163
ANALYSIS OF GAS TRANSMISSION NETWORK OF BANGLADESH AThesis Submitted to the Department of Chemical Engineering In partial fulfillment of the requirements for the Degree of Master of Science in Engineering (Chemical) By PRADIP CHANDRA MANDAL 1111111111111111111111111111111111 #96119# DEPARTMENT OF CHEMICAL ENGINEERING BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY, DHAKA BANGLADESH FEBRUARY 2002

ANALYSISOFGASTRANSMISSION NETWORK OF BANGLADESH

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

ANALYSIS OF GAS TRANSMISSION NETWORK OFBANGLADESH

A Thesis

Submitted to the Department of Chemical Engineering

In partial fulfillment of the requirements for the Degree of Master of Science in

Engineering (Chemical)

By

PRADIP CHANDRA MANDAL

1111111111111111111111111111111111#96119#

DEPARTMENT OF CHEMICAL ENGINEERING

BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY,

DHAKA

BANGLADESH

FEBRUARY 2002

RECOMMENDATION OF THE BOARD OF EXAMINERS

The undersigned certify that they have read and recommended to the Department of

Chemical Engineering, for acceptance, a thesis entitled Analysis of Gas Transmission

Network of Bangladesh submitted by Pradip Chandra MandaI in partial fulfillment of

the requirements for the degree of Master of Science in Chemical Engineering.

Chairman (Supervisor)

Member (Co-Supervisor):

Member:

4~~: ....Dr. Edmond GomesProfessorDept. of Petroleum and Mineral Resources Engg.

~.Q,:-:,.~).(:,~ .Dr. A K. M. A QuaderProfessorDepartment of Chemical Engg.~:~~.~ .

deG'~...................................... _ .Dr. AH.M. ShamsuddinChief GeologistUNOCAL Bangladesh LtdLake ViewHouse No. :12, Road No. :137Gulshan, Dhaka 1212.

Dr. Ijaz HossainProfessor and HeadDepartment of Chemical EngineeringBUET, Dhaka.

Member (External):

Date: February 19,2002

ABSTRACT

The gas transmission pipelines in Bangladesh were initially planned and constructed

targeting particular bulk consumers or potential load centers. In the early stage of the

development of the gas sector, the grid system was possibly not visualized. But over the

years the gas transmission system has expanded considerably and has become

complicated.

The objective of the study is to perform gas transmission network analysis of Bangladesh.

The study has been undertaken to simulate the present network system, identify its

limitations and suggest remedial measures. This study would be useful to understand the

performance of the present gas transmission system of Bangladesh. This study would also

analyze the existing pipeline capacity and examine the level of capacity utilization.

The work was completed with the help of a commercial software, PIPES 1M-Net. After

pressure matching at different load centers, manifold stations and branches, different

scenarios were studied for future performance prediction. Finally, the scenarios were

discussed and highlighted different important points through conclusion and

recommendation. The simulated results will be helpful to identify the bottlenecks and to

plan for future expansion of gas transmission system.

There are twenty-two gas fields in Bangladesh. But twelve producing gas fields can

produce 1300 MMSCFD of gas from 53 gas wells. The study shows that Ashugonj

metering station is the focal points of the National Gas Grid. Gas from the North-Eastern

Gas Fields are being transported through the North-South pipeline to Ashuganj Manifold

Station of GTCL from where it is further transmitted to Titas franchise area (TFA) and

Bakhrabad franchise area (BFA) through Brahmaputra Basin pipe line and Ashuganj-

Bakhrabad Transmission pipe lines. From Bakhrabad Gas Field, Bakhrabad-Chittagong

Pipeline transports part of the required gas for Chittagong. The remaining gases for

Chittagong is supplied from Salda, Meghna and Sangu gas fields.

The results show that effective pipeline diameter of major transmission lines have

decreased due to condensate accumulation. Hence pigging is necessary. Rashidpur-

Ashugonj loop line is essential to supply growing gas demand. It will increase the

. capacity of the North-South pipeline by 456 MMSCFD. To meet the future gas demand

of the Western region, the results show that another loop line is necessary from

Rashidpur-Ashugonj loop line to Dhanua. It will increase the supply of Ashugonj-Elenga

pipeline by 175 MMSCFD. Analysis also shows that it is a better option to install a

compressor station at Bakhrabad to transmit the low-pressure gas of the field through the

high-pressure pipeline.

ii

ACKNOWLEDGEMENT

I would like to express my deep respect to Dr. Edmond Gomes, Professor of the

Department of PMRE, for his valuable guidance and supervision throughout the entire

work.

I would like to express my profound gratefulness to Dr. A.K.M.A. Quader, Professor of

the Department of Chemical Engineering, for his valuable supervision of the work.

I would like to thank Engr. Kh. A. Saleque, GM (R-A Project), GTCL, for his co-

operation in providing me with the permission in collecting gas transmission data and

valuable suggestions.

I would like to express my gratitude to Mr. Tahshin Haq, Engineer, UNOCAL

Bangladesh Ltd., for providing data and encouragement to complete this work.

I would like to thank A. K. M. Shamshul Alam, GM (Planning and development),

JGTDSL, for his administrative support and co-operation, and for providing me with

necessary facilities in collecting the required gas transmission and distribution data.

I would like to express my profound gratefulness to my parents for their support and to

my brothers and sisters, for their support and inspiration.

I would also like to thank the University of Alberta-BUET -CIDA linkage Project officials

for setting up computer facilities in PMRE department, which made this work possible.

iii

USEFUL CORRESPONDENCES

Abbreviations, Acronyms and Terminology

A-B

N-S

B-D

B-C

A-E

MAOP

SCADA

TFA

JFA

BFA

WFA

R-A

Petrobangla

UFFL

ZFCL

APSCUFL

BCIC

EPZ

IOC

NGFF

PSC

PUFF

SHELL

UNOCAL

Ashugonj-Bakhrabad

North-South

Bakhrabad-Demra

Bakhrabad-Chittagong

Ashugonj-Elenga

Maximum Allowable Operating Pressure

Supervisory Control and Data Acquisition

Titas Franchise Area

Jalalabad Franchise Area

Bakhrabad Franchise Area

Western Franchise Area

Rashidpur-Ashugonj

Bangladesh Oil Gas and Mineral Corporation (BOGMC)

Urea Fertilizer Factory Limited

Zia Fertilizer Company Limited

Ashugonj Power Station

Chittagong Urea Fertilizer Limited

Bangladesh Chemical Industries Corporation

Export Processing Zone

International Oil Company

Natural Gas Fertilizer Factory

Product Sharing Contract

Pol ash Urea Fertilizer Factory

Shell Bangladesh Exploration and Development B.Y.

UNOCAL Bangladesh Ltd.

iv

Operating Companies of Petrobangla

BAPEX

BGFCL

BGSL

GTCL

JGTDSL

RPGCL

SGFL

TGTDCL

Bangladesh Petroleum Exploration Company Limited

Bangladesh Gas Fields Company Limited

Bakhrabad Gas System Limited

Gas Transmission Company Limited

Jalalabad Gas Transmission and Distribution Systems Limited

Rupantarita Prakritik Gas Company Limited

Sylhet Gas Fields Limited

Titas Gas Transmission and Distribution Company Limited

Terminology for metering stations

CGS City Gate station, the pressure is being reduced from the transmission pipelinepressure down to 350/300 psig.

TBS Town Bordering Station reduces pressure from 350/300 psig down to 150 psig.

DRS District Regulating Station reduces pressure from 150 psig down to 50 psig.

Symbols, Measures and Conversion Factors

K

Lac

M

Crore

G

I ton

I barrel (bbl)

I BTU

MCF

TCF

I psig

I atmospheric

= 103

= 105 (Bangladesh Terminology)

= 106 (except for MCF)

= 107 (Bangladesh Terminology)

= 109

= 1000 kg

= 0.159 cubic meter

= 0.252 kilocalorie

= thousand standard cubic feet= Trillion (1,000 billion) cubic feet

= 0.06895 bar

= 14.7 psia

v

(

Chapter

J.

2.

TABLE OF CONTENTS

Abstract

Acknowledge

Useful Correspondences

Table of Contents

List of Tables

List of Figures

List of Appendices

Introduction

Literature Review

2.1 Introduction

2.2 Types of Pipelines

2.2.1 Gas Pipelines

2.2.1.1 Gas Gathering

2.2.1.2 Gas Transportation

2.2.1.3 Distribution Pipeline

2.2.2 Oil Pipelines

2.2.3 Product Pipeline

2.2.4 Two-phase pipeline

2.2.5 LNG Pipelines

2.3 Uses of Natural Gas

2.4 Sector Wise Natural Gas Consumption

2.4.1 Ammonia-Urea Fertilizer Sector

2.4.2 Trends of Natural Gas Uses for Power Generation

2.4.3 Industrial, Domestic and Commercial Sectors

2.5 Gas Sector of Bangladesh

2.5.1 Oil and Gas Exploration in Bangladesh

2.5.2 Gas Fields of Bangladesh

VI

. 'PageNo.HI

III

IV-V

VI-IX

X

XI-Xll1

XIV

1-3

4-34

4

5

5

5

6

6

6

7

7

7

7

8

10

13

17

19

19

22

2.5.3 Present Demand and Supply Scenario 27

2.5.4 Future Demand and Supply Scenario 30

2.6 Gas Transmission Network 32

3. PIPESIM 35-41

3.1 Introduction 35

3.2 PIPESIM-Net 35

3.3 Black Oil and Compositional Data 36

3.4 Calibration Data 37

3.5 Model Overview 38

3.6 Network Validation 39

3.7 Flow Correlations 39

3.7.1 Horizontal Flow 39

3.7.2 Vertical Flow 40

3.7.3 Single Phase Correlations 40

3.8 Convergence 41

4. Gas Transmission System and Related Data 42-51

4.1 Introduction 42

4.2 Network Analysis 42

4.3 Gas Composition 46

4.4 Diameter and Length of Transmission Lines 49

5. Steady- State Flow of Gas through Pipes 52-71

5.1 Introduction 52

5.2 Gas Flow Fundamentals 52

5.3 Types of Single-Phase Flow Regimes and Reynolds Number 53

5.4 Pipe Roughness 54

5.5 Pressure Drop Calculations 555.5.1 The Pressure Drop due to Potentia! Energy Change 555.5.2 The Pressure Drop due to Kinetic Energy Change 555.5.3 The Frictional Pressure Drop 56

vii

5.6

5.7

5.8

Allowable Working Pressures for Pipesr

Allowable Flow Velocity in Pipes

Horizontal Flow

57

57

57

5.8.1 Non- Iteration Equations for Horizontal Gas Flow 58

5.8.2 A More Precise Equation for Horizontal Gas Flow (The 59

Clinedinst Equation)

6.

5.9 Gas Flow through Restrictions

5.10 Sub-Critical Flow

5.11 Critical Flow

5.12 Flowing Temperature in Horizontal Pipelines

5.13 Steady-State Flow in Pipeline Networks

5.13.1 The Mathematical Models for the Individual NCE's

5.13.2 Loop Less System

5.13.3 Looped Systems

5.13.3.1 Single-Loop System

5.13.3.2 Multiple-Loop System

Simulation Results

606061

61

62

63

65

666769

72-115

6.1

6.2

Introduction

Demand-supply Scenario of High-pressure gas transmission lines

72

72

of Bangladesh Using Current Data (from 12-July-00 to 13-July-OO)

6.2.1 North-South Gas Transmission Pipe Line 72

6.2.2 Bakhrabad to Chittagong Gas Transmission Pipe Line 74

6.2.3 Ashugonj to Bakhrabad Gas Transmission Pipe Line 75

6.2.4 Bakhrabad to Demra Gas Transmission Pipe Line 75

6.2.5 Ashugonj to Elenga Gas Transmission Pipe Line 75

6.2.6 Titas - Narshingdi - Demra Gas Transmission Pipe Line 76

6.2.7 Titas - Narshingdi - Joydevpur Gas Transmission Pipe 76

Line

6.2.8 Monohordi - Narsingdi - Shiddirgonj Gas Transmission 77

Pipe Line

6.2.9 Western Region Gas Transmission Pipe Line 77

viii

6.3

6.4

6.5

6.6

6.7

6.8

6.2.10 Network Analysis

Modification of Network by Using Known Pressure at Bakhrabad

Gas Field

Modification of Network by Setting up a Compressor Station at

Bakhrabad Gas Field

Gas Demand-Supply Scenario of High Pressure Transmission Line

at Maximum Load

Modified Network Using R-A Loop Line

Extension of Network up to Bheramara

Extension of Network up to Khulna without Modification

6.8.1 Extension of Network up to Khulna with A-D Loop Line

6.8.2 Modification ofNolka to Khulna line by Using Loop Line

from R-A Loop Line to Dhanua

6.8.3 Modified Final Network by Using Compressor Station at

Monohordi

77

85

90

93

96

101

104

107

110

113

References

Nomenclature

Discussions

Conclusions and Recommendations

116-118

119-120

119

120

121-143

144-145

146-147

Conclusions

Recommendations

Appendices

8.1

8.2

7.

8.

ix

LIST OF TABLES

31

334748

49

29

29

28

. Page'No'.

9

13

16

2021

24

25

28

Sector Wise Natural Gas Consumption

Connected Maximum Loads of Gas for Fertilizer Sectors

Trends of Natural Gas Uses for Power Generation

Exploration Phases of Bangladesh

Exploration Activities in Bangladesh since 1972

Gas Fields of Bangladesh

Production Capacities of Various Gas Fields

Downstream Demand and Consumption of Natural Gas of Jalalabad

Gas Franchise Area (JFA), Greater Sylhet

Downstream Demand and Consumption of Natural Gas of Titas

Gas Franchise Area (TFA)

Downstream Demand and Consumption of Natural Gas of

Bakhrabad Franchise Area (BFA)

Downstream Demand and Consumption of Natural Gas of Western

Region Franchise Area (WFA)

Average Base Case SupplylDemand (in MMCFD)

Gas Transmission Network

Gas Composition of Natural Gas in Different Gas Fields

Sales Gas Specification ofTitas Franchise Area

Length and Diameter of Major Gas Transmission Pipelines of

Jalalabad Franchise Area

Table 4.4 Length and Diameter of Major Gas Transmission Pipelines of Titas 50

Franchise Area

Table 2.12

Table 2.13

Table 4.1

Table 4.2

Table 4.3

Table 2.11

Table 2.10

Table 2.9

Table 2.1

Table 2.2

Table 2.3

Table 2.4

Table 2.5

Table 2.6

Table 2.7

Table 2.8

Table 4.5 Length and Diameter of Major Gas Transmission Pipelines of 50

Bakharabad Franchise Area

Table 4.6 Length and Diameter of Major Gas Transmission Pipelines of 51

Western Region Franchise Area

Table 6.1 Comparison of Simulated Pressure to the Measured Pressure 83

x

Page No ..10II

121417233843

III 45

Figure 2.1

Figure 2.2

Figure 2.3

Figure 2.4

Figure 2.6

Figure 2.5

Figure 3.1

Figure 4.1

Figure 4.2

Figure 4.3

Figure 5.1

Figure 5.2

Figure 5.3

Figure 5.4

Figure 6.1

Figure 6.2

Figure 6.3

Figure 6.4

Figure 6.5

Figure 6.6

Figure 6.7

Figure 6.8

Figure 6.9

LIST OF FIGURES

Sector Wise Natural Gas Consumption

Natural Gas Consumption in Bangladesh

Urea Plants in of Fertilizer Factories of Bangladesh

Power Plants in Bangladesh

Trends of Natural Gas Uses for Power Generation

Natural Gas Fields in Bangladesh

Types of Network Used in PIPESIM-Net

The Geographical Areas for the Gas System Development Plan

Gas Transmission Network, Main High Pressure Lines

Bangladesh

Gas Transmission Network, Possible Extension m the Western

Region

Loop Less Pipeline System

Single Looped Systems

Multiple Looped System

Illustration for Stoner's Method

High Pressure Gas Transmission Lines of Bangladesh Using

Current Data

Variation of Pressure along the Major Gas Transmission Lines

Change of Flowrate along the Major Gas Transmission Lines

Change of Liquid Hold up along the North-South line

Demand-Supply Scenario of High-pressure Gas Transmission

Lines of Bangladesh Modified by Known Pressure at Ashugonj

Calculated and Measured Pressure along the N-S Line

Variation of Pressure along the Major Gas Transmission Lines

after Modification

Variation of Pressure along the Major Gas Transmission Lines

Demand-Supply Scenario of High-pressure Gas Transmission

Lines Modified by Using Known Pressure at Bakhrabad Gas Field

xi

46

65

67676973

7878

8081

8282

84

87

Figure 6.10

Figure 6.11

Figure 6.12

Figure 6.13

Figure 6.14

Figure 6.15

Figure 6.16

Figure 6.17

Figure 6.18

Figure 6.19

Figure 6.20

Figure 6.21

Figure 6.22

Figure 6.23

Figure 6.24

Variation of Pressure along Major Transmission Lines Modified

by Using Known Pressure at Bakhrabad Gas Field

Variation of Flow Rate along Major Transmission Lines Modified

by Using Known Pressure at Bakhrabad Gas Field

Effect of Separator on North-South Line

Demand-Supply Scenario of High Pressure Gas Transmission

Lines Modified by Setting up a Compressor Station at Bakhrabad

Gas FieldVariation of Pressure along Major Gas Transmission Lines by

Dropping Bakhrabad Gas Field from the Network

Change of Flow Rate along Major Gas Transmission Lines by

Dropping Bakhrabad Gas Field from the Network.

Effect of Compressor at Bakhrabad Gas Field

Gas Demand-Supply Scenario of High Pressure Transmission Line

at Maximum Load

The Variations of Pressure along the Major Transmission Lines

Modified by Maximum Load

Change of Flow Rate along the Major Transmission Lines

Modified by Maximum Load

Demand-Supply Scenario of High Pressure Gas Transmission

Lines Modified Network by Using R-A Loop Line

The Variations of Pressure with the Length after Modified by R-A

Loop LineChange of Flow Rate with the Length after Modified by R-A Loop

LineDemand-Supply Scenario of Gas Transmission Lines Modified by

Using R-A Loop Line and Mentioning Known Pressure at

AshugonjThe Variations of Pressure with the Length after Modified by R-A

Loop Line for Pressure Matching

xii

88

88

8991

92

92

93

94

95

95

98

99

99

100

101

Figure 6.25 Demand-Supply Scenario of High Pressure Gas Transmission 102

Lines by Extension of Network up to Bheramara

Figure 6.26 Variation of Pressure Drop along Major Transmission Lines by 103

Extension of Network up to Bheramara

Figure 6.27 Change of Flow Rate along the Major Transmission Lines by 103

Extension of Network up to Bheramara

Figure 6.28 Demand-Supply Scenario of High-pressure Gas Transmission 105

Lines by Extension of Network up to Khulna without Modification

Figure 6.29 The Variation Pressure of Major Transmission Lines by Extension 106

of Network without any Modification

Figure 6.30 Change of Flow Rate along the Major Transmission Lines by 106

Extension of Network without any Modification

Figure 6.31 Demand-Supply Scenario of High Pressure Gas Transmission 108

Lines by Extension of Network up to Khulna with A-D Loop Line

Figure 6.32 The Variation of Pressure along the Major Transmission Lines by 109

Extension of Network up to Khulna with A-D Loop Line.

Figure 6.33 Change of Flow Rate along the Major Transmission Lines by 109

Extension of Network up to Khulna with A-D Line

Figure 6.34 Demand-Supply Scenario of High Pressure Gas Transmission III

Lines modified by Using Loop Line from R-A Loop Line to

Dhanua

Figure 6.35. The Pressure Drops of Major Transmission Lines of Nolka to 112

Khulna Pipeline Using Loop Line from R-A Loop Line to Dhanua

Figure 6.36 Change of Flow Rate along the Major Transmission Lines of 112

Nolka to Khulna Pipeline Using Loop Line from R-A Loop Line

to Dhanua

Figure 6.37 Demand-Supply Scenario of High Pressure Gas Transmission 114

Lines modified Final Network by Using Compressor Station at

Monohordi

Figure 6.38 The Variation of Pressure along the Major Transmission Lines lIS

modified by Using Compressor Station at Monohordi

Xlll

LIST OF APPENDICES

-1IP .. :" -~---_.,_ .. _~-<>---. ----. -~--~--~--- ,"

Appendix I

Appendix 2

Appendix 3

Appendix 4

Appendix 5

Appendix 6

Simulated Results of High Pressure Gas Transmission Lines of

BangladeshSimulated Results of High Pressure Gas Transmission Lines of

Bangladesh modified by Known Pressure at Ashugonj

Simulated Results of High Pressure Transmission Lines Using

Known Pressure at Bakhrabad Gas Field.

Simulated Results of High Pressure Transmission Lines by

Setting up a Compressor Station at Bakhrabad Gas Field

Simulated Results of High Pressure Transmission Lines at

Maximum Load.

Simulated Results of High Pressure Transmission Lines

Modified Network Using R-A Loop Line.

121

123

125

127

129

130

Appendix 7 Simulated Results of High Pressure Transmission Lines 132

Modified Network Using R-A Loop Line by Using Known

Pressure at Ashugonj.

Appendix 8 Simulated Results of High Pressure Transmission Lines 135

Modified Network by Extension of Network up to Bheramara.

Appendix 9 Simulated Results of High Pressure Transmission Lines 137

Extension of Network up to Khulna without any Modification

Appendix 10 Simulated Results of High Pressure Transmission Lines 138

Extension of Network up to Khulna with A-D Loop Line.

Appendix II Simulated Results of High Pressure Transmission Lines, 140

Modification of Nolka to Khulna Line by Using Loop Line

from R-A Loop Line to Dhanua

Appendix 12 Simulated Results of High Pressure Transmission Lines 143

~ Modified Network by Using Compressor Station at Monohordi

xiv

Chapter 1

INTRODUCTION

The importance of mineral and energy resources cannot be over emphasized in a

developing country like Bangladesh. These resources are not only considered as the driving

" force but also the backbone of modem economy. These are vital requirement for

industrialization, power generation etc. and thus for enhancement of the social standards of

people through economic development and attainment of comfortable life style. In this

context it is important that the government should make sincere efforts for the development

of this sector.

:':"-

Natural gas is the most important non-renewable resources in Bangladesh. Over the years it

has acquired a position as.an alternative to oil. It is also regarded, as a main source of power

generation. Its use and requirement has been greatly enhanced in recent times. During the

pre-liberation period, around 1968-69, the use of gas stood at 19 percent of total

commercial energy only, when the consumption of oil was more than 70 percent. From 80's

the consumption of natural gas rose a little above 37 percent, and by 90's the consumption

of gas exceeded 70 percent and simultaneously it distinct decrease was noticed in the

consumption of oil and it came down to 30 percent.

Bangladesh has discovered 22 gas fields and one oil well (Sylhet 7 at Haripur). But 12

producing gas fields can produce 1300 MMCFD of gas from 53 gas wells. In 22 gas fields,

total GIIP (proven + probable) reserve is about 24.745 TCF of which about 15.507 TCF (1)

has been confirmed. Out of recoverable reserve, 4.08 TCF gas has been consumed (I). The

present peak demand of 1089 MMCFD (2) which can now be met from the current peak

production of 1300 MMCFD after drawing gas from private producers, namely, UNOCAL

il., Bangladesh Ltd. and Shell Bangladesh Exploration and development B.V. Of the total gas

produced, 35 percent is used for fertilizer, 45 percent for power generation and 20 percent

for other purpose (I).

1.J; 2.

3.

4.

The gas transmission pipelines In Bangladesh were initially planned and constructed

targeting particular bulk consumers or potential load centers. In the early stage of the

development of the gas sector, the grid system was not visualized. But over the years the

gas transmission system has expanded considerably and has become complicated. Four

Companies of Petrobangla'such as Gas Transmission Company Ltd. (GTCL), Titas Gas

Transmission and Distribution Company Ltd. (TGTDCL), Bakhrabad Gas Systems Ltd.

(BGSL), Ialalabad Gas Transmission and Distribution Company Ltd. (IGTDCL) and two

international companies (Unocal Bangladesh Ltd., Shell' Bangladesh Exploration and

Development B.V.) are responsible for operation and maintenance of their respective

transmission pipelines.

As new gas based industries and power plants are being set up, the existing gas

transmission system is being stressed to meet the demand. To overcome this, a loop line is

being constructed from Kailashtilla to Ashuganj to flow more gas from Sylhet region. To

study the performance and the effect of any future development, it is required to analyze the

whole transmission network.

The objective of this study is to perform gas transmission network analysis of Bangladesh.

Various components of the objective are:

i) to simulate the present gas transmission net~ork system and compare with the

actual performance

ii) to identify any limitation of the system

iii) to study the effect of future pipeline expansion, loads etc.

This study has been carried out using a software called PIPESIM. Baker I ardine Inc. (UK)

developed it. Building the pipeline network using the software can be divided in to a

number of stages:

Collecting all necessary data on the transmission network

Setting up the model and naming components

Setting global default (fluid composition, unit etc.)

Setting boundary conditions at wells, sources and sinks (loads)

2

5. Running the model and analyzing the results

The study has been undertaken to simulate the present network system, identify its

limitations and suggest remedial measures. This study would be useful to understand the

performance of the present gas transmission system of Bangladesh. This study would also

analyze the existing pipeline capacity and examines the level of capacity utilization. The

simulated results will be helpful to identify the bottlenecks and to plan for future expansion.~

of gas transmission system.

(

'-

3

"

!

Chapter 2

LITERATURE REVIEW

2.1 Introduction

The natural gas has established itself as a major indigenous hydrocarbon resource in

Bangladesh. It is the chief source of fuel for industrial, commercial and household

operations as well as for power generation. On September 18, 2001 the production was

1042 MMSCFD and the two laCs' contribution was 176 MMSCFD (1) The present peak

demand is about 1089 MMSCFD.

The first discovery of natural gas was made in 1955 at Haripur. Since then the exploration

has led to the discovery of 22 gas fields and one oil field. There are now 53 producing wells

capable of producing about 1300 MMSCFD of gas from 12 gas fields (1) The exploration

activities for gas and oil in Bangladesh started with the exploration at Sitakunda in 1908.

National Energy Policy (NEP), promulgated in 1995, indicated an energy-growth rate of

8.77% by year 2000 equivalent to 12 million tons of oil and 19 million tons of oil

equivalents, representing energy growth rate of 8.86% (3). The major part of the future

energy demand would be met from natural gas and it is estimated that gas demand would

reach about 1450 MMSCD (average) and 1700 MMSCFD (maximum) by 2005 and 1900

MMSCFD (avg.) and 2250 MMSCFD (4) by 2010 (max.) ..

The uses of Natural gas in Bangladesh can be broadly classified into five categories,

namely, power, fertilizer, industrial, commercial and domestic. The fertilizer sector utilizes

natural gas as a feed stock as well as fuel while the remaining sectors use it as a fuel. The

current consumption pattern shows that fertilizer sector consumes approximately 35%,

power 45% and other sectors (industry, domestic, commercial arid seasonal) 20% of the

gaseS). \,

4

2.2 Types of Pipelines

A network of sophisticated pipeline systems transports oil, natural gas and petroleum

products from producing fields and refineries around the world to consumers in every

nation. This network gathers oil and gas from hundreds of thousands of individual wells,

including those in some of the world's most remote and hostile areas. It distributes a range

of products to individuals, residences, businesses and plants.

Most gas and oil pipelines fall into one of three groups: gathering, transportation or

distribution (6) Other pipelines are needed in producing fields to inject gas, water or other

fluids into the formation to improve gas and oil recovery and to dispose of salt water often

produced with oil.

2.2.1 Gas Pipelines

In general, gas pipelines operate at higher pressure than crude lines; gas is moved through a

gas pipelines by compressor rather than by pumps; and the path of natural gas to the user is

more direct.

2.2.I.I Gas Gathering

Gas well flow lines connect individual gas wells to field gas treating and processmg

facilities or to branches of a large gathering system. Most gas wells flow naturally with

sufficient pressure to supply the energy needed to force the gas through the gathering lines

to the processing plant. Down hole pumps are not used in gas wells, but in some very low

pressure gas wells, small compressors may be located near the well head to boost the

pressure in the line to a level sufficient to move the gas to the process plant.

5 r'I\ \'_ ..

2.2.1.2 Gas Transportation

From field processing facilities, dry, clean natural gas enters the gas transmission line

system for movement to cities where it is distributed to individual business, factories and

residences. Distribution to the final users is handled by utilities that take custody of the gas

from the gas transmission. pipeline and distribute it through small, metered pipelines to

individual customers.

Gas transmission lines at relatively high pressures. Compressors at the beginning of the line

provide the energy to move the gas through the pipeline. Then compressor stations are

required at a number of points along the line to maintain the required pressure. The distance

between the compressors varies, depending on the volume of gas, the line size and other

factors. Adding compressors at one or more of these compressor stations or by building an

additional compressor station often increases capacity of the system. The size of the

compressors with in the station varies over a wide range, but many stations include several

thousand horsepower in one station.

2.2.1.3 Distribution Pipeline

Through distribution networks of small pipelines and metering facilities, utilities distrjbute

natural gas to commercial, residential and industrial users.

2.2.2 Oil Pipelines

Flow lines, the first link in the transportation chain from producing well to consumer, are

used to move produced-oil from individual wells to a central point in the field for treating

and storage.

6

2.2.3 Product Pipeline

The industry's products pipeline system is a sophisticated network. Many segments of the

system are highly flexible in both capacity and the products that can be transported. One

part of this system moves refined petroleum products from refineries to storage and

distribution terminals in consuming areas. Another group of product pipelines is used to

transport liquefied petroleum gases (LPG) and natural gas liquid (NGL) from oil and gas

processing plants to refineries and petrochemical plants.

2.2.4 Two-phase Pipeline

In most cases, it is desirable to transport petroleum as either a gas or a liquid in a pipeline.

In a line design to carry a liquid, the presence of gas can reduce flow and pumping

efficiency; in a gas pipeline, the presence of liquids can reduced flow efficiency and

damage gas compressors and other equipment.

2.2.5 LNG Pipelines

Liquefied natural gas (LNG) is natural gas cooled and compressed to a temperature and

pressure at which it exits as a liquid. Significant volumes of natural gas are transported in

the liquid phase as LNG, but these shipments are made by special ocean tanker rather than

by long distance pipeline.

2.3 Uses of Natural Gas

The uses of natural gas in Bangladesh can be broadly classified into the following five

categories:

Fertilizer: As raw material for production of Urea Fertilizer.

Power: As fuel for generation of electricity.

Industrial: As fuel for various industries.

Commercial and

7

(I\

oj)

".

Domestic.

The current consumption pattern shows that fertilizer (ammonia-urea) sector consumes

approximately 35%, power 45% and other sectors (industry, domestic, commercial and

seasonal) 20% of the gas (5).

2.4 Sector Wise Natural Gas Consumption

During the international energy crisis of the 1970's, the rapid rise in international oil prices

increased the demand for natural gas in different sectors for its lower cost. A more

attractive incentive to use natural gas is its easy and clean burning with environment

benefits. With the growth of the economy, demand for energy has increased.

From Table 2.1 and Figure 2.1 show that natural gas consumption In the power and

fertilizer sector started increasing drastically in the mid-80s. This is because at that time

most of the power plants in the eastern grid was being converted from diesel to natural gas

and at the same time some new power plants based on gas were added to the national grid.

In the fertilizer sector, three big urea plants were installed from the middle of 80s to the

beginning of 90s. Industrial and commercial demands also increased during that period,

although the overall percentages or these two sectors were not as significant as the other

two.

In 1996-97, consumption of natural gas in fertilizer sector decreased due to supply crisis of

natural gas in the Chittagong region. As a result, Chittagong Urea Fertilizer factory (CUFL)

stopped its production. Power sector was given priority for supplying gas at that time. After

completion of Ashuganj-Bakhrabad pipeline (A-B pipeline) and production of gas from

Sangu and Jalalabad gas field by two IOCs, CUFL again started production and natural gas

consumption in fertilizer sector increased. A similar supply shortage also occurred during

1989-91 'period due to a fatal accident at Ghorasal Fertilizer Factory. Presently there is no

shortage of supply and daily demand is about 930 MMSCFD.

