Anatoli Romaniouk, TRT IB meeting October 30 th 2013 2
Preliminary plan for TRT/ID Meetings in 2014.Preliminary plan for TRT/ID Meetings in 2014.February
TRT meeting 3-5th February
TRT institute We. 5thID
ID combined 7th February
ATLAS week 10-14 February
May-June
ID commissioning WS May 19th
ATLAS 16-20 June (outside)
TRT meeting (outside?), 3 days 26-28 June?
October
ATLAS 6-10 October (CERN)
TRT meetings 14-16 October
TRT institute 15th October.I
ID commissioning 13 October
2014 Milestone runs:
•M1: Feb 17-21
•M2: March 31-April 4
•M3: May 19-23
•M4: July 7-11
•M5: Sept 8-12
•M6: Oct 13-17
Anatoli Romaniouk, TRT IB meeting October 30 th 2013
2014 M-Runs:
21 Oc 2013 S. Zimmermann, LS1-Weekly 3
M1 M2 M3 M4 M5 M6
PIX X1 X2 1 ready using events simulated at ROD2detector cold
IBL X1 X2 1 ready using events simulated at ROD2detector cold
SCT X1 1detector cold
TRT X
LAR X
TIL X
L1Calo X1 (X1) X2 (X2) 1 Readout only. 2 Trigger part once LAR/TIL available
CSC X1 X2 1 Old RODs, side A only 2 New ROD
MDT X
RPC X X provide trigger for M2 or latest M3
TGC X X2 2operating gas, trigger
BCM X
ALFA -- -- -- -- X --
LUCID -- -- -- -- -- X
TRT starts 31 March-4 April
Anatoli Romaniouk, TRT IB meeting October 30 th 2013
2014 Weeks
9 Oct 2013 S. Zimmermann, ATLAS Week, Marrakech 4
ATLAS outATLAS out
M1-6M1-6
ATLASATLAS
UpGradeUpGradeP & PP & P
TRTTRTIDID
TRT+IDTRT+ID
ID-WS ID-WS
TRT outTRT out
TRT+IDTRT+ID
ATLAS outside
?
Anatoli Romaniouk, TRT IB meeting October 30 th 2013 5
Outside TRT WSOutside TRT WS• 19th – 23rd May– ID Commissioning Workshop on Monday 19th May– ID Week 19-23rd May• Uncoupled with ATLAS or upgrade weeks. Chosen becausethe pixel/IBL installation should be completed andcommissioning is underway• 13th – 17th October– ID Week, with commissioning workshop on Monday– Directly after ATLAS week at CERN
1.Do we want to have it?
2.When: 26-28 of June? Other time?
3.Where?
4.3 possible places