ChapterA:GENERALTERMS --------------------------------- 15

A.1. Introduction ----------------------------------------------------- 15

A.2. Projectphases --------------------------------------------------- 16

A.2.1. Phaseone–initialoperationwithlightfuel --------------- 16

A.2.2. Phasetwo(optional)–operationwithNG ----------------- 16

A.2.3. Phasethree(optional)–Co‐Generation -------------------- 16 

A.3. Projectschedule ------------------------------------------------ 17

A.3.1. Phaseone(SeesectionA2.1) --------------------------------- 17

A.3.2. Phasetwo(SeesectionA2.3) --------------------------------- 17

A.3.3. Phasethree(SeesectionA2.3) ------------------------------- 17

A.4. ScopeofServices&MajorPoints ---------------------------- 18

A.5. ConstructionSequence ---------------------------------------- 19

A.6. LiquidatedDamagesforDelay ------------------------------- 20

A.7. Contractor'sresponsibility ------------------------------------ 21

A.8. Projectlocationandenvironmentalconditions ----------- 21

A.9. ScopemajorItems: --------------------------------------------- 22

A.10. Facility&GasDieselEngineSpecification ------------------ 24

A.10.1. General ----------------------------------------------------------- 24

A.10.2. GasDieselGenerator: ------------------------------------------ 24

A.10.3. Emissions -------------------------------------------------------- 25

A.11. StandardsandRegulations ----------------------------------- 26

A.11.1. ApplicableInternationalStandard -------------------------- 26

A.12. Abbreviations --------------------------------------------------- 27

A.13. DocumentsFormat --------------------------------------------- 29

A.14. Language -------------------------------------------------------- 29

A.15. TechnicaldocumentsthatwillbesubmittedtotheContractor 30

A.16. VerificationbytheContractor ------------------------------- 30

A.16.1. Layoutverificationduringthebid --------------------------- 30

A.17. Contractor'sTechnicalSubmittalswithinthebid --------- 31

A.18. SubmittalsandShopdrawings ------------------------------- 33

A.18.1. ShopDrawings -------------------------------------------------- 33

A.18.2. Drawingidentificationscheme ------------------------------- 34

Annex‐A3  

A.19. Samples ---------------------------------------------------------- 35

A.20. Certification ----------------------------------------------------- 35

A.21. Documentation ------------------------------------------------- 36

A.22. Submittalsbeforefinalcompletion -------------------------- 36

A.23. Contractor'spersonnel ---------------------------------------- 37

A.23.1. Skilledlabor ----------------------------------------------------- 37

A.23.2. ProjectManagement ------------------------------------------- 37

A.23.3. Safetysupervisor ----------------------------------------------- 37

A.23.4. TechnicalAssistanceforgeneratorandabsorptionchiller 37

A.23.5. Local(Israeli)supportforgeneratorandchiller ---------- 38

A.23.6. UseofSubcontractors ----------------------------------------- 38

A.24. Training ---------------------------------------------------------- 39

A.24.1. GeneratorTrainingshallincludeasfollows: --------------- 39

A.24.2. AbsorptionLiquidChillerstraining ------------------------- 40

A.25. WarrantyandMaintenanceServices ----------------------- 41

A.25.1. General ----------------------------------------------------------- 41

A.25.2. Definitions ------------------------------------------------------- 42

A.25.3. WarrantyperiodforPhaseone ------------------------------ 44

A.25.4. Warrantyperiodforphase3 --------------------------------- 44

A.25.5. ServicesduringWarrantyPeriod ---------------------------- 45

A.25.6. SpareParts,SpecialToolsandConsumables -------------- 46

A.25.7. ResponsetimeandSLALiquidatedDamages -------------- 46

A.25.8. ServiceafterWarrantyPeriod(LTSA) ---------------------- 47

A.25.8.1. TechnicalSupportPeriod ------------------------------------- 47

A.25.8.2. MaintenancePeriod-------------------------------------------- 47

B. ChapterB‐EquipmentNumberingSystem ----------------- 49

B.1. Objectives -------------------------------------------------------- 49

B.2. NumberingScheme -------------------------------------------- 49

B.3. MarkingandLabeling ----------------------------------------- 50

B.4. SwitchboardLabeling ----------------------------------------- 50

B.5. CableLabeling -------------------------------------------------- 51

B.6. AuxiliaryEquipmentLabeling ------------------------------- 51

B.7. ConduitIdentification ----------------------------------------- 51

Annex‐A4  

C. ChapterC‐GeneratorTechnicalSpecification ------------- 52

C.1. General ----------------------------------------------------------- 52

C.1.1. GeneralDesign -------------------------------------------------- 52

C.1.2. EmissionsandNoiseLevels ----------------------------------- 55

C.1.3. NoiseLevels ----------------------------------------------------- 55

C.1.4. Vibrations ------------------------------------------------------- 56

C.2. AvailabilityandReliability------------------------------------ 56

C.3. MaintenanceAccess -------------------------------------------- 56

C.4. MechanicalDesign --------------------------------------------- 57

C.4.1. FuelSystem ------------------------------------------------------ 58

C.4.1.1. LiquidFuelSystem --------------------------------------------- 58

C.4.2. NaturalGasFuelSystem -------------------------------------- 60

C.4.3. ExhaustSystem ------------------------------------------------- 62

C.4.4. LubeOilSystem ------------------------------------------------- 63

C.4.5. AirStarting ------------------------------------------------------ 64

C.4.5.1. CompressedAirSystemforStartingGenerator ----------- 64

C.4.6. Blackstart ------------------------------------------------------- 67

C.4.7. CoolingSystems------------------------------------------------- 67

C.4.8. Keep‐WarmSystem -------------------------------------------- 67

C.4.9. Flywheel --------------------------------------------------------- 68

C.4.10. BarringDevice -------------------------------------------------- 68

C.4.11. ProtectiveDevices‐DieselorGasEngine ------------------- 68

C.4.12. Governor --------------------------------------------------------- 69

C.4.13. Accessories ------------------------------------------------------ 69

C.4.14. Shut‐OffValves -------------------------------------------------- 69

C.4.15. AnchorBolts ----------------------------------------------------- 69

C.5. Electricalandcontroldesign --------------------------------- 70

C.5.1. General ----------------------------------------------------------- 70

C.5.2. LocalSwitchboardsandControlPanels -------------------- 70

C.5.3. ControlPanel---------------------------------------------------- 70

C.5.4. WorkingStation ------------------------------------------------ 71

C.5.5. Historicaldata. ------------------------------------------------- 71

C.5.6. MotorControlCenter(MCC)seechapterE ---------------- 72

C.5.7. PLCpanel -------------------------------------------------------- 73

Annex‐A5  

C.5.7.1. PLCPanel -------------------------------------------------------- 73

C.5.7.2. SupplyVoltages ------------------------------------------------- 73

C.5.7.3. PLCComponents ------------------------------------------------ 73

C.5.7.4. CPUandI/OCardHousings(racks) ------------------------- 74

C.5.7.5. CommunicationInterfaces ------------------------------------ 74

C.5.7.6. Communications ------------------------------------------------ 74

C.5.7.7. PLCprogramming ---------------------------------------------- 75

C.5.8. Connectivity ----------------------------------------------------- 76

C.5.8.1. ConnectivitywithMainElectricalSystem ------------------ 76

C.5.8.2. Grounding ------------------------------------------------------- 77

C.5.8.3. ConnectivitywithmainSCADAsystem ---------------------- 77

C.5.8.4. Connectivitywithenvironmentsystem --------------------- 80

C.5.9. SynchronizingSystem ----------------------------------------- 81

C.5.9.1. AutomaticSynchronizer -------------------------------------- 81

C.5.9.2. SynchronizingRouting ---------------------------------------- 81

C.5.10. ProtectionSystem ---------------------------------------------- 82

C.5.11. LoadSharingControl ------------------------------------------ 83

C.6. UpgradingExistingGeneratorsSynchronizationRouting‐Optional 84

C.6.1. DescriptionoftheCurrentOperation ----------------------- 86

C.6.1.1. Case1:NoPowerSupplyfromIEC; -------------------------- 86

C.6.1.2. Case2:NopowersupplyfromIEC22kV; ------------------- 86

C.6.1.3. Case3:NopowersupplyfromIEC; --------------------------- 86

C.6.1.4. Case4:NopowersupplyfromIEC; --------------------------- 87

C.6.1.5. Case5:NopowersupplyfromIEC ---------------------------- 87

C.6.1.6. Case6:Electricaldistributionsystemisfedfromemergencygenerators 87

C.6.1.7. Case7:Electricaldistributionsystemisfedfromemergency generators 88

C.6.1.8. Case8:Peakshavingmodeisconsideredtobeasfollows: 88

D. ChapterD‐MediumVoltage ---------------------------------- 91

D.1. POWERTRANSFORMER -------------------------------------- 91

D.1.1. General ----------------------------------------------------------- 91

D.1.2. GeneralData: --------------------------------------------------- 91

Annex‐A6  

D.1.3. SupplyandInstallation ---------------------------------------- 91

D.1.4. Standards -------------------------------------------------------- 92

D.1.5. TransformerRatingsandOtherData ----------------------- 94

D.1.6. Losses ------------------------------------------------------------- 94

D.1.7. CoolingSystem -------------------------------------------------- 94

D.1.8. Tests -------------------------------------------------------------- 95

D.1.9. Structure --------------------------------------------------------- 98

D.1.10. Controlcabinetandwiring ----------------------------------- 99

D.1.11. Additionalaccessories --------------------------------------- 100

D.2. AUXILIARYTRANSFORMERS ------------------------------- 101

D.2.1. General --------------------------------------------------------- 101

D.2.2. Systemdata --------------------------------------------------- 101

D.2.3. Standards ------------------------------------------------------ 102

D.2.4. Electricaldata ------------------------------------------------ 103

D.2.5. Losses: ---------------------------------------------------------- 105

D.2.6. Construction -------------------------------------------------- 105

D.2.7. Testes ----------------------------------------------------------- 106

D.2.8. TypeTests ----------------------------------------------------- 106

D.2.9. RoutineTests -------------------------------------------------- 106

D.2.10. Accessories ---------------------------------------------------- 107

D.3. NEUTRALGROUNDINGRESISTOR ------------------------ 108

D.3.1. General --------------------------------------------------------- 108

D.3.2. Technicaldata ------------------------------------------------ 108

D.3.3. Enclosure ------------------------------------------------------ 109

D.3.4. CurrentTransformer ---------------------------------------- 109

D.3.5. Wiring ---------------------------------------------------------- 109

D.3.6. Grounding ----------------------------------------------------- 110

D.3.7. Tests ------------------------------------------------------------ 110

D.3.7.1. RoutineTests -------------------------------------------------- 110

D.3.7.2. DRAWINGS,DATA&MANUALS ---------------------------- 111

D.4. MVSwitch‐Gear ----------------------------------------------- 112

D.4.1. General --------------------------------------------------------- 112

D.4.2. Submittals ----------------------------------------------------- 112

D.4.3. Documents ----------------------------------------------------- 112

Annex‐A7  

D.4.4. QualityAssurance -------------------------------------------- 113

D.4.5. Delivery&Storage ------------------------------------------- 113

D.4.6. Coordination -------------------------------------------------- 114

D.4.7. InstallationandConnection -------------------------------- 114

D.4.8. Commissioning ------------------------------------------------ 114

D.5. MVswitchboardenclosures --------------------------------- 115

D.5.1. Standards ------------------------------------------------------ 115

D.5.2. Tests ------------------------------------------------------------ 119

D.5.3. Enclosuremetalwork ---------------------------------------- 120

D.5.4. Maincircuitconductorsandinsulators ------------------- 123

D.5.5. Switchboardratings(formetalcladtype) --------------- 124

D.5.6. Auxiliariesandcontrols ------------------------------------- 125

D.5.7. Heatingarrangementsinmetalcladswitchgear ------- 127

D.5.8. Calibration ---------------------------------------------------- 127

D.5.9. Firedetectionandextinguishing -------------------------- 127

D.6. CircuitBreakers ---------------------------------------------- 129

D.6.1. General --------------------------------------------------------- 129

D.6.2. Technicaldata ------------------------------------------------ 129

D.6.3. Circuitbreakersdesign -------------------------------------- 130

D.6.4. Auxiliaryequipment ----------------------------------------- 132

D.6.5. Groundingswitchesandgroundingarrangements ----- 132

D.6.6. CircuitBreakersfortransformerfeeding ----------------- 133

D.7. MVCurrentTransformers ----------------------------------- 134

D.7.1. General --------------------------------------------------------- 134

D.7.2. Constructionrequirements --------------------------------- 134

D.8. MVPotentialTransformers --------------------------------- 135

D.8.1. General --------------------------------------------------------- 135

D.8.2. Constructionrequirements --------------------------------- 135

D.9. SecondaryProtectionRelays ------------------------------- 137

D.9.1. GeneralRequirements --------------------------------------- 137

D.9.2. Calibration ---------------------------------------------------- 139

E. ChapterE:ElectricalSpecifications ---------------------- 140

E.1. Standardproducts ------------------------------------------- 140

E.2. StandardsandRegulations --------------------------------- 140

Annex‐A8  

E.3. Conduit --------------------------------------------------------- 141

E.3.1. Racewayandchannels -------------------------------------- 141

E.3.2. Surfacemountedconduits. ---------------------------------- 141

E.3.3. Surfacemountedducts -------------------------------------- 142

E.3.4. Undergroundconduits --------------------------------------- 142

E.3.5. Cabletrays,laddersbracketsandaccessories. ---------- 143

E.3.6. Protectiveconduitsfordeviceconnection ---------------- 143

E.4. Cablesandconductors --------------------------------------- 144

E.4.1. General --------------------------------------------------------- 144

E.4.2. Cablemarking ------------------------------------------------ 144

E.4.3. Packing -------------------------------------------------------- 144

E.4.4. LVPowercables ---------------------------------------------- 145

E.4.5. MVPowercables --------------------------------------------- 145

E.4.6. Fireresistantcable ------------------------------------------- 146

E.4.7. Controlcables ------------------------------------------------- 146

E.4.8. Analogsignalcables ----------------------------------------- 147

E.4.9. Coppercommunicationcables ----------------------------- 147

E.4.10. Fiberopticcables --------------------------------------------- 148

E.4.11. Cableaccessories --------------------------------------------- 149

E.4.12. Firebarriersandcables'fireprotections ----------------- 149

E.4.13. Fireresistantcablecoatingproperties:------------------- 149

E.5. ConnectingofElectricalFieldEquipment ---------------- 150

E.5.1. Finalcalibration ---------------------------------------------- 151

E.6. ElectricalSwitchboardsandpanels ----------------------- 151

E.6.1. GeneralDescription ------------------------------------------ 151

E.6.2. Climatecondition,StandardsandRegulations ---------- 151

E.6.3. Workshopdrawingssubmittal ----------------------------- 152

E.6.4. Construction -------------------------------------------------- 152

E.6.5. Switchboardsandpanels------------------------------------ 153

E.6.6. Colorsofbusbarsandwiringinboardsandpanels155

E.6.7. Markingonboards ----------------------------------------- 156

E.6.8. Cableconnection -------------------------------------------- 156

E.6.9. Factorytests ------------------------------------------------- 156

E.6.10. Miscellaneous ------------------------------------------------ 158

Annex‐A9  

E.7. Motorcontrolcenters(MCC) ----------------------------- 159

E.7.1. Generaldescription ---------------------------------------- 159

E.7.2. Submittals ---------------------------------------------------- 159

E.7.3. Qualityassurance ------------------------------------------ 159

E.7.4. Delivery&Storage ----------------------------------------- 159

E.7.5. Coordination ------------------------------------------------- 160

E.7.6. Buses ----------------------------------------------------------- 161

E.7.7. FunctionalFeatures ---------------------------------------- 161

E.7.8. MotorControllers ------------------------------------------- 162

E.7.9. VariableFrequencyControllers ------------------------- 163

E.8. CorrosionProtectionandPaintingSystem ----------- 164

E.8.1. Switchboardsandpanels --------------------------------- 164

E.8.2. EpoxyPaintSystem ----------------------------------------- 164

E.8.3. SyntheticPaintSystem ------------------------------------ 164

E.8.4. Ferrouspartsinsidebuildings -------------------------- 165

E.8.5. Ferrouspartsoutsidebuildings ------------------------ 165

E.8.6. Steelpiping --------------------------------------------------- 165

E.8.7. Galvanizedpipes -------------------------------------------- 165

E.8.8. Pipingcolors ------------------------------------------------- 165

E.8.9. Corrosionprotectionforconnectingaccessories --- 165

E.9. FireProtection ---------------------------------------------- 166

E.9.1. ElectricalPanelsfiresystem ----------------------------- 166

F. ChapterF:MECHNICALSECTION ------------------------ 167

F.1. General -------------------------------------------------------- 167

F.2. PipeWorkandFitting ------------------------------------- 167

F.2.1. General -------------------------------------------------------- 167

F.2.2. Pipingcoating ----------------------------------------------- 168

F.3. Welding ------------------------------------------------------- 169

F.3.1. WeldingQA/QC ---------------------------------------------- 169

F.3.2. References ---------------------------------------------------- 170

F.3.3. Submittals ---------------------------------------------------- 170

F.3.4. ProjectRecordDocuments ------------------------------- 170

F.4. Flanges -------------------------------------------------------- 170

F.5. SealWelding ------------------------------------------------- 171

Annex‐A10  

F.6. Bolts ------------------------------------------------------------ 171

F.7. BuildingPiping ---------------------------------------------- 172

F.8. AirVentsandLowPointDrains ------------------------- 173

F.9. Materialofpiping: ------------------------------------------ 173

F.10. MaterialofpipeFitting: ----------------------------------- 174

F.11. PipeSupportsandAnchors ------------------------------ 174

F.12. PipeInsulationProtectionSaddles --------------------- 175

F.13. PipeSleeves -------------------------------------------------- 175

F.14. FlashingSleeves --------------------------------------------- 175

F.15. Unions --------------------------------------------------------- 175

F.16. ScrewedJointsonSteelpiping --------------------------- 175

F.17. Pocketsinpipesforaccessories ------------------------- 176

F.18. PipePressureTesting ------------------------------------- 176

F.18.1. General: ------------------------------------------------------- 176

F.18.2. TestingBuriedPiping: ------------------------------------- 176

F.18.3. TestProcedures: -------------------------------------------- 177

F.18.4. TestingMedia: ----------------------------------------------- 178

F.18.5. TestRepairs: ------------------------------------------------- 178

F.18.6. TestRecords: ------------------------------------------------- 178

F.19. VALVES -------------------------------------------------------- 179

F.19.1. General -------------------------------------------------------- 179

F.19.2. GateValves --------------------------------------------------- 179

F.19.3. GlobeValves -------------------------------------------------- 179

F.19.4. GlobeValvesWithVariableOrifice --------------------- 179

F.19.5. CheckValves ------------------------------------------------- 179

F.19.6. AutomaticAirVents ---------------------------------------- 180

F.19.7. ReliefValves-------------------------------------------------- 180

F.19.8. ButterflyValves --------------------------------------------- 180

F.19.9. Strainers ------------------------------------------------------ 180

F.19.10. FlexibleConnections --------------------------------------- 180

F.19.11. Threewaycontrolvalves --------------------------------- 180

F.20. CentrifugaloraxialFans --------------------------------- 181

F.20.1. General: ------------------------------------------------------- 181

F.20.2. Ratings: ------------------------------------------------------- 181

Annex‐A11  

F.20.3. FanUnits: ----------------------------------------------------- 181

F.20.4. Housings: ----------------------------------------------------- 181

F.20.5. Wheels(forcent.Fans): ----------------------------------- 181

F.20.6. Motors: -------------------------------------------------------- 181

F.21. DuctWork ---------------------------------------------------- 182

F.21.1. SheetMetalDuctwork ------------------------------------- 182

F.21.2. DuctHangersSupports ------------------------------------ 183

F.21.3. FlexibleDuctwork ------------------------------------------ 183

F.21.4. FlexibleConnections --------------------------------------- 183

F.22. DuctAccessories -------------------------------------------- 184

F.22.1. General -------------------------------------------------------- 184

F.22.2. Grilles&Registers ------------------------------------------ 184

F.22.3. VolumeDampers(V.D) ------------------------------------ 184

F.22.4. Insulation ----------------------------------------------------- 185

F.23. MetersandGages ------------------------------------------- 185

F.23.1. TemperatureGages ---------------------------------------- 185

F.23.2. PressureGagesandFittings: ---------------------------- 186

G. ChapterG:AbsorptionLiquidChillers(Optional) -- 187

G.1. General: ------------------------------------------------------- 187

G.2. Scopeofwork ------------------------------------------------ 187

G.3. Processdata: ------------------------------------------------- 189

G.4. Siteconditions ----------------------------------------------- 190

G.5. Structureandcasing --------------------------------------- 190

G.6. Electricplant‐Controlsandsystemmanagement - 190

G.7. Testing -------------------------------------------------------- 191

G.8. Warranty ----------------------------------------------------- 191

G.9. Maintenance,Serviceandlifespan -------------------- 191

G.10. CentrifugalPumps ----------------------------------------- 192

G.10.1. General: ------------------------------------------------------- 192

G.10.2. DesignCriteria ---------------------------------------------- 192

G.10.3. Submittals ---------------------------------------------------- 192

G.10.4. Pump'sDescriptionandMaterials: -------------------- 193

G.10.5. Installation --------------------------------------------------- 194

G.10.6. Startup -------------------------------------------------------- 194

Annex‐A12  

G.11. COOLINGTOWER -------------------------------------------- 195

G.11.1. General -------------------------------------------------------- 195

G.11.2. Structure ------------------------------------------------------ 195

G.11.3. Fill -------------------------------------------------------------- 196

G.11.4. DriftEliminators -------------------------------------------- 196

G.11.5. SpeedReducers ---------------------------------------------- 196

G.11.6. Fan ------------------------------------------------------------- 197

G.11.7. Louvers -------------------------------------------------------- 197

G.11.8. Motor ---------------------------------------------------------- 197

G.11.9. DistributionSystem ---------------------------------------- 197

G.11.10. VibrationSensor -------------------------------------------- 198

G.11.11. FanDeck ------------------------------------------------------ 198

G.11.12. TowerAccess ------------------------------------------------- 198

G.11.13. Documentation ---------------------------------------------- 198

G.11.14. Performance ------------------------------------------------- 200

H. ChapterH:BasisofDesign–Environmentalsection 201

H.1. General -------------------------------------------------------- 201

H.2. Unitsofmeasurement ------------------------------------- 201

H.3. SITEINFORMATION ---------------------------------------- 202

H.3.1. ClimaticConditions ---------------------------------------- 202

H.3.2. Temperature ------------------------------------------------- 202

H.3.3. Humidity ------------------------------------------------------ 202

H.3.4. BarometricPressure --------------------------------------- 203

H.3.5. Wind ----------------------------------------------------------- 203

H.3.6. Rainfall -------------------------------------------------------- 203

H.3.7. SiteConditions ----------------------------------------------- 203

H.3.7.1. Elevations----------------------------------------------------- 203

H.3.7.2. Seismic -------------------------------------------------------- 203

H.3.8. ENVIRONMENTALPROTECTION ------------------------- 204

H.3.8.1. ExhaustEmissionLimits ---------------------------------- 204

H.3.8.2. WasteWaterEmissionConcentration ----------------- 204

H.3.8.3. Noiselevels --------------------------------------------------- 205

H.3.8.4. SandandDustStorms ------------------------------------- 205

Annex‐A13  

H.4. ATTACHMENTS ---------------------------------------------- 205

H.4.1. WINDDATA -------------------------------------------------- 205

H.5. MaximumMonthlyAveragesforParametersinEffluentsforUnrestrictedIrrigationandDischargetoRivers 207

I. ChapterI:Fuelsupplysystemtostandbydieselgenerator 209

I.1. General: ------------------------------------------------------- 209

This chapter is an appendix chapter C 209

I.2. Background -------------------------------------------------- 209

I.3. Basicdesign -------------------------------------------------- 209

I.4. Detaileddesign ---------------------------------------------- 210

I.5. Equipmentandmaterialsupply ------------------------ 210

I.6. Tanks ---------------------------------------------------------- 210

I.7. Pumps --------------------------------------------------------- 211

I.7.1. Piping ---------------------------------------------------------- 211

I.7.2. Valves ---------------------------------------------------------- 212

I.7.3. Siteinstallation --------------------------------------------- 213

I.8. Commissioning ---------------------------------------------- 213

I.9. Completion --------------------------------------------------- 214

I.10. Documentation ---------------------------------------------- 214

I.10.1. Services -------------------------------------------------------- 215

I.11. Applicablecodesandregulations ---------------------- 215

I.12. Generaloperatingandsafetydescription ------------ 215

I.12.1. Normalcondition ------------------------------------------- 215

I.13. Acceptance --------------------------------------------------- 216

I.14. Attachment --------------------------------------------------- 216

J. ChapterJ: AcceptanceTests ------------------------------ 217

J.1. GeneratorAcceptanceTests‐phase‐1 ---------------- 217

J.1.1. ShopTest(FAT) --------------------------------------------- 217

J.1.2. SiteTestProcedures --------------------------------------- 219

J.1.3. 24‐HoursSiteTestProcedures -------------------------- 220

J.1.4. SOAK‐7‐DaysSiteTest ------------------------------------ 222

J.2. AbsorptionchillerTests‐phase‐3 ---------------------- 223

Annex‐A14  

J.3. GuaranteedPerformanceandLiquidatedDamages 223

J.3.1. Phase1GasEnginePackageLiquidFuel ------------- 223

J.3.2. Phase2‐GasEnginePackageNaturalGasFuel ----- 225

J.3.3. Phase3‐IncludingChillerNaturalGasFuel ---------- 226

K. ChapterK‐.TenderGeneralForm ---------------------- 228

K.1. Guaranteedvalues ----------------------------------------- 228

K.1.1. General -------------------------------------------------------- 228

K.1.2. GuaranteedPerformanceFigures ---------------------- 228

K.2. TechnicalForm:Layoutandconstructionverificationandapproval 233

K.3. EnvironmentalGenerator -------------------------------- 234

K.4. TECHNICALFORM:DIESELENGINEANDACCESSORIES 235

K.4.1. TECHNICALFORM:COOLINGSYSTEM ------------------ 239

K.4.2. TECHNICALFORM:EXHAUSTSYSTEM ----------------- 242

K.4.3. TECHNICALFORM:GENSETUNIT ----------------------- 243

K.5. EquipmentQuestionnaire -------------------------------- 246

K.5.1. StepupMVtransformer ---------------------------------- 246

K.5.2. TECHNICALFORMMV1600/400kVAtransformersinformation 251

K.5.3. TECHICALFORM:NEUTRALGROUNDINGRESISTOR 254

K.5.4. TECHNICALFORM:22Kv‐MVenclosure --------------- 255

K.5.5. TECHNICALFORM:11Kv‐MVenclosure --------------- 257

K.5.6. TECHNICALFORM:MVCircuitBreaker ---------------- 259

K.5.7. TECHNICALFORM:MVCurrentTransformers ------- 265

K.5.8. MVPotentialTransformers ------------------------------ 266  

 

 

 

 

 

Annex‐A15  

A. ChapterA:GENERALTERMS

A.1. IntroductionThe  Israel  Airport  Authority  is  interested  in  upgrading  its  facilities  by 

increasing  the  production  capacity  of  power  and  air  conditioning  at  the 

existing energy center during the normal and/or emergency operations. 

The  existing  energy  center  facility  includes  four  dual  fuel  diesel  generators 

manufactured by STX Korea, with a total capacity of 12MW. 

This  specification  covers  the minimum  requirements  for  the project  for  the 

design,  procurement,  supply,  delivery,  installation,  testing  and  start‐up  and 

commissioning of a power plant  (the  "Facility") based on a dual  fuel Diesel 

Generator  ("Generator",  “Diesel Generator” or  "GEN 5”)   on  a  “Design  and 

Build Turn‐Key Fixed Price basis” (the "Project"). The new Generator's control 

system will be integrated with the control system of the existing power plant 

for  synchronization  and  load  sharing  control  capabilities  in  an  island mode 

type  operation.    The  new  Diesel  Generator will  be  installed  within  a  new 

extension of the existing power plan building that will be built and provided 

by IAA and it will be separated by a concrete fire wall from the existing power 

plant.

Annex‐A16  

A.2. ProjectphasesThe project is divided into three phases: 

A.2.1. Phaseone–initialoperationwithlightfuel The  new  Diesel  Generator  will  be  used  as  an  emergency  standby 

power  source  to  the Airport’s  energy  Center.  The Diesel Generator 

shall  be  equipped  with  all  necessary  means  for  emergency  and 

continuous operation either in parallel with the grid or in island mode 

as  stand‐alone  or  as  part  of  the  whole  energy  center.  The  Diesel 

Generator  shall  be  designed  and  supplied  for  dual  fuel  operation, 

namely both, light fuel oil #2 and natural gas. 

Generator's  control  system  shall  be  integrated  with  the  control 

system  of  the  existing  power  plant  for  synchronization  and  load 

sharing control capabilities in an island mode type operation. 

A.2.2. Phasetwo(optional)–operationwithNG This phase will be  implemented at a  later  stage, when NG  (Natural 

Gas) will be available to the energy center. 

Implementation  of  this  phase  depends  on  the  availability  of  NG 

supply to the generator and it shall be approved in writing by IAA. At 

this  phase,  the  contractor  will  connect  the  NG  system  to  the 

Generator  and  perform  testing  to  the  Diesel  Generator  and  all 

auxiliary  systems,  for  daily  operation  using  either with NG  or with 

light  fuel.  The  intention  is  to  operate  the  Diesel  Generator 

continuously on daily basis with NG, 3000‐8000 hours per year as a 

primary source of power to the airport. 

Remark: Generator operations hour per year depend on the cost production 

of 1kw and the financial savings from operating the generator.  

A.2.3. Phasethree(optional)–Co‐GenerationCo‐Generation  operation  phase will  be  implemented when  natural 

gas supply to the energy center will be available.  Implementation of 

this phase 3 shall be subject to an approval in writing by IAA. 

During this phase, the contractor will, supply,  install and connect an 

absorption chiller. The absorption chiller will operate  in‐conjunction 

with  the  generator  producing  chilled  water  as  a  Co‐Generating 

System. 

   

Annex‐A17  

A.3. Projectschedule Expected schedule for project phases: 

A.3.1. Phaseone(SeesectionA2.1)Phase one shall be two years from commencement of the Project 

(notice to proceed date) to final completion (commissioning of the 

Project), according to the schedule specified in section A.5 below.  

A.3.2. Phasetwo(SeesectionA2.3)Final completion of phase two will be completed within three (3) 

months after notice to proceed for phase 2 (approval in writing by 

IAA).  

A.3.3. Phasethree(SeesectionA2.3)Final completion of phase 3 will be within twenty four (24) months 

after notice to proceed for phase 3 (approval in writing by IAA), 

delivery for phase 3 will be within eighteen (18) months.

Option Notice to Proceed, Authorization Notification: 

IAA will notify  the Contractor  if  it  intends  to  implement  the optional phases 

and  shall authorize  the  contractor  to proceed with phase 2 or 3 within  the 

implementation of phase one, but not  later  than  the  time  set as phase one 

completion date. 

 IAA's  authorization  notice  will  indicate  options’  starting  and  completion 

dates. 

 (See sections A2‐2/3) 

   

Annex‐A18  

A.4. ScopeofServices&MajorPointsThe  biding  format  with  the  successful  Contractor  is  "Engineering, 

procurement &  construction  Turn‐Key  Fixed  Price", where  the  frame work 

and scope of services will consider the following but not limit to: 

1 Engineering and build the various levels of the Project: 

The overall management and control of the Project; 

Control and supervision of all sub‐contractors; 

Provision  of  all  labor,  supervision,  management,  materials, 

equipment, on site storage and material handling and control of 

the complete Project; 

Site investigations and surveys, as required; 

Preparation of the Environmental Impact Statement; 

Compliance  with  the  Environmental  Impact  Statement  and 

Environmental Laws and any Legal Requirements; 

Conducting all necessary study work; 

Engineering, studies and design; 

Detailed engineering; 

Procurement; 

Expediting and Inspection; 

Manufacture and fabrication; 

Packing, shipping, delivery to site and insurance; 

Temporary construction works and facilities; 

Construction and erection; 

Protection and preservation; 

2 Start‐up, performance & reliability testing and Commissioning – Carry 

out  the commissioning process based on commissioning procedures 

approved by IAA. The procedures shall include: 

Training at the manufacturer's facilities 

FAT ‐ at the manufacturer's facilities 

Onsite training  

SAT,  (Site Acceptance  Tests)  ‐As  part  of  the  acceptance  tests, 

minimum  capacity  and  efficiency  parameters  will  be 

determined.  Deviations  from  the  agreed  values  will  result  in 

penalties as determined in the biding forms; 

3 The  contractor  will  complete  all  technical  and  operational 

documentation,   and provide all mandatory  spare parts and  special 

tools for warranty period 

4 Guarantees 

5 Warranty period 

6 LTSA‐ Service  

   

Annex‐A19  

A.5. ConstructionSequenceAll  work  under  this  Contract  shall  be  performed  in  accordance  with  the 

approved construction sequence and schedules, as per the contract's terms. 

1 To prevent delays  in the construction schedule, the construction will 

not  start  until  construction  of  the  Energy  Center  expansion  and  all 

other  facilities  under  IAA's  responsibility  are  complete. 

Notwithstanding  of  the  above,  IAA  may  authorize  or  direct  the 

contractor to start with the construction and installation work, at the 

time  the  IAA  deems  fit,  even  before  the  Energy  Center  and  other 

facilities are complete. 

2 Detailed schedules  that  the contractor has  to provide  to  IAA will be 

based  on  IAA  Contractual  milestones,  see  the  table  below.  The 

detailed schedule shall  include all activities required for meeting the 

project completion on time and shall be approved by IAA.  

 

No  IAA Contractual milestones 

Timeframe after signing the contract 

Remark 

1  Submittals and Shop drawing 

3 Months   See section A.18 

2  Purchase Order (PO), issued by the contractor  to  the generator supplier  

1 Months The PO shall include but not limit to: ‐ Delivery time  ‐ Training at manufacturer's 

facilities,  see section A24 ‐ Fat (Factory Acceptance 

Test), see chapter j section J1     

3  Submission of technical data for all other equipment  

3 Months    

4  Equipment delivery to the site  

See section A.17, A.19 

4.1 Delivery of the Generator and all the auxiliaries required for its operation    

14 Months In case the contractor wants to deliver the Generator to the site in less than 12 months, the contractor needs to receive IAA's approval.  Before deliver the generator the contractor shall complete the follow within 12 months:      

‐ Training at manufacturer's facilities,  see section A24.1

‐ Fat (Factory Acceptance Test), see chapter j section J1      

Annex‐A20  

 

No  IAA Contractual milestones 

Timeframe after signing the contract 

Remark 

4.2   Delivery of the Electrical equipment  

14 Months All major equipment shall be delivered  within 14 months. The time of the delivery will be coordinated with IAA.    

5  Completion of Installation 

18 Months Construction sequence, see section A.4    

6  Start up and commissioning  

22 Months  

7  Submittals before final completion   

23 Months See section A22  

8  Onsite training 23 Months see section A24.1   

9  SAT and SOAK 23 Months See  chapter J 

 

A.6. LiquidatedDamagesforDelayIn the event of delay in completion of Final Site Acceptance Test (milestone No. 9) 

for each of the phases, the Contractor will be required to pay liquidated damages as 

follows: 

 

Up to  3 months delay 0.25%  of  Contract  Price  for  each month  of  delay,  or,  in  the  case  of  a delay  for part of month,  a pro‐rated amount  thereof  according  to  the number of days of delay. 

Between 4‐6 months delay 0.5% of Contract Price for each month of delay or,  in the case of a delay for part  of  month,  a  pro‐rated  amount thereof  according  to  the  number  of days of delay. 

Between 7‐12 months delay 1% of Contract Price  for each month of delay or,  in the case of a delay for part  of  month,  a  pro‐rated  amount thereof  according  to  the  number  of days of delay.  

More than 12 months Rejection of the Facility 

 

   

Annex‐A21  

A.7. Contractor'sresponsibilityContractor  is  responsible  for  the  studies,  design,  obtaining  of  permits, procurements,  supply,  delivery,  erection,  installation,  commissioning  and testing, as well as training of operation and maintenance staff of the complete Facility, including all the interface connections points with the existing energy center, as well as for the proper commissioning of the complete system of the Diesel Generator including all auxiliaries and subsystems. 

This Contractor is responsible to coordinate the work with all sub‐Contractors, as well  as,  ensure  compliance with other  systems  and  subsystems  (but not limited to) as follows: 

1. Civil, structural and building works; 

2. Cooling water system; 

3. Light Fuel supply system; 

4. (Option)  Natural  Gas  Fuel  supply  systems  and  conditioning  with interconnecting pipes within the Facility, up to the boundary limits; 

5. Generator's  exhaust  system,  silencer,  by  pass,  if  included  in  the design; 

6. (Optional) Future exhausts connections to Absorption chiller; 

7. Hot water system; 

8. Interconnection  pipes  and  pipe  racks  and  pipe  bridge  within  the facility, up to the terminal points and boundary limits; 

9. Electrical systems; 

10. (Optional) Absorption  chiller,  cooling  tower,  chilled and  condenser water pumps and all auxiliary systems, if approved to proceed; 

11. Building's Safety and Protection systems; 

12. Main control system (SCADA); 

13. Communication systems; 

A.8. ProjectlocationandenvironmentalconditionsThe Ben‐Gurion airport is located close to the town of Lod, Israel, 

approximately 20 km east from the coast line of Tel Aviv. General information 

for the environmental site conditions:   

Altitude  37 meters above sea level 

Normal ambient temperatures range 

5 ºC – 40 ºC 

Humidity  46 % ‐ 84% 

Extreme temperatures (rare cases) 

‐2.5ºC and 45ºC 

Pollution  Burnt fuel pollution (airport environment conditions), occasional dust storms 

Seismic zone  Zone #3 

 

Annex‐A22  

ScopeofmajorItems:The non‐exhaustive list below includes the major items of the equipment and 

works required to complete the Project: 

1 One dual fuel diesel generator, 6‐7 MW, 11kV. 

One (1) dual fuel Gas Diesel Generator power unit, complete 

with  generator,  coupling,  gear  box,  base  and  auxiliary 

equipment 

Day light fuel tanks and refueling system 

(Option,  if  phase  2  will  be  implemented)  Natural  Gas  Fuel 

supply  systems  and  conditioning with  interconnecting  pipes 

within the Facility, up to the boundary limits; 

Fresh air intake system  

Exhaust system 

SCR (Selective Catalytic Reduction unit), if required. 

Exhaust bypass and damper system for the future absorption 

chiller 

Silencer system 

Exhaust stack, complete with the structural support system 

Increasing  the  height  of  four  existing  stacks,  complete with 

structural requirements. 

Complete  new  compressed  air  starting  system  including  air 

compressor,  and  pipes  for  instrumentation  and  control 

system. 

Complete  new  generator's  cooling  systems  (intercooler  HT, 

LT, lube oil, water). 

Complete air conditioning system for electrical rooms 

Complete  generator's  building  ventilation  and  smoke 

exhausts system. 

Generator's warm up system. 

Lubrication  system,  water  pumps,  batteries  and  battery 

chargers 

Controls  and  synchronization  system  for  GEN  5  at  MV 

switchboards (100,200,600,700) breakers. 

Integration system with the load‐sharing of the existing diesel 

power  plant  (Operated  either  by  light  fuel  oil  #2  or  natural 

gas) 

2 Medium voltage system 

One step up transformer, 11/22kV, power rated according to 

the maximum 

Generator circuit breaker. 

New 22kV switchboard  installed at  the new extension of the 

existing power plant building. 

Annex‐A23  

Adding two new 22kV cubicles to existing 22kV switchboards, 

one for MVP100 and the second for MVP200. 

Auxiliary transformer , 22/0.4KV, 1600Kva 

Auxiliary transformer , 22/0.4KV, 400kVA 

Grounding  resistor  at 22kV  side of  the  step‐up  LV  and MCC 

panels 

Motorized 22kV circuit breaker for connecting the grounding 

resistor 

 

3 LV and MCC panels 

4 UPS power for control protection and communication systems. 

5 Local PLC panel  

6 Integrating with the existing controls and HMI systems 

7 Black start generator  

8 Installation power cabling and wiring of MV, LV and instrumentation  

9 Indoor and outdoor Lighting and service sockets 

10 All supporting structure and metal works for main and sub systems. 

11 Fire detection and protection systems (by others)  

12 Security and access control (by others) 

13 Communication System; 

14 As made drawings & vendors documentation 

15 Operational and Maintenance manuals 

16 Spare parts for 2 year initial operation 

17 Maintenance &  special  tools  and  equipment  for workshops,  stores 

and laboratories; 

18 All consumables for the initial period of six (6) months 

19 Monitoring equipment for effluents, emissions and air pollution. 

20 Maintenance Service agreement  

21 Option  for  building  a  new  synchronization  system  to  include  the 

existing:  four  generators,  tie  breaker  at MVP300, main  breaker  at 

MVP100 and main breaker at MVP200.   

22 Option  for  connecting  the  NG  to  the  generator  and  all  auxiliary 

systems, for daily operation using NG to energize the generator  

23 Option Absorption chiller,1300‐1500TR, Supply and installation, start–

up and commissioning (phase three) include: 

Chilled water pumps 

 Condenser water pumps  

Piping, accessories insulation and controls 

Cooling tower 

   

Annex‐A24  

A.9. Facility&GasDieselEngineSpecification

A.9.1. GeneralThe Facility must be of a proven design, built to appropriate internationally 

recognized standards, and comply with all the applicable statutory codes and 

regulations. 

All plant and equipment components must be of proven design, and must be 

supported by the manufacturer with respect to spare parts availability for the 

duration of the agreement. Plant reliability, availability and maintainability 

consistent with high efficiency, are of paramount importance. The 

Contractors will be solely responsible for the correctness and adequacy of 

their designs and will ultimately bear all risks relating to the installation, 

testing, performance and reliability of the Facility. 

The plant must be designed to allow the operation over the complete range 

of anticipated ambient conditions. 

The Facility shall be designed for fully automatic, un‐attended operation with 

minimum requirement for maintenance staff, consistent with high 

operational safety, reliability and economy. It is foreseen that the Facility will 

be operated in conjunction with IAA's existing power center without 

additional personnel. 

The station must be designed to achieve the levels of availability and 

reliability normally expected for modern Power plants. The expected average 

Equivalent Availability for the lifetime of the Facility shall be equivalent to, or 

greater than 92% during the Warranty Period and 95% thereafter. 

The Facility must be designed for a life of at least 30 years (the equipment & 

auxiliary equipment design life shall be 30 years under the specified 

conditions). 

A.9.2. GasDieselGenerator: The Gas Diesel Generator (GEN 5) shall be reciprocating internal combustion 

engines of proven design, operated by dual fuel, either Fuel oil #2 or natural 

gas, directly coupled to a 50 Hz generator. 

The GEN 5 will be with the following characteristic: 

Annex‐A25  

Rated Continuous output  

Min. / Max.   

 

5,700 kWe / 7.300 kWe  

Number of Engine Generator  one (1) gen‐sets  

Turning speed – low/medium  Max. 750 rpm 

Operating cycle  4‐stroke 

Electrical generation efficiency at 

full load 

 Min. 42% 

Max noise level at 1 m  90 DB >   

 

The GEN 5 shall be installed indoors within a new extension of the existing 

power house that shall be provided by IAA. 

The GEN 5 must be provided with low NOx, lean‐burn concept (or SCR and 

oxidation catalyst for CO, if required) and include all associated ancillary 

(such as turbo charger, intercooler) and auxiliary equipment and systems for 

the safe, efficient and reliable operation. 

Exhaust and by pass ducting must be insulated with cladding of galvanized 

or aluminum sheets. 

The Facility should be capable of achieving full load in all ambient conditions 

up to ambient environment temperature of 45° Degrees C and capable of 

continuous, stable operation over the range of 50% to 100% of load levels.  

The guaranteed heat rate should be defined for every 10 percentage points 

of the range from 50% to 100% of load set forth in the Contractor’s proposal 

for the entire range of ambient temperatures. 

A.9.3. EmissionsThe Contractor shall state, in his proposal, the anticipated emission levels and his  guaranteed  exhaust  emission  levels  for  the  proposed  engine,  and  in compliance with  the  latest  edition  of  the  Best  Available  Technology  (BAT) document  reference  and  the  Israeli  Ministry  of  Environmental  Protection regulations.  The  Contractor  shall  state  the  emission  levels  for  all  operating conditions specified in the data sheets. 

All emission control equipment and monitoring systems provided within  the scope of  the Project  shall be  in accordance with any and all environmental laws, legal requirements and Good Industry Practice. 

Exhaust gas emissions must not exceed the emissions rates allowed by those Israeli  standards,  considering  other  emissions  in  the  area  and  under  all ambient conditions and burning gas which meets the specified range of  fuel oil #2 and natural gas specification. 

 

Annex‐A26  

A.10. StandardsandRegulationsThe design of all facilities must be to an approved  internationally recognized set of standards and codes. The designs must be to an acceptable standard of professional competence and must represent a safe, efficient use of materials to produce the required facilities. The  installation on  Site  shall be  in accordance with  the  following  standards and shall comply with  the  requirements of  the  Israeli Electrical Corporation, and all other standards and regulations enforced (applicable) in Israel: 1 Israeli  law,  regulation  and  standards  for  electrical  equipment  and 

installation. 

2 General  specifications  for  building  work  (  The"  blue  book"  local 

regulations issued by the ministries of housing and defense). 

3 Israel Airports Authority (IAA). 

4 Israel Electric Company (IECo). 

5 Israel Electrical Law. 

6 Safety regulations (Ministry of Labor). 

7 The Standard Institution of Israel (SII). 

8 The  regulations  and  recommendations  for  Environment  Quality  by 

the Ministry of Environment protection. 

9 OSHA  ‐  Occupational  Safety  and  Health  Administration  (Israeli 

Standards). 

10 Israeli  Home  Front  Command  regulations  concerning  chemical 

storage. 

A.10.1. ApplicableInternationalStandardIn the absence of Israeli rules, regulations and/or standards the 

following standards will apply: 

ABGSM TM3 

ANSI C‐39‐1 

ANSI/ASME B31 

AS 1359 

AS 2789 

BS 800 

BS 4999 

BS 5514 

DEMA 

DIN 6271 

DIN 6280 

DIS 8528 

EGSA 101P 

IEC 60034/1 

IEEE 587 (Standards for transient immunity) 

Annex‐A27  

ISO 3036/1 

ISO 3046 

ISO 8528 

ISO 9001 (Quality control) 

JEM 1359 

NEMA MG1‐22 

NFPA   

RFI/EMI Emission: Requirements comply with FCC rules & regulations 

part 15.  

Class RFI/EMI susceptibility: Mill Standards ‐ STD ‐ 461B 

TA LUFT 

UL‐873 Temperature Indication and Regulating Equipment 

UL‐916 Energy Management Systems 

VDE 875 

Even though some standard parameters may be quoted hereunder, 

the Contractor shall comply with the requirements of the most 

updated standards versions. 

A.11. AbbreviationsThe following acronyms and abbreviations shall apply: 

ACC    Air Cooled Condenser 

ACGIH    American Conference of Governmental Industrial Hygienist 

AGA    American Gas Association 

AGMA    American Gear Manufacturer Association 

AIS    Air Insulated Switchyard 

ANSI    American National Standard Institute 

API    American Petroleum Institute 

ASME    American Society of Mechanical Engineers 

ASTM    American Society for Testing and Materials 

AVR    Automatic Voltage Regulator 

CCTV    Closed Circuit Television 

CCR    Central Control Room 

C&I    Control and Instrumentation 

CPM     Construction Project Manager (IAA) 

CPL    Continuous Partial Load 

Annex‐A28  

CPU    Central Processing Unit 

DCS    Distributed Control System 

DGPT     Detection of Gas Pressure and Temperature 

DIN    Deutsches Institut fur Normung e. V. 

DLN    Dry Low NOx 

EMI    Electro Magnetic Interference 

CONTRACTOR    Engineering, Procurement and Construction 

FAC    Final Acceptance Certificate 

FRP    Fiberglass Reinforced Polyester 

FSNL    Full Speed No Load 

GEN    Including engine, gear box, generator and auxiliaries    

GPS    Global Positioning System 

HP    High Pressure 

HV    High Voltage 

HVAC    Heat, Ventilation and Air Conditioning 

IEC    International Electrotechnical Commission 

IECO    Israel Electric Corporation Ltd. 