8

>

,'.-

Table 2.1 : Sector Wise Natural Gas Consumption (8)

Year .•.~~"' '.- - ,~ .,. I- .,"'" ~:; - "'Sectors (MMSCF):-', ~'_". ~~~I.~-r "':~~-":=!'I')";',-~~..:~~'- .,

Power Fertilizer Industrial Commercial. Domestics • Total

1967-68 225 0 0 0 0 225

1968-69 1019 0 5 9 I 1034

1969-70 1140 1828 145 26 4 3143

1970-71 3419 4225 255 41 22 7962

1971-72 3103 602 322 33 36 4096

1972-73 4513 9669 843 66 87 15178

1973-74 7419 10559 1462 115 146 19701

1974-75 6063 2098 1784 181 277 10403

1975-76 6535 11018 2334 266 489 20642

1976-77 8200 10027 3047 370 766 22410

1977-78 9327 8311 3742.17 571.27 1125.43 23076.87

1978-79 9209 11146 4557.36 854.55 1873.09 27640

1979-80 11018 11975 5182.99 1078.10 2561.84 31815.93

1980-81 13321 11210 5978.60 1342.47 3390.00 35242.07

1981-82 18010 19836 7391.06 1680.98 4214.25 51132.29

1982-83 21999 19140 7812.44 1917.57 5217.24 56086.25

1983-84 22886 25805 8687.83 2057.67 5785.14 65221.64

1984-85 38292.70 24296 11447.76 2232.62 6318.95 82588.03

1985-86 39778.27 30070.50 16352.56 2721.54 6796.95 95719.82

1986-87 51852.09 33474.5 18673.16 3415.81 6840.79 114256.35

1987-88 63054.45 50978.72 15665.47 3603.63 7590.41 140892.68

1988-89 66455.80 57886.51 1497.08 3126.15 9261.28 151026.82

1989-90 75557.45 55909.11 13892.44 3098.67 10418.70 158876.37

1990-91 82556.11 54172.33 13911.78 2930.55 10529.37 164100.14

1991-92 88105.07 61642.31 14088.55 3135.73 11645.93 178617.59

1992-93 93212.08 69176.18 15801.05 2547.99 13495.68 194232.98

1993-94 97491.11 74434.89 19895.15 2853.89 15603.05 210278.09

1994-95 107437.37 80464.44 23891.25 2896.42 18781.78 233471.26

1995-96 110827.15 90979.45 27189.53 3029.01 20776.44 252801.58

1996-97 110864.20 77828.57 29303_97 3393.48 22869.06 244259.28

1997-98 123391.93 80000.68 33046.61 3496.83 24984.67 264920.72

1998-99 140837 82730 35779 3652 27183 290181

1999-00 149355 84894 41271 3836 29675 3090312000-01 175204 88465 48094 4066 31872 347701

Total 1761678 1254852 433349.8 64645.93 300638.1 3827964

9

.'..\!!~..(.• .•.... ~•• •

IndustrialCommercial .

--lIE- Domestic

_.~~------

400000 -+- Power

~ 350000-11- Fertilizeru2 300000

::8 250000

.~ 200000a- 150000 __ Total;:l

:g 100000-ou 50000.' -~-~----~~-~~~~~~~o - - w -T-'~'--'-T-'-'-'-'-r-' I

. _.__ __.~96: __._1_97_0 1_975 1~8_0__Year_1985 .~_90__ 1~~___ 2~~~_J

In 1968-69, out of a total consumption of 1034 MMSCF, power sectors alone used 98% of

the total gas and commercial, industrial and domestic sectors together used only 2%. With

the introduction of gas in the Urea Fertilizer Factory Limited (UFFL) at Ghorasal in 1970,

the total demand for gas stood at 7962 MMSCF. Percentage use of gas in power, fertilizer,

industrial and commercial sectors was43%, 53%,4% and 0.5% respectively. Domestic use

of gas was 3% in 1970-71, which increased to 8% in 1979-80. Use of gas in power sector

kept on increasing and in 1996-97 its share was 46%. Figure 2.1 shows percentage of gas

consumption in different sectors from the beginning of its use. It is anticipated that more

and more gas would be used to meet the power demand of the country.

Figure 2.1: Sector Wise Natural Gas Consumption (8)

2.4.1 Ammonia-Urea Fertilizer Sector

Seven ammonia-urea complexes now in operation have a combined connected demand of

289 MMSCFD of gas (5). Table 2.2 shows the growth of this sector, and Figure 2.2 shows

the consumption trend of gas since 1960 with the commissioning of each plant. During the

decade of 1988-1997 the share of this sector accounted for 32 to 37 % of the total gas

consumed (5). The locations of fertilizer factories are shown in Figure 2.3.(

10

. 2008

.2007200620052004200320022001200019991998

. 19971996 ~1995 ~1994 0-1993 u

~~ .

"" .

1992 VJ

"'!" ::; ••• 1

~'.

1991 "N u ' .~N u.. : 1990, is

~ 1989 .;::~-' 1988 "LL

u-ri r:: ::> 1987 .S

u@j~.<t 1986 "co LL I~::> '. 1985 0

a. '.;::

, 1984 0-

1983 ~ E0 '"~. 1982 0> ::l ->- <n

d ..••--- 1981 "0LL 1980 UN 1979 <n

'"1978 01977 :a

0 1976 ~::l

I LL . 1975 -u '"

I(J)

1974 Z:;:; 1973 "!

i 2. ~rI1972 N

.-: <o;J c: .••• 1971 "

u~

ro 1970 ::l

0! lD ~ ,~

...J1969 u-

Vl. 1968

ro(9

1967(\)

. 1966.20 1965iii'S . in

1964

'" E 1963~ "

::. 1962u LL

t ro LL •• . 1961'" (5 0

0

u. f-z 1960,

t T195919581957

0 '" 0 0 0 0 0 0

0 '" 0 0 0 0 0

0""

0 0 0 0 0 (0 r, 0 0 0 0 0

'" 6 '" 0 '" 0 '"co co N N ~ ~ \(:l::JSIJIJiI\I)UO!ldlUnsuo::J se~

, ,,, .

"~" _ LI

~'\,,..,III1,. \

II

TRIPURA

r'\. r,J " (,

\\\\\-I

\,

(INDIA)

v

r,\\

J;-

'"I(,\\

'"

See delailed map

Comi'Aa,",\ '\I ( ,,\ ,

\,., \Felli lown---;;;:;;'/Relll~-----7

Semula~ /

* "/Manldrlle'il

{;.1k:hhIri

\.\

'.HlIltIIlarl

l,Jessore

••••••••••

23'

Io

'I,A

",

~

~

"',-,')I/

"\,r~,I

".,.,;,'"

~ill

Ii

/"f-h! IJ:.[ )~- .

"r1~.~"Nw

C~"'""C- ~N ~'"5"togj03-'"p.."'"::r':s

I'" /,

Table 2.2: Connected Maximum Loads of Gas for Fertilizer Sectors (5)

From Year Plant " ' Load(MMSCFD) ,.' Cumull:1tiv~(MMSCFD)1961 NGFF 19 191970 UFFL 45 641981 ZFCL 50 1141986 PUFF 17 1311987 CUFL 50 1811991 JFCL 43 2241994 KAFCO 65 289

During the period 1986 to 1987, a gas load of 67 MMSCFD was added by the fertilizer

sector with the commissioning of PUFF and CUFL while an additional load of 108

MMSCFD was added during 1991-94 when JFCL and KAFCO came on stream. The

average daily demand of gas by the fertilizer sector for the years 1986, 1989 and 1996 were

103, 154 and 213 MMSCFD respectively against the contracted loads of 121,171 and 284

MMSCFD respectively. During the next five years, the most optimistic annual consumption

of gas would be 90,000 MMSCFD by this sector.

2.4,2 Trends of Natural Gas Uses for Power Generation

From the present trend of economic growth in different areas it is clear that most of the

future gas demand would come from the power sector. A more detailed and lists of the gas

demand scenario in power sector enable us to have a better understanding of the growth

projection. The location of gas based power stations of Bangladesh are shown in Figure 2.4.

Natural gas was first introduced on a trial basis for power generation in Bangladesh in 1967

in a 30 MW power plant at Siddirgonj. Use of gas to produce electricity increased steadily

and in 1999 installed generating capacity by using natural gas stood at 2575 MW which is

about 75% of the total installed capacity. In December 1999, natural gas was supplied to the

western zone for the first time and it is expected that several gas-fired power plants would

be established in the power starved western zone of the country.

13

--------------------------- ------------------------------------

v

See de1ailed map

'-,\I"'I,I\\\

TRIPURA

r \. r\J ~

I,I,\\I-I,\

(I N D I A I

rII\

J.r

./I{\,,./

-./R.~---~--!Semutang ••~ ,.

~-M.~;I,-\FIl'r;H\¥i

\.\

IiIll>lIl.1

rJ\.\"'-I

Com"\

"\, '\I '

"\..'

~

~~Jessorll

.-Kushlla

I-.A.

"2~.~/

/.;/

<;)

>r1QQ''"...,'"tv~-00~'"...,-0- '"..,. ::lfA:;OJ~<e.~'"en;:r3

Table 2.3 shows that natural gas consumption started increasing in power generation from

the very beginning after the installation of a 30 MW trial plant in 1967. Conversion of the

old oil-fired plants and addition of some new power plants pushed the total demand of gas

to the present value. From Figure 2.5 it is clear that in mid 80's, natural gas used power

generation increased sharply. This was due to the addition of three 210 MW units at

Ghorasal and three 150 MW units at Ashuganj. In mid 90's another new power plant at

Raozan with two units each of 210 MW capacity was added to the national grid. A sharp

rise in natural gas consumption curve can be observed during that period. Furnace oil and

HSD/SKO consumed in power generation, mainly in the remote areas and western zone

where natural gas is not available remains almost same from the beginning. Natural gas

completely replaced the use of naphtha and coal in power generation in 1972 and 1983

respectively.

15

Table 2.3: Trends of Natural Gas uses for Power Generation (10).

Installed Capacity by Type ofFuel(MW) . Total "Year

Hydro Coal Furnace Natural Naphtha HSD/SKOinstalledCapacity

Oil Gas

1966-67 80.00 30.96 30.00 30 79.20 220.161967-68 80.00 30.96 117 124.59 265.551968-69 80.00 6.00 24.96 181.50 37.00 95.34 360.301969-70 80.00 4.16 20.80 316.40 43.50 89.00 418.961970-71 80.00 4.16 20.80 316.40 45.70 81.64 548.701971-72 80.00 4.16 20.80 316.40 45.70 81.64 548.701972-73 80.00 4.16 80.80 371.40 45.70 81.23 608.291973-74 80.00 stoDDed 84.96 371.40 45.70 78.03 660.091974-75 80.00 84.96 426.40 45.70 85.38 667.441975-76 80.00 84.96 426.40 45.70 128.52 765.581976-77 80.00 84.96 426.40 45.70 129.60 766.661977-78 80.00 84.96 426.40 32.70 128.08 752.141978-79 80.00 76.64 426.40 7.20 127.74 717.981979-80 80.00 80.00 426.40 234.79 822.191980-81 80.00 80.00 426.40 226.76 813.161981-82 130.00 80.00 414.00 233.00 857.001982-83 130.00 76.64 474.00 6.50 232.10 919.241983-84 130.00 182.45 564.00 13.00 231.55 1121.001984-85 130.00 182.45 577.00 StoDDed 251.55 1141.001985-86 130.00 170.00 633.00 238.23 1171.231986-87 130.00 170.00 1069.00 238.33 1607.231987-88 230.00 170.00 1468.00 278.23 2146.231988-89 230.00 170.00 1678.00 278.28 2365.281989-90 230.00 170.00 1678.00 274.21 2352.211990-91 230.00 170.00 1678.00 271.93 2349.931991-92 230.00 170.00 1875.00 332.68 2397.681992-93 230.00 170.00 1875.00 332.68 2607.681993-94 230.00 170.00 2175.00 332.68 2607.681994-95 230.00 170.00 2175.00 332.68 2907.681995-96 230.00 170.00 2175.00 332.68 2907.681996-97 230.00 170.00 2365.00 326.00 2907.681997-98 230.00 170.00 2365.00 436.00 3091.001998-99 230.00 170.00 2575.00 436.00 3411.00

16

'c

1--

'Q)

.2'+- 4000 -~-----_.- --:.. -o __ Hydro-all~ 3500 - __ Coal

~ 3000 Furnace oil£; 2500 Natural gas>-~

.0 S 2000 __ Naphtha>-:2'5 ~1500 - -- HSD/SKOrog- 1000'-::+- ~?ta~ _u"0 500Q)

,ro 0I~I ~ 1960 1970

1\ ' -- -'~.•.•.~'-,--.---.:1::

1980

Year

1990 2000

---_.-----_._--- --- ------ ------_.- -----_._._---------------_.----~----_. __ .-

Figure 2.5: Trends of Natural Gas uses for Power Generation (10)

2.4.3 Industrial, Domestic and Commercial Sectors

In the current decade, percentage of total gas consumed by the combined industry, domestic

and commercial sector uses between 16 and 22. Commercial consumers account for less

than 1.5% of the total gas consumption and the sector has not shown significant growth

during the past decade.

Industry, the main contributor among others has reached again the 1986-87 level after years

of substantial decline. This fall is partly related- to the poor growth performance of the

manufacturing sector in Bangladesh, only 3.1% as yearly growth for the period 1980-92.

During the same period the whole industry had better performances since the growth rate

has reached 5.1% a year for the period 1990-92 according to World Bank statistics. The

industrial sector during the current decade has been using 8 to 12% of the total gas

consumption. Major application areas in this sector include steam generation, captive power

17

r;:.1 '.

and for process (heating media and heat source). When the Bakhrabad Gas Systems Ltd.

had made natural gas available in Chittagong area, industries using furnace oil, disel or

other liquid fuels immediately switched over to gas. These include ERL, TSP, KPM, KRC,

Osmania Glass, Chittagong Steel Mills, etc. For the industry sector, the growth has been

3.75% during the decade 1986-1995.

In Bangladesh, the domestic sector has ex'perienced a steady growth since the beginning.

Within the Titas Franchise area the average growth has reached 9.7% a year from 1980-81

to 1993-94. For Bakhrabad Franchise area development of gas sales to domestic

consumers' remains extremely strong since during the 90's, growth is constantly above

12%. In the lalalabad Franchise area the growth is more modest with 4.8%. Comparatively

to other developing countries, this is a salient success of the Bangladesh gas sector to have

provided an access to low cost energy to hundreds thousands of residential consumers

living in cities. Its contribution to maintain trees and forests in the heavily populated

Bangladesh deserves to be underlined. The number of domestic consumers now stands

approximately at 900,000. The three transmission and distribution companies can provide

gas supply to about 70,000 new customers each year (Titas: 50,000, Bakhrabad: 15;000 and

lalalabad: 5,000). The domestic sector has shown a growth of 11.7% during the decade

1986-1995.

The seasonal uses, mainly the brick fields, consume a small quantity of gas during the brick

manufacturing season. This is a minor sector for near future.

According to TGTDCL, during the year 1996-97, a domestic consumer consumed about 82

SCFD while an industrial and a commercial consumer consumed 31,000 SCFD and 1031

SCFD respectively. System loss was close to 9 percent. Since 1998, the system loss

amounting to 55 MMSCFD has been added to the industrial sector(\).

18

2.5 Gas Sector of Bangladesh

Being reverie delta having porous and permeable hydrocarbon bearing sand structure and

unique condition of trap Bangladesh is always considered a gas prone country. But due to

resource constraint the exploration activities were kept to a bare minimum. Exploration of

hydrocarbon in this region commenced from the beginning of the current century. Various

national and international companies carried out wild cat exploration in the potential areas

of Bangladesh.

2.5.1 Oil and Gas Exploration in Bangladesh

Oil/gas reserves are non-renewable energy resources depleting with time. Therefore, every

country will have to continue the search to add new reserve to its existing one. Investment

in the oil/ gas exploration is a high-risk gamble. It has also different steps leading to

successful economic production. The steps are Geological and Geophysical Survey, Data

Acquisition, Analysis and Interpretation leading to delineation of a structure, Selection of

drilling location etc.

The exploration for hydrocarbon was initiated for finding oil in 1908 with the first

exploratory well drilled at Sitalakundu. This was followed by three more exploratory wells

by 1914. In the early days (1910-1933) of exploration, drilling was mainly concentrated

near seeps in the fold belt. At this stage shallow wells ranging from 763 to about 1050

meters were drilled. The foreign companies drilled six exploration wells but no success was

met. Second World War disrupted the drilling activities. The second phase of drilling

(1915-1917) unfolded a glorious chapter in the exploration history of this part of the world.

The exploration activities since 1908 can be broadly divided into five distinct phases as

listed in Table 2.4.

19

(

t"Table 2.4: Exploration Phases of Bangladesh (\, 2)

Phase Period " No, of . , , Discovery • , 'SticcessRatio• .• , 1 ' .Exploratory "

Wells - --

I 1010-1933 6 None Zero

British India Minor Oil flow

II 1951-71 22 8 Gas Fields 2,75:1

PakistanIII 1972-78 10 2 Gas Fields (One 4.50:1

offshore)'

IV 1979-1992 14 7 Gas Fields & I Oil 2,00:1Field

V 1993-2000 10 5 Gas Fields 2.60:1

Total 62 22 Gas Fields & 1 Oil 2,87:1field

In a country where possibility of transfonning resources to reserve is high, there comes

PSC mechanism to boost up the cxploration activities through International Oil Company's

investment. That was the time where International Oil Companies started becoming

contractors and partners to the State Oil Company, The country has been divided into 23

blocks for PSc. Six laCs were awarded 7 blocks under PSC for exploration of hydrocarbon

in the early seventies, During the period 1974-77, seven exploratory wells were drilled with

only one gas field discovery.

A new model PSC was prepared in 1988, 4 blocks were awarded to two laCs who drilled

4 exploratory wells leading to the discovery of one gas field. In the early nincties, the model

PSC of 1988 was revised and 8 blocks have been awarded to four laCs. Two of these laCs

have so far drilled 14 exploratory wells since 1994 resulting in the discovery of 3 gas fields

including one offshore field; and have suffered one gas well blowout. With the discovery of

a gas structure in the Bay of Bengal by Anglo Dutch joint venture company Cairn-Shell in

1996, Bangladesh attained the world focus and was being thought to become a happy play

ground of the oil majors. There was tremendous response in the second bidding round for

selecting International Oil Companies (laC) for exploration in the fifteen blocks. During

the period 1972-2000, Petrobangla drilled 16 exploratory wells and discovered 9 gas fields

and one oil field. Table 2.5 lists the exploration activities since 1972.

20o

J,

Table 2.5: Exploration Activities in Bangladesh since 1972(1,5)

Period No, of Exploratory . Discovery RemarksWells Drilled

Petrobangla1972-1990 13 7 Gas Fields

and I Oil Field1991-2000 3 2 Gas Fields

International Oil Company (lOC)1974-1978 7 I Gas Field PSCs Cancelled

1988-1995 4 I Gas Field PSCs Cancelled

1994-2000 14 3 Gas Fields

In terms of gas reserves, IOCs under a wide range of PSCs have made major gas

discoveries in Bangladesh, These IOCs including those operating during pre-I 972 era have

discovered total recoverable reserves of 14.19 TCF from twelve fields while Petrobangla

has discovered a total recoverable gas reserve of 1.47 TCF from ten fields. Since the

emergence of Bangladesh, the IOCs' exploration has contributed 4.46 TCF to recoverable

gas reserves and Petrobangla's discoveries have contributed 1.24 TCF to recoverable gas \.

reserves (I)

During the past decade beginning from 1991, the exploratory drilling program has not

gained the desired momentum in spite of the presence of IOCs. Only 13 exploratory wells

were drilled which means about 1.3 wells per year. Since 1997 BAPEX, the Exploration

Company of Petrobangla, has not undertaken any exploratory drilling. At this moment IOCs

have slowed down their exploratory drilling programs in view of the fact that they are.

unable to market the gas at the rate that they can produce. If IOCs are allowed to produce

from all their fields at the maximum production rate as per PSC, Petrobangla will have to

suspend its production from its own fields. The economic reality of Bangladesh is that

Petrobangla should buy the minimum quantity of gas from IOCs to meet the country's gas

demand and it should not suspend production from any of its producing fields to make

room for IOCs production. This is a painful situation for both Petrobangla and IOCs. If we

want to take advantage of the technological capability and financial strength of IOCs for

accelerating exploratory drillings to augment the existing gas reserve of Bangladesh, one

21

• C::o

c

must examine all the options available for the marketing and utilization of thew gas from

the fields discovered and owned by IOCs.

On the other hand GOB has also signed International Power Purchase (IPP) contracts with

international power producing companies for setting up gas based power plants on Build

Owned and Operate (BOO) basis in Haripur, Meghnaghat, Baghabari and Sirajgonj. Some

peaking power plants may also be setup around Dhaka City to meet the peak demand of

Dhaka Metropolis and adjoining areas. The expansion of Gas Transmission Network on the

Western of the Jamuna river using the Multipurpose Bridge has also opened avenues for

setting up gas based industries in the earlier neglected Western region. For ensuring gas

supply in time to all the future power plants and industries, expansion and balancing of the

national grid require to be implemented on priority basis. Otherwise gas transmission

network may have to encounter the same embarrassing situation in the next couple years as

being experienced in the power sector. The constraints of the gas transmission grid require

to be overcome through construction of loop lines and setting up of compressor stations at

strategic locations to expand the capacity of the national gas grid for balancing the system

and ensuring security of supply (2).

2.5.2 Gas Fields of Bangladesh

The first discovery of natural gas was made in 1955 at Haripur (Sylhet Gas Field) and this

was followed by the discovery of the Chhatak Gas Field in 1959. Since then the exploration

of oil and gas resources has led to the discovery of 22 gas fields and one oil field. There are

now 53 producing wells capable of producing about 1300 MMSCFD of gas from 12 gas

fields (I). The locations of gas fields of Bangladesh are shown in Figure2.6.

Cumulative production of gas up to December 2000 was about 4.08 TCF (I). Gas fields of

Bangladesh have Gas initially in Place (GIIP) of about 24.745 TCF. Summaries of gas

initially in place (GIIP) and reserve estimates of different gas fields by Petrobangla are

shown in Table 2.6.

22

GAS TRANSMISSION PIPELINES, GAS FIELDS & OIL FIELD OF BANGLADESH

..<~-Z<.<-••0z

1--

'" -•••~

WEST BENGAL 8akhrabad Franchise AreaTitas franchise AreaJalalabad Franchise Area

Wes Gas Franchise AreaCas Transmission Pipelines

Proposed Transmission Pipelines

Gas FieldOil FiI~ld

AssAM (INDIA)

o•

Figure 2.6: Natural Gas Fields in Bangiadesh (12)

23

Table 2.6: Gas Fields of Bangladesh (I)

Sl. Field ' Year GIIP Recoverable Net Remarks

No. , (proven + Reserve (proven Recoverableprobable) + probable) ReserveTCF TCF TCF

I Bakhrabad 1969 1.432 0.867 0.280 P

2 Habigonj 1963 3.669 1.895 1.077 P

3 Kailashtila 1962 3.657 2.529 2.297 P

4 Rashidour 1960 2.242 1.309 1.114 P

5 Sylhet 1955 0.444 0.266 0.100 P

6 Titas 1962 4.138 2.100 0.317 P

7 Narshingdi 1990 0.194 0.126 0.097 P

8 Meghna 1990 0.159 0.104 0.081 P

9 Sangu 1996 1.031 0.848 0.757 P

10 Saldanadi 1996 0.200 0.140 0.125 P

11 JalaJabad 1989 1.195 0.815 0.763 P

12 Beanibazar 1981 0.243 0.167 0.162 P

13 Begumgoni 1977 0.025 0.015 0.015 NP

14 Fenchugoni 1988 0.350 0.210 0.210 NP

15 Kutubdia 1977 0.780 0.468 0.468 NP

16 Shahbazpur 1995 0.514 0.333 0.333 NP

17 Semutang 1969 0.164 0.098 0.098 NP

18 Bibiyana 1998 3.150 2.401 2.401 NP

19 Moulavibazar 1999 0.500 0.400 0.400 NP

20 Chhatak 1959 0.447 0.268 0.241 PS

21 Kamta 1981 0.033 0.023 0.002 PS

22 Feni 1981 0.178 0.125 0.085 PS

Total 24.745 15.507 11.42

P: Producing, NP: Non-Producing, PS: Production Suspended

Table 2.6 shows that the total GIIP and initial recoverable reserve of Bangladesh are 24.745

TCF and 15.51 TCF, respectively. Out of this reserve, 4.07 TCF has been produced already

(up to February 2001), and the remaining reserve is 11.42 TCF.

These gas fields as shown in Table 2.6 are under the jurisdiction of different gas companies,

both government owned and multinationals. There are today five companies in the country

producing natural gas. These are:

24

i) Bangladesh Gas Fields limited (BGFCL)

ii) Sylhet Gas Fields Limited (SGFL)

iii) Bangladesh Petroleum Exploration and Production Co. Ltd. (BAPEX)

iv) Shell Bangladesh Exploration and Development B.V. (SHELL)

v) UNOCAL Bangladesh Ltd. (UNOCAL)

Table 2.7 shows a list of these companies and their production capacities.

Table 2.7: Production Capacities of Various Gas Fields (8)

Company Gas Total Produc Product Daily Production ProductionField Wells mg Capacity Goal December

Wells 2000-2001 2001

Bangladesh Titas 14 13 Gas 10.761 3592.206 223.144Gas Fields MS 13.064 5602.230 408.410Company HSD 52.255 20431.968 1690.435

Condnst 65.319 26553.517 2175.592

Habi- 10 10 Gas 7.560 2039.802 192.127gan] Condnst 1.890 655.207 62.524

Bakh- 8 4 Gas 0.962 353.676 30.312Rabad MS 2.209 2173.294 187.658

HSD 3.313 3534.080 258.029Condnst 5.522 1747.654 166.298

Salda 2 I Gas 0.420 154.951 12.462Condnst 1.802 660.056 53.504

Norshi- 1 1 Gas 0.509 176.424 12.755ngdi Condnst 5.879 2239.480 170.104

MS 2.352 - -HSD 3.527 - -

Meghn 1 1 Gas 0.510 156.350 8.438a Condnst 4.170 1349.897 74.945

Sylhet 7 2 Gas 0.141 53.569 4.744MS 3.000 690.000 4.788

25

Note: Gas: MMSCMD (million standard cubic meter per day), Petroleum Products:

Thousand Liters

Company Gas Total Produc Product Daily Production Production

Field Wells mg Capacity Goal DecemberWells 2000-2001 2001

Sylhet Kerosin 0.178 70.087 5.055

GasFields Kailash 4 4 Gas 2.940 886.121 72.735

Company -tilla MS 19.500 6650.739 611.260

Limited HSD 18.500 _5718.689 525.307Condnst 185.500 76446.347 6556.151

Rashid- 7 6 Gas 4.332 914.444 71.880

pur Condnst 34.534 7687.085 567.879

Biani- 2 I Gas 0.992 35.464 7.156

bazar Condnst 97.388 329.392 679.668

Shell Sangu 6 4 Gas 4.248 1354.933 114.74

B.Y. Condnst 7.155 3337.615 314.680

UNOCAL .Talalaba 4 4 Gas 2.832 854.76 73.465

Bangladesh d Condnst - 59212.240 3731.412

Limited -

Shell and UNOCAL are international oil companies (rOCs) operating under Production

Sharing Contracts (PSC) while BGFCL, SGFL and BAPEX are subsidiary companies of

Petrobangla, the public sector corporation to manage oil and gas resources of the country.

Bangladesh Gas Fields Company Limited (BGFCL) owns eight gas fields, namely, Titas,

Habigonj, Bakhrabad, Narshindi, Meghna, Begumgonj, Feni and Kamta. The productions

from the Kamta and Feni fields are now suspended. The production from the Bakhrabad

field is likely to be suspended in near future. The' Begumgonj field has not yet been

developed (1)

Sylhet Gas Fields Limited (SGFL) owns five gas fields, namely, Haripur (Sylhet),

Kailashtilla, Rashidpur, Beanibazar and Chhatak; and one oil field, namely Haripur. The

production from the Chhatak gas field and the Haripur oil field is now suspended. BAPEX

26

has been given the operatorship of the Saldanadi, Fenchugonj and Shahbazpur gas fields. It

produces gas from Salda Nadi field. Shahbazpur and Fenchugonj fields have not yet been

developed. Shell Exploration and Development B.Y. produces from one field, namely,

Sangu, which is an offshore operation. It also owns two other fields, namely, Semutung and

Kutubdia. Kutubdia is an offshore field (I).

UNOCAL Bangladesh Ltd. owns three gas fields, namely, Jalalabad, Maulavibazar and

Bibiyana. It produces gas from the Jalalabad field (5)

After commencement gas production from Jalalabad and Beanibazar gas field and with the

completion of drilling of additional wells at Rashidpur, Habigonj and Titas Gas Fields, it is

possible to produce 1325 MMCFD of gas from 66 wells of 12 gas fields. Out of the above

amount 630 MMCFD gas can be made available from 6 gas fields of the North- East for

North- South pipe line for onward transmission to national gas grid (2)

2.5.3 Present Demand and Supply Scenario

Natural gas use as a fuel in Chhatak Cement Factory in 1960 with supply from the

Chahatak Gas Field marked its first commercial utilization. It was fed to the first ammonia-

urea grass-roots complex, NGFF at Fenchugonj in 1961 (2). Over the years the consumption

of natural gas has been increasing and its contributed to the national development increased

significantly. Gas production of 24 hours from 12-July-00 to 13-July-OO was 931.262

MMSCF (Daily production report, GTCL, 13-July-OO). In the month on March 2000 the

peak production was lOIS MMSCFD (5). The peak production in 2000 (up to September

2000) was 1089 MMSCFD. On September 18,2001 the production was 1042 MMSCFD and

the two laCs' contribution was "176 MMSCFD (I). The down stream demand and

consumption of natural gas are tabulated in Table 2.8, 2.9, 2.10, 2.11.

27

Table 2.8: Downstream Demand and Consumption of Natural Gas of Jalalabad Gas

Franchise Area (JFA) (2)

. , . . , . . ,'. '

c. Flow Rate.

Franchise Area (JFA), greater SvlhetI Kumargaon Power Station 0.55MMCFD

2 Svlhet Pulo and Paper Mills (SPPM) 1.70MMCFD

3 Chatak Cement Factorv 4.00MMCFD4 Private Sector Cement Factory 17.00MMCFD

5 Ainpur Cement Factory 1.00 MMCFD

6 Industrial 1.50MMCFD7 Commercial 1.50MMCFD8 Domestic 6.00MMCFD9 Power 4.00MMCFD

Sub-total 36.75 MMCFDFenchugoni AreaI 90 MW Power Station 17.00MMCFD2 Shahialal Fertilizer Factory I9.00MMCFD

Sub-total 36.00MMCFDHobigoni and Moulavibazar AreasI Shahiibazar Power Plant 4.00MMCFD

2 Tea Gardens 5.00MMCFD

3 Others I.OOMMCFDSub-Total 10.00 MMCFD

JFA Grand Total 82.75 MMCFD

Table 2.9: Downstream Demand and Consumption of Natural Gas of Titas Gas Franchise

Area (TFA) (2)

~ , . ',I FlowRaie'" i", ~':'. . ... , ,

Ashugonj AreaI Ashugonj Power Station 150.00 MMCFD2 Zia Fertilizer and Chemical Comolex Limited 50.00MMCFD

Sub- Total 200.00 MMCFDGhorasal AreaI Palash Urea Fertilizer Factorv 17.00MMCFD

2 Urea Fertilizer Factory, Ghorashal 45.00MMCFD

3 Ghorashal Power Station 150.00 MMCFDSub- Total 212.00 MMCFD

Greater Mvmensing AreaI Mymensing, Kisorgonj, Netrokona, Jamalpur and 10.00 MMCFD

Sherour.

