Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
ANNEX A: GPWG Annual Report 2009, Consolidated Report Data*
*The information is supplied on a national basis in a format appropriate to each country
2
Australia1
Country of
Project
Project Description Project Status: Milestones, Implementation
Comments
Funds Committed
e.g.(July 2002 –
June 2007)
Funds Expended
e.g. (July 2002 –
June 2007)
Russia Japanese-Russian program to
dismantle nuclear submarines
Dismantlement completed (AUD$10 million) All funds have been
fully expended
1 Updated on April 2009
3
Canada
Country
of
Project
Project Description Project Status: Milestones, Implementation Comments Funds
Committed
(June 2002 to
May 2009) in
000's
Funds
Expended
(June 2002 to
March 31
2009)
in 000’s
Total Ten Year GP Pledge & Total Approximate Spending (out of $C 1,000,000,000) $C 623,228.1 C$516,487.4
Chemical Weapons Destruction
Russia Chemical Weapons Destruction:
Railway Construction at the
Shchuch'ye Chemical Weapons
Destruction Facility.
Canada provided C$33M for the construction of an 18km railway at the
Shchuch'ye CWDF, through the UK's bilateral Agreement with Russia.
The construction of the bridge across the Miass River, supported by a
US$1M contribution from the Nuclear Threat Initiative, was completed in
August 2007. Construction of the railway was completed in November
2008.
$C 33,000.0 $C 33,000.0
Russia Chemical Weapons Destruction:
support for key industrial
infrastructure projects at the
Shchuch'ye Chemical Weapons
Destruction Facility.
Canada committed up to C$10M for key industrial projects at the
Shchuch'ye CWDF, including the construction of intersite
communications, which was completed in October 2007, and a local
warning system, which was completed in September 2008.
$C 10,000.0 $C 9,250.0
Russia Chemical Weapons Destruction:
provision of equipment for the second
main destruction building at the
Shchuch'ye Chemical Weapons
Destruction Facility.
C$55M purchased Russian-built equipment needed to destroy nerve agent
munitions within the second main destruction building (MDB2) at the
Shchuch'ye CWDF. The majority of the equipment was delivered in 2007
and 2008 with two outstanding items to be delivered in 2009.
$C 55,000.0 $C 54,608.0
Russia Chemical Weapons Destruction:
provision of equipment for the two
main destruction buildings at the
Kizner Chemical Weapons Destruction
Facility
Work is underway to provide assistance at the Kizner CWDF, pursuant to
a C$100M commitment made by the Prime Minister of Canada at the St.
Petersburg G8 Summit in 2006. Given that the two million munitions at
Kizner are similar to those stored at Shchuch‘ye, Canada is providing
similar destruction equipment for the two main destruction buildings. A
contract for the supply of catalytic reactors was signed in December 2008
and a second major contract for the supply of two metal parts furnaces and
auxiliary equipment was signed in February 2009.
$C 100,000.0 $C 11,784.7
4
Russia Chemical Weapons Destruction:
support to Green Cross International to
establish and operate the Izhevsk
Public Information and Outreach
Office.
The Green Cross Public Outreach office in Izhevsk was established to
increase awareness about Russian plans and programs to destroy nerve
agent stockpiles at the nearby Kizner chemical weapons storage facility.
The office opened in June 2005 and in 2009, Canada provided its fifth
annual contribution of (US$150,000).
$C 492.0 $C 679.4
Chemical Weapons Destruction: Other
Project-Related Expenses
$C 1,280.4
Nuclear submarine dismantlement and spent fuel management
Russia Nuclear submarine dismantlement:
support for dismantlement of a further
2 decommissioned nuclear-powered
submarines (NPS) and the defuelling
of a strategic ballistic missile
submarine (SSBN).
In NW Russia: Canada fulfilled its commitment to dismantle 12
submarines by fully dismantling 11 Victor Class NPS and partnered with
the US and Russia by defuelling a 12th,
a Typhoon Class SSBN (24
reactors de-fuelled by 31 March 2008). By the end of FY 2009/10,
Canada will have fully dismantled two more Yankee Class NPS and
defuelled another SSBN, this time from the Delta III Class.
$C 135,671.7
$C 117,844.9
Russia Nuclear submarine dismantlement:
support for the EBRD Northern
Dimension Environmental Partnership
(NDEP).
Canada contributed C$32M to the EBRD-NDEP in FY03/04 to assist in
the remediation of the nuclear legacy in NW Russia.
$C 32,000.0 $C 32,000.0
Russia Current Projects Design and survey work for projects in Far East Russia has been
completed. Execution has commenced on projects to defuel 10 submarine
reactors and the full dismantlement of two submarines.
$C 30,130.8 $C 10,448.2
Nuclear submarine dismantlement:
Other Project-Related Expenses
$C 8,063.2
Nuclear and Radiological Security
Russia Nuclear and Radiological Security:
Projects to strengthen the physical
protection of facilities that house
nuclear material, including materials
destined for eventual disposition.
Canada is involved in physical protection upgrade projects at seven
Russian nuclear facilities, and is developing several additional projects.
$C 41,446.3 $C 41,202.7
Russia Nuclear and Radiological Security:
Projects to strengthen the security of
nuclear material during transportation.
Canada is involved in four transportation security physical protection
upgrades projects. Involving the provision of special cargo trucks and
railcars to help ensure the safe and secure transportation of nuclear
materials between Russian nuclear facilities.
$C 17,424.6 $C 17,424.7
5
Russia Nuclear and Radiological Security:
support to US DOE-led Elimination of
Weapons-Grade Plutonium Production
program.
Canada's contribution to the US-led project to shutdown the last Russian
weapons-grade plutonium production reactor was completed in June
2007.
$C 9,000.0 $C 9,000.0
FSU Nuclear and Radiological Security:
IAEA projects to strengthen nuclear
and radiological security.
Canadian funding was used to support important physical protection
upgrades and training projects, as well as projects to enhance capabilities
to prevent the illicit trafficking of nuclear and other radioactive materials.
$C 11,089.0 $C 11,049.2
Russia Nuclear and Radiological Security:
Projects to secure highly radioactive
sources (RTGs) and infrastructure
support for removal and securing of
RTGs
Canada funded the manufacturing of transportation and securing shielding
containers for safe and secure transportation of RTGs. This project was
completed in June 2007.
$C 1,260.0 $C 1,259.9
Russia Nuclear and Radiological Security:
Remove secure and replace RTGs.
In cooperation with the US Dept. of Energy, Canada removed 20 RTGs
along the northern sea route in the Russian Arctic. They will be
disassembled and replaced by solar panels by the end of summer 2009.
Additional contribution of C$5 million was made for a similar project in
Russia‘s Far East.
$C 9,000.0 $C 9,000.0
Ukraine Nuclear and Radiological Security:
Prevention of illicit trafficking.
In cooperation with US Dept. of Energy, Canada funded upgrades to key
border crossings, to help prevent the illicit trafficking of nuclear materials
$C 9,825.0 $C 9,825.00
Ukraine Nuclear and Radiological Security:
European Bank for Reconstruction and
Development (EBRD) Chernobyl
Projects
Responsibility for the EBRD Chornobyl Projects was transferred to the
Global Partnership Program in 2004. In April 2006, Canada announced a
C$8M additional contribution. In FY 08/09, a C$5M contribution was
donated to the EBRD ―Nuclear Safety Fund‖ in accordance with Canada‘s
traditional cost-sharing burden of 5%. During FY 09/10, a further C$5M
has been pledged and will be donated to the EBRD ―Chernobyl Shelter
Fund‖, again in accordance with Canada‘s cost-sharing percentage.
$C 13,000.0 $C 13,000.0
Nuclear and Radiological Security:
securing radiological materials
NRS hosted the Global Initiative to Combat Nuclear Terrorism (GICNT)
seminar on securing radiological sources (Ottawa, June 2008).
$C 16.8 $C 16.8
Nuclear and Radiological Security:
Other Project-Related Expenses –
Chernobyl Projects
$C 28.1
Nuclear and Radiological Security:
Other Project-Related Expenses
$C 7,753.1
6
Redirection of Former Weapons Scientists
Russia
and
FSU
Redirection of Former Weapons
Scientists: International Science and
Technology Center (ISTC)
Canada acceded to the ISTC in March 2004 and contributed $C64,340.3
toward efforts to redirect former weapons scientists, including funding of
115 projects involving the redirection of over 2720 former weapons
scientists and several sustainability-driven supplemental programs.
Intensive efforts continued to identify additional Canadian partners and
collaborators to work on projects with former weapons scientists.