IEEE    Institute of Electrical and Electronic Engineers 

ISO    International Standardization Organization 

LAN    Local Area Network 

LP    Low Pressure 

LTSA    Long Term Service Agreement 

LV    Low Voltage 

MCC    Motor Control Centre 

MMI    Man Machine Interface 

MV    Medium Voltage 

NEMA    National Electric Manufacturing Association 

NFPA    National Fire Protection Association 

Annex‐A29  

NG    Natural Gas   

NTP    Notice to Proceed 

OLTC    Off‐Load Tap Changer 

ONAN    Oil Natural Air Natural 

PAC    Preliminary Acceptance Certificate 

PCU    Process Control Units 

PRMS    Pressure Reducing and Measuring Station 

PVC    Poly Vinyl Chloride 

RTD    Resistance Thermal Detector 

UPS    Uninterruptable Power Supply 

UTP    Unshielded Twisted Pair 

VDI    Verein Deutscher Ingenieure 

XLPE    CrossLinked PolyEthylene 

 

A.12. DocumentsFormatAll required documents shall be submitted in three hard copies and computer 

media as follows: 

1 Data sheets in Microsoft excel 2010. 

2 I/O and MMI lists in Microsoft excel 2010. 

3 Work procedures descriptions in Microsoft Word 2010. 

4 All drawings shall be in AutoCAD2012. 

Later  versions of above mentioned  software packs may be used only when 

permitted by IAA 

A.13. LanguageAll  drawings,  PLC  ladder  descriptions,  function  blocks  descriptions  and 

manuals shall be in English 

   

Annex‐A30  

A.14. TechnicaldocumentsthatwillbesubmittedtotheContractor1 Specification. 

2 Single line drawings of the existing Energy center. 

3 Proposed General arrangement drawings. 

4 Proposed Diesel Fuel oil P&ID. 

5 Proposed Lubricating system P&ID. 

6 Proposed Compressed air P&ID. 

7 Proposed Sludge system P&ID. 

8 Proposed Layout Drawings of:     

Generator's  Layout  and  Future  absorption  chiller,  layout‐ 

water condenser & chilled water pumps and piping  

Generator's exhaust system  layout 

Indoor ventilation system 

Roof mounted equipment layout 

Electrical systems layout 

Cooling system layout 

Building construction drawings 

A.15. VerificationbytheContractorDuring  the bidders'  tour  and  conference  the  contractors  shall  conduct  field 

verification  to  capture  all  necessary  details;  dimensions,  structural 

implications,  access  road,  project  are  constructability,  contractor's  set  up 

areas and weather conditions during the project.  

No  future  claim  shall  be  accepted  due  to  mismatches  and  construction 

conflicts on site.   

A.15.1. LayoutverificationduringthebidThe  Contractors  shall  carefully  study  the  Tender Documents,  check 

and  approve  the  IAA  Propose  layout  and  Construction  drawing  as 

specified  in section A‐12.  In case of any discrepancies the contractor 

will notify IAA. 

Contractors may propose alternative layout solutions as part of value 

engineering,  within  the  limitations  and  outline  of  the  planned 

structure, designed by IAA. 

The contractor's alternative layout solutions shall include: 

General arrangement of all major equipment to be presented on the 

building layout drawings, including: 

Generator's  Layout  and  Future  absorption  chiller,  layout‐ 

condenser. water & chilled water pumps and piping  

Annex‐A31  

Generator's exhaust system  layout 

Indoor ventilation system 

Roof mounted equipment layout 

Electrical systems layout 

Cooling system layout 

Day tank  

Building construction drawings 

IAA may approve or reject contractor’s proposals. 

 

A.16. Contractor'sTechnicalSubmittalswithinthebidSpecifications document  and  technical  data  and  schedules  prepared by  the 

Contractor: 

1 For any proposed equipment,  the Contractor  shall  submit  reference 

list  of  similar  systems  and  installations  supplied  by  the  contractor. 

The list shall include; purchaser's name, installation location, name of 

factory  manufactured  equipment,  software  supplier,  system 

configuration and the system's start‐up date. 

2 Dedicated  organizational  chart  for  the  project with  key  personnel, 

names, tasks and experience in the following: 

Hardware manufacturing 

Installation Software 

System Integration 

3 Sub‐Contractors proposed 

4 Systems  and  products  to  be  approved  as  submittals  including 

catalogue cuts, prior to installation. 

5 Any  document  required  by  the  IEC  or  by  the  authorities  for 

calculations, simulations and/or approving of the generator. 

6  Proposed  schedule  for  design,  manufacturing,  source  inspection, 

factory  testing,  shipment,  installation,  integration,  site  testing  and 

commissioning of the system. 

7 Approval procedures will be pending Project Manager's and  system 

teams. 

8 The  contractor  to  approve  in writing  the  proposed  building  layout 

issued  by  IAA,  including,  but  not  limited  to;  building  foundation, 

structural loading (DG, electrical systems, absorption chiller system). 

9 Description  of  synchronization  system,  DG  protection  systems  and 

sequence of operation.  

10 Schematic  drawings  and  block  diagrams  detailing  equipment 

assemblies  and  indicating  dimensions,  weights,  structural  loadings, 

and  required  clearances,  method  of  field  assembly,  components, 

location and size for each field connection. 

Annex‐A32  

11 Schematic  drawings  and  block  diagrams  containing  the  following 

information about the local PLC based control panels: 

Block diagrams showing all significant pieces of equipment as 

well as control devices. 

Details of control panels. 

12 System configuration showing peripheral devices, power and back‐up 

supplies, communication networks and interconnections. 

13 Overall dimensions of typical panels and switchboards to be installed 

on site and all required preparation to be done before installation, 

including; Penetrations and house‐ keeping pads. 

14 Software packages description and sequence of operation. 

15 HMI software packages description. 

16 Proposed list of graphic and non‐graphic screens and windows 

17 Characteristics  of  the  communication  between  the  central  system 

and the local PLCs. 

18 Communication protocols and proposed standards. 

19 Description  of  the  factory  tests  and  acceptance  tests  to  be 

performed. 

20 Mandatory spare part list  

21 MTBF of major equipment 

22 Heat and mass balance diagram 

23 One line diagram  

24 Layout Drawing of the project including the boundaries of supply 

25 P&I Drawing of the complete project 

26 Recommended  training  (at manufacturer's    facilities and on  the  Job 

site) 

27 Recommended service agreement  

Annex‐A33  

A.17. SubmittalsandShopdrawingsafterawardThe  Contractor  shall  provide, within  three months  of  the  signed  contract, 

submittals and shop drawings, for review and approval in accordance with the 

requirements of the contract documents. The Contractor shall be responsible 

for  and  bear  all  cost  of  damages  which  may  result  from  the  ordering  of 

material or from proceeding with any part of the work prior to the approval of 

submittals and shop drawings. 

The review and approval of submittals will not be construed as: 

1 Permitting any departure from the Contract requirements. 

2 Relieving  the  Contractor  of  the  responsibility  for  errors,  including; 

details, dimensions and materials. 

3 Approving  divergences  from  details  furnished  by  IAA  except  as 

otherwise specified. 

The  contractor  shall  perform  and  submit  transient  stability  study  showing 

that the proposed Genset  is capable for working  in the Airport grid without 

getting to any possible oscillations after short circuit on the HV or MV grid.  

A.17.1. ShopDrawingsShop drawings should establish lines and levels for the work specified 

and  check  interferences  with  structural,  architectural  and  other 

disciplines.  If a disciplinary  conflict does occur,  call  the attention of 

the IAA or its representative for clarification in writing. Shop drawings 

shall  include  drawings  to  a  scale  of  1:25  showing  all  equipment, 

ductwork,  piping  and  electrical  work  to  be  installed,  including 

sections and elevations. For critical areas, provide sectional drawings 

to a minimum scale of 1:10.Shop drawings shall be complete, detailed 

and dimensioned and shall include the following: 

1 Fabrication and, layout drawings. 

2 Heat and mass balance diagram 

3 One line diagram  

4 P&I Drawing of the complete project 

5 Installation dimensions, weights & materials 

6 Complete list of materials. 

7 Manufacturing and installation schedules. 

8 Manufacturer’s mechanical and electrical drawings. 

9 Wiring and control diagrams, as applicable. 

10 Catalog cuts or entire catalogs. 

11 Descriptive literature. 

12 Performance  and  test  data  including:  Capacities,  rpm,  BHP, 

design  and  operating  pressures,  temperatures,  complete 

electrical data and Electrical diagrams. 

Annex‐A34  

13 Structural drawings. 

14 Additional  requirements  specified  in  the  technical 

specifications. 

15 Drawings  shall be A0  size  (820 mm  x  1188 mm).  Each  shop 

drawing shall have a blank area 100 mm by 150 mm  located 

adjacent  to  the  title block. The  title block  in  the  lower  right 

hand corner shall display, at least, the following: 

Number and drawing title. 

Date of drawing. 

Revision block 

Name of project. 

16 Name  of  Contractor  and  sub‐Contractor  submitting  the 

drawing. 

17 Clear identification of contents and location of the work. 

18 Title and number of Specifications section. 

If drawings  show  variations  from  the Contract  requirements 

because of  standard  shop practice or  for other  reasons,  the 

Contractor  shall  describe  such  variations  in  his  letter  of 

transmittal . 

If  approved,  each  of  the  shop  drawings will  be  identified  as  having 

received  such  approval.  Shop  drawings  with  required  corrections 

shown will be returned to the Contractor for correction and if required 

will be resubmitted. Resubmitted shop drawings will be handled in the 

same manner as  first  submittals. On  resubmitted  shop drawings  the 

Contractor shall direct specific attention, in writing or on resubmitted 

shop drawings,  to  revisions other  than  the  corrections  requested by 

the  CPM  on  previous  submittals.  The  Contractor  shall  make 

corrections as directed. 

When  the  shop  drawings  have  been  completed  and  signed  by  the 

CPM, the Contractor shall proceed with construction accordingly and 

shall  make  no  further  changes  except  when  received  written 

instructions from the CPM. 

A.17.2. DrawingidentificationschemeThe Contractor shall adopt IAA's identification format and numbering 

system on his drawings. 

   

Annex‐A35  

A.18. SamplesThe Contractor shall submit samples as specified or as directed and shall be 

presented  to  the  CPM  for  approval.  The  Contractor  shall  prepay  shipping 

charges on samples. Materials or equipment shall not be used until approved 

Each sample shall be labeled as follows: 

1 Name of project. 

2 Name of contractor and subcontractor. 

3 Material or equipment represented. 

4 Place of origin. 

5 Name of manufacturer and model. 

6 Location used  in  the project.  Samples of  finish materials  shall have 

additional markings identifying them under the schedules. 

 Product  Substitutions  will  not  be  permitted  unless  they  are  approved  in 

writing 

A.19. CertificationThe Contractor shall submit the following certificates to demonstrate proof of 

compliance  with  requirements  specified  in  the  technical  specifications  for 

each of the following: 

1 Names of Products and materials. 

2 Tests results of equipment and systems. 

3 QA/QC  test  results  of  personnel,  manufacturers,  fabricators  and 

installers. 

4 Test results of specific engine‐generator unit sets and auxiliaries, from 

the original manufacturer and from the Contractor 

Each certificate shall be signed by an official authorized to certify the specific 

type of  equipment on behalf of  the  issuing organization  and  shall bear  the 

name and address of the Contractor, the project name and location, quantity 

and dates of shipment or delivery to which the certificates apply Certification 

shall not be construed as relieving the Contractor from furnishing satisfactory 

systems and equipment.  

Certified test report: 

Submit original. 

Unless otherwise  specified,  testing  shall be conducted by an 

independent  and  recognized  testing  agency  which  certifies 

that it complies with the standards in Israel. 

Contractor shall provide the necessary permits from the Israeli Labor Ministry, 

for operating the engine‐generator plant. 

   

Annex‐A36  

A.20. DocumentationThe Contractor  shall  submit  to  IAA  the original and  two  copies of each  test 

report with  name  and  address  of  testing  laboratory  and  dates  of  tests  to 

which  reports  apply.  The  Contractor  shall  provide  charts  describing 

performance  of  his  proposed  engine‐generator  as  a  function  of  changing 

external variables.  

One such chart shall show KW output as a function of ambient combustion air 

temperatures. 

A.21. SubmittalsbeforefinalcompletionBefore  final completion,  the Contractor  shall provide  the CPM  three  sets of 

record drawings and manuals and “as made drawings”. All documents shall be 

completed and brought up to date, Manuals shall include the following data: 

1 Table of contents. 

2 Contractor’s name, address and telephone number, with similar data 

for his 24‐hour service organization. 

3 List  of  Products'  with  Manufacturer’s  names,  addresses  and 

telephone numbers, with similar data for their  local representatives, 

distributors and service agencies. 

4 Catalog, model and serial number of equipment installed. 

5 Description of equipment. 

6 Diagrams. 

7 Statement of warranty as specified. 

8 Description of modification, servicing and repairs performed prior to 

start of warranty. 

9 Dates warranty begins and expires. 

10 Manufacturer’s  operating  and  maintenance  instructions, 

manufacturer’s parts list, illustrations and diagrams. 

11 One copy of each wiring diagram. 

12 PLC ladder diagrams with the I/O lists. 

13 Software  listing for the graphic displays  including operator sequence 

control. 

14 Complete database listing documentation. 

15 Troubleshooting instructions. 

16 Complete and detailed list of screens and windows. 

17 List  of  spare  parts,  prices  and  recommended  stock  quantities  for 

routine maintenance of the equipment for two years, five years and 

ten years operation .Provide a  list of spare parts that are considered 

critical  and  for which  long  lead delivery would  create unacceptable 

down‐time for equipment.  

18 List  of  Special  tools  required  to  perform  inspections,  adjustments, 

maintenance  and  repairs.  Special  tools  are  those  developed  to 

Annex‐A37  

perform  a unique  function  related  to  the particular  equipment  and 

not available from commercial use.  

19 Copy of each approved shop drawing of equipment and system.  

A.22. Contractor'spersonnelContractor's personnel shall include all persons engaged, at the relevant time, 

in  the  performance  of  the  work  under  the  contract  on  behalf  of  the 

contractor,  including  the  contractor's  employees,  agents,  advisers, 

consultants and suppliers, subcontractors and all subcontractors' employees, 

agents, advisers, consultants and suppliers. 

A.22.1. SkilledlaborThe contractor shall employ skilled personnel throughout the various 

stages  of  this  project.  For  systems’  integration,  testing,  calibrating, 

start‐up,  commissioning  and  training  the  contractor  shall  employ 

skilled  labor  that are also experienced  in  the operating of electrical, 

controls, heating, cooling, ventilation and mechanical systems. 

A.22.2. ProjectManagementThe  project management  is  part  of  the  scope  of  the  work  of  the 

Contractor  and  includes  all  the  usual  activities  of  a  professional 

project management,  including, but not  limited to, the requirements 

specified  in  this  document.  The  Project  Manager  shall  act  as  the 

primary point of contact  to  the  IAA  regarding all matters  relating  to 

the works. 

Project Manager  shall be,  at  least,  a Certified  Practical  Electrical or 

Mechanical Engineer with minimum 10 years' experience in managing 

and supervising relevant work.    

A.22.3. SafetysupervisorThe contractor shall engage "certified safety supervisor" that will be 

submitted  to  the  Ministry  of  Labor,  as  required  by  law.  Safety 

supervisor shall conduct all activities as required by the Israeli law. 

A.22.4. TechnicalAssistanceforgeneratorandabsorptionchiller

The  contractor  shall  engage  technical  advisory  personnel  from 

generator  manufacturer  to  provide  technical  assistance  for  all 

Annex‐A38  

generator  activities  such  as:  installation,  integration,  testing, 

calibrating, start up and commissioning. 

A.22.5. Local(Israeli)supportforgeneratorandchiller

The Contractor shall have local Israeli representative and shall be able 

to provide  solutions and  react promptly  to problems arising, as per 

contract agreement. 

A.22.6. UseofSubcontractors1 If  the contractor wishes  to use subcontractors, he must present 

comprehensive  details  about  each  subcontractor  and  the 

subcontractors’  scope  together with  the  quotation  to  the  IAA's 

approval. 

2 The  contractor  must  not  use  any  additional  subcontractors 

without IAA’s written approval once the contract is signed. 

3 The  contractor  acknowledges  that  IAA’s  approval  of  any 

subcontractor  does  not  relieve  the  contractor  from  any 

requirement as defined  in  this  specification or under elsewhere 

defined  in the contract. The approval from IAA does not confirm 

or acknowledges the suitability of a subcontractor in any shape or 

form.  In  any  case  the  contractor  is  fully  responsible  for  the 

subcontractors  work,  performance  and  schedule.  The  point  of 

contact  with  subcontracted  work  remains  with  the  contractor. 

IAA  is  not  obligated  to  discuss  or  even  negotiate  with 

subcontractors. 

   

Annex‐A39  

A.23. TrainingThe  contractor  shall  provide  at  the  manufacturer's  facilities  (generator, 

absorption chiller) a full comprehensive training required to perform all tasks 

for  preventative maintenance  services  and  corrective maintenance.  During 

the bid period the contractor will submit the training program for review and 

approval by IAA. 

Training and manuals shall be in English.  

A.23.1. GeneratorTrainingshallincludeasfollows:The  generator  training will  be  divided  into  two  rounds  at  different 

time periods, as follow: 

1 Two weeks  training  at  the manufacturer’s  facilities. Without 

additional  cost  to  the  IAA  (except  for  flights  and  hotel 

expenses for the IAA's representatives which will be borne by 

the  IAA. The  training shall  include all  levels of corrective and 

preventative  maintenance  (including  full  overhaul).  The 

purpose  for  this  training  is  for  the manufacturer  to  provide 

Technician's  qualification  for  repair  and  full maintenance  of 

the system. System shall include, but not limited to:  

Safety procedures 

NG safety procedures 

General acquaintance with all system equipment and 

component. 

Review  the  Operational  and  Maintenance  manuals 

supplied  

Operation of all equipment in all modes of operation. 

Maintenance procedures. 

Components / System calibration 

Troubleshooting procedures 

Practical training  

Technician training will include "train the trainer 

Qualification certificate will be  issued by the manufacturer to 

technicians successfully completing the training. 

 

2 Two sessions of one week training, each at the IAA's facilities, 

under real operating conditions. Systems shall include, but not 

limited to: 

Safety procedures 

NG safety procedures 

General acquaintance with all system equipment and 

component. 

Annex‐A40  

Operation of all equipment in all modes of operation. 

Components / System calibration 

Electrical switchboard and transformers operation and 

maintenance 

Troubleshooting procedures 

Additional  two weeks  training  at  the manufacturer’s 

facilities  or  one  week  training  at  the  IAA’s  facilities 

may be required for additional cost  

A.23.2. AbsorptionLiquidChillerstrainingThe  Contractor  shall  furnish  a  competent  engineer  to  instruct  and 

train IAA's designated personnel in the operation and maintenance of 

every part, device and piece of equipment of the Absorption Chillers, 

with  emphasis  on  proper  startup  and  shut  ‐down  procedures, 

preventive  maintenance  and  lubrication  procedures  with 

recommended  lubricants,  overhaul  and  maintenance  methods, 

adjustment  and  calibration  of  instruments  and  controls,  the  use  of 

special  tools  and  safe  practices.  One  engineer  and  three  foremen 

shall be trained for a period of two (2 weeks).  

 

   

Annex‐A41  

A.24. WarrantyandMaintenanceServices

A.24.1. GeneralThe  Contractor  shall  provide  warranty,  support  and  maintenance 

services  for  the Plant,  in accordance with  the service  levels  that are 

specified below (SLA) and the provisions of the Contract. 

 

The Contractor shall  include  the  following  lists  in  its proposal  to the 

Tender: 

(a) List including prices of all Spare Parts, Special Tools, Consumables 

and  costs of  supervision by Contractor's  representative  that are 

required,  according  to  Contractor's  O&M  Manual  and  in 

accordance with prudent  industry practices,  for  all Preventative 

Maintenance (as defined below) up to and including full overhaul. 

The  Contractor  shall  include  a  breakdown  of  all  parts  that  are 

required for each Preventative Maintenance service and whether 

such service requires supervision by the Contractor.  

(b) A  full  list  of  all  Spare  Parts,  Special  Tools  and  Consumables 

required  for  the proper operation of  the Plant according  to  the 

Guaranteed Availability. In this list the Contractor shall specify the 

recommended Spare Parts, Special Tools and Consumables with 

respect to the Warranty Period, the Technical Support Period and 

Maintenance Period.        

 

The above  lists shall be evaluated as part of Contractor's proposal to 

the Tender and shall bind the Contractor. 

   

Annex‐A42  

A.24.2. DefinitionsThe  following  terms  shall  have  the meaning  set  forth  below when 

used in these Technical Specifications: 

 

"Hotline"  means a remote service provided by the Contractor via phone (telephone support) as a response to a call placed by the IAA in the event of malfunctions and/or any other problems discovered. The Hotline service may result the commencement of the Remote Support or the dispatch of  a  technician  to  the  site,  as  further  detailed  in section  A.24.6. 

“Outage”  means  removal of  the  Plant  from  electric  and  thermal power generation service and/or planned downtime for Preventative Maintenance. 

“Planned Maintenance” 

means, with respect to the Plant, the following: (a) Any  major  overhaul,  periodic  inspection, 

testing,  repair,  and/or  replacement  of components  of  the  Plant,  as  specified  in  the supplier O&M manual , as reasonably necessary in  light  of  deterioration  due  to  normal  wear and  tear  on  the  Plant  and  as  required  in accordance with  the  generator  supplier  O&M manual  to  ensure  continuous  and  reliable operation of the Plant. 

(b) the  repair and/or  replacement of  components and parts of  the Plant  subject  to maintenance set out in paragraph (a) above, (1) the need for which  is  found  during  any  Planned Maintenance  Outage  and  (2)  which  is reasonably determined to be necessary prior to the  next  scheduled  Planned  Maintenance Outage to continue safe operation in each case in accordance with Prudent Industry Practices; 

"Preventative Maintenance" 

Means  both  Planned  Maintenance  and  Routine Maintenance. 

“Prudent Industry Practices” 

Means the exercise of that degree of skill and diligence, and of such practices, methods and acts, at a minimum as would ordinarily be expected in the power generation industry  from a prudent owner and/or operator acting lawfully,  reliably  and  safely  in  connection with  power generation facilities and equipment similar to the Plant. 

"Remote Support" 

Means the remote service, provided by the Contractor, by  using  additional  available  skilled  personnel,  with computer  remote  facilities  to  log  into  the  systems located  at Ben Gurion Airport,  for providing  additional support and/or failure repair. 

 

   

Annex‐A43  

 “Routine Maintenance” 

Means maintenance  of  a  regular,  preventive  or minor nature  that  is  performed  periodically,  during  Plant shutdown  or during  operation,  to maintain  equipment in working order on a day‐to‐day basis without the need for  an  Outage,  including,  but  not  limited  to, maintenance of the Spare Unit in accordance with O&M manual,  inspection,  lubrication, calibration, adjustment, minor  leak  repair,  provision  of  fluids,  greases,  and resins, cleaning and replacement of operational spares, filters,  strainers  and  cartridges,  maintenance  or replacement of  sensors,  fuses,  thermocouples,  gauges, switches, and  light bulbs, and other  similar preventive, painting, corrosion prevention  of minor nature, heating and air‐conditioning units, routine or minor work.  

“Unplanned Maintenance”  or "Corrective Maintenance" 

Means  maintenance  of  the  Plant  that  is  required  to remedy  an  in‐service  failure  or  abnormality  of  a component,  whether  discovered  during  an  Outage which occurs as a  result of a problem or  failure of  the Plant, or during inspection or monitoring of the Plant. Unplanned  or  Corrective maintenance  shall  include  all measures  required  to  rectify  or  repair  the  defect, including diagnostics, all kind of mechanical, electrical or software  works,  removal  of  a  defective  part  and installation  of  a  replacement  part,  testing,  calibration and adjustment of  the equipment as necessitated by a repair or replacement. 

Mandatory Spare Parts 

“Mandatory Spare Parts” means parts and components for  the Plant which Owner must  keep and maintain at the Site during the term of this service more specifically will be  identified in suppliers proposal 

 

   

Annex‐A44  

 

A.24.3. WarrantyperiodforPhase‐1. 

The contractor shall provide Warranty for the engine Generator itself 

and any auxiliary system that are in used for Phase one of the project, 

installation works and all interfaces. 

Warranty  Period  shall  be  for  a  period  of  24  months  after  final 

commissioning  under  max  load  conditions  and  as  of  the  date  of 

issuance of the Final Acceptance Certificate for the Generator  

    

A.24.4. WarrantyperiodforPhase‐2The contractor shall provide Warranty for the Gas system of the 

Generator for a period of 24 months after final commissioning of 

Phase 2 under max load conditions and as of the date of issuance of 

the Final Acceptance Certificate for the Generator 

A.24.5. Warrantyperiodforphase3The Contractor shall also provide warranty period for the third phase 

of  the Project  for 24 months as of  the date of  issuance of  the Final 

Acceptance Certificate for the Absorption Chiller. Warranty period for 

phase  3  shall  include  warranty  for  the  Absorption  Chiller  and  any 

auxiliary systems, installation works and interfaces. 

   

Annex‐A45  

A.24.6. ServicesduringWarrantyPeriod 

Services  during  the  Warranty  Period  will  be  carried  out  by  the 

contractor,  without  costs  to  the  IAA.  The  Contractor  will  be 

responsible  to  maintain  skilled  and  trained  staff  available  for 

remedying  any  defects  and/or  performing  all  maintenance  at  all‐

times throughout the Warranty Period. 

 

As part of the Warranty for phase 1 and phase 2, the Contractor shall 

be  responsible  for  performing  Corrective Maintenance  services.  All 

Preventative  Maintenance  services  for  the  Generator  during  the 

Warranty Period will be carried out by the qualified IAA personnel. A 

representative of  the   contractor will be required  to be present    for 

those  services  which  the  contractor  has  listed  on  its  Proposal  as 

services that its actual presence on site for supervision  are required.  

During  Warranty  Period  for  phase  3,  the  Contractor  shall  be 

responsible  for  performing  full  Preventive  Maintenance  and 

Corrective Maintenance services. 

 

The  scope  of  services  to  be  provided  by  the  Contractor  during 

Warranty Period,  including with respect to major overhauls, shall be 

as specified  in Contractor's proposal to the Tender, and  in any event 

not less than the minimum requirements specified in these Technical 

Specifications.  All works shall be coordinated with the IAA. 

 

As part of the Services the Contractor shall provide a Hotline service 

24  hours  a  day  365  days  a  year  for  on‐going  telephone  support 

service. 

The Contractor shall provide contact details  including phone and fax 

numbers and e‐mail through which it will provide the Hotline. 

 

Level  1‐  online  trouble  shooting:  an  engineer  on  behalf  of  the 

Contractor will register all relevant information (incident description, 

error message etc.) given by the IAA's representative using a report in 

the form acceptable to the IAA.  

Such  information  will  be  analyzed  by  the  engineer,  which  shall 

provide an answer/procedure to the  IAA's representative  in order to 

solve the defect within the day. 

In addition  to  the  telephone  support  services  the  IAA  shall have an 

option to order services of repair through Remote Support. If the IAA 

decides to exercise such option, at  its sole discretion, the Contractor 

shall provide the IAA with such services as specified herein.  

Annex‐A46  

Level  2  ‐  on‐site  support:  In  case  the  incident  is  not  solved  by  the 

assistance of Level 1 and/or due  to any other urgent necessity  (e.g. 

mechanical  brake  down  or  other  justified  reason)  that will  require 

immediate  intervention,  the Contractor will  send on‐site  support of 

an engineer or an expert technician and will take all necessary actions 

including all necessary tests in order to repair the defect. 

In  case  equipment  is  needed  in  order  to  repair  the  defect,  the 

Contractor will  take  all measures  in  order  to  transport  and  deliver 

such equipment without any delay, using air express transportation if 

needed and will use all means in order to repair the defect as soon as 

possible.  

A.24.7. SpareParts,SpecialToolsandConsumablesDuring Warranty  Period  the Contractor  shall be  responsible  for  the 

supply of  any  and  all  Spare  Parts  and Consumables  (except  for  the 

fuel/natural  gas),  as  may  be  required  for  the  operation  of  the 

generator  according  to  the  guaranteed  availability,  at  its  sole 

expense. The contractor  shall also  supply at  its expense a complete 

set  of  special  tools  that  are  required  for  performing  all  the 

maintenance services during the Warranty Period. 

 

Upon  signing  of  the  Contract,  the  IAA  shall  purchase  first  batch  of 

Spare  Parts  which  will  include  any  Spare  Parts,  Special  Tools  and 

Consumables as the IAA may decide to purchase, based on the list of 

recommended  Spare  Parts  that  was  provided  by  the  Contractor. 

Should the Contractor use any of these Spare Parts during Warranty 

Period, it shall immediately resupply such part at its expense. 

 

At any time during the Contract Period the IAA shall have the option 

to  purchase  from  the  Contractor  Spare  Parts,  Special  Tools  and 

Consumables,  in quantities as may be determined by  the  IAA, at  its 

sole discretion, as specified in the Contract. 

A.24.8. ResponsetimeandSLALiquidatedDamages 

The contractor shall respond to IAA telephone call within maximum 1 

hour.  In  case on‐site  support  is  required, a  skilled  representative of 

the Contractor shall arrive on site within no later than 48 hours from 

the telephone call. 

 

Annex‐A47  

Correction  time  of  any  defect  or  malfunction  shall  not  exceed  8 

working days. 

 

In the event of failure by the Contractor to comply with the SLA, the 

Contractor shall pay a penalty according to the following: 

Between 8 ‐15 working days – 2,000 Euro per each day of delay. 

Between 15 ‐90 working days – 2,500 Euro per each day of delay 

More than 90 working days delay shall be considered material breach 

of contract. 

A.24.9. ServiceafterWarrantyPeriod(LTSA)

A.24.9.1. TechnicalSupportPeriodFollowing  the Warranty  Period  for  phase  1,  the  Contractor  shall 

continue  to provide  the  IAA with  technical  support  services  for a 

period of 120 months (the "Initial Technical Support Period"). The 

IAA  shall  be  entitled,  at  its  sole  discretion,  to  extend  the  Initial 

Technical  Support  for  additional  periods, which  in  the  aggregate 

shall  not  exceed  15  years  (together,  the  "Technical  Support 

Period"). 

 

During  the Technical Support Period,  the Contractor shall provide 

the Hotline support services as specified above.  In  the event  that 

the incident is not solved by the assistance of Level 1, the IAA shall 

be entitled to purchase from the Contractor on‐site support of an 

engineer or an expert technician, as specified in the Contract. 

In case on‐site support  is  required, a skilled  representative of  the 

Contractor shall arrive on site within no later than 8 days from the 

telephone call. 

 

In  the event of  failure by  the Contractor  to comply with  the SLA, 

the Contractor shall pay a penalty according to the following: 

Above the 8 working days –  2,000 Euro per each day of delay. 

A.24.9.2. MaintenancePeriodFollowing  Warranty  Period  for  phase  3,  the  Contractor  shall 

provide  the  IAA  with  the  same  Preventative  Maintenance  and 

Corrective Maintenance services as provided during  the Warranty 

Period for phase 3, as of the end of the Warranty Period and until 

Annex‐A48  

the  end  of  the  Technical  Support  Period  (the  "Maintenance 

Period").  Services  during  Maintenance  Period  shall  include  the 

supply  of  all  Spare  Parts,  Consumables  and  Special  Tools,  at  the 

Contractor's expense.     

   

Annex‐A49  

B. ChapterB‐EquipmentNumberingSystem

B.1. Objectives1 Enable computerized tracking of the equipment inventory, maintenance 

and operation 

2 Referencing the equipment to main/sub group it belongs to 

3 Identifying the location of the equipment 

4 Identifying a unique ID number for each item 

B.2. NumberingScheme1 Equipment Numbering (TAGS): 

All materials shall be marked for construction with identification 

numbers which correspond with the part numbers on the appropriate 

drawings of the contract works. The Contractor shall follow the Energy 

Center equipment numbering system, but he may also propose his 

standard numbering system for IAA approval.  

2 Conduits and cable numbering: 

Conduits will not be tagged but will be color coded on the drawings, 

according to the Israeli Standard including directional arrows. 

3 Cables: Cables will be tagged by an eight character identification 

number composed of the following elements: 

The first three characters: are defined the cable type‐ HV cable, 

LV cable, control cable, etc. 

The next three characters: are defined according to the cubicle 

number from which the cable origins from. 

The last two characters: are digits of the sequential number of 

cables in this cubicle. 

4 In the event the cable route extends outside the perimeters of the 

building where the feeding equipment is located, the cable will be 

tagged by an additional tag (eight characters) which identifies the 

equipment to which it is hooked to. 

   

Annex‐A50  

B.3. MarkingandLabelingThe contractor shall ensure identification of all components, including: wires, 

cables, conduits, junction boxes, motors, control devices, etc. 

Labels shall be in Alphanumeric English in capital letters and in Hebrew, 

according to IAA’s numbering system. 

Lettering will be engraved, painted, or printed with unfading materials. 

Labels shall be adhesive and fastened by means of screws or shrinkable 

sleeves which will keep the labels from falling or dislodged from their 

location. 

 

B.4. SwitchboardLabeling1. Each switchboard shall be labeled by a 200x100mm, engraved 

“Lamecoid Plates" denoting its name both in English and Hebrew along with a full tag number. 

2. Each cubicle (for switchboard longer than a single cubicle) shall be labeled by a 50x100mm, engraved with Lamecoid Plates" denoting it's full tag number. The same label shall be installed on the back access door to the same cubicle, if exists 

3. Each equipment component installed in the switchboard shall be marked with a 50x20mm “Lamecoid Plates” in black letters on a white background. The markings shall be connected to fixed parts (not onto plastic cable duct covers or likewise). 

4. Each control or power conductor shall be marked at both ends by plastic strips with printed markings, denoting the specific terminal number to which the wire is connected (terminal numbers on equipment pieces or terminal number on terminal strips), as well as the cables original source and destination. 

5.  Each individual terminal shall be marked by up to six digits (in two groups). Each logical group of terminals (e.g. one typical motor starter) shall be identified by an additional group label. All terminal identification materials and auxiliary equipment, such as marker holders, terminal protection cover, bridges etc., shall be of the same make as the terminals. Substitute materials will not be permitted and accepted. 

6.  Main circuit breaker or trip push‐buttons of each switchboard shall be marked by 50x100mm red letters on a white background, engraved with “Lamecoid Plates".

 

Annex‐A51  

B.5. CableLabeling1. Each control or power conductor shall be marked at both ends by 

plastic tags with printed markings denoting the specific terminal number to which the wire is connected (terminal numbers on equipment pieces or terminal number in terminal strip), as well as the cables source connecting point. The label needs to be threaded or otherwise strongly connected to the cable or wire. 

2. Each individual terminal shall be marked by up to six digits (in two groups). Each logical group of terminals (e.g. one typical motor starter) shall be identified by an additional group label. All terminal identification materials and auxiliary equipment, such as marker holders, terminal protection cover, bridges etc., shall be of the same make as the terminals. Substitute materials will not be permitted and accepted. 

3. Underground cables or conduit routes shall be marked with a galvanized 2 Inchpipe, 80cm above the ground level, embedded in a 30x30cm concrete cubicle installed in the center of the route, painted with red and white (horizontal/ vertical) stripes (each stripe 20cm wide). The markers shall be installed on each bend and on straight lines at a maximum distance of 50 meters apart. 

B.6. AuxiliaryEquipmentLabeling1. Junction‐boxes shall be marked twice, once on the cover and once 

inside the box by 50x20mm “Lamecoid” labels. 2. Socket‐outlets, light switches, push buttons etc., shall be marked by a 

25x8mm “Lamecoid ”  label (black on white)denoting the circuit and switchboard number of each item. The label shall be firmed to the wall by two screws. 

3. Poles shall be identified by tag numbers and circuit numbers, using 40mm dye (letters) and painting them with a contrasting color on the pole, 1 meter above ground level with permanent materials. 

B.7. ConduitIdentification1. A conduit identification system shall be applied using color strips 

around the conduits. These color strips shall preferably be of an adhesive plastic material suitable for the surface temperature of the conduits or insulation as well as for the prevailing in ambient conditions. 

2. Flow directional arrows and identification inscription shall preferably be of the same material sand shall be provided in visible places as well as at the inlet branch connections and downstream of each valve. 

3. Where plastic adhesive material cannot be applied, pipe identification has to be carried out by painting. 

4. The contractor shall propose a piping identification system, subject to approval by the IAA. 

   

Annex‐A52  

C. ChapterC‐GeneratorTechnicalSpecification

C.1. General

C.1.1. GeneralDesign1. The proposed Genset will be in the range of 5,700kW to 7,300kW of net 

capacity at continuous operation and shall comply with the following characteristic: 

Number of Engine Generator  one (1) gen‐sets  

Turning speed – low/medium  Max. 750 rpm 

Direct Axis Synchronous Reactance [pu] 

Xd” saturated 

no less than 0.16.5pu 

2. The generator shall be synchronous 11,000 volt, 3‐phase, 50 cycle, and skid mounted bracket type designed for direct connection to the engine flywheel. 

3. The generator shall be mounted on the engine skid and arranged for easy adjustment and alignment. Provisions shall be made to enable the generator removal without disturbing the engine or the removal of other equipment. 

4. The full‐load continuous‐rated kilowatt capacity of the generator shall be computed at 0.80 power factor, at the nominal speed and voltage and shall not be less than the continuously rated BHP of the engine multiplied by 0.746 at the full‐load generator efficiency (less 0.01 wind, friction and exciter losses). 

5. Capable of carrying 110% of the load for 2 hours out of any 24‐hour period 

6. The generator shall be capable of carrying a momentary overload of 250% of the normal ampere rating without causing any damage with the field current set for rated load excitation. The grounding resistor of the generator shall suit this condition as well as protective relays' setting. 

7. Under full‐load conditions, the temperature rise of the stator shall not 

exceed 105C, by RTD measurement, in accordance with AIEE standards 

based upon an ambient temperature inside the room, calculated at 40C. 

8. The generator voltage regulation system shall be a three phase sensing 

solid state Volts‐per‐Hertz type, providing voltage regulation within 1%. 

The generator voltage regulation shall not exceed 25% where the load is reduced from full load to zero when the generator is operating at rated voltage and power factor. 

Annex‐A53  

9. According to IEC requirements and regulations, the contractor is required to perform a study confirming the GENSET capability to remain stable following a specific disturbance occur at the connection point to 161kV NATIONAL GRID, considering any pre‐fault working point of   "P‐Q  CAPABILITY CURVE".  

The specific disturbance is:  

o Bolted Three Phase  short circuit eliminated in first Zone of system's protections (up to 100msec) 

o From "Transient stability" point of view,  the "critical time" of the GENSET must be at least 180 msec. 

10. In addition to the individual data of the GENSET components, the contractor shall provide the following data: 

o Full Moments of Inertia "J" for the full machine, including engine, flywheel, coupling and alternator in [ Kgm2] 

o Total Inertia Constant "H" (Generator, Prime mover, etc.) in [MWs/MVA] 

Power System Stabilizer (PSS) shall be included to improve the damping of possible oscillations in the HV and MV networks by adding a signal to the voltage regulator of the excitation system . 

11. Damper windings shall be provided to eliminate all tendencies to hunt, due to pulsating torque characteristics of the diesel engine, to assure the best parallel operation. 

12. The insulation of the field and armature of the generator shall be of Class "F" classification in accordance with the latest AIEE standards. 

13. The stator shall be equipped with six embedded temperature detectors of the 100 ohm resistance coil type. Temperature indication shall be provided on the local control panel as well as on the main operator workstation (from the local PLC via communication system). 

14. The generator cooling shall be by air‐water radiators, installed on the roof of the generators building, provided by the contractor. 

15. A space heater of a proper capacity shall be furnished for the generator stator winding compartment to prevent condensation from forming. The space heater shall be controlled by local PLC. The space heater will be activated during stand‐by mode of the generator. 

16. The design of the generator, together with its exciter, shall be such that a generator field rheostat will not be necessary. 

17. A neutral grounding resistor shall be sized to limit the bolted line‐to‐ground fault current at the generator terminals, to the three‐phase line‐to‐line fault current. This should be checked to meet installation requirements. 

18. The "GEN" (Including engine, gear box, generator and auxiliaries) shall have the standard AIEE tests before shipment from the factory. The test results shall be provided. 

19. All constructions shall conform to the NEMA or International Electrical Commission standards. 

20. The generator output shall have a wave form deviation of less than 5%, with a TIF factor less than 50 and a THD factor less than 3%. 

Annex‐A54  

21. The generator and its excitation system shall be able to operate within voltage limits providing full rated generating power. 

22. The exciter shall be rotary brushless design with a permanent magnet alternator as a source of excitation power. The exciter shall be direct driven. 

23. The exciter temperature rise shall not exceed 105C, by RTD measurement, in accordance with AIEE standards based upon an 

ambient temperature of 40    

Annex‐A55  

C.1.2. EmissionsandNoiseLevelsPollutants emissions shall be in compliance with the latest edition of 

the Best Available Technology (BAT) document reference and the 

Israeli Ministry of Environmental Protection regulations and comply 

with the latest German TA‐Luft 2002 standards for emissions 

requirements, when operating at full nominal load. There are no 

specific requirements for transient start‐up and shut down 

operations. 

Exhaust gas emissions must not exceed the emissions rates allowed 

by the Israeli standards, considering other emissions in the area and 

under all ambient conditions and burning fuels which meets the 

specified range of liquid fuel or gas fuel specification. The following 

table presents the emission limit values standards. 

1‐ DSCM: Dry Standard Cubic Meter, 0 0C, 1atm @5%O2.  

C.1.3. NoiseLevelsThe engine supplied will contribute to the noise level within the operating 

space in the EC building, see annex C appendix A. 

Pollutants 

 

Limit Value 

T.A.Luft2002 

SOx(mg/DSCM1)  ‐‐‐ 

NOx(mg/DSCM1) 500 (Liquid Fuel) 

250 (other, 4‐stroke Otto Engine) 

(No standard under 300 operating hours)  

PM(mg/DSCM1)  20 (Liquid Fuel continuous)_ 

80 (Liquid under 300 operating hours)  

No limits (Natural Gas Fuel)  

CO(mg/DSCM1)  300 

(No standard under 300 operating hours) 

NH3(mg/DSCM1)  30 

TOC(mg/DSCM1)  ‐‐‐

Formaldehyde(mg/DSCM1)  60 

Annex‐A56  

C.1.4. VibrationsMaximum vibrations permitted shall be as follows (1‐order, peak‐to‐peak values, firmly mounted): 

1. 0.15 mm/s RMS horizontal 

2.  0.15 mm/s RMS vertic 

C.2. AvailabilityandReliabilityThe station must be designed to achieve the levels of availability and reliability 

normally expected  for modern power plants.  It  is expected  that  the  Facility 

will operate on a variable mode of plant loading based on economic basis. The 

expected average equivalent availability, for the lifetime of the facility will be 

equivalent to, or greater than 92% for the first year following the commercial 

operation date and 95% thereafter. 

C.3. MaintenanceAccessConsideration will be given  for easy accessibility, as per code,  to all systems 

and components for maintenance needs and operational requirements, when 

designing the layout of the equipment package. Access will be provided to all 

equipment  and  any  areas  requiring  maintenance.  The  equipment  shall  be 

designed  so  that  all maintenance  can  be  carried  out with  the minimum  of 

special facilities or tools. 

All equipment and piping will be neatly placed and carefully arranged on the 

skid, where  it  is  possible  to  ensure  that  they  do  not  obstruct maintenance 

operations.   The successful contractor shall work closely with  the CPM&  IAA 

management  to  ensure  that  the  most  effective  layout  is  applied,  and 

adequate access for maintenance is achieved effectively within the facility. 

 

   

Annex‐A57  

C.4. MechanicalDesignThe engine design shall be such that the engine will be capable to develop full rated horsepower operating, as a dual fuel (diesel fuel oil and natural gas) engine. The engine shall supply the rating and speed which it was designed for. 

The engine shall be, V‐ (Vee) or L‐ (inline configuration), turbocharged mechanically injected, dual‐fuel engine. The engine and generator shall be mounted on a common base frame that also includes a lube oil pump for engine lubrication in addition to other accessories.  

 

In emergency mode, the engine shall be capable of starting with the use of compressed air, pre‐lube and fuel oil prime functions, and with only 24 VDC control voltage available. 

 

The engine design shall be such that, together with its driven equipment, critical speeds will not appear within the normal operating ranges. 

The nominal rotation speed of the engine shall be 750 RPM or lower. 

 

The engine will be designed to be four (4) stroke. 

 

The maximum exhaust back pressure of the engine shall not exceed 6.7 kPa at full rated continuous load. 

 

The engine design shall permit using diesel fuel oil for pilot ignition while running on natural gas. The dual fuel engine design shall be able to allow changing from diesel fuel oil to natural gas (or vice versa) while running without surging or significantly affecting the speed or load carried by the engine.   

The proposed engine should be designed for the minimum amount of residual unbalance. The contractor shall furnish with his proposal primary and secondary unbalanced forces and couples for the engine being offered.  

The engine and the generator shall be assembled on a common base by the engine‐generator manufacturer. The base will be designed and built to resist deflections, maintain alignment and minimize linear resonant vibrations. The diesel generator sets shall be provided with mobile type spring vibration isolators. The anchor bolts shall be supplied complete with the diesel generator sets. 

 

Ignition of the fuel or air charge, when operating in the dual fuel or diesel oil modes, will be by heat of compression. In the dual fuel mode, ignition shall be by pilot fuel oil supplied by direct injection into the cylinder. 

The diesel generator will reach, in normal procedure, nominal operating speed and voltage and at least 1/3 of its full load capacity within 60 seconds, or less, after receiving a start signal when kept warm as described herein. Full 

Annex‐A58  

load at stable nominal speed and voltage shall be delivered in accordance with manufacturer’s instructions but not more than300 seconds from the start signal. All piping serving the engine‐generator set will have flexible connectors and supports. 

C.4.1. FuelSystemThe Diesel Generator shall be designed and supplied for dual fuel operation, namely both, liquid fuel oil #2 and natural gas.  

C.4.1.1. LiquidFuelSystemThe Liquid fuel shall be Diesel Fuel Oil (LFO) ASTM No.2, known in Israel as "Soler", with the following parameters as per Israeli Standard No. 107: 

Property  e.u.  Value 

Density at 15C  g/ml  0.870 max. 

Flash point (closed) Pensky‐Martens  C  66 min. 

Pour point  C  0 (Nov.‐Mar.) 

5 (Apr.‐Oct.) 

Sulfur content  % weight  0.2 max. 

Copper strip corrosion at 100C for 3 hours 

  No. 1 max. 

Kinematic viscosity at 40C  cSt  2.5 ‐ 6.0 

Carbon residue on 10% bottoms  %  0.2 max. 

Ash content  % weight  0.01 max. 

Water content  % weight  0.05 max. 

Sediment content  % weight  0.01 max. 

Cetane Number    N/A 

Gross calorific value  Kcal/kg  10000 min. 

Distillation at 357C  % weight  90 min. 

Total acidity    0.7 max. 

Annex‐A59  

To enable the operation with the liquid fuel, the diesel generator set shall be provided with a day tank with a total capacity of 10 m3 and will be installed at ground level and will be positioned outside the building, near the engine. See IAA chapter C appendix I for contractor approval or the contractor may offer alternative as part of value engineering during the bid. The contractor design shall include but will not be limited to: 

A. Tank dimensions  

B. Concrete containment enclosure (in which tank will be installed at 

C. Pipe connections  

D. Valves and counters 

The tank shall be connected by means of a manually operated valve to enable maintenance work on the tank. 

Tank shall have threaded pipe connections, float switch, fuel analog gauge (flag type), high‐high level, high level low level and low‐low level alarm contacts wired to a local PLC. The local PLC shall transfer signals to the Main Utilities PLC through I/O system, controlling fuel pumps operation for tank refilling the same signal will operate an air operated valve, the air to the valve will pass via a pilot operated mechanical floating system. A mechanical float shutoff valve and a manual shutoff valve on the engine supply line and a drain valve will also be included. 

As on option:  the contractor shall offer supply of additional day tank at capacity of 10m3 that will be connected to the existing LFO system and will be replace the old daily tank that shall be remove from the site by the contractor. 

The design of this option shall be based on the existing design system the two tanks will be in the same and will be interchangeable. 

      

The diesel fuel oil injection system shall be pump‐timed type with the amount of fuel being controlled by the governor. The fuel pump(s) shall be attached as an integral part of the engine. 