28

,~,.

2 Jamuna Fertilizer Faetorv 43.00MMCFD ,3 RPCL Power Plant 25.00MMCFD

Sub-Total . 78.00 MMCFDGreater Dhaka AreaI Industrial 120.00 MMCFD2 Commercial 20.00MMCFD3 Domestic 80.00MMCFD4 Seasonal 05.00MMCFD

Sub-Total 225.00 MMCFDTFA Grand Total 680.00 MMCFD

Table 2.10: Downstream Demand and Consumption of Natural Gas of Bakhrabad Franchise

Area (BFA) (2)

I . Flow RateBakhrabad Franchise AreaI KAFCO 65.00MMCFD2 CUFL 50.00MMCFD3 2X210 MW Rauian Power Plant 90.00MMCFD4 60 MW and 56 MW Sikalbaha Power Plant 15.00MMCFD5 KPM 8.00MMCFD6 Others 40.00MMCFD

BFA Total 268.00 MMCFD

Table 2.11: Downstream Demand and Consumption of Natural Gas of Western Region

Franchise Area (WFA) (2)

.. I' Flow RateWestern Franchise AreaI 90 MW barge Mounted Power Station 22.00MMCFD2 71 MW PDB Power Plant 21.00MMCFD

WFA Total 43.00MMCFD

Total Gas Demand = 1088.75 MMCFD '" 1089 MMSCFD.

From above tables, it is clear that the present peak demand of the connected down stream

consumer is 1089 MMCFD which can now be met from the current maximum production

capacity of 1300 MMCFD after drawing gas from private producer Shell & UNOCAL. The

situation has improved with the commencement of production from Beanibazar with effect

29

from May 1999. Obviously it is very rare that all the consumers would ever attain peak

concurrently. As such the system peak hovers around 900 to 950 MMCFD which is being

met effectively from national gas grid.

2.5.4 Future Demand and Supply Scenario

International Oil companies which have already commenced production under PSC will

continue their exploration campaign. It is also expected that on achieving significant

discovery followed by appraisal and development additional quantity of gas will be

available for down stream use. UNOCAL in Surma basin (Block 12, 13 & 14) has already

made a significant discovery at Bibyana where two wells have been drilled and a 3-D

seismic survey has been carried out for confirming the ultimate recoverable reserve.

UNOCAL has also discovered a new gas field at Moulvibazar. Shell, UMIC, REXWOOD

are also expected to continue their exploration campaign in their respective blocks. New

discoveries will further enhance our gas reserve.

Sylhet Gas Fields Ltd. (SGFL) under IDA funded Gas Infrastructure Development Project

(GIDP) has completed drilling of 3 wells and installation of required gas treatment plans at

Rashidpur Gas Field. Bangladesh Gas Field Company Ltd. (BGFCL) has also implemented

drilling of 6 additional wells (3 each at Habiganj and Titas Gas Fields) and work over of

some gas wells in these fields. Bangladesh Petroleum Exploration Company (BAPEX) has

also completed drilling second well at Salda. These new wells have provided additional

information about the reservoir of the respective gas fields and have also increased

production by 400-300 MMCFD. On the other hand gas demand is also growing steadily

and is expected to grow significantly over the next couple of years as new power plants will

come into production in Haripur, Meghnaghat and Western side of the Jamuna river.

Government is also planning to set up gas based export oriented fertilizer factories. A

Korean EPZ in Chittagong and industrial parks in Sirajganj, Bogura and Ishwardi also

being set up if supply of gas and stable power can be ensured. For an urea plant having the

production capacity of 5,00,000 tons per year natural gas would require approximately 45

MMCFD. But for adding 100 MW of electricity generation capacity based on natural gas

30

would need about 25 MMCFD additional natural gas. In industrial sector, it will have to

consider the supplemental of existing fuel such as furnace oil and diesel oil in industrial

installation such as boilers and generators plus new industries to be set up. Replacement of

100,000 ton of Furnace oil per year with equivalent quantity of natural gas means an

additional requirement of 12 MMCFD natural gas.

By analyzing the demand and supply situation a projection is made here under the Average

Base Case Supply/Demand which is shown in Table 2.12.

Table 2.12: Average Base Case Supply/Demand (in MMCFD) (2)

.. ' ,' . . ,~

".", ,~{ . Fisca1'Year , .e. c, • ., . ,,~ ,.;:- '~!'.;'", •.', ;, '

"

1998/99 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05

Total Supply 900 1095 1395 1395 1395 1500 1500Total 920 950 1050 1160 1260 1440 1440DemandBalance 20 145 345 235 135 60 60

Table 2.12 indicates that there will be a surplus of 345 MMSCFD in 2000/0 I (2). This is

primarily due to the development of the Rashidpur Gas Field (3 new wells), Habiganj (3

wells) and Titas (3 wells) coming on stream. Utilization of the additional gas will largely

depend on the expansion of the transmission capability of the national gas grid through the

completion of Rashid pur- Ashuganj Gas Transmission Loop line.

It is important to consider that Bangladesh's natural gas resources are concentrated in a few

numbers of big fields (Titas, Habiganj, Rashidpur and Kailashtila) which are at their early

stage of development. Of which there are limited field data are available. It is important to

conducted regular pressure tests in these fields to keep track of their behavior. A prudent

gas supply surplus above average demand should be about 200 MMCFD (2) for the

following reasons:

This will permit temporary shut-in of one or more well of a field at a time in order to

get pressure build up data that are critical for the reservoir management.

31

.P

This amount will allow the temporary loss of production from the equivalent of

nearly a field without causing many difficulties to the consumers.

This amount of surplus should permit taking advantage of the available line pack to

better manage deliveries.

It should be noted that the supply values in the preceding analysis represent short-term

capabilities of the individual fields. These fields are not capable of sustained production for

long at those rates. Several fields have peak supply and average supply at the same level. In

these cases, the fields are not capable of sustained production above average. The Titas

field peak supply and average supply are the same and are at rates lower than current well

capacity. More appraisal drilling is needed, as currently planned, along with systematic

reservior pressure measurements over time wh'ich will allow engineers and geologists to

draw reliable conclusions and to find the strategy to exploited this potential important field.

2.6 Gas Transmission Network

The gas transmission Pipeline in Bangladesh have been planned and constructed targeting a

particular bulk consumer or potential load center. In the early stage of development of gas

sector the grid concept was possibly not visualized. Gas Transmission Company Ltd. And

three transmission and distribution companies are responsible for operation and

maintenance of these transmission pipelines. Over the years, a national gas line grid has

been built and it is connected to lateral and distribution networks. The major gas

transmission lines are described in Table 2.13.

32

Table 2.13: Gas Transmission Network (2)

Gas Transmission Pipelines' Controlling Dianieter (incb) Designed. , .DesignCompany and Length (Km) Operating Capacity

Pressure(MAOP)

Haripur- Fenchugani JGTDCL 8"-25 Km 600 Psi 40MMCFDTangratilla Chhatak JGTDCL 4"-15 Km 750 Psi 30MMCFDShahjibazar - Shamshemagar - Juri JGTDCL 6"-45 Km 600 Psi 40MMCFDValleyTitas - Narshindi - Demra TGTDCL 14"-96 Km 1000 Psi 150MMCFDTitas - Narshindi - Joydevpur TGTDCL 16"/14"-91 Km 1000 Psi 170MMCFDHabigani - Ashugani Trunk Line TGTDCL 12"-38 Km 1000 Psi 88MMCFDBeanibazar - Kailashtilla GTCL 20"-18 Km 1135 Psi IIOMMCFDJalalabad Gas Field- Kailashtilla Unocal 14"-15 Km 1135 Psi 160 MMCFDNorth-South Gas Transmission GTCL 24"-174Km 1135 Psi 330MMCFDPipelineBakhrabad - Demra Pipeline BGSCL 20"-48 Km 1000 Psi 250MMCFDAsguganj - Bakhrabad Gas BGSCL 30"-58 Km 1000 Psi 220MMCFDTransmission PipelineSalda-Bakhrabad Gas Transmission BGSCL 10"-37 Km 1000 Psi 60MMCFDPipelineMeghna-Bakhrabad Gas BGSCL 8"-28 Km 1000 Psi 40MMCFDTransmission PipelineBakhrabad-Chittagonj Gas BGSCL 24"-174Km 960 Psi 350MMCFDTransmission PipelineSangu Gas Transmission Pipeline Shell 20"-45 Km 1135 Psi 240MMCFD

The development of Kailashtilla Gas field in early eighties opened avenues for expansion of

gas transmission network in Sylhet area. A pipeline was built from the Kailashtilla Gas

Field to Chhatak for meeting the demand of that area.

Two more important gas transmission network were developed simultaneously following

the drilling of 11 wells Beanibazar, Kailashtilla, Rashidpur, Habiganj, Titas , Belabo and

Meghna gas fields under second development project.

174 Km. 24" Diameter North-South Pipeline from Kailashtilla- Ashuganj with a

parallel 6" Diameter Condensate/NGL pipeline.

33

v(

117 Km. 24" Diameter Brahmaputra Basin Pipeline from Ashuganj to Elenga for

delivering gas to greater Mymensing areas, Jamuna Fertilizer Factory at Tarakandi

with a future provision for gas supply to the western region of Bangladesh.

The emergence of BGSL created revolutionary changes in the economic development

activities of Southeast. The power plants, fertilizer factories, paper mill, refinery, steel mill

and various other industries of Chittagong region become absolute dependent on gas

available from Bakhrabad as well as Feni gas field. But unfortunately poor production

strategy led to the dramatic decline of gas production from Bakhrabad Gas field and

suspension of gas supply from Feni Gas Field. Under compelling situation due to alarming

sand flow and water production the gas production was drastically reduced causing

suspension of production of Chittagong Urea Fertilizer Factory and some power plants.

This resulted in unbearable load shedding counfrywide. The situation was partially

overcome by expediting construction of 58 Km. 30" Diameter Ashuganj to Bakhrabad Gas

Transmission Pipeline for diverting the surplus gas from the northern Gas Fields to the

Southeast. Subsequently transmission pipelines were also constructed from Meghna Gas

Fields to Bakhrabad and Salda Gas Field to Bakhrabad for augmenting the gas supplies to

the South-East. For flexibility of gas transmission a 20" gas transmission lateral has been

built through Monohordi-Narshigdi-Shiddhirgonj.

18 Km. 20" Beanibazar to Kailashtilla gas transmission pipeline has been constructed and

commissioned in April 1999. 15 Km. 14" gas transmission pipeline from Jalalabad gas

field to Kailashtilla has also been commissioned in February 1999. Transmission pipeline is

also being built along and on either sides of Bangabondhu Jamuna Multipurpose Bridge to

supply gas to the Western Region.

34

Chapter 3

PIPESIM

3.1 Introduction

PIPESIM for Windows is a user-friendly and multiphase software product developed by

Baker Jardine. The PIPES 1M for Windows family of multiphase software consists of:

PIPES 1M for Windows-Single Branch, PIPES 1M-Net, PIPESIM-Goal, HoSIM,

PlPESIM-FPT, WinGLUE (13). In this study PIPES 1M-Net software is used for network

analysis.

3.2 PIPESIM-Net

PIPES 1M-Net is a network analysis model extension to PIPESIM for Windows Single

Branch. Features of the network model include: unique network solution algorithm to

model wells. in large networks, rigorous thermal modeling of all network components,

multiple looped pipeline/flow line capability, well inflow performance modeling

capabilities, rigorous modeling of gas lifted wells in complex networks, comprehensive

pipeline equipment models and gathering and distributing networks.

Baker Jardine's PIPES 1M-Net for Windows is a highly sophisticated but user-friendly

software package for modelling steady state flow in networks. Combining powerful

three phase and thermodynamic analysis methods with rapid convergence algorithms

PIPESIM-Net for Windows will give accurate results in the shortest possible time.

Furthermore, with PIPES 1M-Net for Windows the user can simulate networks having

multiple sources and multiple sinks, flowing compositional mixtures or black oil fluids.

And, since PIPESIM-Net for Windows is truly Microsoft Windows compatible, the user

enjoy multi-tasking, printer sharing, data exchange and all the other benefits of this

operating system.

PIPES 1M-Net allows the users to simulate networks flowing just about any single phase

or two-phase mixture. If the user wish to get up and running quickly then the user can

35("'2->'""-=(

specify different source fluids as a simple black oils. However, the users are also able to

enter full compositional data for each source should the user wish. Furthermore, the

users are free to enter either global fluid properties or completely different fluids at

different sources.

3.3 Black Oil and Compositional Data

The difference between black oils and compositional fluids is that the formers are

approximations to the latter. Black oil fluids are generic fluid models that can be tuned

slightly to match your experimental data, whilst compositional fluids are defined

precisely as consisting of quantities of basic constituents (methane, ethane, glycols,

water etc.). Using a black oil model often requires less computation time than running a

fully compositional model but the user may lose some accuracy. The user may wish,

therefore, to run a black oil simulation first and then complete a compositional

simulation once satisfactory convergence has been attained. PIPESIM-Net for Windows

allows the user to mix black oils or compositional fluids, but the user can not mix black

oil with a compositionally specified fluid.

Before PIPESIM-Net for Windows can be run using rigorous compositional data, a

composition file must be created which contains a component list, quantities and the

equation of state (EOS) to be used. This file contains all input information entered by

the user and so this file can be restored and modified if necessary. Stream components

can be selected fr.om the built-in library, and/or created using the petroleum fraction

prediction utility.

In reality, oil systems contain many thousands of pure components, consisting of a

spectrum of molecules with different carbon numbers and exponentially increasing

numbers of different isomers of each. It would be impossible to model the behavior of

such systems by explicitly defining the amount of each of these molecules, both because

of the excessive computing power needed and the fact that laboratory reports could not

possibly supply all this information. Luckily, since the alkane hydrocarbons are non-

polar and therefore mutually relatively ideal, lumping them together in the form of a .

number of 'pseudo-components' results in fairly accurate phase behavior and physical'

property predictions.

36

" (

3.4 Calibration Data

The PIPESIM-Net for Windows toolbox contains all the components that the user will

need to view and build and edit a network flow sheet, namely; branches, manifolds,

sources and sinks. In PIPESIM-Net the User is able to specify volumetric flow rates at

both sources and sinks. The flow rate specification is made in STOCK TANK or

STANDARD volume units and is applied to the volumetric flow rate of either the gas or

liquid phase depending on whether the User chooses a GAS RATE or a LIQUID RATE.

The ability in PIPES 1M-Net to specify Stock Tank flow rates is exceedingly convenient

for most Petroleum Industry applications since flow rates of hydrocarbons are normally

reported at Stock Tank conditions. However, it is important to remember that

specifying flow rate in this way increases the chance of the user providing PIPESIM-Net

with a set of unphysical specifications.

It is possible for users to specify PIPESIM-Net problems that have no physically

reasonable solution. Such a set of specifications is termed a set. of unphysical

specifications. If the user supplies such a set then PIPESIM-Net will attempt to find the

solution. It will usually fail, however, because its algorithms are designed to look only

for physically reasonable solutions. An example of unphysical specifications would be

a pressure and flow rate specified at the entrance to a pipeline that causes the fluid to

"run-out" of pressure before the outlet of the pipeline.

37

3.5 Model Overview

PIPESIM-Net for Windows follows Baker Jardine's PIPES 1M-Net 2.01, which itself

was designed as a logical extension to PIPES 1M, a successful point-to-point pipeline

simulator. It is a powerful commercial software to solve just about any possible

multiphase network, and also retains most of the functionality. of both DOS PIPES 1M

and PIPES 1M for Windows. PIPES 1M-Net for Windows allows the user unlimited

flexibility with regard to type of problem (13):

• unlimited number of source and sink nodes (max. 256 branches)

• reverse flow if boundary conditions so dictate

• any number of branches connected to a particular node

• loop, crossover and recycle specifications

• in-line flashing of black oil and compositional streams

Hence, it is possible to solve any of the three generic network types, which is shown in

Figure 3.1.

I) Gathering 2) Distribution 3) Looped

Figure 3.1: Types of Network used in PIPESIM-Net

38

3.6 Network Validation

All computers modelling software requires a certain amount of physical data before

simulation can proceed. PIPES1M-Net for Windows is no different in this respect since

the solving of a network requires that values specified for pressure, flow rate and

temperature around the system will allow a solution. The criteria that must be satisfied

when seeking to model any network with PIPES 1M-Net for Windows can be

summarized as follows:

The connectivity of the network must be defined

The fluid composition at all sources must be defined

At least one pressure must be specified somewhere in the system.

The total number of boundary conditions must equal the total number of lone

nodes. This means that the number of flow, pressure and flow versus pressure

curves (inflow performance relationships) that the users specify must equal the

number of sources and sinks in the network.

3.7 Flow Correlations

Single-phase correlations are, as the name, implies, used by PIPES 1M-Net for Windows

for the simulation of pure gas or pure liquid i.e. not multiphase conditions. A number of

correlations are available including Moody and AGA (for dry gas). P1PES1M-Net for

Windows provides the user with a multitude of multiphase pressure drop and holdup

correlations for Horizontal and Vertical Flow Correlations.

3.7.1 Horizontal Flow

The following horizontal flow correlations are currently available in P1PES1M-Net for

Windows

Duns & Ros

Beggs and Brill (Original)

Beggs and Brill (Revised)

Oliemans

No Slip

Mukherjee and Brill

Dukler (AGA and Flanagan)

Mukherjee and Brill

39

Swap Angle is an angle (default 45 degrees) above which horizontal flow correlations

are used.

3.7.2 Vertical Flow

The following vertical flow correlations are currently available 111 P1PES1M-Net for

Windows

Duns and Ros

Beggs and Brill (Original)

Baker Jardine (Revised)

Orkiszewski

Hagedorn and Brown

No Slip

Govier, Aziz and Fogarasi

Mukherjee and Brill

Gray

3.7.3 Single Phase Correlations

Several single-phase pressure drop correlations are available for both liquid and gas

based systems. PIPES 1M will automatically select either the specified two-phase or

single-phase correlation depending on the phase behaviour at the particular section in

the pipeline. The single-phase correlation is set by default to the MOODY correlation.

So, by default if single-phase flow is encountered in the system, the program will

automatically switch to the MOODY correlation. The available single-phase

correlations are briefly described below:

Moody: At Reynolds numbers greater than 2000, the Moody correlation uses the

Colebrook-White equation (Moody chart) and at Reynolds numbers less than

2000, assume laminar flow (f=64/Re). (Default).

AGA: Known more fully as the AGA Gas correlation. This is the recommended

correlation for single-phase gas based systems.

Panhandle 'A': Empirical gas based correlation. Limited range of applicability. AGA

or Moody correlation recommended.

40

Panhandle 'B': Empirical gas based correlation. Limited range of applicability. AGA

or Moody correlation recommended.

Weymouth: Empirical gas based correlation. Limited range of applicability. AGA or

Moody correlation recommended.

In addition to the above, a number of sophisticated new correlations (e.g. mechanistic

models) are available as optional extras to PIPES 1M for Windows. These correlations

are the result of extensive research and development in multiphase flow laboratories

worldwide.

3.8 Convergence

PIPES 1M-Net for Windows uses a GNET algorithm to solve all networks. Reaching a

solution involves continually estimating and refining a matrix of results for each branch

while simultaneously taking into consideration the many sources of discontinuity within

the network. These sources of discontinuity' include, dead wells, two phase vertical

flow, critical flow, phase changes and flow regime boundaries.

By default the tolerance for PIPESIM-Net for Windows simulations is set to 0.01.

Mathematically this means that the .simulation will terminate when the root mean square

error for pressure at the junction node having the greatest root mean square pressures

error is less than 0.01. If the user decrease this value then the user are forcing

PIPESIM-Net for Windows to do more calculating and produce more accurate results.

PIPESIM-Net for Windows will by default complete a maximum of 100 iterations per

simulation. If after 100 iterations no solution meeting the required tolerance has been

found then PIPESIM-Net for Windows will stop and display existing results. If the user

find that a particular system is not converging then, generally, it is best to relax the

tolerance rather than increase the maximum number of iterations.

PIPESIM-Net for Windows makes use of convergence techniques that are tuned to suit

each individual problem. These routines are based on well-accepted mathematical

theorems but modified to allow for the discontinuities that might be generated by

different flow correlations, as well as those originating from the problem specification.

41

Chapter 4

GAS TRANSMISSION SYSTEM AND RELATED DATA

4.1 Introduction

The gas transmission pipelines in Bangladesh were initially planned and constructed

targeting particular bulk consumers or potential load centers. In the early stage of the

development of the gas sector, the grid system was possibly not visualized.'But over the

years the gas transmission system has expanded considerably and has become

complicated. Four Companies of Petrobangla such as Gas Transmission Company Ltd.

(GTCL). Titas Gas Transmission and Distribution Company Ltd. (TGTDCL),

Bakhrabad Gas System Ltd. (BGSL). Jalalabad Gas Transmission and Distribution

System Ltd. (JGTDSL) and two international coinpanies (Unocal Bangladesh Ltd .. Shell

Bangladesh Exploration and Development B.V.) are responsible for operation and

maintenance of their respective transmission pipelines (Chapter 2). The locations of

existing transmission lines (with future extension) were shown in Figure 2.6.

4.2 Network Analysis

A geographical breakdown of the demand is a prerequisite to any analysis of a

transmission network. In order to reliably cope with the gas transmission constraints and

more specifically with the maximum flow rates to transfer through the pipelines, the

geographical breakdown must go beyond the traditional split in four areas Ti las

Franchise Area (TFA). Bakhrabad Franchise Area (BFA), Jalalabad Franchise Area

(JFA). and Western Franchise Area (WFA) which are respectively under the

responsibility of TGTDCL, BGSL, JGTDSL, GTCL. The eight areas (Figure 4.1)

correspond to a compromise between a significant level of actual demand with a

dominant focal point for the demand, meaning that the necessary links (gas pipelines)

between areas are reasonably identified (9L

Area I: Western zone

42

LEa~ND

eor- ••.• _ •••••.• IP_I

S.",_",lC'"fU.rv ••••C"'_"

.,. •• __ ••••• rs"' ••.•• C •••.•• _"' ••..•.1I'a__ ••.• C,,"II"" .b •••••••••.'_'

....... ~.

,--

•. ••••..i'''. '•.•""""""'V'

o

G c... ••.__ •..

__ ~••••_ •.••••••1I!1"_

TR1PUAA

I I N D I A I'

BENGAl

-C:r Kulubd a

U A Y

"'': I t \,/"'"."~.'I <,; " I

~."""'-;~~oII' I '1.. \ At."'"1 "\'j') II 'I > ( i, I ' I" I .!.' to. I 1

'\1-<'11'11/'" I pj 1 i"'ulin Y ,

I .21~"o,,,,o,,, 0 '\ 1

@ ~~. '),,' \1,,1,@ CHI.' TAGONG\~ \ ~ •.,fbi'" '

CD V - ••• e&l ! !It I I",;" I, I-",-,~I" \~

\ 91' \ \,'----~-~iIlA1':GL,\DESI! I I

I TilE GE()(;RAPIUCAL A;lEAS ; :! FOR TIlE GAS SYSTEM D:,Vt:LOPMENT PIAN I Ii jl~ Calc \295 Map~, \,

"l~ --- I______ .-l_. ~-,---: ..Jr. >; ."'C '.'_-=-_ . .:i

o SO kIT'.

Ei£L:::b:~=-

00'I

Figure 4.1: The Geographical Areas for the Gas System Development Plan (9)

43/

Area 2: Dhaka (the greater Dhaka non-bulk market)

Area 3: Meghna (mainly three power stations)

Area 4: Bakhrabad-Chittagong (the BFA gas market)

Area 5: Ghorasal (mainly the power station and two fertilizer plants)

Area 6: Brahmaputra (mainly a fertilizer factory)

Area 7: Titas-Ashugonj (mainly the power plant and fertilizer plant)

Area 8: Sylhet (the .lFA gas market and the ultimate excess gas resources)

The main high-pressure lines of Bangladesh are shown in Figure' 4.2. Possible

extensions in Western zone are also shown in Figure 4.3.

Network analysis is a complex process. In this study, the gas transmission network is

analyzed with the help of PIPES 1M-Net. To simulate the network the following

information was required:

i) Source temperature, pressure/ flow rate

ii) Composition of natural gas of sources

iii) Pipe diameter, length, thickness, roughness, ambient temperature

iv) Minimum one source/ load pressure

The required data is collected from GTCL, .lGTDSL, TGTDCL, and UNOCAL

Bangladesh Ltd. All required data are available except pipe thickness and roughness.

Therefore, it is assumed that pipe thickness and roughness of pipe are 0.5 inch and

0.0006 respectively. The ambient temperature is changed with the season and place. The

. assumed ambient temperature is 25°C because of unavailability of data. The source

temperature of Kailashtilla gas field is 110°F and .lalalabad gas field is 83°F. The

temperature of other fields varies from 95°F to 110°F. In this simulation, the source

temperature of other fields is considered to be 100°F. The Weymouth equation, AGA

equation and Moody equation are used to simulate the network. To convergence the

simulation, maximum 11 % tolerance is used. But most of the cases the tolerance is

below 10 % only.

44

(INDIA)

BANGLADESH

GAS TRANSMISSION NETWORK

,..

\,'"\I'"\

I\I1I\I

23"

-

Map B

I\\

TRIPURA

r,- r,oJ " I,

\\\II

v

rII\

J",/

I(\\,"

Dale 12.95

See delalled map 9

ComJlIa ,"24", 115km

\ '\1(\\ \ \

",' \Feni lown

-./ R'l\'Ig~------l

SemUlarlg ,/

*/~/M.n~n

-'\ F.:JIl::M ••.,

\,\\ H.'hUItI

I T'

'IT,59kn,J\,\"l-I

-- ..•......_-------

'8 A Y OF 8 E N G A L

0 SO ,•. f:r Kutubdia'-

",. g, •,

Figure 4.2: Gas Transmission Network Main High Pressure Lines in Bangladesh (9)

45

,•

,r'")(

l h •••.w.

l,Jessore

~"\I...•,,I\

\.

\\\

-

TRIPURA

~.••r\J " I,,

\\\\

( I N D I A I

v

rI\\I

.//

I(,,,/

-/;''''{lI~-----7Semutang .'

tr /,,/1c.nIo;::l'Ilwll

~F.~,\,

"\

See delailed map

Camilla

\"-\, ",I ( ," ,\,., \

Feni Iown

~

J~f.,

161020"" \::a

62km

• 2.',165km, IBh,!IIam8f8 to Khulna I

""

Possible ~o,ec1in 2010

,."(

r.//

",.•.•..r-1I/

r',,r_,I

5' d' ~,.N !il, 0il: ~ &;I, ~ ~= 15 r-s' >er !l5 tl~ 0 f:l:E z ;c~~3

•...~ 0 0= ~~"

"

]

"."<"'""3;>:l"er3.o"

z"~o~"'"0o'"'"cr:"rnx""'"0'"

oI;:-1i3"'"3'"'"o"

>-c1~.(l..,.w

..,.e;,

Table 4.1: Chemical Composition of Natural Gas in Different Gas Fields (151

NP = Non-producing A = AbandonedN.B. P = Producing

SL Name of Chemical Composition of Gas (Volume Percent) Caloric Specific Remarks

No Gas Fields Value GravityMethane Ethane Propane i-Butane n-Butane High Nitrogen Carbon Gross

Composition Dioxide BTU/CFT

A UnderBGFCL1. Bakhrabad 94.20 3.65 0.72 0.20 0.10 0.24 0.42 0.47 1057.73 0.5970 P

2. Begumganj 95.46 3.19 0.64 0.17 0.04 0 0 0.30 1045.61 0.5833 NP

3. Belabo 94.79 2.49 0.60 0.20 0.15 0.13 0.34 0.60 - 0.6070 P

4. Feni 95.71 3.29 0.65 0.15 0.05 0 0 0.15 1049.84 0.5782 A

5. Habigoni 97.60 1.31 0.27 0.08 0.04 0.06 0.38 0.07 1023.91 0.5700 P

6. Kamta 95.36 3.57 0.47 0.09 0 0 0 0.51 1043.13 0.5743 A

7. Me£hna 95.15 2.83 0.60 0.16 0.09 0.07 0.37 0.53 - 0.5910 P

8. Titas 97.33 1.72 0.35 0.08 0.05 0.06 0.30 0.11 1031.55 0.5720 P

9. Shabbazpur 93.68 3.94 0.71 0.20 0.07 0.04 0.46 0.90 1046.21 0.5800 NP

10. Saldanadi 96.32 2.16 0.45 0.12 0.07 0.05 0.27 0.56 1032.60 0.5700 P

B UnderSGFL1. Beanibazar 93.68 3.43 1.10 0.29 1.23 0.17 0.99 0.12 1061.95 1.600 P

2. Chattak 97.90 1.80 0.20 0 0 0 0 0 1005.71 0.548 A

3. Fenchu£anj 95.66 2.50 0.63 0.11 0.04 0 0 0.06 1043.33 0.5740 NP

4. Haripur 96.63 2.00 0.05 0.14 0.01 0.17 0.66 0.34 1050.68 0.546 P

5. Kailashtilla 95.57 2.70 0.94 0.21 0.20 0.14 0.24 0 1056.00 0.5860 P

6. Rashidour 98.00 1.21 0.24 0 0 0.17 0.02 0.05 1012.00 0.5690 P

C Under International Oil Companies1. Jalalabad 93.50 3.50 1.30 0.20 .80 0.20 0.30 0.50 - - P

2. Kutubdia 95.72 2.87 0.57 0 0.31 0 2.36 1041.66 0.5860 NP

3. Sangu 94.51 3.17 0.61 0.19 0.07 0.41 2.44 1061.00 0.5900 P

4. Semutan£ 96.34 1-....-1.70 0.14 0 0.01 0 0.86 - - NP

N.B. BAPEX has been given the operator-ship of the Shahbazpur and Salda Nadi fields.

'\(

47

4.3 Gas Composition

The gases at the wellhead contain largely light hydrocarbons plus CO2, Nz and O2 in

small quantity including HzS in trace. The composition of the gases at the wellhead

differs from field to field in respect of liquefiable hydrocarbons in particular. The

compositions of natural gas of different gas fields are given in Table 4.1. In order to

meet the sale gas requirements with respect to composition and other parameters,

liquifiable hydrocarbons and water are removed/ recovered in gas processing plants.

Table 4.2 lists the specified sale gas composition including other parameters. A typical

composition of the sale gas actually delivered is also shown in Table 4.2. The gas

processing plants recover about 330 litres of natural gas condensates / liquids per

MMSCF gas processed.

Table 4.2: Sales Gas Specification ofTitas Franchise Area (II)

Date: June,2000 Duration: June 1 to 30 Time: 08:00

Sample Point: Ashugonj Metering Station Manifold Header, Ashugonj, Brahmanbaria

Pressure: 57 Barg Temperature: 22.8 0 C

Number of Samples: 11024

Average Gas Composition:

Composition Average Mole % Maximum Mole % Minimum Mole %

C6+ 0.07004 0.15998 0

Propone 0.36262 0.67065 0.21472

i-Butane 0.13491 0.35396 0.03368

n-Butane 0.07349 0.35791 0

Neo-Pentane 45.04450PPM 0.1509 0

i-Pentane 0.04678 0.30706 0

n-Pentane 0.01699 0.18902 0

Nitrogen 0.42046 0.92935 0.34037

Methane 97.2701 98.9522 95.9185

Carbon-Di-Oxide 0.07243 0.22977 0

Ethane 1.52804 2.14383 0

Physical Properties of Supplied Gas:

Average Gas Relative Density or S.G. : 0.57456

Average Heating Value, Gross BTU Dry: 1033.94

Heating Value, Net BTU Dry: 932.59

Liquid Hydrocarbon C5+ : 0.05626 GPM

48

4.4 Diameter and Length of Transmission Lines

The diameter and length of the transmission pipelines are given in Table 4.3, Table 4.4,

Table 4.5, and Table 4.6.

