Upload
leonard-boone
View
219
Download
0
Embed Size (px)
Citation preview
AND-710/LAAS Page 1
Local Area Augmentation System (LAAS)
CAT I Contract Overview
Alaskan Region Briefing1 October 2002
Raymond Wasilko, FAA AND 710(202) 267-9432
AND-710/LAAS Page 2
Overview
• LAAS Description and Associated LAAS Ground Facility (LGF) Equipment
• Contract Structure
• LAAS LRIP Schedule
• LAAS CAT I Performance Requirements
• Facilities/Physical Integration
• Functional Integration
• Security
• Test and Evaluation
• Implementation and Transition
AND-710/LAAS Page 3
Space Segment
Airborne Segment
GPS and WAAS Signals
Corrections, Path Data, and IntegrityData
GPS and WAAS Signals
Local Area Augmentation SystemGround Facility (LGF)
(External to this program) (External to this program)
LAAS Integrated System
AND-710/LAAS Page 4
Auxiliary Equipment
Backup PowerTelco
LGF Standard Equipment Configuration
VDB Antenna
ProcessorGroup
LGF Processors
VDB Antenna
* As Required
NIMSAir Traffic
Control Unit(s)
Local Status PanelNIMS InterfaceMaintenance Data TerminalAir Traffic Control Unit
Operations and Maintenance Group
Equipment Shelter
Reference Receiver GroupGPS/SBAS Receiver (Qty. 4)GPS Antenna (Qty. 4)
VHF Data Broadcast Group
Primary VDB Subsystem (1)
VHF Transmitter (2)VHF Power Amplifier (2)VDB Monitor (2)
Equipment Shelter
Reference Receiver GroupGPS/SBAS Receiver (Qty. 4)GPS Antenna (Qty. 4)
Reference Receiver GroupGPS/SBAS Receiver (Qty. 4)GPS Antenna (Qty. 4)
Reference Receiver GroupGPS/SBAS ReceiverGPS Antenna
*AVS *Additional VDB Subsystem (0-3)VHF Transmitter (2)
VHF Power Amplifier (2)
VDB Monitor (2)
Note: Minimum 4 Reference Receiver Groups Required
Auxiliary Equipment
Backup PowerTelco
AND-710/LAAS Page 5
LAAS CAT I Contract Structure
Phase I. Limited Rate Initial Production (LRIP)
• Development and Test of LAAS Ground Facility
• Logistics Development & Support
• Turnkey Siting & Installation
• Engineering Services
• 10 LRIP LAAS Ground Facility Systems 4 Support Systems
Contractor Facility, WJHTC Atlantic City, AOS Oklahoma City, FAA
Academy Oklahoma City
6 Airport Sites Chicago O’Hare, Houston International, Juneau, Memphis, Phoenix,
Seattle
AND-710/LAAS Page 6
LAAS CAT I Contract Structure (Continued)
Phase II. Full Production
• Production Options Five (5) Option-Years
15-40 Systems Per Option Year (20/year target for FAA
install)
Technical Instruction, Manuals, Support Equipment, and Site
Spares
Engineering Services
Logistics Support
Depot Maintenance
Installation and Checkout
AND-710/LAAS Page 7
LAAS CAT I Program Schedule
•RFI (SPEC/Schedule)
•Draft RFO
•Final RFO
•LAAS Business Case
•Contract Award
•System Development (18 – 24 Months)
•LRIP Deliveries
•DT&E (5 Months)
•OT&E (5 Months)
•IOC (Commissioned)
•Production
•RFI (SPEC/Schedule)
•Draft RFO
•Final RFO
•LAAS Business Case
•Contract Award
•System Development (18 – 24 Months)
•LRIP Deliveries
•DT&E (5 Months)
•OT&E (5 Months)
•IOC (Commissioned)
•Production
FY01 FY02 FY03 FY04 FY05 FY06
4th Q
10/02
2nd Q
3/04
12/04
3/04 7/04
8/01
1/02
4/02
4/04 8/04
8/04
5/03 8/036/02
9/04
9/04 1/05
10/04 2/05
2/05 6/05
9/05
Proposed Revised Dates
AND-710/LAAS Page 8
·
LGF CAT I Performance Requirements
2190 hrs. Mean Time Between Failures (MTBF)
7200 hrs.Mean Time Between Critical Failures
0.99993Inherent Availability
4.0 metersVertical Accuracy 95%
8x10-6 Seconds SIS Continuity Risk
2x10-7 Per Approach / 10mIntegrity Risk / VAL
/15
Mean Time to Repair (MTTR) 0.5 hrs.
AND-710/LAAS Page 9
8 ft.
400 m
1.5 nm
23 nmVDB Antenna
Max. field strength coverage exclusion areaNot to exceed 200 meter radius about VDB antenna.
VHF Data Broadcast Coverage Volume
Min. field strength coverage exclusion area.
10,000 ft.