Fuel injection system shall be designed with injection nozzles and fuel oil lines for each cylinder. Fuel injection nozzles shall be liquid‐cooled (kept warm when the engine is not running) with jacket water as the coolant. Isolating valves shall be provided to allow for the removal of any injection nozzle without drainage of coolant. 

A heat exchanger for return fuel cooling shall be supplied, mounted nearby the diesel generator and connected to the cooling water system as described here. The diesel generator contractor will accomplish cooling loop including piping, control and measuring devices as required. The fuel excess shall be returned to the day tank passing the heat exchanger. 

 

   

Annex‐A60  

 

C.4.2. NaturalGasFuelSystemNatural Gas specifications are according to data available from Israel Natural Gas Line ("INGL") and/or the gas distributor stated below: 

At the battery limits the Natural Gas pressure will be available at 4.0 Bar: 

The Natural Gas Higher Heating Value shall be between 0.0346 to 0.0395 MBTU/m3. 

"CUBIC METER" (m3) means a cubic meter at standard conditions, being a temperature of fifteen (15) Degrees Celsius and pressure of 1.01325 Bar(a). 

Natural Gas which will be distributed shall, at the Natural Gas Supply Terminal, be free from odors, materials, dust or other solid or fluid matter, waxes, and shall contain no more than 1 (one) part per million of condensates. 

Expected Natural Gas Parameters: 

Methane  Contain not less than ninety five (95.0) per cent by volume of methane (CH4) 

Water Dew Point  Not greater than zero (0) Degrees Celsius at any pressure up to and including eighty (80) bars gauge. 

Hydrocarbon Dew Point 

Not greater than five (5) Degrees Celsius at any pressure up to and including eighty (80) bar gauge. 

Total Sulphur  Normally not more than one hundred (100) parts per million by volume of total sulphur expressed as hydrogen sulphide at any time 

Hydrogen Sulphide  Not more than eight (8) parts per million by volume of hydrogen sulphide at any time and no more than five (5) parts per million during any eight (8) hour period). 

Carbon Dioxide  Not more than three (3.0) mol per cent of carbon dioxide. 

Total Inerts  Not more than five (5.0) mol per cent of inerts. 

Oxygen  Contain not more than one tenth (0.1) parts per million by volume of oxygen. 

Higher Heating Value  have a Higher Heating Value which is not less than zero point zero three five (0.035) MMBTU per Cubic Meter and not more than zero point zero three eight (0.038) MMBTU per Cubic Meter. 

Temperature  have a temperature which is not less than five (5.0) Degrees Celsius and not more than thirty eight (38.0) Degrees Celsius. 

 

The natural gas system must include provision of check metering facilities, on‐line analysis facilities (to determine the heating value of the natural gas), together with natural gas separators and pressure reducing stations (to be supplied by INGL (the Israeli National Gas 

Annex‐A61  

Transportation Company).  Natural gas piping and systems shall comply with the Israeli standards, and to be designed in accordance with Israel Natural Gas Company and Israeli Nat. Gas authority requirements. 

 

The generator engine will be supplied and installed with all the necessary accessory devices needed for operation in gas. 

The contractor shall provide documents and detail drawings for gas operation and will include the following but will not be limited to: 

A.  Gas pressure at the engine; 

B.  Detail drawing for the gas system (pipe, valves, safety valves, measuring device and all other accessories required); 

C.  Connection point inside/ outside the building to the gas supplier;  

D.  List of input data that will be connected to the PLC and to the fire alerts system;     

E.  Safety protection against gas leaks; 

F.  Special tools;  

G.  Safety regulation 

The Contractor shall include within its scope of supply, an electrical heater with heating capability of 30 up to 500C, to allow a smooth and continuous operation of the plant during the deviation from specification of the natural gas, mainly in hydrocarbons and water content (about two weeks per year, due to the maintenance works of the natural gas supplier). The heating equipment is in addition to the INGL heating system with heating capability of up to 300C. 

   

Annex‐A62  

C.4.3. ExhaustSystemThe contractor will furnish an exhaust silencer for the diesel generator set. The silencer equipment shall have capacities as recommended by the engine manufacturer and shall reduce noise to the level required by environmental regulations. 

The exhaust silencer shall be of the industrial grade incorporating a flanged inlet and outlet. 

The silencer shall be from welded steel construction suitable for 

engine exhaust up to 700C. The unit shall be a chamber type. All internal tubes shall be perforated and inner liners shall be provided in each chamber to ensure the industrial level of sound attenuation. 

The exhaust silencer shall be equipped with hand holes in each compartment, explosion relief covers and a drain valve. 

The exhaust silencer shall be supported on suitable fabricated galvanized steel supports for mounting on a concrete pad. Support dampers and springs shall be included where necessary to isolate vibration. 

The silencer shall have a minimum dynamic insertion loss of 25 decibels over octave band center frequencies ranging  from 63 to 8,000 Hz. Pressure loss through the silencer at the exhaust gas flow rate will not exceed 7 inches WG. 

Each engine cylinder and each part of exhaust system shall be equipped with thermocouples for exhaust gas temperature measurements. 

All necessary heat wrapped elbows, flexible exhaust connectors and expanders shall be provided. Piping will be self‐supported and braced to prevent any weight or thermal growths from being transferred to the engine. Flexible expansion fittings shall be provided to accommodate thermal growth. Piping supports shall be provided where necessary. 

Exhaust piping shall have appropriate thermal insulation with galvanized steel cover preventing occasional contact with hot pipe.  

On the exhaust system outlet an exhaust gas temperature measuring device shall be installed including local scale as well as 4‐20 mA temperature transducer for temperature reading by local PLC. 

A 30 meter height self‐supporting stack with a silencer shall be supplied and installed by the contractor for the diesel generator set. The stack structure will be made of at least 10 mm thick anti‐corrosive treated steel with heat resistant painted, and will be stable suitable to withstand wind forces,  damped to prevent stress, and sufficiently durable to endure metal “fatigue”. Welded inside of it, will be rod ladder stairs to reach the top. External exhaust piping and silencers shall have thermal insulation of at least 10 cm in thickness, covered with stainless steel to top off silencers. A proper foundation will be provided for stack and air filter. No anchoring wires shall be 

Annex‐A63  

allowed. External steel parts shall be paint protected. General design shall be in visually similar to the existing stack.  

C.4.4. LubeOilSystemThe engine shall be provided with a forced fed lubricating oil system. A positive displacement lubricating oil pump shall be provided and equipped with a positive drive from the crankshaft. 

 

 Cylinder wall lubrication shall be provided by mechanical lubrication. 

 

The contractor shall provide the equipment necessary to complete the lubrication oil system external to the diesel engine. A lubricating oil storage tank equipped with high level and low level alarm contacts, lube oil strainers and filters, lube oil cooling system and lube oil keep warm system, shall be supplied and mounted including all control and measuring devices, as required. 

 

Provisions shall be made for the removal of lubricating oil from the engine and the lube oil system without disassembly of the lube oil system. The pre‐lube system shall consist of two pumps one electrical and one pneumatic. 

The lube oil keep warm system shall be installed including heat exchanger. The contractor shall accomplish the secondary keep warm loop including piping, two electrical motor driven oil pumps or approved equal, three‐way adjustable bypass valve and all control and measuring devices as required. 

 

The lube oil cooling system shall be installed including heat exchanger as described here. The contractor shall provide the cooling loop including piping, two electrical motor driven oil pumps or approved equal, three‐way adjustable bypass valve and all control and measuring devices as required. The pumps will keep minimum oil pressure for parallel mode 

 

All piping serving the engine‐generator set shall have flexible connectors and supports. 

 

The lube oil strainers shall be of the basket and cartridge type. Temperature and pressure gauges shall be provided for the strainers as required being scaled for the normal operation ranges. 

 

The lube oil filter shall be of the cartridge type for continuous bypass operation and provided with a pressure gauge, relief valve, spare cartridge and automatic air vent. The pressure gauges shall be scaled 

Annex‐A64  

for the range of pressures anticipated for normal operating conditions. 

 

Two sludge tanks with storage capacity of 3 m3 each shall be provided. Sludge tank shall be equipped with level switches for automatic level control. The waste oil will be collected in the sludge tanks. When the high level is reached, the waste oil shall be transferred to the drain pipe means of electrical motor driven oil pump (one pump per sludge tank). 

C.4.5. AirStartingThe complete air starting system is an integral part of this contract. 

Rotation of the engine shall be accomplished by an air motor driving system or air stating valves and shall be designed so that the engine shall be started at any position. 

The contractor shall supply two compressed air receivers for the diesel‐generator set having storage capacity to provide five consecutive starts. 

Air compressors shall be installed near the generator to supply compressed air needed to fill these receivers. 

The air compressors should be operated to control air pressure as follows: 

B. ON/OFF / AUTO  

C. Red lamp in case of a fault in the air compressors 

D. Loss of pressure alarm signal 

 

The system must be able to handle the black start conditions, i.e. no electrical power supply and no air pressure to start emergency power generator. 

C.4.5.1. CompressedAirSystemforStartingGenerator

The compressed air system for generator starting will be installed according to the relevant standards.  All specifications herein are supplementary to the specification mentioned above. The whole compressed air supply system: compressors, receivers (cylinders), valves, filters, coolers, control board, piping, all equipment as a whole will be supplied and installed, as an integral part of the supplied generator. The system will supply adequate compressed air at the required flow and pressure (adjusted to the ambient conditions of the location where it is installed) in order to have a minimum of 5 starts at the same time (tri‐sequence operation). The system will work with reciprocating compressors, 30 bar working pressure.  The system will have a double‐piping system supply. The required size and technical 

Annex‐A65  

data/performance of compressors, receivers and all other equipment will be adapted ‐ at no additional cost ‐ in order to meet the requirements for starting the generator. All the changes/adaptation of equipment size or performance will be done with the approval of the project manager. 

The following information is prepared for reading by the Main SCADA system by means of digital and analog I/Os. The information will be transferred to the proper SCADA controller and by means of holding registers in the local PLC(s) intended to be read by the Main SCADA system: 

B. Air pressure in the system (Loss of pressure alarm) 

C. Operating status of the compressor (running, failure) 

D. Motor current of the compressor 

E. Status of control devices 

F. Control valves operating 

Technical demands for Air Compressor 

1. Piston Air Compressor, oil‐lubricated, complete with direct flanged motor from the selected list of suppliers: 

“ATLAS COPCO”. 

“INGERSOLL RAND”  

“COMPAIR‐REAVELL” 

Or Ohaliav Compressors israel. 

or approved equal. 

2. Minimum free air delivery at normal working pressure and 1,500 rpm: 35 CFM. 

3. Squirrel‐cage induction motor, flanged with the Compressor Unit.  Maximum noise level: 89 dB (A), measured at 1 m. distance, 3‐phase, 50 Hz., 400V, IP45/55. 

4. With inlet silencer filter, safety valve, discharge pressure gauge, shutoff valve. 

5. Oil level protection. 

6. High temperature protection of outlet air. 

7. With air‐cooled after cooler, water separator, drain valve, air filter. 

8. With silencing hood and ventilator. 

9. Control/regulation and instrument panel with: 

ON/OFF switch with full automatic load/unload operation 

Auto restart and emergency stop 

Hour counter 

Automatic alternator to equalize running time of each unit 

Adjustable electric contacts, set to start and stop at different pressures 

Pressure and temperature switches 

Annex‐A66  

Adjustable idling timer 

Rubber cork pads and springs, as by Mason Industries, “Vibration mountings” or approved equal 

Technical demands for refrigerated Air Dryer 

1. Air flow: 70 CFM 

2. Working pressure: 30 bar 

3. Self‐contained, complete with heat exchangers, moisture separator,  manual bypass 

4. Heat Exchanger: Air to refrigerant coils with centrifugal‐type moisture separator and automatic trap assembly 

5. Refrigeration unit: hermetically sealed, to maintain dew point of 6°C at ‐20 bar, housed in steel cabinet with access door and panel 

6. Freon magnetic solenoid valve 

7. Air‐inlet temperature gauge and pressure gauge 

8. Control panel with micro‐processor with: 

Dew‐point indicator 

High‐temperature light 

POWER ON light 

Contacts for remote indication of power status and high‐temperature alarm 

9. Receiver (Capacity as recommended by Manufacturer) working pressure 30 bar 

Test pressure:          45 bar 

Size:       900 mm. diameter 

      2,300mm overall height 

Sheet steel:   SA516/70 

With: 

A. Manhole 

B. Relief valve 

C. Pressure gauge 

D. Drain test cock 

E. Automatic moisture removal trap 

Outside paint: primer and two epoxy coats 

Factory Test Certification 

Comply with ASME Boiler and Pressure Vessel Code, Section VIII, “Pressure Vessels” 

   

Annex‐A67  

C.4.6. Blackstart   A separate 0.4kV generator that is part of this bid, is located outdoor in order to supply a super‐essential power to that system in case of both normal and essential power failures. 

C.4.7. CoolingSystemsThe water for the cooling system shall be supplied by cooling radiators installed on the roof of the new Energy Center extension. The contractor shall provide the primary cooling loop for the diesel generator set with electrical motor driven centrifugal pumps for the following systems: Jacket water cooling heat exchanger, expansion tank, lubricating oil cooling heat exchanger, fuel cooling heat exchanger, generator air cooler, piping, piping accessories, controls and measuring devices etc. as required. 

The secondary loops shall be executed as described in the corresponding paragraphs. 

The cooling water temperature and pressure shall be measured in sufficient points of the cooling system. The measured values shall be read by the Main SCADA system as described hereafter. High and low alarms shall be executed locally as well as, monitored by the Main SCADA system. 

Cooling water system shall be supplied by galvanized steel pipes and all piping accessories, supports, gauges and insulation. 

Piping shall be pressure tested, flushed and chemically treated prior to system start up. Procedures should be documented in the commissioning manuals.

C.4.8. Keep‐WarmSystemThe contractor shall accomplish the primary keep warm loop for the diesel generator set with electrical motor driven centrifugal pump, jacket water keep warm heat exchanger, lube oil keep warm heat exchanger, piping, control and measuring devices as required. 

The secondary keep warm loops shall be executed as described in the corresponding paragraphs. 

The contractor shall install hot water heaters (electric boiler) for heating the water, according to the manufacture recommendation for starting the engine in E‐mode. The capacity of the electric boiler will be calculated by engine manufacture. 

The hot water temperature and pressure shall be measured in sufficient points of the keep warm system. The measured values shall be prepared for reading by the Main SCADA system as described hereafter. High and low alarms shall be executed locally as well as prepared for reading by the Main SCADA system. 

Keep warm water system shall be performed from galvanized steel pipes and appropriate equipment and isolation.  

Annex‐A68  

Piping shall be pressure tested, flushed and chemically treated prior to system startup. Procedures should be documented in the commissioning manuals. 

 The system shall be similar to the system now working on site. The System to include but not limit to: 

large insulated water collector 

external electric heater 

SS dry coil, pumps 

Connection to the exciting  electric boiler system the Water temperature 60 degrees 

flexible connections, valves, insulated piping,   

safety elements 

PID controller connected to BMS SCADA etc.

C.4.9. FlywheelThe flywheel shall be of the solid type with size and weight as required. The flywheel shall have sufficient mass to prevent undue fluctuation in speed and voltage. The flywheel shall be designed according to transient stability requirements calculations. 

The periphery of the flywheel shall have a ring gear to permit turning the engine over with a manual barring device or with the air motor starter. 

The flywheel shall be inscribed for every degree from 0 degrees to 20 degrees, both left and right of top dead center for each cylinder. Sufficient numbers shall be used to facilitate reading. 

C.4.10. BarringDeviceThe engine shall be equipped with a manually and electrical Motor operated turning gear that will, when meshed with flywheel ring gear, be capable of barring the engine over from any position. The electrical motor shall have the option to rotate in two directions   

C.4.11. ProtectiveDevices‐DieselorGasEngineAn adjustable over‐speed device with spare auxiliary contacts, separate from the engine, shall be provided to close the fuel injection pump racks to the NO FUEL position in case of over‐speed. 

Fuel oil, fuel gas, lubricating oil, air receiver and jacket water pressure devices as well as jacket water temperature, lubricating oil temperature and air receiver temperature devices shall be provided being wired to a JB in the installation/ From the JB to the local PLC provide an alarm on failure or abnormal pressure or temperature or any other value given by any other protective devices recommended by the manufacturer and installed by the contractor and wired as described here. 

Annex‐A69  

C.4.12. GovernorThe engine governor shall control engine speed and transient load response within commercial and referenced standard tolerances. 

The governor shall be mechanical with hydraulic assist as required. The transient response and steady state stability of the engine shall be in compliance with ISO Class 2 requirements. 

The maximum generated power shall be determined for the unit from the Main SCADA system through compatible communication link as described hereafter. 

C.4.13. AccessoriesThe following accessories, in addition to those specified shall be supplied and installed:  

All piping supports and flexible piping connections.  Piping insulation.  Piping accessories; temp and press indicators and transmitters, air vents, drain valves, future connection valves, etc. 

 

C.4.14. Shut‐OffValves1. Ball valve, three‐piece, fill port 

2. Body: Carbon steel 

3. Ball and Stem: Stainless Steel 316 

4. Working pressure: 30 bar 

5. Connections: welded, socket welded or butt‐weld ends 

C.4.15. AnchorBoltsAnchor bolts of the sizes and lengths required by the manufacturer shall be furnished with the engine/generator/exciter skid. The anchor bolts shall be designed to be embedded in the concrete foundations. 

All anchor bolts shall be provided with hex nuts, washers and pipe sleeves of an internal diameter equal to twice the diameter of the bolts. 

   

Annex‐A70  

C.5. Electricalandcontroldesign

C.5.1. GeneralThe generator shall have the ability to operate manually from the local control station and/or automatically from the control room.  The generator will be synchronized with the existing electrical power supply system before connection can be done. 

C.5.2. LocalSwitchboardsandControlPanelsThe contractor shall furnish a control panel, a PLC panel and Motor Control Center panel for the diesel generator set and the accessories and added on systems. All these panels shall be located in the electrical equipment room. The contractor shall provide overall dimensions of above mentioned panels with his proposal. 

All equipment inside a panel (including PLC‐I/O, etc.) must be monitored and displayed on SCADA in case of a failure. Note: I/O card external power supply most be monitored from an adjacent I/O card to distinguish between card and power supply failure. All other signal dependencies must be treated similarly. 

C.5.3. ControlPanelThe control panel will include as follows: 

1. protection relays 

2. load sharing and speed control device 

3. Import/export load commander 

4. Automatic synchronizer 

5. Automatic voltage regulator 

6. Alarm signaling devices ( annunciation or LCD display) 

7. Selector switches and push buttons as required 

8. General failure indicating beacon light and horn 

The Control panel shall also include measuring devices as follows: 

1. Engine RPM meter 

2. Left turbocharger RPM meter 

3. Right turbocharger RPM meter 

4. Engine operating hours.  Accumulator (totalizer) 

5. Exciter voltage meter 

6. Exciter current meter 

7. Three generator current meters (one per phase) 

8. Active power meter 

9. Reactive power meter 

10. Power factor meter 

Annex‐A71  

11. Double bus‐generator voltage meter 

12. Double bus‐generator frequency meter 

13. Synchroscope 

14. Temperatures. 

15. Pressure. 

16. HT controller.  

C.5.4. WorkingStation(For HMI stations, Engineering, Trends, Reports, etc.) 

The  contractor  shall  supply  four  (4)  fully  equipped  operator  workstations connected to the generator control panel: 

The working stations shall be supplied: 

located in Gen‐5 control room  

Central control room (CCR) of the Energy Center with 42 screen. 

The Both computers shall be able to monitor and control the Gen 5 systems,  the  new  building  systems,  and  the  synchronizing  routing system.  

C.5.5. Historicaldata.The system shall have the ability to collect all historical DATA that are required for performance and Maintenance. The information shall be storage for five years and shall include but not limit to: 

Generator production capacity 

Internal electrical consumption 

NG  consumption 

LFO consumption 

Heat rate consumption 

Emission level   

Noise level  

Faults and alarm list 

And all data that are specified in section C.5.7       

Annex‐A72  

C.5.6. MotorControlCenter(MCC)seechapterEThe motor starters for the auxiliary equipment shall be of standard types as shown in the attached drawings. 

 

Motor starters should be supplied by the contractor and installed in MCC panels. VSD units exceeding 25 KW shall be installed out of the MCC panel, IP30. The control of those VSD units will be in the MCC panel, complete wiring between VSD units and the MCC panel.  

 

Control voltage for 0.4kV motors MCCs will be 230 VAC. PLCs control voltage is determined to be 24 VDC, and all operating signals from PLCs to the control equipment installed in different MCCs will be transmitted by means of 24 VDC interposing relays. These interposing relays should be installed in MCCs by the contractor and wired by him up to MCC control terminals. 

The desired signals from motor starters to PLCs will be transmitted using the control equipment dry contacts. The necessary wiring within MCCs up to control terminals will be executed by the contractor. The control voltage for these signals will be 24 VDC, supplied from PLC panels. 

The control voltage for all analog signals should be supplied from DC power supplies located in PLC panels. 

Local control station should be located near each motor. A three‐position control switch, a set of 2 push buttons and a lockable mushroom push button should be installed in such a station for motor local operation.  

The positions of control switch should be as follows: 

a. OFF ‐ disables motor operation whether in automatic operation mode or manual. 

b. Operation mode: 

i. MANUAL ‐ enables motor operation by the push buttons 

ii. AUTO‐ remote starting/ PLC/ operated, Lockable mushroom push button: 

Normal position‐ enable 

Activated position‐ disable in Manual or Auto mode 

Release of the push button‐ only with a proper key by an authorized person. 

Junction box (JB) should be installed on site for each group of motors. Motor local control equipment, such as thermistor temp sensors, vibration sensors, temperature sensors, etc., will be wired to the junction box. Separate JB for 230 AC control voltage and for 24VDC control voltage shall be supplied. 

 

A multi‐wire control cable(s) shall connect each junction box with the corresponding MCC pane   

Annex‐A73  

C.5.7. PLCpanel

C.5.7.1. PLCPanel All indoor equipment will be mounted in enclosures ‐ IP42 with 

integrated fans and filters with flow switches. 

Enclosures shall be with front access only, with hinged doors and locks. All locks shall be keyed alike. 

Incoming and outgoing cables shall be wired to screw type wire connectors and not directly to the I/O racks. 

All wiring within the enclosure shall have numbers stamped on the wires and color coded according to the voltage level. 

Each I/O card, CPU etc. shall be protected by a miniature circuit breaker. 

Main switches shall be mounted on the door. 

The PLC panel shall be protected by both, surge arrestor and lightning arrestor 

The I/O Section shall contain two terminal blocks for I/O wiring. 

Terminal block: 

1. One terminal block (TBP) will be used for I/O cards wiring. The terminal order will  follow  the order of  I/O points  in  installed I/O cards. 

2. The  second  terminal block  (TBF) will be used  for  field  cables wiring.  Its  terminal  order  will  follow  the  order  of  wires  in connected cables 

3. .Cross‐wiring  shall  be  executed  between  the  two  parallel terminal blocks completing the I/O loops 

4. Terminal block colure shall be in accordance with annex E. 

C.5.7.2. SupplyVoltages The supply voltage is 230 volts  10 %, 50 cycles  230VAC  incoming  power  supply  for  the  PLC  will  be  brought  in  from 

critical power distribution Panel. 

Digital  input/outputs  shall  be  24V  DC.  The  supply  voltage  for  the  (4‐20mA) analog I/O shall be the same. 

C.5.7.3. PLCComponents The local PLCs shall be of industrial type and the latest model. Power for 

all  equipment  installed  within  the  PLC  panel  shall  be  supplied  from Critical Power Supply Panel by mean of circuit breaker with appropriate rating.  

Analog I/Os shall be typically 4‐20 mA loops. 

Annex‐A74  

Wherever  required  contractor  shall  supply and  install a 4‐20 mA  / 4‐20 mA or 4‐20 mA / 0‐10 V etc. transducers to  isolate any field device  local supply. These transducers shall be installed in the PLC enclosure. 

All  PLC  components  shall  be  immune  to  RF  /  EM  radiation.  Additional equipment  shall  be  installed  if  required  to  prevent  RF  /  EM  radiation influence. 

PLC shall be  installed  in enclosures with 10% additional wired and ready to use I/Os of each type. 

All  local PLCs  including  their  I/O cards shall be supplied,  installed, wired and programmed by the contractor. Allow 25% I/O card extra capacity. 

In addition to the above the PLC shall have 20% spare slots and available I/O addresses of each I/O type for an additional 25% I/Os 

This incoming supply shall serve all the internal voltages as required, logic power supply, power supply for communications, etc. 

Each  module  (and  the  CPU)  shall  be  equipped  with  spike  voltage suppresser. 

C.5.7.4. CPUandI/OCardHousings(racks) The  logic  power  supply,  the  I/O  scanners,  the  data  interface  and  all 

input/outputs  shall  be  installed  in  card  racks  allowing  removing  and interchanging of all components without wiring disconnection. 

The  racks  shall  be  wired  to  exterior  separate  connectors  within  the enclosure. 

I/O card assignment within each rack shall be via software. 

Shock resistance: 10G for 10ms. 

C.5.7.5. CommunicationInterfacesThe  local PLC shall  include communication module suitable for redundant fast Ethernet communication system Modbus TCP/IP protocol and BAC net protocol of EC building. 

C.5.7.6. CommunicationsThe  communication  equipment  supplied  by  the  contractor  shall  be  fully compatible with  the main communication system provided by  the SCADA contractor.  Protocol  converters,  adapters  and  other  means  shall  be supplied by the contractor if necessary to fulfill this requirement. 

The contractor shall provide the communication protocol to fit the SCADA connectivity  requirements  and  PLC  addressing  with  complete documentation and explanations. 

Annex‐A75  

C.5.7.7. PLCprogrammingPLC  programming  shall  be  performed  in  ladder  logic  diagram  or/and  in high‐level  language.  Ladder  logic  and  program  documentations  shall  be written in English. 

 

   

Annex‐A76  

C.5.8. Connectivity

C.5.8.1. ConnectivitywithMainElectricalSystem

The generator unit shall be connected to 12kV breaker supplied and installed by the contractor. The contractor shall perform an insulation coordination study to see if the breaker should be ordered for higher voltage range. 

 

The switchboard's cubicle will contain a 12kV circuit breaker, current transformers, fuse‐protected potential transformers and control terminal block for generator's protection devices connections. 

 

The protection relays of generator units shall be coordinated for selective operation. All control and protection wiring within the generator unit shall be performed by the contractor. For external connection to the main electrical system, terminal boards shall be provided within the generator's panels.  

 

Generator's beaker will be connected to the 22kV grid trough a step‐up transformer and 24kV switchboard as shown in the single line drawing. 

Generator's power shall be distributed in three ways: 

1. By adding additional cubicle to switchboard HVP‐100 

2. By adding additional cubicle to switchboard HVP‐200 

3. Through new switchboard HVP‐600, allowing bypassing the energy center network 

 

The synchronizing system of generator 5 shall be designed to 

synchronize the main breakers in HVP‐100, HVP‐200, HVP‐600. 

Annex‐A77  

C.5.8.2. GroundingThe generator's neutral shall be grounded via a grounding resistor. This resistor shall be rated for voltage of 11kV and shall have a withstanding capacity of 15 A for 10 seconds. Temperature sensor shall be incorporated in the resistor winding, enabling continuous reading of winding temperature by local PLC. In the case of temperature rise, appropriate alarm shall be activated. 

Continuous reading of grounding current shall be provided by means of toroid current transformer installed on the grounding conductor. 

The protective grounding system shall be designed as required by the Israel Electrical Law. 

Local grounding (equipotential) buses will be installed within the generator hall. 

The contractor shall be responsible for ensuring of grounding continuity of all systems supplied that have been supplied by the contractor. 

C.5.8.3. ConnectivitywithmainSCADAsystem

The operation of the diesel‐generator unit shall be fully controlled by local PLC supplied by the contractor as an integral part of this bid. The local PLCs shall be equipped with proper communication devices to be able to communicate with the Main SCADA System. The main operating parameters of the diesel‐generator units as well as alarm conditions and protection relays activity shall be read by the Main SCADA System using the mentioned communication system. 

In addition to above mentioned, the Main SCADA System will be able to read status of auxiliary system and to operate the low and medium voltage switchboard via the local PLC.    

The current values of the operating parameters shall be arranged as the consecutive table of registers in the local PLC. The contractor shall provide the PLC addressing (reference number) for each operating parameter including the data format (integer, signed integer, long integer, floating point number, etc.) and engineering units used for measuring of each value. 

The following values and parameters shall be prepared by the contractor to be read by the Main SCADA System (all sensors, measuring instruments, transmitters, etc. necessary for these indications shall be provided by the contractor as an integral part of this contract): 

 

1. Diesel‐generator unit status (remote control, local control, off, lockout) 

2. Each auxiliary motor (e.g. air compressor) status (run, fault) 

Annex‐A78  

3. Generated power 

4. Generator frequency 

5. Voltage on the generator terminals 

6. Phase current earth leakage current 

7. Generator speed 

8. Generator temperature 

9. Generator's excitation current and voltage 

10. Generator power factor  

11. Lube oil pressure at pump discharge 

12. Lube oil pressure at engine header 

13. Lube oil temperature at pump discharge 

14. Lube oil temperature at engine header 

15. Fuel oil consumption 

16. Natural gas consumption (preparation only) 

17. Fuel oil pressure 

18. Fuel oil temperature at heat exchanger inlet 

19. Fuel oil temperature at heat exchanger outlet 

20. Jacket water pressure 

21. Jacket water temperature at jacket inlet  

22. Jacket water temperature at jacket outlet  

23. Intake air temperature before and after air cooler 

24. Air cooling water pressure 

25. Air cooling water temperature before and after air cooler 

26. Air pressure in each compressed air cylinders 

27. Keep warm water pressure 

28. Keep warm water temperature after each heat exchanger 

29. Exhaust gas temperature for each engine cylinder 

30. Exhaust gas temperature in exhaust duct at the rapture disc connection, inside the building  

31. Exhaust gas temperature at exhaust silencer outlet 

32. Vibration monitoring level for each main bearing and alarms 

33. Vibration monitoring for main mechanical coupler, motor – alternator, and alarms 

34. TCa. rpm 

35. Control air pressers  

36. Stating air pressing 

37. Maun bearing and connecting rod bearing temperature   

 

All other values and parameters, in addition to the mentioned above, required for the comprehensive data collection of all systems and subsystems of the diesel generating plant, shall be provided for monitoring by the Main SCADA system. 

The alarm conditions of the diesel‐generator as well as the protection relays operation will be logged in the PLC internal table(s) 

Annex‐A79  

for further reading by the Main SCADA system. The alarm log table will include the times and codes for the 25 most recently occurring events and alarms, that took place in the localized system. For this purpose, two 25‐register tables shall be prepared in the local PLC. One of these tables shall gather times of events, and the second table–event codes. Both tables will be filled simultaneously by FI‐FO in a first in – first out method. 

The contractor shall provide the PLC addressing (reference number) for these tables as well as the alarm codes' description. It is important to synchronize the local PLC clock used for the alarm logging to the Main SCADA system clock. Therefore, the local PLC clock shall be updated from time to time by the Main SCADA system. The contractor shall provide a procedure to update the "real time" clock of the local PLC via the communication link with the Main SCADA system. 

 

The maximum allowed generated power shall be determined by the Main SCADA system through the communication's link. This value will limit the unit operation either in stand‐alone mode or in load sharing mode. In the load sharing mode of operation, the power generated by the limited unit shall not exceed the limitation, while the other units, that are not limited, will share the remaining load. 

 

Two discrete control signals will be transmitted from the Main SCADA system by means of voltage free contacts: remote start command and remote stop command. The remote stop signal shall be always accepted by the local control system and will cause an immediate shutdown of the unit. The remote start signal shall be accepted only if the local selector switch is in the "remote control" position, otherwise it will be ignored. 

 

An analog signal shall be issued by the Main SCADA system determining the total generated power required. The load sharing control system shall be affected by this signal and will properly control all operating and connected generating units in consideration of the individual limitations for each unit as mentioned above. 

   

Annex‐A80  

C.5.8.4. Connectivitywithenvironmentsystem

The Contractor shall implement an effective Environmental Management System to control environmental performance of the project, see Appendix H 

The Environmental Management System shall have the ability to emissions Monitoring (CEMS) the flue gas from the exhaust stack. The monitoring shall be in compliance with the requirements of all Environmental Laws and in accordance with all the relevant Environmental Approvals, but shall, as a minimum, be monitored continuously for NOx, CO. The continuous monitoring shall include relevant process operation parameters such as oxygen content, temperature and pressure. The continuous measurement of water vapor content of the exhaust gases shall not be necessary, provided that the sampled exhaust gas is dried before the emissions are analyzed. 

Representative measurements i.e. sampling and analysis of relevant pollutants and process parameters as well as reference measurement methods to calibrate automated measurement systems shall be carried out in accordance with CEN (Committee European de Normalization) standards or Israeli standards. 

Continuous measuring systems shall be subject to control by means of parallel measurements with the reference method at least once per year . 

SO2 and particulates shall be measured at least every 6 months. All monitoring and sampling should follow the relevant CEN standards 

 

 

 

 

 

 

     

 

Annex‐A81  

C.5.9. SynchronizingSystem

C.5.9.1. AutomaticSynchronizerA microprocessor‐based automatic synchronizing device shall be provided for the diesel‐generator set. The synchronizer shall initiate a closure of the generator circuit breaker, located in the 12kV main switch board, when voltage magnitude, slip frequency and phase difference are within preset limits. The synchronizer will calculate an advance angle based on preset circuit breaker closing time and maximum allowable slip frequency. It shall deliver the breaker closing signal ahead of synchronization so that actual closure of the breaker contacts occurs when the phase angle between the "generator" and the "bus" voltage are within the predetermined limits. A dead bus feature will be available to allow immediate closure under the circumstance of total power failure. 

After the breaker close contact has been closed, the synchronizer will go into lockout position if the breaker reopens within 15 seconds. This is to prevent repeatedly closing the breaker into a fault. If a lockout occurs, the synchronizer will be inhibited from further operation until reset. Reset may be done manually or it will occur automatically if the breaker is closed by other means and remains closed for 15 seconds. 

A special watchdog circuit shall check that the microprocessor is operational. If some transient condition has disrupted its normal pattern of operation, the watchdog circuit will reset the microprocessor and reinitialize the program.  

C.5.9.2. SynchronizingRoutingSynchronization may be done at different points of electrical system. In the most common and most simple case, generator shall be synchronized with the corresponding field bus in the 22kV switchboard and the appropriate 11kV circuit breaker will be closed. In some cases, however, either the synchronization between different fields of 22kV switchboard need to take place, or a synchronization with the main power supply from IEC at 22kV level may be required (22kV Main entry breaker should be closed). 

A synchronizing routing panel will be installed performing the required switching of voltage/frequency sensing lines and circuit breakers' closure control lines between automatic synchronizer of the generator and pre‐defined synchronization points of the electrical system. 

 

A terminal strip will be prepared for each 22kV cubicle in synchronizing routing panel, containing terminals for "bus" and "generator" voltage/frequency sensing, breaker closure signal and breaker opening/closing position, routing these signals to appropriate potential 

Annex‐A82  

transformers and circuit breakers as is needed for required mode of operation. 

 

The operation of the mentioned synchronizing routing panel is the generator's contractor responsibility. Cooperation between generator's contractor and IAA's SCADA contractors shall be coordinated by the CPM for the site test and commissioning. 

C.5.10. ProtectionSystemThe following protection relays will be installed in circuit breaker cubicle: 

1. Instantaneous over‐current relay 

2. Time over‐current relay 

3. Thermal image overload relay 

4. Phase balance relay 

5. Lockout relay with manual reset 

 

The contractor shall accomplish the generator protection system, including control/measurement cables connection, using the above listed relays and providing additional protection devices as follows: 

1. U/F over fluxing relay 

2. Under‐voltage/over‐voltage relay 

3. Reverse power relay 

4. Over‐excitation relay 

5. Loss of excitation relay 

6. Current negative sequence relay 

7. Over‐current relay with voltage control/restraint 

8. Earth fault relay 

9. Over‐frequency/ under‐frequency relay 

10. Phase differential relay 

 

The protection relays provided by Generator Supplier shall be installed in the generator's control panel. Modern multifunction relays with built‐in RTU, communication and diagnostic features shall be preferred. Each action of the protection relays shall be logged in the local PLC to be read by the Main SCADA system. 

   

Annex‐A83  

C.5.11. LoadSharingControlThe load sharing control shall be provided for diesel generator units matching the load carried by different units. Load sharing will be capable to operate automatically in "Island Mode". The isochronous mode shall be used usually. The load sharing system supplied by the contractor shall be able to work with other existing generator units working in parallel as well as with other combination groups according to the 6.3kV tie breaker and 22kV breakers positions. The system shall be capable to limit the load carried by each single unit in conformity with external analog signals, e.g. in the case a unit overheating takes place. 

All parts of the load sharing control system shall be of low voltage design suitable for 24 VDC power supply. 

 

The AVR system shall be capable of working automatically in "Island Mode" and in parallel with the IEC network. When operating in parallel with the IEC, the power factor set‐point shall be controlled by the Main SCADA system. 

 

   

Annex‐A84  

C.6. UpgradingExistingGeneratorsSynchronizationRouting‐OptionalThis section is pertaining to the option to replace the existing Synchronization 

Routing Panel (SRP) installed inside the EC building and to making any 

changes to existing generators control panels.  The work shall be performed 

only after Gen 5 project is completed and tested. 

The SRP is designed for "loss of mains" detecting, starting of the four existing 

generators and synchronizing them to the grid. It allows making synchronizing 

operations via the SCADA system or manually via the panel switches using the 

synchronizing modules of the generators.  

Existing Synchronization Routing Panel 

 

 

 

The required change at existing generator's control panels is to disconnect 

the Basler Synchronizing units installed at the lower part of each panel and 

instead connect the synchronizing modules that already exist inside the 

SYNPOL‐D generator control relays 

Annex‐A85  

 

Existing generators control panel 

 

 

 

The synchronizing of the complete power plant, GEN. No.1 to GEN. No.5 will 

be done also by synchronizing and routing system installed in GEN. No.5 

control room. 

   

Annex‐A86  

C.6.1. DescriptionoftheCurrentOperationIn general, each generator has to be synchronized with the existing electrical 

power supply system before connection can be done. 

 There are a few common cases of existing generator synchronization 

procedures, as follows: 

C.6.1.1. Case1:NoPowerSupplyfromIEC;1.  first generator has to start (Dead Bus) 

2. No synchronization is needed in this case 

3. Main 22kV entrance breakers should be disconnected 

4. The generator might be connected to the bus when voltage 

and frequency generated by it are within normal limits 

5. The first portion of essential loads (first priority) should be 

reconnected consecutively while the generated power 

increases 

C.6.1.2. Case2:NopowersupplyfromIEC22kV;

1.  Main entrance breakers should be disconnected 

2. Tie breakers 102 and 320 are opened. No generators are 

working connected to the same busbar in the 6.3kV switch‐

board as the target generator. 

3. This case is similar to the case described in the previous sub‐

paragraph 

C.6.1.3. Case3:NopowersupplyfromIEC;1.  one generator is working  

connected to the same field in 6.3kV switchboard as the target  

generator 

2. 22kV Main entrance breakers should be disconnected. Tie 

breakers 102 and 320 are opened. 

3. The target generator should be synchronized with 

corresponding field in 6.3kV switch‐board. 

   

Annex‐A87  

 

C.6.1.4. Case4:NopowersupplyfromIEC;1.  one generator is working  

connected to the other field in 6.3kV switchboard as the 

target  

generator 

2. 22kV Main entrance breakers should be disconnected. Tie 

breakers 102 and 320 are closed. 

3. This case is similar to the case described in the previous sub‐

paragraph 

C.6.1.5. Case5:NopowersupplyfromIEC1. 22kV Main entrance breakers should be disconnected. Tie 

breakers 102 and 320 are opened. 

2. There are working generators connected to both fields in 6kV 

switchboard 

3. Generator G300 should be synchronized with non‐

corresponding field in 6.3kV switch‐board in case tie breaker 

320 is closed. 

C.6.1.6. Case6:Electricaldistributionsystemisfedfromemergencygenerators

1. 22kV Main entrance breakers are opened. Tie breakers 102 

and 320 are closed. IEC power supply is restored. 

2. All working generators should be synchronized simultaneously 

with 22kV Main entrance to enable 22kV Main entrance 

breaker closing. 

   

Annex‐A88  

C.6.1.7. Case7:Electricaldistributionsystemisfedfromemergency generators

1. 22kV Main entrance breakers are opened. Tie breakers 102 

and 320 are opened. IEC power supply is restored. 

2. All working generators connected to each field in 6.3kV 

switchboard should be synchronized simultaneously with 

corresponding 22kV Main entrance, to enable corresponding 

22kV Main entrance breaker to close. 

C.6.1.8. Case8:Peakshavingmodeisconsideredtobeasfollows:

1. Case 8.1: Both 22kV Main entrance breakers (101, 201) are 

closed. 

The tie breakers 102, 320 are opened, i.e., the system is 

divided to two independent parts. 

In each part of the system the generators should be started 

one‐by‐one, independently, and synchronized with 

corresponding 6.3kV bus. 

2. Case 8.2: One 22kV Main entrance breaker (either 101 or 201) 

is closed, while the other is opened. 

The tie breaker 102 is closed, while the tie breaker 320 is 

opened. 

The generators should be started and synchronized 

consecutively with corresponding 6.3kV bus. 

There is no need to connect the grounding transformers and 

disconnect transformers' neutral grounding, in peak shaving mode, 

when the local generators are working in parallel with normal IEC 

power supply. 

   

Annex‐A89  

 

Synchronizing routing panel is supervised by the SCADA system providing 

updated parameters (GV ‐ generator voltage, BV ‐ bus voltage) to each 

generator accordingly to desired connection point. The parameters for 

synchronization (voltage, frequency) are measured by means of potential 

transformers from both sides of the breaker (CB) that makes the connection. 

The table below lists the potential transformers supplying the 

measurements for each mentioned case. 

GEN100  GEN200 GEN300 

  GV  BV  CB GV BV CB GV  BV  CB

Case 1  PT304  PT301 304 PT303 PT301 303 PT313  PT312 313

Case 2  PT304  PT301 304 PT303 PT301 303 PT313  PT312 313

Case 3  PT304  PT301 304 PT303 PT301 303 PT313  PT312 313

Case 4  PT304  PT301 304 PT303 PT301 303 PT313  PT312 313

Case 5  PT312  PT301 320 PT312 PT301 320 PT312  PT301 320

Case 6  PT102  PT101 101 PT102 PT101 101 PT102  PT101 101

  PT202  PT201 201 PT202 PT201 201 PT202  PT201 201

Case 7  PT102  PT101 101 PT102 PT101 101 PT202  PT201 201

Case 8.1  PT304  PT301 304 PT303 PT301 303 PT313  PT312 313

Case 8.2  PT304  PT301 304 PT303 PT301 303 PT313  PT312 313

 

The synchronization routing panel is a stand‐alone system, driven by its own 

PLC, but it has data handshake with the EC Electrical Distribution Main PLC. 

Each breaker, mentioned in the table above should be checked for automatic 

operation mode, truck in operating position and protection relays non‐lockout 

status, while each relevant potential transformer should be checked for phase 

balance and under‐voltage conditions before the requested routing may be 

performed. 

In the case of IEC power supply total failure, all available generators should be 

started, synchronized and connected to electrical system as soon as possible. 

Annex‐A90  

When the main IEC power supply is restored, the previous connected 

emergency generators should remain working for a certain period of time, thus 

creating a situation similar to peak shaving mode as described further. After this 

time delay, and verifying that the normal supply is steady, the generated power 

should be decreased close to zero and the generators should be disconnected 

and stopped one by one. 

Annex‐A91  

D. ChapterD‐MediumVoltage

D.1. POWERTRANSFORMER

D.1.1. GeneralThis specification covers the requirements for the supply and installation of indoor, oil filled, three phase, and two copper windings, Generator step up power transformer. 

The contractor shall furnish and install complete, new power transformers, auxiliary systems and works as specified herein and required for a complete installation, start‐up, operating and commissioning. 

Transformers shall be operated in electrical polluted environment that includes large motors and large frequency converters. The manufacturer shall include in his proposal, a description of his design considerations for transformers operation under these conditions.  

The transformer intended to be connected directly to a generator; therefore it should meet load rejection conditions as described in IEC 60076‐1. 

D.1.2. GeneralData:1. 10 MVA ONAN/ONAF (Sizing can be changed according to Generator 

MVA rating + 10%) 

2. 11/22 KV 

3. 50Hz 

4. Connection group: Ynd11 

5. Uk%= 8% 

6. Maximum winding temperature rise of 55ºC at full ONAN/ONAF capacity 

7. Maximum oil temperature rise of 50ºC at full ONAN/ONAF capacity 

8. Oil preservation system. 

9. 22kV neutral side may be floated or connected to the ground via grounding resistor. 

10. NLTC of 0, ±2.5, ±5,±7.5% . 

D.1.3. SupplyandInstallationThe present specifications shall mean supply and installation, which will include the following for every part of the work and for the whole work: 

1. Factory witness tests 

2. Storage and delivery to site 

3. Coordination with other contractors. 

4. Installation on site 

Annex‐A92  

5. Commissioning, testing on site before electrifying and Setting to work. 

6. As made documentation and manuals 

7. Training of staff for operation and maintenance 

8. Warranty period

D.1.4. StandardsThe following table indicates the general standards for the transformer. Additional standards may be required in the following detailed design sections. 

Description  Standard 

Specification for unused mineral insulating oils for 

transformers and switchgear IEC 60296 

Power transformer  IEC 60076 

General  IEC 60076‐1 

Specification for temperature rise requirements  IEC 60076‐2 

Specification for insulation levels and dielectric tests  IEC 60076‐3 

Specification for tapping and connections  IEC 60076‐4 

Specification for ability to withstand short circuit  IEC 60076‐5 

Specification for bushings for alternating voltages above 

1000V IEC 60137 

Packaging code  BS1133 

Introduction to packaging  BS1133 Section 1‐3 

Protection of metal surfaces against corrosion during 

transportation of storage BS1133 Section 6 

Metal containers  BS1133 Section 10 

Methods of protection against shock  BS1133 Section 12 

Specification for cable boxes for transformers and reactors  BS2562 

Radiographic examination of fusion coded butt joints in steel  BS2600 

Annex‐A93  

Description  Standard 

Method of radiographic examination of fusion welded 

circumferential butt joints in steel pipes BS2910 

Specification for granular desiccant silica gel impregnated with 

cobalt chloride BS3523 

ISO metric screw threads  BS3643 

Principle and basic data  BS3643 Part 1 

Specification for selected limits of size  BS3643 Part 2 

Specification for ISO metric black hexagon bolts, screws and 

nuts. Metric units. BS3692 

Specification for approval testing of welders when welding 

procedure approval is not required BS4872 

Specification for tests on hollow insulators for use in high 

voltage electrical equipment 

IEC 233 

Code of practice for protective coding of iron and steel 

structures against corrosion BS5493 

Specification for sound level meters  IEC 60651 

Determination of transformer and reactor sound levels  IEC 60551 

Specification for unfilled enclosures for the dry termination of 

HV cables for transformers and reactors BS6435 

Guide to loading of oil‐immersed power transformers  IEC 60354 

Power transformers – oil draining devices  DIN42551 

Deaerator and filling nozzle for transformer  DIN42553 

Thermometer case for oil immersed transformers  DIN42554 

Transformers – magnetic oil indicator  DIN42569 

Screwed glands for cables  DIN46320 

Annex‐A94  

D.1.5. TransformerRatingsandOtherDataRatings of the transformer shall be based on the following temperature conditions: 

1. Winding temperature rise as measured by resistance at 55C. 2. Top oil temperature rise as measured by thermometer at 50C. 3. Maximum temperature of the cooling air as measured by thermometer 

at 40C. 

D.1.6. LossesThe maximum permitted losses, with no tolerance allowed, on nominal tap is: 

Power  No load (excitation)  Load (copper) 

At 10MVA  9KW  40KW 

D.1.7. CoolingSystemThe Transformer shall be air cooled, ONAN /ONAF. The cooling system shall be divided into sections (or coolers), one of them being considered a reserve section. The reserve cooling section shall normally be in operation to maintain free oil circulation. In a forced outage of any cooling sections, cooling shall continue without exceeding temperature rise limits. 