Table 4.3: Length and Diameter of Major Transmission Pipelines of JFA (9.15. and 16)

SL. From To Length (kIn) Diameter (inch)No.

1 Haripur Khadim 20 82 Khadim Sylhet 9 63 Khadim Kuchai 10 84 Kuchai KS-1 (Manifold) 39 65 Kuchai Kailashtilla 13 86 Kuchai NGFF 10 87 KS-l SPPM Regulator8 SPPM Inter (Manifold) 105 49 SPPM SC-1 (Manifold) 105 610 SC-1 CCF RegulatorI 1 CCF Inter 0.5 812 CCF Tagratilla 19 413 Tagratilla Sunamganj 13.5 414 Kailashtilla Jalalabad 18 1415 Kailashtilla Kailash GFI 3.5 1416 Kailashtilla Beanibazar 18 2017 Kailashtilla Fenchuganj 27 2418 Fenchllganj FenPP 5 619 Fenchllganj NS-1 (Manifold) 30 2420 NS-l Rashidpur 39.2 2421 Rashidpur Bibivana 30 2022 Rashidpur RashidGf 2 2023 Rashidpur Habiganj 28 2424 Habigani HGFI 10 1225 HGFI SH-I (Manifold) 20 626 SH-J HabigTN 5.6 627 SH-I Srimangal 10 628 Srimangal Shamshemagar 10 629 Srimangal Moulavibazar 26 630 HGFI Shahjibazar 2.5 831 HGFJ Katihata 35 1232 Katihata Ashllgani 18 1233 Habigani Ashugani 53 24

49

..

Table 4.4: Length and Diameter of Major Transmission Pipelines ofTFA (9. 16)

, SL. From To Length (km) Diameter (inch)No.34 TitasGF Bbaria I 1235 BBaria TN-I (Manifold) I 1436 BBaria TN-2(Manifold) I 1637 TN-I TN-3(Manifold) 21.1 1438 TN-2 TN-4(Manifold) 45 1639 TN-3 Narshindi 30 1440 TN-4 Narshindi I 1641 Narshindi Ghorasal 8.4 1442 Narshindi Demra 32 1443 Narshindi Shidd 45 2044 Narshindi BelaboGF 13 845 Shidd .T27(Manifold) 10 1046 J27(Manifold) Demra 10 1447 Demra Gulshan 32 1448 Gulshan Joydevour 25 1249 Joydevpur Elenga 56 1050 Ashllganj Daulatkandi 9 2451 Daulatkandi Daulot#(Manifold) 0.1 1252 Daulatkandi Monohordi 25 2453 Monohordi Elenga 89 2454 Monohordi Kishorganj 36 455 Monohordi Narshindi 32 2056 Dhanua Mymen 63.004 1257 Mymen Netrokona 32.5 6

Table 4.5: Length and Diameter of Major Transmission Pipelines of BFA (9. 16)

SL. Length (km) Diameter (inch)No.

58 Ashllganj Bakharabad 57.1 3059 Bakharabad Falljdar 171.5 2460 Bakharabad Dewanbag 60 2061 Sangu Falljdar 49 2062 Falljdar Chittagoni city 2.5 2463 Dewanbag Demra 8 2064 Dewanbag HariPP 1.58 1465 Bakharabad Salda 35 1066 Bakharabad Meghna. 28 867 Bakharabad BakharabadGF I 20

50

I\.

Table 4.6: Length and Diameter of Major Transmission Pipelines of WFA (9. 16)•

SL. Length (km) Diameter (inch)No.68 Elenga .fB1(Manifold) 15 2469 .fBI .fB2(Manifold) 9 30

70 .fB2 Nolka 15 24

71 Nolka . Sira;gonj 5 2072 Nolka Bbari 43 20

73 Nolka Ishurdi 65 24

74 Ishurdi Bheramara 25 2475 Bheramara Kuatia 15 2476 Kustia Jhenaidha 20 2477 Jhenaidha Jessore 50 2478 Jessore Khulna 64 24

51

Chapter 5

STEADY- STATE FLOW OF GAS THROUGH PIPES

5.1 Introduction

Pipes provide an economIc means of producing (through tubing or casing) and

transporting (via flow lines or pipelines) fluids in large volumes over great distances.

They are convenient to fabricate and install, and provide an almost indefinite life span.

Because flow is continuous, minimal storage facilities are required at either end (field

supply end, and the consumer end). Operating costs are very low, and flow is guaranteed

under all conditions of weather, with good control (an installed pipeline can usually

handle a wide range of flow rates). There are no spillage or other handling losses. unless

the line develops a leak, which can be easily located and fixed for surface lines. The

flow of gases through piping systems involves flow in horizontal, inclined, and vertical

orientations, and through constrictions such as chokes for flow control. This chapter

introduces some basic concepts of horizontal flow types.

5.2 Gas Flow Fundamentals

All fluid flow equations are derived tl'om a basic energy balance which, for a stcady

state system (no time dependence offlow parameters), can be expressed as:

Change in internal energy + Change in kinetic energy + Change in Potential energy +

Work done on the fluid + Heat energy added to the fluid - Shaft work done by fluid on

the surroundings = 0

Thus, on a unit mass basis, the energy balance for a fluid under steady - state flow.

conditions can be written as:

dv' g .dU+-+-dz+d(pV)+dQ-dw, = 0

. 2g, g, ................... (5.1)

It is converted into a mechanical energy balance using the well-known thermodynamic

relations. For an ideal process. Equation 5.1 becomes:

52

d 2

Vdp+ _V_ + JLdz + df" - dw, = 02g, g,

. .... . . .. . ; .. .. .. . (5.2)

........................... (5.3)

Neglecting the shaft work ws, and multiplying throughout by the fluid density, p:

dp + pdv' +JL pdz + pdf" = 02g, g,

All the terms in Equation 4.4 have units of pressure. Equation 4.4 can also be written as:

.............. (5.4)

where 6pl' represents the pressure drop due to friction, and is independent upon the

prevailing flow conditions.

5.3 Types of Single-Phase Flow Regimes and Reynolds Number

Four types of single-phase flow regimes are possible: laminar, critical, transition and

turbulent. Reynolds applied dimensional analysis to flow phenomena, and concluded

that the flow regime that will prevail is a function of the following dimensionless group

known as the Reynolds number, NR,:

N' = inertia - forcesR, V' fiISCOUS - orces

upd 4qp--=--

..................................................... (5.5)

For most practical applications, the Reynolds number for a gas is given by:

20q"Yg

N R, '" -f.l-d-

Where, q" is in mscfd, f.l is in cp and d is in inches.

As shown in the Moody fi'iction factor chart, flow regime is related to Reynolds number

as follows (171;

Flow type N Re, smooth pipes

------------ ----------------------Laminar <2000

Critical 2000-3000

Transition 3000-4000

Turbulent >4000

53

5.4 Pipe Roughness

Friction to flow through a pipe is affected by pipe-wall roughness. However, pipe

roughness is not easily or directly measurable, and absolute pipe roughness E is,

therefore, defined as the mean height of protrusions in uniformly sized, tightly packed

sand grains that give the same pressure gradient as the given pipe. This roughness may

change with pipe use and exposure to fluids. Some typical values for roughness are

shown below (IS!:

Types of pipe

Drawn tubing (brass, lead, glass)

Aluminum pipe

Plastic-lined or sand blasted

Commercial steel or wrought iron

Asphalted cast iron

Galvanized iron

Cast iron

Cement-lined

Riveted steel

E

0.00006

0.0002

0.0002-0.0003

0.0018

0.0048

0.006

0.0102

0.012-0.12

0.036-0.36

Commonly used well tubing and line pipe:

New pipe 0.0005-0.0007

12-months old 0.00150

24-months old 0.00175

From dimensional analysis, it has been deduced that relative roughness, the ratio of the

absolute roughness and inside pipe diameter, E/d, rather than absolute roughness, affects

flow through pipes.

54

5.5 Pressure Drop Calculations

pipeline (a pump, compressor, turbine etc.), this equation is readily integrated to yield

g pAu' 2!fpu'dlp,_p, =_ p6.z+--+--- (5.7)g, 2e, g,d

The pressure drop over a distance, L, of single-phase flow in a pipe can be obtained by

solving the mechanical energy balance equation, which in differential form is (\7)

dp udu g 2!fu'dl_ +_ +-dz +_'---.+ dW, =0 (5.6)P g, g, g,d

If the fluid is incompressible (p= constant), and there is no shaft work device in the

~=~~+~u+~ •...: (5.~

for fluid moving from position I to position 2. The three ten11Son the right-hand side

are the potential energy (PE), kinetic energy (KE) and frictional contributions to the

overall pressure drop, or

5.5.l The Pressure Drop due to Potential Energy Change (ApPE)

API'Eaccounts for the pressure change due to the weight of the column and fluid (the

hydrostatic head); it will be zero for flow in a horizontal pipe. From Equation (5.7), the

potential energy pressure drop is given by:

gApl'!' = -p6.z ., (5.9)g,

5.5.2 The Pressure Drop due to Kinetic Energy Change (ApKE)

ApKEis the pressure drop resulting from a change in the velocity of the fluid between

positions I and 2. It will be zero for an incompressible fluid unless the cross-sectional

area of the pipe is different at the two positions of interest. From Equation (5.7),

API'E=L(Au,)=L(u: -u~)= 8~g2 (~-~J (510)2g, 2g, J[ g, ld, d,

55

5.5.3 The Frictional Pressure Drop ("'PF)

The frictional pressure drop is obtained from the Fanning equation,

21fpu21"'PF =-~- (5.11)

g,d

where, fr is the Fanning friction factor. Usually, the Moody friction factor is used. The

friction factor includes, besides roughness, the flow characteristics of the flow regime. It

is therefore a function of Reynolds number and relative roughness:

where, k is the length of the protrusions on the pipe wall.

In laminar flow, the friction factor is a simple function the Reynolds number,

16If =- (5.12)NRC

In turbulent flow, the friction factor depends on both the Reynolds number and the

relative pipe roughness.

The Fanning friction factor is most commonly obtained from Moody friction factor

chart. This chart was generated from the Colebrook-White equation (191,

k = -410g( 3.7~65 +~r~P;J (5.13)

The Colebrook-White equation is implicit in fr, requiring an iterative procedure, such as

the Newton-Raphson method, for the solution. An explicit equation for the friction

factor with similar accuracy to the Colebrook-White equation is the Chen equation (I"!:

S6

5.6 Allowable Working Pressures for Pipes

It is desirable to operate a pipe at a high pressure in order to achieve higher throughputs.

This is, however, limited by the maximum stress the pipe can handle. The maximum

allowable internal working pressure can be detennined using the following ANSI (1976)

specification:

2(1-e)SEPmax = do - 2(t - c)Y

............... : (515)

5.7 Allowable Flow Velocity in Pipes

High flow velocities in pipes can cause pipe erosion problems, especially for gases that

may have a flow velocity exceeding 70 ft/sec. The velocity at which erosion begins to

occur is dependent upon the presence of solid particles, their shape, etc., and is,

therefore, difficult to determined precisely. The following equation can be used as a

simple approach to this problem (20!;

v, =C/ p05 ....•........................................................... (5.16)

The gas flow rate at standard conditions for to occur, (qe)", can be obtained as follows:

I ]0.5(q,t = 1,012.435d'lr g~T (5.17)

5.8 Horizontal Flow

Many pIpe line equations have been developed from the basic mechanical energy

balance (Equation 5.3):

pdv' gdp + -- + - pdz + pdf" = 0 (5.18)2g, g,

For simplification above equation, it is required to assume horizontal, steady- state,

adiabatic, isothennal flow of gas, with negligible kinetic- energy change. The gas

compressibility factor, Z, is made independent of temperature and pressure by using

57

,,

average compressibility factor, Zav, for simplicity. Integrating Equation 5.18 over the

pipe length from 0 to L and pressure PI to Pz, we have:

(

2 )(( 2 2 ~5 J2 _ Rg,T"PI - P2q" - 49.9644 P~, rgZ"TfL

ln common units, Equation 4.19 becomes:

5.8.1 Non-Iteration Equations for Horizontal Gas Flow

i) Weymouth Equation (17)

........................... (5.19)

.............. " (5.20)

Weymouth proposed the following relationship for friction factor as a function of pipe

diameter d in inches:

f = 0.0032/ dl"

......................... : (5.21)

Substituting for f from Equation 5.21 in Equation 5.20:

.......................... (5.22)

This is known as Weymouth for horizontal flow. It is used most often for designing gas

transmission systems because it generally maximizes pipe diameter requirements for a

given flow rate and pressure.

ii) Panhandle (Panhandle A) Equation (17)

This equation assumes that fis a function of Reynolds number as follows:

f = 0.0768/ N~~14(" ...... :. (5.23)

Substituting for f from Equation 4.23 in Equation 5.20:

......................... (5.24)

The Panhandle A equation is most applicable to large diameter pipelines, at high flow

rates.

58

iii) Modified Panhandle (Panhandle B) Equation (17)

One of the most widely used equations for long transmission lines, the Panhandle B

equation assumes that fis a function of Reynolds number as follows:

f ':'0.00359/ N~;~3922

The pipeline flow equation is thus given as follows:

........................ 025)

( JI.020( 2 2 JO'510( Jo.490 2.530

q" = 109.364 1;, PI - P2 _1 d 0.020 ••..•••••.•••••.••••..••..•..... (5.26)Ps(' ZCII,1;,J... Y g" f-1g

The Panhandle B equation is most applicable to large diameter pipelines, at high values

of Reynolds number.

iv) AGA Equation (6)

American Gas Association (AGA) developed a formula, as computer programs became

available to solve this more complex equation. The AGA formula involves the

calculation of a transmission factor based on the flow regime and other parameters and

takes into account changes in elevation. This equation for calculating pipeline flow is

somewhat more complex than above equations but involves the same basic parameters.

( J0.5

2 2 0.0375GHp;';

( JPI - P, - Z T1; III f 25q=38.77 P.

b

' F. d' (5.27)GTfZ",L

5.8.2 A More Precise Equation for Horizontal Gas Flow (The Clinedinst'

Equation)(1?)

The Clinedinst equation rigorously accounts for the deviation of natural gas from ideal

behavior (an average gas compressibility factor, Z,," is not used in this method), and

the dependence of friction factor, f, on Reynolds number and pipe roughness, leading to

a trial and error solution scheme.

59

0/\ .•'\ ...•

[p pcJ:c l[ d' lO., [ rp"l ( ) rPr1 ( ) JO"q" =7.969634 - -- J, p,lZ dp,-.L p,lZ dp, (5.28)p" YgT",Lf

This is known as the Clinedinst equation for horizontal flow.

5.9 Gas Flow through Restrictions

In several instances in a gas production system, the gas must pass through relatively

short restrictions. Chokes, consisting of a metal plate with a small hole to allow flow,

are the most common restriction devices used to effect a pressure drop or reduce the rate

of flow.

The velocity of a fluid flowing through a restriction (orifice, nozzle, or choke) IS

expressed as follow (20L

v = [1- (d, ~d 2 r]'"[2g(p, - p,)/ p]'" (5.29)

Here dl = diameter at the throat of the restriction device, ft

d2 = pipe diameter, ft

The flow through chokes (and flow restrictions in general) may be of two types: sub-

critical and critical.

5.10 Sub-Critical Flow

Flow is called sub-critical when the velocity of the gas through the restriction is below

the speed of sound in the gas. In the sub-critical flow regime, the flow rate depends

upon both the upstream as well as the downstream pressure. Subsurface chokes are

usually designed to allow sub-critical flow. The general equation for sub-critical flow

through chokes are given below (17):

( ~

~2 I k f( )21' ( )(k+I)/']q" = 974.6ICdP,d,,, T k-I tP, / PI - P, / PI (5.30)

Y g I

where gas flow rate in Mscfd, pressure in psia, temperature in oR

60

(J'. ,\\ ,', / .

5.11 Critical Flow

Flow is called critical when the velocity of gas through'the restriction is equal to the

speed of sound (about 1,100 ft/sec for air) in the gas. The maximum speed at which a

pressure effect or disturbance can propagate through a gas cannot exceed the velocity of

sound in the gas. Thus, once the speed of sound is attained, further increase in the

pressure differential will not increase the pressure at the throat of the choke. Therefore,

the flow rate cannot exceed the critical flow rate achieved when the ratio of the

downstream pressure P2 to the upstream pressure PI reaches a critical value. The well

known choke design equation for critical flow are given below (17):

456.71C"p,d:"q" = &g7; )", : (5.31)

5.12 Flowing Temperature in Horizontal Pipelines

For a gIven inflow temperature, T1, and surrounding soil temperature, Ts, the

temperature of gas flowing in a pipeline depends upon heat exchanger with the

surroundings, given by the overall heat transfer coefficient; the (pressure dependent)

Joule-Thomson effect due to pressure. changes caused by friction, and velocity and

elevation changes; phase changes (condensation, vaporization) in the gas due to pressure

and temperature changes; and energy loss (due to friction) during flow that is converted

into heat.

Considering thesc factors, Papay (1970) has derived the following equation, assuming

steady-state flow of gas, for the temperature TLx at a distance Lx from the pipeline

inlet(19l;

r _ [r, +C4 / C, - (c,C,)/(C,(C, +C,))]c;,W,I.X (C

l+ CzLx fe,e ..

where

C2=k/m

C, = (Z"2 - z,., )(c pI. - C pv ); L

~+~~+~~+~~) (5.3~c, C,(c, +C,)

61

c,

c,

I'-P[ )c ]Z-Z v-v brd, 'z C fldL + (1 - Z .lldv +"' ,-,Q + _2__ ' V + gil / L - __ 0 TL l'I pI. 1'1 1,1" L Lim 1

(2" - 2" Xp, - p,) (c j1dL _ C j1dv) + V, - V,L2 pI. pV L

Subscripts 1 and 2 indicate the inlet and outlet ends of the pipe, respectively (except in

the numbering of the constants C), and subscripts L and V represent liquid and vapor

(gas), respectively_

In deriving equation 4.32, Papay (1970) assumed that pressure, flow rate, and phasc-

transitions are linear functions of distance from the inlet end of the pipeline. This

equation, therefore, is very accurate for short line segments. For the case where phase

changes. can be neglected (single-phase flow), Equation 5.32 can be simplified to (17!:

J;.x = T;+(1; - r,)e-KL, j1,IV(P,- P')(I_e-K1x )_~(I_e-KL, )_(1" -v, IKL KL~v KL~vj

l(v, - v';~")1- e-KL, )+ (v,-2' )L, }... (5.33)

Iewhere K=--

mcpv

In equation 5.33, the first two tenns represent the heat exchange with the surroundings,

the third ternl represents the Joule-Thomson effect, the fourth term accounts for the

elevation changes, and the fifth term accounts for the change in velocity head. The last

two terms are small and may be neglected for most practical purposes. If the pressure

drop is small, then the temperature drop due to expansion is small, and the third term

may also be neglected. Neglecting these terms, Equation 5.33 simplifies to the following

familiar fornl (17!:

T,v =T +(T.,-T)e-KL, •••..•.••.••....•••.•.••..•.•..••..•.••..•.••..•.• (5.34)

_,\ s S

5.13 Steady-State Flow in Pipeline Networks

Gas transmission systems often form a connected net, flow through which is almost

always transient (unsteady). Most design and operation control problems, however, can

be solved reasonably well assuming flow to be steady state. The basic model considers

the transmission system to be a pipeline network with two basic elements: nodes and

node connecting elements (NCE's). Nodes are defined as the points where a pipe leg

62

ends, or where two or more NCE's join, or where there is an injection or off-take

(delivery) of gas. The NCE's include pipe legs, compressor stations, valves, pressure

and flow regulators, and underground gas storages.

5.13.1 The Mathematical Models for the Individual NeE's

I. High-pressure pIpe leg: The characteristic equation for a high pressure pIpe,

according to Equation 5.20, is as follows:

2 2 k 'P, - P, = ,q

I' ,J0.5or q = (, I~P, (5.35)

2. Low-pressure pipe leg: For a low-pressure pipe leg, with pressure close to

atmospheric, Zav'"1,and

P,' - P~ =(PI + P,)(P, - p,)'" 2p,,(PI - p,) (5.36).

Thus, the flow relationship simplifies to2P, - P, = k,q

or q = lP, ;,P2r (5.37)

p"y g (TZ)"fLwhere k, = 0.015744 2 , •••••.•••••.•••••..••....•••...••••. (5.38)T"d'

3. Compressors: Compressor characteristics vary depending upon the type and the

manufacturer. These are usually provided by manufacturer, and can be approximated

as follows:p .

q = k](p, I p,)" +k, (5.39)

where P is the compressor power and kJ, k4, and ks are compressor constants.

4. Pressure regulators: Pressure regulators are similar to chokes, and may be described

by the flow relationships for chokes. For sub-critical flow, equation may be used:

63

r( )" x ( )(X+')I X ]0.5q =k"p,t 1', II', - 1',11',. . (5.40)

where k6 = 974.6ICdp,d:JI/(rgd05[x/(X-I)r'

For critical flow, the flow relationship given by equation 5.31 is applicable:

q = k,p, (5.41)

where k, = 456.7ICdd:;, I(r gT, )05

5. Underground gas reservoirs and storage:

(, ,)".q = kg 1', - 1', (5.42)

where 1', = Average reservoir pressure

1', = Wellhead pressure

With these relationships for the components of a gas transmission system, a model

can be constructed for the system using the analogy of Kirchhoffs laws for the flow

of electricity in electrical networks to gas flow in pipeline networks. According to

Kirchhoffs first law, the algebraic sum of gas flows entering and leaving any node

IS zero:mLqi = 0 (5.43)

;=1

where m = number ofNCE's meeting at the node

q = positive for flow into the node, negative for flow of gas out from the node

By Kirchhoffs second law, the algebraic sum of the pressure drops (taken with

consistent signs around the loop is zero. Thus, if n is the number of NCE'sin the

loop, then for a high-pressure pipeline:

:t(1',' - p;)i = 0 (5.44);=1

and for a low pressure pipe system:

"L(I', - 1',) = 0 (5.45)i"l

A pipeline distribution system may either be loopless, or contain one or more loops.

The application of the relationships developed so far is described below for each of

these system types.

64

5.13.2 Loop Less System

A loop less pipe system, defined as one where the NeE's joined by nodes form no

closed loops, is shown in Figure 5.1. There are n pipe legs, and n+ I nodes. Gas

enters through node 1 and leaves through nodes j, for j=2,3, ..... ,n+ 1.

q, q"

q,

Node No.: ]Pressure : PI

2P,

3P,

n-]

Pn-lnP"

n+!Pn-t-l

Figure 5.1: Loop Less Pipeline System.

If one of the terminal pressures, inlet pressure or outlet pressure, is given and the

other is to be calculated for a given set of pipe leg parameters and the flow rates into

or out of the nodes, then the calculation procedure is quite straightforward. If the

inlet pressure, PI, is known, the pressure at any node j can be computed using

Equation 5.35 (for high-pressure pipe legs) summed over the applicable pipe legs in

the system:i-I

, ''''k 2Pi = P, - L. i'Ii;=1

. . .. . .. . . . . .. . . . . . . . .. . . . . . . . .. . . . . .. . . . . .. . .. . . . . .. . ... (5 .46)

wherej = 2, 3, .... , n, n+1

Similarly, if the outlet pressure, Pn+l, is known, Equation 5.47 can be used:

"P: = p,~"+ Lki'Ii' (5.47)i==j

wherej = n, n-I, ,2, I

The problem requires a trial and error type of solution if the maximum throughput

through the line at the outlet (node n+1) is desired for a given set of terminal

pressures and flow rates into or out of the intermediate nodes. Hain (1968) describes

an efficient procedure for solving this problem:

65

I',II

\

0,,'c;\ i \- \.

1. Guessing the maximum throughput of pipe leg 1, q~'). The superscript (1)

indicates that this is a first approximation.

2. Calculating the throughputs for individual pIpe legs, q~') usmg equation

5.46.

3. Using equation 5.47, calculate the outlet pressure for the system, (p~':,)4. If (p~':,)differs from the given outlet pressure- P'~+I by a value greater than

the prescribed tolerance, then correct the throughputs for the individual pipe

legs detemlined in step 2 using:

q?) = q~')+ f\.q (5.48)

where f\.q

5. Repeating steps 3 and 4 until convergence within a specified tolerance is

reached.

In step 4, the correction f\.q becomes more complex for flow systems with a greater

variety of NCE's. Hain (1968) gives the following correction for a line containing a

compressor station:

f\.q = _I(p~'!,)'- P,~",II,: (5.49)

[(p~), - (PI'),]; q, +L),q?)where (PI),.' (p,),. = compressor intake and discharge pressures, respectively, psia.

5.13.3 Looped Systems (17)

There are two types of looped pipe systems: single-loop (Figure 4.2), and multiple-loop

(Figure 5.3). Cross (1936) gave the first solution for low-pressure looped systems,

which was later extended to high-pressure systems (Hain, 1968).

66

r:

5.13.3.1 Single-Loop System

q,

Tq,

Figure 5.2: Single Looped Systems

B

A

Figure 5.3: Multiple Looped System

c

D

67

................ ~

......~

.......~

................••

The problem requires a trial and error solution scheme. An initial value for the flow rate

in pipe leg I is assumed. If this assumed value, q;'), differs from the actual throughput

by !'o.q, then by the node law of Equation 5.44 or 5.48 for steady-state flow (17.21):

I k;(q~i) + !'o.qM) + !'o.ql= 0 (5.50)i=l

where n = number of pipe legs in the single-loop system.

Solving equation 5.50 for !'o.q, and assuming that !'o.q« q, we get:

- Ik,lq!')ll)!'o.q - '='" (5.51)

22),jq!')\1=1

The gas throughputs for the next iteration, q~2) , are computed as before (Equation 5.48):

q~2) = q!') +!'o.q (5.52)

This procedure is repeated until for iteration k, !'o.qis less than or equal to a specified

tolerance. After this successful k-th iteration, the node pressures can be calculated using

the relationship (Equation 5.46) for a high-pressure network:i-i .

2 2" I (k)I (k) .Pi = P, - ~k, q, q, (5.53)i=l

for j= 2, 3, .... , n, n+ 1

where ki for pipe legs are calculated using Equation 5.35 for high-pressure lines. For a

low-pressure network, k, for pipe legs are calculated using Equation 5.37, and the node

pressures are computed using Equation 5.54:

P, = P, - 2),lq)k1Iq!!) (5.54)

for j= 2,3, .... , n, n+1

68

5.13.3.2 Multiple-Loop System

Stoner (1969, 1972) has presented an effected method for handling looped networks

with all kinds ofNCE's. In this method, the equation of continuity is used to express the

flow at each node in the system. The solution to the system of equations is complex, but

the method offers the ability to compute any set of unknowns. It thus overcomes the

limitation of the Cross method that can only be used to generate throughput or pressure

solutions. Illustration for Stoner's method is shown in Figure 5.4.

Figure 5.4: Illustration for Stoner's Method (17).

For any node j, the continuity equation (Equation 5.43) express the fact that the sum of

the inflows and outflows at the node is zero:

"Fj

. =" q (5.55)~ I,)

;=1

where q i,j is the flow from node i to node j, flows into the node are considered positive,

flows out of the node are negative. Fj thus represents the flow imbalance at the node and

will be equal to zero when the system is in balance, For example, consider node 2 that

receives gas from gas from underground storage (1,2) and pipe leg (10,2), and delivers

gas to compressor intake (3,2), and consumer supply attached directly to node 2.

Equation 5,55 for node 2 can now be written as:

F2= ql.2 - q),2 + QIO,2 - q, = 0 (5.56)

69

With the substitution of the appropriate NeE equations (from Equations 5.35 through

5.48), Equation 5.56 becomes:

( ) ( 2 2)" P,-4 (p,20 - p~t~ (557)F, ~ k p, -p S, - . +~~~S ,-q ~o .~ l\ 1,2 _ I I,~ k ( / )" k (k )0,5 l().~ 2

.1 P4 P.I + 5 \ 0.2

where S'j is the sign term that accounts for the flow direction:

S'.i = sigll(p, - Pi)

= + 1 for Pi 2:Pi

= -1 for Pi< Pi

Similar equations are written for all the other nodes in the system. Each of the node

continuity equations, such as Equation 5.57, can be expressed as follows:

FJx"x2,x" ,xJ = 0, for j=l, 2, 3, , n (5.58)

This non-linear system of equations can be solved using various iterative techniques on

a computer. Stoner (between 1969 to 1972) used the most popular solution method:

Newton-Raphson iteration. The values of the unknowns are computed repeatedly, until

the values from any two successive steps converge. The values of any unknown at the

(k+ 1) th iteration is computed as follows:

X~k+l)= X!k) + ,',x)'+') (5.59)

" ofwhere ",,_.l,',x. = -F forj. = 1 2 , nL...~ 1.1' "i=1 uXi

wherc the derivatives &F/&x, are obtained by differentiating the node continuity

equations. The method reqUlres an initial estimate for each of the unknowns, XiO

Generally, good initial guesses are required to achieve satisfactory convergence. A

standard mathcmatical technique for improving and accelerating convergence is to

introduce an accelerating factor, (X,. in the correction (Equation 5.59), as done by Stoner

in 1969:

xi"') = x!') + ,',xi'+I)a, (5.60)

where (x, is computed using the t.Xi for the current and previous steps. Stoner (1969)

proposed the following scheme for obtaining (Xi

Let A, = ,',x!'+I) / ,',x!'). For the first two iterations, where divergence is most likely tooccur, an (Xi = 0.5 is best to use in order to ensure convergence. In subsequent steps, the

70

OJ = O.SIAjl

OJ = 1.0 - O.SIAj IOJ = 1.0 + O.SIAjl

For-1<A1<1,

value of (Xi is determined as below for every other step; for the steps in between, (Xi = 1.0

is used:

For Aj ~ -1,

For Aj 2: 1, ° =3,

Stoner obtained these specifications for (Xi by experimenting with the mathematical

model on a computer. Naturally, these are empirical, system-dependent values, and the

user may have to do some experimentation to obtain similar or better schemes for the

acceleration factor (Xi applicable to the system.

71

Chapter 6

SIMULATION RESULTS

6.1 Introduction

The major part of the future energy demand would be met from natural gas and it is

estimated that gas demand would reach about 1450 MMSCD (average) and 1700

MMSCFD (maximum) by 2005 and 1900 MMSCFD (avg.) and 2250 MMSCFD

(max.)(4) by 2010. In this Chapter,. high-pressure transmission network has been

simulated and pressure at different sources, sinks and manifolds are matched with the

existing conditions. The existing pipeline capacity is analyzed and the level of capacity

utilization is examined. Then different cases have been studied for future prediction.

6.2 Demand-supply Scenario of High-pressure Gas Transmission Lines of

Bangladesh Using Current Data

The transmission pipeline network compnses of high-pressure trunk gas pipelines,

which operate at a pressure greater than 900 psig. Gas production in 24 hours from 12-,

July-OO to 13-July-00 was 931 MMSCFD. Out of this, Jalabad franchise area (.lFA),

Titas franchise area (TFA), Bakhrabad franchise area (BFA) and Westem region

franchise area (WFA) consumed 54, 621, 241 and 15 MMSCFD of gas, respectively.

Figure 6.1 shows the present network system. Description of the present network IS

given below.

6.2.1 North South Gas Transmission Pipeline (N-S line)

The North South pipelines was built under the Projcct Implementation Unit (PIU) of

Petrobangla which was then transferred to the Gas Transmission Company Limited

(GTCL), now in charge of operating this pipeline. World Bank financed this project.