$C 64,340.3 $C 64,340.3
FSU
Ukraine
Redirection of Former Weapons
Scientists: Science and Technology
Center in Ukraine (STCU)
Canada acceded to the STCU in April 2006 and has contributed
$C7,431.6 toward efforts to redirect former weapons scientists, including
funding of 47 projects involving the redirection of over 150 former
weapons scientists and several sustainability-driven supplemental
programs. Intensive efforts continued to identify additional Canadian
partners and collaborators to work on projects with former weapons
scientists.
$C 7,431.6 $C 7,232.9
Redirection of Former Weapons
Scientists: Other Project-Related
Expenses
$C 2003.1
Biological Non-Proliferation
Russia
and FSU
Redirection of Former Weapons
Scientists
Biological redirection projects funded through the ISTC (a total of 33
projects to date) and the STCU.
**
Russia
and FSU
Biosafety, Biosecurity and Biological
Non-Proliferation
A GPP Biosecurity and Biosafety Strategy focuses on:
-Guidelines: Developing and implementing national biosecurity and
biosafety standards and related legislation
-Training: Biosecurity and biosafety training which includes workshops
reference materials, tools and the establishment of regional training
centers (in Russia, Ukraine and Kazkhstan).
-Associations: Providing assistance to engage with the international
biosecurity/biosafety community and to establish national and/or regional
biosafety associations (including a new Biosafety Association for Central
Asia and the Caucasus).
- Strengthening export controls and multilateral Non-Proliferation /Arms
Control and Disarmament instruments (e.g. BTWC)
$C 3,1 $C 3,108
7
Kyrgyz
Republic
Infrastructure Improvements Canada is assisting the Government of the Kyrgyz Republic to enhance
biosecurity, biosafety, and biocontainment capabilities in the Kyrgyz
Republic, including through the design, construction, commissioning and
start-up of a new human & animal health facility in Bishkek. The new
laboratory will serve as the central repository for the consolidation of
dangerous pathogens from several existing, vulnerable facilities in the
Kyrgyz Republic. As the design and construction of the new lab will
take several years, Canada is implementing interim security upgrades at 3
existing biological facilities in 2009.
$C 40,000.0 $C 3,056
Biological Non-Proliferation: Other
Project-Related Expenses
$C 2,232.8
General GP Projects
Other Operating Costs $C 3612.8
Outreach and Support $C 109.7
8
Czech Republic
Country of
Project Multilateral Initiatives Funds Committed
Funds Expended
Russia 2007 Chemical Weapons
Destruction
Shchuch'ye chemical weapons destruction site (UK project); the
same amount of funds has been extended annually since 2003
CZK 2 000. 000
CZK 2 000. 000
Ukraine 2004 Nuclear Security IAEA Nuclear Security Fund: ―Strengthening Security of Nuclear
Materials‖ (IAEA project UKR/0/008)
CZK 1 000.000
CZK 1 000.000
Ukraine Nuclear Safety IAEA Programme of Technical Cooperation ―Action Plans for
Nuclear Power Plant Lifetime Management‖ IAEA Project
UKR/4/013
10 685 000,- CZK
(2004-2008)
10 685 000,- CZK
(2004-2008)
Armenia
Physical Protection IAEA Nuclear Security Fund: ―Improvement in the Physical
Protection System at the Armenian Nuclear Power Plant‖ (IAEA
project ARM/9/017)
CZK 1 500.000
(2006)
CZK 1 500.000
(2006)
Armenia Nuclear Safety IAEA Programme of Technical Cooperation ―Improvement of
Design Safety of the Armenian NPP‖ ARM/9/016
8 400 000,- CZK
(2005-2008)
8 400 000,- CZK
(2005-2008)
Armenia Nuclear Safety Strengthening of In-Service Inspection through Modern Non-
Destructive Testing Methods‖ IAEA Project ARM/4/004
1 450 000,- CZK
(2004)
1 450 000,- CZK
(2004)
Moldova Nuclear Security IAEA Nuclear Security Fund - strengthening security of radiation
sources and nuclear facilities in Moldova
1 000 000,- CZK 1 000 000,- CZK
Serbia Repatriation of Spent
Fuel
IAEA TC RER/4/028 Repatriation of spent fuel from Vinca RA
research reactor
18 000 000,- CZK
(2008-2010)
6 000 000,- CZK
(2008)
Kyrgyzstan Monitoring Establishment of a Radio-ecological Monitoring and Assessment
Network – IAEA TC Project KIG/9/003
1 400 000,- CZK
(2008)
1 400 000,- CZK
(2008)
Tajikistan,
Kyrgyzstan Radiation Protection Upgrading Radiation Protection Infrastructure in Eastern Europe and
Central Asia – IAEA TC Project RER/9/079
1 220 000,- CZK
(2005-2006)
1 220 000,- CZK
(2005-2006)
Mexico Incident Management Human Resource Development and Nuclear Technology Support –
IAEA TC Project MEX/0/014
350 000,- CZK
(2005)
350 000,- CZK
(2005)
Bosnia and
Herzegovina Sources Management ―Strengthening National Capabilities in Radiation, Waste and
Transport Safety in the Mediterranean Region‖ – IAEA Project
RER/9/080
500 000,- CZK
(2005)
500 000,- CZK
(2005)
9
European Union
Overview of EU Council Joint Actions and Council Decisions against the Proliferation of Weapons of Mass Destruction 2
Title Objective and implementing entity Budget and duration
Council Decision
2009/42/CFSP in
support of Arms
Trade Treaty
The overall objective is to promote the participation of all
stakeholders in the discussion on an Arms Trade Treaty
(ATT), integrate national and regional contributions to the
international process under way, and to identify the scope
and implication of a possible treaty on the trade in arms.
The project provides for the organisation of a launching
event, six regional seminars, a final seminar to present
overall results and a side-event in the margins of the 1st
Committee (UNGA 64th session).
Implementing entity: United Nations Institute for
Disarmament Research (Unidir)
Budget: 836.260 EUR
Adopted: 19.01.2009
Official Journal: L 17 - 22.01.2009
Duration: 15 months - end: April 2010
Council Decision
2008/974/CFSP in
support of HCoC
The EU supports three aspects of the Code as follows:
— Universality of the Code,
— Implementation of the Code,
— Enhancement and improved functioning of the Code.
Implementing entity: Fondation pour la Recherche
Stratégique
Budget: 1.015.000 EUR
Adopted: 18.12.2008
Official Journal: L 345 - 23.12.2008
Duration: 24 months - end: December 2010
Council Joint Action
2008/588/CFSP in
support of BTWC
The overall objective is:
- to support the universalisation of the BTWC,
- to enhance the implementation of the BTWC, including the
submission of CBM declarations, and
- to support the best use of the Inter-Sessional Process 2007-
2010 for the preparation of the next Review Conference.
Implementing entity: United Nations Office for Disarmament
Affairs (UNODA) - Geneva
Budget: 1.400.000 EUR
Adopted: 10.11.2008
Official Journal: L 302 - 13.11.2008
Duration: 24 months - end: November 2010
2 More information is available in the last Six-monthly Progress Report on the implementation of the EU Strategy against the proliferation of Weapons of Mass Destruction, adopted
on 25-26 June 2009, available at: http://www.consilium.europa.eu/uedocs/cmsUpload/st11490.en09.pdf
http://www.consilium.europa.eu/uedocs/cmsUpload/st11490.en09.pdf
10
Council Joint Action
2008/588/CFSP in
support of CTBTO
The EU supports the development of capacity of the
Preparatory Commission of the CTBTO in the area of
Verification by:
- Noble gas monitoring: radio-xenon measurements and data
analysis
- Integrating States Signatories in Africa to fully participate
in and contribute to the implementation of the CTBTO
monitoring and verification system
Implementing entity: The CTBTO Preparatory Commission
Budget: 2.316.000 EUR
Adopted: 15.07.2008
Official Journal: L189 - 17.07.2008
Duration: 18 months - end: January 2010
Council Joint Action
2008/487/CFSP in
support of the
Ottawa Convention
The overall objectives are the promotion of the
universalisation of the Convention, support for full
implementation of the Convention by States Parties and
support for the preparations for the Second Review
Conference which will take place in 2009. Maximum
synergy will be ensured with other relevant EU financial
instruments.
Implementing entity: The Geneva International Centre for
Humanitarian Demining (GICHD)
Budget: 1.070.000 EUR
Adopted: 23.06.2008
Official Journal: L165 - 26.06.2008
Duration: 21 months - end: March 2010
Council Joint Action
2008/368/CFSP in
support of the
implementation of
UNSCR 1540
The projects in support of the implementation of UNSCR
1540 will take the form of six workshops aiming at
enhancing the capacity of officials responsible for managing
the export control process in six subregions (Africa, Central
America, Mercosur, the Middle East and Gulf Regions,
Pacific Islands and South-East Asia), so that they can at a
practical level undertake implementation efforts of UNSCR
1540. The proposed workshops will be specifically tailored
for border, customs and regulatory officials and will
comprise the main elements of an export control process
including applicable laws (including national and
international legal aspects), regulatory controls (including
licensing provisions, end-user verification and awareness-
Budget: 475.000 EUR
Adopted:14.05.2008
Official Journal: L127 - 15.05.2008
Duration: 24 months - end: May 2010
11
raising programmes) and enforcement (including commodity
identification, risk-assessment and detection methods).