Pipe connections to the cooling sections shall be removable, and the cooling sections shall be replaceable without lowering the oil level in the tank. Vent holes with plugs shall be provided at the top and drain holes with plugs at the bottom of each radiator. 

The operation alternatives of the cooling system (ONAN/ONAF) shall allow operating the transformer at the power indicated in Paragraph “C” and in the temperature conditions indicated in “Site Conditions”. 

Provision shall be made for using power supply sources 3x400 volts, 50 Hz, provided by the purchaser. 

A complete control system for automatic operation of the cooling system shall be provided, including automatic transfer from one operation alternative ONAN/ONAF to another. An alarm shall be included for exceeding the limit temperature conditions. The control system shall be operated from the winding temperature and shall comprise the following: 

Winding temperature simulator device with thermal element mounted in a well and responsive to the hottest simulated winding temperature of the transformer or manufacturer’s standard. 

Switching for automatic and manual control. 

Wiring for cooling equipment. 

 

Remote control circuits of the cooling system shall include: 

Position signal of the selector switch for automatic or manual control. 

Alarm signal for power source failure. 

Annex‐A95  

Alarm signal for circuit‐breaker or contactor trip by protection or manual operation. 

Winding and oil temperature remote LCD unit, to be installed on the front door of the 12kV or 22kV panel. 

The contractor shall supply two N.O/N.C sets of dry contacts for all alarms and indicators. 

Contractor shall include the “Power and Control Voltage Supply Diagram” and the “automatic Control Design” in the proposal.  

D.1.8. TestsThe transformer shall be subjected to the following production routine, mechanical, dielectric, etc., type tests at the manufacturer’s plant to check the quality and uniformity of the workmanship and materials used in manufacture of the transformer. The tests shall be performed according to applicable IEC Publications, unless otherwise specified. 

Production tests, routine tests, mechanical tests, dielectric tests, etc., shall be performed as specified, and copies of the relevant test reports shall be submitted to the CPM for his review and approval. 

Contractor shall also submit test data to prove that the design has the capability to meet all the ratings and performance specified. 

Contractor shall submit copies of test procedures to be performed at the factory, and on‐site, after installing the transformers and during operation. 

Each transformer shall be subjected to all routine tests according to latest IEC Publication 60076‐1, unless otherwise specified. 

Measurement of impedance voltage, short circuit impedance and load loss shall be performed at principal tap, and on the highest and lowest tap. 

The tank and oil filled compartments shall be tested for oil tightness. The test shall be performed according to manufacturer’s standards. The contractor shall supply with his required submittals, manufacturer’s data which indicates how the oil leak test will be performed. 

Mechanical test shall be made on tanks, oil level gauge, etc., for proper functioning. 

 

Type tests shall include the following tests: 

Measurement of acoustic sound level (guaranteed). The measurement of sound level shall be performed according to NEMA standard TR‐1. The test shall be made on the energized transformer at no‐load. 

Temperature tests. 

Oil temperature rise at top of tank 50ºC. 

Expected temperature rise of windings under rated conditions 55ºC. 

Insulation level and dielectric tests. 

 

Annex‐A96  

After assembly, the transformer shall be subjected to high voltage dielectric tests, according to IEC Publication 60076‐3, and amendment, unless otherwise specified. During these tests, the transformer shall be equipped with the bushings that will be used in permanent operation. 

Power frequency separate source tests. 

Lightning impulse on line terminals. 

Lightning impulse on neutral terminal. 

Induced over‐voltage test. 

Measurement of the polarization index. 

The rated withstand voltage of the windings and the application of the above tests shall be as follows: 

1. Rated lightning impulse withstand voltage 1.2/50 sec:  22KV line terminal‐ 125kv peak 

22kV neutral terminal‐    125 kV peak 

11kV line terminal‐   75 kV peak 

2. Rated short duration power frequency withstand voltage: 

22kV line terminal‐ 50kV rms 

11kV line terminal‐ 28kV rms 

22kV neutral terminal‐ 50kV rms 

 

The lightning impulse test shall be made on each unit, for both line terminals, in the following order: 

1st‐Reduced voltage full wave ‐ one application 

2nd‐Chopped wave ‐ two application 

3rd ‐ Full wave ‐ one application 

 

The peak value of the chopped impulse and the time to chopping shall be as follows: 

22KV ‐ 125kV peak 

11kV ‐ 75 kV peak 

Time to chopping 2 sec Impulse tests on transformer neutral shall consist of one (1) reduced voltage full wave and two (2) full wave tests. These tests shall be performed on each transformer. 

Neutral current measurement shall follow each reduced and full voltage wave if current records are not obtained simultaneously with voltage records. 

 

Measurement of polarization index: 

Measurement of the polarization index (the ratio of apparent insulation resistance after 10 min. to that after 1 min. after the application of testing voltage), shall be made with 5kV DC voltages. 

The measurement shall be done: 

Between HV winding and LV winding, (tank connected to guard) 

Annex‐A97  

Between HV winding and tank (LV connected to guard)  Between HV winding and tank (LV connected to guard)  Between LV winding and tank (HV connected to guard)  The tank shall be grounded during all measurements 

Test report for the polarization index measurement as well as variation of apparent winding insulation resistance with time shall be provided. 

Each transformer shall be designed and constructed to withstand thermal and dynamic effects of external short circuits, according to IEC Publication 60076‐5, without damage. 

Contractor shall comply with measurements indicated in the following table. 

 

Subject  22kV –side  11kV‐ side 

Number Q. Bushing   4  3 

Rated withstand voltage (kV Bil)  125  75 

Impulse withstand voltage positive and negative (kV  peak)  

125  75 

One minute power frequency test ( kV rms) 

50  28 

Creepage  not less than (mm)  800  450 

No of HV arcing horn gaps (not less than 120o) 

2  2 

 

The client explicitly requires that Contractor submit data from the manufacturer that indicates in summary form the type and the name of the manufacturer of all bushings, on the HV side and LV side. 

Bushings shall be designed and tested according to IEC Publication 60037. In lieu of this design and testing, the manufacturer shall design and test bushings in accordance with approved local procedures and standards, suitable for the applicable service conditions, and shall submit a certified statement indicating that the bushings comply with all Contract requirements. 

Bushings shall have temperature limits according to IEC Publication 60137, clause 10. 

Transformer leads for the high voltage and low voltage windings and LV Neutral shall be brought out through the cover of the transformer tank for connection to conductors/cables. 

 

 

 

 

 

 

 

Annex‐A98  

D.1.9. Structure Studs, as well as their threaded holes, used in various sub‐assemblies in contact with the atmosphere shall be silicone greased before fastening. 

The bottom of the transformer shall have a steel skid base, suitable for skidding in direction parallel to both center lines of the tank. A plan with all relevant dimensions shall be provided. Contractor shall submit an accurate plan that indicates all relevant dimensions to the CPM for his review and approval. 

Thermally upgraded paper or approved equivalent shall be used for winding insulation. 

The tank shall be designed to withstand full vacuum. The construction of the tank shall enable easy removal or installation of bushings and current transformer, without disturbing the leads, emptying the oil from the transformer, or removing the cover. 

Painting of the transformer tank, lid, conservator and all other parts shall include: 

100 micron hot‐spray galvanizing 

150 micron hot‐spray galvanizing layer. 

Two 40 Micron (min.) Epoxy based primer layer. 

Two 80 Micron (min.) outer gray epoxy glossy paint layer (oven baked). 

 

The finish and painting of the tank shall enable it to satisfactorily withstand the most severe service conditions normally expected or encountered at the site. 

Transformer oil shall meet the requirements indicated in GE Specifications for mineral insulating oil, No. A13A3A2 and shall be "NYNAS Inhibited" type. 

Technical data and oil test report shall be submitted to the PM for his review and approval. 

Oil preservation system shall be provided for protecting oil against atmospheric moisture and oxygen. 

Silica‐gel air drier for oil preservation shall be mounted and shall be clearly visible through a glass. 

Paint, insulation materials, and all other materials in contact with transformer oil shall not contain any substance that may, to any extent, influence its dielectric properties or result in chemical reactions with the oil, or in any way lead to a deterioration of oil quality. 

Manufacturer shall provide two (2) 55 gallon drums over and above the quantity required to fill each transformer tank. 

The details of the oil preservation system shall be completely described in the proposal. 

The oil preservation system shall be provided with all necessary drain corks, plugs for oil filling, connections to tank, etc. 

“Bucholz” fault gas pressure device shall be provided to suit manufacturer’s method of oil preservation. 

Annex‐A99  

Rating plate shall list the rating of the transformer with forced and natural 

cooling at 55C and 65C rise in addition to the data specified in Publication 60076‐1 of the IEC Recommendations. 

In order to determine the extent of the field installation, Contractor shall supply manufacturer’s list all items which will be shipped separately. It is understood that items not so listed in Summary of Data will be shipped completely factory installed and factory connected. 

D.1.10. ControlcabinetandwiringAll necessary automatic control, motor starters, protective devices, switches, etc. of each transformer shall be assembled in a dust proof and weather‐proof, hot dip galvanized, metal cabinet arranged for satisfactorily mounting on each one of the respective transformer units (Space shall be reserved for future additional cooling equipment switch gear). 

The control cabinet shall be accessible from ground level. The cabinet shall be provided with a door for front access, handles, locking facilities (key locks) and all equipment required for local operation. 

The cabinet shall be provided with type IP54 environmental protection, according to DIN 40050 and shall be fit for plant "Site conditions". 

Small wiring for control or accessory equipment shall have 600 volts, 90C, polyvinyl chloride insulation with flameproof braid covering or cross‐linked polyethylene, and shall be installed in standard galvanized rigid steel conduits, or electrical metallic tubing or ducts, with watertight joints. 

Small wiring enclosures shall be grounded. 

A weather proof box shall be provided for terminating the conduits and wiring for exterior connections. 

Drain holes shall be provided at low points of boxes and conduits. 

Power and control circuit conductors shall be adequately dimensioned and shall not be smaller than 2.5 sq. mm. 

Control and instrument wiring, alarm leads and instrument transformer secondary connection to incoming cables shall be terminated at terminal blocks. Blocks shall be spaced to allow 1 1/2 inch clearance on all sides. Extra space shall be provided for training and crossing incoming leads. 

Ten (10) free terminals shall be left for future use in each terminal block. 

The control cabinet shall be supported by a suitable vibration damping devices. 

Compression type (solder‐less) lugs shall be furnished with each terminal block for incoming control wires. The size of these control wires shall be as indicated on the drawing or approved by the CPM. 

Provide a 11W, 230VAC PL lamp in each of the enclosures together with a switch that is mounted inside the box. 

The assembled control equipment and wiring connections shall be subjected to a one minute test of 2000 VAC at the factory, after fabrication and assembly is complete. 

   

Annex‐A100  

D.1.11. AdditionalaccessoriesTransformer shall be furnished with the following additional accessories: 

1. Lifting eyes for transformer cover and lugs for safely lifting the assembled transformer. 

2. Four (4) jacking points shall be provided at a height not less than 350mm to transformer foundation. Location and relevant dimensions shall be submitted to the CPM for approval. 

3. Pulling eyes shall be provided at the base of each transformer for skidding transformer parallel to either center line of the transformer. 

4. Provide a thermal image system for indication of hot‐spot temperature. The thermal image system shall include: 

a. Standard resistance temperature element for measuring hot spot temperature. 

b. Hot spot temperature indicator shall be furnished for the transformer for use with the above resistance temperature element. In case the indicator shall also be used for an alarm signal, it shall be connected to DC auxiliary supply. Hot spot temperature indicator shall be suitable for flush mounting on the control panel. 

c. The heating resistance shall be fed by a bushing current transformer. A bushing current transformer shall be provided for this purpose on the HV winding terminal. The rating and other parameters of bushing current transformers shall be established by the manufacturer, suitable for measuring. 

5. Four (4) grounding pads with tapped holes, one on each side of the transformer. Locations shall be as indicated on the relevant drawings. 

6. Pressure Relief Devices 

7. Oil level gauge, magnetic type, with low level alarm contacts for 220 VDC ungrounded service. 

8. Oil drain and filter valve, (2 inch minimum). 

9. Oil sampling connection (3/8 inch minimum) placed on the drain side of the drain valve. 

10. Top connection with 1 inch, or larger, valve for oil purifier. 

11. Dial type hot oil thermometer with manually reset maximum indicating hand and 250 VDC ungrounded alarm contacts to close on high temperature. 

 

Sudden pressures relay (Bucholz) 

A Bucholz or sudden pressure relay shall be supplied, to protect the transformer against damage due to internal faults. 

The relay shall operate on the base of pressure change. The relay shall have at least two sets of N.O/N.C contacts, one to activate the alarm and the other for trip. The relay shall be installed at the connection pipe between the highest point of the tank and the oil conservator.  

Annex‐A101  

The contractor shall install valves, with SCADA indication contacts, to bypassing the relay and for taking gas samples (while the transformer is loaded). 

D.2. AUXILIARYTRANSFORMERS

D.2.1. GeneralThis paragraph covers the specifications and requirements for a low losses, oil immersed, sealed tank, three phase, two copper windings and 22/0.4kV power transformer. The transformer shall be used for energizing VFD motors and standard domestic loads. 

 

Two transformers shall be supplied: 

1. Rated power for type 1 1600kVA 

2. Rated power for type 2  630kVA  

D.2.2. SystemdataThe system has the following characteristics: 

Rated system voltage (line to line) 22kV ± 10%

Nominal Highest system voltage (line to line) 24kV

Frequency 50Hz ± 4%

Utility side grounding Grounding 

transformer

 

For calculation of the short circuit current at transformer terminals, the 

short circuit power of the 22kV system shall assume to be 750MVA. 

The power transformer will be installed indoor. 

The transformer shall be connected to 22kV utility network.  

 

Annex‐A102  

D.2.3. StandardsDescription  Standard 

Specification for unused mineral insulating oils for 

transformers and switchgear IEC 60296 

Power Transformer  IEC 60076 

General  IEC 60076‐1 

Specification for temperature rise requirements  IEC 60076‐2 

Specification for insulation levels and dielectric tests  IEC 60076‐3 

Specification for tappings and connections  IEC 60076‐4 

Specification for ability to withstand short circuit  IEC 60076‐5 

Specification for converter transformers for industrial 

applications  IEC 61378‐1 

Three‐phase oil‐immersed distribution transformers 50 Hz, 

from 50 kVA to 2500 kVA with highest voltage for equipment 

not exceeding 36 kV 

DIN EN 50464‐1/40/ 

Specification for bushings for alternating voltages above 

1000V IEC 60137 

Packaging code  BS 1133 

Introduction to packaging  BS 1133 Section 1‐3 

Protection of metal surfaces against corrosion during 

transportation of storage BS 1133 Section 6 

Metal containers  BS 1133 Section 10 

Methods of protection against shock  BS 1133 Section 12 

Specification for cable boxes for transformers and reactors  BS 2562 

Radiographic examination of fusion coded butt joints in steel  BS 2600 

Method of radiographic examination of fusion welded 

circumferential butt joints in steel pipes BS 2910 

Specification for granular desiccant silica gel impregnated 

with cobalt chloride BS 3523 

ISO metric screw threads  BS 3643 

Principle and basic data  BS 3643 Part 1 

Specification for selected limits of size  BS 3643 Part 2 

Specification for ISO metric black hexagon bolts, screws and 

nuts. Metric units. BS 3692 

Annex‐A103  

Description  Standard 

Specification for approval testing of welders when welding 

procedure approval is not required BS 4872 

Specification for tests on hollow insulators for use in high 

voltage electrical equipment 

IEC 60233 

Code of practice for protective coding of iron and steel 

structures against corrosion BS 5493 

Specification for sound level meters  IEC 60651 

Determination of transformer and reactor sound levels  IEC 60551 

Specification for unfilled enclosures for the dry termination of 

H.V. cables for transformers and reactors BS 6435 

Guide to loading of oil‐immersed power transformers  IEC 60354 

Power Transformers – Oil draining devices  DIN 42551 

De‐aerator and filling nozzle for transformer  DIN 42553 

Thermometer case for oil immersed transformers  DIN 42554 

Transformers – Magnetic oil indicator  DIN 42569 

Screwed glands for cables  DIN 46320 

D.2.4. ElectricaldataTransformer rated power at 55C  rise (KVA)   

Type 1  1600kVA 

Type 2  630kVA 

Highest primary system voltage (kV)  24 

System primary neutral  IECo substation  

System secondary neutral  Solid Ground 

Transformer connection group  Dyn11 

Rated voltage of primary winding (kV)  22kV 

Rated voltage of secondary winding (kV)  0.4kV 

Duty  Continuous 

Annex‐A104  

Rated lightning impulse withstands voltage.  125 kV peak 

Noise levels at 1m  50 db (max.) 

Temperature rise limit  55/60ºK 

K factor   

Type 1  6 

Type 2  1 

Short circuit impedance voltage:  Uk%   

Type 1  6% 

Type 2  4.5% 

Short circuit duration  2s 

OFF load tap‐changer:  

Full capacity is required for the entire range of 

voltage regulation 

 

Number of taps  5 

Voltage range (%)   +5, +2.5, 0, ‐2.5, ‐5 

Rated step voltage (kV)  0.55 

At principal tap (‘O’ position), transformer 

ratio shall be: 

22/0.4kV 

Bushings and terminals:   

Nominal voltage for MV plug‐in bushing  24kV rms 

Rated withstand voltage for MV plug‐in 

bushing kV (BIL) 

125kV 

Rated lighting impulse withstand peak voltage  125kV 

Creepage distance LV side: (mm)  90mm as Minimum 

Air clearance to earth LV side: (mm  58mm as Minimum 

Annex‐A105  

D.2.5. Losses:Maximum allowed losses according to Israeli 

standard IS 50464 ‐1   for distribution 

transformers 

Ao Ak 

D.2.6. ConstructionTransformer shall be three phase, oil immersed, self‐cooled, designed for indoor installation. 

Oil shall be free from PCB (Polychlorinated Biphenyls) and a certificate for "PCB free" shall be submitted.  

The core shall be manufactured of grain oriented transformer sheet steel to ensure low core losses, accurate dimensions and flatness. The core shall be glued. Yokes shall be pressed together with steel sections. Steel sheet cutting 

angle shall be 45 to reduce losses and noise. The MV and LV windings shall consist of copper wires or copper foils with press board insulation between them. 

Transformers shall be equipped with a manual type, off load tap changer. The contacts shall be designed in such a way that an increase in load shall increase the contact pressure. The operating handle shall have a position maker with a latch for each position thus preventing the tap charger from being set between the two positions. The operating handle shall have provisions for a padlock. 

Transformer shall have corrugated sheet steel tank cover for increased cooling. 

MV bushings shall be according to DIN 42532‐30 and IEC Publication No. 60076. 

LV bushings shall be according to DIN 42539. Marking of phase and neutral shall be clear. 

Transformer shall have the following paint layers: 

1. 100  micron hot‐spray galvanizing layer 

2. Two 40 Micron (min.) Epoxy based primer layer. 

3. Two 80 Micron (min.) outer grey epoxy glossy paint layer (oven baked). 

Transformers shall be vacuum dried while coils are heated. Oil filling shall be 

made under vacuum with degassed oil 

Annex‐A106  

Transformer Tank Hermetic Sealed

Transformer skid type On wheels

D.2.7. TestesEach transformer shall be supplied with its own test report. Testing shall be carried out according to I.E.C 60076 latest edition, and as follows: 

D.2.8. TypeTestsType test certificates for the following tests of identical design of transformer shall be submitted with the bid. The certificates shall be issued by a reputable and internationally recognized testing body or the testing laboratory of the manufacturer. The same tests shall be carried out during the acceptance testing of the first consignment of transformers for each transformer rating. Cost of tests shall be included in the price of the transformers. 

1. Temperature rise test. 

2. Noise level tests. 

3. Impulse test. 

4. Withstand short circuit test. 

D.2.9. RoutineTests1. Transformer ratio. 

2. Winding resistance. 

3. Vector group test. 

4. Short circuit tests to determine load losses and short circuit impedance. 

5. No load test to determine no load losses and no load current. 

6. Dielectric Tests. 

7. Insulation resistance. 

8. Induced over voltage withstand test (100 Hz and twice the nominal voltage) 

9. Short duration AC test .(power frequency) 

10. Oil pressure test on transformer to check against leakages past joints and gaskets. 

Contractor shall perform production tests to check the quality and uniformity of the workmanship and materials used in the manufacture of the power transformers. 

Contractor shall also submit test data to prove that the design has the capability to meet the ratings and performances specified. 

Contractor shall submit a list of all production tests to be performed at the factory and a list of tests to be performed on site, after installing power transformers and during operation. 

Annex‐A107  

D.2.10. AccessoriesTransformers shall be supplied with the following accessories: 

1. MV plug‐in bushings. 

2. LV bushing with flat terminal Acc. To DIN 42539. 

3. Earth connection. Acc. To DIN 48088. 

4. Rating plate. 

5. Terminal marking plate. 

6. Bi‐directional rollers Acc. To DIN 42561. 

7. Lifting lugs. 

8. Bi‐directional hauling lugs. 

9. Oil drain device Acc. To DIN 42551. 

10. DGPT2 protection unit with Dial thermometer. 

11. Wheels 

12. Safety valve. 

Annex‐A108  

D.3. NEUTRALGROUNDINGRESISTOR

D.3.1. GeneralNeutral grounding resistor (NGR) shall be connected to the star point of the 

generator step‐up transformer at the 22kV side. The NGR shall be energized 

via motorized MV disconnect or creating a ground reference point when the 

power source is the local generator in island mode. 

The rated earth fault current or specified thermal current shall be 500A at 15 

seconds. The Bidder shall quote for neutral grounding resistor with final 

temperature as per allowable limit due to the specified current for specified 

time.  

The resistor unit shall be air‐cooled type suitable for installation also at 

outdoor locations.  

Rated system voltage (line to line): 22kV. 

Highest system voltage (line to line): 25.8kV. 

System neutral effectively earthed. 

Frequency: 50Hz. 

For calculation of the short circuit current at transformer terminals, the 

short circuit power of the 22kV system shall be assumed to be 750MVA. 

D.3.2. Technicaldata 

The resistor element shall be made of non‐aging stainless steel or equivalent 

corrosion resistant material having high electrical resistivity and low 

temperature co‐efficient of resistant. The NGR shall have temperature 

limited to the maximum allowable temperature for the material offered 

considering the air ambient temperature at site as mentioned earlier.  

The resistor unit shall consist of a no. of elements. All the elements shall be 

mounted inside the cubicle so as to ensure ease of inspection and 

replacement of individual element. The resistors shall be edge‐wound type.  

Resistor element shall possess a balanced combination of both mechanical 

and electrical properties over the entire intended operating temperature 

range without any harmful effect on the elements and their accessories.  

All resistor elements constituting the NGR shall be assembled and supported 

inside the cubicle in such a way that no distortion or breakage shall occur 

during the passage of through fault current to earth. 

All element connections shall be bolted type to ensure stable resistance 

value throughout the working life of the unit.  

Wet process type brown glaze porcelain insulators shall be used for 

supporting resistor elements. Porcelain insulators shall have high creepage 

value suitable for heavily polluted atmosphere charged with dust particles.  

Annex‐A109  

D.3.3. EnclosureThe neutral grounding resistor shall have structural steel work enclosed on 

all sides and on top by sheet steel having a minimum thickness of 3 mm. 

Suitable ventilating louvers shall be provided on sides to ensure proper 

ventilation. The louvers shall be provided with fine wire mesh to make it 

vermin proof.  

Enclosure shall be self‐supporting, weather proof type suitable also for 

outdoor mounting having a protection class as indicated in "ratings and 

requirements table".  

Cubicle shall be complete with a front access door with handles, lock and 

also a removable bolted cover. All doors and removable covers shall be 

properly gasketed with neoprene rubber gaskets. All cubicle door hinges 

shall be concealed type.  

Cubicle shall be complete with a suitably mounted cable end box fitted with 

removable double compression brass type cable gland for fixing cable gland. 

The cable size shall be as indicated in the annexure. Double compression 

cable gland and tinned copper lugs shall be provided.  

Cubicle shall be provided with suitable base channels for direct bolting to 

the foundation at site. All necessary galvanized bolts, nuts, washers etc. shall 

be supplied by the Bidder for installation of Cubicle at site.  

Cable entry in NGR enclosure shall be from the upper part.  

Fine mesh screen of corrosion resistant material shall be furnished on all 

ventilating opening to prevent entry of insects.  

D.3.4. CurrentTransformerThe toroidal (window type) current Transformer shall be cast resin type, 

insulation class ‘B’, suitably mounted inside the NGR cubicle in such a way as 

to ensure easy removal and/or maintenance works. 

The secondary leads of CT shall have polarity markings as per IS. The 

secondary leads shall be brought out to the terminals at terminal box 

provided at suitable location completely isolated from high voltage 

equipment.  

D.3.5. WiringAll internal wiring between control or measuring equipment and terminal 

block shall be carried out by PVC insulated grade 2.5 Sq.mm stranded 

copper conductor wires.  

All wiring shall be suitably ferruled with corresponding wiring identification 

marks used in the schematic / wiring diagrams.  

All devices and terminal blocks within the terminal box shall be clearly 

identified by symbol corresponding to those used on applicable 

Annex‐A110  

schematic/wiring diagram. 20% spare terminals shall be provided in terminal 

block.  

D.3.6. GroundingAll parts of enclosure, supporting structures, equipment frames etc. shall be 

properly grounded at two points separately.  

Cubicle shall be completed with two (2) nos. ground pads, tapped holes and 

bolts suitable for connection of 2x150mm2 copper wires.  

D.3.7. Tests

D.3.7.1. RoutineTestsThe NGR shall be completely assembled, wired, adjusted and 

routine tested as per relevant standards at manufacturer's 

works. The tests shall include:  

1. Resistance measurement  

2. Voltage measurement  

3. Insulation resistance measurement  

4. Dielectric test 

5. Type Tests  

Type test reports shall be subject to the approval of Owner. In 

case the bidder has to carry out these type tests, all such tests 

shall be done at bidders risk and cost within the schedule 

specified herein. No deviation in this regard is acceptable.  

   

Annex‐A111  

D.3.7.2. DRAWINGS,DATA&MANUALS1. Proposal sheets duly filled in.  

2. Scheme showing series/parallel combination of resistor 

elements. 

3. Dimensional general arrangement drawings showing 

constructional features etc. along with necessary 

foundation plan.  

4. Cable termination details.  

5. Technical leaflets on each piece of electrical equipment 

along with write up on salient features.  

6. Type test certificate of similar type and rating of offered 

equipment.  

7. Instruction manuals for the complete system. The manual 

shall clearly indicate method of installation, checkups and 

tests to be carried out before commissioning of the 

equipment.  

8. Any other relevant drawing or data necessary for 

satisfactory installation, operation and maintenance.  

Annex‐A112  

D.4. MVSwitch‐Gear

D.4.1. General   This section includes 22kV and 12kV switchgear. 

D.4.2. SubmittalsThe bidder shall submit with the bid the following documents and 

information: 

1. General structural drawings. 

2. Typical cubicle drawings (internal and external) with equipment specified. 

3. One line diagram of the switchgear. 

4. Technical information and catalogue/data sheet of main equipment, 

including breakers, earthling switches, contactors, potential and current 

transformers, bus‐bars, protection relays, H.V. fuses, surge arrestors, 

control relays, selector switches, etc 

D.4.3. DocumentsThe Contractor shall submit within 30 days after notification of award, for 

Purchaser’s approval at least the following: 

Detailed complete set of diagrams and schemes of the switchgear, such as: 

1. General view from all sides. 

2. One line diagrams. 

3. Internal wiring diagrams and connection of each equipment type. 

4. Schematic and wiring diagram for control and measuring circuits of each 

field (cubicle). 

5. Terminal block and plug ‐ socket unit with internal and external 

connection. 

6. Detailed drawing for earthing connection of the switchgear. 

7. Detailed drawing of all compartments and especially for H.V cable 

connection parts. 

8. Part list and all technical information of each equipment piece. 

Annex‐A113  

9. Instruction manuals for all equipment supplied including: maintenance, 

testing, diagrams, spare parts. 

10. Full computerized protection calculations and settings. 

After installation complete the Contractor shall supply final “AS‐MADE” 

drawings and acceptance tests documents 

D.4.4. QualityAssuranceManufacturer shall maintain a service center capable of providing training, 

parts, and emergency maintenance and repairs. Manufacturer shall use an 

independent testing agency with experience and capability to satisfactorily 

conduct testing indicated in codes. Manufacturer shall supply drawings to 

indicate maximum dimensions for switchgear, including clearances between 

cubicles and adjacent surfaces and items, based on types and models 

indicated. 

D.4.5. Delivery&StorageStorage shall prevent condensation or in the equipment. If required, heaters 

shall be used. 

The equipment shall be shop assembled to ensure proper fit of all 

components and shall be disassembled to whatever extent is necessary for 

shipping, transporting and handling up to the final location. 

All equipment and other items shall be packed suitable for shipping, 

transportation and storage until installed. 

The Contractor shall furnish and install necessary covers to protect the 

equipment from sun, rain, hail, wind, dust and salt spray. Equipment shall be 

adequate sealed and protected during shipment to prevent corrosion and 

penetration of foreign matter. All exposed surfaces shall be protected, if 

required, with a suitable antirust compound or cover until completion of 

erection. 

All components or accessories shall be suitably tagged to show identification 

and service. 

Contractor shall submit, prior to installation, a detailed tabulation of all field 

mounted items with at least the following information: 

1. Item number, consistent with Contractor’s Bill of   materials. 

2. Contractor’s shop order number (if any). 

Annex‐A114  

3. Number of items. 

4. Manufacturer and/or Supplier, if other than Contractor. 

5. Type and catalogue number if listed. 

6. Short description including to what bus‐bar system the item belongs. 

Contractor shall submit detailed storage instructions for the specially 

designed equipment. 

D.4.6. CoordinationCoordination features of controllers and accessory devices with pilot devices 

and control circuit to which they connect. Coordinate features, accessories, 

and functions of each cubicle with the ratings and characteristics of the 

supply circuit, the required control sequence, and the duty cycle of the load. 

D.4.7. InstallationandConnectionInstall cubicle according to manufacturer’s written instructions. 

Anchor each cubicle to steel channel sills arranged and sized according to 

manufacturer’s written instructions. Attach by tack welding or bolting. Level 

and grout sills flush with mounting surface.  Tighten bus joints, electrical 

connectors, and terminal bolts according to manufacturer’s published 

torque tightening values. Where manufacturer’s torque values are not 

indicated, use those specified in UL 486A and UL86B. 

D.4.8. CommissioningFor testing provide services of a qualified independent testing agency to 

perform specified testing procedures: Perform on each cubicle visual and 

mechanical inspection and electrical test. Certify compliance with test 

parameters. Remove and replace malfunctioning units with new units, and 

retest. Simulate normal and fault operation conditions and verify operation 

of all protection, measuring metering and control functions. Inspect interior 

and exterior of each cubicle. Remove paint splatters and other spots, dirt, 

and debris. Touch up scratches and mars of finish to match original finish. 

Clean devices internally, using methods and materials recommended by 

manufacturer. Participate in commissioning of the entire system with all 

other concerned contractor/suppliers. 

 

   

Annex‐A115  

D.5. MVswitchboardenclosures

D.5.1. StandardsEnclosures shall be designed, constructed and tested in accordance with the 

requirements of the latest relevant published recommendations of the 

International Electromechanical Commission (IEC) and their amendments for 

metal clad switchgear Internal ARC Proof. All aspects, tests, etc. not covered 

by IEC Recommendations shall be made according to the latest published 

issue of official or otherwise approved standards of manufacturer's country. 

In such cases, the standards themselves shall be supplied. 

The relevant standards are:  

IEC 60038  IEC standard voltages 

IEC 60044‐1  Instrument transformers ‐ Part 1: Current 

transformers 

IEC 60044‐2  Instrument transformers ‐ Part 2 : Inductive 

voltage transformers 

IEC 60044‐3  Instrument transformers ‐ Part 3: Combined 

transformers 

IEC 60044‐5  Instrument transformers ‐ Part 5: Capacitor 

voltage transformers 

IEC 60056  High‐voltage alternating‐current circuit‐breakers 

IEC 60068‐1  Environmental testing ‐ Part 1: General and 

guidance 

IEC 60068‐3‐3  Environmental testing ‐ Part 3: Guidance. Seismic 

test methods for equipment 

IEC60068‐2‐6  Environmental testing ‐ Part 2‐6: Tests ‐ Test Fc: 

Vibration (sinusoidal) 

IEC 60068‐2‐27  Environmental testing ‐ Part 2‐27: Tests ‐ Test Ea 

and guidance: Shock 

IEC 60068‐2‐60  Environmental testing ‐ Part 2: Tests ‐ Test Ke: 

Flowing mixed gas corrosion test 

IEC 60099‐1  Surge arresters ‐ Part 1: Non‐linear resistor type 

gapped surge arresters for a.c. systems 

IEC 60099‐4  Surge arresters ‐ Part 4: Metal‐oxide surge 

arresters without gaps for a.c. systems 

IEC 60099‐5  Surge arresters ‐ Part 5: Selection and application 

recommendations 

IEC 60099‐6  Surge arresters ‐ Part 6: Surge arresters 

containing both series and parallel gapped 

Annex‐A116  

structures ‐ Rated 52 kV and less 

IEC 60137  Insulated bushings for alternating voltages above 

1000 V 

IEC 60255‐1  Measuring relays and protection equipment ‐ Part 

1: Common requirements 

IEC 60255‐3  Electrical relays ‐ Part 3: Single input energizing 

quantity measuring relays with dependent or 

independent time 

IEC 60255‐5  Electrical Relays ‐ Part 5: Insulation coordination 

for measuring relays and protection equipment ‐ 

Requirements and tests 

IEC 60255‐6  Electrical relays ‐ Part 6: Measuring relays and 

protection equipment 

IEC 60255‐11  Measuring relays and protection equipment: Part 

11: Interruptions to and alternating component 

(ripple) in a.c and d.c. auxiliary energizing input of 

measuring relays and protection equipment 

IEC 60255‐12  Electrical relays ‐ Part 12: Directional relays and 

power relays with two input energizing quantities 

IEC 60255‐13  Electrical relays ‐ Part 13: Biased (percentage) 

differential relays 

IEC 60255‐16  Electrical relays ‐ Part 16: Impedance measuring 

relays 

IEC 60255‐25  Electrical relays ‐ Part 25: Electromagnetic 

emission tests for measuring relays and 

protection equipment 

IEC 60255‐26  Electrical relays ‐ Part 26: Electromagnetic 

compatibility requirements for measuring relays 

and protection equipment 

IEC 60255‐27  Measuring relays and protection equipment ‐ Part 

27: Product safety requirements 

IEC 60265‐1  High‐voltage switches ‐ Part 1: Switches for rated 

voltages above 1 kV and less than 52 kV 

IEC 60282‐1  High‐voltage fuses ‐ Part 1: Current‐limiting fuses 

IEC 60282‐2  High‐voltage fuses ‐ Part 2: Expulsion fuses 

IEC 60282‐3  Specification for high‐voltage fuse‐links for motor 

circuit applications 

IEC 60470  High‐voltage alternating current contactors and 

contactor‐based motor starters 

IEC 60529  Classification of Protection Provided by 

Enclosures. 

IEC 60721‐2‐1  Classification of environmental conditions ‐ Part 

Annex‐A117  

2‐1: Environmental conditions appearing in 

nature ‐ Temperature and humidity 

IEC 60947‐1  Low‐voltage switchgear and controlgear ‐ Part 1: 

General rules 

IEC 60947‐5‐1  Low‐voltage switchgear and controlgear ‐ Part 5‐

1: Control circuit devices and switching elements ‐ 

Electromechanical control circuit devices 

IEC 60694  Common specifications for high‐voltage 

switchgear and controlgear standards 

IEC 61000‐4‐1  Electromagnetic compatibility (EMC) ‐ Part 4‐1: 

Testing and measurement techniques ‐ Overview 

of IEC 

IEC 61000‐4‐2  Electromagnetic compatibility (EMC) ‐ Part 4‐2: 

Testing and measurement techniques ‐ 

Electrostatic discharge immunity test 

IEC 61000‐4‐3  Electromagnetic compatibility (EMC) ‐ Part 4‐3: 

Testing and measurement techniques – Radiated; 

radio‐frequency; electromagnetic field immunity 

test 

IEC 61000‐4‐4  Electromagnetic compatibility (EMC) ‐ Part 4‐4: 

Testing and measurement techniques ‐ Electrical 

fast transient/burst immunity test 

IEC 61000‐4‐5  Electromagnetic compatibility (EMC) ‐ Part 4‐5: 

Testing and measurement techniques ‐ Surge 

immunity test 

IEC 61000‐4‐6  Electromagnetic compatibility (EMC) ‐ Part 4‐6: 

Testing and measurement techniques ‐ Immunity 

to conducted disturbances; induced by radio‐

frequency fields 

IEC 61000‐4‐8  Electromagnetic compatibility (EMC) ‐ Part 4‐8: 

Testing and measurement techniques ‐ Power 

frequency magnetic field immunity test 

IEC 61000‐4‐11  Electromagnetic compatibility (EMC) ‐ Part 4‐11: 

Testing and measurement techniques ‐ Voltage 

dips; short interruptions and voltage variations 

immunity tests 

IEC 61000‐6‐2  Electromagnetic compatibility (EMC) ‐ Part 6‐2: 

Generic standards ‐ Immunity for industrial 

environments 

IEC 61140  Protection against electric shock ‐ Common 

aspects for installation and equipment 

IEC 61850  all parts Communication networks and systems in 

Annex‐A118  

substations 

IEC 61936‐1  Power installations exceeding 1 kV a.c. ‐ Part 1: 

Common rules 

IEC 62271‐1  High‐voltage switchgear and controlgear – Part 1: 

Common specifications 

IEC 62271‐3  High‐voltage switchgear and controlgear – Part 3: 

Digital interfaces based on IEC 61850 

IEC 62271‐4  High‐voltage Switchgear and Controlgear ‐ Part 4: 

Use And Handling of Sulphur Hexafluoride (sf[6]) 

IEC/EN 62271‐

100 

High‐voltage switchgear and controlgear – Part 

100: High‐voltage alternating‐current circuit‐

breakers 

IEC 62271‐101  High‐voltage switchgear and controlgear – Part 

101: Synthetic testing 

IEC/EN 62271‐

102 

High‐voltage switchgear and controlgear – Part 

102: Alternating current disconnectors and 

earthing switches 

IEC/EN 62271‐

105 

High‐voltage switchgear and controlgear – Part 

105: Alternating current switch‐fuse combinations

IEC 62271‐107  High‐voltage switchgear and controlgear – Part 

107: Alternating current fused circuit‐switchers 

for rated voltages above 1 kV up to and including 

52 kV 

IEC/EN 62271‐

200 

High‐voltage switchgear and controlgear – Part 

200: A.C. metal enclosed switchgear and 

controlgear for rated voltages above 1 kV and up 

to and including 52 kV 

IEC 62271‐202  High‐voltage switchgear and controlgear – Part 

202: High‐voltage/low voltage prefabricated 

substation 

IEC/TR 62271‐300  High‐voltage switchgear and controlgear – Part 

300: Seismic qualification of alternating current 

circuit‐breakers 

IEC/TR 62271‐301  High‐voltage switchgear and controlgear – Part 

301: Dimensional standardization of terminals 

 

 

 

   

Annex‐A119  

D.5.2. TestsAll components and materials forming part of the enclosure and the main 

circuit equipment shall comply with this Specification and the IEC 

Recommendation as specified. The contractor shall submit with his offer, 

certified type test reports of the offered enclosures and circuit breakers. 

In case of equipment or cubicle parts assembled or not built by the original 

manufacturer but by other contractor, it is required that the contractor shall 

have QA and QC approved by original manufacturer and the work shall be 

performed according to original manufacturer’s drawings to make sure that 

the cubicles are identical to the type tested. 

The Contractor shall submit to the owner's representative a check list of all 

components integrated into the enclosure and the enclosure itself, for his 

approval. 

All tests shall be carried out at the Contractor’s facilities. 

The Purchaser shall have the right to inspect and witness all tests. 

The Contractor shall conduct on site the acceptances test, including: 

1. Insulation test. 

2. Functional operation tests (including electrical and 

electromechanical interlocks). 

3. Calibration and protection devices. 

4. Calibration and measuring devices. 

Annex‐A120  

D.5.3. EnclosuremetalworkEach enclosure type shall have test certificates and approvals of a licensed 

standard institution. 

Locking bar with waterproof double bit cam lock, which is exchangeable for 

square or triangle spindle plugs. 

Hinges shall be screwed to the cabinet and shall protrude neither into the 

door aperture nor into the cabinet interior, allowing doors to open to 120. 

The following shall define treatment and painting of exposed ferrous surface 

for metal surface for metal construction of electrical switchboards. All such 

treatment and painting shall be carried out by automated equipment. 

Material used for construction shall be cold rolled steel sheet, spec ‐ SD ‐ 

oiled. 

Pre‐treatment of metal surfaces shall be automated and consist of the 

following: 

Oil, grease and similar contaminants shall be removed by alkali solvent 

spray at temperature up to 60CPhosphatic layer by means of iron 

phosphate spray at temperature up to 60C.Clean water wash. Drying in 

oven at temperature of 120C. 

Painting metal surfaces shall be automated based on electrostatic 

application of specially designed epoxy polyester powders. 

Application shall be accomplished by means of industrial robots. 

Application to areas with low accessibility shall be completed manually 

where necessary using suitable epoxy handgun equipment. 

Thickness of paint layer shall be 30 microns. 

Color shall be RAL 7030 or RAL 1011 or equally approved. 

Resistance to peeling shall be DIN 53151 standard. 

Elasticity of paint layer shall be to DIN 53156 standard. 

The coated surface shall be baked, up to a temperature of 200C. Exact 

temperature adjustment shall be made in accordance with thickness of 

metal and conveyer belt. 

All application equipment shall be adjusted and controlled to produce a 

smooth even layer of uniform thickness over all required surfaces 

according to IEC 68‐2‐11.Properties of paint finish: 

Impact strength >  1Kg/50cm. 

Annex‐A121  

Heat resistance 24 hours at 140C. 

Corrosion resistant for a minimum of 200 hours against 30% citric acid, 

petrol or alcohol. 

Internal partitions shall be galvanized with chrome passivation. 

 

All components of the same rating and construction shall be interchangeable. 

Metal sheets, covers and doors shall be of evenly and smooth rolled steel 

sheets of two (2) mm thickness (minimum). 

Rigidity of structure, doors and covers shall be achieved by properly welded or 

bent ribs. 

The metal enclosure shall be of steel sheets and shall assure complete 

protection of persons from approach to live parts or to internal moving parts. 

Vent openings shall be protected so as to prevent the access of vermin, snakes 

or large insects. The floor surface, even if not metallic, shall be considered as 

part of enclosure for this purpose. A sheet metal floor shall be provided 

wherever trenches exist under switchgear. 

The enclosure, covers, partitions and front of circuit breaker, where it serves as 

a cover, shall be strong enough to provide adequate protection to persons from 

the hot gases and the instantaneous pressure caused by a fault arc, even 

though,  the  purpose of the enclosure and its compartments is to limit the 

damage caused by such an arc. Moreover, each compartment shall have a 

suitable vent opening or cover to relieve such pressures. 

Covers shall conform with all the requirements of the metal enclosure. Use 10 

mm diameter, minimum, hexagon bolts to fasten covers. 

Partitions shall be of the same steel sheet as the covers, or of other material of 

equivalent mechanical strength which complies with all the mechanical 

requirements, non‐burning and not containing carbon, and which includes an 

electrically incorporated grounded potential that is not temperature or 

humidity affected. 

Conductors passing through partitions shall be protected by bushings. 

Mounting of these bushings shall be secured by proper means and supports. 

Removable contact arrangements in circuit breaker case construction shall 

provide the completion of the insulation and shall be an integral part of the 

circuit breaker and shall be airtight. Bushings will not be required in this case. 

The complete withdrawing arrangement shall be tested at all positions with 

relevant test of the circuit breaker.  

Annex‐A122  

The enclosure shall be mounted on a base frame for each row, constructed to 

form a self‐supporting rigid construction despite its being placed on the floor 

foundations. 

Each compartment, except the instrument compartments shall be provided 

with heating elements. The heating elements shall be fitted so as to enable 

their replacement even while the fixed contacts of the removing arrangement 

of the circuit breaker are live. 

A grounding conductor shall be provided running the whole length of the metal‐

clad switchgear. The terminal of the conductor shall be brought out of the 

enclosure from each side with a 17 mm diameter bore for the connection of the 

external grounded conductors. 

 

Each unit enclosure shall be connected to the ground conductor. Metallic parts 

intended to be grounded. Metallic parts which do not belong to a main or 

auxiliary circuit shall be connected to the ground conductor. The inter 

connection within a unit, fastening, e.g.; bolting or welding together of the 

frame, covers, partitions or other structural parts, shall provide electrical 

continuity. Doors and shutters shall be connected by flexible copper connectors 

to the enclosure. The cross section of these connectors shall not be less than 50 

sq. mm. The removable metallic parts, which are normally grounded, shall 

remain ground connected until the prescribed conditions for isolating distance 

are met. Withdraw able parts may be locked in this position by padlock or 

equivalent. The continuity of the grounding shall be ensured in the test position 

and shall only be interrupted in the removed position. Grounding arrangements 

and mounting of conductors shall enable the conductors to carry the full three 

phase short circuit.  

These grounding arrangements shall only be copper, and by removable contacts 

where necessary. Grounding switches shall be connected to the main grounding 

conductor by copper connectors, 600 sq. mm cross section minimum. 

 

 

 

Annex‐A123  

D.5.4. MaincircuitconductorsandinsulatorsContractor shall obtain approval, in writing, of arrangement, size and 

material of main circuit connections as well as of their post insulators 

and bushings before starting manufacturing. 

Main circuit conductors shall be copper and shall withstand the rated 

current at normal service conditions and the forces exerted at rated 

peak, as well as, the thermal expansion at short time withstand current 

without any damage whatsoever. 

Bolted main circuit conductor connections shall be silver plated. Bolts 

shall be of Cuprodur or stainless steel or approved equivalent. Bolts 

shall be provided with lock washers of non‐corrosive material. Silver 

plating shall be electrolytic. 

Main circuit conductors shall be completely insulated. Insulation shall 

be epoxy impregnated glass cloth type or thermal powdered 

cycloaliphatic Araldite. Insulation shall be continuous, covering all 

connections and bolts and of quality and thickness to successfully 

withstand a one minute,(minimum) voltage breakdown test. Special 

attention shall be paid and additional insulation provided at all edges, 

ends and corners. Bus bars shall be marked with phase colors (red, 

yellow, blue) at visible places in bus bar and circuit breaker 

compartments. 

Main circuit conductor insulation shall be free of air bubbles. Tan delta 

of the insulation shall not exceed 0.025 at 25kV and the knee point of 

the tan delta curve shall not be lower than at Un+10%. Insulation shall 

be non‐flame sustaining, high temperature resistance type.  

Contractor shall submit to the CPM catalog data, construction details, 

composition, and all other information about the epoxies intended for 

main circuit conductor insulation. 

Contractor shall submit to the CPM a test report of the prototype. 

Contractor shall furnish all necessary material, such as tapes, fillers, 

epoxy, etc., to complete the main circuit insulation on site, including 

connections to cable sealing ends. 

Post insulators and bushings shall be constructed and mounted to 

prevent any jar or movements due to the forces exerted at rated peak 

withstand currents. Suitable arrangement shall allow for the expansion 

and contraction of the main circuit conductors without overloading or 

causing any damage to the conductors, post insulators or bushings at 

Annex‐A124  

normal service conditions and rated currents, and when the switchgear 

is assembled. 

Main circuit post insulators shall be designed, constructed and tested in 

accordance with the requirements of IEC Publication 60168. 

Bushings shall be designed, constructed and tested in accordance with 

the requirements of IEC Publication 60137. 

Main circuit post insulators and bushings shall be of type which has 

successfully passed all the type tests of the relevant IEC 

recommendations. Contractor shall have all test results available for 

review and approval by the owners and authorized Representatives. 

D.5.5. Switchboardratings(formetalcladtype) The following requirements are also applicable for load centers and MV   

  MCCs: 

  SYSTEM 

System voltage  11kV  22kV 

Rated voltage  12kV  24kV 

Insulation level 

kV rms 50HZ/1min. 

28kV  50kV 

Insulation level peak 

1.2/50 microseconds. 