The North South pipeline was commissioned in May 1992 but put in operation in

September 1993. It is a 175 km pipelinc of 24" diameter, made of OS' wall thickness

API5L grade X56 line pipes. Its origin is at Kailashtilla manifold station and termination

point is at Ashugonj metcring station where metering, regulating and fractionation

facilities are in place. It was built by SAIPEM (Itally). It transports gas from Kailashtilla

72

_L.

P: 106B Psig

Tltel$GF: 303.2 mmscfld

Sheh;PP: 36.61 mrnsc11d

N106: 5.00 ntnsc1~

Fef'ilP: 0.00 mmscfldRashidGF: 70.62 mm,d/d

4)HOF1: 187.9 mmscl/d

KTL234 6B.09 mm,d/d r,;}P: 1090 p,ig ~~odGF: 1092 Psig

F: 82.54 mmscf/d

(\)

Menifold

•TN1eK8I:ihata

r ,j ;'rl"

/

G ZiOFF:0.0~11d

Sal . APS: 1da. 15.12 rrmsd/d 00,99 mmscffd

. CtgCity:241.2 mmscf/d;: ," !F .-.-&...-o-.O-.~O-.e-_._e-_~.

Bokhro' K"Bopur eto L••••••m Ford J42 _OllO. BEWobP: 1075 Psig

",,",c'"D8Ulot#

1oIegt-naPP: 0.00 """did

D~1~e

73

•10 TN3

~

eg,BeloboOF 17.14

16.31 mmsd/d BekhraGF

8D hn~ 34.43 mrmlcl/d

MenthOl'~

Han?P: 29.BFi m'ffiicf/d

10

p

T8~T'.Jrsbo*

Dhanua

Sl'*JdPS 14.62 rrrnscfJd

Psigo

o

~ OO~"'~ c1ld~ur: 3. l\tnenPP:14.~e... NelKono: 200 """''lour

N16

JB1JB2

P 1006 Plig

~Jo

P: 1

B8ari:

Nob

Figure 6.1: High Pressure Gas Transmission Lines of Bangladesh simulated by Using Current Data

()

gas field, J alalabad gas field and Beanibazar gas field ta the inlet .of Narth Sauth

pipeline (Kailashtilla manifald statian). Gas alsa carnes from Rashidpur gas field and

Habiganj gas field ta the Narth-Sauth line at Rashidpur manifald statian and Habiganj

manifald statian respectively. There is na bulk cansumer from Narth-Sauth line except

90 MW Fenchuganj pawer plant, which cansume gas from Fenchuganj manifald

statian. The maximum allawable .operating pressure .of the N-S pipeline is 1135 psig, its

maximum inlet pressure 1090 psig. And the narmal pressure at Ashuganj is 850 psig.

The capacity afthis line is 385 MMSCFD.

6.2.2 Bakhrabad to Chittagong Gas Transmission'Pipeline (B-C line)

B-C line is a 174 km lang, 24" diameter pipeline. Its inlet paint is at Bakhrabad

manifald statian and .outlet paint is at Faujdarhat city gate statian. There is na bulk

cansumer al.ong this line.>Its capacity is 350 MMSCFD. The pressure at Bakhrabad

manifald statian is between 850 and 900 psig and with the maximum flaw rate .of 170

MMSCFD at Bakhrabad. The pressure dr.op is abaut 100 psig ta ga ta Chittagang. The

gas at Chittagang is distributed in a 350 psig ring main around the city. Mast cansumers

there are bulk c.onsumers, pawer plants .or fertilizer fact.ories. The damestic cansumptian

is .only 4% .of the tatal. The delivery pressure t.o all pawer and fertilizer plants is 350

psig except the delivery pressure ta KAFCO fertilizer plant in Chittagang, which is .only

120 psig.

B-C line is unfartunately limited at ANSI 400. This is inc.onvenient because it limits the

pipeline MAOP ta 960 psig but alsa because ANSI 400 valves and fittings are nat easily

f.ound an the market and can nat be exchanged with ather gas transmissian campanies

which are using ANSI 600 equipment. A cathadic protectian is applied an the pipeline

with a negative valtage .of at least 0.85 V between the pipe and a saturated caper- caper

sulfate reference electrode, which is satisfactary.

74

6.2.3 Ashugonj to Bakhrabad Gas Transmission Pipeline (A-B line)

To create stability in transmission system of Bakhrabad Franchise Area, A-B line is

constructed. It has also benefited from the physical integration of the three systems, such

as JFA, TFA, and BFA. GTCL is responsible for the operation of the A-B line. This

pipeline is 59 km long, 30" diameter, made of APIX52 line pipes with a MAOP of 1000

psig and ANSI 600 ancillaries. A 10m wide right of way was acquired with a IS m

wide working area during construction. This line delivers gas from Ashugonj metering

station to Bakhrabad manifold station. There is no bulk consumer from this line. Its

capacity is 500 MMSCFD. Mc Connel-Dowel of Australia constructed this line.

6.2.4 Bakhrabad to Demra Gas Transmission Pipeline (B-D line)

The gas flowing from Ashugonj to Bakhrabad will supplement the short supply from the

Bakhrabad gas field to the Chittagong area. To create stability in the transmission

system an idle pipeline was constructed to flow gas from Bakhrabad to Demra. It is a 68

km long, 20" diameter pipeline. Its origin is at Bakhrabad manifold station and

termination point is at Demra City Gate Station. Haripur power plant receives gas from

Dewanbag manifold station of Bakhrabad-Demra line. Its capacity is 250 MMSCFD.

The pressure of Bakhrabad-Demra line is smaller than the other transmission lines due

to the pressure problem of Bakhrabad gas fields. There are valves in inlet and outlet of

Bakhrabad-Demra line for controlling flow as well as pressure in Bakhrabad-Demra

line. There is also a by pass line from Bakhrabad manifold station to the point where

Bakhrabad gas field connects with the B-D line. A pressure regulator is connected to

this by pass line to regulate pressure according to the pressure of Bakhrabad gas field.

Even though, Demra City gate station accepts gas from Bakhrabad-Demra line by

controlling pressure (using pressure regulator) ofDemra city gate station. Spie-Capag of

France completed sub-surface drilling over Meghna River (4700 feet) by Directional

Drilling Method.

6.2.5 Ashugonj to Elenga Gas Transmission Pipeline (A-E line)

A-E line, which is known as Brahmaputtra Basin line, is a 124 km, 24" diameter

pipeline. Its inlet point is at Ashugonj metering station and outlet point is at Elenga

75

manifold station. It delivers gas to Kishoregonj from Monohordi manifold station;

Netrokona, Mymenshing power plant from Dhanua manifold station; Sherpur, Jamuna

fertilizer factory, Jamalpur from Elenga manifold station. Its capacity is 340 MMSCFD.

A-E.line was commissioned in 1991. Spie Capag of France constructed Titas-Elenga

Transmission lines. Both Elenga-Tarakandi line (43 km, 12" aD) and Dhanua-

Mymenshing line (56 km, 12" aD) were commissioned in 1991. Both Monohordi-

Kishoregonj line (35 km, 4" aD) and Tarakandi-Sherpur line (47 km. 8"/6" aD) were

commissioned in 1993. 40 km, 8"/6" Mymenshing-Netrokona line was also

commissioned in 1993.

6.2.6 Titas-Narsingdi-Demra Gas Transmission Pipeline (T-D line)

It is an 81 km long, 14" diameter pipeline. Its capacity is 175 MMSCFD. There are two

bulk consumers (Ashugonj power station and Zia fertilizer factory) from this line. Its

origin is at Titas gas field and termination point is at Demra city gate station. This line is

commissioned in 1968. Mis Society Des Grands Travaux De Marseille (GTH) of France

constructs this line.

6.2.7 Titas-Narsingdi-Joydevpnr Gas Transmission Pipeline (T-J line)

It is an 82.81 km (46.3Ikm + 36.50km) long, 16"/14" diameter pipeline. Its capacity is

265/220 MMSCFD. Its origin is at Titas gas field and termination point is at Narshindil

Joydevpur city gate station. Both Titas-Narshindi line (46.31 km, 16" aD) and

Narshindi-Joydevpur line (36 km, 14" aD) were commissioned in 1985. There are two

lines between Narshindi city gate station to Ghorasal manifold station. One line is 12 km

long, 14" diameter and other line is 12 km long, 16" diameter which is parallel to each

other. 12 km, 14" aD Narshingdi-Ghorasalline was commissioned in 1970 and 12 km,

16" aD Narshingdi-Ghorasal line was commissioned in 1999. Ghorasal manifold

station is the focal manifold of this line because two fertilizers and one power station

receive gas from this manifold. The capacity of Narshingdi to Ghorasal line is 370

MMSCFD. A group of companies are constructed T-J line. The name of the companies

are given below:

i) Maxwell Engineering Works Ltd.

ii) Probash Prokaushali

iii) Royal Utilization Services (Pvt.) Ltd.

iv) Business King

v) Shamsuddin Miah and Associates Ltd.

vi) Dawn Construction and Co. Ltd.

6.2.8 Monohordi-Narsingdi-Shiddhirgonj Gas Transmission Pipeline (M-S line)

It is a 67 km long, 20" diameter pipeline. Its starting point is Monohordi manifold

station and ending is Shiddhirgonj District Regulating station. Shiddhirgonj power

station consumes gas from this line. This line is inter connected to 14" Narshingdi-

Demra line. Monohordi-Narshingdi line and Narshingdi-Shiddirgonj line were

commissioned in 1997 and 1999 respectively.

6.2.9 Western Region Gas Transmission Line

It is 70 km long, 24"/30"/24"/20" diameter pipe line. Its ongm is Elenga manifold

station and tennination point is Baghabari station. Baghabari power station consumes

gas from this line.

6.2.1 0 Network Analysis

The network is analyzed by assuming 1092 psig pressure at Ialalabad gas field. The

simulated flow rate of Ialalabad gas field is 82.54 MMSCFD that is nearly accurate to

the original value (82.66 MMSCFD). Hence the simulation is correct. The simulated

results and pressure drop along the transmission lines are tabulated in Appendix 1. The

capacity of the North-South pipeline is 335 MMSCFD.

The variations of pressure and flow rate with the length are shown in figure 6.2 and 6.3.

NOffilally, as a rule of thumb 1 psig pressure drop occurs for 15-km length. From figure

6.2, it is clear that the pressure in North-South line is gradually decreased from 1090

psig to 1077 psig (pressure drop 13 psig) for 174 km. Velocity of gas in Bakhrabad-

Demra line (3.36 million fUhr) is greater than the Bakhrabad-Chittagong line (1.59

million fl/hr). Hence the pressure drop in Bakhrabad-Demra line is greater than the

Bakhrabad-Chittagong line.

77

I-+--N-S line-D- B-C line

B-D lineA-E line

200150100Length, Km

50o1065

1090

1085OJ i'iii I0- 1080 IQ)

I I~:J({) 1075 ''\"~~J::l-_ !(() --~--nf$___Q)~ I '0Q.. 1070

Figure 6.2: Variation of Pressure along the Major Gas Transmission Lines.

I

! ! II ' I

I : I, I

! - I !, I I~ • L_ . I I

I ; I, I I, , ,

400350o

b 300~ 250~ 200Q)~~ 150~ 100

LL50

oo 50 100

Length, Km

150

1I

I

200

-+- N-S line--/lO-- B-C line

B-D lineA-E line

Figure 6.3: Change ofFlowrate along the Major Gas Transmission Lines.

78

Figure 6.3 shows the variation of flow rate along the transmission lines. In North-South

line, first jump of flow rate occurs due to the addition of 70.62 MMSCFD at Rashidpur.

The second jump of flow rate occurs due to the addition of 132.24 MMSCFD at

Habigonj from Habigonj Gas Field. In Bakhrabad-Chittagong line, jump of flow rate

occurs due to the addition of 119.8 MMSCFD of gas at Faujdarhat manifold station

from Sangu gas field. In A-E line, 1st jump of flow rate occurs due to the addition of

83.11 MMSCFD gas at Daulatkandi from Daulot# (Manifold station on 16" Titas-

Narshingdi line). At Monohordi point, a sharp decrease in flow rate is observed due to

158.8 MMSCFD of gas is delivered to Narshindi manifold station and Kishoregonj area

from this point.

On July 12, 2000, the inlet and outlet pressures of North-South line were 1090 psig and

915 psig, respectively; but the simulated pressures in this line were 1090 psig and Ion

psig respectively. Therefore, a 17.6 % error in pressure was observed at Ashugonj

metering station. Demra, Chittagong, Bakhrabad, Elenga, Narshingdi, Ghorasal and

other important points also showed unacceptable pressure differences.

Variation of liquid holdup along the North-South pipeline is shown in Figure 6.4. At

Kailashtilla manifold station, the liquid holdup is 52.7% only. This value is become 53.9

% up to Rashidpur manifold station. After Rashidpur manifold station, liquid holdup is

decreased due to the addition of dry gas from Rashidpur gas field at Rashidpur manifold

station. At Habigonj manifold station, liquid holdup is 44.8% only. After this point, this

value decreases again due to the addition of dry gas from Habigonj gas field at Habigonj

manifolld station. At Ashugonj metering station, liquid holdup increases and becomes

25.9 % due to pressure drop.

79

60

50;,Roci 40:::l-0

o 30I-0

'S 200-:.::J

10

, ,: --+-- N-S line i

oo 50 100

Length, km

150 200

Figure 6.4: Variation of Liquid Holdup along the North-South Pipeline

If the same simulation is revised with the known pressure at Kailashtil1a manifold

station (1090 psig) and Ashugonj metering station (915 psi g); the simulated pressure at

other manifold station nearly matches with the measured data. Figure 6.5 shows the

present scenario. Good pressure match is observed at different nodes and delivery

points, which is shown in Table 6.1. The percentage of error at different nodes and

manifolds are very low (Table 6.1). Figure 6.6 shows the comparison of calculated

pressure to the measured pressure of North-South line. There is almost negligible

pressure error is observed at North-South line. But from Figure 6.7, it is observed that

the pressure drop in Bakhrabad-Demra line is greater than the Bakhrabad-Chittagong

line. Since the velocity of gas in Bakhrabad-Del11ra line is greater than the Bakhrabad-

Chittagong line, therefore, the pressure drop in Bakhrabad-Demra line is greater than the

Bakhrabad-Chittagong line. Even through, the pressure drop in North-South line is 174

psig. A significant pressure drop and flow constraints is also observed at Ashugonj-

Bakhrabad line and Narshindi-Demra line. Therefore, it is required to find out the reason

of the above situation.

80

HGf: 18790mmscf/d

TitasGF: 303 mmscl/d

FenPP: O.OOmmscf/d

ShahjiPP: 36.61 mmscf/d

N106: 5.00 mmscf/d

Barab Fa~darCtgCity: 750.00 psig

MSharai

lani10ld

J42

TN1

Kalihata

8.[ line

Feni

KTL1~KTL234f ':12 604 68 08£ P 1090 PStgmmscf/d mmscf/d JalaGE.

~ /P1090P"g

N61 - _...@KTdl~1\1111 ~.,... 88azer 0 00 mmscl/d

ZiaFF: 0,00 m~f~i/d100.99 mmscf/d

Laksham

N108: 916.00 psig

Sylhet: 17.28 mmscf/d

.".-8 line

Bakhra

P: 891.17 Psig KuBapur SIJreMegilePP

A.c i:n",

B.D line

BeleboGF: 16.31 mmscf/dMeghnaG

~fl

T

Dhanua

N107: 5.00 mmscf/d

ShiddPS: 14.62 m~~~rrd 29.86 mmscf/d MegPP: 0.00 mmscf/d

P: 864.98 Psig

DGhoraFF: 43.20 mmsc&Ro~aFF

~

~ ~mmS1U~enpp ~ ~N98: 4.00 mmscfld Ja~pur ~ LX NetKona:

j ~menDMymen: 2.00.mmscf fJ

P: 862.53 E'.,.r,g,~.Nr:,binePsig

NoIlka JB2

BBeri: 13.19 mmscf/d

DGulshen: 52.00 mmscfll

DJDevpur: 6.00 mmsc1fd

DemriDDemre: 87.00 P: 750.01

mmscf/d Psig

SanguOF: 119.8 mmscl/d

8o

Figure 6.5: Demand-supply Scenario of High-pressure gas transmission lines of Bangladesh modified by known pressure at Ashugonj.

81

I~---.._.--.---..

--+- Calculated-_ Measured

200

. ~~---~~---

50 100 150

Length, Km

o

.Ql 1100C/)

0.. 1050

~ 1000::lC/)C/) 950~

0.. 900

Figure 6.6: Calculated and Measured Pressure along the N-S Line.

--+- N-S line--B-C line

I B-D line_....~~E line

-----.----1

~::lC/)C/)

~0..

11501100 - -------.-~ .. --._._.--.~.--.~._~-~.~--~--._-~-~--- ..

1050

.~ 1000c.

950900 ,1--

850 ---.- - - - - .. -

800 -~----.-.----

750

700o 50 100

Length,Km

150 200

Figure 6.7: Variation of Pressure along the Major Gas Transmission Lines after

Modification

82

Table 6.1: Comparison of Simulated Pressure to the Measured Pressure

Node/ Delivery Point Measured Calculated %Pressure (psig) Pressure (Psig) Error

APS 860 873.11 0.02GhorasalPP 685 655.55 0.04HaripurPP 700 761.61 0.09RPCL(PP) 830 855.71 0.03GhorasalFF 704 793.82 0.13Bakhrabad 867.3 891.17 0.03Ashugonj 915.81 915.79 0.00Demra 710 750.01 0.06Chittagonj 712.5 700 0.02Kailashtilla 1090.74 1090 0.00Rashidpur 1046.64 1035 0.01Habigonj 1020.41 1005 0.02

The reasons of flow constraints are given below:

i) Due to the condensate accumulation in transmission lines, the effective

diameter of the lines may get reduccd and flow constraint may arise.

ii) Due to the corrosion of pipe, the roughness of the pipe may increase.

Hence pressure drop through the line will increase.

iii) Un-authorized delivery line (which is common problem in Bangladesh)

can exist in the transmission system. Hence pressure drop may arise.

Variations between simulated results and measured results might be due

to the system loss in transmission system. During 12-lul-00 to 13-lul-00,

the production of gas was 931 MMSCFD but consumption was only 905

MMSCFD. Therefore, 26 MMSCFD of gas are lost during transmission

and distribution system.

iv) During the simulation pressure losses due to valves and fittings are over

looked.

v) There are two-flow controllers, one the Ashugonj to Elenga line and the

other on the Ashugonj to Bakhrabad line that are over looked during

simulation due to the Software limitations. The flow controllers are used

to control flow of A-B line and A-E line. The diameter of A-B line is

83

greater than the A-E line. Hence A-B line can carry large volume of gas

than A-E line. But practically this was not happened due to the constraint

ofB-D line. Therefore, A-B line carry gas depends on the demand ofB-C

line and B-D line that is controlled by flow controller.

vi) Pressure drop occurs in every metering, regulating, condensate separating

station that is also over looked during simulation due to Software

limitation.

As a result of condensate accumulation the effective diameter of the North-South line

may get reduced and pressure drop occurs in every metering, regulating, condensate

separating station. To investigate these point, the network has been simulated by

reducing the diameter of the North-South line (assumed diameter of North-South line is

22" OD), installing choke at the inlet of Ashugonj-Elenga line, Bakhrabad-Chittagong

line and Bakhrabad-Demra line of bean size 14.5", the measured pressure in

transmission lines, except Bakhrabad-Demra line, turned out to be close to the simulated

pressure. Figure 6.8 shows the variation of pressure along the major gas transmission

lines. The inlet pressure of the North-South line is 1090 psig and the outlet pressure is

928 psig. On this day, the measured pressure of Ashugonj metering station was 915

psig. Therefore, it can be said that the diameters of the transmission lines have been

reduced.

11501100

.gJ 1050(/)

D.. 1000

~ 950:J(/)

(/) 900~D.. 850

800

750

.w.... - ..,.....--.:.-.

o 50 100

Length, km

150 200

-+- N-S line

--A-E line

B-D line

B-C line

Figure 6.8: Variation of Pressure along the Major Gas Transmission Lines.

84

The outlet pressure of the Bakhrabad-Demra line is 784 psig that is larger than the

measured pressure. The measured pressure of Bakhrabad-Demra line varies from 550

psig to 600 psig that depend on the pressure of Bakhrabad gas field. The measured

pressure .of Bakhrabad gas field was 600 psig. In the next simulation, attempts were

made to match pressure at Bakhrabad gas field.

6.3 Modification of Network by Using Known Pressure at Bakhrabad Gas Field

From the previous study, it is clear that the pressure at Bakhrabad gas field is 891 psig.

But it is impossible for this field to produce 35 MMSCFD at this pressure. Current

producing pressure of this field is 600 psig only. At present, Bakhrabad gas field is

connected to the network system by reducing the pressure of Bakhrabad-Demra line. To

reduce pre~sure of Bakhrabad-Demra line, two valves and pressure regulator are used

which are described before.

Currently Bakhrabad-Demra line is the focal line of the transmission lines, which is

treated as an idle line, which means that the volume it transports is much lower than its

capacity. Bakhrabad-Demra line transport gas to Demra city gate station and Haripur

power station. But pressure in Bakhrabad-Demra line is lower than the Demra city gate

station. Therefore, it is facing serious problems to transport gas parallel to the other

transmission lines. Low pressure at the Bakhrabad gas field has created this problem

because the field producil}g pressure is 600 psig. It is apprehended that if production of

Bakhrabad gas field is stopped, the well would die due to accumulation of sand and

water. There are valves in inlet and outlet of Bakhrabad-Demra line for controlling flow

as well as pressure in Bakhrabad-Demra line. There is also a by pass line from

Bakhrabad manifold station to the point where Bakhrabad gas field connects with the B-

D line. A pressure regulator is connected to this by pass line to regulate pressure

according to the pressure of Bakhrabad gas field. Even though, Demra City gate station

accepts gas from Bakhrabad-Demra line by controlling pressure of Demra city gate

station using pressure regulator. When Demra city gate station accept gas from~,

Bakhrabad-Demra line, delivery pressure from Demra City gate station decreases

drastically. The present simulation (Figure 6.9) is simulated by reducing the diameter of

85r-'-

.~-""(~-e,

/

North-South line, taking a separator at Ashugonj, installing a choke of bean size OS' in

the inlet of Bakhrabad-Demra line and blocking reverse flow from Demra city gate

station. Assuming 625 psig pressure at Bakhrabad gas field, the scenario is simulated.

The calculated flow rate of this field is 34.32 MMSCFD that is equal to the delivered

flow rate, 34.43 MMSCFD. The simulated results are shown in Appendix 3.

The variation of pressure with length are given in Figure 6.10. The outlet pressure of

North-South line is 917 psig that is close to measured pressure at Ashugonj (915 psig).

The measured pressure of Bakhrabad-Demra line varies from 550 psig to 600 psig that

depend on the pressure of Bakhrabad gas field. After simulation, the calculated pressure

along this line varies from 907 psig to 619 psig. Figure 6.11 shows the variation of flow

rate along major transmission lines modified by using known pressure (625 psig) at

Bakhrabad gas field. After Dewanbag manifold station, the flow rate of Bakhrabad-

Demra line is reduced and become zero because the outlet pressure of Bakhrabad-

Demra line is smaller than the Demra city gate station.

Effect of separator at the end of North-South line is shown in Figure 6.12. At

Kailashtilla manifold station, the liquid holdup is 40% only. This value is become 41.4

% up to Rashidpur manifold station. After Rashidpur manifold station, liquid holdup

decreases due to the addition of dry gas from Rashidpur gas field at Rashidpur manifold

station. At Habigonj manifold station, liquid holdup is 32.6% only. After this point, this

value decreases again due to the addition of dry gas from Habigonj gas field to Habigonj

manifolld station. At Ashugonj metering station, liquid holdup decreases and becomes

0.05 % due to separation of liquid from gas by using 90% efficient separator.

86

~da QgCIy

P: 795.2P,;g

Tlt• .oF303.00rrrn,cfld

FenPP

ShotjlP!'36.61 rrrnocfld

Nl06

ea.,

F: 70.62 fIlIllOcfld

_ ..

: 100.99 fIlIllOcfld

FenGanj

.142

E-Cnre

Manifold

Manlf

HalJigan]

Rashidp

educed Die. of N.S line is 22"

KatihEia

N.S line

T [i :I'-,'~

T.J line

Separator

Sylhel : 17.28rml$cf/d

HOliiF:3.47"""",lid

o

8""lYobadlI KuB"""'S-". L.I"il_'~enI'Choke Be8"lSize 0.5"

Me!1'PNl07

B.D fine

'ewnbog

-

~LX~KOO.

ShId'S

.e'JB1

\'.':;,!ern ,eQK,r,~,.~r';;r",I~_:iQt., lin",

N98

'SOMj

SnJuGf'

Figure 6.9: Demand-Supply Scenario of High Pressure Gas Transmission Lines modified by Known Pressure at Bakhrabad Gas Field

87

."Q

1200 -

1100----+-N-S line--A-E line

B-D lineB-C line

50 100 150 200

Length, km

Figure 6.10: Variation of Pressure along Major Transmission Lines modified by Using

Known Pressure atEakhrabad Gas Field

-+-N-S line--A-E line

B-D lineB-C line

20015010050

400o 350~ 300(fJ:2 250 -:2. 2002~ 150

~ 1~~ t=~~=----t=-----~-~-~-~- ~--~-=-----ol---~-o

Length, km-- -- ------------_._--------_.--- -~----.-.------_._--_.- ---~ --~

Known Pressure at Bakhrabad Gas Field

, \Figure 6.11: Variation of Flow Rate along Major Transmission Lines mod:ified-by Using

'l "

\ ''"''~

, ,'. ' n'- --'

88

45 .40. -~----- ._- ...-..- ..

?f2. 35 .---~-.- ...ci 30::J-0 25aI 20 -.-~--.._..-0.S 15 .CT::i 10--5.-----o

l. 1

-+- N-S line~- --------- --- -

o 50 100Length, km

150 200

Figure 6.12: Effect of Separator at the End of North-South Line

89 i,

6.4 Modification of Network by Setting up a Compressor Station at Bakhrabad

Gas Field

The pressure of Bakhrabad gas field is decreasing day by day. Current producing

pressure of this field is 600 psig (year 2000). Bakhrabad-Demra line accepts gas from

Bakhrabad manifold station by reducing and regulating pressure of this line. This is

possible by setting valves at the inlet and out let of Bakhrabad-Demra line. There is also

a by pass line from Bakhrabad manifold station to the point where Bakhrabad gas field

connects with the B-D line. A pressure regulator is connected to this by pass line to

regulate pressure according to the pressure of Bakhrabad gas field. This special

arrangement is taken only for accepting gas from Bakhrabad gas field. At Demra city

gate station, the pressure is regulated according to inlet pressure with pressure-regulator.

To connect Bakhrabad gas field with the transmission system without reducing the

pressure of B-D line, a compressor station need to set up at Bakhrabad gas field. To

investigate this point, setting up a compressor (700 hp, 70% efficiency) at Bakhrabad

gas field simulates the scenario (Figure 6.13). The simulated results are shown in

Appendix 4.

The variation of pressure and flowrate with length are given in Figure 6.14 and 6.15.

The inlet pressure to the N-S pipeline is 1090 psig. If a 70 % efficient compressor of

700 hp is set up at Bakhrabad, the pressure increase to 846 psig which is close to the

Bakhrabad-Demra transmission line. Figure 6.16 shows the effect on transmission

system after setting up a compressor at Bakhrabad gas field. Therefore, no significant

unreality in pressure drop is observed in the transmission lines.

90

r(,

Shl:lt1JIPP: 36.61 nrnsctJd

TilasGF: 303.2mmsdd

N106: 5.00 ITIfTlsc11d

e(;) .

TN1

Mani101dKal:ihala

Of'"APS: 100.99 mmscfld

428.04 msm31d 37.76 C

Menlt

T ".j "n.;------0--------

3.i: lint:'

0-.0.0-.0-.0 ..• --0- .• _0--.__0-_

Kl&pu' 8ijro lol<ohom Fori J42 MSh",oi Sarab

N61 ~/

.J')N112 BBazarGF:0.00 mmscfld

~ar; -0- [email protected]'N4 (;) FenPP: 0.00 rnnsc11d. ~

~st1idP RashldGFSylhet: 17 .28 mlTlScfld '

ell,_.

,.:\.E fine

---o--~_~ N103 5.00 mmsOf/dDhanua Morl('nor -0-- __...,

o

,.hFF: 12.8""'$01'"lN3

N C~. 0~r$rll'"lgdl

~JId---O- ,-.--o-----~---- O\e, Issl .r

Q). .. -.es'---V--O NB7

NSf'OhoroPP:~~~Ctld

Tarabo~

o hoob""

~ OO~~ 00tTYnsc1Jd~, 3. MmenPP: 14.88 ,,... NelKana: 2.lipur

N76

'.JJ,:;.~~~:r, ~;:'r-_~'linE:

~J,

(J

--~---'tt'l__J82-.

SeJanj:

HoriPP: 29.66 "JIml'P<Is.00 m~1fP: 0.00 rnm<c1/d

Shid(f='S: 14.62 mmscfld

Figure 6.13: Demand-Supply Scenario of High Pressure Gas Transmission Lines by setting up a Compressor Station at Bakhrabad Gas Field

91--,

/ \~'\

-11-

11501100 --- - --------------------- -------------

rn 1050;r 1000

950900850800750700

-+-N-S line---A-E line

B-D lineB-C line

o 50 100Length, km

150 200

Figure 6.14: Variation of Pressure along Major Gas Transmission Lines after setting up

a Compressor Station at Bakhrabad Gas Field

4000 350u..0 300(f)

~ 250~ 200OJ 150-ro'-;;: 1000 50u..

0o 50 100

Length, km

150 200

-+- N-S line-11--- A-E line

B-D lineB-C line

Figure 6.15: Change of Flow Rate along Major Gas Transmission Lines after setting up

a Compressor Station at Bakhrabad Gas Field

92

-----~._---_._-~---------------------------

-

--- -- - --

- - ----- - -- - -

- -- - - - --

- - -- - - - - - - -

.2'(/)a..

1000

800600400200

oo 0.5 1 1.5

__ Compressor atBGF, HP=700.Efficiency=70% .~_._-_.._--~- .-

Length. ft-- --- -------- -~- ------------- - _.- --------

Figure 6.16: Effect on Transmission System after Setting up a Compressor at Bakhrabad

Gas Field

6.5 Gas Supply- Demand Scenario of High Pressure Transmission Line at

Maximum Load

The demand of gas is increasing day by day in power, fertilizer, industrial and domestic

sectors. To meet this demand, it is required to produce gas from the fields at desired

capacity. If the proposed power plants come into production and all fertilizer and power

plants operate at their peak production, the consumption of gas will be 1496 MMSCFD.

Then the capacity of N-S pipeline will have to be 696 MMSCFD. Presently this line is

carrying gas at a rate of 400 MMSCFD. Using maximum load at all delivery points and

setting proposed power plants does the present simulation. The network is shown in

Figure 6.17. The simulated results are tabulated in Appendix 5.

The variations of pressure and flow rate along the major transmission lines are shown in

Figures 6.18 and 6.19. The capacity of North-South pipeline is 696 MMSCFD. But the

pressure at inlet point of North-South pipeline is 1312 psig, which is much above the

design pressures (l090 psi g). The pressure drop in this line is 536 psig that is also very

high. It is clear that the pressure drops in North-South line are greater than the

recommended pressure drop. Though the pressure drops in the other transmission lines

are acceptable, many important points experience shortage of pressure. This serious

pressure drop of North-South line is the indication of inability of the pipeline to carryC

93

Figure 6.17: Gas Demand-Supply Scenario of High Pressure Transmission Line at Maximum Load

, 20.00 IMlScl/d

135000 P3IlI

P:769 p,;,

FerilP: 20.00 I1lITlSCfA::l

OOll%lIr.35.00 mmscf/d

~: 160.00rrJl'lSCf,ld

Tte:sGF: 300.00 IlYY'IJd/d

..r , 311. 9 P$igKTile

Shetdf'P: 35.00 rrrnsc1'A::I

....,""','"..142

N'

o "Rashk:lOF: 161100 tnrl'lSef/d

K_.