Implementing entity: United Nations Office for Disarmament
Affairs (UNODA)
Council Joint Action
2008/314/CFSP of 14
April 2008 on
support for IAEA
activities in the areas
of nuclear security
and verification -
IAEA V
The objectives are:
- strengthening national legislative and regulatory
infrastructures for the implementation of relevant
international instruments in the areas of nuclear security and
verification, including comprehensive safeguards agreements
and the Additional Protocol,
- assisting States in strengthening the security and control of
nuclear and other radioactive materials,
- strengthening States' capabilities for detection and response
to illicit trafficking in nuclear and other radioactive
materials.
Implementing entity: The International Atomic Energy Agency (IAEA)
Budget: 7.703.000 EUR
Adopted: 14.04.2008
Official Journal: L107 - 17.04.2008
Duration: 24 months - end: April 2010
Council Joint Action
2008/307/CFSP of 14
April 2008 in
support of the World
Health Organisation
activities in the area
of laboratory bio-
safety and bio-
security
The overall objective is to support, the implementation of the
BTWC, in particular those aspects that relate to the safety
and security of microbial or other biological agents and
toxins in laboratories and other facilities, including during
transportation as appropriate, in order to prevent
unauthorised access to and removal of such agents and
toxins.
- Promotion of bio-risk reduction management through
regional and national outreach,
- Strengthening the security and laboratory management
practices against biological risks,
Implementing entity: The World Health Organisation
Budget: 2.105.000 EUR
Adopted: 14.04.2008
Official Journal: L106 - 16.04.2008
Duration: 24 months - end: April 2010
12
Council Joint Action
2008/230/CFSP of 17
March 2008 to
promote the EU
Code of Conduct on
arms exports
The objectives are:
(a) to promote the criteria and principles of the EU Code of
Conduct on Arms Exports among third countries;
(b) to assist third countries in drafting and implementing
legislation to ensure effective control of arms exports;
(c) to assist countries in the training of licensing officers to
ensure adequate implementation and enforcement of arms
export controls;
(d) to assist countries in the elaboration of national reports on
arms exports and the promotion of other forms of scrutiny in
order to promote transparency and accountability of arms
exports;
(e) to encourage third countries to support the United Nations
process aiming at the adoption of a legally binding
international treaty establishing common standards for the
global trade in conventional arms, and to assist in ensuring
that they are in a position to comply with such possible
common standards.
Implementing entity: EU Presidencies
Budget: 500.500 EUR
Adopted: 17.03.2008
Official Journal: L75 - 18.03.2008
Duration: expires 17.03.2010
Council Joint Action
2008/113/CFSP of 12
February 2008 in
support of marking
and tracing of
SALW
The UN Secretariat (Office of Disarmament Affairs),
organised in 2008 a series of regional and sub-regional
workshops in order to allow relevant government officials
and others (including SALW points of contact, law
enforcement officials, members of national coordinating
bodies, and parliamentarians) to become better acquainted
with the provisions of the International Instrument to Enable
States to Identify and Trace, in a Timely and Reliable
Manner, Illicit Small Arms and Light Weapons (SALW)
Implementing entity: United Nations Office for Disarmament
Affairs (UNODA)
Budget: 299.825 EUR
Adopted: 12.02.2008
Official Journal: L 40 - 14.02.2008
Duration: 12 months - end: February 2009
13
Council Joint Action
2007/753/CFSP of 19
November 2007
in support of IAEA
monitoring and
verification activities
in the DPRK
Objective:
- to contribute to the implementation of monitoring and
verification activities in the DPRK, in accordance with the
Initial Actions of 13 February 2007, as agreed in the
framework of the six-party-talks.
Implementing entity: The International Atomic Energy Agency (IAEA Department of Safeguards)
Budget: 1.780.000 EUR
Adopted: 19.11.2007
Official Journal: L304 - 22.11.2007
Duration: 18 months - end: May 2009
Council Joint Action
2007/185/CFSP of 19
March 2007 - OPCW
The objective is to support the universalisation of the
Chemical Weapons Convention (CWC), and in particular to
promote the ratification/accession to the CWC by States not
Parties (signatory States as well as non-signatory
States) and to support the full implementation of the CWC
by the States Parties.
- promotion of universality of the CWC,
- support for full implementation of the CWC by States
Parties,
- international cooperation in the field of chemical activities,
as accompanying measures to the implementation
of the CWC,
- support for the creation of a collaborative framework
among the chemical industry, OPCW and national authorities
in the context of the 10th anniversary of the OPCW
Implementing entity: The Organisation for the Prohibition of
the Chemical Weapons.
Budget: 1.700.000 EUR
Adopted: 19.03.2007
Official Journal: L85 - 27.03.2007
Duration: 18 months - end: 31.07.2009
Council Joint Action
2006/184/CFSP of 27
February 2006 -
BTWC
Overall objective: to support the universalisation of the
BTWC and, in particular, to promote the accession to the
BTWC by States not Party (signatory States as well as non-
signatory States) and to support the implementation of the
BTWC by the States Parties.
- Promotion of the universality of the BTWC;
Budget: 867.000 EUR
Adopted: 27.02.2006
Official Journal: L65 - 07.03.2006
Duration: 18 months
14
- Support for implementation of the BTWC by the States
Parties.
Implementing entity: The Graduate Institute of International
Studies, Geneva
Council Joint Action
2007/528/CFSP of 23
July 2007 - CCW
The overall objective of this Joint Action is to support the
universalisation of the CCW by promoting the accession to
the CCW by States not Party to it and to enhance the
implementation of the CCW.
Activities are workshop, regional seminars and publications.
Implementing entity: United Nations Office for Disarmament
Affairs, Regional Centres for Peace and Disarmament of the
UN and The Geneva International Centre for Humanitarian
Demining
Budget: 828.000 EUR
Adopted: 23.07.2007
Official Journal: L194 - 26.07.2007
Duration: 18 months
Council Joint Action
2007/468/CFSP of 28
June 2007 - CTBTO
II
The objective is to support the early entry into force of the
Treaty, and need to the rapid buildup of the Comprehensive
Nuclear-Test-Ban Treaty (CTBT) verification regime via:
- Improvement of the knowledge of Provisional Technical
Secretariat noble gas measurements;
- Support to on-Site Inspection via the support for the
Preparations for the Integrated Field Exercise 2008
Implementing entity: The CTBTO Preparatory Commission
Budget: 1.670.000 EUR
Adopted: 28.06.2007
Official Journal: L176 - 06.07.2007
Duration: 15 months
Council Joint Action
2006/243/CFSP of 20
March 2006-
CTBTO I
The objective is to improve the capacity of CTBT Signatory
States to fulfil their verification responsibilities under the
CTBT and to enable them to fully benefit from participation
in the treaty regime by a computer-based training/self-study.
Implementing entity: The CTBTO Preparatory Commission
Budget: 1.133.000 EUR
Adopted: 20.03.2006
Official Journal: L88 - 25.03.2006
Duration: 15 months
15
Council Joint Action
2006/418/CFSP of 12
June 2006 - IAEA III
The objective is to strengthen nuclear security in selected
countries which have received EU assistance such as:
- Legislative and Regulatory Assistance;
- Strengthening the Security and Control of Nuclear and
other Radioactive Materials;
- Strengthening of States' Capabilities for Detection and
Response to Illicit Trafficking.
Implementing entity: The International Atomic Energy Agency
Budget: 6.995.000 EUR
Adopted: 12.06.2006
Official Journal: L165 - 17.06.2006
Duration: expires on 12.09.2007
Council Joint Action
2005/574/CFSP of 18
July 2005 - IAEA II
The objective is to strengthen nuclear security in selected
countries which have received EU assistance such as:
- Strengthening the Physical Protection of Nuclear Materials
and other Radioactive Materials in Use, Storage and
Transport and of Nuclear Facilities;
- Strengthening of Security of Radioactive Materials in Non-
Nuclear Applications;
- Strengthening of States‘ Capabilities for Detection and
Response to Illicit Trafficking;
- Legislative Assistance for the Implementation of States‘
Obligations under IAEA Safeguards Agreements and
Additional Protocols
Implementing entity: The International Atomic Energy Agency
Budget: 3.914.000 EUR
Adopted: 18.07.2005
Official Journal: L193 - 23.07.2005
Duration: 15 months
Council Joint Action
2004/495/CFSP of 17
May 2004 -IAEA I
The objective is to strengthen nuclear security in selected
countries which have received EU assistance such as:
- Strengthening the Physical Protection of Nuclear Materials
and other Radioactive Materials in Use, Storage and
Transport and of Nuclear Facilities;
- Strengthening of Security of Radioactive Materials in Non-
Nuclear Applications;
Budget: 3.329.000 EUR
Adopted: 17.05.2004
Official Journal: L182 - 19.05.2004
Duration: 15 months
16
- Strengthening of States' Capabilities for Detection and
Response to Illicit Trafficking
Implementing entity: The International Atomic Energy Agency
Council Joint Action
2005/913/CFSP of 12
December 2005 -
OPCW II
The objective is to support the universalisation of the CWC
and in particular to promote the accession to the CWC by
States not Party (signatory States as well as non-signatory
States) and to support the implementation of the CWC by the
States Parties.