75kV  125kV 

Short time withstand 

current (rms) 

  3 sec 

peak 

 

 

31.5KA 

80KA 

 

 

25KA 

63KA 

Service conditions 

temp. range 

Max. relative humidity 

5C to 40C 

 

84% 

1. 5C to 40C  

84% 

 

Annex‐A125  

D.5.6. AuxiliariesandcontrolsAll auxiliary and control equipment and all necessary wiring shall be supplied 

by the Contractor and installed as indicated on the drawings, or as called for 

in this specification. Conductor bunches shall be protected by ducts or flexible 

conduits where required, especially in the circuit breaker, bus bars and cable 

compartments. All wiring from the instrument compartment to those 

compartments shall be complete in metal conduits. Conduits from the 

instrument compartment to the circuit breaker compartment or the cable 

compartment shall not pass through bus bar compartments. Heater circuits 

shall have separate conduits, voltage transformers, and separate conduits for 

all other auxiliaries. Internal circuits of circuit breaker operating mechanisms 

need no additional protection other than the mechanical protection. 

Conductors of auxiliary and control circuits shall be flexible copper, 50 wires 

0.25 mm diameter per conductor equivalent to 2.5 sq. mm cross sectional 

area. Secondary current transformer circuit conductors shall be flexible 

copper, 84 wires of 0.30 mm diameter per conductor equivalent to 6 sq. mm 

cross sectional area.  

Conductors shall have double insulation: 90 degrees centigrade P.V.C and 

Nylon for 600V. Conductors shall be installed between terminal boards and 

clamps which shall allow for the flexibility of the bunch, with no damage 

caused to the conductors. Conductors shall be terminated by compression 

type ferrules or lugs for connecting to the terminal boards or instrument 

terminals. 

When connections to the operating mechanism is by flexible cable and plug‐

socket arrangement, the conductors of this cable may be of 1.5 mm sq. cross 

sectional area only, but not less, as long as the cable is wired completely and 

supplied by the circuit breaker’s manufacturer. 

Control terminals shall be up to 6 mm sq., 500V minimum. Secondary 

terminals for current transformers shall be glazed steatite, with suitable 

bridges. Terminals shall be mounted on proper rails with all parts properly 

arranged according to the wiring diagrams and in the order shown on the 

diagrams. Attention shall be given to connecting conductors to the proper 

side of the terminal as shown on the diagrams. Terminal strips shall be 

mounted vertically. Where shown, on the wiring diagrams, partition plates 

shall be inserted between terminals to avoid flashovers. Assembly rails shall 

have ample reserve for an additional ten per cent of quantity of terminals to 

be designated in the future, but not less than five terminals. Terminals shall 

be labeled by original printed letters (both individual and group 

identifications). 

Annex‐A126  

Conductors belonging to common logical groups shall be arranged together. 

Suitable conductors for interconnecting the groups shall be furnished to 

complete the wiring on site. 

Control and measuring circuits shall be protected by a miniature MCBs with or 

without normally closed auxiliary contact. Current ratings and number of 

poles shall be provided according to the wiring diagrams. 

Measuring instruments shall be square type, flush mounted, not less than 

96X96mm, extended scale, black frame, white scale and black numbering. 

Voltage and current ratings shall correspond to the ratios and accuracies of 

the relevant voltage and current transformers, and shall withstand the rated 

permissible overloads of the latter. 

Maximum current ammeters for feeders shall be of class 3 accuracy and 15 

min. response time. Temporary peak currents shall not contribute markedly 

to an indication. Internal consumption (including protection of instrument) 

shall not exceed 3.5VA. Slave pointer shall be externally resettable. 

Sandwich plates shall be provided on the instrument compartment panels and 

in the compartments for identification of instruments and terminal strips. 

 

Plates shall be black with white lettering. Letters shall not be less than 3mm, 

except for field identification, plates shall be 5 mm. Plates shall be fixed by 

non‐corrosive screws. Supply non‐engraved plates for field identification. 

Field identification plates shall be lettered on‐site. Lettering shall be according 

to wiring diagrams. 

All auxiliary and control switches and relays shall be of protected type. 

A visual display diagram (mimic) made of colored Aluminum figures shall be 

installed on the front of all switch boards. All control devices and position 

displays shall be incorporated into this diagram. Detailed drawings of these 

diagrams shall be submitted for the Inspector’s inspection and approval, 

together with the construction drawings. 

   

Annex‐A127  

D.5.7. Heatingarrangementsinmetalcladswitchgear

The purpose of the heating is to avoid condensation on the inner parts of the 

switchgear, especially on bushings and post isolators, isolating materials such 

as bus bar isolation, isolating etc. This object is achieved by maintaining a 

temperature difference of three to five degrees centigrade between the 

warmer isolators and the ambient temperature, as well as keeping the 

temperature above a set minimum. 

Only active elements, especially the main circuit isolators, shall be heated. 

Heating shall be by radiators in form of heating elements in metal tubes shall 

be attached to the partitions so that the heat is conducted to the partitions 

which will serve as radiators themselves. 

The heating elements shall be in contact with the metal‐partitions and shall 

be designed so as not to impair the painting or alternatively the paint shall be 

of epoxy type, which withstands the heating element temperature. In no case 

shall heating elements be installed on removable parts, as the compartment 

will be alive then, but without heating. 

D.5.8. CalibrationAll protection devices shall be calibrated on site under real operating 

conditions by the Contractor. The Contractor shall provide and maintain all 

calibration aids as well and shall employ an expert licensed professional to 

execute the calibration. 

D.5.9. FiredetectionandextinguishingElectrical boards shall be furnished with heat/smoke detection means as well 

as fire extinguishing systems. 

The fire extinguishing system shall be an internal sub‐system of the general 

fire smoke detection system. The system shall be designed acc. to NFPA 1201 

regulations.  

The gas shall be released by one of the following modes: 

1. Automatic release via cross zoning signals from smoke  / heat 

detectors installed in each cubicle.  

2. Manual release actuated by an electric push‐button command. 

3. Manually by mechanical release. 

Extinguishing gas shall be of “Clean Agent” type NFPA 2001 approved, such as 

NAFS ‐ III 

Annex‐A128  

Gas containers shall have UL/FM approval. Gas volume and nozzle type, 

location and quantity shall be designed according to the various switch board 

structure. 

   

Annex‐A129  

D.6. CircuitBreakers

D.6.1. GeneralCircuit breakers shall be based on the SF6 or vacuum arc quenching 

technology enclosed in a “metal‐clad” type withdraw‐able 

compartment. 

D.6.2. Technicaldata 

  SYSTEM 

System voltage  11kV  22kV 

Rated voltage  12kV  24kV 

Insulation level 

kV rms 50HZ/1min. 

28kV  50kV 

Insulation level peak 

1.2/50 micro sec. 

75kV  125kV 

 

Short time withstand current 

3 sec. 

 

31.5KA 

 

25KA 

Making capacity  80KA  63KA 

Opening time (max.)  70msec.  70msec. 

Arcing time (max.)  15msec.  15msec. 

Breaking time (max.)  85msec.  85msec. 

Closing time (max.)  50msec.  50msec. 

Gear motor for spring charging  24VDC  24VDC 

Spring charging time (max.)  10sec.  10sec. 

Opening/closing releases  24VDC  24VDC 

 

Annex‐A130  

D.6.3. CircuitbreakersdesignEach circuit breaker shall be three pole vacuum or SF6 arc extinction. Each 

circuit breaker shall consist of an independent unit with no need for any 

general auxiliary equipment, such as a compressed air system. 

The circuit breakers shall be designed, constructed and tested in accordance 

with the requirements of the latest published Recommendations of IEC, 

Publication No. 56: “High Voltage Alternating‐Current Circuit‐Breakers” 

according to following data and the following additional requirements: 

The circuit breaker shall fit into and comply with the requirements of 

the metal clad switchgear. 

Rated current shall be in conformity with the drawings. 

Rated short circuit breaking capacity (min) 20% higher than the actual 

local value. 

Rated operating sequence according to IEC Publication 60056‐2. 

Operating mechanisms shall be designed for successful local and remote 

electrical control and local manual control. The manual tripping device shall 

be protected against accidental operation. 

The actuation of the manual tripping device shall lock the mechanism in the 

trip position, either by mechanical means or by interrupting the remote 

closing circuit, so that after local tripping the mechanism shall not respond 

to any remote closing operation. Release of this locking shall be local and 

manual. The operating mechanism shall have facilities for manual operation, 

such as winding up the spring in addition to the automatically operated 

spring winding motor. 

Six normally closed and six normally open spare auxiliary switches (contacts) 

shall be provided in addition to the used switches. At least two switches of 

each type shall be adjustable. All switches shall be wired to the instrument 

compartment terminal board. The spare auxiliary switches shall be 1 Amp. 

220V AC and 0.5 Amp.  Inductive burden 220VDC  rated. 

Circuit breaker shall be withdraw‐able, mounted on transportable carriage 

frame to be anchored rigidly to the enclosure in service position. The 

anchorage shall prevent any jar or movement of the circuit breaker at 

tripping or on a short circuit.  

Adequate means shall facilitate easy transfer or circuit breaker by manual 

means on each circuit breaker from one position to another as follows: 

Annex‐A131  

From service position to test position. 

From test position to removed position. 

From removed position to test position. 

From test position to service position. 

Transfer shall be in the above order. Transfer or circuit breaker shall be by 

separate carriage or by wheels on the circuit breaker frame. Suitable means, 

e.g. wheels with ball bearings, shall facilitate easy transfer from one position 

to another. A suitable lever shall enable the proper insertion and withdrawal 

by a single person. 

This lever shall be either single movement type (not repetitive) or the screw‐

in type by a rotary handle. Chain or ratchet type arrangements will not be 

accepted. If electrical control connections are made by portable cable and 

plug‐socket connectors, four (4) such portable cables shall be supplied with 

each switchgear. 

Interlocks shall prevent withdrawal or engagement of a circuit breaker 

unless in open position. Means shall also be provided to padlock the circuit 

breaker in the service and in the test position or alternatively to padlock the 

circuit breaker compartment door, if this door closes in the test position. 

Interlocks shall prevent any operation of the circuit breaker, unless in one of 

the defined positions: Service, test or removed. Circuit breaker shall not be 

able to close in service position unless auxiliary circuit connectors are 

engaged. Interlocks shall prevent engaging the circuit breaker in the service 

position while the grounding switch is in closed position. 

Withdraw able contacts of the main circuit shall be silvered. The females 

shall be in the form of sectionalized contact fingers. Arrangement may be 

either flat‐to‐fit a knife or round (tulip) ‐ to fit a pin type contact. The 

females shall be mounted on the circuit breaker and the non‐spring part on 

the fixed bushings or post insulators. There shall be one stop only for the 

withdraw‐able contacts, either on the finger side or on the fixed side, but 

not on both. 

Circuit breakers of the same rating shall be interchangeable with each other, 

both electrically and mechanically. However, adequate means shall be made 

to prevent insertion of an 800A breaker into a compartment designed for a 

1250A breaker and insertion of a 1250A breaker into an 800A breaker 

compartment, etc. 

Annex‐A132  

The circuit breaker insulator shall be shaded, ceramic or of cycloaliphatic 

epoxy resin. 

Circuit breakers shall each be equipped with all necessary accessories for 

operation, including the following: 

Trip free and anti‐pump features of operating mechanism. Closing 

mechanism shall automatically become inoperative after, and while the 

breaker is closed, until after the breaker has had ample time to 

complete the closing operation. It shall be impossible to operate the 

closing mechanism again until the operator has first reset the breaker 

control switch to the neutral position. 

Position indicators. 

Operations counter to indicate the number of trip operations. 

Circuit breakers shall be of type which has successfully passed all tests 

required by the relevant standards. 

D.6.4. AuxiliaryequipmentSF6 gas condition indication lamps (if SF6 type is used): 

green ‐ normal pressure 

yellow ‐ low pressure 

red ‐ insufficient pressure 

Spring charging gear motor with anti‐reclosing device, and position 

indicator auxiliary switches. 

Hand operating mechanism. 

Shunt closing release. 

Shunt opening release. 

Under‐voltage release (on request) 

Lock magnet on operating mechanism. 

Key lock system for interlocking purpose. 

Semaphore condition indicator (on, off, no‐voltage). 

D.6.5. Groundingswitchesandgroundingarrangements

The grounding switches shall be designed constructed and tested in 

accordance with the requirements of IEC Publication 60129 and shall be of 

rated voltage and insulation level of those recommendations. 

Annex‐A133  

The grounding switches shall withstand the rated short time and peak 

withstand current specified for the switchgear. The grounding switches shall 

be capable of closing without damage caused on the full rated voltage and 

ground the circuit until interrupted by the protection. 

The grounding switch shall have suitable means to prevent opening of 

contacts when carrying the short time and peak withstand currents, or when 

full rated voltage appears in the main circuit while being grounded. 

Grounding switches shall be manually operated from the front of the 

switchgear. The mechanical operation transmission shall be rigid so that the 

position of the operating lever indicates if the grounding switch is in open or 

closed position. Levers shall have padlocking facilities in either closed or 

open position. The mechanical operation transmission shall pass between 

fields or through the circuit breaker compartment, but in no case through 

the bus bar compartment. 

Interlocks shall prevent operation of grounding switch unless circuit‐breaker 

is in test or removed position. Interlocks shall prevent moving of circuit 

breaker from test to service position while the grounding switch is closed. 

Grounding switches shall be equipped with three (3) Change‐over 

5A/220VDC auxiliary contacts. 

Fields not equipped with grounding switches shall have three grounding 

terminals connected to the fixed side of the withdraw‐able contacts in the 

circuit breaker compartment, one per phase. The terminals shall be either in 

the form of flat galvanized strips or spheres of 20 mm diameter. Those fields 

shall have any extension from the main grounding conductor brought out in 

front of the shutters, so as to facilitate connection of the grounding device 

connector to ground before opening the shutters. The terminals shall be 

connected to the bus bar side of the inner fed fields and to the cable side of 

the other fields. 

D.6.6. CircuitBreakersfortransformerfeedingMV Circuit Breakers feeding transformers 22/0.4 kV and 22/11kV shall be 

interlocked with relative Main Circuit Breakers connected from the lower 

voltage side of the transformers. When the 22kV Circuit Breaker disconnects 

the feeding circuit from any reason, the lower side Main Circuit Breaker 

must be also opened. The lower side Circuit Breaker cannot be closed, while 

the 22kV side Main Circuit breaker is opened. 

The Contractor shall provide the necessary interlock functions in the control 

circuits of the Circuit Breakers supplied by him and shall make the necessary 

Annex‐A134  

provisions by means of appropriate terminal block to enable for other 

contractor to accomplish his control scheme.  

D.7. MVCurrentTransformers

D.7.1. GeneralThe current specification covers epoxy molded current transformers (CT) for metering or protective applications, indoors or outdoors type ‐ as defined. The CTs shall comply with IEC 60185 standards and shall be insulated for 

metal clad switchgear. Service conditions shall be as per project's site condition. 

 

D.7.2. Constructionrequirements1. The primary to be wound with pure heavy copper, to provide a 

maximum mechanical strength against short circuit currents. 2. The secondary to be evenly distributed on a very low loss core for 

best accuracy. 3. The transformer is to be hot cast in an insulating resin under 

vacuum to achieve a compact unit. 4. Base plate to be furnished if required 5. Terminals shall be tin plated copper 6. The epoxy surface of the transformer to be fully coated with zinc, 

hot sprayed after casting. 7. Short time current: up to 500 x primary 8. Permanent over current factor: 1.2 (other upon request) 9. Secondary current: 5A to 1A 

10. Accuracy :  Commercial metering and check meters: cl 0.2S 

Measuring: cl 0.5 

Protections: cl 5P10 and 5P20    

Annex‐A135  

D.8. MVPotentialTransformers

D.8.1. GeneralThe current specifications covers line to line or line to ground epoxy molded potential transformers (PT) with one or both MV ‐ insulated bushings, fused 

or unfused, for metering or protective use or for auxiliary power application . Service conditions shall be as per project's site condition.

D.8.2. Constructionrequirements

1. Primary and secondary windings shall be mounted on a very low losses core, hot cast in an insulating epoxy resin. 

2. Insulation: 24 kV. 

3. Frequency: 50Hz. 

4. Primary voltage: 

- Phase to ground: 22,000/3 V 

- Phase to phase:   22,000 V 

5. Secondary voltage: 

- Phase to ground: 100/3 or 110/3 V 

- Phase to phase: 100 or 200 V 

6. Voltage factor for line to ground units: 

- 1.5xUn ‐ 30 sec. for grounded neutral 

- 1.5xUn ‐ 30 sec. for impedance neutral 

1.9xUn ‐ 8 hours for isolated neutral 

7. Voltage factor for line to line units: 1.2xUn ‐ continuous 

8. Secondary terminal (LV), for each secondary winding one terminal is to be grounded. The core is to be grounded via base frame. 

9. Line to ground PTs: 

- The MV primary terminal to be connected directly to the bus bar or by means of a medium voltage fuse and a spring contact. 

- The residual voltage winding is to be connected in open delta, closed by a resistor (typical value 100 OHMS, 320W). 

- One end of the delta must be grounded. 

 

10. Line to line PTs: 

Annex‐A136  

- The two HV terminals to be connected directly to the bus bars or by means of high voltage fuses. 

- Impulse test ratings (1.2/50s):  

 

11. Un = 24 kV BIL  test  = 125Kv 

Annex‐A137  

D.9. SecondaryProtectionRelays

D.9.1. GeneralRequirements

Protective relays shall be provided as necessary for 5A secondary CTs and for 110V PTs. 

Control voltage 24VDC or according to future coordination with the IAA. 

Protective relays shall be draw‐out electronic microprocessor based type and shall be mounted on the door of control compartments of the cubicles. 

Main protection relay and backup protection relay shall be installed. 

Each protection relay shall be connected to a separate CT and VT. 

Disconnection or fault one relay shall not require stopping the diesel generator. 

Protective relays shall be furnished with continuous self‐monitoring that in an event of internal fault affecting the unit, an alarm will be initiated and, if necessary, unit shall be automatically taken off line. 

Each of the relays shall have at least one contactor for tripping and additional isolated NO/NC contact for monitoring. 

The protective relays shall have 100% redundancy in auxiliary power supply. 

Means for function test of all protective relays shall be provided and supplied with the switchgear. 

At least one potential free alarm and one trip contact shall be wired to terminals for purchaser’s use (connections to remote control room). 

Communication port shall be provided for interface to PLC and DCS systems. Communication software and communication protocol shall also be provided. Communication standard shall be IEC61850. 

The protection relays shall be designed also to communicate and to exchange date with the existing SCS system by ABB. 

The protection relay system shall be designed assure a high level of cyber security in order to address requirements of NERC‐CIP, IEEE 1686, etc. 

Protective relays shall be latest model, computer based type and shall be 

mounted on the door of control compartments of the cubicles. 

At least one potential free alarm and one trip contact shall be wired to 

terminals for purchaser’s SCADA use. 

Relay shall have fault logs and event logs containing up to 40 events with 

time tagging of 1msec. 

Relays shall have wide graphical LCD display for reading alarm and fault indications. The LCD display shall serve also as digital multi‐meter showing 

minimum three different measuring values at the same time. 

Annex‐A138  

Changing of protection setting from relay's panel keyboard, shall be possible 

only after entering special password. 

Indication Led lamps on relay's panel shall be programmed to indicate: 

Ready, Trip and other fault enunciations. 

Standard Communication ports shall be provided for interface with PLC and HMI systems at the back side of each relay. Additional port shall be used for 

connecting engineering portable computer. 

All relays shall be connected by means of bi‐directional communication network capable for reading data events and measurements from each relay to an HMI system, capable for synchronizing all relays simultaneously to the same time clock. The time tagging for each event shall be 1 millisecond resolution. System's central time clock shall be GPS based and shall be 

included as a part of the system. 

Communication connection between relays and for communication network 

coupler shall be "fiber‐optic" connected. 

Communication, diagnostic software and communication protocol shall also be provided including all required modems, couplers, protocol converters, 

FO wiring and control wiring by the contractor. 

The protection relays shall have internal programming ladder logic for controlling cubicles operation and for interlocking with other cubicles or systems. Relays shall include minimum eight (8) digital inputs and four (4) 

outputs. 

Relays shall have integrated protection against harmonics on the control 

voltage supply. 

Protection relays shall include IDMT protection curves according to IEC 

standard. Current protection shall include three setting stages: 

a. I> with IDMT curves and definite time characteristics 

b. I>> with definite time characteristics 

c. I>>> for definite time and instantaneous tripping. 

All a.m. protection stages shall be combined, functioning together for 

achieving system grading. 

Protection relays shall include IDMT function for residual current Io including curves, definite time and instantaneous characteristics. Minimum relay sensitivity for earth fault currents shall be 0.1xIon  

Relays shall have internal lockout function and option for remote "Reset" 

command by means of dry contacts and communication. 

Relays shall have also a secondary protection setting. Main and secondary setting shall be selected by remote command via communication and 

auxiliary dry contact. 

Contractor shall design, supply and install zone selectivity functions including: Blocking, Acceleration and circuit breaker failure protection 

Annex‐A139  

functions. All required wiring shall be designed, supplied and installed by the contractor. 

 

Separate check synchronizing relays shall be installed on: generator breaker, SUT breaker, outgoing breakers to switchboards 100 and 200, additional breakers at switchboards 100 and 200 and future connection to IAA's flight control tower.  

 

D.9.2. CalibrationAll relays shall be calibrated on site by a commissioning specialist, utilizing calibration equipment and accessories defined by the manufacturer. Protection, metering, communications and control functions shall be simulated and verified during the commissioning procedure. 

   

Annex‐A140  

E. ChapterE:ElectricalSpecifications

E.1. StandardproductsContractors must supply new, standard, unmodified products of the various 

manufacturers . Contractors shall describe their standard products being 

supplied and shall highlight those features that exceed the specification 

requirements .All products shall be in accordance to climatic conditions for 

tropical climates, mentioned in “Project location and environmental 

conditions" section A. vibrations,  and be protected against rust, corrosion, 

fungus, and salty atmosphere 

E.2. StandardsandRegulationsThe onsite installation shall comply with the following standards, the Israeli 

Electrical Corporation requirements, as well as all other standards and 

regulations enforced and applicable in Israel: 

1. Israel Electrical Law 

2. General specifications for building work 

 (The" blue book" local regulations issued by the ministries of 

housing and defense) 

3. Israel Airports Authority (IAA) 

4. Israel Electric Corporation Ltd. (IECo) 

5. Safety regulations (Ministry of Labor) 

 

   

Annex‐A141  

E.3. Conduit

E.3.1. RacewayandchannelsFlush mounted conduits. Flush mounted conduits shall be flexible, thick 

wall, self‐extinguishing type. Flexible PVC conduits shall be heavy wall 

color coded according to the system they are used for: 

1. Fire detection system ‐ Red conduits 

2. Electrical system ‐ Green conduits 

3. Telephone system ‐ Gray conduits 

4. Computer & control system ‐ White conduits 

5. Public Address – Yellow / White 

6. Communications – Blue 

7. Emergency Lighting – Brown 

E.3.2. Surfacemountedconduits.Heavy PVC rigid conduits shall be surface mounted by means of either 

stainless steel or UV retardant PVC clamps. All accessories for this type 

of conduits shall be original prefabricated items (bends, connectors, 

penetrations, sealing, etc.). Substitutes will not be accepted. Surface 

mounted PVC ducts, with or without; integrated accessories shall have 

the following properties: 

1. Density       2  0.05 (ISO R/1183) 2. Water absorption      0.21%  0.02 (ISO 62) 3. Halogen content      0% (S.E.V) 

4. Inflammation point       1000C (IEC 695‐2‐1) 5. Dielectric strength      8 kV/mm 

6. Ambient temperature    ‐80C to +150C 7. UV resistance      ASTM/G/35388 

 

Annex‐A142  

E.3.3. SurfacemountedductsSurface mounted polyester ducts shall have the following properties: 

 

1. Density          1.915 (ISO R/1183) 

2. Water absorption      0.166% (ISO 62) 

3. Tensile strength at break point    158 Mpa (ISO R/178) 

4. Halogen content                    0% 

5. Inflammation point      900C  (IEC 695‐2‐1) 6. Dielectric strength      4.8 kV/mm 

7. Ambient temperature      ‐80C to +150C 8. UV resistance        ASTM/G/35388 

E.3.4. UndergroundconduitsUnderground conduits shall be laid in trenches. Conduits used for 

underground installation shall be of rigid PVC with wall thickness not less 

than 3.5 mm or flexible (corrugated) conduits made from hard PVC. 

Underground conduits shall be joined by the bell and spigot method or 

threaded coupling. Sealing shall be achieved by a rubber ring mounted in the 

bell groove and pressed against the conduit end. The end of the spigot shall 

be covered with contact glue in order to ensure sealing. 

Conduit entries into manholes or into channels shall be rounded off with 

mortar to prevent injury of cables during pulling. The conduit ends shall 

terminate at the straight surface of the wall, the manhole or the channel, 

which shall be cleaned beforehand from burrs that may injure the cables. 

A  PVC coated steel wire of suitable diameter, a nylon wire or galvanized 

wire shall be inserted into each conduit. In the absence of other instructions, 

this shall be a 6 mm diameter nylon wire. The ends of the pulling wires shall 

terminate in the manholes or channels. In any case, a length of wire not 

shorter than 0.5 m shall be left outside the conduit. This overlapping excess 

wire shall be wound on a peg to prevent its returning into the conduit. 

Between two manholes, the conduits shall be laid in straight lines and in the 

depths as shown on the drawings. The gradient shall be uniform in each 

section between two manholes (except where explicitly shown otherwise on 

the drawings) to prevent accumulation of water in the conduit system. 

During backfilling care shall be taken that the joints are not damaged and 

that the conduits are not displaced. The ends of the conduits shall be well 

closed with tar paper to prevent ingress of moisture and foreign bodies into 

the conduit lines. 

Annex‐A143  

E.3.5. Cabletrays,laddersbracketsandaccessories.

All items shall be hot‐dip galvanized according to DIN50976 

 (50‐60 microns = 350‐420 g/m2 surface). 

Bolts, nuts, washers, lock washers etc., shall be hot dip galvanized with a 

minimum coat thickness of 40 microns according to DIN 267 part 10. 

All exposure specifications shall be according to DIN 4114, sheet 2. 

Stainless steel material shall be no. 1.4301. 

Cable routes shall be electrically connected at the joints and shall be 

equipotential bonded. 

Each type shall be supplied with a factory certificate. 

All auxiliary materials ( supports, clamping brackets, bends, covers, 

partitions, reducing units, termination plates, branches, bolts, anchors, 

mounting rails, girders, protection caps, barriers, etc.) shall be of the same 

made as the main raceway or channel. 

E.3.6. Protectiveconduitsfordeviceconnection

Flexible wiring conduit with characteristics as follows shall be used for 

protecting cables connected to motors or control devices. 

1. Material: Hardened PVC Spiral and soft PVC wall, IP65. 

2. Standards: IEC144, DIN 40050, BS4607 (crush strength 

requirements) 

3. Self‐extinguishing, halogen free. 

4. Service temperature: ‐10C to 90C. 5. Each end shall be equipped with an IP65 connection gland of proper 

size and connection type. 

 

   

Annex‐A144  

E.4. Cablesandconductors

E.4.1. GeneralThis specification defines the technical requirements of single core and 

three cores extruded stranded cross‐linked polyethylene insulated power 

cables for rated voltage  

Uo/U=18/30kV, Uo/U=12/20kV and 0.6/1 kV. 

The cables are designated to be installed in conduits and on ducts. 

The maximum rated conductor temperature is 90C. 

The maximum conductor temperature in case of short circuit (max. 1s 

duration) is 250C. 

E.4.2. CablemarkingEach cable shall be marked with: 

1. Manufacturer trade mark 

2. Cable type (VDE mark) 

3. Conductor number and size 

4. All necessary information according to 2.5.11 above. 

E.4.3. PackingThe cables shall be furnished wound on strong new seaworthy wooden 

drums or metal reels. 

The cable on the drum will be protected against damage by wooden plates, 

mounted around the flanges of the drum, so that the drum will be closed 

from all sides. 

On each drum the following data shall be printed on a tag strongly attached: 

1. Manufacturer’s Name. 

2. Drum Serial No. 

3. Manufacturing Date. 

4. Cable Title. 

5. Cross Sectional area in sq. mm. 

6. Cable length. 

7. Gross weight. 

8. Cable Standard/Specification. 

Annex‐A145  

9. The cable ends on the drum must be closed by water tight end cups, to prevent penetration of humidity or water into the cable. 

E.4.4. LVPowercablesPower cables for operating voltages of up to 400V for non‐hazardous outdoors, 

indoors as well as buried applications shall be N2XY‐FR cables with copper 

conductors. 

Rated Voltage  Uo/Un = 0.6/1 kV 

AC test voltage  3 kV 

Permissible operating temperature 

90C 

Designation Standards  IEC 60502, DIN VDE 0207, 0250, 0281, 266, 0289, 0293, 0298, 0472 

E.4.5. MVPowercables

Power cables for operating voltages of up to 24kV for non‐hazardous 

outdoors, indoors as well as buried applications shall be single core and 

three cores extruded solid cross‐linked polyethylene (XLPE) insulated cables 

with copper conductors. 

Rated Voltage  Uo/Un = 12/20 kV 

Uo/Un = 18/30 kV 

Permissible operating temperature 

90C 

Maximum conductor temperature under emergency condition 

130C for max. 8 hours continuously not exceeding 100 hours per annual 

Designation Standards  IEC 60060, 60183, 60228, 60229, 60230, 60502, DIN VDE 0273/10.87, 0295/5.86, IECA A‐66‐524 NEMA WC7 

Annex‐A146  

E.4.6. FireresistantcableCritical loads which must continue to operate under fire conditions shall use fire 

resistant safety cables. 

Type Designation  NHXHX‐FE 180/E90 

Rated Voltage  Uo/Un = 0.6/1 kV 

AC test voltage  4 kV 

Retention of circuit integrity under fire conditions 

FE180 

Functionality of cabled system 

E90 

Designation Standards 

 

DIN VDE 0472, 4102, 0207, 0266, IEC 60332‐1, 60332‐3, 61034‐1, 60331, BS 6387/CW 

 

E.4.7. ControlcablesControl and instrumentation multi‐core control cables to be used for local control stations and instrumentation for discrete signals operating on 24VDC/220VAC/220VDC. 

Rated Voltage  0.6/1 kV AC 

AC test voltage  3500V 

Minimum bending radius  15 x cable diameter 

Conductors  1.5 sq. mm fine wire to VDE 0295 class 5 and IEC 228 class 5 

Color code  black cores with white numbers (VDE 0293) 

Protective Conductor  green‐yellow 

Designation Standards  VDE 0250, 0815 

Outer Jacket  Self‐extinguishing flame‐retardant PVC, test method B according to VDE 0472 part 804 and IEC 332‐1  

Temperature range  ‐40C to +90C 

Insulation resistance  min. 20 MOhm x km 

Annex‐A147  

E.4.8. Analogsignalcables1. Multi shielded twisted pairs or triads with served wire armor. 

2. Conductors: 16AWG, 7 strand concentric bare copper, class B. 

3. Conductor resistance: max. 39 Ohm/km 

4. Temperature range: ‐30C to +70C 5. Nominal voltage: max. 300V 

6. Test voltage:   

a. core/core 2000V 

b. core/screen 1000V 

7. Insulation resistance: min. 5 GOhm x km 

8. Mutual capacitance: nominal 75 nF/km @ 800 Hz 

9. Inductance: max. 0.75 mH/km 

10. Cross‐talk attenuation: min. 1.02 dB/km @ 60 kHz 

11. Color code: Pair black‐white 

a. Triad: black‐white‐red 

b. Each pair/triad numbered. 

12. Pair shield: 100% coverage Aluminum polyester foil. 

13. Drain wire: 22AWG tinned copper 

14. Overall shield: 100% coverage Aluminum polyester foil. 

15. Inner & outer Jacket: Self‐extinguishing flame‐retardant PVC, test method B according to VDE 0472 part 804 and IEC 332‐1. 

16. Armor: Multiple strands of served soft steel wire. 

 

E.4.9. Coppercommunicationcables

The copper communication cables shall comply with requirements of the following standards: 

1. ANSI/EIA/TIA‐568 Category 7A 

2. ANSI/EIA/TIA‐568A Category 7A 

3. ISO/IEC DIS 11801 Category 7A 

4. CENELEC EN 50167 

 

The cables shall feature low attenuation and low crosstalk. The cables shall be tested up to 1000 MHz and be suitable for fixed installations, indoor use. 

The cables shall be shielded twisted‐pair cables with at least 24 AWG copper conductors, self‐extinguishing fire retardant PVC outer jacket. 

Annex‐A148  

E.4.10. FiberopticcablesFiber optic cables shall be suitable for indoor and outdoor installation in partial occupied ducts and/or cable trays and/or blown into pipe. 

The cable shall hold optical fibers with primary coating inserted in jelly‐filled or unfilled loose tubes (not more than two fibers per tube). The loose tubes shall be of different colors, arranged around central strength member. The glass yarns shall surround the cable core acting as strength members and rodent protection. The cable outer sheath shall be made from wear‐resistant, UV‐resistant PE. A longitudinal water barrier shall be provided. 

Technical (optical and mechanical) characteristics shall be as follows: 

Fiber attenuation (maximum) 

 850 Nm 

1300 Nm 

 

3.75 dB/km 

1.75 dB/km 

Fiber bandwidth (minimum) 

 850 Nm 

1300 Nm 

 

160 MHz/km 

500 MHz/km 

Fiber numerical aperture  0.2750.02 

Fiber core diameter  62.53 m 

Fiber cladding diameter  1252 m 

Fiber primary coating diameter  25015 m 

Fiber core non‐circularity (maximum) 

6% 

Fiber cladding non‐circularity (maximum) 

2% 

Fiber MDF/cladding concentricity error (maximum) 

1.5 m 

Cable maximum tensile strength  3000 N 

Operating temperature  ‐30 to +70 C 

 

Each section of fiber optic cable shall be supplied in one full length segment on separate cable drum. The required length with 10% spare shall be determined by the measurement on site. A factory Optical Time Domain Reflect meter (OTDR) test shall be performed for each cable section supplied with test certificate submitted. A final OTDR test shall be executed after the cable installation and connection. 

Each fiber optic cable shall be threaded through 1¼” flexible protective pipe (one cable per pipe). 

Annex‐A149  

E.4.11. CableaccessoriesCable compression lugs shall be marked with manufacturer’s emblem with die size code number. Number of compression shall be marked along each lug. 

Standards: DIN 46267, 48201, 40500/2, 57295, 46235, ISO 9002, Quality management standard. 

Compression tools shall be pneumatic with hexagonal compression dies. 

Cable ties shall have the following properties: 

1. Limited Fire Hazard (LFH) Product 

2. UV protected 

3. Halogen Free. 

4. Service temperature ‐10C to +90C  

E.4.12. Firebarriersandcables'fireprotections

Opening in walls or ceilings which are designed for cable passage shall be sealed by UL approved sealing plates sprayed on both sides with 1.6 mm thick (minimum) fire resistant coating. 

Each cable penetrating through a fire sealing plate shall be sprayed by fire resistant coating covering at least 50 cm of cable on each side of the plate. 

Long runs of cables on trays or ladders shall be sprayed at 6 meters intervals with 1.5 meter long cable sections with the same coating. 

Fire sealant plate properties: 

1. UL approved to UL 1479, 2079 and ASTM C719 

2. pH: 10‐11 

3. Volume expansion ‐ 1000% 

4. Elastomeric, water‐based high solids, with no solvents, no silicones and no outgassing. 

5. Caulk able or trowel able. 

6. Easily repaired/repenetrated. 

E.4.13. Fireresistantcablecoatingproperties:1. Factory Mutual approved. 

2. Fire Propagation limitation: less than 10 according to ASTM E84‐81. 

3. Solid contents: 73% 

4. Flash point: None 

5. Dry coverage 18.5 sq. foot /gal for 2 mm thick coating. 

6. Ampacity reduction: None (for 4 mm thick coat). 

7. K factor: 4.09 

Annex‐A150  

E.5. ConnectingofElectricalFieldEquipmentElectrical Field Equipment includes motors, heating elements, control devices, 

etc. The connection of any load shall include as a minimum: 

1. Studying and verifying the specific wiring schemes, name plates 

supplied with any specific item ensuring it is compatible to the local 

electrical conditions. 

2. Adjustment of cable entrances on the load to the specific local 

condition, such as direction of cable entry route, diameter and/or 

thread of cable gland, improvement of the load connection box 

protection degree, etc. 

3. Preparing cable routes by means of cable trays, duct, rigid protection 

sleeve, etc. 

4. Installing flexible PVC coated armored sleeves on the last cable 

section entering the load. 

5. Testing the operation of the equipment including: rotational 

direction, measuring current consumption to be within rated values, 

calibration of all protection devices to the desired values, testing of 

manual and automatic modes of operation, and verifying 

inputs/outputs with the control system. 

6. Tag number on the load. Installing labels on all cables, wires, junction 

boxes, etc., as defined. 

7. Connection of a control device shall be same as described above with 

the following additions: 

a. The contractor shall coordinate the exact location of any 

control device with all other relevant subcontractors 

(mechanical, water, sewage, etc.). The final location shall 

enable easy maintenance and re‐calibration as well as 

aesthetic installation. 

b. The testing and calibration of the control device shall be 

performed according to the device’s instruction manual, using 

all auxiliary calibrating and measuring equipment dictated by 

the manufacturer. 

c. The proper function of the control device shall be finally 

approved only after verifying its integration in the complete 

control loop via operator’s control console and all other 

relevant displays. 

   

Annex‐A151  

E.5.1. FinalcalibrationFinal calibration of electrical loads and control devices shall be performed 

only when the relevant system operates under the nominal operating 

conditions on site. 

Contractor shall provide detailed calibration tables including: 

1. Tag number. 

2. Equipment type and Cat No. 

3. Calibration range and measuring units. 

4. PLC address. 

E.6. ElectricalSwitchboardsandpanels

E.6.1. GeneralDescriptionThis chapter deals with the Supply and Delivery of Electrical Switchboards and 

panels which are divided into the following main categories: 

1. Power distribution, PLC/RTU and auxiliary panel boards for indoor 

installations, located in electrical rooms or electrical niches. 

2. Motor Control Centers (MCCs) 

3. All LV ‐ Power distribution and control shall be design and build 

accordance to Israel regulation 61439 

E.6.2. Climatecondition,StandardsandRegulations

The work under this chapter shall be in accordance to climatic conditions for 

tropical climates, mentioned in "Project location and environmental 

conditions" see section A, and be protected against rust, corrosion, fungus, 

and salty atmosphere. 

 

   

Annex‐A152  

E.6.3. WorkshopdrawingssubmittalThe following shop drawings shall be submitted to the CPM within three 

months from date of contract award: 

1. Detailed drawing of each panel showing overall dimension, typical 

cross sections and mounting details. 

2. Single line diagram of the board. 

3. Connection diagram (Wiring diagram). 

4. Front view of the panel with closed doors. 

5. Front view of the panel with open doors, showing all the equipment 

installed, including wiring ducts. 

6. Official laboratory test results to short‐circuit current withstand. 

7. List of electrical and mechanical parts in the panel, name of 

manufacturer related to the tag numbers shown on drawings and 

quantities required for each panel. 

8. Manufacture’s catalogues standardized items. 

9. Corrosion protection details for each item including painting 

procedures, materials, etc., as applicable. 

10. Quality control program, with certification of ISO 9002 standard. 

11. Proposed inspection program. 

12. Performance Testing procedure and program. 

13. Installing, Operating and maintenance instructions. 

14. Schedule of Particulars. 

E.6.4. ConstructionThe construction shall suit the following installation modes: 

1. For installation on pre casted concrete bases. 

2. For installation on walls. 

3. For installation on pre casted bases on rising frames, supports, etc. 

4. For installation on floating floor with supports and frame with back 

access or only front access. In case of back access possibilities back 

panel doors shall be installed with key locks or padlocks. 

5. The board structure shall ensure safe and separate access to each of 

the compartment according to different functions and tensions as 

describes below: 

6. Explosion ventilation ducts. 

7. Functional unit. 

8. Bus bars. 

9. Cables' race way. 

10. Accessible live parts in the boards shall be protected by means of 

insulation plates. 

Annex‐A153  

11. The Contractor is responsible for the equipment performance of both, 

mechanical and electrical aspects, and shall meet the specification 

requirements and targets of the switch board. 

E.6.5. SwitchboardsandpanelsThe construction of the switchboard has to be fabricated by using a complete 

modular system where all the components are standard items. All structure 

must be made of phosphatized TC sheet metal or alu‐zinc. 

All doors and plates must be interchangeable and may be hinged left, right, 

top or bottom as standard. 

Doors may be lifted to the front, back, side top or bottom of a panel. 

Double doors must be lifted without any dividing bar to provide a total 

opening of 1500 mm. 

Doors must be provided with an integral gasket and earth stud as standard 

and a range of locks to meet all regulations. 

Doors must be fully locked before a device can be switched on, to ensure 

operator safety in the event of switching onto a fault. 

All switchboards must be type tested as per IEC 60439‐1. There must be 

separation of bus bars from the other functional units in order to: 

1. Eliminate accident contact with live parts. 

2. Limit the probability of initiating arc fault. 

3. Prevent the penetration of solid objects. 

 

The bus bar system should be tested by official laboratories as KEMA, IPH and 

ASTA for a safety past a short circuit x 100 kV for 2 sec. 

The bus bar section must obtain its own explosion flap to allow the safe 

escape of the resultant overpressure and ionized gases. 

The busbars system and the framework must be modular design. 

In designing a type 2 tested assemblies, width of cableways must be 

incorporated on the number of cables and their size. 

Cables must run the whole length of the switchboard at the top and bottom 

as well as vertically beside each functional unit section. 

Gland facilities must be provided at the top, bottom or, adjacent to each 

functional unit. Cable support rails on to which cables may be clamped must 

Annex‐A154  

be provided at various heights in each cableway. Cableways must also be 

provided with explosion flaps. 

Where necessary, a heating element controlled by thermostat shall be 

installed to prevent condensation. 

Visual and thermograph implication for hot spots on all outgoing cables under 

live conditions will be achieved by removing the cableway panel. 

All sections in the switchboard must be designed to contain smoke detectors 

(two for each section) and space to install gas suppression system. 

25% space allocation shall be reserved for future use (minimum). 

   

Annex‐A155  

E.6.6. ColorsofbusbarsandwiringinboardsandpanelsThe colors of bus bars and of wires in the boards shall be as follows. 

  

  Voltage/Ampere  Color code Wire 

Color code Terminal 

CABLE  Phase R Phase S Phase T Neutral ‐0 Ground  

230/400V AC  BrownBrown ‐Orange Brown –Black blue yellow‐green 

gray 

Wire In side  cabinet 

Phase R Phase S Phase T 

230V AC   BrownRemark‐all the 230V wires are brown  

gray 

Neutral ‐0    blue  blue 

Ground    yellow‐green  yellow‐green 

  +24V DC  Red  red 

  ‐0V DC  Black  black 

Input PLC  24 V DC  violet  blue 

Output PLC  24 V DC  orange  orange 

Analog  equipment  4‐20mmA  Black/ white  Pink or White 

  Fire  +24V DC  Red  red 

    ‐0V DC  black  red 

Annex‐A156  

E.6.7. MarkingonboardsEvery field device or cell of the board shall be clearly marked at its upper fixed by an identification number and/or name of the field device or the cell, such marking being separated from the other marking and signboards. 

The Contractor shall mark all equipment including, busbars with identification marks, signboards, labels or other marking, all according to the drawing and the engineer’s approval. The identification tags shall also be placed on the fixed frame of the board, so as to remain undisturbed in the event of replacement of equipment, cover, etc. 

All terminals shall be tagged in accordance with the tag names on the approved drawing. 

Every wire shall be tagged at each end, in keeping with the approved drawings. The end of the wire connected to a busbar shall bear the tag of the supply circuit or the control circuit, this being in accordance with the single line diagrams or control diagrams. 

Where several wires are connected to the same bus bar or the same terminal, in the same supply, or control circuit ‐ every wire shall be tagged with the marking of the circuit, followed by dash and by the phase number or by a serial number. 

E.6.8. Cableconnection

Provision shall be made for every cable to be fixed as its entry into a board, instrument or box. The cable armor shall be grounded and protected by a shrink‐on sleeve. 

 

The labeling of every cable/wire shall be made in accordance with the “Marking and Labeling” chapter above. 

 

The ground bar shall be located as to permit the ground of the armor or screen of the cable in an easily accessible conspicuous location`. 

 

E.6.9. FactorytestsBoards specified under this chapter shall pass the tests stipulated below. Such tests shall be carried out in the presence of the CPM and/or owner and/or his Representative. 

For each assembled Switchboard and its compartments, the following inspections and tests are required: 

1. Examination of materials and quality of workmanship. 2. Examination whether the Switchboard, i.e. construction 

electrical equipment, complies with the codes and standards, especially VDE 0660. 

3. Tests according to VDE 0660. 4. Paintwork tests: 

Annex‐A157  

Visual examination of the paintwork on all part of the Switchboard. 

Paint adhesion test in accordance with ISO 2808 on at least three parts. 

Determination of paint film thickness in accordance with ISO 2808 method 5 (nondestructive tests for paints and varnishes) on at least three parts of each group of Switchboards. 

5. Material specifications of: 

Insulators and insulating materials. 

Busbars 

Screw, bolts, nuts, etc. 

6. For low voltage equipment such as: protective relays, measuring instruments, lamps, push buttons, and switches. Test reports of the manufacturer are acceptable. 

7. Tests confirming the control and protection functions by means of Contractor’s simulator board. 

   

Annex‐A158  

E.6.10. MiscellaneousThe subsidiary panels will be built as metal cupboards with metal panels and 

doors for wall installation and/or free standing. 

In order to dismantle panels or open doors it will not be necessary to release 

screws of handles, switches, other fittings. 

Bus bars will be made of electrolytic copper. They will be arranged and fixed 

inside the structure of the panels in such a way that all the connection 

screws can be dealt with easily. Fastening of the busbars will not be 

attached to the structure. The bus bars will be suited to the nominal current 

intended for the panel, and their fixing will withstand the short‐circuit 

currents. The bus bars will be covered with a transparent covering for 

protection against accidental touch. The bus bars will be finished on both 

sides of the panel in such a way that it will be at the top of the panel. The 

order of the phases in all instruments will be identical. The section of the 

conductors will conform to the Israeli Standard, the electricity regulations, 

and the size of the automatic switch. 

The neutral and the earth strips will be installed in such a way as to allow 

connection of every separate conductor. 

Every conductor will have a separate tightening screw, with an addition of 

25% for future connections. The strips will be marked with standard marks. 

The panels will be painted with powder epoxy paint by the electrostatic 

method, after the required preparation. The color will be fixed by the 

customer. The thickness of the color will be at least 90 microns. 

The external marking signs will be plastic of the standard size, no smaller 

than 25 x 17.5 mm. In addition, on the external panel all the fittings will be 

marked with numbers by stickers in a place visible after removal covers or 

the doors. The wording of the sign will be in accordance with the plans or 

the supervisor’s instructions. The sticker marking will be by typing or clear 

technical writing. 

The panel will contain a compartment for the plans and drawings 

All contactors will be adapted to AC‐3, 1 million operations at 400 VAC. 

The circuit breakers will have a short circuit capacity, according to IEC 

60947‐2 regulations. 

   

Annex‐A159  

E.7. Motorcontrolcenters(MCC)

E.7.1. GeneraldescriptionThis section includes motor control centers for use on AC circuits rated up to 

600V. 

E.7.2. SubmittalsProduct Data: For products specified in this Section. Include dimensions, 

rating and data on features and components. 

Shop drawings: For each motor control center, specified in this Section, 

Include dimension drawings, elevations and component list, ratings 

including short time and short circuit ratings, as well as horizontal and 

vertical bus assemblies. 

Schedule of features, characteristics, ratings, and factory settings of 

individual motor control center units 

Wiring Diagrams: Interconnecting wiring diagrams pertinent to class and 

type specified for motor control center.  Schematic diagram of each type of 

controller unit indicated. Power and control terminals including PLC control 

terminals and their addresses. 

Equipment schedules with nominal and short circuit capacities according to 

IEC 60947‐2. 

E.7.3. QualityassuranceManufacturer shall have a service center capable of providing spare parts, 

emergency maintenance and repairs and onsite training. 

Provide similar motor control devices from one source and from a single 

manufacturer. 

Comply with the codes: IS 1238, IEC 60292, 60947‐2 

Product Selection for Restricted Space: Drawings indicate maximum 

dimensions for motor control centers, including; clearances between motor 

control center panels, adjacent surfaces, and components.  All is based on 

types and models indicated. 