S.C line

N111

,..•••••••••••

A 6.00mmtd/d

..,.

a~

Khodm

K""";o..l'lTDSL: 78.00 11mM""",

SoGaon

-~~. 3.00 1M'lSC1/d , NetKona: 2.00 mmscfA::lLX

ShidlPS:40.001mISc1~ 7000 lTrf'lItI!6dS: 2.001MlSCf~ 90110rrmsc1.t1

""'"'" .""solrt 40DD rnrnsc11d

N••••

94

I'\ .

expected flow rate. Therefore, it is required to increase the carrying capacity of North-

South pipeline at desired pressure to remove the constraint of transmission system.

--~-----_._---- ----- -_._----_._---------------

---------- -_.-------_.

.--.-::= -~~•••~=-.:.-'I', _11----_- - ----'1 . "a=_------.--

___ N-S line__ B-C line

B-D lineA-E line

200150100Length, Km

50o

14001300 .- - ------- ----

.~ 1200 -----. - - -.----.------.---..---a. 1100~ 1000:J~ 900£ 800

700600

II

Figure 6.18: The variations of Pressure along the Major Transmission Lines modified by

Maximum Load

800700 ------ ._----

0 600 ---_.- --------- ---LL()CJ) 500 ------- -~~ 400

I(])-C1l 300 -I -- --_.~ l~ • I0 200 .~~~--

-u:: ..__ ." - -

II

100 ._--- - ---

0

=-..=-N~s-lin-~11-lIl-----B-C linel!

B-D line I__.A -~J.!~.1

o 50 100Length, Km

150 200

Figure 6.19: Change of Flow Rate along the Major Transmission Lines modified by

Maximum Load

95

6.6 Modified Network Using Rashidpur-Ashugonj Loop Line

Petrobanglal GTCL intend to expand the transmission capacity of the existing 175 kIn

24" OD Kailashtilla to Ashugonj (North-South) gas transmission pipeline from 330

MMSCFD to 755 MMCFD by constructing 30" OD loop line between Rashidpur and

Ashugonj. The proposed pipeline will be more or less parallel to the existing 24" OD

North-South pipeline. Considering the projected downstream demand and upstream

supply potential from the sources it has been planned to implement the project in two

phases. Phase I i.e. 47 km section extending from Habigonj gas field to Ashugonj

metering station of GTCL is scheduled to be commissioned by 30th June 2001 to

transport 230-250 MMSCFD gas from Habigonj and Titas gas field (Khatihata). Phase

II i.e. 35 km section extending from Rashidpur-Habigonj gas field is scheduled to be

commissioned by 30th June 2002 (12)

To overcome the constraints of N-S pipeline, construction of 82 km 30" OD Rashidpur-

Ashugonj loop line is required. Figure 6.20 shows the loop line with provision for a

back-up manifold station a Habigonj and at other two suitable locations. Titas

(Khatihata) well is connected to this loop line. The simulated results are tabulated in

Appendix 6.

The variations of pressure with the length are shown in Fig!1re 6.21. The capacity of

North-South pipeline with Rashidpur-Ashugonj loop line is 850 MMSCFD. The inlet

pressure to the North-South pipeline is 1091 psig that is near about the design pressure

(1090 psig). The pressure drop in Bakhrabad-Chittagong line is greater than the

Bakhrabad-Demra line because the velocity of gas in Bakhrabad-Chittagong line is

greater than the Bakhrabad-Demra line. The changes of flow rate along the major

transmission lines are shown in Figure 6.22. In North-South line, up to Rashidpur the

flow rate is 268.51 MMSCFD. At Rashidpur point, Bibyana gas field (assume flow rate

100 MMSCFD) and Rashidpur gas field will delivered 280 MMSCFD of gas. From

Rashidpur point, 56.73 MMSCFD gas will pass through North-South line and 491.73

MMSCFD gas will pass through Rashidpur-Ashugonj loop line. At Habigonj point

211.17 MMSCFD of gas will be added to the North-South line from Habigonj gas field.

After Habigonj point, the flow rate of gas through North-South line is 267.9 MMSCFD.

96

The Khati well of Titas will deliver 90 MMSCFD of gas to the Rashidpur-Ashugonj

loop line. Therefore, total carrying capacity of Rashidpur-Ashugonj loop line is 582

MMSCFD. The jump of flow rate at Faujdarhat point is observed due to delivery of 160

MMSCFD of gas from the Sangu gas field. In Ashgonj-Elenga line, the first jump of

flow rate occurs due to the addition of 57.94 MMSCFD gas at Daulatkandi from

Daulot# (a manifold on T-J line). At Monohordi point, a sharp decrease in flow rate is

observed due to 173.18 MMSCFD of gas is delivered from this point.

Assuming 950-psig pressures at Ashugonj (normal pressure at Ashugonj), the simulated

'result does not show any significant pressure change downstream of Ashugonj. Figure

6.23 shows the scenario. The simulated results are tabulated in Appendix 7. The

graphical representations of the simulated results are shown in Figure 6.24.

97

o. I "-.-,

ctgClyQ: 312.01 mmsclld

. P: 1063 P,ig

160 """,clld-SonguGI'

MSher~.b

IIISl

J42

Nll1

o.C I!re

Lakshern Fenl

T.J ,in~

Nl03

Baktra# KuBepUr 88YaP:1074 P'ig

Sylhel: 76 mmscfld

MegPP

IKisOanj

Monohoe

8-0 !ine

~~LX - \i:l!!?

'ewnbag

HariPP:

SHddPS : 40 mmscfld

o

P,ig 0

Dh••.•.•• e40 mm,clld

DG~FF

laGanj

P: 1064 P'ig

'Elenge

N76

~ AerourISlpur

-0-.0"0-

Figure 6.20: Demand-Supply Scenario of High Pressure Gas Transmission Lines modified Network by Using R-A Loop Line

98:>

, "

._- -- - -- --_._--~-_._. - ..... ~._---~-_._~.-----------------~-----

,.,,------- ------_.------ --u- _

10951090

.~ 10850... 1080~iil 1075en£ 107.0

10651060

o 50 100Lrength, Km

150 200

,----------- N-S line--B-C line

B-D lineA-E line

___ R-A loop line

Figure 6.21: The Variations of Pressure with the Length after modified by Rashidpur-

Ashugonj Loop Line

i

.. ------- .. .. . . .. .. . ----- .. .. -- -

(" ~

- .. - . .. .. .1 --_._- .. ---- ..

- .. . - -- ..

I . . .... ~. --~. - ....-..------1-- '-'-- --- ...- ----- _.__ ., ..

"'"-

--,. _. .- ..._- ---- ----_.-

~~.

700

600

0 500LL0en:2 400:2.,;- 300'"~;:.QLL 200

100

0a 50 100

Len 9 th, K m

150

__ N-S line

--.••- B -C lin e

B-D line

_'_.' A -_EJi_n~_.J

200

Figure 6.22: Change of Flow Rate with the Length after modified by Rashidpur-

Ashugonj Loop Line

99

/',

880.33 psig

BBeter: 991.09 rnsm3/d

HGF1: 7645.55 msm3fd

@,N117: 10:30.00 psig

ritBSdGF'

I

FenPP: 20.00 mmsctJd4530.70 msm3fd

ZiaFF: 45.00 mmscfJd

KaliGF:

KTL1: 707.92Jnsm3/d

Figure:6.23

~ 1'","

~.Ba'h,e' K,Bep", B;j,e Lok,hem Fen; J42 MSh"e; Bereb Fo,lderagC'y:

DJDTDSl: 76.00 mmscfJi

Nel:Kona:~

.~

BakhraGF:

'men

N115: 2.00 mmscf/d70.00 mmscfJd MegPP

Dhanua

,:':...E hj)~

ShiddP5: 40.00 mmscffd

;;:}~-J82 JB1

. ,OM,eFF

Elenga.Nolka line

Jamunaff: 4S.UO mmsc

Dlongi:

DJDevpur: 6.00

DJamal: 4.00 m~c

Ndka

BBari: 56.00 rr1rnscf/d

SanguGF: 4530.70 msm3Jd

Figure 6.23: Demand-Supply Scenario of Gas Transmission Lines modified by Using R-A Loop Line and mentioning Known Pressure atAshugonj

,.~ ,.~

100

,1,-,,-.. I-------~1'-~----'-~R__- ,-- - . ----

1150

1100

.Ql 1050(/)

0...1000

~iil 950(/)

~0... 900

850

800o 50 100

Length, Km

150 200

----- -_ ..__ ._----

__ N-S line

-D--B-ClineB-D lineA-E line

----*- R-A loop line

Figure 6.24: The Variations of Pressure with the Length after modified by Rashidpur-

Ashugonj Loop Line for Pressure Matching

6.7 Extension of Network up to Bheramara

The existing network will be expanded up to Bheramara in near future according to the

plan of Asian Development Bank. In Figure 6.25, 85 km 24" OD Nolka-Ishwardi-

Bheramara gas transmission pipeline is connected to the network to facilitate gas supply

to the planned industries in the Ishwardi EPZ and the power plants at Ishwardi and

Bheramara. Assuming the total loads in the Western region are 140 MMSCFD, the

network is simulated, The simulated results are tabulated in Appendix 8. Figure 6.26

shows the pressure drops along the major gas transmission lines. The inlet pressure at

North-South pipeline is 1090 psig. The pressure drops in the major transmission lines

are comparable to pressure drop which is obtained from the rule of thumb. Therefore,

there is no unusual pressure drop anywhere in the network after extension of network up

to Bheramara. Figure 6.27 shows the flow rate of major gas transmission lines. After

extension, the capacity of North-South line with Rashidpur-Ashugonj loop line will be

840 MMSCFD. The capacity of Ashugonj-Elenga line is 387 MMSCFD. Therefore,

there is no unreal situation in the network. The R-A loop line will increase the gas flow

between Rashidpur and Ashugonj points significantly.

101

HGF1

270 mmscl/d

agC~yQ: 258 mmscf/dP: 1062 Psig

N113APS175 mmscf/d

20mmscf/d

ShahjiPP

SanguGF

MShar~arab

~ B~ria

~-~

N61

J42

N4~ FenPP

Rashidp 160 mmscf/dRashidGF

S.C line

N111

Laksham Feni

Sylhel: 76 mmscf Id

MegPP : 77 mmsf/d

'ewnbag

Tarabo#

B-D line

N115HariPP: 80 mmsf/d

@

Tarabo

Elenga

N76

~Ae,pu,~~14 mmscf/d ~ LX

NetKona

DDemra

olka

DGulshan

DJDevpur

DTangileBBari46 mmscf/d

BheraPP40 mmscf/d

shurdi

,0~ShlddPS: 52 mmscf/d

Figure 6.25: Demand-Supply Scenario of High Pressure Gas Transmission Lines by extension of Network up to Bheramara

102

-- - ---------~-------- ----------- -----------------------

-+--N-S line--B-C line

B-D lineA-E line

__ R-A loop line

20015010050o

----- ---1----- ---._-,~- -_ .._._-- -------- -- -

10951090

.~ 1085c.. 1080~ 1075:J~ 1070£ 1065

10601055

Length, Km

Figure 6.26: Variation of Pressure Drop along Major Transmission Lines by Extension

of Network up to Bheramara

( -".- -_._--_.----~_._- --- - ----- -_. - -- - ----- j;--_. -------

_._- -- ------ -_.__ ._- ----- ---- --,,

- ._-- . - ---- -- -- _._- -- - -- _._- -- - --- ------------ - _.

I ~I

- ---- - - . ---- -- _._. - ---- - --- .-

"'"_ . .- . - ---- - ---_ .._-----

1-,

600

500

~~ 400u(/)

:::s:::s 300"'iii•...~ 2000G:

100

0o 50 100

Length,Km

150 200

-+-- N-S line

--B-C line

B-D line

A-E line

Figure 6.27: Change of Flow Rate along the Major Transmission Lines by Extension of

Network up to Bheramara

103

\...)

6.6 Extension of Network up to Khulna without Modification

In near future the demand of gas in the Western region will increase. According to the.

report of Asian Development Bank, the network should be extended up to Khulna

within 2010. Then the demand would reach 1900 MMSCFD (average). But GTCL

forecasted that the average gas demand would be 1700 MMSCFD to 1900 MMSCFD.

Therefore, this case has been studied using the demand as 1734 MMSCFD. In Figure

6.28, extending of transmission lines up to Khulna modifies the network. Assuming

total loads in the Western region are 320 MMSCFD, the scenario is simulated. The

major loads are assumed as follows:

Bheramara 70MMSCFD

Khulna 100MMSCFD

EPZ IOMMSCFD

Baghabaria 100MMSCFD

Shirajgonj 40MMSCFD

The simulated results are shown in Appendix 9.

The large pressure drop (I78 psig) in Ashugonj-Elenga line (Figure 6.29) is the

indication of inability of line to carry the expected flow. The pressure drop in Elenga-

Khulna line is 88 psig, which is also greater than the recommended pressure drop (20

psig). The pressure at Khulna is 749 psig. Therefore, it is not possible for Ashugonj-

Elenga line to carry the required flow.

The flow capacity in major transmission lines by extension of network withou! any

modification is shown in Figure 6.30. In Bakhrabad-bemra line, the flow rate is

increased at Dewanbag point because 41.85 MMSCFD flow is added at this point from

Demra and 53.17 MMSCFD flow is added at the same point from Sonargaon. The flow

situation of other transmission lines has been discussed previously.

Therefore, it is required to modify the network. The next cases are studied to overcome

the existing pressure problem.

104

./' ...

CgCity

F: 300 mmscf/dP: 982.9 Psig

aujdar

FenPP

A. JaBadGF

120 mmscl/d

K~

BBezar

: 250 mmscl/d

HasGF: 300 mmscf/d

ShahjiPP

SarabMSharai

KatjGF: 40 mmscl/d

J42

Manifold

8.C line

APS

Laksham Feni

N111

15 mmscf/d

N60

~r;GF

Khadim

Bakhrabadlt Ku8apur Bijra

MegPP

Sylhet: 80 mmscf/d

N115

oGaon

B-D line

,t•..E line

N76

J81

DDemra

~~ ••pur~~DJamal ~ MmenPP a LX NetKona

J ail'ur JJI

~Mymen40 mmscf/d

JamunaFFE,i., hp,::

Khulna

100 mmscf/d740.55 Psig

hurdi h'olka JB2

~

_ 160 mmscf/d

ShiddPS SanguGF

Figure 6.28: Demand-Supply Scenario of High Pressure Gas Transmission Lines by extension of Network up to Khulna without Modification

;;'(iii , F~

105

~:J(/)(/)

~0...

--'---

11001050

0> 1000'wc. 950

900850800750700

,-~.-

o 100 200Length, Km

300 400

-+- N-S line--B-C line

B-D lineA-E line

--R-A loop__ E-K line

Figure 6.29: The Variation Pressure of Major Transmission Lines by extension of

Network without any Modification

.- 1-- - - - ---- -- --

I!' ----------------_. ----- -- - - ------.

- ._--~_ .._- --- - -- - -- -- --- - - -- ---_.- -----

._ .._- -

- - --

- t--.: - ~ -- .------ -----,,-_.- ;:v-

~ ..~-._-- -- _.

'"_I

T

900800

0 700LL0 600(J):2: 500:2:Q) 400-ro•...::: 3000LL 200

1000

o 100 200 300

-+- B-C line1---- B-D line

A-E lineR-A loop I

__ E-K lineJ--N-S line--------------

Length, Km

Figure 6.30: Change of Flow Rate along the Major Transmission Lines by extension of

Network without any Modification

106

6.6.1 Extension of Network up to Khulna with Ashugonj-Dhanua Loop Line

According to the study of Asian Development Bank, it is clear that the existing network

will be extended up to Khulna within 2010. New power plant and fertilizer factory will

be set up in the Western region. Then demand of gas in this region will increase. Before

the extension to Khulna within the transmission lines, R-A loop line (69 km, 30" aD)

and Ashugonj-Dhanua loop line (69 km, 30" aD) will be completed on priority basis.

The network with Bheramara to Khulna transmission line is shown in Figure 6.3 J.

Assuming the total load in the Western region as 320 MMSCFD, the scenario is

simulated. The major loads are assumed as follows:

Bheramara 70MMSCFD

Khulna 100MMSCFD

EPZ 10MMSCFD

Baghabaria 100MMSCFD

Shirajgonj 40MMSCFD

The simulated results are tabulated in Appendix 10.

Figure 6.32 shows the pressure drops along the major gas transmission lines. The

pressure gradient in Ashgonj-Dhanua loop line is 0.0662 psig/km. The pressure gradient

in other lines is very close to the recommended pressure gradient. The pressure at

Khulna is 1039 psig. Therefore there is no shortage of pressure anywhere in the network

after completing Ashgonj-Dhanua loop line.

Figure 6.33 shows the simulated flow rates of major gas transmission lines. After

completing Ashgonj-Dhanua loop line, the capacity of North-South line with Rashidpur-

Ashugonj loop line will be 1116 MMSCFD. The capacity of Ashgonj-Dhanua line is

3689 MMSCFD. Then the capacity of Ashugonj-Elenga line with Ashgonj-Dhanua loop

line will be 559 MMSCFD.

Therefore, it is a possible option to construct the Ashgonj-Dhanua loop line for

increasing the gas flow in the Western Region in future.

107

014<1'" ctgCllyP.1056.6 P1igF: 300 """ef/d

FenPl'20nmscf/d

250 rnrnocf/d

Tlos(lf

Ilor'"

SI10hjFP

_01

KatiGF: 40 mrmclld

Illart/old

.142

~Resl"lkt3F

B.C iin,:,

N61

N.5 rme

Lakstlem Feni

N1ll

15mmscl/d

N80

BokIv.bodlI ~r 8IjraP: 1062.6 p,ig

5yihot eo mmsefld

:oGaon

N1l5

B-Dline

N7B

~A._~~OJ.mol ~1Put MmenPl' ri LX NelKOIl8

~ - AMymenSGIlrj : 40 """ef/d

160.00 nmscf/d_:52nmscf/d ~

Figure 6.31: Demand-Supply Scenario of High Pressure Gas Transmission Lines by extension of Network up to Khulna with A-D Loop Line

108

:'\ ,

-+- N-S line-a-B-C line

B-D lineA-E line

__ R-A loop__ E-K line

--+- A-D loop

400300200Length,Km

100

--r ----~ -----~~l-

~

11001090

.gl 1080(/)

C-

Ol 1070,...::J 1060(/)(/)

Ol... 1050a.10401030

0

Figure 6.32: The Variation of Pressure along the Major Transmission Lines by

Extension of Network up to lUmina with Ashugonj-Dhanua Loop Line.

-+-N-S line-a-B-C line

B-D lineA-E line

__ R-A loop__ E-K line

--+- A-D line

300200

.1 _

100

-----:-- ..---d-" ------.._~.:---------

o

1000900800700600500400300200100

o

oLL()(/)~~Ol

~;;:oLL

Length, Km

Figure 6.33: Change of Flow Rate along the Major Transmission Lines by Extension of

Network up to Khulna with Ashugonj-Dhanua Line.

109

r\\"\.

6.6.2 Modification of Nolka to Khulna Line by Using Loop Line from Rashidpur-

Ashugonj Loop Line to Dhanua

To reduce the stress on the Ashugonj Station, the network has been modified with a loop

line from Rashidpur-Ashugonj loop line to Dhanua (69 KIn, 30" OD). Figure 6.34

shows the modification of Nolka to Khulna line by using loop line from Rashidpur-

Ashugonj loop line to Dhanua. Assuming the total load in the Western region is 320

MMSCFD, the scenario is simulated. The major loads are assumed as follows:

Bheramara 70 MMSCFD, Khulna 100 MMSCFD

EPZ 10 MMSCFD, Baghabaria 100 MMSCFD

Shirajgonj 40 MMSCFD

The simulated results are tabulated in Appendix 11.

Figure 6.35 shows the pressure drops along the major gas transmission lines. In North-

South line, the pressure gradient is 0.112 psig/km. The pressure gradient in Rashidpur- .

Ashugonj loop line, Bakhrabad-Demra line, Bakhrabad-Chittagong line, Ashugonj-

Elenga line and loop line from Rashidpur-Ashugonj loop line to Dhanua are 0.124

psig/km, 0.274 psig/km, 0.082 psig/km, 0.0934 psig/km and 0.062 psig/km respectively.

The pressure gradient in Bakhrabad-Demra line is larger due to the larger velocity of gas

in this line compare to others.

Figure 6.36 shows the flow capacity of major gas transmission lines. First jump of flow

in North-South line occurs at Rashidpur manifold station due to 250 MMSCFD gas is

added from Rashidpur gas field. Then it is divided into two parts; one part (741

MMSCFD) is passed through Rashidpur-Ashugonj loop line and other part (128

MMSCFD) is passed through N-S line. The loop line from Rashidpur-Ashugonj loop

line to Dhanua can carry 188 MMSCFD for which sharp decrease of flow is observed in

Rashidpur-Ashugonj loop line. Therefore, after completion of the proposed loop line,

the capacity of North-South line with Rashidpur-Ashugonj loop line will be 1117

MMSCFD.

Considering the above discussions, it is clear that it is possible to modify the network by

using loop line from Rashidpur-Ashugonj loop line to Dhanua.

110

~) ..

\"

HQfl270mrmcf/d

Tltl!llsGF300mmscf/d

SI,,".PI'36t1'll1'1SCfJd

'el4der QgCIy300 mrnsc:f/d

......,

KallGF : 40 mmtelld

N113

'*'ntfcld

•••••••••

200 """",f/d _ ----<li)KTL234 P:lIl9JP~ ;120='fd

KT~

BBelntr

Kl!tl"lata

J42

8.( 1'(;'"

F,

N111,0

- ----<!rIOF~ 4~.cfl

_dim

MegPP : 105 mrnscIJd

B.D line

,.SOGoon

R-A loop line toDhanu" loop line

ShId(FS : 52 nmscf/d

P:l059Psig <\-t:: Ilr,e

Bengo

".

~ ~SI1etP'" ~ --o---@DJIIIm!III .L..lelmeIlpur ~pp ./ LX NetKonll

40 rrmed/d Y ~ /"febi DMyme1'I•• Mymen

E ¥, 'jne D.De'IIJJUI'

1<h.AnlI: 100 RW'RIcl/d

folio

Sh ••70 mmtef/d

rJl'$$Of8

~

........,.,Figure 6.34: Demand-Supply Scenario of High Pressure Gas Transmission Lines modified by Using Loop Line from R-A Loop Line to Dhanua

/\III

--~-- ._.-_. __ .- ----- --- -----_. -- -----.- ----- -----_. -~-------------------

------_. __ ._------109510901085

.~ 1080Q. 1075[1! 1070::>~ 1065[1! 1060Q. 1055

10501045

o 50 100Length,Km

150 200

-+-N-S line___ B-C line

B-D lineA-E line

__ R-A loop line___ R-A to Dhanua

-------- ----_.- -------- -------- ------------------_._-_.--

Figure 6.35: The Pressure Drops of Major Transmission Lines of Nolka to Khulna

Pipeline Using Loop Line from Rashidpur-Ashugonj Loop Line to Dhanua

I 0u..o(f)

:2:2

1000800600400200

o

~.-I~----:

o 50 100Length, Km

150 200

__ N-S line

-- B-C line

B-D line

A-E line

---.*-R-A loop line

--------- -----_.--------------- ----------------- .----- _._._--

Figure 6.36: Change of Flow Rate along the Major Transmission Lines of Nolka to

Khulna Pipeline Using Loop Line from Rashidpur-Ashugonj Loop Line to Dhanua

112

----/"(

'.

6.8.3 Modification by Using Compressor Station at Monohordi

The construction of loop line is time consuming and lengthy process. Therefore, the

network can be modified alternatively. Using compressor station at Monohordi (1500

hp, 70% efficiency) instead of Ashugonj-Dhanua loop line the network can be modified

as shown in Figure 6.37. The simulated results are shown in Appendix 12.

The inlet pressure to the North.South pipeline is 1090 psig which is equal to the design

pressure. But the pressure drop in the North-South line is high. The pressure drops in the

other transmission lines are nearly equal to the recommended pressure drop. The

variation of pressure along the transmission lines is shown in Figure 6.38. Ashugonj-

Elenga line shows the effect of compressor at Monohordi.

113 I

\

Ferl'!'

_orJl """cf/d

••.••••. OgClyP:llm.1 P.igF: JlO rnmad/d

Sl\ehjPp: 36 mm.cf/d

TlasGFF: JlO mnm:f/d

MSMrai B«ab

KstlOF : 40 lTITl~f/d

J42

NIl1

8-C line

N.S line

Laklll1am Feli

N111N60

Bakh_ K1lIloIJU'BITe

D.J)TDSl: 90.00 mmscf/d

N76

~~_r~~0JemaI" ; 1=J'>..."'-LX NetKona

HerI'P

: 95 mmsl/d W F: 160 nmad/dSltiP.; : 52 rnmad/d SanguClF

Figure 6.37: Demand-supply Scenario of High Pressure Gas Transmission Lines modified Final Network by Using Compressor Station aMonohordi

.~.114

11001080

OJ"iii 1060c.~ 1040~ 1020VJ~ 1000D..

980960

o 100 200

Length, Km

300 400

-+-N-S line__ B-C line

B-D lineA-E line

--*- R-A loop--E-K line

---------- - _._"---~-----------_._----_._----- --

Figure 6.38: The Variation of Pressure along the Major Transmission Lines modified by

Using Compressor Station at Monohordi

115

Chapter 7

DISCUSSIONS

There are twenty-two gas fields in Bangladesh. At present, gas is lifted from twelve gas

fields. The peak lifted gas in June 2000 was 1013 MMSCFD. After lifting natural gas

from the fields, the gas Companies produce pipeline quality gas through process plants.

Then, the treated gases are delivered to the transmission pipeline through fiscal meter.

The Orifice meter is used as a fiscal meter and for monitoring accurately the flow

recorder is connected with the orifice meter. Beyond this, the hourly calculations of

flowing gas are recorded from the gas fields to the transmission line.

To improve the supply/demand balance and to enhance the satisfaction of gas

customers, Petrobangla has moved progressively from four separate systems (JFA, TFA,

BFA and WFA) to an integrated transmission network. The reliability and security of

gas supply in the national gas grid is largely dependent on the following pipelines:

1. 174 km, 24" OD North-South Gas Transmission Pipeline

2. 12" OD 38 km Ashuganj- Habiganj Gas Transmission Pipeline

3. 14" OD 58 km Titas-Narshindi-Demra Gas Transmission Pipeline

4. 16"/14" OD 82.81 km Titas-Narshindi-Joydevpur Gas Transmission Pipeline

5. 20" OD 48 km Bakhrabad-Demra Gas Transmission Pipeline

6. 20" OD 48 km offshore Sub Sea Sangu Gas Transmission Pipeline

7. 14" OD 15 km Jalalabad - Kailashtilla Gas Pipeline

8. 20" OD 18 km Beanibazar-Kailashtilla Pipeline

9. II" OD 37 km Salda- Bakhrabad Pipeline

10. 8" OD 28 km Meghna Gas Field- Bakhrabad Pipeline

If the transmission network is carefully analyzed it appears that Ashuganj is the focal

points of the National Gas Grid. Two key locations of Ashuganj are mainline Valve

Station-3 of Titas-Narshindi-Demra transmission pipeline and Manifold station of

GTCL. Gas from the Northern Gas Fields (Beanibazar, Jalalabad, Kailashtilla,

.Rashidpur, Habiganj) are being transported through the North-South pipeline to

Ashuganj Manifold Station of GTCL from where it is further transmitted to Titas

116

franchise area (TFA) and Bakhrabad franchise area (BFA) through Brahmaputra Basin

pipe line and Ashuganj- Bakhrabad transmission pipe lines respectively. From

Bakhrabad Gas Field, Bakhrabad-Chittagong Pipeline transports part of the required gas

for Chittagong. The remaining gases for Chittagong is supplied from Salda, Meghna and

Sangu gas fields. The mother trunk line i.e. North- South Pipeline has a design capacity

of 330 MMSCFD. However considering the staggered nature of input into the pipeline

and adjusting the terminal pressures at various in-take points and at Ashuganj it may be

possible to transport 400 MMSCFD through the pipeline. Currently it is transporting

approximately 353-380 MMSCFD, which merely cater to the downstream gas demand.

During the past few years Bakhrabad gas field has been experiencing rapid pressure

decline and increased water cuts in the wells. As a result, some wells have been shut off

and some have been re-completed. In the year 1992 this field produced in its peak at an

average 195 MMSCFD. In 1998, only five wells were producing from three sands at the

rate of 50 MMSCFD. At present, the field is delivering gas at the rate of 35 MMSCFD

at 600 psig. Currently Bakhrabad gas field is connected to the network system by

reducing the pressure of Bakhrabad to Demra pipeline. If the line pressure is not reduced

the Bakhrabad gas field could not be connected to the transmission system without

compressor. When the proposed power plant will be started in peak production, the

pressure of B-D line needs to be increased. Then Bakhrabad gas field will face a lot of

pressure problem. If BGF is stopped production, it will not be possible to reach

recoverable reserve and it will be a dead well. To overcome this problem, a compressor

station should be set up at Bakhrabad gas field. The power of compressor must be

greater than 700 hp at 70 % efficiency.

The demand of gas was increasing day by day in fertilizer, power, industry and

commercial sectors. If the proposed power plants start their production, the demand of

gas will increase. To recover this demand, it is necessary to lift gas at higher rate.

Therefore, 856 MMSCFD will be delivered from JFA. The maximum allowable

operating pressure of the North- South p-ipeline is 1135 psig, its maximum inlet pressure

1090 psig and the normal pressure in A-shugonj is 850 psig. From Appendix 3, it is clear

that N-S pipeline and Gas Fields experience unexpected pressure that is greater than its

design pressure to reach the desired flow rate. From the simulated result, it is clear that

after completing R-A loop line, the capacity of N-S pipeline with R-A loop line will be

117

increased and become 850 MMSCFD. Therefore, it is necessary to construct a loop line

from Rashidpur to Ashugonj to deliver excess flow at design pressure on priority basis.

If a new loop line from R-A loop line to Dhanua is constructed, the capacity ofN-S line

with R-A loop line will be 790 MMSCFD. Even though the pressure drop in the major

transmission lines will be low to meet the demand of Western Region. Therefore, R-A

loop line to Dhanua loop line needs to be completed after completing R-A loop line.

Now Ashugonj is the main points of the National Gas Grid. To reduction stress on

Ashugonj station, it is required to construct loop line from R-A loop line to Dhanua loop

line. There will be no problem in gas transmission system when the network will be

extended up to Bheramara.

Within 20 I 0, the existing network will be expanded up to Khulna according to the

report of Asian Development Bank. Then the gas demand would reach 1900 MMSCFD

(average). Then the capacity of A-E line will have to be increased. If no loop line is

constructed with A-E line, unexpected pressure drop will occur in A-E line (187 psig).

Therefore, it is required to modify the network. To overcome the constraints of A-E line,

three cases have been studied: i) A-D loop line ii) loop line from R-A loop line to

Dhanua and iii) compressorstation at Monohordi. If A-D loop line is constructed, there

is no shortage of pressure in the network. Therefore, it is possible to modify the network

with A-D loop line. If a loop line from R-A loop line to Dhanua is constructed, large

pressure gradient is observed in B-D line due to the larger velocity of gas in this line. To

minimize pressure problem in Western region a compressor station may be set up at

Monohordi. Therefore, according to the over all study, it will be better to construct A-D

loop line or loop line from R-A loop line to Dhanua for reducing the stress on Ashugonj

metering station.