- Promotion of universality of the CWC;
- Support for implementation of the CWC by the States
Parties;
- International cooperation in the field of chemical activities.
Implementing entity: The Organisation for the Prohibition of
the Chemical Weapons.
Budget: 1.697.000 EUR
Adopted: 12.12.2005
Official Journal: L331 - 17.12.2005
Duration: 12 months
Council Joint Action
2004/797/CFSP of 22
November 2004 -
OPCW I
The objective is to support the universalisation of the CWC
and in particular to promote the accession to the CWC by
States not Party (signatory States as well as non-signatory
States) and to support the implementation of the CWC by the
States Parties.
- Promotion of universality of the CWC;
- Support for implementation of the CWC by the States
Parties;
- International cooperation in the field of chemical activities.
Implementing entity: The Organisation for the Prohibition of
the Chemical Weapons
Budget: 1.841.000 EUR
Adopted: 22.11.2004
Official Journal: L349 - 25.11.2004
Duration: 12 months
Council Joint Action
2007/178/CFSP of 19
The objective is to assist the Russian Federation in
destroying some of its chemical weapons, towards fulfilment
Budget: 3.145.000 EUR
Adopted: 19.03.2007
17
March 2007 -
Russian Federation
IV
of Russia‘s obligations under the Convention on the
Prohibition of the Development, Production, Stockpiling and
use of Chemical Weapons and on their Destruction.
This Joint Action supported the completion of the electricity
supply infrastructure at Shchuch‘ye chemical
weapon destruction facility, in order to provide a reliable
power supply for the operation of the chemical weapon
destruction facility.
Implementing entity: The Ministry of Defence of the United
Kingdom of Great Britain and Northern Ireland
Official Journal: L81 - 22.03.2007
Duration: 18 months
Council Joint Action
2004/796/CFSP of 22
November 2004 -
Russian Federation
III
The objective is to contribute to reinforcing the physical
protection of nuclear sites in Russia, so as to reduce the risk
of theft of nuclear fissile material and of sabotage by
improving the physical protection for fissile materials at the
Bochvar Institute in Moscow (VNIINM) of the Russian
Federal Agency for Atomic Energy FAAE (formerly
MINATOM).
Implementing entity: The Federal Republic of Germany
Budget: 7.937.000 EUR
Adopted: 22.10.2004
Official Journal: L349 - 25.11.2004
Duration: 3 years
Council Joint Action
2006/419/CFSP of 12
June 2006 - UNSCR
1540
The action aimed at addressing three aspects of the
implementation
- awareness-raising of requirements and obligations under
the Resolution,
- contributing to strengthening national capacities in three
target regions (Africa, Latin America and Caribbean, Asia-
Pacific) in drafting national reports on the implementation of
UNSC Resolution 1540 (2004) and
- sharing experience from the adoption of national measures
required for the implementation of the Resolution.
Implementing entity: United Nations Office for Disarmament
Affairs (UNODA - formerly the Department for
Disarmament Affairs)
Budget: 195.000 EUR
Adopted: 12.06.2006
Official Journal: L165 - 17.06.2006
Duration: expires on 12 June 2008
18
Council Joint Action
1999/878/CFSP of 17
December 1999 -
Russian Federation I
The project contributed to:
- a chemical weapons pilot destruction plant situated in
Gorny, Saratov region, Russia;
- a set studies and experimental studies on plutonium
transport, storage and disposition.
Budget: 8.900.000 EUR
Adopted: 17.12.1999
Official Journal: L331 - 23.12.1999
Duration: expires on the date of expiry of the European Union
Common Strategy 1999/414/CFSP on Russia
Council Joint Action
2003/472/CFSP of 24
June 2003 - Russian
Federation II
This Joint Action aims at financing a unit of experts under
the cooperation programme for non-proliferation and
disarmament in the Russian Federation.
Budget: 680.000 EUR
Adopted: 24.06.2003
Official Journal: L157 - 26.06.2003
Duration: expires on the date of expiry of European Union
Common Strategy 1999/414/CFSP on Russia.
Commission's CBRN assistance programmes - Nuclear Material Accountancy and Control (NMAC) - TACIS/INSC programmes
Project
identification Title Objective Amount
Execution
periode
R5.01/95
R5.01/96A
R5.01/97A
R5.11/03S
Establishment of the RU
methodology and training centre
(RMTC) in Obninsk
Specification and procurement of equipment and material
standards, installation of a calibration laboratory,
development of training materials, and conduct of training
courses and seminars for instructors, for supporting the
RMTC in Obninsk in the education and training of Russian
experts on modern NMAC.
~€ 5 million TACIS
1997-2008
R5.02/95
R5.03/96C
R5.01/97C
R5.03/98
R5.03/03S
Establishment of production
strategy of instrumentation for
the State System of
Accountancy and Control of
nuclear materials in Russia
VNIIA Moscow
Development of a programme concerning the provision of
NMAC equipment for the Russian State System of
Accounting and Control (SSAC), including a strategy to
produce such equipment, and arrangement for the production
and testing of prototypes for high-priority instruments
~€ 3 million TACIS
1997-2009
R5.02/96B
R5.01/97B
R5.12/03S
Design and setup of three
laboratories for independent
analysis, nuclear metrology
analysis of nuclear material of
unknown origin (Bochvar
Institute, RU)
Provision of necessary instruments for three laboratories at
VNIINM and training for laboratory staff in their operation
in order to improve the analytical capabilities of the Russian
organizations in the areas of NMAC and IT prevention
~€ 3.5
million
TACIS
1997-2009
19
R5.04/96
R5.01/97D
R5.04/98
R5.04/03S
Establishment of the Ural
Siberian methodology and
training centre (UrSiMTC) in
Snezhinsk
Creation of second training centre in Russia in the region
with several large nuclear fuel cycle facilities for NMAC-
related training, including performance of a feasibility study,
provision of a pilot plutonium storage module, and training
of future UrSiMTC instructors
~€ 1.8
million
TACIS
1997-2009
U5/95
Application to the technical
assistance programme providing
effective assistance in
counteracting non-authorised
transfer of nuclear material in
Ukraine
Delivery of equipment, development of a handbook, and
training of the representatives of relevant authorities in
Ukraine for the detection of IT and identification of the
material involved
~€ 0.5
million
TACIS
1999-2001
R5.01/98
R5.01/00
Enhancing safeguard system on
a pilot plant and supply of
modern equipment for control of
access to nuclear material on all
RU NPPs
Feasibility study in respect of the plan to implement a
computerised NMAC system in all nuclear power plants
(NPP) in Russia
~€ 0.8
million
TACIS
2000-2006
K5.01/97
K5.01/98
Establishment of facilities for
mass/volume containment /
surveillance and training at Ulba
metallurgical plant, Mangyshlak
fast breeder reactor, the Almaty
VVR and the Kurchatov reactors
in Kazakhstan
Provision of methodology and equipment, and training to the
Ulba plant operators and national inspectors in order to fulfil
the safeguards requirements of the IAEA
~€ 3 million TACIS
2000-2007
R5.01/02
R5.01/02S
Modernisation and enhancement
of NMAC at the Mayak RT-1
plant
The specific objective is to improve the mass measurements
of Pu and U in hold-ups and in wastes to meet the
requirements of the State NMAC
~€ 3 million TACIS
2004-2010
TAREG 5.01/05 Integrated Safeguards & Illicit
Trafficking – service part
Strengthening non-proliferation regime by enhancing the
Safeguards system and in particular the Nuclear Material
Accountancy and Control (NMAC); counteracting nuclear
and radiation terrorism threat; strengthening and improving
institutional control by enhancing collaboration and
capacities of national regulatory authorities (12 sub-projects,
some of them continuing already started activities)
~€ 14
million
TACIS
2006-2013
20
TAREG 05/06S
Nuclear Material Accountancy
and Control – procurement of
equipment 1st part
Provision of the first batch of equipment for NMAC
identified by the project TAREG 5.01/05 € 5.3 million
TACIS
2008-2011
financing agreement
with beneficiary
countries (Armenia)
not yet signed
Nuclear Material Accountancy
and Control – procurement of
equipment 2nd part
Provision of the second batch of equipment for NMAC
identified by the project TAREG 5.01/05 € 0.5 million
INSC
AAP2008
RISK MITIGATION AND PREPAREDNESS RELATING TO CHEMICAL, BIOLOGICAL, RADIOLOGICAL AND NUCLEAR MATERIALS OR AGENTS - Instrument
for Stability, priority 1
Project
identification/
CRIS number
Title Objective Amount Execution
periode
n.a.