E.7.4. Delivery&StorageIn case of long electrical panels if prepared in advance, it is possible to splits 

the length of the panels to enable easy transportation and delivery to site. 

Panels will be reassembling on site. If site storage is required, avoid 

condensation. 

Annex‐A160  

E.7.5. CoordinationCoordinate features of controlled and accessory devices with pilot devices 

and control circuits to which they connect. 

Coordinate features, accessories and functions of each motor controller with 

the ratings and characteristics of the supply circuit, the motor, the required 

control sequence, and the duty cycle of the motor and load. 

Provide separate terminal strips with different colors for various voltage 

level and destinations; field wiring, PLC discrete wiring, PLC analog wiring, 

internal wiring, etc. 

Enclosures shall be surface mounted cabinets as indicated. IP23, unless 

otherwise indicated, to meet environmental conditioned at installed 

location. 

Compartments: Modular, individual doors with concealed hinges and quick‐

captive screw fasteners. Interlocks on combination controller units require 

disconnect means in off position before door can be opened or closed, 

except by consciously operating a permissive release device. 

Interchangeability: Compartments shall be constructed to remove units 

without opening adjacent doors, disconnecting adjacent compartments, or 

disturbing the operation of other units in control center. Units requiring the 

same size compartment shall be interchangeable and compartments shall be 

constructed to permit ready rearrangement of units, such as replacing 3 

single units with a unit requiring 3 spaces, without cutting or welding. 

Wiring Spaces: Each vertical section of structure with horizontal and vertical 

wiring shall have spaces for wiring to each unit compartment in each 

section, with supports holding wiring in place. 

Short Circuit Current:  

Rating shall be equal to or greater than indicated available fault current in 

asymmetrical amperes at motor control center location. 

65kA ‐ If not specified otherwise. 

Annex‐A161  

E.7.6. BusesMaterial: Plated copper. 

Ampacity Ratings: As indicated for horizontal and vertical main buses. 

Neutral Buses: Full size. 

Ground Bus: Non insulated, horizontal copper. 

Horizontal Bus Arrangement: Main phase, neutral and ground buses 

extended with same capacity the entire length of motor control center, with 

provision for future extension at both ends by bolt holes and captive bus 

splice sections or approved equivalent. 

E.7.7. FunctionalFeaturesDescription: 

Modular arrangement of motor controllers, control devices, over‐current 

protective devices, transformers, panel boards, instruments, indicting 

panels, blank panels, and other items mounted in compartments of motor 

control center as indicated. 

 

Motor controller units:  

Combination controller units of types and with features, rating and circuit 

assignments indicated. 

Units with full voltage, across the line, magnetic controllers are installed on 

drawout mounting with connectors that automatically line up and connect 

with vertical section buses while being racked into their normal, energized 

position. 

Units shall have short circuit current ratings equal to or greater than short 

circuit current rating of motor control center section. 

 

Over‐current Protective Devices: Types of devices with features, ratings and 

circuit assignments indicated. Individual units shall be installed on the draw‐

out mounting. 

 

Annex‐A162  

Transient Voltage Surge Suppressers: Connected to motor control center 

bus. (If shown on drawing). 

 

Spaces and Blank Units: Compartments fully bused and equipped with guide 

rails or equivalent, ready for insertion of draw out units. 

 

Spare units: Type, sizes and rating as indicated, and installed in 

compartments indicated “spare”. 

E.7.8. MotorControllersDescription: 

1. Full voltage, non‐reversing, across the line, unless otherwise 

indicated. 

2. Control circuit: 230 VAC and 24 VDC obtained from central control 

supply panel. 

3. Combination Controller: Factory assembled combination controller 

and disconnect circuit breaker with or without over‐current 

protection as indicated. 

4. Overload Relay: Ambient compensated type with inverse time 

current characteristic. Provide with heaters or sensors in each phase 

matched to nameplate full load current of specific motor to which 

they connect, and with appropriate adjustment for duty cycle, with 

protection against voltage unbalance and single phasing. 

5. Star Delta Controller: Closed transition with adjustable time delay. 

6. Part Winding Controller: Closed transition with separate overload 

relays for starting and running sequences. 

7. Auto transformers Reduced Voltage Controller: NEMA ICS2, closed 

transition. 

8. Solid state, Reduced Voltage Controller: suitable for use with 

polyphase, medium induction motors. 

9. Adjustable acceleration and deceleration rates control using voltage 

or current ramp, and adjustable starting torque control shall have 

up to 500% current limitation for 20 seconds. 

10. Surge suppresser in solid state power circuits shall provide 3 phase 

protection against damage from supply voltage surges 10% or more 

above nominal line voltage. 

   

Annex‐A163  

 

11. LCD indicators for motor and control status, including the following 

parameters: 

i. Control power available. 

ii. Controller on. 

iii. Overload trip. 

iv. Loss of phase. 

v. Shorted silicon controller rectifier. 

vi. Voltages. 

vii. Currents. 

viii. Ramp/slope parameters. 

 

12. Automatic voltage reduction controls to reduce voltage when motor 

is running at light load. 

13. Dry contact shall indicate “end of start” condition. 

14. Motor running contactor shall operate automatically when full 

voltage is applied to motor. 

E.7.9. VariableFrequencyControllersDescription: 

1. Variable frequency controller shall be listed and labeled as a complete unit, and arranged to provide variable speed of a standard 3 phase, induction motor by adjusting output voltage and frequency. 

2. Design and Rating: Match load type, such as fans, blowers, pumps and type of connection used between motor and load such as direct or through a power transmission connection. 

3. Isolation Transformer: Match transformer voltage rating and capacity to system and motor voltages, and controller, motor, drive and load characteristics. 

4. Output Rating: 3 phase, 6 to 100 Hz, with horsepower constant throughout speed range. 

5. Starting Torque: 100% of rated torque or as indicated. 6. Speed Regulation: Plus or minus 1%. 

Annex‐A164  

E.8. CorrosionProtectionandPaintingSystemNo bare surfaces of metal parts and material are allowed. All such surfaces shall be painted, coated and protected. 

E.8.1. SwitchboardsandpanelsAll the surface of the switchboard structures shall be cleaned and be given a complete treatment of surface preparation, priming and finishing costs to attain durable corrosion protection system. 

Surface protection shall be as follows: 

Structure and frame: electro‐galvanized. 

Internal subsections, zinc passivation. 

 

This coating procedure shall be carried out and tested according to Israel standard No. 265 (October ‘71), “zinc electrolytes coating on ferrous metals.” 

The thickness of the coats will be according to table 2, degree 3 of I.S. 265, and at least 25 microns. 

E.8.2. EpoxyPaintSystem

The surfaces to be painted shall be cleaned and prepared as specified and shall be coated as follows: 

A prime coat of epoxy paint to a finished dry thickness of 40 microns; 

A second prime coat of epoxy paint to a finish dry filed thickness of 40 microns; 

A finishing coat of epoxy paint to a finished dry thickness of 40 microns. 

 

The dry film thickness of all the coating together shall nowhere be less than 100 microns. 

E.8.3. SyntheticPaintSystem

The Surface to be painted shall be cleaned and prepared as specified and shall be coated as follows: 

A prime coat of zinc chromate primer to a finished dry film thickness of 40 microns. 

A phenolic based paint system, comprising one or two coats, to a total finished dry film thickness of 40 microns. 

A finishing coat of synthetic mat paint to a finished dry film thickness of 40 microns. 

The dry film thickness of all the coating together shall nowhere be less than 100 microns. 

Annex‐A165  

E.8.4. FerrouspartsinsidebuildingsAll steel construction parts, supports, bare pipes and ferrous accessories shall be painted. Painting of such parts and material shall be after a “commercial grade” sand blast cleaning. Painting shall be with 2 coats (two different colors) of zinc‐bromate prime coat, 25µ thickness of each coat. Another 2 coats of exterior finish, each coat in a different color, shall be applied. Paint shall be of “exterior for steel construction” type. Finish shall be “light steel gray” unless otherwise instructed. 

E.8.5. FerrouspartsoutsidebuildingsAll steel‐made equipment, supports and other ferrous exposed parts shall be epoxy painted after sand‐blast cleaning to “near white” grade (2½ according to the Swedish Code). Painting shall be with four coats of epoxy primer paint, each coat 40µ thick. 

E.8.6. SteelpipingAll pipes shall be painted after cleaning with mechanical steel wire brush. Painting shall be with two coats of lead oxide (“minimum”) in two different colors. Each coat shall be 25µ thickness minimum. Another 2 coats of exterior finish, each coat 25µ thick, shall be applied. 

E.8.7. Galvanizedpipes

Outside surfaces of all galvanized pipes and fittings shall be painted. Surface cleaning shall be performed using the adequate solvent cleaner. Painting shall be with one coat of binder and one 40µ thick layer of zinc‐chromate primer. 25µ thick finish coat of “exterior for steel constructions” type shall be applied. 

E.8.8. Pipingcolors

Colors for piping and fittings shall be according to I.S. 659. 

E.8.9. Corrosionprotectionforconnectingaccessories 

Bolts, nuts, washers, threaded rods and similar accessories shall be galvanized with 25µ minimum galvanization coat or cadmium‐plated with 12.5µ thick coat. 

Rivets shall be galvanized only. 

   

Annex‐A166  

E.9. FireProtectionThe fire detection and protection system must provide coverage for all of the Facility and comply with NFPA codes in addition to all statutory and local authority requirements, and the requirements of IAA. The winning Bidder must present for approval the Facility design fire detection and protection systems to: 

•  IAA's Technical Manager 

•  Israel Fire and Rescue department 

E.9.1. ElectricalPanelsfiresystemAll electrical panels above 63A shall be equipped with fire protection device as follows: 

1. Electrical panels from 63 A  to 100 A (100A not included) shall be design with smoke detection only. 

2. Electrical panels from 100 A  and higher with smoke detection and dry extinguishing system. 

The fire protection device shall be connected to the fire control system. In case of smoke detection inside the panel the system shall behave as follows: 

1. Disconnecting power supply to the panel  2. All cooling fans shall be stop, in order to prevent oxygen (air) 3. Fire alarm and system shall be presented on the SCADA  

  

 

 

Annex‐A167  

F. ChapterF:MECHNICALSECTION

F.1. GeneralThis chapter covers all mechanical and equipment work required for the 

installation of the new generator and absorption Liquid Chillers. 

F.2. PipeWorkandFitting

F.2.1. GeneralThis Section specifies the requirements to furnish and install the plant piping 

systems.  The work shall include, but not be limited to, all pipes, tubing, 

restraints, isolators, pipe cleaning, and pressure testing. 

The Contractor shall employ labor that is qualified by training and 

experience to perform the specified activities required to accomplish the 

work in a satisfactory manner. 

All pipe drops shall be truly vertical, no joints shall be welded in thickness of 

walls, floors or ceilings. The Contractor is responsible for obtaining from 

other trades the thickness of plaster and other wall finishes, skirting heights, 

and floor finishes. 

Pipe work, in general, shall be set around all columns and shall follow the 

building contour. Piping shall not pass in front of door ‐ways so that it is at 

least 8 cm. above finished floor level and at least 5.0 cm from finished wall 

face. Sufficient space shall be allowed for piping insulation, piping supports 

and accessibility for servicing. 

Piping shall be pitched for proper circulation and drainage. Run‐outs shall be 

graded in such a manner as to prevent air traps from being formed.  

Automatic or open vents are to be provided at high points and piped to be 

suitably sloped to allow for system drainage. 

All drain piping shall pitch down in the direction of flow. 

All low points of the system must be fitted with drain valves with hose end 

connections and cap, to permit the complete draining of the system  

Bottoms of all risers must have dirt pockets the same size of the riser and at 

least 

 30 cm long with a capped drain valve fitted. 

All piping to equipment and valves shall be connected with either flanges or 

unions for dismantling and removal. 

All piping shall be reamed after cutting to remove all burrs. 

Annex‐A168  

All reductions in sizes of piping in the direction of downward pitch shall be 

installed with eccentric fittings to maintain a leveled bottom. 

Approved pipe fittings shall be used and bending of pipes shall not be 

allowed. 

Pipe bends showing kinks, wrinkles, or other malformations, are not 

accepted. 

Cutting of bends shall not be permitted. Piping passing through ductwork or 

directly under electric light outlets or extend beyond furring lines, shall not 

be installed. 

In placing pipes through sleeves, near walls, partitions or in chases care 

must be taken to provide sufficient space for pipe insulation and supports. . 

Where pipes are held by vises, or screwing. Care shall be taken to ensure 

that the pipe surface is not damaged.  Damaged pipe‐work shall not be 

installed. 

All pipes stored on site shall be kept clear off the ground and where possible 

stored under cover. Pipes corroded beyond normal "stock rust" condition 

shall not be used. Special care should be taken to prevent dirt and foreign 

matter entering open ends of pipes during installation. 

All pipe‐work, valves, fittings, etc., for the various services, shall be as 

detailed in the schedules forming part of this specification. 

The contractor is responsible for all underground piping excavation including 

permits and coordination needed. 

 

F.2.2. PipingcoatingAll metal piping shall be cleaned to 2.5SA with sand or blast clean and 

painted 3 layers of epoxy type coating as TAMAGLASS or equal. 

 

Annex‐A169  

F.3. WeldingWelding shall be used as follows: Where shown on drawings, specified or 

directed welded joints, outlets and flanges. Care shall be taken to ensure that 

welding metal or flux does not project into the bore of the pipe. All welds 

shall be of good clean metal free from slag and porosity. All welded joints 

shall be of even thickness and contour, well fused with the parent metal. 

When completed, all welded joints shall be hammered on completion and 

finished smoothly. 

The Engineer reserves the right to have 2 % of all welds examined by an 

approved lab. If welds examined do not meet standards, the Contractor shall 

re‐weld these joints at no extra charge. IAA / owner representative reserves 

the right to examine two additional welded joints, one before and one after 

the failed welded joint. 

All welded joints (except pipe welded end to end ) shall be made by use of 

forged one ‐piece, welding flanges, caps, elbows , branch outlets and tees of 

approved make. 

All such fittings, etc. shall be of a type which maintains full wall thickness at all 

points, ample radius fillets, and proper levels or shoulders at ends. 

All welding may be by electric welding or acetylene process. 

Wherever piping   connections to equipment, valves, or other units need  

maintenance, servicing , or require possible removal , the connecting joint 

shall be by means of unions of flanges. Pressure rating of flanges shall match 

the pressure rating of the flanges on the equipment to which the pipe is 

connected to. 

F.3.1. WeldingQA/QCThe Contractor for pipe installation quality control shall designate a quality 

control professional (QCR) examiner acceptable to the Contractor to inspect 

the installation, cleaning, and testing of the piping systems.  He shall also be 

responsible to maintain records of all inspected spools and appurtenances 

and records of approval by the owner / representative.  QCR/examiner shall 

be qualified as a welding inspector specialist (WIS), and Welding Inspector 

Assistant, which includes; visual examination, education, experience, 

training, qualification, and ethical requirements. QCR/examiner shall submit 

necessary proof of qualification to the Contractor, owner / representative, 

for approval.  Documentation shall include Contractor “written practice” 

which covers inspector's training, qualification, certification, topics and 

subjects of training programs and names of company personnel 

administering and auditing the certification program. 

Annex‐A170  

If the Contractor has developed alternative techniques or intends to apply 

alternative methods considered equivalent to those indicated herein, a 

proposal on such techniques or methods shall be submitted in writing to the 

CPM / owner representative for review and approval at least 14 days before 

intended date of use. 

 

F.3.2. References American Society of Mechanical Engineers (ASME). 

American Society for Nondestructive Testing (ASNT). 

National Fire Protection Association (NFPA). 

 

F.3.3. Submittals Subcontractor shall submit a weld procedure specification (WPS), 

per the ASME BPV code, Section IX, to the Contractor/QAR for 

approval for all pipe and tube welding. 

Qualifications shall be done by an ASME or ASNT lab certified for 

GTAW and SMAW. 

Copies of test reports shall be provided to the owner / 

representative. 

 

F.3.4. ProjectRecordDocuments At close of the project, the Contractor shall submit to the owner / 

representative all welding installation records which shall include:  

Weld examination procedures, weld examinations, weld logs, 

welder qualification examinations, pressure tests, and leak tests. 

F.4. FlangesFlange face vertical:  Bolt holes to straddle the vertical centerlines. 

Flange face horizontal:  Bolt holes to straddle plant north‐south centerlines. 

Welds at orifice flanges shall have internal surfaces ground smooth to the 

pipe wall. 

Slip‐on flanges shall be welded inside and outside.  There shall be a distance 

of approximately 1/16 to 1/8 inch between the edge of the fillet weld and the 

Annex‐A171  

face of the flange.  The seal weld shall be applied so that the flange face shall 

be free of weld spatter and does not require resurfacing. 

Use flat‐faced flanges when mating to Class 125 flanges.  Use full‐face gaskets 

with flat‐faced flanges and ring gaskets with raised faced flanges. 

Weld neck flanges shall be used with butt‐weld fittings unless specified 

otherwise in individual piping section. 

Flange bolts shall be torqued to the minimum value required by the 

manufacturer of the gasket material specified. 

The bore of weld‐neck flanges shall match the pipe wall thickness. 

Use of flanges on welded systems shall only be permitted where required to 

connect to a flanged component such as a flanged valve, pressure vessel or as 

identified by component data sheet / submittals.  Exceptions are flanges for 

future requirements as noted on drawings or by RFI process. 

F.5. SealWeldingWhen seal welding is required, connections shall be made without using 

sealing compound or Teflon tape. 

Do not seal weld threaded joints that have failed a pressure test unless all 

thread compound and Teflon tape was removed. 

Seal welds of threaded connections shall cover all exposed threads. 

F.6. BoltsAll bolt threads are to be coated with Never‐Seez (Cat. No. NSBT‐16) prior to 

being made up with nuts, unless otherwise specified in the Detail Piping 

System Specifications or Pipe Class Specification Sheets. 

Alternate coating shall be used only with prior review by the Engineers.   

 Approved products (or equal): 

Krytox 206 (Dupont). 

Krytox LVP (Dupont). 

815Z/1613 (Bray Co.). 

   

Annex‐A172  

F.7. BuildingPiping 

Provide chrome escutcheon finish plates where piping passes through walls, 

floors, or ceilings in finished areas and cabinets. 

All major piping penetrations of footings, slabs, floors, walls, and roofs shall 

be as shown on the Drawings.  It shall be the contractor’s responsibility to 

verify the size and location of all building and structure penetrations prior to 

pouring concrete or finishing. Ensure that fire‐stops are installed for all piping 

penetrations requiring fire‐stops. 

Wall pipes and pipe sleeves embedded in concrete walls, floors, and slabs 

shall be embedded as shown on the Drawings.  Support all pipes embedded in 

concrete walls, floors, and slabs with formwork to prevent contact with the 

reinforcing steel. 

Galvanized steel pipe sleeves shall be used on all standard wall penetrations.  

Waterproof pipe sleeves that incorporate waterproof membrane. Seals shall 

be used for all piping penetrating exterior walls, roof, and floor slabs on 

grade. 

Galvanized or PVC sleeves shall be used on penetrations of footing walls and 

grade beams 

 Fire‐rated or smoke‐rated pipe penetrations:  All piping that penetrates fire‐

rated or smoke‐rated, walls, floors, or ceilings shall be fitted with insulated 

and encased pipe sleeves. 

 All piping shall be installed parallel to horizontal and vertical building lines 

except as indicated in the plan drawings.  Uniform slope between bottom‐of‐

pipe elevations defined on the plan drawings shall be maintained. Piping 

installation shall be at high elevations to maintained sufficient headroom. 

 Where unions are indicated on the Drawings, dielectric unions shall be used 

for the following service locations: 

Aboveground/underground dissimilar metal pipe transitions. 

Copper/steel transitions for cold services, less than 60 degrees F, not 

insulated, not chemically treated. 

Copper/steel transitions for services greater than 60 degrees F, bronze or 

brass unions are required. 

Dielectric unions used on boiler water piping shall have EPDM or Viton 

seals. 

Annex‐A173  

F.8. AirVentsandLowPointDrains1. Piping vents and drains required for operation are shown on the piping and 

instrumentation drawings (P&ID).  However, vents and drains at all high and 

low points in the piping that are required for complete venting and draining 

may not be shown on these Drawings.  The Contractor shall add such items 

as found to be necessary during detail piping design and/or piping 

installation to allow both operation and testing without air remaining 

trapped in the system. 

2. Vent the high points and drain at low points shall be with 25mm ‐ 50mm ball 

valves on those pipelines, pending on pipe size.  Vent and drain branch pipes 

shall be welded to header not threaded.  Each drain or vent valve shall have 

hose bib connection and cap.  Provide automatic air vents at high points, 

including piping to nearest drain. 

3. Dead legs – Contractor shall configure piping to eliminate dead‐legs 

exceeding 4 times the internal diameter.  Examples are at future pumps, and 

isolation valves.  Valves should be close to the main pipe.  Where this is not 

possible, a hard pipe jumper of the same material and specification as the 

rest of the system shall be installed between supply and return.  This applies 

to CHW & HW systems.  Jumper size shall be as approved by owner / 

representative. 

4. Contractor shall plan pipe flushing and passivation procedures to be 

approved by the CPM / owner representative. Contractor shall provide 

piping connections required to achieve the flushing and chemical treatment 

procedures 

F.9. Materialofpiping:  

Service                       Material Type                Specification standard   

Chilled and        Seamless                       Black Schedule 40 ASTM A53,A120 

condensing                

   

water  

Vent                    Seamless                        Black steel  Schedule 40  ASTM  

Drain           Copper              Hard type L 

 

 

Annex‐A174  

F.10. MaterialofpipeFitting: 

Service          Size                Material Type  standard   

Chilled & condensing       2" & below               M.I Screwed ANSI B16.11 

Water                

Chilled and condensing       2" & above     Steel welding ANSI B16.9   

Water        

Vent            All       M.I Screwed   ANSI B16.11  

Drain            All      wrought copper  

   

F.11. PipeSupportsandAnchorsAll supports for steel piping shall be ferrous. Brackets or supports shall be set 

out so they do not obstruct the access to valves, flanges or other fittings 

requiring maintenance. 

All pipe work shall be supported by means of approved clips or hangers at 

centers described below. In the event of two or more pipes being carried by a 

single support the spacing shall be for the shorter interval. 

All piping supports and anchors to be provided by the contractor and 

approved by the building civil engineer. 

All vertical drops shall be supported so as to prevent sagging or swinging. 

Unless otherwise indicated, pipe hangers shall be spaced as follows: 

Pipe size  Max. hanger spacing Galvanized Rod size one 10mm 

1" and smaller 1 1/4" to 3 " 4" to 8" 10" to 12"  14"and larger 

- 1.80 m -  2.70 m  

one 12mm two 18 mm  two 24mm   two 35mm 

 

 

   

Annex‐A175  

 

F.12. PipeInsulationProtectionSaddlesInsulation shields shall be used to protect the insulation on all pipes. 

Insulation protection saddles shall be welded to insulated pipes at roller 

supports. Wherever fiberglass pipe insulation is installed, alternative high 

density insulation of equal thickness shall be  inserted. The insulation shields 

shall bear only on an insulation material which is of such density that it will 

not compress, crush or deform. 

Saddles shall consist of 1.5 mm galvanized steel plate. Plate shall be curved to 

fit the contour of the insulation and shall cover the lower surface. 

Saddles shall be secured to insulation by means of steel bands. 

F.13. PipeSleevesAll pipes opening through walls, partitions and slabs shall have sleeves having 

an internal diameter at least 25mm larger than the outside diameter of the 

pipe or of the pipe with insulation passing through. 

Pipe sleeves shall be of galvanized standard weight steel pipe, and shall be 

flush with walls, ceilings and extending 25mm above finished floors. 

Pipes passing through interior partitions shall be provided with sleeves of 0.8 

mm galvanized sheet steel flush with finished wall surfaces. 

F.14. FlashingSleevesFlashing sleeves shall be provided where pipes pass through water¬ proof 

membranes .Flashing sleeve details shall be submitted to the Engineer for 

approval but generally they shall be provided with an integral flange set into 

the membrane. The associated pipe shall also have a flange and shield which 

shall extend beyond the insert and be sealed with approved mastic. 

F.15. UnionsUnions are required on pipe sizes 2" and under. Unions shall be ground taper 

joint type suitable for 10 bar working pressure. Unions shall have bronze 

conical seats. Flat unions shall not be used. 

F.16. ScrewedJointsonSteelpipingScrewed joints shall be clean threaded with approved joint compound and 

long strand hemp. After joints have been formed all surplus hemp shall be cut 

away and the joints wiped clean. Where pipes are galvanized care shall be 

taken to ensure that threads are   carefully   cut so that the number of 

exposed threads is minimized. 

Annex‐A176  

F.17. PocketsinpipesforaccessoriesThe contractor shall furnish and install all pockets required in the pipes for 

accessories sensors and controls. All pocket shall be bronze  3/4" ‐1" in 

diameter. Provide 50mm extension for insulated piping, provide cap nut with 

chain fastened permanently to thermometer well. Submittals to be approved 

prior to installation 

F.18. PipePressureTesting

F.18.1. General:The pressure testing requirements defined herein apply to all piping 

systems unless specified in specific piping systems. 

Testing shall be performed by the Contractor on all piping after piping 

installation but before insulation is applied.  Furnish all necessary 

equipment and material and make all taps in the pipe as required.  

The installing Contractor's QA/QC representative will monitor the 

tests.  

Testing shall also be required to this standard for any section or 

sections which are modified or repaired after the initial pressure test 

is conducted and completed.  This is to insure that every component 

and joint in the system is pressure tested prior to being used for 

production. 

Unless otherwise required by the Specifications, shop fabricated pipe 

spools are not required to be hydrostatically tested at the shop.  

Spools shall be field tested after installation.  The contractor shall be 

responsible for the cost of correction of any defects revealed during 

field hydrostatic tests. 

Test pressure to be not less than 10 bar. 

F.18.2. TestingBuriedPiping:Conduct final acceptance tests on buried piping that is to be pressure 

tested after the trench has been partially backfilled unless otherwise 

specified.  The installing Contractor shall, if field conditions permit 

and as determined by the Contractor over all the works, partially 

backfill the trench and leave the joints open for inspection and 

conduct an initial service leak test.  The acceptance test shall not, 

however, be conducted until backfilling has been completed. 

Where any section of pipe is provided with concrete reaction 

blocking, do not conduct the pressure test until at least 5 days have 

elapsed after the concrete thrust blocking is installed. 

Annex‐A177  

Buried piping that is to be pneumatically tested or subjected only to 

an initial service leak test shall have all joints exposed for the 

acceptance test. 

F.18.3. TestProcedures:The Subcontractor is responsible for providing the necessary test 

gauges. The gauges shall have plus or minus 0.25 percent accuracy 

and a 4‐1/2‐inch dial or larger. 

Calibration records for gauges used for testing shall be submitted to 

the Contractor. Gauges used for testing shall be calibrated once per 

year. Calibration records to be included in the Operational & 

Maintenance manual submitted to the owner / representative. 

One pressure gauge shall be installed for each testing system.  Gauges 

used for testing shall be installed as close as possible to the low point 

of the piping system. 

When starting the filling of lines to be hydrostatically tested, all vents 

and other connections that can serve as vents shall be open during 

filling so that all air is vented prior to applying test pressure to a 

system. 

If the maximum operating conditions of piping attached to a vessel 

are the same as those of the vessel, then the piping and the vessel 

may be tested together.  However, if the vessel has different 

maximum operating conditions, then it must be isolated and tested 

separately. 

Valves shall be tested at the same time that the adjacent pipeline is 

tested.  Joints shall show no visible leakage under test.  Repair joints 

that show signs of leakage prior to final acceptance.  If there are any 

special parts of control systems or operators that might be damaged 

by the pipeline test, they shall be properly protected.  The contractor 

shall repair or replace, to the satisfaction of the owner / 

representative, any valve damaged by the testing. 

Valves shall not be used as blanking devices for the hydrostatic test. 

Examination for leakage shall be made at all joints and connections.  

The piping system shall show no visual evidence of weeping or 

leaking.  Any visible leakage shall be corrected at the Subcontractor’s 

sole expense. 

If the pressure falls after the pressurizing system is shut off, the 

source of pressure loss must be determined and corrected. 

Annex‐A178  

Pressure drop in most piping leak tests shall be zero, after correction 

for temperature variation allowance, unless specified otherwise.

F.18.4. TestingMedia:Clean, fresh city water shall be used for hydrostatic testing. 

After hydrostatic testing, all water shall be drained immediately.  

Authorization is required prior to discharging water containing oils or 

chemicals being drained to the public waste system.  Coordinate with 

owner / representative before any discharge to the public waste 

system.  Care shall be taken not to pull a vacuum during draining by 

opening all vents. 

F.18.5. TestRepairs:Materials such as gaskets, bolting, etc., damaged during tests and 

flushing shall be replaced. 

New gaskets shall be used each time a flanged joint is made up. 

Any welded joint that is defective shall be repaired in accordance 

with the applicable requirements.  As mentioned, two joints, adjacent 

to the failed joint, shall be examined. Repaired components shall be 

reexamined by the original method to determine freedom from 

defects and all repaired joints shall be retested.  Costs for such repair 

shall be the responsibility of the contractor. 

F.18.6. TestRecords:Records shall be made by the Subcontractor for each piping installation.  

These records shall include, at a minimum, the following items: 

Date of test, Description and identification of piping tested, Test fluid, 

Test pressure, Test duration, Remarks, to include such items as:  Leaks 

(type, location), Repairs made on leaks. Signature and date of persons 

performing and witnessing the test at start and at completion.  

Witnessing shall be by Contractor or owner / representative. 

Certification by Contractor and reviewed by the Contractor/QAR. 

 

 

 

 

 

Annex‐A179  

F.19. VALVES

F.19.1. GeneralAll valves shall be designed for packing under pressure when fully open. 

Shut‐off valves shall be installed on both sides of all equipment, and on all branches from main risers. 

Balancing valves shall be installed on the outlets of air coolers, cooling / heating coils & on all branches from main risers. 

Check valves in horizontal position shall be 15 degree swing check valves. Check valves shall be of the low pressure drop type. 

All valves shall be of 200 psi non‐ shock pressure rating. 

All gate and globe valves shall be of type that can be repacked under pressure. 

Threaded valves shall be supplied with taper pipe thread. 

All valves to be of the same manufacturer as existing – Rephel, Kochav, KSB or equal.   

F.19.2. GateValvesGate valve size 2 " and smaller shall be screwed, bronze body and trim, solid wedge disk, non‐rising stem, screwed bonnet. 

Gate valves size 2.5" and larger shall be flanged, cast iron body, bronze trim, solid wedge disk, non‐ rising stem, flanged bonnet. 

F.19.3. GlobeValvesGlobe valves size 2 " and smaller shall be screwed, bronze body and trim, integral seat, revolving disk, inside screw, rising stem, screwed bonnet. 

Globe valves size 2.5" and larger shall be flanged, cast iron body, bronze trim, renewable seat and disk, outside screw, rising stem , flanged bonnet. 

 

F.19.4. GlobeValvesWithVariableOrificeValves size 2" and smaller shall be screwed, gunmetal body and bonnet, valves 2.5" and larger shall be flanged, cast iron body and bonnet, brass stem. 

F.19.5. CheckValvesCheck valves size 2" and smaller shall be screwed, bronze body and trim, spring horizontal lift pattern, renewable composition disk, screwed cap. Check valves size 2.5" and larger shall be flanged, cast iron body, bronze trim, swing pattern, renewable seat, bolted cap. 

 

 

Annex‐A180  

F.19.6. AutomaticAirVentsWherever possible, all water pipe work system should have open venting at all high points in the system.  Where this is not possible, an automatic air vent 1/2 "  shall be fitted and connected to nearest drain . Automatic air vents shall be fitted with a suitably sized gate valve. 

F.19.7. ReliefValvesRelief valves shall be of the spring loaded , angle type, with screwed ends , male bottom inlet , female side outlet, bronze body and trim , suitable for working pressure of  not less  than 10 bars. The Relief valves shall be tested at the factory and the pressure setting shall be clearly stamped on the valve nameplate. 

F.19.8. ButterflyValvesButterfly valves shall be suitable for insulation, flanged ,cast iron body , bronze disc ,stainless steel shaft, and  shall be supplied with  reduction gear. 

F.19.9. StrainersApproved "self ‐ cleaning "'strainers shall be provided in the suction line of each pump and at the inlet connections to feeders and make ‐ up connections to coils. The intention is to protect, by strainers, all apparatus of an automatic character , whose proper functioning would be interfered by  debris in the piping system. 

All strainers shall be suitable for pressures as stipulated for the system and shall be inspected and tested during the system's pressure test procedures. 

Strainer basket screens shall be stainless steel and shall be of ample strength to prevent collapsing the basket under shock loading. 

Each water strainer shall be provided with an approved shut‐off valves connected to the dirt blow ‐ out connection and capped. 

F.19.10. FlexibleConnectionsPumps and chillers shall be connected to the chilled water pipes through flexible connections, as manufactured by Mason, Power, Bell & Gosselt or equal. 

F.19.11. ThreewaycontrolvalvesThree way valves shall be supplied and installed as indicated in the schematic flow diagram. 

The three way valves shall be proportional. Valves shall be Danfoss ,  Simense or equal. 

 

 

Annex‐A181  

F.20. CentrifugaloraxialFans

F.20.1. General:Forward curved centrifugal fans having sizes and capacities or axial fans as 

indicated on the schedule. Material accessories and arrangement as indicated 

on the drawings. Manufacturer as Nicotra, Comfri or greenheck or equal. 

F.20.2. Ratings:Fans shall be rated and tested in accordance with ASHRAE Standard 51(AMCA 

Certified Ratings Seal). Ventilation rates as indicated on the drawings are 

minimum values and should be calculated by contractor. Internal conditions 

not to exceed 40C at normal operation.  Calculations shall be supplied and 

approved by owner. 

F.20.3. FanUnits:Provide factory‐assembled and tested fan units consisting of housing, wheel, 

fan shaft, filters box and support structure. Clean and prime paint sheet metal 

parts prior to final assembly .Apply final coat of enamel to exterior surface 

after assembly. 

F.20.4. Housings:Provide curved housings, lock seam construction. 

F.20.5. Wheels(forcent.Fans):Constructed from hot dip galvanized steel.  Provide inclined plate‐type blades 

constructed of high tensile steel. True and dynamically balance wheels after 

assembly. 

F.20.6. Motors:Motors shall be 400V, 50Hz, 3 phase, hot‐rolled, shaft steel bearings heavy 

duty selected for minimum average life of 100,000 hours. 

 

 

 

 

 

 

Annex‐A182  

F.21. DuctWork

F.21.1. SheetMetalDuctwork1. All sheet metal ductwork shown on the drawings , specified or required for the , 

ventilating systems, shall be fabricated from 0.8 mm, with not less than 10 

microns, mild steel sheets , of soft bending quality suitable for air conditioning 

works . 

2. Galvanized sheet steel shall comply with ASTM A527  lock forming  quality with 

ASTM A525, G90 zinc coating mill phosphatized for exposed locations.

3. Ductwork shall be fabricated and installed according to SMACNA and ASHRAE 

standard.  

4. All bracing and  reinforcement angles shall be made of black steel, properly 

cleaned from rust and painted with 2 prime coats of antirust red paint for 

installation . Angles shall be carried around all four sides of ducts. 

5. Reinforcing angles shall be fixed to the duct by means of bolted joints made 

with cadmium plated or sheradized mild steel hexagonal nuts with flat steel 

washers to the following sizes:

1" angle: 1/4" diameter bolts @ 10cm  centers 

1/2" angle: 5/16" diameter bolts @ 10 cm centers

6. All slip joints shall be made in the direction of flow 

7. All elbows shall have a center line radius equal to 1.5 times the width of the 

duct.

8. Ductwork shall be constructed so that when installed it shall be made airtight 

by tightly approved sealing  after fabrication and free from movement , sagging 

or drumming under all operating conditions.

9. Where ducts pass through interior partition ceiling and walls provide galvanized 

frame and conceal space between construction duct plus insulation with sheet 

metal flanges of same duct gauge. overlap opening on 4 sides by fire proof 

sealants, if partition is fire rated. 

10. Provide heavy gauge wire mesh on the open end of return or supply duct.

11. Tender drawings shall be adhered to as closely as possible. However, for 

coordination purposes with other trades, runs and sizes of ductwork may vary 

by the engineer, at no extra cost to the owner.  

Annex‐A183  

12. All duct elbows having an inside radius smaller than the width of the elbow shall 

be equipped with approved vanes tightly riveted to the duct. 

13. Approved duct ‐ turns shall be installed in all cases where 90 square elbows are 

used and short take ‐ off are used large ducts . Guide splitter vanes shall not be 

spaced more than 6" apart. 

 

F.21.2. DuctHangersSupports1. Duct work shall be supported by means of mild steel angle iron sections 

with spacing between supports not exceeding 2.5 meters and projecting 2" 

either side to allow for proper insulation. The hanger rods ( or alternatively 

hanger flat iron bars) shall be suspended from the structure  by means of 

Hexagonal headed bolts and double nuts with flat steel washers. 

2. All supports and angles shall be painted with one coat of red oxide paint 

prior to installation and a further coat of gray paint on exposed metal parts 

after installation. 

F.21.3. FlexibleDuctworkFlexible ductwork shall be glass ‐flex type ‐use only minimum length 

required  not to exceed 2 meters to make connection .Where horizontal 

support is required use 3/4" wide metal hanger. 

F.21.4. FlexibleConnectionsFlameproof flexible connections shall be fitted on all suction and discharge 

connections of fans units, for preventing the transmission of vibration 

through the ducts. 

Flexible connections shall be factory fabricated from chemically 

impregnated canvas. 

Connections shall fit closely and be secured in an airtight fashion for 

connections between ductwork fans and apparatus. 

The unclamped section of the flexible connection between equipment and   

ductwork shall not be less than 0.15 m in length. Flexible connections shall 

not be painted. 

 

 

 

Annex‐A184  

F.22. DuctAccessories

F.22.1. GeneralAir outlets grilles and air inlets grilles / diffusers shall be industrial grade of 

an approved manufacturer, type and model shall be provided with sizes as 

indicated on the drawings. They shall all be of anodized aluminum 

construction with sponge rubber gaskets behind the frames and nylon 

bushings at the blades connection to the frame.  

A shop drawing / sample must be approved by the engineer prior to 

ordering. 

F.22.2. Grilles&RegistersSupply air registers shall have individually adjustable horizontal front blades, 

vertical rear blades and shall be equipped with opposed blade dampers for air 

volume control. 

Return air grilles shall be in general with adjustable blades of the same shape 

and construction as the supply air register but without dampers. 

Exhaust air grilles shall be of the same type and pattern as the return air grilles. 

Exhaust air registers shall be of the same type and pattern as 

The exhaust grilles but equipped with volume dampers. 

Outside air louvers shall be equipped with bird screens. 

F.22.3. VolumeDampers(V.D) A substantially constructed manual volume damper of the single or multiple 

blade type shall be fitted, where shown on the drawings, required for balancing 

purposes. 

Damper shall be constructed according to SMACNA. 

   

Annex‐A185  

F.22.4. InsulationDuctwork Insulation: 

All ductwork   in the occupied areas shall be insulated on the outside with 

Flexible Fiber glass 32 kg/m³ UL label with Factory applied Flame retardant 

aluminum Foil vapor barrier laminated with Kraft paper. 

The insulation shall have an average Thermal conductivity not to exceed 0.4 

W/mcº in at mean temperature of 24C°.  

Insulation shall be 25‐ 40 mm thick in corridor and outdoors. 

Insulation shall be fixed to the duct with approved adhesive‐The adhesive 

shall cover the entire surface of the metal. 

Insulation shall be held in place with galvanized straps of not more than 

1.5m centers. For sealing insulation joints 3 inch wide tape of same facing 

should be applied. 

F.23. MetersandGages

F.23.1. TemperatureGages Glass thermometers: 

- The Contractor shall provide glass thermometers with ranges suitable 

for service indicated.

- Case die cast aluminum finished in baked epoxy enamel, glass front, 

spring secured, 225 mm long. 

- Adjustable Joint: Die cast aluminum, finished to match 

case,180°adjustment in vertical plane,360° adjustment in horizontal 

plane, with locking device. 

- Tub and Capillary : Mercury filled, magnifying lens 1% scale 

- Range accuracy, shock mounted. 

- Scale: stain faced, non‐reflective aluminum, permanently etched 

markings. 

- Stem: copper‐plated steel or brass, for separable socket, length to suit 

installation. 

Direct Mount Dial Thermometers. 

- Provide and install direct mount dial thermometer with ranges, designed 

and constructed for use in service indicated. 

Annex‐A186  

- Type: vapor tension, universal angle. 

- Thermal Bulb: copper with phosphor bronze bourdon pressure tube, on 

scale division accuracy. 

- Stem copper plated steel, or brass for separable socket, length to suit 

installation. 

- Range: conform to the following: ‐10±40ºc.. 

 

F.23.2. PressureGagesandFittings: - Provide and install pressure gages of materials capacities, and ranges, 

designed and constructed for use in service indicated. 

- Type: General use, 1% accuracy, ANSI/ASME B 40.1 grade A, phosphor 

bronze bourdon type, bottom connection. 

- Case: Drawn steel or brass, glass lens, 115mm diameter. 

- Connector: Brass with 6 mm male NPT. Scale: white coated aluminum, 

with permanently etched markings. 

- Range: conform to the following: water 0‐ 700 kPa. 

Pressure Gage Cocks: 

Provide and install pressure gage cocks between pressure gage and gage 

tees on piping systems. Construct gage cock of brass with 6mm female 

NPT on each end, and "T" handle brass plug. 

Snubber :  

6mm brass bushing with corrosion resistant porous metal disc, through 

which pressure fluid is filtered.  Select disc material for fluid served and 

pressure rating. 

Locations:  

Install at suction and discharge of each pump and elsewhere as indicated. 

 

Annex‐A187  

G. ChapterG:AbsorptionLiquidChillers(Optional)

G.1. General:Co‐Generation operation will be implemented in the event that natural gas 

supply to the energy center will be available. During this phase, the contractor 

will, supplied, installed, and connected absorption chiller to the – Generator 

exhaust, cooling water system and condensing water system. The absorption 

chiller will operate in‐conjunction with the generator producing chilled water 

as a Co‐Generating System‐ utilizing water as refrigerant and utilizing li‐br as 

absorber, similar to absorption chillers manufactured by: Broad, Thermax, 

York or equal.  

The absorption chiller Unit shall be designed, manufactured and tested in a 

facility with a quality assurance certification ISO 9001.  

Unit to be witness tested at the factory in the presence of the owner, his 

representative and/or the Engineer  

The absorption chiller manufacturer shall have a local representative to 

commission and service the unit. The unit shall include automatic anti‐

crystallization, and auto de‐crystallization technology preventing chiller 

malfunctioning due to LiBr solution crystallization. 

G.2. ScopeofworkThe list below is the major items, but not limited to, the equipment and works 

required to complete and operating absorption chiller system: 

1. Full set of technical documentation required for the 

system installation,(as detailed below, but not limited 

to): 

System description 

Structural engineering data and foundation 

guidance drawings. 

P&ID 

PFD (Process Flow Diagram) including process data 

(flow rates, pressure drops, inlet and outlet 

temperatures of powering exhaust gas, chilled 

water and cooling water). 

Absorption chiller performance curves (COP versus 

load and cooling water temperature and flow rate)

   

Mechanical Engineering data required for the 

piping design. 

Utilities requirements (quality and quantity). 

Annex‐A188  

Engineering data required for the unit electrical 

connection. 

Engineering data required for the integration of 

the unit controls within the power plant control 

system. 

Full set of Operational and Maintenance 

documentation. 

Maintenance costs 

2. Absorption chiller with cooling capacity of  1300‐1500TR 

3. Cooling tower 

4. Chilled water pumps 

5. Condenser water pumps  

6. Auxiliary pumps 

7. Connecting the Absorption chiller to the generator 

exhaust system 

8. Complete water Piping system include all the 

accessories and controls devices that required  for 

connecting the absorption chiller to  the energy center 

cooling and condensing water system 

9. Connectivity/interface with the main SCADA   

10. Connectivity to the electrical system 

11. First charge of the working fluid 

12. Spare parts for 5 year operation 

13. Supervision during installation 

14. Commissioning start‐up and performance testing 

15. Maintenance / service for the first 2+3 year period. 

Annex‐A189  

G.3. Processdata: Combustion air flow rate:           TBD by generator 

Exhaust gas side allowable pressure drop:      TBD by generator 

Ambient air design temperature:         See chapter. 

Chilled water supply temperature:        5ºC 

Chilled water return temperature:        11.1ºC 

Gas generator exhaust temperature:         TBD not less than 350ºC 

GT exhaust gas flow rate required for the absorption chiller:  TBD by vendor 

Cooling water supply temperature:         32 ºC 

Cooling water return temperature:         37 ºC 

Cooling water flow rate:           TBD by vendor (EPC) 

Calculated cooling duty (Min):                          1,300 USTR (to be verified by vendor) 

Annual working hours:           Approx. 4000‐ 8,000 Hrs /Yr.  Hours   

Electrical power:             400V (+/‐ 10%) / 50 Hz/ 3 ph  

Absorption solution:            Li‐Br 

Pressure drop (chilled water and cooling water):    not to exceed 5 mWG 

Min COP              1.4 

Stepless modulation:     design to operate optimally from 10 – 100% load conditions.  

System pressure test (water side)        16atm. 

Fouling Factor:                                                             0.00025 hr.°F.ft2/BTU 

                                                            0.044 m2.K/kW 

 

 

Annex‐A190  

G.4. SiteconditionsSee capter‐A 

G.5. StructureandcasingThe unit shall be constructed of steel .The structure shall be designed for easy internal access to all the components of the Chiller. Unit will be installed in industrial polluted area. All parts to be protected of external and internal condition by proper materials. Unit to include all needed purge systems.  

Unit to be insulated (both hot and cold sides). 

Vacuum seal Isolation valves to be installed on vacuum pumps. 

 

G.6. Electricplant‐ControlsandsystemmanagementChiller and system switchboards and electric installation shall comply with all relevant   local codes. Contractor will design and supply full electric plant and control for all pumps, fans, cooling tower, chiller etc. electric and control plant will be similar to existing electric chillers. 

Switchboard to include at least the following: chiller SB including condensing pumps, chilled water pumps SB,  cooling tower SB, ventilation and smoke exhaust SB for complete project. 

All pump's motors to be Variable Speed Drive (VSD) including harmonic filters. 

Control and management functions are assigned to an electronic board (PLC microprocessor electronic card and a terminal). The chiller controller shall perform the following: 

Control evaporator supply water temperature; 

Control Solution and vacuum pumps; 

Control Refrigerant level  

Display and monitor supply and return chilled water temperatures; 

Display alarm messages, including: 

Condensation high temperature alarm 

Evaporator CHW supply water temp. (Freezing alarm) Online concentration measurement control and alarm which is to be 

displayed continuously on the control panel. 

Alarm for breakdown of compressor, fans, and/or pumps 

Alarm for insufficient water flow through the evaporator 

Condenser Supply and Return high water temperatures 

Working hours of unit with over run alarm for the number of hours pre‐set for maintenance 

Viewing alarm history; Serial interface: 

Modbus RTU ‐ interface 

Network remote connection  

Free contacts for a general alarms and operation;  to a remote location. 

All electric panels to include fans operated by thermostat for ventilation. 

Annex‐A191  

Unit to include multi stage level sensing electrodes located in High temperature  generator (HTG), Absorber and Evaporator . 

An automatic purging system should be included with the unit. 

The unit shall be equipped with online concentration measurement and control which is to be displayed continuously on the control panel. 

 

G.7. TestingThe chiller should be tested at nominal conditions in the factory (FAT), at full load and at partial loads, for a sufficient amount of time to evaluate the correct functioning of all its components. The tests and checks should specifically cover: 

Verifying no refrigerant or absorber leaks. 

Verifying the correct assembly of all components. ; 

Electrical safety tests, as prescribed by the electrical safety codes and standards. 

Verifying the controls are operating correctly with working parameters correctly set; 

Verifying the temperature sensors and the pressure transducers are calibrated, complete with calibration certificates. 

Setting the nominal water flow through the evaporator and operating each cooling circuit in a controlled environment to verify and monitor the following: Evaporating and condensing water temperatures, pressure drops through evaporator and condenser, part‐load and full load cooling capacity, electrical power consumption and chiller's efficiency. 

SAT (same as FAT) and commissioning will be performed and a report will be delivered to client. 