118

(

Chapter 8

CONCLUSIONS AND RECOMMENDATIONS

8.1 Conclusions

After analyzing the integrated gas transmission network of Bangladesh, the following

conclusion can be drawn:

I. Simulated results compare well with the actual data. Therefore, the network can be

used to predict the future demand/supply scenario under existing and future supply

and loads.2. The results show that effective pipeline diameter of major transmission lines have

decreased due to condensate accumulation. Hence pigging is necessary.

3. The maximum capacity of N-S pipeline is 400 MMMSCFD. Significant flow

constraints and pressure drop arise in this line when the demand of gas is increased.

4. Rashidpur-Ashugonj loop line is essential to supply the growing gas demand. It will

increase the capacity of the North-South pipeline by 456 MMSCFD.

5. Analysis shows that it is a better option to install a compressor station at Bakhrabad

to transmit the low-pressure gas of the field through the high-pressure pipeline.

6. After completing R-A loop line, another loop line from R-A loop line to Dhanua or

A-D loop line is required to minimize pressure problems in the transmission lines.

7. To extent of network up to Khulna, R-A loop line and loop line from R-A loop lines

to Dhanua or A-D loop line must be completed on priority basis.

8. To minimize pressure problem in Western region a compressor station may be set up

at Monohordi after completing R-A loop line instead of A-D loop line or loop line

from R-A loop line to Dhanua.

9. To meet the future gas demand of the Western region, the results show that another

loop line is necessary from Rashidpur-Ashugonj loop line to Dhanua. It will increase

the supply of Ashugonj-Elenga pipeline by 175 MMSCFD.

119

8.2 Recommendations

1. To remove the constraint ofN-S pipeline, a loop line from Rashidpur to Ashugonj is

to be constructed in priority basis.

2. The author strongly recommended for setting up a compressor station at Bakhrabad

gas field.

3. For creating stability of gas supply in the Western region, a loop line is being set up

from R-A loop line to Dhanua.

120 () . {«

I\. ,

-}

APPENDICES

Appendix 1: Simulated Results of High Pressure Gas Transmission Lines of

Bangladesh.

From Node "To Node Up Stream Down Stream . . Lengtn 'Leg Flow ,PressurePressure Pressure . . (}adiant

Psig Psig km MMSCFD PsiglkmJabadGF Ktilla 1092 1090 18 82.54 0.11111Ktilla FenGanj 1090 1088.6 27 150.59 0.05185FenGanj Rashidpur 1088.6 1084.9 67.5 150.59 0.05481Rashidpur Habigonj 1084.9 1082.7 27.5 221.23 0.08Habigonj KJ 1082.7 1079.3 35.5 354.2 0.096KJ Ashugonj 1079.3 1077 18 354.2 0.13Ashugonj Bakhrabad 1077 1075.7 57.1 229.4 0.02277Bakhrabad KuBapur 1075.7 1075.2 15.7 120.1 0.03185KuBapur Bijra 1075.2 1074 27.8 120.1 0.04317

Bijra Laksham 1074 1073.8 6 120.1 0.03333Laksham Feni 1073.8 1072.1 40 120.1 0.0425

Feni J42 1072.1 1071.7 10 120.1 0.04J42 Msgrai 1071.7 1070.6 25 120.1 0.044Msgrai Barab 1070.6 1070.2 9 120.1 0.04444Barab Faujdarhat 1070.2 1068.4 38 120.1 0.04737Faujdarhat CtgCity 1068.4 1068 2.5 241.34 0.16SanguGF Faujdarhat 1071.3 1068.4 49 119.8 0.05918Bakhrabad Meghnaghat 1075.7 1071.8 30 175.86 0.13Meghnaghat Sonar£!aon 1071.8 1068.1 15 175.85 0.25Sonargaon Dewnbag 1068.1 1066.7 15 170.83 0.093Dewnbag Demra 1066.7 1066 8 140.86 0.0875Ashugonj Daulotkandi 1077 1075.9 5 134.58 0.22Daulotkandi Monohordi 1075.9 1072.8 27 217.9 0.115Monohordi Dhanua 1072.8 1071 37 59.08 0.04865Dhanua Elenga 1071 1069.1 52 40.14 0.03654

Elenga Joydevpur 1069.1 1062.2 56 14.13 0.1232Joydevpur Gulshan 1062.2 1061 25 11.45 0.048Gulshan Demra 1061 1065.1 32 63.65 -0.1281elenga nolka 1071.1 1068.5 39 15.24 0.06667nolka Sganj 1068.5 1068.2 5 2 0.06nolka Bbari 1068.5 1065.8 43 13.19 0.06279

Elenga JaGanj 1071.1 1068.6 43 10.75 0.05814JaGanj JamunaFF 1068.6 1068.6 2 3.74 0JaGanj Shbari 1068.6 1059.9 11 7.02 0.79091shBabi Jamalpur 1059.9 1058.8 18 7.02 0.06111Jamalpur Sherpur 1058.8 1052.4 16 3 0.4

121

I

Dhanua GafGaon 1072 1071.7 19 18.94 0.01579GafGaon Trishal 1071.7 1070.4 20.004 18.94 0.06499Trisa1 mymen 1070.4 1065.5 16 18.94 0.30625Mymen LX 1065.5 1060.6 8 16.94 0.6125LX Mymenpp 1060.6 1058.2 5 14.88 0.48Lx Neykona 1060.6 1053.8 32.5 2 0.20923Monohordi kisGanj 1073.8 1071.5 36 2 0.06389KA1 APS 1076.1 1015.1 1.5 100.99 40.6667KA1 ZiaFF 1076.1 1075.9 2.4 0.005 0.08333Dewnbag hariPP 1066.7 1066.7 1.58 29.86 0FenGanj fenpp 1088.6 1088.6 0.5 0.005 0RashidGF Rashidpur 1085.3 1084.9 1.9 70.62 0.21053HGF1 Manifold 1085.3 1085.3 0.006 187.9 0Manifold ShahjiPP 1085.3 952.2 2.5 36.61 53.24Manifold Habigonj 1085.3 1082.7 1 132.24 2.6Manifold Katihata 1085.3 1078.5 42 17.47 0.1619Katihata Manif 1078.5 1076.1 11.5 17.47 0.2087Manif Ashuganj 1076.1 1077 2 35.97 -0.45N61 Ktilla 1090.01 1090 0.02 67.97 0.5N111 N61 1088.9 1090.01 28 0.116 -0.0396Nl11 N105 1088.9 1088.7 2.082 12.82 0.09606N105 Sylhet 1088.7 1088.68 0.03 17.28 0.66667HariGF N105 1089.2 1088.7 12 3.47 0.04167SaldaGf Bakhrabad 1088.3 1075.7 35 15.12 0.36MeghnaGF Bakhrabad 1117.7 1075.7 28 17.14 1.5TitasGf Bbaria 1160.6 1092.4 1 303.2 68.2Bbaria . TN1 1092.4 1090.8 1 152.4 1.6Bbaria TN2 1092.4 1091.4 1 75.45 1TN1 KA1 1090.8 1076.1 14.1 152.4 1.04255KAI TN3 1076.1 1073.6 7 32.9 0.35714TN3 Nars 1073.6 1066.8 30 32.9 0.22667TN2 Daulot# 1091.4 1076 16 145.8 0.9625Daulot# TN4 1076 1068 29 62.49 0.27586TN4 Nars' 1068 1067.8 1 62.49 0.2Nars Tarabo 1067.8 1066.5 20 2.87 0.065Tarabo Demra 1066.5 1065.1 12 4.33 0.11667Nars Tarabo# 1066.8 1066.1 40 21.91 0.0175Tarabo# ShiddPP 1066.1 1066 5 20.45 0.02ShiddPP ShiddPS 1066 1066 0.0003 14.62 0ShiddPP N76 1066 1065.7 10 5.81 0.03N76 Demra 1065.7 1065.1 10 5.81 0.06Nras Ghorasal 1066.8 1060.1 8.4 233.7 0.79762Ghorasal GhoraPP 1060.1 760.38 0.4 175.54 749.3Ghorasal GhoraFF 1060.1 1051.8 8.4 55.31 0.9881GhoraFF DGhoraFF 1051.8 1051.8 0.0003 43.2 0GhoraFF PalashFF 1051.8 1051 0.8 12 1

122

Monohordi Nars 1073.8 1066.8 32 151.8 0.21875Daulot# Daulotkandi 1076 1075.9 0.1 83.11 1BelaboGF Nars 1084.9 1067.8 13 16.31 1.31538

Appendix 2: Simulated Results of High Pressure Gas Transmission Lines of

Bangladesh modified by Known Pressure at Ashugonj.

From Node To Node Up Stream Down Stream . .'Len~ 'Leg Flow ,Pressure".' "

Pressure Pressure 0

. Gadianto. 0

'Psig 'Psig " km MMSCFD PsigfkmJabadGF Ktilla 1108.6 1090 18 82.66 1.03333Ktilla FenGanj 1090 1075.1 27 57.17 0.55185FenGanj Rashidpur 1075.1 1035 67.5 57.16 0.59407Rashidpur Habigonj 1035 1005 27.5 127.8 1.09091Habigonj KJ 1005 948.44 35.5 242.98 1.59324KJ Ashugonj 948.44 915.79 18 242.98 1.81389Ashugonj Bakhrabad 915.79 891.17 57.1 188.88 0.43117Bakhrabad KuBapur 891.17 876.67 15.7 122.98 0.92357KuBapur Bijra 876.67 836.53 27.8 122.98 1.44388Bijra Laksham 836.53 830.14 6 122.98 1.065Laksham Feni 830.14 794.82 40 122.98 0.883Feni J42 794.82 781.35 10 122.98 1.347J42 Msgrai 781.35 756.07 25 122.98 1.0112Msgrai Barab 756.07 743.5 9 122.98 1.39667Barab Faujdarhat 743.5 701.42 38 122.98 1.10737Faujdarhat CtgCity 701.42 700 2.5 242.79 0.568SanguGF Faujdarhat 710.35 701.42 49 119.8 0.18224Bakhrabad Meghnaghat 891.17 834.73 30 132.41 1.88133Meghnaghat Sonargaon 834.73 790.54 15 132.41 2.946Sonargaon Dewnbag 790.54 761.72 15 127.4 1.92Dewnbag Demra 761.72 750.01 8 97.57 1.46375Ashugonj Daulotkandi 915.79 912.36 5 151.02 0.686Daulotkandi Monohordi 912.36 895 27 184.83 0.643Monohordi Dhanua 895 880.0J 37 87.97 0.41Dhanua Elenga 880.01 864.98 52 69.16 0.29Elenga Joydevpur 864.98 793.74 56 4.03 1.27214Joydevpur Gu1shan 793.74 730.48 25 32.34 2.5304Gulshan Demra 730.48 750.01 32 19.42 -0.6103elenga no1ka 864.98 862.53 39 15.13 0.06282nolka Sganj 862.53 862.12 5 2 0.082nolka Bbari 862.53 859.68 43 13.19 0.06628Elenga JaGanj 864.98 861.85 43 10.7 0.07279JaGanj JamunaFF 861.85 861.85 2 3.74 0JaGanj Shbari 861.85 859.22 11 6.97 0.23909

123

shBabi Jamalpur 859.22 858.28 18 6.97 0.05222Jamalpur Sherpur 858.28 855.61 16 3 0.16687Dhanua GafGaon 885.01 860.72 19 18.81 1.27842GafGaon Trishal 860.72 859.15 20.004 18.81 0.07848Trisal mymen 859.15 858.09 16 18.81 0.06625Mymen LX 858.09 856.07 8 16.82 0.2525LX Mymenpp 856.07 855.71 5 14.88 0.072Lx Neykona 856.07 853.93 32.5 2 0.06585Monohordi kisGanj 895 865.72 36 2 0.81KAI APS 915.2 873.11 1.5 100.99 28.06KAI ZiaFF 915.2 915.2 2.4 0.005 0Dewnbag hariPP 761.72 761.61 1.58 29.86 0.06962FenGanj fenpp 1075.1 1075.1 0.5 0.005 0RashidGF Rashidpur 1037.5 1035 1.9 70.62 1.31579HGFI Manifold 1013.1 1013.1 0.006 187.9 0Manifold ShahjiPP 1013.1 987.3 2.5 36.61 10.32Manifold Habigonj 1013.1 1005 1 115.17 8.1Manifold Katihata 1013.1 938.72 42 36.12 1.77095Katihata Manif 938.72 915.2 11.5 36.12 2.04522Manif Ashuganj 915.2 915.79 2 40.34 -0.295N61 Ktilla 1090.1 1090 0.02 66.98 5N111 N61 1088 1090.1 28 1.1 -0.075Nll1 Nl05 1088 1088 2.082 13.8 0NI05 Sylhet 1088 1088 0.03 17.28 0HariGF NI05 1090.6 1088 12 3.47 0.21667SaldaGf Bakhrabad 906.58 891.17 35 15.12 0.44029MeghnaGF Bakhrabad 942.22 891.17 28 17.14 1.82321TitasGf Bbaria 1075.1 1000.1 1 303.2 . 75Bbaria TNI 1000.1 988.7 1 69.99 11.4Bbaria TN2 1000.1 992.4 1 107.79 7.7TNI KAI 988.7 915.2 14.1 69.99 5.21277KAI TN3 915.2 895.86 7 45.69 2.76286TN3 Nars 895.86 827.65 30 45.69 2.27367TN2 Daulot# 992.4 912.41 16 107.79 4.99938Daulot# TN4 912.41 832.49 29 73.96 2.75586TN4 Nars 832.49 827.65 1 73.96 4.84Nars Tarabo 827.65 787.86 20 34.53 1.9895Tarabo Demra 787.86 750.01 12 54.61 3.15417Nars Tarabo# 827.65 787.86 40 69.53 0.99475Tarabo# ShiddPP 787.86 781.1 5 1.63 1.352ShiddPP ShiddPS 781.1 781.1 0.0003 14.62 0ShiddPP N76 781.1 763.52 10 1.15 1.758N76 Demra 763.52 750.01 10 1.15 1.351Nras Ghorasal 827.65 794.3 8.4 116.8 3.97024Ghorasal GhoraPP 794.3 655.55 0.4 175.53 346.875Ghorasal GhoraFF 794.3 793.82 8.4 55.1 0.05714

124

GhoraFF DGhoraFF 793.82 793.81 0.0003 43.2 33.3333

GhoraFF PalashFF 793.82 793.17 0.8 12 0.8125

Monohordi Nars 901.13 827.65 32 89.9 2.29625

Daulot# Daulotkandi 912.41 912.36 0.1 33.83 0.5

BelaboGF Nars 851.24 827.65 13 16.31 1.81462

Appendix 3: Simulated Results of High Pressure Transmission Lines Using Known

Pressure at Bakhrabad Gas Field.

From Node To Node Up Stream Down Stream Length Leg Flow Pressure

Pressure, Pressure, Psig km MMSCFD GadiantPsig Psildkm

JabadGF Ktilla 1098.5 1090 18 83.52 0.47222

Ktilla FenGanj 1090 1085.6 27 150.58 0.16296

FenGanj Rashidpur 1085.6 1055.7 67.5 150.58 0.44296

Rashidpur Habigonj 1055.7 1035.3 27.5 221.23 0.74182

Habigonj KJ 1035.3 980.3 35.5 361.14 1.5493

KJ Ashugonj 1035.3 917.45 18 361.14 6.54722

Ashugonj Bakhrabad 917.45 907.66 57.1 91.01 0.17145

Bakhrabad KuBapur 907.66 902.77 15.7 121.5 0.31146

KuBapur Bijra 902.77 894.03 27.8 121.5 0.31439

Bijra Laksham 894.03 892.51 6 121.5 0.25333

Laksham Feni 892.51 875.74 40 121.5 0.41925

Feni J42 875.74 868.78 10 121.5 0.696

J42 Msgrai 868.78 851.4 25 121.5 0.6952

Msgrai Barab 851.4 843.16 9 121.5 0.91556

Barab Faujdarhat 843.16 808.4 38 121.5 0.91474

Faujdarhat CtgCity 808.4 795.2 2.5 241.33 5.28

SanguGF Faujdarhat 860.15 808.4 49 119.8 1.05612

Bakhrabad Meghnaghat 907.66 622.2 30 34.87 9.51533

Meghnaghat Sonargaon 622.2 620.43 15 34.86 0.118

Sonargaon Dewnbag 620.43 618.77 15 29.86 0.11067

Dewnbag Demra 618.77 618.77 8 0 0

Ashugonj Daulotkandi 917.45 910.83 5 255.52 1.324

Daulotkandi Monohordi 910.83 895.2 27 262.93 0.57889

Monohordi Dhanua 895.2 875.97 37 97.38 0.51973

Dhanua E1enga 875.97 850.48 52 78.48 0.49019

Elenga Joydevpur 850.48 776.24 56 40.5 1.32571

Joydevpur Gulshan 776.24 763.24 25 0.348 0.52

Gulshan Demra 763.24 765.3 32 51.52 -0.0644

elenga nolka 870.48 860.3 39 15.21 0.26103

nolka Sganj 860.3 860 5 2 0.06

nolka Bbari 860.3 855.85 43 13.19 0.10349

Elenga JaGanj 850.48 865.4 43 10.75 -0.347

125

JaGanj JamunaFF 865.4 865.3 2 3.74 0.05JaGanj Shbari 865.4 863.81 11 7.01 0.14455shBabi Jamalpur 863.81 857.69 18 7.01 0.34Jamalpur Sherpur 857.69 853.29 16 3 0.275Dhanua GafGaon 875.97 865.25 19 18.9 0.56421GafGaon Trisha1 865.25 859.58 20.004 18.9 0.28344Trisal mymen 859.58 855.04 16 18.9 0.28375Mymen LX 855.04 840.96 8 16.9 1.76

LX Mymenpp 840.96 840.06 5 14.88 0.18

Lx Neykona 840.96 837.17 32.5 2 0.11662

Monohordi kisGanj 895.2 868.62 36 2 0.73833

KA1 APS 870.44 504.82 1.5 100.99 243.747

KA1 ZiaFF 870.44 870.44 2.4 0 0Dewnbag hariPP 618.77 617.95 1.58 29.86 0.51899FenGanj fenpp 1085.6 617.95 0.5 0 935.3

RashidGF Rashidpur 1089.1 1055.7 1.9 70.62 17.5789

HGF1 Manifold 1073.3 1073.2 0.006 187.9 16.6667Manifold ShahjiPP 1073.2 1047.8 2.5 36.61 10.16

Manifold Habigonj 1073.2 1035.3 1 139.89 37.9

Manifold Katihata 1073.2 1012.7 42 11.39 1.44048

Katihata Manif 1012.7 980.3 11.5 11.39 2.81739

Manif Ashuganj 980.3 917.45 2 11.39 31.425

N6l Ktilla 1091 1090 0.02 66.98 50N111 N61 1088.9 1091 28 1.1 -0.075NIl! N105 1088.1 1085.9 2.082 13.8 1.05668

N105 Sylhet 1085.9 1085.4 0.03 17.28 16.6667

HariGF N105 1089.4 1085.9 12 3.47 0.29167

SaldaGf Bakhrabad 922.78 907.66 35 15.12 0.432MeghnaGF Bakhrabad 957.78 907.66 28 17.14 1.79

TitasGf Bbaria 1087.5 1005 1 303.2 82.5Bbaria TN1 1005 996.4 1 173.32 8.6Bbaria TN2 1005 999.9 1 124.88 5.1TN1 KA1 996.4 870.44 14.1 173.32 8.93333KA1 TN3 870.44 860.33 7 72.32 1.44429TN3 Nars 860.33 820.31 30 72.32 1.334

TN2 Daulot# 999.9 910.86 16 124.88 5.565Daulot# TN4 910.86 820.31 29 117.48 3.12241TN4 Nars 820.31 817.29 1 117.48 3.02Nars Tarabo 817.29 803.09 20 47.76 0.71Tarabo Demra 803.09 765.3 12 4.32 3.14917Nars Tarabo# 817.29 803.09 40 105.32 0.355

Tarabo# ShiddPP 803.09 802.7 5 148.76 0.078ShiddPP ShiddPS 802.7 802.69 0.0003 14.62 33.3333ShiddPP N76 802.7 801.1 10 134.15 0.16N76 Demra 801.1 765.3 10 134.15 3.58Nras Ghorasal 817.29 771.99 8.4 206.58 5.39286

126

Ghorasa1 GhoraPP 771.99 633.49 0.4 175.54 346.25

Ghorasal GhoraFF 771.99 723.53 8.4 55.2 5.76905

GhoraFF DGhoraFF 723.53 723.52 0.0003 43.2 33.3333

GhoraFF PalashFF 723.53 722.94 0.8 12 0.7375

Monohordi Nars 895.2 817.29 32 158.55 2.43469

BelaboGF Nars 841.2 817.29 13 16.31 1.83923

Appendix 4: Simulated Results of High Pressure Transmission Lines by setting up

Compressor at Bakhrabad Gas Field.

From Node: . To Node~- Up Stream Down Stream' ':Leilgth:- . Leg Flow. rPressure. '.......", ',;, Pressure, Pressur~, Psig . km." MMSCFD Gadiant,Psillikm. Psig . . . ,-

JabadGF Ktilla 1098.5 1090.1 18 82.77 0.46667

Ktilla FenGanj 1090.1 1089.8 27 149.84 0.01111

FenGanj Rashidpur 1089.8 1060.9 67.5 149.83 0.42815

Rashidpur Habigonj 1060.9 1026.6 27.5 220.48 1.24727

Habigonj KJ 1026.6 950.6 35.5 318.65 2.14085 .

KJ Ashugonj 950.6 873.32 18 371.79 4.29333

Ashugonj Bakhrabad 873.32 845.97 57.1 162.53 0.47898

Bakhrabad KuBapur 845.97 841.02 15.7 121.57 0.31529

KuBapur Bijra 841.02 832.18 27.8 121.57 0.31799

Bijra Laksham 832.18 830.64 6 121.57 0.25667

Laksham Feni 830.64 817.71 40 121.57 0.32325

Feni J42 817.71 810.56 10 121.57 0.715

J42 Msgrai 810.56 801.22 25 121.57 0.3736

Msgrai Barab 801.22 795.42 9 121.57 0.64444

Barab Faujdarhat 795.42 772.7 38 121.57 0.59789

Faujdarhat CtgCity 772.7 770.84 2.5 241.33 0.744

SanguGF Faujdarhat 798.38 772.7 49 119.8 0.52408

Bakhrabad Meghnaghat 845.97 829.52 30 107.65 0.54833

Meghnaghat Sonargaon 829.52 819.89 15 107.65 0.642

Sonargaon Dewnbag 819.89 808.1 15 102.64 0.786

Dewnbag Demra 808.1 805.45 8 72.76 0.33125

Ashugonj Daulotkandi 873.32 869.24 5 182.87 0.816

Daulotkandi Monohordi 869.24 855.58 27 203.66 0.50593

Monohordi Dhanua 855.58 850.61 37 86.33 0.13432

Dhanua Elenga 850.61 845.62 52 67.47 0.09596

Elenga Joydevpur 845.62 777.89 56 29.59 1.20946

Joydevpur Gulshan 777.89 778.64 25 8.76 -0.03

Gulshan Demra 778.64 805.45 32 43.32 -0.8378

elenga nolka 845.62 840.25 39 15.17 0.13769

nolka Sganj 840.25 839.1 5 2 0.23

nolka Bbari 840.25 829.8 43 13.19 0.24302

127 .(

Elenga JaGanj 845.62 842.73 43 10.73 0.06721

JaGanj JamunaFF 842.73 842.7 2 3.74 0.015

JaGanj Shbari 842.73 842.05 11 6.99 0.06182

shBabi Jamalpur 842.05 836.95 18 6.99 0.28333

Jamalpur Sherpur 836.95 832.32 16 3 0.28938

Dhanua GafGaon 850.61 844.07 19 18.86 0.34421

GafGaon Trishal 844.07 837.07 20.004 18.86 0.34993

Trisal mymen 837.07 831.44 16 18.86 0.35188

Mymen LX 831.44 817.44 8 16.86 1.75

LX Mymenpp 817.44 817.41 5 14.88 0.006

Lx Neykona 817.44 813.11 32.5 2 0.13323

Monohordi kisGanj 855.58 841.04 36 2 0.40389

KAI APS 836.96 400 1.5 100.99 291.307

KAI ZiaFF 836.96 836.96 2.4 0 0

Dewnbag hariPP 808.1 808.1 1.58 0 0

FenGanj fenpp 1089.8 1089.8 0.5 0 0

RashidGF Rashidpur 1089.3 1060.9 1.9 70.62 14.9474

HGFI Manifold 1073.1 1073 . 0.006 187.9 16.6667

Manifold ShahjiPP 1073 1047.5 2.5 36.61 10.2

Manifold Habigonj 1073 1026.6 1 98.16 46.4

Manifold Katihata 1073 1016.6 42 53.13 1.34286

Katihata Manif 1016.6 915.8 11.5 53.13 8.76522

Manif Ashuganj 915.8 873.32 2 53.13 21.24

N61 Ktilla 1090.2 1090.1 0.02 66.98 5

Nlll N61 1090.1 1090.2 28 1.1 -0.0036

Nlll NI05 1090.1 1090 2.082 13.8 0.04803

NI05 Sy1het 1090 1089 0.03 17.28 33.3333

HariGF NI05 1090.6 1090 12 3.47 0.05

SaldaGf Bakhrabad 846.24 845.97 35 15.12 0.00771

MeghnaGF Bakhrabad 899.73 845.97 28 17.14 1.92

TitasGf Bbaria 1000.9 961.28 1 303.2 39.62

Bbaria TNI 961.28 944 1 145.6 17.28

Bbaria TN2 961.28 946.61 1 152.6 14.67

TNI KAI 944 836.96 14.1 145.6 7.59149

KAI TN3 836.96 832.6 7 44.6 0.62286

TN3 Nars 832.6 813.67 30 44.6 0.631

TN2 Daulot# 946.61 869.33 16 152.6 4.83

Daulot# TN4 869.33 816.09 29 131.81 1.83586

TN4 Nars 816.09 813.67 1 131.81 2.42

Nars Tarabo 813.67 810.17 20 24.52 0.175

Tarabo Demra 810.17 805.45 12 29.44 0.39333

Nars Tarabo# 813.67 810.17 40 47.7 0.0875

Tarabo# ShiddPP 810.17 809.75 5 42.78 0.084

ShiddPP ShiddPS 809.75 809.1 0.0003 14.62 2166.67

ShiddPP N76 809.75 807.6 10 28.17 0.215

N76 Demra 807.6 805.45 10 28.17 0.215

128

Nras Ghorasal 813.67 776 8.4 225.84 4.48452

Ghorasal GhoraPP 776 616.4 0.4 175.54 399

Ghorasal GhoraFF 776 730.55 8.4 55.19 5.41071

GhoraFF DGhoraFF 730.55 730.53 0:0003 43.2 66.6667

GhoraFF PalashFF 730.55 729.88 0.8 12 0.8375

Monohordi Nars 855.58 813.67 32 110.35 1.30969

BelaboGF Nars 850.69 813.67 13 16.31 2.84769

Appendix 5: Simulated Results of High Pressure Transmission Lines at Maximum

Load.

Name Source/ Pressure Mass Rate Liquid Gas Rate GLR Water

Sink Rate Cut

Inlet F psig 1b/s STB/d" mmscf/d scfi'stb vol %

JaBadGF Source 1350 81.79 161.88 0

BBazar Source 1312.7 17.68 35 0

KTL234 Source 1311.9 47.39 424.55 85 200210 0

KTLl Source 1311.5 13.94 124.87 25 200210 0

HariGF Source 1311.5 3.1 6 0

BibvaGF Source 1324.5 63.09 120 0

RashidGF Source 1312.9 80.84 160 0

HGFI Source 1214.3 136.42 270 0

TitasGF Source 918.75 155.24 300 0

KatiGF Source 981.67 47.69 90 0

Salda Source 837.5 15.52 30 0

MegnaGF Source 850.6 10.35 20 0

BakhraGF Source 772.17 0.00259 0.005 0

BelaboGF Source 725.75 10.35 20 0

SanguGF Source 5538.6 84.12 160 0

CtgCitv Sink 769.13 162.41 15.74 311.99 19815000 0

MegPP Sink 667.45 46.35 6.41 90 14030000 0

N115 Sink 668.38 1.03 0.143 2 14030000 0

HariPP Sink 668.92 36.05 4.99 70 14030000 0

ShiddPS Sink 678.19 20.61 0.835 40 47876000 0

DDemra Sink 668.92 46.36 3.26 90 27572000 0

DGulshan Sink 662.65 42.24 2.97 82 27572000 0

DJDevour Sink 662.3 3.09 0.384 6 15608000 0

BBari Sink 687.82 28.84 4 56 13984000 0

SGani Sink 687.84 20.6 2.86 40 13984000 0

JamunaFF Sink 687.76 23.18 3.22 45 13984000 0

GhoraPP Sink 524.92 96.33 5.09 187 36723000 0

DGhoraFF Sink 660.2 20.61 1.09 40 36723000 0

PalashFF Sink 660.2 10.82 0.572 21 36723000 0

MmenPP Sink 687.84 10.3 1.43 20 13984000 0

DJDTDSL Sink 1296.8 42.12 336.36 76 225950 0

FenPP Sink 1311.4 10.28 8.16 20 2452300 0

129

ShahiiPP Sink 1200 17.68 35 0

APS Sink 665.05 89.61 1.73 175 10130000 0

ZiaFF Sink 761.56 23.04 0.444 45 10130000 0

KTilla Manifold 1311.9 121.78 96.63 236.97 2452300 0

FenGanj Manifold 1290.8 121.78 96.63 236.97 2452300 0

Rashidp Manifold 1235.7 255.44 67.08 496.99 7409200 0

Habigani Manifold 1158.2 310.64 62.9 606.25 9638900 0

KJ Manifold 965.28 358.33 59.91 696.24 11621000 0

Ashugani Manifold 775.21 358.33 59.91 .696.24 11621000 0

Bakhra# Manifold 772.17 192.88 26.69 374.49 14030000 0

DauKandi Manifold 773.92 177.78 24.68 345.18 13984000 0

Dhanua Manifold 735.93 108.06 15 209.8 13984000 0

Elenga Manifold 687.84 95.7 13.29 185.82 13984000 0

Nolka Manifold 686.84 49.44 6.86 96 13984000 0

JDevpur Manifold 662.3 24.42 3.04 47.42 15608000 0

Dewnbag Manifold 690.54 67.21 9.3 130.5 14030000 0

SoGaon Manifold 730.38 68.24 9.44 132.5 14030000 0

MegnaPP Manifold 751.46 114.6 15.86 222.5 14030000 0

Faujdar Manifold 655.83 162.41 15.74 311.99 19815000 0

Kuchai Manifold 1310.3 42.12 336.36 76 225950 0

Appendix 6: Simulated results of high-pressure transmission lines modified network

using R-A loop line.