Retraining former weapon scientists
and engineers through support for
International Science and Technology
Centre (ISTC, Moscow) and Science
and Technology Centre (STCU,
Kiev)
The main objective of the Centres is to redirect
scientists/engineers' talents to civilian and peaceful activities
through science and technological cooperation.
€ 235 million TACIS
1997-2006
€ 15 million
€ 8 million
€ 7 million
IFS
2007
2008
2009
AAP 2007 (excluding funding for ISTC/STCU)
145156
Combating illicit trafficking of
nuclear and radioactive materials in
FSU countries (Russian Federation,
Ukraine, Armenia, Moldova,
Georgia, Azerbaijan and Belarus)
The purpose of the action is to supply equipment for detection
of NRM at border check points as it was identified in the
previous phase of the activity financed by TACIS Nuclear
Safety programme, contributing thus to reduce nuclear and
radiation terrorism threat
€ 5 million 11/07/2008 -
10/07/2011
145130 Assistance in export control of dual-
use goods
The specific objective is to support the development of the legal
framework and institutional capacities for the establishment and
enforcement of effective export controls on dual-use items,
including measures for regional cooperation with a view of
contributing to the fight against the proliferation of WMD and
related materials, equipment and technologies
~€ 5 million 19/03/2008 - 18/09/2010
21
145132 Knowledge Management System on
CBRN Trafficking
The overall objective of the activity is to improve capabilities
of participating states, neighbouring countries of the EU in
South-East Europe and possibly Caucasus, to combat the illicit
trafficking and criminal use of CBRN materials
€ 1 million 31/01/2008-
30/01/2010
AAP 2008 (excluding funding for ISTC/STCU)
200523
Knowledge management system on
CBRN trafficking in North Africa
and selected countries in the Middle
East
The aim of the project would be to develop a durable co-
operation legacy in the area of trafficking of CBRN materials € 1 million
16/03/2009 -
15/03/2011
-
Strengthening bio-safety and bio-
security capabilities in Russia and in
Central Asian countries
The project will address shortcomings in the safety/security
practices of key biological facilities in Russia and the selected
countries of the Central Asia. The main objectives of the
project are to raise the skills of the personnel working at
facilities (laboratories) handling dangerous biological agents or
supervising those facilities, and to provide additional
equipment, as needed, to ensure an adequate level of bio-safety
and security.
€ 6.8 million in preparation
-
Combating illicit trafficking of
nuclear and radioactive materials in
selected FSU and Mediterranean
Basin countries and preparation of
border management activities in the
ASEAN region
The overall objective of this project is to reduce the threat of
nuclear and radiation terrorism. For this purpose the assistance
will be provided to the partner countries in the improvement of
the technical and organisational measures for detection of
nuclear and radioactive materials (NRM) illicit trafficking.
€ 6.7 million in preparation
-
Assistance to the Russian Federation
on control of exports of dual-use
goods
The overall objective of the project is to enhance the
effectiveness of export control of dual use items in the Russian
Federation, with a view to contribute to the fight against the
proliferation of WMD. The specific objectives will be achieved
through information exchange with EU exporters, support
industry and researchers for awareness raising, organisation of seminars for exporters in the regions of the Russian Federation.
€ 1 million in preparation
IP 2009-2011
Regional centres of excellence The creation of ―CBRN centres of excellence‖ will aim at
developing comprehensive tailored training and assistance
packages (export control including of dual-use goods,
illicit trafficking, redirection of scientists, safety and
security culture).
25-30 million In preparation
22
Fighting illicit CBRN trafficking Broaden the geographic scope of its cooperation
programmes to new regions of significance for EU
security, including the Middle East and South-East Asia,
as well as parts of Africa.
12-14 million In preparation
Support to bio-safety and bio-
security
Priority should be given to increasing bio-safety and
security in the Middle East, Former Soviet Union, notably
Central Asia, South and South-East Asia. Additional
actions in Africa will also be considered.
14-18 million In preparation
Assistance and cooperation on
export control on dual-use goods
This project will consolidate existing actions, reinforce
related training, and move to new countries in regions of
concern.
6-10 million In preparation
Support for the retraining and
alternative employment of former
weapons scientists and engineers
To reduce the risk of WMD expertise proliferation and the
associated threat to international security.
20-26 million
(2010-2011)
In preparation
Support for Multilateral Nuclear
Assurance (MNA) initiatives
Creation of a nuclear fuel bank of low enriched uranium
(LEU) with the objective of sending a positive signal to
countries willing to develop civil nuclear programmes by
increasing the security of fuel supply.
€ 20-25
million
In preparation
23
Finland3
Country of
Project
Project Description Project Status: Milestones, Implementation
Comments
Funds Committed
January 2004 - April
2009
in 000’s EUR
Funds Expended
January 2004 - April
2009
in 000’s EUR
Russia and
Ukraine
Nuclear material safeguards Long-term projects in 4 areas: cooperation with
Russian authorities, development of verification
methods, participation in multilateral
cooperation, support for nuclear material
controls in Ukraine
830 660
Russia Nuclear waste management Long-term cooperation area. Projects include
development of control manuals and methods,
training and participation in multilateral
cooperation
428 388
Russia Nuclear safety at Kola Nuclear
Power Plant
Several long-term projects on technical safety
improvements have been carried out. Ongoing
projects cover e.g. development of working
methods, training in non-destructive inspections,
improving fire safety and supporting
probabilistic safety analyses
2712 2247
Russia Nuclear safety at Leningrad
Nuclear Power Plant
Several long-term projects have been completed.
Ongoing projects cover e.g. development of
working methods, enhancing non-destructive
inspection equipment and skills, improving fire
safety and supporting probabilistic safety
analyses
4635 3735
Russia Nuclear Emergency
Preparedness
Long-term cooperation area. Projects located
mainly in Northwest Russia. Several projects
completed. Ongoing projects cover e.g. radiation
monitoring systems for environment and
personnel as well as testing alarm systems
830 730
3Updated on April 2009
24
Russia and
Ukraine
Regulatory Cooperation on
nuclear safety
Long-term cooperation area. Projects aim at
strengthening the capacity of nuclear and
radiation safety authorities
1155 930
Russia and
Eastern
Europe
Other non-specified international
projects on nuclear safety and
safeguards
Covering funding for e.g. cooperation in
multilateral fora, planning, organising and
reporting on bilateral cooperation
1870 1570
Russia Northern Dimension
Environmental Partnership
(NDEP)
Finland's contribution to the nuclear window of
the NDEP in 2002-06
2000 2000
Ukraine Chernobyl Shelter Fund Finland's contribution to the EBRD's Chernobyl
Shelter Fund totals EUR 700 000 in 2005-06. A
further contribution will be made in 2007.
1000 1000
Russia Elimination of Weapons Grade
Plutonium Production
Finland's contribution to the Zheleznogorsk
Plutonium Production Elimination Project,
implemented by the US, made in June 2006
500 500
Russia Contribution to the Russial
Special Federal Programme of
Destruction of Chemical
Weapons Stockpiles
Delivery and installation of a fixed Chemical
Warfare Agent Detection Network to the
Chemical Weapons Destruction Facility in
Gorny completed in 2003. Contribution through
UK programme towards electricity installations
at Shchuch'ye Destruction Facility in 2008 (715
000 euros).
1319 715
Russia Support to non-governmental
organisations' activities for
facilitating Russian chemical
weapons destruction
Public outreach and information projects
implemented by Green Cross Legacy
Programme in 2005, 2006, 2007 and 2008
(104 550 euros/2008).
810 765
Russia RTG, Removing radioactive
lighthouses from Gulf of Finland
Finland's contribution to the RTG project in
2009-2011
1500 0
Russia EBRD/Nuclear Safety Account Finland's contribution to the NSA in 2009 2000 2000
Ukraine Mobile radiation monitoring
laboratory for Radiation and
Nuclear safety Authority of
Ukraine
Delivery of the mobile radiation monitoring
laboratory, training related to it
500 0
22089 17240
25
France
Country Project description / Detailed Project
Funding Commitments
Project Status: Milestones, Observations on
Implementation
Funds Committed
(from beginning to
date)
in € (000's)
Funds
contracted or
almost
contracted
(to date in €
(000’s)
Russia Contribution to the nuclear window of
the Northern Dimension Environmental
Partnership (NDEP) Support Fund,
administered by the European Bank for
Reconstruction and Development.