Earth
5º
DRAWING NOT TO SCALE
0.9º
AND-710/LAAS Page 10
Facilities
Land• Installation on Airport Property
• In some cases may have to install components off airport
Space• Equipment installed in a standard design ILS Shelter
• New Shelters will be procured
• Potential use of existing building or shelter
AND-710/LAAS Page 11
Facilities (Continued)
Environmental• FAA Order 1050.1D (Policies and Procedures for Considering Environmental Impacts)• FAA Order 1050.19 Environmental Due Diligence Audits in the Conduct of FAA Real Property Transactions• Initial Systems, ILS Overlays• Categorical Exclusion (CATEX) expected for most
installations• Separate Environmental Assessment for New Complex
Procedures
AND-710/LAAS Page 12
Facilities (Continued)
Cables• RF Cable for VDB, 1000’ Max from LGF Shelter• GPS Reference Receivers antenna assembly up to 5 miles from LGF Shelter• Use existing Fiber Optic Loop for data communications, if available at the Airport
Power Systems and Commercial Power• Equipment/system must comply with FAA-G-2100 & 6950.2• Backup Power (Supplemental Power)
Battery 4 Hours of Backup Capability
• Grounding, Bonding & Lightning Protection IAW FAA STDs 19 & 20
AND-710/LAAS Page 13
Facilities (Continued)
Shelter Requirements• Existing ILS Shelter Design
Physical Size – 4 Existing Sizes Maximum Size – 10 ft. x 16 ft. x 8 ft.
Contractors Design Based on current Logistic Center Design
May be two different sizes for Primary and AVS Shelter
• Heat and AC• Battery Backup Power • Telco
AND-710/LAAS Page 14
Air Traffic Control Unit
VHF Broadcast
Functional Integration LAAS-NAS Interfaces
FAA FACILITIES
AIR TRAFFIC CONTROLTOWER
(ATCT) and APPROACHCONTROL
LAAS
Ground Facility
Users
NASINFRASTUCTURE
MANAGEMENT SYSTEM(NIMS)
AND-710/LAAS Page 15
LAAS CAT I Security
• Security Certification and Authorization
Package (SCAP) will be generated IAW FAA
Order 1370.82
• LGF will be installed in secure area on airport
property
• Contractor personnel will meet all security
requirements at each respective airport
AND-710/LAAS Page 16
LAAS CAT ITest and Evaluation
• One-Time Tests Developmental Test (DT) (Design Qualification Tests)
Factory and on-site at WJHTC & AOS Oklahoma City
Operational Test (OT)/ Independent Operational Test & Evaluation On-site at WJHTC, AOS Oklahoma City and selected LRIP site
• Production Acceptance Test (PAT) on each system at
factory
• Site Acceptance Test (SAT) performed by contractor
at each site
• Field Familiarization Conducted at each site by AT & AF field personnel
Follows CAI and leads to IOC
AND-710/LAAS Page 17
LAAS CAT IImplementation and Transition
• Ten LRIP Systems … Contractor Turnkey Installed
• Turnkey efforts include
Site Survey,
Site Preparation,
Installation and Checkout, and
Site Acceptance Test.
• Turnkey options available for production systems if
FAA resources are not available
AND-710/LAAS Page 18
Siting Criteria Development
• Siting Working Group has been formed to develop siting criteria
for the CAT I LGF.
• The LGF siting criteria document provides guidance to the
Contractor to identify the optimum site which achieves CAT I
LAAS operational requirements at a given airport.
• One of the benefits of LAAS is the siting flexibility allowed by
the system design. For example, there are no siting location
constraints with respect to runway threshold as in terrestrial
precision approach and landing systems (e.g. ILS, MLS).
• Siting T&E and math modeling is being performed to define
object free areas and critical areas around the LGF antennas.
AND-710/LAAS Page 19
Siting Survey (LRIP Sites)
• Contractor Required to Identify Three Prospective Sites
• Government Will Select Preferred Site
• Survey Criteria Operational Requirements
Impact on Airport Operations
Constructability/ Cost
Environmental
• Contractor Will Use LGF Components to Collect Data
During Site Survey GPS Receivers
VDB Transmitters
AND-710/LAAS Page 20
Notional LAAS CAT I Generic Installation and Checkout Timeline
• Government Tasking Letter
• Site Survey Kick-Off Meeting
• Site Survey
• Site Survey Report
• Site Selection
• CSER … 50% Submission
• CSER … 90% Submission
• CSER … 100% Submission
• CSER Approval
• Site Preparation
• Start Installation and Checkout
• CAI
• Note: Total Time Equates to 16 ½ months
Fiscal Year
Day 30
Fiscal Year
Day 0
Day 165
Day 75
Day 255
Day 315
Day 375 435
Day 466Day 436
Day 496
1St Qtr. 2nd Qtr. 3nd Qtr. 4nd Qtr. 1St Qtr. 3nd Qtr. 2nd Qtr.
Day 30 45
Day 345
Day 195
AND-710/LAAS Page 21
Prospective LAAS CAT I Site-Specific LRIP Schedule … Juneau
• Government Tasking Letter (NLT)
• Site Survey
• Site Selection
• Start Site Preparation
• Start Installation and Checkout
• CAI
• IOC (Commissioned)
FY02 FY03
FY04 FY05 FY06
9/04
10/04
2/05
9/05
11/05
2/06
3/06
Note: Schedule based on required CAI date of 41 months after contract award.