Upload
kimberly-bates
View
213
Download
0
Embed Size (px)
Citation preview
André Augustinus10 September 2001
Common Applications to Prototype
A two way learning process
10 September 2001DCS workshop 2André Augustinus
Introduction
Why seeking common solutions?• Avoid duplication of work in the detectors• More efficient support from experts• Bulk purchase may reduce hardware costs• Spares can be shared; thus less spares• Easier maintenance, very important in the longer
term future• Aim for a coherent, homogeneous DCS
10 September 2001DCS workshop 3André Augustinus
Common Solutions
Try to find communalities across detectors• Need requirements
Look what solutions already exist or are proposed• In ALICE• In other experiments (JCOP)• In the accelerator and services
10 September 2001DCS workshop 4André Augustinus
Common Solutions
Currently we concentrate on the process level of DCS
For solutions we concentrate on:• CERN accepted commercial solutions• CERN supported solutions (IT/CO, JCOP, …)
10 September 2001DCS workshop 5André Augustinus
Prototyping
We would like to participate actively in the prototyping:• To learn the problems one might encounter• To learn and test current technologies
10 September 2001DCS workshop 6André Augustinus
Prototyping
How will we proceed• Participate actively in getting clear requirements
• This usually involves several iterations
• Based on the requirements, propose a solution that would fulfill the requirements (with help of experts in e.g. IT/CO)
• If accepted, provide support for the implementation and commissioning
• Collect feedback
10 September 2001DCS workshop 7André Augustinus
Objectives
The objectives of prototyping• Validate current ideas
• Ease of implementation and maintenance• Evaluate performance and reliability issues• Evaluate scalability
• Validate possible “final solutions” on “real systems”
10 September 2001DCS workshop 8André Augustinus
Objectives
The objectives of prototyping• Compose a “catalogue” of tested and supported
solutions, easy to implement and maintain• Guidelines• Framework, examples
Inconveniences: • To start it might be heavy on resources (manpower,
money and time), but it’s not a waste, it is an investment
• System might at first be “over-dimensioned”
10 September 2001DCS workshop 9André Augustinus
Current status
Currently concentrating mainly on the process level of DCS
Two pilots:• TPC
• High Voltage• Low Voltage• Cooling• Fieldcage (drift field)
• HMPID• High Voltage• Low Voltage• Fluid system
10 September 2001DCS workshop 10André Augustinus
Current status (HMPID)
Started well before the central team existed Gained a lot of experience with hardware
and software that is most likely to be used more generally in ALICE
• CAEN HV, PLC (Siemens), PVSS, DIM, SMI
Should make this expertise available to a wider public (even outside ALICE)
We learn more from them then they from us
10 September 2001DCS workshop 11André Augustinus
Current status (TPC)
Established first contacts with the various sub-systems: HV, LV, cooling and Fieldcage
High and Low Voltage:• Based on tests and surveys the TPC found a
devices that satisfied their needs: ISEG for HV and Wiener for LV
• We are currently investigating how these devices can fit in the global DCS picture (mainly a communication issue)
10 September 2001DCS workshop 12André Augustinus
Current status (TPC)
Cooling:• A test system has been built and is in principle
running. But might not be the most optimal choice to apply to the “final system”
• In the process of gathering more detailed requirements
• Based on this we should be able to propose a solution applicable to the “final system”; and adaptable to other detector needs
10 September 2001DCS workshop 13André Augustinus
Current status (TPC)
Fieldcage:• HV Power Supply, Current monitor, Cooling, Internal safety
• Most advanced as far as our involvement is concerned.
• Currently refining the user requirements for the system. We are preparing a third iteration.
• Close to proposing a solution that in principle should be a “final solution”.
• The prototype control system should be running by the end of the year.
10 September 2001DCS workshop 14André Augustinus
Current status (Testlab)
Announced in May, but little progress during summer• Siemens PLC is installed
Foreseen in the near future:• More “typical” hardware to be installed• Develop simple demo-applications
Goals:• Get acquainted with hardware and software• Use as a development platform for prototypes
10 September 2001DCS workshop 15André Augustinus
Future developments
Continue work on pilots Start work on a “vertical slice” of ALICE
• Build a control system from the hardware up to the highest level
• Validate the proposed architecture of the DCS (see a later talk)
10 September 2001DCS workshop 16André Augustinus
Conclusions
Inform us on what you are doing We need your requirements
• You’ll be getting more questionnaires• You’ll be invited for meetings• You’ll get examples/instructions to prepare your URD
The ideal DCS would have for all systems standard solutions, no “special cases”.
10 September 2001DCS workshop 17André Augustinus
Conclusions
We will not force you into a solution that will not match your requirements
We might be annoying you now, but you will profit from it in the long run
We are a collaboration