The development of the "Strategic Master Plan" for
work in North-Western Russia, associated with the
nuclear submarine legacy under the NDEP Fund, will
enable improved coordination (as for example in
Gremikha).
40,000 13,600
Russia Contribution to the MPDG (Multilateral
Plutonium Disposition Group) to
implement the Russian weapons-grade
plutonium disposition programme in
Russia.
Pending the conclusion of corresponding multilateral
agreement (MPDG negotiation).
70,000 USD _
(No progress
in multilateral
negotiation)
Russia Aida Mox 1: this cooperation project is
aimed at providing support to the Russian
Federation for the dismantlement of
Russian nuclear weapons. Bilateral
cooperation initiated in 1992, to which
France contributed up to €70 million.
France proposed to update the equipment provided
under this programme and to allocate €1 million to this
project in the framework of the Global Partnership.
1,000 0,750
Ukraine Contribution to the EBRD‘s Chernobyl
Shelter Fund
Total contribution to the CSF: 47,500,000 €
(31,400,000 € before 2002))
22,300 16,100
Lithuania Contribution to the Ignalina International
Decommissioning Support Fund.
Decommissioning of the Ignalina nuclear power plant
(Lithuania).
1,500 1,500
Russia Kalinin: improvement of the safety of the
Kalinin nuclear power station, in Russia.
Feasibility study completed for 2 M€. Agreement with
Russian Federation for tax exemption signed in
February 2007.
2,200 2,200
26
Country Project description / Detailed Project
Funding Commitments
Project Status: Milestones, Observations on
Implementation
Funds Committed
(from beginning to
date)
in € (000's)
Funds
contracted or
almost
contracted
(to date in €
(000’s)
Russia Gremikha: the remediation of the
Gremikha former naval base consists of
several projects, including the removal
and dismantlement of "Alfa" nuclear
reactors, safe storage of SNF and nuclear
waste, as well as remediation of facilities
and site.
Feasibility study: supply of nuclear safety equipment to Russian partners (two contracts
fulfilled in 2005) and radiation and engineering
survey to be ended in 2007.
Pre-design studies contract (DON and OBIN)
started in 2006 and were implemented in 2007/2008.
Urgent priority works revealed by first stage of the engineering survey in order to improve safety and
security of workers and to prepare further work
(removal and clean-up of radiological hot spots,
refitting utilities and buildings). Nine contracts
signed in 2007 and 2008:
cloakroom refitting ;
diesel generators maintenance (motors and building)
dry-dock improvement ;
consolidation of walls and roof of building 19 used for radwaste storage;
radiological situation improvement on the Open Pad and the SNF inventory;
Development of the means for the intact VVR SNF handling.
Handling means refurbishment (crane, ..).
Works for securisation of spent VVR fuel and Alpha class cores
Decontamination and unloading of reactor head
up to 10,000 -> 2007, further
funding subject to
results of
feasibility study
up to 9,000 => 2007 / 2008
up to 13,600 => 2007 / 2008
10,010
8,800
6,400
27
Country Project description / Detailed Project
Funding Commitments
Project Status: Milestones, Observations on
Implementation
Funds Committed
(from beginning to
date)
in € (000's)
Funds
contracted or
almost
contracted
(to date in €
(000’s)
of ―alpha‖ submarine n°910
Development of handling means for shipment damaged VVR fuel out of Gremikha
Other contracts for securisation works will be signed in 2009
Preparation of the sites where the SNF will be removed.
Russia Severodvinsk: the refitting of the nuclear
waste incinerator in Zvezdochka shipyard
will enable this shipyard to increase
corresponding capacity for the
disposition of solid nuclear waste.
Diagnosis and feasibility study initiated in cooperation
with Russian partners in 2004. This technical phase
completed in summer 2006 for an amount of 420 k€.
The concrete implementation of this project started in
December 2006. Contracts of 9, 6 M€ signed with
AREVA/TA and Zvezdochtka shipyard. Detail design
studies are completed.
Oven manufactured and tested in France end of 2008
and delivred to Zvezdochtka – Incinerator Building is
refitted end of 2008.
Equipment is being mounted. Operation is planed to
start by autumn 2009.
up to 10,000 for
period 2004-2008
10,020
Russia Dismantlement of Radio isotopic
Thermoelectric Generators (RTG) in
Russia and safe storage of the
corresponding strontium nuclear sources.
Operation implemented in 2005 and 2007 in close
coordination with Norway (two agreements signed for
600 K€).
Experience gained is used to promote bilateral
french/russian actions in the same field.
One contract is being signed for:
dismantlement and replacement of 4 high powerful RTG on the Baltic coast
Another is being prepared for the removal of 12 other
up to 5,000
(-> 2008) further
funding subject to
results of
discussions
3,300
28
Country Project description / Detailed Project
Funding Commitments
Project Status: Milestones, Observations on
Implementation
Funds Committed
(from beginning to
date)
in € (000's)
Funds
contracted or
almost
contracted
(to date in €
(000’s)
RTG on the Baltic coasts.
Overall cost to be adapted to the results of discussions.
Ukraine Disused high active spent sources
management in Ukraine
Two contracts are being prepared for:
Radiological measurement devices supply
Design of hot modular cells Following work pending signature of an agreement with
Ukrainian governemental authorities.
up to 2,000 0,300
Russia Chemical weapons destruction:
environmental survey of the Shchuch‘ye
destruction facility
Intergovernmental agreement ratified in France and
Russia entered in force in May 2007.
Contracts signed end of October 2007. 98% of the work
is completed. Last operationnal tests realized in March.
9,000
(->2008) including
technical assistance
to French
management team
9,000
Russia Chemical weapons destruction:
realisation of the Shchuch‘ye destruction
facility
Purchasing equipment for the second process line of the
destruction facility in close cooperation with UK and
Canada. French-UK agreement and related
memorandum of understanding between MOD and
CEA signed in April 2007 (Equipment purchase under
way) All the equipment was delivered on the site in
March 2009 on time for operating the destruction of the
first weapons filled with SARIN.
6,000
(->2008)
6,000
Russia Biosecurity and biosafety programmes in
Russian biological facilities. These
projects focus on immunology and
genetics programmes with commercial
potential.
Seven research projects expected in 2005. These
projects were to be implemented in Russia through the
International Scientific and Technical Center (ISTC).
Only four projects started in 2006 concerning scientific
collaboration in the field of new therapeutic molecules
and new diagnosis and environmental surveillance tools.
These projects involve French and Russian laboratories
working together and will run for 3 or 4 years.
up to 1,700 1,300
29
Country Project description / Detailed Project
Funding Commitments
Project Status: Milestones, Observations on
Implementation
Funds Committed
(from beginning to
date)
in € (000's)
Funds
contracted or
almost
contracted
(to date in €
(000’s)
Russia Redeployment of scientists from military
field. The project focuses on supporting
public/private partnerships enabling to
join forces between Russian laboratories
and French enterprises in order to create
sustainable employment.
In 2006, a feasibility study assessed an existing demand
of industrials and a possible match with technical offer
of Russian laboratories.
The main part of the project (about to be launched) aims
to identify and escort partnership projects between
Russian laboratories and industrials.
A second phase aims to implement sustainable research
and commercial links between Russian laboratories and
industrials. A contract was placed in June 2008.
2,800
(2007 – 2009)
2,800
30
Germany
Country of
Project
Project Description Project Status: Milestones, Implementation
Comments
Funds
Committed
(06/02 -
12/08)
in 000's
Funds
Expended
(06/02 -
12/08)
in 000's
Federal Ministry for Economy and
Technology
Russia o construction of a land based long-term interim storage facility for 150 submarine
reactor compartments and 28 other nuclear
objects (sections from nuclear vessels,
icebreakers, Lepse) at Sayda Bay;
o dismantlement of nuclear submarines and preparation of the reactor compartments for
interim storage in Sayda Bay;
o reconstruction of Nerpa Ship Yard; o recreation of a ecologically healthy
condition at Sayda Bay;
o construction of a centre for conditioning and long-term storage for all radioactive
waste from nuclear submarines and surface
vessels at Sayda Bay.
- the construction site for the long-term interim
storage facility was opened back on July 10,
2004; and the first work done in preparation of
construction activities. On July 18, 2006 started
the operation of the first section of the long-
term interim storage facility. 28 reactors
compartments were stored on the concrete
platform of the first section by the end of 2008.
The whole long-term interim storage facility is
scheduled to be completed at the end of 2009
(budget EUR 300 million).
- the first construction work of the centre for
radioactive waste began in 2008. The additional
budget for this project is also EUR 300 million.