 

G.8. WarrantySee Chapter A section A.25  

 

G.9. Maintenance,ServiceandlifespanAll parts should be design for easy maintenance. Hatched area on the drawings, around the chiller provides reserved cleared area for cleaning of all fire tubes and soot passes. The unit shall be designed for a life span of at least 20 years.

 

 

   

Annex‐A192  

G.10. CentrifugalPumps

G.10.1. General: The Contractor shall furnish and install as shown on the drawings and as 

described in these specifications. Single stage, end suction horizontal 

centrifugal pumps each of the size and capacity shown in the drawings. 

Main chilled water pump (Flow equal to chiller capacity and defined DT). 

Min pressure drop not less than 15 meters.  

Main condenser water pump (Flow equal to chiller requirement capacity 

and defined DT).Min pressure drop no less than 15 meters. 

High stage hot water pump (to be defined by generator requirement and 

available heat flow). 

G.10.2. DesignCriteria Select pump impeller diameters not to exceed 85 percent of maximum 

casing capacity. 

Select motors for non‐overloading operation at all points on the pump's 

curves. 

Select pumps at or, to the left of, the point of maximum efficiency, on the 

pump's curve. 

Select pumps for open systems with an NPSH required equal to or less 

than the NPSH available at the minimum suction conditions while 

maintaining full‐rated capacity. 

Oil lubrication is preferred over greased units. 

Burgmann Mechanical seals and REXNORD or John Crane couplings, or 

equal, shall be provided for all pumps.  

All pumps shall be provided with inertia base and spring isolators.  

Balance:  All impellers shall be two‐planes dynamically balanced. 

 

G.10.3. SubmittalsProvide the following information in addition to the standard 

requirements: 

Performance curves, including:  

o Capacity versus discharge head,  

o Driver horsepower,  

o NPSH, Efficiency,  

o Impeller size versus maximum,  

o Inlet and outlet sizes and types,  

o Base‐plate mounting details,  

Annex‐A193  

o Mechanical seal, couplings and bearings, makes and models. 

o Plan and elevation drawings 

o Motor specifications including:  

o Manufacturer and model,  

o Enclosure,  

o Bearings used; type and life expected, Service factor,  

o Winding insulation class,  

o Speed,  

o Shaft size.  

 

G.10.4. Pump'sDescriptionandMaterials: Impeller shall be bronze, cast in one piece, enclosed type, statically and 

dynamically balanced and keyed to the shaft and secured with a suitable 

locknut. 

Shaft shall be of high‐ grade stainless steel. 

Mechanical seal: All pumps shall be provided with mechanical seals of 

flexible bellows type and shall withstand specified pump design 

pressure. Springs shall be of stainless steel and metal parts of seal head 

shall be non‐rusting material. 

Bearings shall be heavy duty ball bearings sealed for life, sized to 

transmit highest loads and pre‐packed with high temperature grease. 

Pump working pressure shall be 150 psi at the design water 

temperature. 

Impeller diameter shall be selected so that the design capacity of each 

pump shall not exceed 80 % of the capacity obtainable with maximum 

impeller diameter at the design speed for that model. 

A replaceable shaft sleeve shall be furnished to cover the wet area of 

the shaft under the seal or packing. 

The pump and motor shall be mounted on a common base plate of 

heavy structural steel design with securely welded cross members and 

open grouting area. 

A flexible coupler, capable of absorbing torsion and vibration. Coupler 

shall be installed between the pump and motor, and shall be equipped 

with a suitable coupling guard as required. 

Annex‐A194  

Motor sizes shall be selected completely non overloading over the entire 

performance range of the particular pump. Motor shall be TEFC or drip ‐ 

proof squirrel ‐ cage type , with class F insulation. 

Pump casing shall be manufactured from close ‐ grained cast iron 

machined to fine limits . 

The pump shall be factory, thoroughly cleaned, and painted with one 

coat of machinery enamel prior to shipment. A set of installation 

instructions shall be included.    

G.10.5. Installation Install pumps in accordance with the manufacturer's written installation 

instructions and as shown on the Drawings. 

Support interconnecting piping independently to prevent stresses from 

being transmitted to casings. 

Lubricate in accordance with manufacturer's instructions before 

operation. 

 

G.10.6. Startup Verify that piping systems have been flushed, cleaned, and filled. 

Prime pumps, vent all air from the casings, and verify that rotations are 

correct.  To avoid damage to mechanical seals, never start or run the 

pumps in dry condition. 

After several days of operation, remove disposable startup strainers. 

Perform field mechanical balancing if necessary to meet specified 

vibration tolerances. 

 

 

   

Annex‐A195  

G.11. COOLINGTOWER 

G.11.1. GeneralThe scope of supply includes the design, fabrication, testing, delivery and 

installation of a complete mechanical induced draft, multi‐cell counter‐flow 

type cooling tower including all necessary accessories for proper operation 

and maintenance. The cooling tower to be similar to the existing cells. 

 The cooling tower will be made of pultruded fiberglass reinforced polyester 

(FRP) structure connected with 316 SS accessories. The structure will be 

positioned over reinforced cement concrete (RCC) basin. The cooling tower 

will be based on two cells and should include all  accessories.  

Cooling tower shall be rated tested according to CTI (Cooling Technology 

Institute USA) or equal west European standards. 

Fans shall be rated, tested, in accordance with ASHRAE (AMCA) or equal west 

European standards. 

All instrumentation and controls shall be of approved industrial quality. Other 

design criteria are detailed herewith. 

G.11.2. StructureThe cooling tower manufacturer is responsible to provide all necessary data 

required for a structural engineer to check the design the tower foundation. 

Data shall include weights and arrangements of equipment, access 

requirements for installation and maintenance, and other pertinent 

construction details. 

These arrangements shall suit the requirements as underlined here and 

shown on the drawings. Only after structural engineer's approval of the 

cooling tower's structural details, and the air conditioning contractor's 

approval, will the CT vendor start manufacturing the CT.  

The FRP structure (support beams and columns) shall be made of composite 

continuous fiberglass pultruded sections. The materials to be used are 

Isophtalic Polyester and chopped glass strand E type complying with CTI 

STD‐37 (88) Grade 1. The pultruded sections shall conform to the ASTM E84D 

with a flame spread rating of not less than 25. 

The casing of the tower shall be made of FRP panels;  gel coated on both  

sides, UV protected and fire retardant, UL/FM approved (or, European equal). 

Fan stack will be made of three layers of hand fabricated FRP (a minimum of 

450gr per square meter). The resin would be a isophtalic. Carrier of the gear 

and motor will be made of 316 SS.  All bolts, nuts, washers, fasteners and bird 

Annex‐A196  

screens will be made of 316 SS. The tower will be installed over a concrete 

cement basin which will be provided by others, based on the supplier scale 

drawings.  Static and dynamic loads for each unit, for purposes of supporting 

structure design, shall be supplied. The air conditioning sub‐contractor shall 

provide the civil contractor all required cooling tower's piping sleeves, so they 

can be imbedded in the concrete during construction. The air conditioning 

contractor shall coordinate and supervise the civil contractor with the exact 

location and installation of these sleeves. Piping connections at the tower 

including flanges shall be of 316 SS.     

Furnish and install an external staircase and maintenance platforms attached 

to the fiberglass tower structure for external access to the cooling tower fan 

deck. Staircases and handrails shall be made of FRP or 316 SS and shall meet 

all safety code requirements. 

Provide a maintenance platform that will enable easy access to the gear box 

made of 316 SS or FRP, and an inspection hatch made of FRP in the drift 

eliminator's level.  

G.11.3. FillThe fill to be used should be made by Brent Wood, or equal, PVC film fill, cross 

fluted with 19mm flute size opening. The materials of the fill should comply 

with. CTI‐136 standard. The PVC fill sheets shall conform to the ASTM E84D 

with a flame spread rating of not less than 25.  The fill packs should be 

positioned over support beams made of pultruded FRP.  The PVC fill pack shall 

be bottom supported by FRP support lintels on about 500 mm maximum 

center‐to‐center spacing. 

G.11.4. DriftEliminatorsThe drift eliminators should be of cellular type designed to remove entrained 

water droplets from the leaving air stream at minimum pressure losses 

ensuring a drift loss less than 0.005%, per CTI standard 140.  The PVC sheets 

shall conform to the ASTM E84D with a flame spread rating of not less than 

25. 

G.11.5. SpeedReducersThe speed reducer gear should be spiral bevel, double‐reduction type and 

meet CTI STD‐111 requirements. Design features and ratings of the speed 

reducer should be in accordance with the minimum requirements of American 

Gear Manufacturers Association (AGMA) standards but not less than 2. The 

speed reducer should be provided with an integral sight glass to check the oil 

level and a designated oil level indicator, installed outside of the airstream. 

The air breather should be located outside of the air stream in order to 

Annex‐A197  

prevent water infiltration. The speed reducer should be fitted with a drive 

shaft made of composite materials.  

The cooling tower manufacturer shall furnish oil reservoir and for speed 

reducer unit lubrication, designed to provide positive lubrication at all fan 

operating speeds. Oil and vent lines shall be 316 stainless steel. 

 In order to shorten installation time on site and reduce risk, the speed 

reducer and the motor should be installed on a common metal chassis which 

should be delivered to the job site as a single unit.  

G.11.6. FanThe complete fan assembly shall be designated to give maximum fan 

efficiency and long life when handling saturated air at high velocities.  

The blades of the fan should be made of anti‐corrosive cast aluminum or FRP. 

Each blade of the fan should be air foiled, variable pitch. Fans shall be 

balanced after production, and fans’ blades angles will be field balanced after 

production. The noise level one meter from the tower should not be more 

than 80 dB(A). 

G.11.7. LouversThe cooling tower should be equipped with anti‐light louvers, installed in 

designated FRP or stainless steel frames. The louvers should prevent water 

from getting out of the cooling tower and serve as a filter to prevent  air born 

objects (e.g. birds or plastic bags) from getting into the tower.  

G.11.8. MotorThe motor should be designed and built for arduous environments, suitable 

for S1 operation (continuous operation under rated load), IE3. Standard levels 

of enclosure protection for the motor should be IP66 for both motor and 

terminal box. All castings and steel parts should be primed with a 2‐pack 

epoxy coating.  

The motor should be fitted with one set (3) of PTC thermistors, selected for a 

tripping temperature of 145°C. Motors shall be located out of air stream and 

shall be connected to the gearbox by a drive shaft as detailed above.   

Motors shall be close‐coupled to the gearbox by means of a flexible coupling. 

Design tower so shaft shall be 316 SS full floating type with flexible couplings 

at both ends, made by Amarilo, or equal.  

G.11.9. DistributionSystemThe distribution system will be based on 2" polypropylene nozzles.  The 

nozzles shall be accessible for cleaning and maintenance. The pressure loss of 

Annex‐A198  

the nozzles would be less than 0.2 Bar at 50 GPM. The distribution system will 

ensure that water distribution is even and efficient. The distribution system 

will support a scenario in which water flow is increased by or decreased by 

30%. 

G.11.10. VibrationSensorThe supplier will equip each and every motor with a protective vibration 

sensor. The vibration sensor/transmitter will provide 4‐20 mA analog output 

signal to the owners HMI system. The 4‐20 mA current output should be 

proportional to the overall vibration of the equipment or machinery they are 

monitoring. 

G.11.11. FanDeckFan deck shall be constructed of fiberglass, forming a rigid base for mounting 

the fan, speed reducer, coupling/drive shaft and motor. An access opening 

with double wall fiberglass or ABS access into the cooling tower cell. Roof 

deck drains shall additionally be furnished and installed by the cooling tower 

manufacturer or the roof deck shall be designed to slope and drain without 

the need of roof drains. Provide service crane "Davit" (lifting beam) to allow 

replacement of motor or drive as necessary  

G.11.12. TowerAccessThe cooling tower manufacturer shall provide access openings to the roof 

deck, deck handrails, and an access ladder within the tower cell to access 

internal components. All access platforms, ladders and hand rails shall be 

made of RFP or 316 SS, pending owner's representative approval 

G.11.13. DocumentationThe supplier shall provide all drawings in 2D (AutoCAD) and 3D (Solid Works). 

The supplier shall provide thermal rating of the proposed solution including 

performance curves according to CTI’s ATC‐105 standard (which will be used 

as testing procedure for performance of the cooling tower). 

 

Manufacturer shall certify in print that the performance of the cooling towers 

shall meet all specified contract requirements, stating air wet bulb 

temperature, entering and leaving water temperatures, water flow rate, fan 

horsepower, motor horsepower, and pump head at tower inlet nozzle (Pumps 

and external piping are provided by others). 

 

Should the field performance test prove the tower’s performance is deficient, 

the cooling tower manufacturer shall bear the costs necessary to correct the 

Annex‐A199  

deficiencies within one week, or, a time period agreed with the owner / 

representative. In such case the tower shall be re‐tested and certified after all 

deficiencies are corrected. 

The dimensions of the individual tower cell, and the over‐all tower 

arrangement, shall be as indicated on the Drawings.  

The manufacturers shall take these arrangements and dimensions into 

consideration for the various designs required, including; water cooling 

capacity, performance, fan air handling capacity, and the motor brake 

horsepower requirements.  

The towers shall be arranged so that each of the tower's cells can be operated 

independently of the adjacent cell, and can be repaired, maintained, and 

cleaned while the adjacent cell remains in service.  

Cooling towers shall be furnished complete as shown on the data sheets and 

shall  

include all necessary bolts, nuts, gaskets, all internal piping and accessories, 

and all  

water distribution headers. All bolts, nuts, gaskets, hold – down lugs, and 

internals shall be compatible   with the cooling tower water. 

   

Annex‐A200  

G.11.14. Performance 

No  Description  requirement

1  Heat Rejection  2350 Tons Heat Rejection per Cell (0ne required) 

2  Fluid  Cooling water in open circuit with city water make‐up 

3  Temperatures  Design Wet Bulb:  26.5°C

4  Water out  30°C

5  Water in  35°C

6  Water flow  1400 m3/h 

7  Fan type  Multi‐blade axial (propeller), FRP construction 

8  Diameter  No. of blades: (indicate)

9  Fan motor  Power: 125HP

9.1  Fan motor  TEFC to suit operation with Variable Frequency Drive (VFD) 

9.2  Fan motor  Electrical data       400 Volt ;3 phase ; 50 Hz 

10  Control:    230 Volt ; 50 Hz

11  Fan drive  Gear and shaft, with motor located out of air‐stream on cooling tower deck. 

12  Bearings  Gear calculated life‐time: 100,000 hours. 

13  Dimensions:  See drawings

 

 

 

 

 

Annex‐A201  

H. ChapterH:BasisofDesign–Environmentalsection

H.1. General      This chapter is an appendix chapter A 

H.2. Unitsofmeasurement

The metric system of units will be used as follows:  

Description  Unit Pressure  barg / bara 

Temperature  ºC 

Mass  Kg 

Mass Flow  kg/h 

Volumetric Flow  m3/h 

Molecular Weight  kg/kmol 

Density  kg/m3 

Specific Heat  kJ/kg ºC 

Thermal Conductivity  W/m ºC 

Heat Transfer Coefficient  W/m2 ºC 

Heat Flow  MW 

Enthalpy  kJ/kg 

Power  MW, kW or W 

Length  mm or m 

Viscosity  Cp 

Surface Tension  Dynes/cm 

Time  s or h 

Current  A 

Voltage  V or kV 

Force  N 

Energy  J 

Volume  m3 

Area  m2 

 

Annex‐A202  

H.3. SITEINFORMATION

H.3.1. ClimaticConditions

H.3.2. TemperatureTemperature (C0) 

XII XI X IX VIII VII VI V IV III II I Month 

20.4 24.6 29.2 31.0 32.4 31.6 30.1 28.0 24.2 21.0 19.1 18.5 Average 

daily 

maximum 

14.6 17.9 21.9 24.6 26.0 25.2 23.2 20.3 17.0 14.3 13.0 12.7 Daily 

average 

8.7 11.2 14.6 18.1 19.7 18.7 16.2 12.6 9.7 7.6 6.9 6.9 Average 

daily 

minimum 

11.7 13.4 14.6 12.9 12.7 12.9 13.9 15.4 14.5 13.4 12.2 11.6 Average 

daily range 

28.0 32.2 34.6 34.5 35.2 35.3 37.6 37.2 35.1 30.6 26.5 25.6 Average 

monthly 

max. 

36.7 38.6 43.3 42.2 38.6 39.1 44.4 45.4 43.3 37.7 32.7 32.2 Absolute 

maximum 

3.1 4.5 9.8 13.7 15.8 15.4 12.2 7.8 3.8 2.0 1.6 1.1 Average 

monthly 

min. 

0.7‐  0.6 6.7 9.5 14.6 14.0 9.5 5.4 0.5 0.5‐  2.2‐  2.5‐  Absolute 

minimum 

 

    DESIGN (recommended) temperature:    20 oC     Absolute MAXIMUM design temperature:  45 oC     Absolute MINIMUM design temperature:  1 oC 

H.3.3. Humidity

  RELATIVE HUMIDITY (%) XII XI X IX VIII VII VI V IV III II I Month 

70 66 62 64 66 65 63 60 66 71 74 73 Daily average 

77 

55 

79 

70 

51 

76 

64 

49 

73 

67 

52 

76 

69 

52 

76 

68 

52 

76 

64 

50 

74 

61 

46 

72 

68 

52 

78 

76 

55 

82 

80 

56 

84 

77 

55

83 

                    08 

Average       14 

                    20 

    Design (recommended) relative humidity:    66 %     Absolute MAXIMUM relative humidity:      98 %     Absolute MINIMUM relative humidity:      10 % 

Annex‐A203  

H.3.4. BarometricPressureDESIGN (recommended) barometric pressure:  1012 mbara  Absolute MAXIMUM barometric pressure:          1026 mbara Absolute MINIMUM barometric pressure:             996 mbara  

H.3.5. WindSee attached table of Wind Data and Wind Rose (4.1). MAX wind velocity:        90 km/h Prevailing wind direction for DESIGN:  From WNW and SE 

H.3.6. Rainfall

12 11 10 9 8 7 6 5 4 3 2 1 Month 

   

Annually 

130 79 16 1 ‐‐‐ ‐‐‐ ‐‐‐ 3 12 57 83 132 513 

Average annual rainfall 513 mm Daily max rainfall 144mm

H.3.7. SiteConditions

H.3.7.1. Elevations

30 m above sea level. 

H.3.7.2. Seismic

The  site  is  located  in  a  ‘moderate  risk’  earthquake  zone.  The  seismic coefficient  for  the  maximum  horizontal  ground  acceleration  is  0.1 PGA(g) [Israel Standard 413].  According  to  The  Geophysical  Institute  of  Israel Map  of  Zones  with Potentially High Ground Motion Amplification – the site  is  in a region where  soft  soil  directly  overlies  hard  basement  rocks.  Here  ground motion  amplification  increases  significantly,  due  to  the  trapping  of energy within the soil layer and the development of resonance.  

Annex‐A204  

H.3.8. ENVIRONMENTALPROTECTION

H.3.8.1. ExhaustEmissionLimits

The following values are presented in Standard Conditions. Standard  Conditions  ‐  dry  exhaust  gas  at  a  temperature  of  273  degrees Kelvin, a pressure of 101.3 kilopascal, and an excess oxygen of 5 percent for Diesel generators (comply with T.A.Luft 2002): 

 For natural gas fuel: 

NOx:  500 mg/Nm3 

SO2:   ‐‐‐ 

CO: 300 mg/Nm3 

NH3:  30 mg/Nm3 

CH2O:  60 mg/Nm3  

 For Backup fuel ‐ liquid fuel (under 300 operating hours): 

Particulates: 80 mg/Nm3 

CH2O:     60 mg/Nm3 

H.3.8.2. WasteWaterEmissionConcentration Oily effluents and Rain Water from potentially polluted areas: 

All  new  compounds  in  the  energy  center  which  could  create  runoff containing oil or chemical contamination due to spills, will be built from sealed surfaces to fuel and oil, shall be drained to an oil/fuel separator system. 

RAIN WATER (from clean Areas): See Attachment 4.2. 

Cooling  towers blowdown: Evacuated  to  the  local waste water treatment plant. 

   

Annex‐A205  

H.3.8.3. Noiselevels

 At  5 m  from  the  generator  enclosures  and  1.5m  above  the ground: 80 dB (A) 

 At 1 m from each equipment unit installed on the roof:    75 dB (A) 

At 1 m  from  the  cooling  towers and 1.5m above  the ground:   85 dB (A) 

H.3.8.4. SandandDustStormsEvents  (average) of sand and dust storms occur per year, usually  in  the winter 

and spring 

H.4. ATTACHMENTS

H.4.1. WINDDATA  

ANNUAL WIND ROSE 

 

 

WIND CLASS FREQUENCY DISTRIBUTION

Annex‐A206  

 

 

WIND FREQUENCY DISTRIBUTION

 

Total 11.1 > =  11.1 – 8.8  8.8 – 5.7  5.7 – 3.6  3.6 – 2.1  2.1 – 0.5  Wind Direction 

0.035256 0 0 0.001512 0.00773 0.015916 0.010098 11.25 – 348.75  

0.026813 0 0 0.000342 0.003337 0.011695 0.011438 33.75 – 11.25  

0.020908 0 0 0.000171 0.000827 0.00599 0.01392 56.25 – 33.75  

0.015089 0 0 0.000057 0.000913 0.003366 0.010754 78.75 – 56.25  

0.025387 0.000285 0.000143 0.002196 0.002482 0.006019 0.014262 101.25 – 78.75  

0.054196 0.000285 0.000941 0.005534 0.006275 0.017685 0.023475 123.75 – 101.25  

0.132837 0.000029 0.000086 0.001711 0.009727 0.07519 0.046095 146.25 – 123.75  

0.10959 0 0.000029 0.00271 0.025073 0.059929 0.02185 168.75 – 146.25  

0.05411 0.000029 0.000656 0.008358 0.0172 0.020851 0.007017 191.25 – 168.75  

0.043328 0.000029 0.000856 0.007074 0.013207 0.015945 0.006218 213.75 – 191.25  

0.041845 0.000856 0.001683 0.007787 0.009613 0.01526 0.006646 236.25 – 213.75  

0.043984 0.000713 0.001426 0.010411 0.014205 0.012265 0.004963 258.75 – 236.25  

0.072252 0.000285 0.001426 0.019653 0.032575 0.012864 0.005448 281.25 – 258.75  

0.097153 0.000228 0.000713 0.020252 0.051401 0.018484 0.006076 303.75 – 281.25  

0.082977 0.000086 0.000114 0.01991 0.038137 0.017143 0.007587 326.25 – 303.75  

0.068857 0 0.000143 0.011809 0.025187 0.021821 0.009898 348.75 – 326.25  

0.923792 0.002824 0.008215 0.119488 0.257887 0.330424 0.205745 Total 

Annex‐A207  

H.5. MaximumMonthlyAveragesforParametersinEffluentsforUnrestrictedIrrigationandDischargetoRivers

Parameter Units Unrestricted Irrigation*

Rivers

Electric Conductivity dS/m 1.4

BOD mg/l 10 10

TSS mg/l 10 10

COD mg/l 100 70

Ammonia mg/l 10 1.5

Total nitrogen mg/l 25 10

Total phosphorus mg/l 5 1

Chloride mg/l 250 400

Fluoride mg/l 2

Sodium mg/l 150 200

Faecal coliforms Unit per 100 ml 10 200

Dissolved oxygen mg/l <0.5 <3

pH mg/l 6.5-8.5 7.0-8.5

Residual chlorine mg/l 1 0.05

Anionic detergent mg/l 2 0.5

Total oil mg/l 1

SAR (mmol/L)0.5 5

Boron mg/l 0.4

Arsenic mg/l 0.1 0.1

Mercury mg/l 0.002 0.0005

Chromium mg/l 0.1 0.05

Nickel mg/l 0.2 0.05

Selenium mg/l 0.02

Lead mg/l 0.1 0.008

Cadmium mg/l 0.01 0.005

Zinc mg/l 2 0.2

Iron mg/l 2

Copper mg/l 0.2 0.02

Manganese mg/l 0.2

   

Annex‐A208  

Parameter Units Unrestricted Irrigation*

Rivers

Aluminum mg/l 5

Molybdenum mg/l 0.01

Vanadium mg/l 0.1

Beryllium mg/l 0.1

Cobalt mg/l 0.05

Lithium mg/l 2.5

Cyanide mg/l 0.1 0.005

 

Annex‐A209  

I. ChapterI:Fuelsupplysystemtostandbydieselgenerator

I.1. General:

      This chapter is an appendix chapter C 

I.2. BackgroundThe  Israel  Airport  Authority  (hereinafter  the  “Purchaser”)  operates  an 

emergency  power  generating  installation  comprising  four  (4)    3.0 MW  diesel 

generators  at  the  Ben  Gurion  Airport  Energy  Center.    The  emergency  power 

generating  installation now  includes  two  (2) 100 m3 diesel  fuel  storage  tanks 

and  a  3 m3  day  tank  for  each  of  the  4  diesel  generator  units  complete with 

interconnecting piping, fuel transfer pumps and the associated  instrumentation 

and electrical systems.  

The Purchaser plans to install a fifth 7.0 MW diesel generator in parallel with the 

existing four units, which will include one (1) new 10 m3 day tanks. 

This  request  for  proposal  is  for  the  supply  and  installation  of  the  fuel  supply 

system required by the new 7.0 MW diesel generator which will be  included  in 

the supply of the diesel generator.  

The  basic  fuel  supply  system  is  shown  on  the  attached  flow  diagram 

(Attachment A). 

I.3. BasicdesignThe  following  design  items  are  included  in  the  Generator  Vendor’s  scope  of 

work: 

1. Fuel  system  flow  sheet  (P&I  diagram),  showing  existing  and  new 

installation, will be provided by  the  vendor  (developed  from  attached 

flow sheet (drawing No. 4566‐100‐001) 

2. The fuel supply piping to the new 10 m3 day tank is to be connected to 

the  existing  fuel  line  to  the  day  tanks  now  installed  in  the  diesel 

generator hall. 

3. This  Vendor  shall  coordinate  with  existing  civil  contractor  the 

dimensions  of:  Concrete  foundations,  curbs,  walls,  piping  &  cable 

penetrations and cover of the new fuel tank pit. 

4. Completed data  sheets  for  all  required equipment  items  for  approval, 

including, but not limited to: 

Annex‐A210  

Day tank. 

Fuel transfer pumps. 

Instrumentation  including  level,  pressure  and  temperature 

instruments, control valves, pneumatic valves, etc. 

5. System  layout  showing  required  space,  dimensions  of  equipment  and 

equipment layout and arrangement 

6. Piping plans and elevations together with piping specifications 

I.4. DetaileddesignThe following shall be issued to the Purchaser: 

1. Finalized and approved documents listed in paragraph 2 above. 

2. Fabrication  drawings  and  specifications  of  all  fabricated  items  (tanks, 

etc.) 

3. Completed data sheets of transfer pumps 

4. Final piping plans, elevations and details 

5. Piping connections to existing fuel supply system 

6. Piping specification  

7. Instrument list 

8. Instrument specifications and data sheets 

9. Electrical wiring diagram and electrical equipment manufacturer’s data 

10. Final computer logic diagram showing condition of fuel supply system 

I.5. EquipmentandmaterialsupplyAll equipment of a given type shall be furnished by a single Manufacturer.  

I.6. TanksOne (1) carbon steel fuel oil auxiliary (day) tanks. 

Tank volume ‐10 m3 

Type – horizontal 

Material of construction – carbon steel to ST 37/2 or A 328 Gr. C. 

Tank to slope at 1% towards outlet connection. Invert level of outlet nozzle shall 

be 50 mm above bottom drain. 

Annex‐A211  

Tank  shall be equipped with 2”  vent,  to be ended with downward bent,  and 

screen, to avoid ingress of rainwater, etc.   

Tank  shall have  local 2 1/2”  fill  connection  for  filling  from  road  tankers.  This 

quick connection to be supplied with  lockable ball valve and hanging screw‐on 

cap connected by a chain to the tank.  Tank to be supplied with lifting lugs.  

Tank shall further be fitted with nozzles, as shown on the flow sheet, for  level 

indication and overfill and under fill protection. 

Tanks  shall be  fabricated  in accordance with  the  requirements of API 12 F or 

equivalent code. 

All  tank  nozzles  shall  be  fabricated  of  SCH  40  carbon  steel  pipe  and  hanging 

screw‐on cap connections where required. 

I.7. Pumps Two  (2) positive displacement gear pumps shall be provided. One pump shall 

be  electric  motor  driven  and  the  second  shall  be  a  stand‐by  pump 

pneumatically driven. 

The capacity of each pump to be 3 m3/h at a head of 4 barg (for reference only) 

or as per the new generator manufacturers requirements. 

Pumps  shall be of  the herring‐bone  gear design, or  equal.    Pump  and motor 

drive shall be close coupled, directly connected through a  flexible coupling, or 

flexibly coupled to a gear reducer. 

Pump  shaft  speed  shall  not  exceed  1500  RPM.  Pump  connections  shall  be 

screwed NPT, or flanged to ANSI 16.5. 

Pump to be fitted with  integral pressure relief valve and coupling guard,  if not 

close coupled. 

The  pump  and  driver  shall  be mounted  on  a  common  fabricated  steel  base 

plate.  

Acceptable Manufacturers shall be Viking Pump Inc, IMO Pumps, Worthington, 

or equal. 

I.7.1. PipingAll piping up to and  including 2” shall be seamless carbon steel SCH 40 to A53 

Gr. A or B.   All connections shall be screwed NPT. 

Annex‐A212  

Fittings shall be series 2000 forged carbon steel to A 105 with screwed ends.  

Where flanged ends are required, flanges shall suit the equipment connections. 

All underground piping shall be double contained.  

I.7.2. Valves Manual shut‐off valves shall be ball valves, fire‐safe to API 607  lever operated 

with screwed ends to NPT, or flanged.  Similarly, solenoid‐operated valves shall 

be ¼ turn ball valves with screwed ends, or flanged. 

Any fusible emergency shut‐off valve shall be screwed, full ported bronze body 

lever‐operated  with  fusible  link,  set  to  automatically  close  the  valve  at  a 

temperature of 165oF (74oC).  The valve to be supplied with a spare fusible link. 

The fusible shut‐off valve shall be UL‐ or FM‐approved. 

All underground piping  shall be  cathodically protected by means of  sacrificial 

anodes, which will include supply and installation of magnesium strip, reference 

electrodes and test box.  

The  supply  and  delivery  to  site  of  all  required  equipment  and  materials  is 

included in Vendor’s scope of supply, comprising: 

1. Shop and site inspection – Note that Purchaser may elect to be present 

at inspections of his choice. 

2. Packaging and transport to site 

3. Site storage  to ensure cleanliness and proper protection of equipment 

and materials prior to installation. Storage of all material and equipment 

shall be above ground. 

 

Annex‐A213  

I.7.3. SiteinstallationIncluded in the Vendor’s scope of work are the following:  

1. Design  and  construction  of  all  necessary  concrete  foundations,  bund 

walls,  curbs, metal  cover  to  close  opening  above  storage  tank,  vent 

pipe, epoxy painting of inner walls to form secondary containment, etc. 

2. Excavation,  trenching  and  core  drilling  for  aboveground  and 

underground piping 

3. Installation of equipment 

4. Installation  of  piping  including  design  and  installation  of  piping 

supports, anchors and guides – all  in accordance with  the piping code 

requirements (ASME B 31.3 or similar code approved by the Purchaser). 

5. Installation  of  instrumentation  and  connection  of  instruments  to 

instrument air and electrical power supply, and wiring as required.  

6. Wiring  of  transfer  pump(s)  and  any  other  equipment  as  may  be 

required. 

7. Painting  of  all  external  carbon  steel  surfaces  with  a  zinc‐rich  epoxy 

coating in accordance with the paint manufacturer’s instructions. 

8. Labeling of all components and piping, including directional arrows. 

9. Cleaning  of  all  equipment  including  internal  cleaning  of  tank  and 

blowing out of piping. 

10. Pressure  testing of piping  followed by drying with methanol or other 

approved method.  

11. Connection to existing fuel supply and return piping.  

I.8. CommissioningFollowing  inspection  and  approval  by  the  Purchaser,  the  Vendor  shall 

commission the fuel supply system.  Commissioning shall include: 

1. Check  that  all  instrumentation  is  operating  as  designed  including: 

Analog  level  indicators, alarms and trips, all valves operate as planned 

and  all position  indicators  indicate  correctly.   Also  check  that pump’s 

indicators show pump running/not running. 

2. Check  that  computer  system  displays  all  screens  associated with  the 

fuel supply system and operates correctly. 

Annex‐A214  

3. Check  that  all  pumps  operate  correctly,  are  lubricated  in  accordance 

with manufacturer’s  instructions and  that  fuel  is  transferred  from  the 

main  storage  tanks  to  the  day  tanks  and  from  the  day  tanks  to  the 

diesel generator at the specified flows and pressures.  

I.9. CompletionOn  completion  of  installation  and  commissioning,  the  Vendor  shall  clean  and 

restore all work areas to the condition prior to commencement of work.  

I.10. DocumentationOn completion of commissioning and acceptance by Purchaser, the Vendor shall 

revise all documentation “as built” and transmit the following documents to the 

Purchaser: 

1. Fuel system flow sheet (P & I diagram) 

2. Layout 

3. Equipment data sheets 

4. Equipment test reports and calibration certificates 

5. Piping plans, elevations and details and piping test reports 

6. Instrument list and data sheets 

7. Wiring diagram and electrical equipment data 

8. Operational & Maintenance Manuals will include: 

a. Installation instructions for pumps 

b. Maintenance instructions for pumps 

c. Performance test reports 

d. Data sheets for main equipment items 

e. Instrument list 

f. Wiring diagram 

g. Control logic diagram 

h. Operating manual 

i. P & I diagram 

   

Annex‐A215  

j.  

I.10.1. ServicesThe following services are available on site: 

1. Instrument air –   0.4 mPa ‐ 0.5 mPa (dry and oil‐free) 

2. Service air –  0.5 mPa. 

3. Control power – by vendor 

4. Electrical power –   220 v 1 ph 50 Hz 

380 v 3 ph 50 Hz 

I.11. ApplicablecodesandregulationsAll materials,  equipment  and  implementation  shall meet  the  requirements  of 

the following codes and regulations: 

Storage tanks ‐‐         API 12F 

Piping ‐‐           ASME B 31.3 

Electrical ‐‐        NFPA 70 and IEC 

Instrumentation ‐‐         ISA Standards 

Israeli Safety at Work Regulations ‐‐ 18001 

Israeli electric law –       1954  with  all  updates  and 

additions 

NFPA 31 

 

I.12. Generaloperatingandsafetydescription

I.12.1. NormalconditionAll five diesel generators will normally be on stand‐by so that the fuel supply 

system will  be  set  for  immediate  engine  start‐up.    This  requires  that  the 

normal system conditions are: 

Both main 100 m2 storage tanks are 75% or more full 

All day tanks are full 

All manual valves in supply piping are open 

Computer diagram showing tank levels, valve positions, etc. is “on”. 

Annex‐A216  

On  the  “start”  command  the  electrical  driven  “day  tank”  fuel 

transfer pump starts 

With the establishment of fuel pressure the engine air start system 

is initiated 

The fuel level in the day tank initiates the main fuel transfer pumps 

to maintain the day tank level.  These pumps operate on an “on‐off” 

mode  such  that  the pumps  switch “off” on high  level and “on” on 

low  level.    In  the  event of  failure of  the  automatic  system, pump 

operation  can  be  switched  to manual  and  be  operated  by  a  local 

“on/off”  switch.  Under  normal  operation,  the  electrical  ‐driven 

transfer pumps will be “on line”.  In the event of power failure, the 

stand‐by pneumatically driven pumps will start. 

In  the  event  that  the  level  in  any  tank  exceeds or  falls below  the 

normal  operating  range  (High‐High  /  Low‐Low,  operators  driven)  , 

the control computer will trigger both a visual and audio alarm.  

I.13. AcceptanceThe acceptance conditions are as follows: 

All  equipment,  piping  and  systems  are  tested  and  approved  by 

Purchaser 

The fuel supply system  is tested and shown to operate as designed 

and approved by Purchaser 

All “as built” documents are submitted and approved by Purchaser 

All work areas are cleaned and returned to original condition. 

I.14. AttachmentNo  Description  DWG

1  Flow Sheet  4566‐100‐001

2  Tank data sheet 4566‐100‐002

3  Tank Lay Out  4566‐500‐001

 

   

Annex‐A217  

J. ChapterJ: AcceptanceTests

J.1. GeneratorAcceptanceTests‐phase‐1

J.1.1. ShopTest(FAT)The shop acceptance test/factory acceptance tests shall be conducted at the 

manufacturer's plant in accordance with the manufacturer's standard acceptance 

test procedures (the supplier shall indicate on which international standards and 

codes the test procedures are based). Those procedures should be approved in 

advance by IAA. The test procedures shall include, but are not limited to, all of the 

following: 

1. Test Objective: 

The purpose of the test is to verify engine mechanical integrity and 

compliance with acceptance criteria performance levels. 

Measurements are made at test points in the engine maximum power 

range. This data is used to determine horsepower ‐ shaft or 

isentropic, depending on the test method ‐ and heat rate. The test 

data is corrected to the guarantee conditions for comparison to 

contract requirements. The major acceptance criterion of the Factory 

Test demonstrates Engine compliance with specified chapter C and 

the Engine data sheet: 

Performance  

Vibration 

Mechanical Integrity 

2. Test Description: 

Engine test is performed with two major objectives: 

Break‐in and functional checkout 

Acceptance Test‐ Factory Acceptance Test is performed 

immediately after completing the functional checkout test as 

a continuation of the test points. The engine generator set 

shall be completely factory tested under rated full load and 

rated power factor for performance and proper functioning of 

control and interfacing circuits. Test shall be a minimum of 2 

hours or time required reaching operating temperature. 

3. Acceptance Criteria: 

The rated performance of the Engine in the new and clean 

condition shall be based upon the “As tested” conditions. 

Engine acceptability will be determined based upon 

comparison to the specifications and approved Engine data 

sheet.

Annex‐A218  

 

The following is a list of as tested conditions which are 

accounted for by the performance comparison to determine 

actual engine operating margins: 

A. Ambient temperature 

B. Ambient Air Pressure  

C. Relative Humidity  

D. Fuel Heating value LFO (kj/kg) or Natural Gas 

 (Btu/lb or Btu/nm3) 

E. Inlet pressure Loss 

F. Exhaust pressure Loss 

The following is a list of minimum performance data that will 

be tested and will be conducted in dual fuel configuration 

(NG, LFO) : 

A. Engine capacity at full load–MW 

B. Engine capacity at 110%, 75%,50%,25%‐ MW 

C. Engine heat rate at full and partial load‐ Btu/kwh 

D. During engine test, the changeover between  the 

fuels will be demonstrated  

4. In addition, the following functional tests will be carried out: 

Engine safety shut downs 

Start/stop via central engine control and verify transient and 

steady state governing 

Crank web deflection measurement (cold/warm( 

Monitor voltage regulation 

Monitor engine operating parameters: Coolant temperature, 

oil pressure, Generator temperature, etc . 

Test generator / alternator to determine that it is free of 

mechanical and electrical defects. Tests shall include the 

following: 

A. Resistance of all windings (cold)  

B. Insulation resistance of all windings  

C. High potential on all windings  

D. Open circuit saturation  

E. Voltage balance on windings 

F. Voltage transient at rated KVA (voltage regulation, 

stability and response) 

G. Mechanical balance (vibration)  

H. Circulating current  

I. Dissipation factor tests 

Annex‐A219  

After the acceptance test, the main running gear, camshaft 

drive and gear train will be inspected through the opened 

access covers. 

The test will be performed in the presence of the Contractor 

and the IAA representative. At the end of the test, the Engine 

manufacturer shall submit detailed test reports as performed 

at the manufacturer's plant. 

J.1.2. SiteTestProceduresThe objective of the site performance test is to evaluate the Plant 

Performance at full and partial loads on liquid fuel and Natural Gas (if 

available at stage A of the project. In case IAA will implement stage B of the 

project‐ demonstration of operation of the plant with NG)  

As tested results shall be corrected to the base reference conditions as 

defined in chapter‐ A using correction curves to be provided by the supplier. 

In order to determine the Plant Performance, the plant will be operated in a 

manner as close to the Base. Reference Conditions as possible given the 

ambient conditions and schedule constraints under which the performance 

testing is conducted   

Annex‐A220  

 

J.1.3. 24‐HoursSiteTestProceduresThe site test shall be executed by the contractor under supervision of the 

engine‐generator manufacturer's technical representative or a qualified 

commissioning engineer. All test equipment shall be provided by the 

contractor. The first site test shall be performed for a continuous period of 24 

hours with various loadings as described below. 

The contractor will provide all required tools, lube, oil and material for testing 

the unit under real operating conditions. The IAA will supply the oil fuel only 

for the first 24‐ hours test, in case of test failure‐ the contractor will purchase 

the fuel from the IAA required to repeat the testing optimal results take place. 

The fuel price will be determined by IAA, and will be in accordance to costs. 

The first site test (24‐hours test) shall be performed in the following order. 

Each step shall be recorded 

1. Verify and put into operation all auxiliary subsystems; Water cooling system, 

keep‐warm water system, fuel, etc. 

2. Put into operation all equipment provided and installed, except as 

specifically noted otherwise. Make all necessary adjustments to equipment. 

Lubricate equipment prior to operation, in accordance with the 

manufacturer's instructions. 

3. Upon approval by the authorized representative, operate diesel generating 

unit under the supervision of the manufacturer's technical representatives 

at varying loads, throughout the load range for a sufficient time, in order to 

demonstrate proper operation and verifying that all pressures and 

temperatures are normal within the specified limits. 

4. Operate engine for a period of time sufficient to assure that the unit is ready 

to carry the test loads, without damaging any of the engine parts. 

5. During this preliminary operation, check the operation of all auxiliary 

equipment to establish proper functioning and complete any necessary 

adjustments to the equipment, in order to bring it to a first‐class operating 

condition, in conformance with the contract requirements. 

6. When installation is complete and ready for operation, a written notification 

needs to be sent out by an authorized representative, indicating that the 

diesel generating unit, along with its' auxiliary equipment, are ready for final 

field tests. 

7. Other tests that may be performed if necessary or if desired to make sure 

that all equipment is functioning properly include, but are not limited to the 

following: 

Annex‐A221  

a. A test to determine generating unit speed control under a gradual 

change from zero to full load (using plant electrical system load for 

loading the generating unit under test); 

b. A test to determine generating unit instantaneous speed change 

with 25 percent load on and off; 

c. A test to assure synchronization and load sharing  with the existing 

system  

d. A test to assure proper functioning of the over‐speed trip; 

e. An individual test of each pressure and temperature alarm switch; 

f. An individual test of each protection relay operation; 

g. A test to insure  proper functioning of the  annunciation and alarm 

logging; 

h. A test to check proper functioning of the automatic synchronizers; 

i. A test to  check proper operation of the generating units in parallel; 

j. Simulating fault conditions for all protection relays verifying proper 

protection values and alarm signals; 

8. Inspect all auxiliary equipment such as pumps, compressors, fans, heat 

exchangers, instruments, valves, etc., all to assure proper functioning. Any 

or all auxiliary equipment shall be field tested at the presence of the 

authorized representative. 

9. Perform operational tests for a minimum duration of 4 hours for each load 

at following scopes: at 100%, 75% and 50% loads. Register temperatures of 

ambient combustion air, cooling water and generator. Demonstrate also 

satisfactory performance of all automatic and parallel operations. 

10. After the full load tests, conduct a supplementary test in 110%of a full load 

for 2 hours, to demonstrate expected fuel consumption, smokeless 

combustion, adequate engine and complementary equipment capacities, 

and to insure freedom from undue strain. 

11. The oil will be drained and inspected for presence of metal fragments 

and/or water. 

12. Samples of lubricants and coolants shall be tested in official licensed labs. 

The contractor shall bear all costs involved in obtaining those test reports. 

If the specified tests do not reach the desired performance, the contractor is obligated 

to make all necessary adjustments and changes to further check the performance of the 

equipment, until optimal operation has been achieved. The contractor will bear all costs 

associated with any additional tests required, including the cost of fuel used for testing. 

Electrical loads shall be real existing loads in absence of the IEC power supply. 

Electrical and mechanical calibrations shall be performed during the test period. 

   

Annex‐A222  

 

J.1.4. SOAK‐7‐DaysSiteTestThe second site test shall be performed for a continuous period of 7 days with rated load. The IAA will supply the oil fuel only for the first 7‐days test; in case of test failure, the contractor will be responsible for purchasing the fuel from the IAA in order to repeat any testing necessary. The fuel price will be in accordance to IAA'S costs.  During this test, the following values shall be recorded continuously: 

1. Engine Operating Load –MW 2. Engine Heat Rate at Operating Load‐ Btu/kwh 3. Synchronize and load sharing with the existing system  4. During engine test, the changeover between  the fuels will be demonstrated 

( In case NG will be available or in stage B)  5. Oxygen (O2) content of the exhaust gas 6. Carbon monoxide (CO) content of the exhaust gas 7. Carbon dioxide (CO2) content of the exhaust gas 8. Sulfur dioxide (SO2) content of the exhaust gas 9. Nitric oxides (NOx) content of the exhaust gas 10. Noise level 11. Vibration level 12. Exhaust Flow rate (kg/s) and exhaust gas temperature (Deg. C) 13. Ambient combustion air temperature 14. Bearings temperature 15. Windings temperature 16. Lube oil pressure 17. Lube oil temperature 18. Jacket water pressure 19. Jacket water temperature 20. Lube oil loss 21. Generated voltage 22. Generated frequency 

Graphical trends of the above mentioned values, recorded during testing, along with the pre‐submitted chart (of power versus air temperatures) shall be presented to CPM and IAA client personnel for approval.  The tests shall be coordinated with the IAA and carried out upon written approval. All tests shall take place in the presence of IAA personnel.  The tests shall be performed by skilled, experienced personnel. Maintenance procedures supplied by the generator manufacturer shall be carried out during the test. The contractor will be responsible to provide all labor, equipment, water, fuel, lubricants, temporary instrumentation, piping, electrical wiring and connections, and incidentals required for the tests. The contractor shall give to the authorized representative of the purchaser an ample notice time, and will submit in advance dates and times scheduled for all tests, trial operations and inspections. All deficiencies and malfunctions found during these tests are to be completely rectified within three months and any work affected by such deficiencies shall be completely retested at the contractor's expense until spec conditions are reached.  

Annex‐A223  

Only after receiving IAA's approval and issuance of the Final Acceptance Certificate, the Warranty Period will start.    The contractor shall submit all necessary documents to the Israeli Ministry of National Infrastructures, Energy and Water Resource for licensing the generator.   

J.2. AbsorptionchillerTests‐phase‐3For Phase 3 (Absorption chiller etc) FAT and SAT procedures see relevant section in chapter G. All test to be performed integrated with engine to comply with guaranteed performance.   

J.3. GuaranteedPerformanceandLiquidatedDamages

J.3.1. Phase1GasEnginePackageLiquidFuel Phase 1

Gas Engine Package Liquid Fuel

Capacity Bidder will specify in its proposal the guaranteed Net Power Output and percentage of degradation (the "Guaranteed Performance Values") within the following range: Maximum (MW) - 7.3 Minimum (MW) - 5.7 Max annual degradation (%) – 2% per year. Capacity will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) at the end of the Warranty Period (only 24 hours test will be implemented). If during the Acceptance Test there is a negative deviation of up to 10% from the Guaranteed Performance Value, Contractor shall be required to pay Liquidated Damages of US$ 1,500 for each 1 kW by which the electrical output demonstrated by the Plant is less than the Guaranteed Performance Values (the "Capacity Shortfall"). In the event that the negative deviation is of more than 10% from the Guaranteed Performance Values, then the Contract will be terminated. At the end of the Warranty Period, the Capacity will be measured again, but this time against the relevant Guaranteed Performance Value as adjusted based on the guaranteed degradation percentage that was specified by the Contractor (the "Adjusted Guaranteed Performance Value"). If there is negative deviation of up to 10% from the Adjusted Guaranteed Performance Value a, Contractor shall be required to pay Liquidated Damages of US$ 1,500 for each 1 kW by which the electrical output demonstrated by the Plant is less than the Adjusted Guaranteed Performance Values. It is clarified, that the Contractor shall not be required to pay additional liquidated damages for the Capacity Shortfall that it had already paid for after the first measurement (if any), and the liquidated damages shall be calculated based on the difference between the previously measured Capacity value and the new value measured. In the event that the deviation is of more than 10% from the Adjusted Guaranteed Performance Values, then the Contract will be terminated. In any event, any deviation of the Net Power Output from the Minimum and Maximum values that were set by the IAA will cause termination of the Contract.