The regional centre is scheduled to be
completed in 2014
2003- 2008
300.000 EUR
2009:
30.000 EUR
2003
- March 2009:
303.000 EUR
Federal Foreign Office
Russia CW destruction:
Support for construction of CWDF´s in
Gorny, Kambarka, Leonidowka and
Pochep
1. Gorny (1995 – 2003)
• Draining facilities for barrels and tanks
- started operations in 2003 and had successfully destroyed the stock of CW end of 2005;
343.060 EUR
50.000
281.940 EUR
50.100
31
• Stationary and mobile laboratory • Building for incinerator for liquid and
solid residues
• Equipment for CW-destruction by hydrolysis
• Equipment for arsenic extraction by electrolysis
• Equipment for purification of toxic gas/smoke and toxic water
• Relevant engineering and expertise
2. Kambarka
• Construction and delivery of a turn-key ready thermal destruction facility for
solid, liquid and gaseous residues
generated during the destruction of
lewisite, along with the building to
house it (building 44)
• Construction of a draining system for Lewisite cisterns containing the combat
agent (85 cistern draining devices
• Supply of technological equipment for the safety, temperature control and
ventilation systems including double-
wall, heat-insulating enclosures of the
5 storage buildings
• Construction and delivery of filter systems for contaminated buildings
• Production and delivery of 2 detoxication modules mounted on 2
mobile transborders
• Delivery of spare parts to ensure the operationability of the equipment
- support by spare part delivery
- agreed between FFO and FAI in 2003 - Construction began in 2004. - Kambarka was officially inaugurated in March
2006, destruction of stock ( 6350 t) completed in
March 2009
- Official hand-over to Russia in March 2007 - Delivery of spare parts implemented in spring
2008
(including
budget
ressources
earlier than
2002)
153.060
152.840
32
delivered by Germany
3. Leonidowka planned contribution (turn-key ready thermal
destruction facility) was not implemented after
Russian partner decided to construct
Leonidowka without German assistance
4. Pochep - construction of a complete building
(building 11), which will contain the
thermal destruction equipment for solid
and liquid residues including the
reaction masses from the destruction,
the incinerator and equipment for the
thermal treatment of the munition,
- water treatment and air purification.
- German FFO concluded contracts with German
main contractor for some preliminary engineering
work, contract immediately cancelled in September
2006 after Russian decision to refrain from German
assistance in Leonidowka
- intergovernmental agreement in March 2007 - laying of foundation stone in June 2008 - acceptance procedure for pre-assembled
equipment September 2008
- engineering and design of the installations completed, transportation to site under way;
construction of building in progress; assembly of
equipment in the building to start in June 2009
- start of operations planned for spring 2010
(Originally up
to 140.000)
up to 140.000
4.000
75.000
Russia Physical protection of nuclear material
Upgrading security of nuclear material and
facilities in nuclear cities, research institutes
and nuclear weapons storage sites in Russia
- legal instruments concluded; security analyses and
project engineering completed;
- some projects in Osjorsk, Seversk, Moscow
successfully completed
- further projects in Osjorsk, Seversk, Moscow,
Dimitrowgrad and other sites under way.
167.165 EUR
81.756 EUR
33
Ukraine Physical Protection of nuclear material Upgrading of the physical protection of a site
for handling of radioactive sources and
installing of new equipment for radioactive
sources of different origin
legal instrument about to be signed in the next weeks
preparatory work and planning under way
6,4 Mio 0,0 EUR
Multilateral
Russia/FSU Contribution to Nuclear Security Fund of
IAEA
1.000 EUR 1.000 EUR
Russia Contribution the Northern Dimension
Environmental Programme in the Russian
Federation Fund
2.000 EUR 2.000 EUR
34
Ireland
Country of
Project
Project Description Project Status: Milestones, Implementation
Comments
Funds Committed
(July 2004- June 2007)
Funds Expended
(July 2004-June 2007)
Nuclear
Ukraine Chernobyl Shelter Fund
Funds contributed through EBRD
€3,420,000 €2,565,000
Chemical
Russia Schuch‘ye Chemical Weapons
Destruction Facility
Note - Funds contributed through
the UK for the installation of the
Metal Parts Furnace and towards
the procurement of other
equipment for the second
munitions destruction building.
Construction of the Schuch'ye facility has
been completed and it is now operating.
€110,000 €110,000
35
Italy
Country of
project
Project Description Project Status: Milestones, Implementation, Comments Funds
Committed
Funds
Expended
Total GP Pledge:up
to € 1 billion over 10
years
€ 110 million
€ 32 million
Russia
Nuclear submarine
dismantlement ,
spent fuel and
radioactive waste
management:
A bilateral agreement between the Italian and Russian Governments has
been signed on November 5th, 2003 and entered into force in November,
17th
2005 after ratification by the Italian and the Russian parties for a total
funding of 360 Million Euro in 10 years. The institutions responsible for the
agreement‘s implementation are the Italian Ministry for Economic
Development (MSE) and ROSATOM.
A Steering Committee (2 Representatives of Italian MSE and 2
Representatives of Rosatom) defines the strategy, manages the general
activities and solves any controversy. Specific project management and
administration has been entrusted to a dedicated unit (Project Management
Unit) based in Moscow (5 Russian and 5 Italian employees). .
In July 2006 the first Contract for the dismantlement work of one submarine
class Yankee was signed and the activities were completed in January 2008.
The dismantling work of a second submarine, class Viktor, started in May
2007 and was completed by the end of 2008. A contract for the dismantling
of the third submarine (class Viktor) was signed in May 2008 and the
dismantling work is being completed in 2009.
A new contract , concerning the dismantling of an additional 4th
submarine,
for an amount of € 4.6 million, has also been recently signed
€ 19.3 million
€ 14.3 million
A contract for the unloading of spent nuclear fuel from the reactors of the
heavy cruiser 090 has recently been signed.
€ 5.4 million
€ 0.8 million
36
Following open tendering procedures, in December 2007, two contracts for
the supply of equipment and systems for the improvement of Nerpa and
Zvyozdochka shipyards infrastructures were signed. The contracts provide
the supply, in two deliveries, of special equipment as cutting, welding and
sealing tools, portable cranes, other lift and transport systems as well as
individual protection means. The first delivery has already arrived at both
shipyards. The second delivery is under way.
€ 3.5 million
€ 2.1 million
Following a preliminary study, a contract for the detailed design of
improvements to the physical protection systems of Zvezdochka shipyard
has been signed, and a parallel contract for Nerpa shipyard is under
definition. Additional contracts for equipment and systems delivery are
foreseen.
€ 0.530
million
€ 0.08 million
Two contracts for the preliminary design of SRW (building N. 203) and
LRW (building N.1) treatment facilities were signed in March 2007 and
completed in February 2008.,
A new contract for the basic design and the APDD of these two facilities,
and for an interim storage facility of conditioned RW is under definition.
€ 0.64 million
€ 0.64 million
Two contracts for the detailed design of two shelters (buildings N.201 and
N.202) in the existing area used for temporary storage of SRW, were signed
in November 2006 and are under implementation.
Following a previous contract on the execution of radiological and
geological investigations on site, a contract for dose rate reduction in the
same area was signed in November 2007 and is under implementation.
€ 0.5 million
€ 0.2 million
Transport ship for RW and SNF
€ 71.6 million
€ 7.3 million
37
After completion of the preliminary design, a 71 Meuro contract for the
detailed design and construction of a ship for SNF and RW transportation
was signed on 28/07/08.Delivery time will be 30 months.
Operational costs (PMU) at June 2008, including the preliminary study of
interim storage facilities for RW
€ 7.8 million
€ 6.4 million
Russia
Chemical weapons
destruction:
Chemical weapons
destruction facility in
Pochep.
Construction of one
portion of the gas
pipeline in Schuch‘ye.
Further activity in
Schuch‘ye.
Bilateral Agreement between Italy and Russian Federation signed on 5
November 2003
Funding Commitment: €360 million. Ratification pending.
Programme completed in 2004.
Bilateral Agreement between Italy and Russian Federation signed on 17
April 2003, funds allocated, negotiations under way to identify new sector of
activity after original project already completed.
€7.7 million in
two years.
€5 million
€ 7.7
million.
Ukraine
Chernobyl Shelter
Fund
Italy contributed € 33 million since 1997. An additional contribution of € 8.5
million has been approved by the Parliament.
€ 8.5 million
38
Italy: Activities in Countries other than Russia and Ukraine in line with the GP objectives
Period Project
countries
Project type4 Project Name
/Summary
Project description Funds5
(Committed/Expended)
2005-2008 Iraq Seminars,
training courses,
workshops,
scientific
roundtables and
fellowships
Project for the
internationalisation
of Iraqi institutional-
scientific facilities
and collaboration
with Italian scientific
and academic centres
- 4 international workshops;
- 4 closed roundtables;
- 7 intensive seminars and training courses;
- short term fellowships involving participation in
specialisation seminars and primary scientific
events: in all, 59 fellowships;
- long-term fellowships (2-9 months) for retraining
and specialised activities at Italian Universities and
scientific institutes: in all, 52 Fellowships and 194
months in Italy. Project carried out by the Landau
Network – Centro Volta (LNCV).
Over € 1. 5 million
2005-2008 Iraq Acquisition of
technical and
scientific
equipment
Project for the
internationalisation
of Iraqi institutional-
scientific facilities
and collaboration
with Italian scientific
and academic centres
Academic publications and technical and scientific
equipment provided to selected Iraqi academic and
scientific institutions. Project carried out by the
Landau Network – Centro Volta (LNCV).
2005-2007 Kyrgyz
Republic
Redirection of
scientists and
technicians
Mechanism of
pollution of the
territory by Anthrax
agent
Project carried out by the Centro di Referenza
Nazionale per l‘Antrace in cooperation with the
ISTC.
2008-2010 Kyrgyz
Republic
Redirection of
scientists and
technicians
Mechanism of
pollution of the
territory by Anthrax
agent (Second Stage)
Project carried out by the Centro di Referenza
Nazionale per l‘Antrace in cooperation with the
ISTC.
USD 348,370 (from ISTC)
4 Please indicate activity type, such as seminar/workshop, capacity-building, equipment supply, facilities construction, physical operation, and, in particular, the
redirection/engagement of scientists and technicians. 5 Please fill in this column where appropriate. For seminar-type activities, information on the funds may not be so significant to the overall purpose of the discussion at the GPWG.
39
Japan
Country of
Project
Project Description Project Status: Milestones, Implementation
Comments
Funds Committed
(July 2002 -May 2009)
in 000’s
Funds Expended
(July 2002 - May 2009)
in 000’s
Russia Pilot project of dismantling a
Victor-III class nuclear
submarine and improvement of
related infrastructure at Zvezda
Shipyard
All the works were completed in December
2004
JPY854,000
JPY793,977
Russia Project of dismantling a Victor-I
class nuclear submarine
An implementing Arrangement for the
dismantlement of the five nuclear submarines
was signed in November 2005. Contracts
concerning a Victor-I class nuclear submarine
were sigend in September 2006 and the
dismantlement project was completed in 2008.
JPY869,864 JPY869,864
(Including Funds from
Australia and Republic
of Korea)
Russia Project of dismantling three
Victor III Class submarines
An implementing Arrangement for the
dismantlement of the five nuclear submarines
was signed in November 2005. Contracts
concerning threee Victor III Class submarines
were signed in August 2007 and one of them
has already been dismantled.
JPY 3,192,989 JPY1,064,330
(Including Funds from
Republic of Korea and
New Zealand)
Russia Project of dismantling a Charlie
I Class submarine
An implementing Arrangement for the
dismantlement of the five nuclear submarines
was signed in November 2005. Contracts
concerning a Charlie I Class submarines were
signed in January 2008 and the dismantlement
project was completed in 2009.
JPY 944,013 JPY944,013
Russia Cooperation for the construction
of an On-shore Storage Facility
for Reactor Compartment at
Razboynik bay
In 2007, Japan decided to cooperate for the
construction of this facility. A series of
negociations for the implementing arrangement
and for the specification of the items which
Japan will provide to Russia are conducted.
- -
Russia Cooperative R&D project on
fablication and irradiation of
For the period from 2004 to 2009, Japan
(PESCO and JAEA) and Russia (RIAR) has
USD 7,051.5 USD 6,506.5
40
vibro-packed MOX fuel
assemblies
carried out the cooperative R&D program in
order to demonstrate the integrity and reliability
of vibro-packed MOX fuel assemblies in BN-
600 reactor under the contact between MEXT
and PESCO. 21 fuel assemblies, which are
made from Russian surplus weapon grade
plutonium (120kg), were fabricated and
irradiated,
Ukraine Chernobyl Shelter Fund Contribution to the Chernobyl Shelter Fund - USD 21837
FSU IAEA Nuclear Security Fund Contribution to IAEA‘s Nuclear Security Fund USD 473 USD 341
Russia and
FSU
Redirection of former weapon
scientists through ISTC
Japan is a board member of ISTC since its
foundation in 1994, and contributes to its
activities and projects. To date, Japan has
funded more than 200 projects worth
approximately USD 60 million in total.
USD 13,520 USD 13520
Period Country of Project Project Type Project Name/Summary Project Description Funds
to be
scheduled
Kazakhstan provision of
equipment
Nuclear security upgrade
project for the Ulba
Metallurgical Plant and
Institute of Nuclear Physics
This project aims to improve the security-
related equipment of the facilities, by
upgrading protective fence, installing or
upgrading surveillance systems, etc..
Up to 500,000,000
JPY
(Committed)
2003- Asia Policy
Dialogue
Asian Senior-level Talks on
Non-proliferation (ASTOP)
The purpose of ASTOP is to discuss ways
to accelerate efforts for non-proliferation of
WMDs in Asia. It also touches upon s
possible assistance to Asian countries to
facilitate domestic implementation of non-
proliferation measures. At present four
Talks have been held since its first meeting
in November 2003. At the latest ASTOP
held in April 2008, officials from 10
ASEAN countries, China, Japan, RoK, US,
Australia Canada, NZ participated.
n/a
41
2004,02 Western Africa Seminar IAEA Safeguards Seminar Western Africa Economic Community
Seminar, in Burkina Faso
n/a
2004,03 Southern Africa Seminar IAEA Safeguards Seminar Southern Africa Development Community
Seminar, in Namibia
n/a
2004,11 Asia-Pacific Seminar IAEA Safeguards Seminar South Pacific Regional Seminar , in
Australia
n/a
2004,11 The Philippines Seminar IAEA Additional Protocol
Seminar
Seminar on ratification of Additional
Protocol
n/a
2005,09 International Seminar IAEA Integrated Safeguards
Meeting
Technical Meeting for Integrated
Safeguards, in Vienna
n/a
2005,09 Mexico Seminar IAEA Additional Protocol
Seminar
Workshop on Additional Protocol n/a
2005,1 Northern Africa Seminar IAEA Safeguards Seminar Outreach Seminar Maghreb Region,
Morocco
n/a
2006,07 Asia-Pacific Seminar IAEA Additional Protocol
Seminar
Additional Protocol Seminar for Asia &
Pacific countries, in Australia
n/a
2007,08 Vietnam Seminar IAEA Additional Protocol
Seminar
National Seminar on the Additional
Protocol to Vietnam's Safeguards
Agreement
n/a
2004 Asia Seminar Second Regional Meeting of
National Authorities of the
CWC in Asia, held in Beijing
n/a
2004 Middle East Seminar Regional Workshop on
promoting the universality of
the CWC, held in Malta
n/a
2004 Libya Seminar Assistance Visit to Libya Assistance to the Libyan authorities in
drafting their national legislation and other
administrative measures
n/a
2004 Cambodia Seminar Bilateral Assistance Visit to
Cambodia, held in
cooperation with UK &
OPCW
n/a
2005 Iraq Seminar 2nd Regional Workshop on
promoting the universality of
n/a
42
the CWC, held in the Hague,
in cooperation with UK,
USA, and OPCW
2005 Asia Seminar Third Regional meeting of
National Authorities of the
CWC in Asia, held in Iran
n/a
2006 Asia Seminar Fourth Regional Meeting of
National Authorities of the
CWC in Asia, held in
Indonesia
n/a
2006 Iraq Seminar 3rd Training Course on the
CWC for Iraqi Officials, in
cooperation with UK, USA
and OPCW
n/a
2007 The Philippines Seminar Industry Workshop on
Implementing the CWC, held
in Manila, in cooperation
with Australia and OPCW
n/a
2007 Asia Seminar Fifth Regional Meeting of
National Authorities in Asia,
held in Jordan (Amman)
n/a
2007 Iraq Seminar 4th Workshop on the CWC
for Iraqi Officials, held in
Jordan (Amman), in
cooperation with UK, USA
and OPCW
n/a
2008 Cambodia Seminar National Awareness
Workshop on the Chemical
Weapons, held in Phnom
Penh
n/a
2008 Asia Seminar Sixth Regional Meeting of
National Authorities in Asia,
held in Bangladesh (Dhaka)
n/a
43
2008 Laos Seminar National Awareness
Workshop on the Chemical
Weapons, held in Vientiane
n/a
2004- Asia Seminar Asia Non-Proliferation
Seminar focusing on
Maritime Cooperation
Through this seminar, participants are
expected to: (1) study procedures of
maritime non-proliferation activities of the
weapons of mass destruction, their delivery
systems and their related materials, (2)
establish networks among the participating
states, and (3) study the concept of PSI
(Proliferation Security Initiative)