Annex‐A224  

Phase 1 Gas Engine Package

Liquid FuelHeat Rate Bidder will specify in its proposal the guaranteed Heat Rate and percentage of

degradation (the "Guaranteed Performance Values"), whereas the Max degradation (%) – 2% per year. Heat Rate will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) at the end of the Warranty Period (only 24 hours test will be implemented). If during the Acceptance Test there is a positive deviation of up to 10% from the Guaranteed Performance Value, Contractor shall be required to pay Liquidated Damages of US$ 2,000 per kilojoule/kWh by which the Heat Rate demonstrated by the Plant during the Acceptance Tests exceeds the Guaranteed Performance Value (the "Heat Rate Surplus"). In the event that the deviation is of more than 10% from the Guaranteed Performance Values, then the Contract will be terminated. At the end of the Warranty Period, the Heat Rate will be measured again, but this time against the relevant Guaranteed Performance Value as adjusted based on the guaranteed degradation percentage that was specified by the Contractor (the "Adjusted Guaranteed Performance Value"). If there is positive deviation of up to 10% from the Adjusted Guaranteed Performance Value, Contractor shall be required to pay Liquidated Damages of US$ 2,000 per kilojoule/kWh by which the Heat Rate demonstrated by the Plant during the Acceptance Tests exceeds the Adjusted Guaranteed Performance Value. It is clarified, that the Contractor shall not be required to pay additional liquidated damages for the Heat Rate Surplus that it had already paid for after the first measurement (if any), and the liquidated damages shall be calculated based on the difference between the previously measured Heat Rate value and the new value measured. In the event that the deviation is of more than 10% from the Adjusted Guaranteed Performance Values, then the Contract will be terminated.

Exhaust Flow

The Contractor shall specify in its proposal the guaranteed: Exhaust Flow (kg/s) and Exhaust Gas Temp. (oC). The Exhaust Flow data shall also be reflected in Contractor's basic design of phase 1 including the absorption chiller. Exhaust Flow will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) at the end of the Warranty Period (only 24 hours test will be implemented). Liquidated Damages for deviation from the Guaranteed Performance Values of the Exhaust Flow will only be paid in phase 3 (Absorption Chiller), however, if in this stage there is a deviation (positive or negative) of more than 15% from the Guaranteed Performance Value the Contract will be terminated.

Availability The Contractor shall specify in its Proposal the guaranteed average availability of the Facility during the Warranty Period which shall be equivalent to, or greater than 92% (the "Guaranteed Performance Value"). Following the Warranty Period the availability of the Facility shall not be less than 95%. The availability will be measured once - at the end of the Warranty Period. The Contractor shall be required to pay liquidated damages of US$ 15,000 per each percentage (%) by which the Plant Availability during the relevant period is less than the Guaranteed Performance Value.

Annex‐A225  

J.3.2. Phase2‐GasEnginePackageNaturalGasFuel Phase 2

Gas Engine Package Natural Gas Fuel

Capacity Capacity and liquidated damages for any deviation will be measured in the same manner as specified for Phase 1 above, based on the Guaranteed Performance Values specified by the Contractor in its proposal, whereas the degradation will remain the same as in phase 1. The Capacity in phase 2 will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) after 8000 operating hours SOAK test will be implemented.

Heat Rate Heat Rate and liquidated damages for any deviation will be measured in the same manner as specified for Phase 1 above, based on the Guaranteed Performance Values specified by the Contractor in its proposal, whereas the degradation will remain the same as in phase 1. The Heat Rate in phase 2 will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) after 8000 operating hours SOAK test will be implemented.

Exhaust Flow

Exhaust Flow will be measured in the same manner as specified for Phase 1 above, based on the Guaranteed Performance Values specified by the Contractor in its proposal, whereas the degradation will remain the same as in phase 1. The Exhaust Flow in phase 2 will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) after 8000 operating hours SOAK test will be implemented. Liquidated Damages for deviation from the Guaranteed Performance Values of the Exhaust Flow will only be paid in phase 3 (Absorption Chiller), however, if in this stage there is a deviation (positive or negative) of more than 15% from the Guaranteed Performance Value the Contract will be terminated.

   

Annex‐A226  

J.3.3. Phase3‐IncludingChillerNaturalGasFuel

Phase 3

Including Chiller

Natural Gas Fuel Capacity Capacity and liquidated damages for any deviation will be measured in the same

manner as specified for Phase 1 above, based on the Guaranteed Performance Values specified by the Contractor in its proposal, whereas the degradation will remain the same as in phase 1. The Capacity in phase 3 will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) at the end of the Warranty Period (only 24 hours test will be implemented).

Chiller Capacity

Bidder will specify in its proposal the guaranteed Chiller Capacity and percentage of degradation (the "Guaranteed Performance Values") within the following range: Maximum (TON ref.) - 1500 Minimum (TON ref.) - 1300 Max degradation (%) – 2% per year. Chiller Capacity will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) at the end of the Warranty Period (only 24 hours test will be implemented). If during the Acceptance Test there is a negative deviation of up to 10% from the Guaranteed Performance Value, Contractor shall be required to pay Liquidated Damages of US$ 2,000 for each 1 ton ref. by which the chiller output demonstrated by the Plant is less than the Guaranteed Performance Values (the "Chiller Capacity Shortfall"). In the event that the negative deviation is of more than 10% from the Guaranteed Performance Values, then the Contract will be terminated. At the end of the Warranty Period, the Capacity will be measured again, but this time against the relevant Guaranteed Performance Value as adjusted based on the guaranteed degradation percentage that was specified by the Contractor (the "Adjusted Guaranteed Performance Value"). If there is negative deviation of up to 10% from the Adjusted Guaranteed Performance Value a, Contractor shall be required to pay Liquidated Damages of US$ 2,000 for each 1 ton ref. by which the chiller output demonstrated by the Plant is less than the Adjusted Guaranteed Performance Values. It is clarified, that the Contractor shall not be required to pay additional liquidated damages for the Chiller Capacity Shortfall that it had already paid for after the first measurement (if any), and the liquidated damages shall be calculated based on the difference between the previously measured Chiller Capacity value and the new value measured. In the event that the deviation is of more than 10% from the Adjusted Guaranteed Performance Values, then the Contract will be terminated. In any event, any deviation of the Chiller Capacity from the Minimum and Maximum values that were set by the IAA will cause termination of the Contract.

   

Annex‐A227  

Phase 3

Including Chiller

Natural Gas Fuel Heat Rate Heat Rate and liquidated damages for any deviation will be measured in the

same manner as specified for Phase 1 above, based on the Guaranteed Performance Values specified by the Contractor in its proposal, whereas the degradation will remain the same as in phase 1. The Heat Rate in phase 3 will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) at the end of the Warranty Period (only 24 hours test will be implemented).

Exhaust Flow Exhaust Flow will be measured in the same manner as specified for Phase 1 above, based on the Guaranteed Performance Values specified by the Contractor in its proposal, whereas the degradation will remain the same as in phase 1. The Exhaust Flow in phase 3 will be measured twice: (i) during the Acceptance Tests (full site acceptance test of 24 hours and SOAK 7 days), and (ii) at the end of the Warranty Period (only 24 hours test will be implemented). If during the Acceptance Test there is a deviation (negative only) of up to 15% from the Guaranteed Performance Value, Contractor shall be required to pay Liquidated Damages of US$ 210 per kg/hr. deficiency (the "Exhaust Flow Difference"). In the event that the deviation (positive or negative) is of more than 15% from the Guaranteed Performance Values, then the Contract will be terminated. At the end of the Warranty Period, the Exhaust Flow will be measured again, but this time against the relevant Guaranteed Performance Value as adjusted based on the guaranteed degradation percentage that was specified by the Contractor (the "Adjusted Guaranteed Performance Value"). In the event that the deviation is of more than 15% from the Adjusted Guaranteed Performance Values, then the Contract will be terminated.

 

Annex‐A228  

K. ChapterK‐. TenderGeneralForm

K.1. Guaranteedvalues

K.1.1. GeneralBidders should complete this Tender Form K1 in accordance Annex A chapter A 

and C, and Appendix H, when doing so, Bidders must refer to Appendix J – 

Tests Specifications and Penalties, referring to the requirements stipulated 

herein. 

The Guaranteed and Specified Performance Criteria should be stipulated in the 

tables herein. 

The Specified Performance Criteria values are the basis of the process design. 

Those values are required for the evaluation of the proposals and for process 

design quality and redundancy during the tender period. During the testing of 

the Gas Engine Package, Specified Performance Criteria values will be used to 

verify engine mechanical integrity, vibrations and compliance with acceptance 

criteria performance levels. 

Bidders should specify and provide the following curves for Prime Mover 

Generator: 

Power Output vs. Ambient Temperature 

Heat Rate vs. Ambient Temperature 

Power Output vs. Ambient Pressure 

Heat Rate vs. Ambient Pressure 

Power Output vs. Relative Humidity 

Heat Rate vs. Relative Humidity 

K.1.2. GuaranteedPerformanceFiguresThe Guaranteed Performance Figures provided by Bidders within this chapter k  

will be checked and verified, in accordance with the tests specified in Appendix 

J, during the various tests: the Shop Test (FAT) and, thereafter throughout the 

24‐Hours Site Test and the SOAK‐ 7‐Days Site Test. 

Annex‐A229  

 

  Description     

REQUIRED   

OFFERED (Phase I & II) 

Liquide  Nat. Gas 

1.         Engine Inlet:          

   Ambient Temp (Deg. C)  25       

   Ambient Pressure (kPa)  99       

   Relative Humidity (%)  60%       

2.         Pressure Losses (at 100% load): 

        

   Inlet Loss (mm H2O)          

   Exhaust Loss (mm H2O)          

3.         Engine Pack Performance:          

   Overall Heat Rate at 100% load, Btu/kWh 

        

   Overall Heat Rate at 75% load, Btu/kWh 

        

   Overall Heat Rate at 50% load, Btu/kWh 

        

   Total Gross Power Output , at 100% load, at acceptance test ‐ MW 

        

   Total Internal / Parasite / Pumping / etc. consumption ‐ MW 

        

   

Annex‐A230  

  Description     

REQUIRED   

OFFERED (Phase I & II) 

Liquide  Nat. Gas 

   Net Overall Guarantied Power, at 100% load, at acceptance test ‐ MW 

5.7 MW min.       

   Net Overall Guarantied Power, at 75% load, at acceptance test ‐ MW 

        

   Net Overall Guarantied Power, at 50% load, at acceptance test ‐ MW 

        

   Overall Power Plant Electrical Efficiency – at 100% load (%) 

        

4.         Engine Operation Data:          

   Exhaust manifold Flow Rate, at 100% load, kg/s 

        

   Exhaust manifold Temperature, at 100% load, Deg. C 

        

   Engine Gas Consumption, LHV ,at ISO condition, 100% load, Nm3/kWh 

        

   Engine Gross Power annual Degradation (%) 

max/yr.       

   Engine Heat Rate annual Degradation (%) 

max/yr.       

   Exhaust Flow Rate annual degradation (%) 

max/yr.       

   Specific Oil Consumption, gr/kWh 

        

   

Annex‐A231  

  Description     

REQUIRED   

OFFERED (Phase I & II) 

Liquide  Nat. Gas 

5.         Startup times from:  

   Cold conditions, sec.          

   Warm conditions, sec.          

6.         Availability:          

   Availability – First Year  92%       

   Availability ‐ Others  95%       

7.         Exhaust Gas Emissions:         

   SOx  (mg/DSCM1)  ‐‐‐       

   NOx  (mg/DSCM1)  500       

   CO (mg/DSCM1)  300       

   NH3 (mg/DSCM1)  30       

   Formaldehyde(mg/DSCM1)  60       

   

Annex‐A232  

  Description     

REQUIRED   

OFFERED (Phase III) 

Liquide  Nat. Gas 

1.         Engine Pack Performance including Chiller, at 100% load: 

        

   Net Overall Guarantied Power, at 100% load, at acceptance test ‐ MW 

5.7 MW min.       

   Overall Heat Rate at 100% load, Btu/kWh 

        

   Chiller Capacity (TON ref.)  1,300 min.       

   Chiller Capacity annual Degradation (%) 

max/yr.       

 

   

Annex‐A233  

K.2. TechnicalForm:Layoutandconstructionverificationandapproval

No  Description  Approve IAA 

design  

Contractor  

Propose/Remarks 

1  Building construction drawings     

2  General arrangement drawing      

2.1  Layout of Generator and future absorption 

chiller, condenser, water, chilled water pumps 

and piping 

   

2.2  Generator's exhaust system layout     

2.3  Indoor ventilation system     

2.4  Roof mounted equipment layout     

2.5  Cooling system layout      

2.6  Hot water system  Not in IAA drawing    

2.7  Day tank     

2.8  Compressed air system      

2.9  Electrical equipment layout including: 

MV switch board 

LV switch board 

MV transformer  

UPS 

Black start generator 

   

  

 

 

 

 

Annex‐A234  

 

 

K.3. EnvironmentalGeneratorThe following table presents the mandatory conditions for dry exhaust gas at 

a temperature of 273 degrees Kelvin, a pressure of 101.3 kilopascal, and an 

excess oxygen of 5 percent for Diesel generators (comply with T.A.Luft  2002) 

and with appendix H: 

For natural gas fuel:

Emission pollutant

Limit Value

T.A.Luft2002

Contractor

Approval

SOx (mg/DSCM1) ---

NOx (mg/DSCM1) 500

CO (mg/DSCM1) 300

NH3 (mg/DSCM1) 30

Formaldehyde(mg/DSCM1) 60

1‐ DSCM: Dry Standard Cubic Meter, 0 0C, 1atm @5%O2.  

   

Annex‐A235  

K.4. TECHNICALFORM:DIESELENGINEANDACCESSORIESNo  Description  Contractor  

Propose/Remarks 

1.   General Information    

1.1.     Diesel engine manufacturer :    

1.2.     Type and Model No. :    

1.3.     Total weight of unit, Tones :    

1.4.     Basic type and rating at standard condition, HP/KW :   

1.5.     One line diagram   

1.6.      Heat and mass balance    

1.7.     P&I Drawing of the complete project   

2.   Rotation direction (viewed from Power take‐off end) :    

3.   Derating factors for altitude, % :    

4.   Derating factor for ambient temperature, % :    

5.   Engine Performance, at site condition :    

5.1.   Power output at 100% load (kW at site conditions)   

5.2.   Power generation (kW at generator output terminals)   

5.3.   Minimum Load (%)   

5.4.   Heat Rate (kJ/kWh, at site conditions and 25 Deg. C)   

5.5.   Gas Consumption (Nm3/kWh, at site conditions and 25 Deg. C)   

5.6.   Electrical Efficiency at 100% load, %   

6.   Operating speed, rpm ( max. 750 rpm) :    

7.   Number of strokes per cycle :    

8.   Arrangement of cylinders :    

9.   Number of cylinders :    

10.   Bore, mm :    

11.   Stroke, mm :    

12.   Swept volume, cc :    

13.   Compression ratio :    

14.   Maximum firing pressure, kg/sq.cm (g) :    

15.   Mean piston speed, rpm :    

16.   Brake mean effective pressure at rated load, kg/sq.cm (g) :    

17.   Mean indicated pressure at rated load, kg/sq.cm :    

18.   Firing order (viewed from power take off end), kg/sq.cm :    

19.   Maximum time required to start the engine from cold condition and to bring up to full speed, seconds :  

 

   

Annex‐A236  

No  Description  Contractor  Propose/Remarks 

20.   Rate of loading per second after attaining full speed, KW/Sec. :    

21.   BSFC at :    

21.1.     1/4 load, gm/kWh :    

21.2.     1/2 load, gm/kWh :    

21.3.     3/4 load, gm/kWh :    

21.4.     Full load, gm/kWh :    

22.   Lub oil temperature, inlet / outlet, Deg. C :                    / 

23.   Lub oil pressure, kg/sq.cm (g) :    

24.   Fuel oil pressure, kg/sq.cm (g) :    

25.   Water inlet/outlet temperature, Deg. C :                    / 

26.   Cyclic irregularity :    

27.   Recommended specification of fuel oil :    

28.   Governing :    

29.   Material of construction (Indicate) specific codes/standards) :    

29.1.     Cylinder :    

29.2.     Cylinder head :    

29.3.     Cylinder liners :    

29.4.     Crank shaft :    

29.5.     Connecting rod :    

29.6.     Piston :    

29.7.     Piston rings :    

29.8.     Gudgeon pin :    

29.9.     Inlet/exhaust valves :    

29.10.   Valve springs :    

29.11.   Heat exchanger :    

29.11.1.      Shell :    

29.11.2.      Tubes :    

30.   Protection Devices    

30.1.     High water temperature Deg. C :    

30.2.     Low lube oil pressure, kg/sq.cm(g) :    

30.3.     Overspeed, rpm    

31.   Lubricating Oil System    

   

Annex‐A237  

No  Description  Contractor  Propose/Remarks 

32.   General Information    

32.1.      Type :    

32.2.      Minimum acceptable lub oil temperature at start up, Deg. C :    

32.3.      Lub oil consumption at rated load, gm/kWh :    

32.4.      Recommended specification of lubricating oil :    

33.   Engine Driven Lubricating Oil Pump    

33.1.     Type :    

33.2.     Number/engine :    

33.3.     Location :    

33.4.     Capacity, L/min. :    

33.5.     Drive rating, KW :    

33.6.     Discharge pressure, Kg/sq.cm. :    

34.   Motor Driven Lubricating Oil Pump (For priming/pre‐lubrication of lub oil circuit, if required)  

 

34.1.     Type :    

34.2.     Number/engine :    

34.3.     Location :    

34.4.     Capacity, L/min. :    

34.5.     Drive rating, kW :    

34.6.     Delivery pressure, kg/sq.cm. :    

34.7.     Materials of construction (Indicate applicable codes/ standards):   

34.7.1.      Casing :    

34.7.2.      Shaft :    

35.   Turbo‐Charger    

35.1.     Make :    

35.2.     Type :    

35.3.     Number/engine :    

35.4.     Speed, r.p.m. :    

35.5.     Charger air pressure at rated load, kg/sq.cm :    

35.6.     Material of construction (Indicate specific codes/ standards)    

35.6.1.      Turbine blade material :    

35.6.2.      Blower blade material :    

   

Annex‐A238  

No  Description  Contractor  Propose/Remarks 

36.   After‐Cooler    

36.1.     Type :    

36.2.     Water flow, L/min. :    

36.3.     Water inlet temperature, Deg. C :    

36.4.     Water outlet temperature, Deg. C :    

36.5.     Free air flow, cu.m./hr. :    

36.6.     Inlet air pressure, kg/sq.cm :    

36.7.     Inlet air temperature, Deg. C :    

36.8.     Air temperature drop, Deg. C :    

36.9.     Material of construction :    

37.   Governing System    

37.1.     Type :    

37.2.     Make :    

37.3.     Steady state speed :    

37.4.     Steady state incremental speed regulation :    

37.5.     Prescribed speed band :    

37.6.     All other details of speed control arrangement :    

37.7.     Class of governing    

   

Annex‐A239  

K.4.1. TECHNICALFORM:COOLINGSYSTEMNo  Description  Contractor  

Propose/Remarks 

1.   Engine Jacket Water Cooling    

1.1.     Type :    

1.2.     Engine jacket capacity :    

1.3.     Expansion tank/Head rank on radiator    

1.3.1.      Capacity of each tank, Litre :    

1.3.2.      Number :    

1.3.3.      Dimension, mm x mm :    

1.3.4.      Location :    

1.4.     Water pump    

1.4.1.      Type :    

1.4.2.      Number :    

1.4.3.      Capacity of each pump, L/min. :    

1.4.4.      Drive rating, kW :    

1.4.5.      Location :    

1.5.     Heat Exchanger ‐ Coolers   

1.5.1.      Type and make :    

1.5.2.      Number/engine :    

1.5.3.      Jacket water flow, L/min :    

1.5.4.      Inlet jacket water temperature, Deg.C :    

1.5.5.      Outlet jacket water temperature, Deg.C :    

1.5.6.      Cooling Water flow, L/min :    

1.5.7.      Design pressure for shell/tubes, Kg/sq.cm :    

1.5.8.      Hydro‐test pressure for shell/tubes, Kg/sq.cm :    

1.5.9.      Effective heat transfer area, Sq.M :    

1.5.10.      Number of plates per heat exchanger (including extra):    

1.5.11.      Gasket type & material :    

1.5.12.      Cleaning frequency of heat exchanger, hours:    

1.5.13.      Whether Cooler by‐pass line with control valve, provided ? :  

      Yes/No  

 

   

Annex‐A240  

No  Description  Contractor  Propose/Remarks 

2.   Lub Oil Cooling    

2.1.     Type :    

2.2.     Engine lub‐oil capacity, Litres :    

2.3.     Lub‐oil cooling circulating pump    

2.3.1.      Type :    

2.3.2.      Number/engine :    

2.3.3.      Location :    

2.3.4.      Capacity, L/min. :    

2.3.5.      Delivery pressure, kg/sq.cm(g) :    

2.3.6.      Type of drive :    

2.3.7.      Drive rating, KW :    

2.4.     Lub‐oil HX cooler :    

2.4.1.      Type :    

2.4.2.      Number/engine :    

2.4.3.      Lub‐oil flow, L/min. :    

2.4.4.      Lub‐oil inlet temperature, Deg.C :    

2.4.5.      Lub‐oil outlet temperature from cooler, Deg.C:    

2.4.6.      Water inlet temperature to cooler, Deg.C :    

2.4.7.      Water outlet temperature from cooler, Deg.C:    

2.4.8.      Water flow, L/min :    

2.4.9.      Design pressure, kg/sq.cm(g) :    

2.4.10.      Test pressure, kg/sq.cm(g) :    

2.4.11.      Effective heat transfer area, sq.m :    

2.4.12.      Number of plates per heat exchanger (including extra):    

2.4.13.      Cleaning frequency, Hours :    

2.5.     Whether provided Lub‐oil by‐pass to cooler with control valve : Yes/No 

 

3.   Engine air intake filter    

3.1.     Type :    

3.2.     Manufactured by :    

3.3.     Pressure Drop across filter, at 100% load :    

3.4.     Free area :    

3.5.     Particle removing efficiency :    

   

Annex‐A241  

No  Description  Contractor  Propose/Remarks 

4.   Fan cooled Radiators    

4.1.     Type :    

4.2.     Make :    

4.3.     Location :    

4.4.     Water inlet temperature, Deg. C :    

4.5.     Water outlet temperature, Deg. C :    

4.6.     Cooling air flow, cu.m./hr :    

4.7.     Total cooling surface area, sq.m. :    

4.8.     Material of construction (Indicate specific codes /standard)    

4.8.1.      Tubes :    

4.8.2.      Fins :    

4.8.3.      Header :    

5.   Cooling Fan    

5.1.     Type :    

5.2.     Number :    

5.3.     Location :    

5.4.     Capacity of each fan, N.cu.m/hr :    

5.5.     Power installed for each fan, kW :    

5.6.     Maximum power consumption of cooling air fan at MCR of     

  generator at rated operating condition, kW :  

 

5.7.     Fan speed, r.p.m. :    

5.8.     Total cooling surface area, sq.m. :    

5.9.     Material of construction (Indicate applicable codes/standards)    

6.   Total cooling water required per engine, Cu.M/Hr :    

7.   Cooling water make up required per engine, Cu.M/Hr (To be provided by the owner):  

 

8.   Total auxiliary power supply required for the cooling system: KVA/Amps/Voltage 

 

 

Annex‐A242  

K.4.2. TECHNICALFORM:EXHAUSTSYSTEMNo  Description  Contractor  

Propose/Remarks 

1.   General Information    

1.1.     Type :    

1.2.     Exhaust manifold Flow Rate, at 100 % load, kg/hr. :   

1.3.     Exhaust manifold Temperature, at 100 % load, Deg. C :   

1.4.     Exhaust manifold pressure, kg/sq.cm. :    

1.5.     Exhaust manifold temperature, Deg. C :    

1.6.     Maximum allowable temperature difference from two cylinders, Deg.C :  

 

2.   Silencer    

2.1.     Type :    

2.2.     Maximum noise attenuation, at 1 m distance, db:    

2.3.     Material of construction :    

2.4.     Diameter, mm :    

2.5.     Spark arrester, Yes/No :    

3.   Stack    

3.1.     Diameter, mm :    

3.2.     Height, m :    

3.3.     Material of construction :    

3.3.1.   Body   

3.3.2.   Insulation material and thickness   

3.4.     Whether rain protection cowl provided : Yes/No    

3.5.     Lightening arrester provided? : Yes/No    

3.6.     Weight   

4.   Increasing the height of four existing stacks   

4.1.     Diameter, mm :    

4.2.     Section Height, m :    

4.3.     Material of construction :    

4.4.     Lightening arrester? : Yes/No    

4.5.     Additional section Weight   

 

 

 

Annex‐A243  

K.4.3. TECHNICALFORM:GENSETUNIT1. Generator Description: 

Manufacturer:  

Model Number:  

2. Prime Mover Description: Diesel Engine for dual fuel operation, namely both, light fuel oil #2 and natural gas.  

Manufacturer:   

Model Number:  

Unit Description and Technology: 

No  Description  Contractor  Propose/Remarks 

PF  Rated Power Factor    

Un  Rated Voltage [kV]   

Fn  Rated Frequency [Hz]   

Pmax  Maximum generating capacity of Prime Mover  [MW]   

Pmin  Minimum generating power of  Prime Mover  [MW]   

Paux  Total auxiliary power load demand [MW]   

n‐g   Rated Generator Shaft Speed [rpm]   

n‐gt   Rated Prime Mover Shaft Speed [rpm]   

p   Number of Poles Pairs   

  Moment of inertia of Generator  [kgm2]                     

I  Moment of inertia of Prime Mover [kgm2]   

  Moment of inertia of Gearbox and Coupling (if exists) [kgm2]   

H   Total Inertia Constant (Generator, Prime mover, etc.) [MWs/MVA]   

Xd  Direct Axis Synchronous Reactance [pu] saturated   

unsaturated   

Xq  Quadrature Axis Synchronous Reactance [pu] saturated   

unsaturated   

Xd’  Direct Axis Synchronous Reactance [pu] saturated   

unsaturated   

Xq’  Quadrature Axis Synchronous Reactance [pu] saturated   

unsaturated   

Xd”  Direct Axis Synchronous Reactance [pu] saturated   

unsaturated  no less than 0.2pu 

Xq”  Quadrature Axis Synchronous Reactance [pu] saturated   

unsaturated   

Annex‐A244  

No  Description  Contractor  Propose/Remarks 

Xl  Stator Leakage Reactance [pu]   

Tdo'   Direct Axis Transient Open Circuit Time Constant [sec] at ___oC   

Tqo'  Quadrature Axis Transient Open Circuit Time Constant [sec] at ___oC   

Tdo"  Direct Axis Subtransient Open Circuit Time Constant [sec] at ___oC   

Tqo"  Quadrature Axis Subtransient Open Circuit Constant [sec] at ___oC   

Td'  Direct Axis Transient Time Constant [sec] at ___oC   

Tq'  Quadrature Axis Transient Time Constant [sec] at ___oC   

Td"  Direct Axis Subtransient Time Constant [sec] at ___oC   

Tq"  Quadrature Axis Subtransient Time Constant [sec] at ___oC   

Ta  Stator Time Constant [sec] at ___oC   

Ra  Stator Resistance [ohm] at ___oC   

Rf  Field Winding Resistance [ohm] at ___oC   

R0  Zero Sequence Resistance [ohm] at ___oC   

X0  Zero Sequence Reactance [pu]   

R(damp)  Dampers Resistance [ohm] at ___oC   

L(damp)  Dampers Inductance [H]   

R2  Negative Sequence Resistance [ohm] at ___oC   

X2  Negative Sequence Reactance [pu]   

Cph  Phase earth capacitance [µF]   

XP  Potier reactance [pu]   

SCR  Short Circuit Ratio    

S  Saturation Factors:  ‐ S(1.0)   

    ‐ S(1.2)   

1  Continuous unbalanced load, maximum    I2∞  [pu]   

2  Short time capability for unbal. faults, max.  I22 *t [pu]*s   

3  Voltage increase at sudden load rejection and rated cosφ = 0.85 

(without AVR action) [%] 

 

4  Voltage increase at sudden load rejection and rated cosφ = 1 

(without AVR action) [%] 

 

5  3‐phase short‐circuit current (peak value) [kA]   

6  3‐phase short‐circuit current (RMS value) [kA]   

   

Annex‐A245  

No  Description  Contractor  Propose/Remarks 

  Generator diagrams:   

1  Calculated Capability Curve P‐Q   

2  Generator Power versus Ambient Temperature Curve   

3  Saturation Curves (Air Gap Line, No Load Saturation, SC Saturation)   

4  Unbalanced load curves   

5  Generator Losses curves   

5  Generator Efficiency curves   

6  V ‐ Curves   

7  Excitation System 

Block Diagram: Excitation system block diagram and parameters values, preferably in accordance with one of the commonly used transient‐midterm‐longterm stability computer programs, such as PSS/E (PTI). 

 

 

8  Turbine and Speed Governor 

Block  Diagram:  Turbine  and  Speed  Governor  system  block  diagram  and 

parameters values, preferably in accordance with one of the commonly used 

stability computer programs, such as PSS/E (PTI). 

 

9  Power Stabilizer System   : Block Diagram: Stabilizer block diagram and parameters values, preferably in accordance with one of the commonly used stability computer programs, such as PSS/E (PTI). 

 

10  Additional Models 

Block  diagrams  and  parameters  values  for  additional models,  such  as  for 

Minimum  Excitation  Limiter,  Maximum  Excitation  Limiter,  preferably  in 

accordance with  one  of  the  commonly  used  stability  computer  programs, 

such as PSS/E (PTI). 

 

 

 

 

Annex‐A246  

K.5. EquipmentQuestionnaireThe “required” column in the tables (if used) displays minimum requirements. 

The bidder must fill all data in the “offered” column displaying equal or better properties to the required 

K.5.1. StepupMVtransformer 

Power Transformer:  Manufacturer Data/Remarks 

Manufacturer/country   

Power rating based on the temperature conditions indicated in the spec. 

 

Transformer rated power :   

ONAN (MVA) at 55C rise   

ONAF (MVA) at 55C rise    

ONAN (MVA) at 65C rise   

ONAF (MVA) at 65C rise   

Is the transformer capable of operating at these ratings 

(65C) continuously without loss of life? ......................(yes or no) 

 

 

   

Annex‐A247  

 

Tap‐changer:  Manufacturer Data/Remarks 

At principal tap (kV/kV)   

At maximum tap (kV/kV)   

At minimum tap (kV/kV)   

Number of taps above principal (‐%Tap)   

Number of taps below principal (+%Tap)   

Taps position mechanical indication   

 

 

Impedance:  

Positive sequence 

Zero sequence 

Measured between high voltage (22kV) and low voltage winding 11kV) terminals (%) 

   

Impedance for extreme positions of tap‐changer 

Max. tap (%) 

Min. tap (%) 

Tolerance (+%) 

   

 

Bushing current transformer  Bushing  CTs for thermal image 

Bushing  CT for LV Neutral 

Overload capability of the bushings:     

Maximum permissible overload  of the bushing CTs (A) 

   

The bushing CTs hottest‐spot temperature, above the temperature of the immersion medium in overload conditions (C) 

   

Duration (s)     

Temperature rise of the hottest spot of the current carrying parts, above the temperature of the immersion medium in rated conditions(C) 

   

Rated short‐time current 1 sec. (kA)     

Rated short‐time current 2 sec. (kA)     

Dynamic short‐circuit withstand current (kA) 

   

 

   

Annex‐A248  

 

Insulation:  Offered 

Insulation levels of winding dielectric test: 

High voltage winding 

Low voltage neutral terminal 

Low voltage winding 

Insulation class (kV)       

Rated withstand voltage of the windings 

     

Rated lightning impulse withstand 

voltage 1.2/50 sec (kV peak)      

Rated short duration power frequency withstand voltage (kV rms) 

     

 

Dielectric strength:  

High voltage   Low voltage  

Lightning impulse test     

Full impulse wave test voltage (kV peak)     

Full chopped impulse wave test voltage (kV peak) 

   

Minimum time to copping (sec)     

Full impulse wave test voltage for neutral terminal (kV peak) 

   

Separate source voltage withstand test (kV rms) 

   

Induced voltage test (kV rms)      

   

Annex‐A249  

 

Subject: (MVA base shall be revised according to proposed generator ratings) 

Manufacturer Data/Remarks 

Losses (guaranteed):   

No load loss (excitation loss)   

Load loss (at 10MVA):   

At principal tap (kW)   

At maximum tap (kW)   

At minimum tap (kW)   

Total loss excluding auxiliary power at 10MVA (no load plus load loss with 10MVA loading of the low voltage winding at principal tap (kW) 

 

Auxiliary power (total requirements for future cooling):   

At 10 MVA (guaranteed) (kW)   

At 7 MVA (kW)   

Guaranteed efficiency (not including power for cooling) at 0.85 power factor and  22/11kV: 

 

Full load (10MVA) (%)   

3/4 LOAD (%)   

1/2 LOAD (%)   

1/4 LOAD (%)   

Guaranteed regulation (H winding to X winding with rated MVA on X winding 

 

Unity power factor (%)   

0.8 power factor (%)   

Exciting current (guaranteed) ‐ referred to 10MVA   

Inrush RMS magnetizing current with no residual magnetism at 11.5kV (times full load current) 

 

Permissible short‐time power frequency over‐voltage of the transformer, at no‐load, stating from full‐load temperature: 

 

At 135% over‐voltage 

sec 

 

At 130% over‐voltage 

sec 

 

At 125% over‐voltage 

sec 

 

   

Annex‐A250  

 

Subject: (MVA base shall be revised according to proposed generator ratings) 

Manufacturer Data/Remarks 

At 120% over‐voltage 

Sec 

 

At 115% over‐voltage 

min 

 

At 110% over‐voltage 

min 

 

High voltage winding (ohms)   

Low voltage winding (ohms)   

Temperature rise at 10MVA of:   

Winding (guaranteed) measured by resistance (C)   

Hottest spot (C)   

Top of oil (C)   

Per cent capacity reduction with one cooler out of service (%)   

Estimated time that transformer can carry full load, without damage, with fans out of service under the following conditions: 

Starting cold (hours) 

After operating continuously at full load (hours) 

 

Average sound level according to NEMA at 22kV:   

Immediately near the transformer (dBA)   

50 Meters from the transformer (dBA)   

100 Meters from the transformer (dBA)   

Average sound level according to NEMA at 22kV when operating at no load (11MVA) with cooing in operating: 

 

Immediately near the transformer (dBA)   

50 Meters from the transformer (dBA)   

100 Meters from the transformer (dBA)   

 

   

Annex‐A251  

 

K.5.2. TECHNICALFORMMV1600/400kVAtransformersinformation

Description  Manufacturer Data/Remarks 

Manufacturer   

Country of origin   

Performance Data:   

Transformer rated power at 55C  rise (KVA):   

Transformer rated power at 60C rise for continuous operation without loss of life (kVA): 

 

Highest primary system voltage (kV)   

System primary neutral   

System secondary neutral   

Transformer connection group   

Rated voltage of primary winding (kV)   

Rated voltage of secondary winding (kV)   

Rated lightning impulse withstands voltage.   

Sound pressure levels at 1m   

K factor   

Short circuit impedance voltage:    

Uk%   

Ur%   

Ux%   

Load losses: (kW)   

   

Annex‐A252  

Description  Manufacturer Data/Remarks 

No load losses: (kW)   

Oil:   

Oil Type   

Oil igniting temperature (C)   

OFF load tap‐changer:  

Full capacity is required for the entire range of voltage 

regulation 

 

Number of taps   

Voltage range (%)    

Rated step voltage (kV)   

At principal tap (‘O’ position), transformer ratio shall be:   

Bushings and terminals:   

Nominal voltage for HV plug‐in bushing   

Rated withstand voltage for HV plug‐in bushing kV    

Rated lighting impulse withstand peak voltage(BIL)   

Creepage distance LV side: (mm)   

Air clearance to earth LV side: (mm   

Maximum permissible overload of the HV bushing (A)   

Maximum permissible overload of the LV bushing (A)   

The bushing hottest‐spot temperature, above the 

temperature of the immersion medium in overload 

conditions (C) 

 

Temperature rise of the hottest spot of the current 

carrying parts, above the temperature of the immersion 

medium in rated conditions(C) 

 

Annex‐A253  

Description  Manufacturer Data/Remarks 

Temperature rise of HV current carrying parts during 

short‐circuit (1 sec. with rated short time current (C)  

Temperature rise of LV current carrying parts during 

short‐circuit (1 sec. with rated short time current (C)  

Diameter of the HV conductor (mm)   

Diameter of the LV conductor (mm)   

Cross sectional area of the MV conductor (mm2)   

Cross sectional area of the LV conductor (mm2)   

Dimensions and weights:   

Total weight (Kg)   

Oil weight (Kg)   

Dimensions: W x H x D (Max)   

Skid type   

 

   

Annex‐A254  

K.5.3. TECHICALFORM:NEUTRALGROUNDINGRESISTOR

No  DATA  OFFERED 

1.   General    

1.1.   Applicable standard   

1.2.   Service    

1.3.   Rated system Voltage  & allowable variation   

1.4.   Rated frequency and  allowable variation   

2.   Rating   

2.1.   Rated Voltage KV   

2.2.   Rated current at rated time duration Amp  500A 

2.3.   Rated time duration Sec.  15 

2.4.   Resistance in design ambient temp. Ohm   

2.5.   Allowable Tolerance in resistance value%   

2.6.   Design ambient Temperature ° C   

2.7.   Maximum permissible temperature  rise of resistor 

°C  

 

2.8.   Temp rise of Enclosure °C   

2.9.   Basic Insulation level and system insulation class  

2.9.1.   System insulation class for   line end & ground end 

KVrms  

 

2.9.2.   Insulation level (applied 1min. power frequency 

potential) KVrms  

 

3.   NGR  

3.1.   Materials of resistor   

3.2.   Enclosure material   

3.3.   Min. Thickness of aluminum sheet mm   

3.4.   Enclosure protection class   

3.5.   Finish paint of    

3.5.1.   Interior    

3.5.2.   Exterior    

3.6.   Terminal arrangement   

3.7.   Type & size of cable to be terminated   

4.   Insulators   

4.1.   Type    

4.2.   Materials    

4.3.   Bushing rating KVrms   

4.4.   Creepage distance mm   

Annex‐A255  

K.5.4. TECHNICALFORM:22Kv‐MVenclosure

    Required  Offered 

1.   Manufacturer  ‐   

2.   Country of production  ‐   

3.   Production quality supervision  ISO 9002   

4.   Prototype tested at (laboratory name 

and date of test) 

 

ISO 9002 

 

5.   Dimensions (maximum) 

Height (cm) 

Width (cm) 

Depth (cm) 

 

 

 

6.   Bus Bars ‐ type 

material 

Current (In) 

Short circuit capacity 

Insulated 

copper 

2000A 

25kA 

 

7.   Back and front access doors with 

handle and padlock attachment 

(Yes/No) 

   

8.   Control selector switch with visual 

switching position indicator 

   

9.   R.S.T indication lamps with capacitor 

(Yes/No) 

   

10.   Emergency push button type     

11.   Heating elements, quantity, capacity 

and type 

   

12.   Enclosure lighting PL9/IP44 limit 

switch operated type 

   

Annex‐A256  

    Required  Offered 

13.   Control relays     

14.   Indication lamps 22 mm diameter, 

manufacturer and type 

   

15.   Control terminals     

16.   Miniature circuit breakers (10KA)     

17.   Timers (manufacturer and type)     

18.   Mimic diagram ‐ colored Aluminum 

strips and figures (Yes/No) 

   

19.   Current/voltage/power, power factor 

4‐20mA converters (manufacturer and 

type) 

   

20.   Pressure release upper vent (Yes/No)     

21.   Local measuring instruments for 

current, voltage and power factor 

96X96mm (manufacturer and type) 

   

22.   Rated voltage  24kV   

23.   Insulation 

1 min/50Hz/kV RMS 

50kV   

24.   Peak insulation level 1.2/50s  125kV   

25.   Short time withstand current (3sec)  25kA RMS   

26.   Peak withstand current  63kA   

 

   

Annex‐A257  

K.5.5. TECHNICALFORM:11Kv‐MVenclosure    Required  Offered 

1.   Manufacturer  ‐   

2.   Country of production  ‐   

3.   Production quality supervision  ISO 9002   

4.   Prototype tested at (laboratory name 

and date of test) 

 

ISO 9002 

 

5.   Dimensions (maximum) 

Height (cm) 

Width (cm) 

Depth (cm) 

 

240 

100 

200 

 

6.   Bus Bars ‐ type  

material 

Current (In) 

Short circuit capacity 

Insulated 

copper 

2000A 

31.5kA 

 

7.   Back and front access doors with 

handle and padlock attachment 

(Yes/No) 

   

8.   Control selector switch with visual 

switching position indicator 

   

9.   R.S.T indication lamps with capacitor 

(Yes/No) 

   

10.   Emergency push button type     

11.   Heating elements, quantity, capacity 

and type 

   

12.   Enclosure lighting PL9/IP44 limit 

switch operated type 

   

13.        

Annex‐A258  

    Required  Offered 

14.   Indication lamps 22 mm diameter, 

manufacturer and type 

   

15.   Control terminals     

16.   Miniature circuit breakers (10KA)     

17.   Timers (manufacturer and type)     

18.   Mimic diagram ‐ coloured Aluminum 

strips and figures (Yes/No) 

   

19.   Current/voltage/power, power factor 

4‐20mA converters (manufacturer and 

type) 

   

20.   Pressure release upper vent (Yes/No)     

21.   Local measuring instruments for 

current, voltage and power factor 

96X96mm (manufacturer and type) 

   

22.   Surface treatment 

‐ Outside panels acc. to (galvanized + 

epoxy polyester coating) 

‐ Internal partitions 

 

 

IEC 60068‐2‐11 

Galvanized with 

chrome passivation 

 

23.   Rated voltage  12kV   

24.   Insulation  

1 min/50Hz/kV RMS 

28kV   

25.   Peak insulation level 1.2/50s  75kV   

26.   Short time withstand current (3sec)  31.5kA RMS   

27.   Peak withstand current  80kA   

 

   

Annex‐A259  

K.5.6. TECHNICALFORM:MVCircuitBreaker  Description   REQUIRED          OFFERED 

    12 kV  22kV

1.   Manufacturer   

2.   Type  

3.   Rated voltage (kV) 12/24  

4.   Rated insulation level:  

5.   Impulse withstand 

voltage: 

‐ to earth, between 

poles and across open 

switchgear device (kV) 

‐ across the isolating 

distance (kV) 

 

6.   One‐minute power 

frequency withstand 

voltage: 

‐ to earth, between 

poles and across open 

switching device (kV) 

‐ across the isolating 

distance (kV) 

 

7.   Rated frequency (Hz) 50  

8.   Rated current of main 

22kV breakers (A) 

2000A ‐  

9.   Rated current  of 

secondary 22kV  

breakers                    (A)   

800A ‐  

Annex‐A260  

  Description   REQUIRED          OFFERED 

    12 kV  22kV

10.   Rated current of main 

12kV breakers (A) 

2000A ‐ 

11.   Rated current of 

secondary 12kV 

breakers 

1600A ‐ 

12.   Rated short time 

withstand current Ith       

(kA/3 sec) 

 

13.   Rated peak withstand 

current (kA) 

 

14.   Rated breaking capacity  

15.   At 12kV (KA)  31.5 ‐ 

16.   At 24kV (KA)  25 ‐  

17.   Note: with operating 

sequence 0‐3min‐co‐

3min‐co and 0‐0.35‐co‐

15S‐co 

 

18.   Rated short circuit 

making capacity (kA) 

 

19.   Rated breaking 

capacities for on‐load 

isolator 

 

20.   SF6 gas:   

21.   Rated filling pressure  

22.   Minimum functional 

pressure 

 

Annex‐A261  

  Description   REQUIRED          OFFERED 

    12 kV  22kV

23.   Volume of gas used in 

the SF6 switchgear 

 

24.   Internal fault withstand 

for 1 sec (kA) 

 

25.   Maximum permissible 

partial discharge 

quantity at 1.1 Un (pC) 

 

26.   Technical 

characteristics for 

motor drive: 

 

27.   Rated voltage (V)  220VDC  

28.   Maximum continuous 

current (A) 

 

29.   Maximum inrush 

current (A) for a 

maximum duration of 

(sec) 

 

30.   Maximum no. of 

operations (close‐open) 

(no.) 

 

31.   Quality assurance 

system 

ISO 9001  

32.   Standard   

33.   Operating time   

34.   Opening time (msec)  

35.   Arcing time (msec)  

36.   Break time (msec)  

Annex‐A262  

  Description   REQUIRED          OFFERED 

    12 kV  22kV

37.   Closing time (msec)  

38.   Gas  

39.   Rated pressure at 20C (kPa) 

 

40.   Number of gas pressure 

indication lamps 

3  

41.   Operating mechanism  

42.   Removable manual 

spring charging lever 

(yes/no) 

 

43.   Manual closing push 

button (yes/no) 

 

44.   Manual opening push 

button (yes/no) 

 

45.   Key lock/interlock 

(yes/no) 

 

46.   Indicator lamp for 

ON/OFF positions 

(yes/no) 

 

47.   Value for SF6 gas filling 

(yes/no) 

 

48.   Indicator for 

charged/discharged 

spring condition 

 

49.   Operation counter  Y/N

50.   Breaker enclosure  

Annex‐A263  

  Description   REQUIRED          OFFERED 

    12 kV  22kV

51.   Compliance with  IEC 60298  

52.   C.B racking in/out with 

door closed (yes/or) 

 

53.   Automatically operated 

metallic shutters 

(yes/no) 

 

54.   Number of definite 

positions 

(inserted/isolated/ 

withdrawn) 

3  

55.   Auxiliaries:   

56.   Shunt closing release Y/N

57.   Locking magnet 

(yes/no) 

 

58.   Shunt opening release Y/N

59.   Free auxiliary contacts 

for low gas pressure 

number and rating 

 

60.   Free auxiliary contacts 

for charged spring, 

condition (yes/no) 

number and rating 

 

61.   Ten free auxiliary 

contacts for CB 

switching condition 

(rating and number) 

 

Annex‐A264  

  Description   REQUIRED          OFFERED 

    12 kV  22kV

62.   Free auxiliary contacts 

for “connected” and 

“isolated” positions 

(rating and number) 

 

63.   Locking magnet on 

truck 

Y/N

64.   Racking out handle 

(yes/no) 

 

65.   Foot controlled lock Y/N

66.   Padlock device for open 

position 

Y/N

 

 

Annex‐A265  

K.5.7. TECHNICALFORM:MVCurrentTransformers    Required  Offered 

1.   Manufacturer/type     

2.   Country     

3.   Copper     

4.   Hot cast insulating resin under vacuum (yes/or) 

   

5.   Core materials 

‐ Nickel iron (75% NI) for measuring cores 

‐ mill patterned cold rolled silicon iron for protection  cores 

  yes/no 

6.   Standard: IEC 185 (1987)    yes/no 

7.   Insulation level: 

for 11kV systems 

for 22kV systems 

 

17.5kV 

24kV 

 

8.   Insulation Impulse test (BIL) 

‐ for 11kV C.T 

‐ for 24kV C.T 

 

 

95kV 

125kV 

 

9.   Current error for class 5P at rated primary current 

1%   

10.   Composite error at error limit factor 

5%   

11.   Terminal identification and information on name plate 

  yes/no 

12.   Dielectric routine tests    yes/no 

13.   Inter‐turn test    yes/no 

14.   Accuracy tests    yes/no 

15.   Partial discharge test    yes/no 

16.   Polarity test    yes/no 

17.   Type tests    yes/no 

 

   

Annex‐A266  

K.5.8. MVPotentialTransformers    required  offered 

C.1  Manufacturer/type     

C.2  Country     

C.3  Hot cast insulating resin under vacuum 

  yes/no 

C.4  Standard  IEC   

C.5  Voltage factor for line to ground units 

‐ for grounded neutral  

‐ for impedance neutral 

 

 

1.5Un‐30sec 

1.9Un‐30sec. 

 

C.6  Voltage factor for line to line units (conditions) 

1.2Un   

C.7  Insulation Impulse test (BIL) 

‐ for 11kV P.T 

‐ for 24kV P.T 

 

 

95kV 

125kV