From Node: .::.t, To Node'": Up Streilin .Down'Stream' ~Length1 -Leg.Flow 1 "-Piessure1-1;.;.. ...•..•-. ..' ~ - .,.~..~.".1'l ~••.._,. ,",,",-.:.~ t "'n"" "~'. ~'"T'" '-,:"

: ~; .• J;" "!' ••• ~ l' p'" -', - ,';" ,'~

Pressure' • 'Pressure':: .- .. ' Gadiant

• .., . Psig '.' ,. Psig . km MMSCFD Psiglkm.JabadGF Ktilla 1100 1091.4 18 210.85 0.47778

Ktilla FenGanj 1091.4 1090.2 27 289.18 0.044

FenGanj Rashidpur 1090.2 1086.5 67.5 268.51 0.055

Rashidpur Habigonj 1086.5 1084.9 27.5 56.73 0.058

Habigonj KJ 1084.9 1080.1 35.5 267.9 0.135

KJ Ashugonj 1080.1 1076.5 18 267.9 0.02

Ashugonj Bakhrabad 1076.5 1074.5 57.1 440.4 0.03503

Bakhrabad KuBapur 1074.5 1073.9 15.7 158.11 0.03822

KuBapur Bijra 1073.9 1072.2 27.8 158.11 0.06115

Bijra Laksham 1072.2 1071.6 6 158.11 0.1

Laksham Feni 1071.6 1069.1 40 158.11 0.0625

Feni J42 1069.1 1068.2 10 158.11 0.09

J42 Msgrai 1068.2 1066.7 25 158.11 0.06

Msgrai Barab 1066.7 1066.2 9 158.11 0.05556

Barab Faujdarhat 1066.2 1064 38 158.11 0.05789

Faujdarhat CtgCity 1064 1063.7 2.5 312.01 0.12

SanguGF Faujdarhat 1064.7 1064 49 160 0.01429

130

Bakhrabad Meghnaghat 1074.5 1066.6 30 332.29 0.26

Meghnaghat Sonargaon 1066.6 1064.2 15 239.43 0.16

Sonargaon Dewnbag 1064.2 1061.7 15 237.36 0.17

Dewnbag Demra 1061.7 1061.1 8 165.14 0.075

Ashugonj Daulotkandi 1076.5 1075.8 5 306.38 0.14

Daulotkandi Monohordi 1075.8 1071.4 27 364.32 0.163

Monohordi Dhanua 1071.4 1068.2 37 191.14 0.086

Dhanua Elenga 1068.2 1064.6 52 166.39 0.069

Elenga Joydevpur 1064.6 1057.3 56 1.39 0.13036

Joydevpur Gulshan 1057.3 1059.5 25 0.796 -0.088

Gulshan Deinra 1059.5 1061.4 32 85.38 -0.0594

elenga nolka 1064.6 1062.3 39 99 0.05897

nolka Sganj 1062.3 1061.8 5 40 0.1

nolka Bbari 1062.3 1059.7 43 56 0.06047

Elenga JaGanj 1064.6 1052.1 43 53.62 0.2907

JaGanj JamunaFF 1052.1 1051.8 2 45 0.15

JaGanj Shbari 1052.1 1046 II 7.22 0.55455

shBabi Jamalpur 1046 1041.9 18 7.22 0.22778

Jamalpur Sherpur 1041.9 1037 16 3 0.30625

Dhanua GafGaon 1070.2 1066.8 19 24.75 0.17895

GafGaon Trishal 1066.8 1060.8 20.004 24.75 0.29994

Trisal mymen 1060.8 1056 16 24.75 0.3

Mymen LX 1056 1053.6 8 22.69 0.3

LX Mymenpp 1053.6 1053.6 5 20 0

Lx Neykona 1053.6 1049.9 32.5 2 0.11385

Monohordi kisGanj 1071.4 1070.1 36 2 0.036

KAI APS 1080.7 1057.3 1.5 175 15.6

KAI ZiaFF 1080.7 1073.4 2.4 45 3.04167

Dewnbag hariPP 1061.7 1060.7 1.58 90 0.633

FenGanj fenpp 1089.9 1063.8 0.5 20 52.2

RashidGF Rashidpur 1084.8 1086.5 1.9 160 0.15789

HGFI Manifold 1085.2 1085.2 0.006 270 0

Manifold ShahjiPP 1085.2 1006.4 2.5 35 31.52

Manifold Habigonj 1085.2 1084.9 I 211.17 0.3

Manifold Katihata 1085.2 1077.6 42 22.12 0.181

Katihata Manif 1077.6 1075.3 11.5 22.12 0.48696

Manif Ashuganj 1075.3 1076.5 2 100.86 -0.6

N61 Ktilla 1091.4 1091.4 0.02 43.33 0

NIII N61 1084.3 1091.4 28 41.67 -0.2536

NIII Kuchai 1084.3 1083 2.082 66.67 0.6244

Kuchai Sylhet 1083 975.5 0.03 76 3583.33

HariGF Kuchai 1085 1083 12 6 0.16667

SaldaGf Bakhrabad 1078.4 1074.5 35 30 0.11143

MeghnaGF Bakhrabad 1078.12 1074.5 28 20 0.12929

TitasGf Bbaria 1139 1088.2 I 300 50.8

Bbaria TNI 1088.2 1087 I 149.26 1.2

13].

Bbaria TN2 1088.2 1087.4 I 147.67 0.8

TNI KAI 1087 1080.7 14.1 149.26 0.44681

KAI TN3 1080.7 1072.6 7 45.81 1.15714

TN3 Nars 1072.6 1064.9 30 45.81 0.25667

TN2 Daulot# 1087.4 1075.8 16 147.67 0.7625

Daulot# TN4 1075.8 1065.2 29 89.73 0.34483

TN4 Nars 1065.2 1064.9 I 89.73 0.3

Nars Tarabo 1064.9 1063.1 20 7.66 0.09

Tarabo Demra 1063.1 1061.1 12 6.93 0.16667

Nars Tarabo# 1064.9 1063.4 40 46.55 0.0375

Tarabo# ShiddPP 1063.1 1062.1 5 47.28 0.2

ShiddPP ShiddPS 1062.8 1062.8 0.0003 40 0

ShiddPP N76 1062.8 1062 10 6.14 0.08

N76 Demra 1062 1061.1 10 6.14 0.09

Nras Ghorasal 1064.9 1058.7 8.4 264.2 0.7381

Ghorasal GhoraPP 1058.7 839.58 004 187 547.8

Ghorasal GhoraFF 1058.7 1056.8 8.4 62.74 0.22619

GhoraFF DghoraFF 1056.8 1056.8 0.0003 40 0

GhoraFF PalashFF 1056.8 1056.6 0.8 21 0.25

Monohordi Nars 1071.4 1064.9 32 165.95 0.203125

Daulot# Daulotkandi 1075.8 1075.8 0.1 57.94 0

BelaboGF Nars 1091.8 1064.9 13 20 2.0692308

Rashidpur NI08 1086.5 1085.8 10 491.79 0.07

NI08 NI09 1085.8 1083.5 30 491.79 0.077

NI09 Ashugonj 1083.5 1076.5 37 581.79 0.189

BibyanaGF Rashidpur 1097.3 1086.5 30 120 0.36

KatiGF NI09 1090.8 1080.5 I 90 10.3

Appendix 7: Simulated Results of High Pressure Transmission Lines modified Network

Using R-A Loop Line by using Known Pressure at Ashugonj.

From Node To Node Up Stream Down Stream Length Leg Flow Pressure

Pressure Pressure Gadiant

Psig Psig km MMSCFD Psiglkm

JabadGF Ktilla 1115.5 1090 18 120 1.41667

Ktilla FenGanj 1090 1086.5 27 493.4 0.12963

FenGanj Rashidpur 1086.5 1070 67.5 473.52 0.244

Rashidpur Habigonj 1070 1055.9 27.5 226.12 0.51

Habigonj KJ 1055.9 1020.7 35.5 377.35 0.992

KJ Ashugonj 1020.7 990.4 18 377.35 1.68

Ashugonj Bakhrabad 990.4 974.01 57.1 416.64 0.28704

Bakhrabad KuBapur 974.01 969.21 15.7 255.99 0.30573

KuBapur Bijra 969.21 956.66 27.8 255.99 0.45144

Bijra Laksham 956.66 952.51 6 255.99 0.69167

132

Laksham Feni 952.51 932.94 40 255.99 0.48925

Feni J42 932.94 925.61 10 255.99 0.733

J42 Msgrai 925.61 913.79 25 255.99 0.4728

Msgrai Barab 913.79 907.36 9 255.99 0.71444

Barab Faujdarhat 907.36 889.75 38 255.99 0.46342

Faujdarhat CtgCity 889.75 887.33 2.5 415.99 0.968

SanguGF Faujdarhat 895.25 889.75 49 160 0.11224

Bakhrabad Meghnaghat 974.01 905.04 30 210.63 2.299

Meghnaghat Sonargaon 905.04 880.04 15 120.84 1.67

Sonargaon Dewnbag 880.04 855.02 15 118.84 1.668

Dewnbag Demra 855.02 850.01 8 49 0.626

Ashugonj Daulotkandi 990.4 987.83 5 331.72 0.514

Daulotkandi Monohordi 987.83 969.96 27 393.03 0.662

Monohordi Dhanua 969.96 960.93 37 216.98 0.244

Dhanua Elenga 960.93 946.91 52 193.03 0.27

Elenga Joydevpur 946.91 897.88 56 33.36 0.87554

Joydevpur Gulshan 897.88 889.09 25 50.47 0.3516

Gulshan Demra 848.09 850.01 32 31.33 -0.06

elenga nolka 946.91 944.9 39 95.8 0.05154

nolka Sganj 944.9 944.6 5 40 0.06

nolka Bbari 944.9 941.9 43 56 0.06977

Elenga JaGanj 946.91 943.87 43 51.89 0.0707

JaGanj JamunaFF 943.87 943.76 2 45 0.055

JaGanj Shbari 943.87 942.79 11 6.99 0.09818

shBabi Jamalpur 942.79 942 18 6.99 0.04389

Jamalpur Sherpur 942 941.12 16 3 0.055

Dhanua GafGaon 966.93 965.15 19 23.95 0.09368

GafGaon Trishal 965.15 963.85 20.004 23.95 0.06499

Trisal mymen 963.85 962.43 16 23.95 0.08875

Mymen LX 962.43 961.9 8 21.95 0.06625

LX Mymenpp 960.9 959.84 5 20 0.212

Lx Neykona 960.9 958.46 32.5 2 0.07508

Monohordi kisGanj 979.96 976.58 36 2 0.09389

KAI APS 995 917.26 1.5 175 51.8267

KAI ZiaFF 995 987 2.4 45 3.33333

Dewnbag hariPP 860.02 850.04 1.58 90 6.31646

FenGanj fenpp 1086.5 1083.3 0.5 20 6.4

RashidGF Rashidpur 1090.5 1070 1.9 160 10.79

HGFI Manifold 1108.2 1108.2 0.006 270 0

Manifold ShahjiPP 1108.2 1092.5 2.5 35 6.28

Manifold Habigonj 1108.2 1052.9 1 151.23 55.3

Manifold Katihata 1108.2 1024.2 42 83.77 0.97143

Katihata Manif 1024.2 994.8 11.5 83.77 5.05217

Manif Ashuganj 994.8 990.4 2 93.39 2.2

N61 Ktilla 1090 1090 0.02 40.01 0

Nlll N61 1089.4 1090 28 44.99 -0.0214

133

NIII Kuchai 1089.4 1087.9 2.082 69.99 0.72046

Kuchai Sylhet 1087.9 926.36 0.03 76 5384.67

HariGF Kuchai 1089.4 1087.9 12 6 0.125

SaldaGf Bakhrabad 1025.9 974.01 35 30 1.48257

MeghnaGF Bakhrabad 1036.5 974.01 28 20 2.23179

TitasGf Bbaria 1103.1 1050.5 I 300 52.6

Bbaria TNI 1050.5 1046.8 I 116.95 3.7

Bbaria TN2 1050.5 1046.5 I 180.05 4

TNI KAI 1046.5 995 14.1 116.95 3.65248

KAI TN3 995 982.65 7 74.34 1.76429

TN3 Nars 982.65 929.42 30 74.34 1.77433

TN2 Daulot# 1046.5 983.07 16 180.05 3.96438

Daulot# TN4 983.07 930.46 29 118.72 1.81414

TN4 Nars 930.46 929.42 I 118.72 1.04

Nars Tarabo 929.42 900.04 20 65.83 1.469

Tarabo Demra 900.04 850.Dl 12 75.61 4.16917

Nars Tarabo# 929.42 900.04 40 125.28 0.7345

Tarabo# ShiddPP 900.04 896.83 5 115.5 0.642

ShiddPP ShiddPS 896.83 896.83 0.0003 40 0

ShiddPP N76 896.83 870.21 10 75.5 2.662

N76 Demra 870.21 850.Dl 10 75.5 2.02

Nras Ghorasal 929.42 902.59 8.4 188.8 3.19405

Ghorasal GhoraPP 902.59 799.69 0.4 187 257.25

Ghorasal GhoraFF 902.59 890.52 8.4 60.98 1.4369

GhoraFF DGhoraFF 890.52 890.52 0.0003 40 0

GhoraFF PalashFF 890.52 890.41 0.8 21 0.1375

Monohordi Nars 969.96 929.42 32 169.08 1.267

Daulot# Daulotkandi 983.07 987.83 0.1 61.33 -47.6

BelaboGF Nars 960.51 929.42 13 20 2.3915385

Rashidpur NI08 1070 1061.6 10 527.41 0.80

NI08 NI09 1061.6 1040.8 30 527.41 0.69

NI09 Ashugonj 1040.8 990.4 37 617.42 1.3621622

BibyanaGF Rashidpur 1104.7 1065 30 120 1.3233333

KatiGF NI09 1046.5 1040.8 I 90 5.7

, ')

134

,\ / \

V

Appendix 8: Simulated Results of High Pressure Transmission Lines modified Network

by Extension of Network up to Bheramara.

From Node To Node Up Stream Down Stream Length Leg Flow Pressure

Pressure Pressure Gadiant

Psig Psig km MMSCFD Psiglkm.

JabadGF Ktilla 1115 1090 18 120 1.38889

Ktilla FenGanj 1090 1088.9 27 284.54 0.041

FenGanj Rashidpur 1088.9 1084.4 67.5 264.18 0.067

Rashidpur Habigonj 1084.4 1081.9 27.5 44.16 0.09091

Habigonj KJ 1081.9 1077.4 35.5 270.21 0.127

KJ Ashugonj 1077.4 1074.6 18 270.21 0.16

Ashugonj Bakhrabad 1074.6 1072.8 57.1 406.68 0.03152

Bakhrabad KuBapur 1072.8 1072.4 15.7 134.7 0.02548

KuBapur Bijra 1072.4 1071.8 27.8 134.7 0.02158

Bijra Laksham 1071.8 1071.6 6 134.7 0.03333

Laksham Feni 1071.6 1069.8 40 134.7 0.045

Feni J42 1069.8 1069 10 134.7 0.08

J42 Msgrai 1069 1067.5 25 134.7 0.06

Msgrai Barab 1067.5 1067.3 9 134.7 0.02222

Barab Faujdarhat 1067.3 1063.1 38 134.7 0.11053

Faujdarhat CtgCity 1063.1 1062.4 2.5 258 0.28

SanguGF Faujdarhat 1066 1063.1 49 128 0.05918

Bakhrabad Meghnaghat 1072.8 1064.9 30 322.01 0.26

Meghnaghat Sonargaon 1064.9 1062.6 15 242.83 0.15

Sonargaon Dewnbag 1062.6 1058.5 15 240.77 0.27

Dewnbag Demra 1058.5 1057.8 8 158.52 0.0875

Ashugonj Daulotkandi 1074.6 1074.3 5 329.6 0.06

Daulotkandi Monohordi 1074.3 1069.4 27 387.12 0.18

Monohordi Dhanua 1069.4 1065.7 37 224.31 0.1

Dhanua Elenga 1065.7 1062.3 52 205.8 0.065

Elenga Joydevpur 1062.3 1058.2 56 12.52 0.07321

Joydevpur Gulshan 1058.2 1059.6 25 4.44 -0.056

Gulshan Demra 1059.6 1057.8 32 60.99 0.05625

elenga nolka 1062.3 1060.6 39 139.82 0.04359

nolka Sganj 1060.6 1060 5 30 0.12

nolka Bbari 1060.6 1057.6 43 46 0.06977

Elenga JaGanj 1062.3 1050 43 53.46 0.28605

JaGanj JamunaFF 1050 1050 2 45 0

JaGanj Shbari 1050 1044.1 11 7.2 0.53636

shBabi Jamalpur 1044.1 1040.1 18 7.2 0.22222

Jamalpur Sherpur 1040.1 1035.1 16 3 0.3125

Dhanua GafGaon 1065.7 1064.6 19 18.5 0.058

GafGaon Trishal 1064.6 1061.3 20.004 18.5 0.165

135

Trisal mymen 1061.3 1057.8 16 18.5 0.21875

Mymen LX 1057.8 1056 8 16.45 0.225

LX Mymenpp 1056 1056 5 14 0

Lx Neykona 1056 1052 32.5 2 0.12308

Monohordi kisGanj 1069.4 1067.6 36 2 0.05

KAI APS 1072.6 1056.5 1.5 175 10.7333

KAI ZiaFF 1072.6 lO72.4 2.4 45 0.08333

Dewnbag hariPP 1060.5 1058.9 1.58 80 1.01266

FenGanj fenpp 1087.9 1068.6 0.5 20 38.6

RashidGF Rashidpur 1084 1082.4 1.9 160 0.84211

HGFI Manifold 1084.6 1084.5 0.006 270 16.67

Manifold ShahjiPP 1083.5 1060.6 2.5 20 9.16

Manifold Habigonj 1083.5 1079.9 1 226.04 3.6

Manifold Katihata 1083.5 1076.8 42 22.98 0.13333

Katihata Manif 1076.8 1074.4 11.5 22.98 0.47826

Manif Ashuganj 1074.4 1074.6 2 98.78 -0.1

N61 Ktilla 1090 1090 0.02 43.33 0

Nlll N61 1083.2 1090 28 41.67 -0.2429

Nlll Kuchai 1083.2 1088.9 2.082 66.67 -2.7378

Kuchai Sylhet 1088.9 976.47 0.03 76 3747.67

HariGF Kuchai 1063.3 1088.9 12 6 -2.1333

SaldaGf Bakhrabad 1019 1072.8 35 30 -1.5371

MeghnaGF Bakhrabad 1028.8 1072.8 28 20 -1.5714

TitasGf Bbaria 1100 1087.2 1 300 12.8

Bbaria TNI 1087.2 1086 1 150.57 1.2

Bbaria TN2 1087.2 1086.4 1 147.39 0.8

TNI KAI 1086 1072.6 14.1 150.57 0.95035

KAI TN3 1072.6 1071.7 7 46.22 0.12857

TN3 Nars 1071.7 1064.2 30 46.22 0.25

TN2 Daulot# 1086.4 1074.4 16 147.39 0.75

Daulot# TN4 1074.4 1064.5 29 89.88 0.34138

TN4 Nars 1064.5 1064.2 1 89.88 0.3

Nars Tarabo 1064.2 1063.4 20 8.09 0.04

Tarabo Demra 1063.4 1057.8 12 4.2 0.46667

Nars Tarabo# 1064.2 1063.4 40 50.57 0.02

Tarabo# ShiddPP 1063.4 1063.1 5 54.47 0.06

ShiddPP ShiddPS 1063.1 1063.1 0.0003 52 0

ShiddPP N76 1063.1 1062.2 10 1.08 0.09

N76 Demra 1062.2 1057.8 10 1.08 0.44

Nras Ghorasal 1064.2 1058.4 8.4 254.62 0.69048

Ghorasal GhoraPP 1058.4 899.7 0.4 166 396.75

Ghorasal GhoraFF 1058.4 1056.5 8.4 61.6 0.22619

GhoraFF DGhoraFF 1056.5 1056.5 0.0003 40 0

GhoraFF PalashFF 1056.5 1056.4 0.8 20 0.125

Monohordi Nars 1069.4 1064.2 32 158.71 0.225

Daulot# Daulotkandi 1074.4 1074.3 0.1 57.5 1

t36

BelaboGF Nars 1090.5 1064.2 13 20 2.0230769

Rashidpur NI08 1084.4 1082.8 10 480.03 0.16

NI08 NI09 1082.8 1080.1 30 480.03 0.09

NI09 Ashugonj 1080.1 1074.6 37 570.03 0.15

BibyanaGF Rashidpur 1091.1 1084.4 30 100 0.223

KatiGF NI09 1085.6 1078 1 90 7.6

Appendix 9: Simulated Results of High Pressure Transmission Lines Extension of

Network up to Khulna without any Modification

Source/ Delivery Name Source/ Deliverv. Pressure, Psig Flow Rate, MMSCFD

Titas gas field Source 1114.3 300

Habigoni Gas field Source 1106.1 270

Rashidpur Gas Field Source 1091.7 250

Jalalabad Gas Field Source 1112.3 120

Sangu Gas Field Source 1004.7 160

Narshindi Gas Field Source 956.39 15

Meghna Gas Field Source 1038.5 15

Salda Gas field Source 1017.6 15

Kailashtilla(MSTE) gas Field Source 1090 200

Kailashtilla(Sillica) gas field Source 1089.9 60

Beanibazar Gas Field Source 1090.7 30

Haripur Gas Field Source 1088.9 4

Bibyana Gas Field Source 1181.3 300

Kati (Titas) Source 1097.9 40

Bakhrabad Gas Field Source 1004.9 0.005

APS Sink 947.75 140

GhoraPP Sink 863.38 180

HaripPP Sink 938.82 95

MvmenPP Sink 906.98 18

ShiddPP Sink 939.04 52

FenPP Sink 1088.9 20

ShahiPP Sink 1089.5 36

ZiaFF Sink 1002 56

GhoraFF Sink 932.84 40

PalashFF Sink 931.84 20

JamuanaFF Sink 828.01 45

Joydevpur Sink 932.81 9

Gulshan Sink 932.87 80

Shiraigoni Sink 824.87 40

Baghabari Sink 824.72 100

Ctgcity Sink 982.9 300

Sylhet Sink 926.24 80

Demra Sink 938.85 110

Khulna Sink 740.55 100

137

!EP-PP .BheraPP

SinkSink

812.2805.13

1070

Appendix 10: Simulated Results of High Pressure Transmission Lines Extension of

Network up to Khulna with A-D Loop Line.

From Node .' To Node' , Up Stream DoWn Stream' Length ~Leg Flow~ ::.:Ptessure;:'. . -. . . , GadiantPressure Pressure <.

Psig . Psig . kID .•.. MMSCFD Psiglkm

JabadGF Ktilla 1112.3 1090 18 120 1.23889

Ktilla FenGanj 1090 1088.6 27 339.29 0.052

FenGanj Rashidpur 1088.6 1083.9 67.5 319.45 0.07

Rashidpur Habigonj 1083.9 1080.8 27.5 140.42 0.11273

Habigonj KJ 1080.8 1075.2 35.5 346.79 0.158

KJ Ashugonj 1075.2 1070.9 18 346.79 0.239

Ashugonj Bakhrabad 1070.9 1068.9 57.1 481.5 0.03503

Bakhrabad KuBapur 1068.9 1068.3 15.7 144.04 0.03822

KuBapur Bijra 1068.3 1067.1 27.8 144.04 0.04317

Bijra Laksham 1067.1 1066.9 6 144.04 0.03333

Laksham Feni 1066.9 1065.1 40 144.04 0.045

Feni J42 1065.1 1064.4 10 144.04 0.07

J42 Msgrai 1064.4 1062.2 25 144.04 0.088

Msgrai Barab 1062.2 1061.3 9 144.04 0.1

Barab Faujdarhat 1061.3 1056.6 38 144.04 0.12368

Faujdarhat CtgCity 1056.6 1056.6 2.5 300 0

SanguGF Faujdarhat 1060.6 1056.6 49 160 0.08163

Bakhrabad Meghnaghat 1068.9 1062.6 30 367.47 0.21

Meghnaghat Sonargaon 1062.6 1060 15 260.39 0.17333

Sonargaon Dewnbag 1060 1057.9 15 258.35 0.14

Dewnbag Demra 1057.9 1057.2 8 161.47 0.0875

Ashugonj Daulotkandi 1070.9 1070.7 5 190.5 0.04

Daulotkandi Monohordi 1070.7 1069.2 27 246.76 0.05556

Monohordi Dhanua 1069.2 1066.1 37 47.81 0.08378

Dhanua Elenga 1066.1 1058 52 394.16 0.15577

Elenga Joydevpur 1058 1052.5 56 14.88 0.09821

Joydevpur Gulshan 1052.5 1050.4 25 0.466 0.084

Gulshan Demra 1050.4 1057.2 32 81.15 -0.2125

elenga nolka 1058 1054 39 326.27 0.10256

nolka Sganj 1054 1053.9 5 40 0.02

nolka Bbari 1054 1049.8 43 100 0.09767

Elenga JaGanj 1058 1045.7 43 53.02 0.28605

JaGanj JamunaFF 1045.7 1045.7 2 45 0

JaGanj Shbari 1045.7 1039.8 11 7.14 0.53636

138 ••

shBabi Jamalpur 1039.8 1035.8 18 7.14 0.22222

Jamalpur Sherpur 1035.8 1030.9 16 3 0.30625

Dhanua GafGaon 1066.1 1065.2 19 22.43 0.04737

GafGaon Trishal 1065.2 1063.8 20.004 22.43 0.06999

Trisal mymen 1063.8 1055.6 16 22.43 0.5125

Mymen LX 1055.6 1053.4 8 20.39 0.275

LX Mymenpp 1053.4 1053.4 5 18 0

Lx Neykona 1053.4 1049.8 32.5 2 0.11077

Monohordi kisGanj 1069.2 1066.4 36 2 0.07778

KAI APS 1070.6 1058.3 1.5 140 8.2

KAI ZiaFF 1070.6 1066.8 2.4 56 1.58333

Dewnbag hariPP 1058.9 1050.7 1.58 95 5.18987

FenGanj fenpp 1087.6 1067.9 0.5 20 39.4

RashidGF Rashidpur 1084 1083.9 1.9 250 1.10526

HGFI Manifold 1080 1080 0.006 270 0

Manifold ShahjiPP 1080 996.8 2.5 36 33.28

Manifold Habigonj 1080 1076.8 1 206.36 3.2

Manifold Katihata 1080 1072.4 42 25.88 0.17857

Katihata Manif 1072.4 1069.7 11.5 25.88 0.61739

Manif Ashuganj 1069.7 1070.9 2 70.12 -0.6

N61 Ktilla 1090 1090 0.02 187.66 0

N1l1 N61 1088 1090 28 12.38 -0.0714

Nlll Kuchai 1088 1062.1 2.082 72.33 12.44

Kuchai Sylhet 1062.1 970.18 0.03 80 3064

HariGF Kuchai 1065.3 1062.1 12 4 0.26667

SaldaGf Bakhrabad 1080.8 1068.9 35 15 0.34

MeghnaGF Bakhrabad 1100.3 1068.9 28 15 1.12143

TitasGf Bbaria 1135.5 1082.5 1 300 53

Bbaria TNI 1082.5 1081.3 1 151.09 1.2

Bbaria TN2 1082.5 1081.3 1 146.86 1.2

TNI KAI 1081.3 1070.6 14.1 151.09 0.75887

KAI TN3 1070.6 1067 7 46.14 0.51429

TN3 Nars 1067 1059.5 30 46.14 0.25

TN2 Daulot# 1081.3 1061.8 16 146.86 1.21875

Daulot# TN4 1061.8 1059.8 29 90.6 0.06897

TN4 Nars 1059.8 1059.5 1 90.6 0.3

Nars Tarabo 1059.5 1058.2 20 12.01 0.065

Tarabo Demra 1057.2 12 14.97 -88.1

Nars Tarabo# 1059.5 1058.2 40 73.05 0.0325

Tarabo# ShiddPP 1058.2 1057.9 5 70.09 0.06

ShiddPP ShiddPS 1057.9 1057.8 0.0003 52 333.333

ShiddPP N76 1057.9 1057.5 10 16.93 0.04

N76 Demra 1057.5 1057.2 10 16.93 0.03

Nras Ghorasal 1059.5 1053.5 8.4 259.52 0.71429

Ghorasal GhoraPP 1053.5 857.06 0.4 180 491.1

Ghorasal GhoraFF 1053.5 1051.6 8.4 61.34 0.22619

139

GhoraFF DGhoraFF 1051.6 1051.6 0.0003 40 0

GhoraFF PalashFF 1051.6 1051.5 0.8 20 0.125

Monohordi Nars 1069.2 1059.5 32 194.87 0.30313

Daulot# Daulotkandi 1069.7 1070.7 0.1 56.26 -10

BelaboGF Nars 1074.4 1059.5 13 15 1.1461538

Rashidpur NI08 1083.9 1083.2 10 729.22 0.07

NI08 NI09 1083.2 1079.5 30 729.22 O. t23

NI09 Ashugonj 1079.5 1071 37 769.2 0.23

BibyanaGF Rashidpur 1172.4 1083.9 30 300 2.95

KatiGF NI09 1076.4 1075.5 I 40 0.9

Ashugonj NI25 1070.9 1070.4 5 368.79 0.1

NI25 Dhanua 1070.4 1066.1 65 368.79 0.0661538

Appendix 11: Simulated Results of High Pressure Transmission Lines, Modification of

Nolka to Khulna Line by Using Loop Line from R-A Loop Line to Dhanua

From Node' "To Node .' 1,JpStr.earn' Down Stream" :Length; ~Legflow' " Pressure", ' Pressure . Pressure ,~ " ; Gaai;rnt. . .

Psig Psig . Ian MMSCFD Psiglkm

JabadGF Ktilla 1112.3 1090 18 120 1.23889

Ktilla FenGanj 1090 1088.6 27 339.29 0.052

FenGanj Rashidpur 1088.6 1084.1 67.5 319.45 0.067

Rashidpur Habigonj 1084.1 1080.1 27.5 128.34 0.145

Habigonj KJ 1080.1 1072.5 35.5 335.28 0.214

KJ Ashugonj 1072.5 1070.3 18 335.28 0.12222

Ashugonj Bakhrabad 1070.3 1068.2 57.1 481.71 0.03678

Bakhrabad KuBapur 1068.2 1067.8 15.7 144.51 0.02548

KuBapur Bijra 1067.8 1066.1 27.8 144.51 0.06115

Bijra Laksham 1066.1 1065.8 6 144.51 0.05

Laksham Feni 1065.8 1063.6 40 144.51 0.055

Feni J42 1063.6 1062.7 10 144.51 0.09

J42 Msgrai 1062.7 1060.7 25 144.51 0.08

Msgrai Barab 1060.7 1059 9 144.51 0.18889

Barab Faujdarhat 1059 1055 38 144.51 0.10526

Faujdarhat CtgCity lOSS 1054 2.5 300 0.4

SanguGF Faujdarhat 1060.9 lOSS 49 160 0.12041

Bakhrabad Meghnaghat 1068.2 1059.1 30 367.23 0.303

Meghnaghat Sonargaon 1059.1 1054.4 IS 259.78 0.313

Sonargaon Dewnbag 1054.4 1051.2 IS 257.74 0.213

Dewnbag Demra 1051.2 1049.6 8 160.55 0.20

Ashugonj Daulotkandi 1070.3 1070.1 5 170.37 0.04

Daulotkandi Monohordi 1070.1 . 1068.8 27 227.39 0.04815

Monohordi Dhanua 1068.8 1066.4 37 25.3 0.06486

Dhanua Elenga 1066.4 1059 52 392.1 0.14231

140

Elenga Joydevpur 1059 1053 56 15.06 0.10714

Joydevpur Gulshan 1053 1052.8 25 0.649 0.008

Gulshan Demra 1052.8 1049.6 32 81.22 0.1

elenga nolka 1059 1054.9 39 324.33 0.10513

nolka Sganj 1054.9 1054.8 5 40 0.02

nolka Bbari 1054.9 1050.7 43 100 0.09767

Elenga JaGanj 1059 1046.7 43 52.71 0.28605

JaGanj JamunaFF 1046.7 1046.7 2 45 0

JaGanj Shbari 1046.7 1040.8 11 7.09 0.53636

shBabi Jamalpur 1040.8 1036.7 18 7.09 0.22778

Jamalpur Sherpur 1036.7 1030.9 16 3 0.3625

Dhanua GafGaon 1066.4 1066.1 19 22.3 0.01579

GafGaon Trishal 1066.1 1060.8 20.004 22.3 0.26495

Trisal mymen 1060.8 1056.5 16 22.3 0.26875

Mymen LX 1056.5 1054.3 8 20.27 0.275

LX Mymenpp 1054.3 1054.3 5 18 0

Lx Neykona 1054.3 1050.7 32.5 2 0.11077

Monohordi kisGanj 1068.8 1067 36 2 0.05

KAI APS 1071 1058.6 1.5 140 8.26667

KAI ZiaFF 1071 1067.2 2.4 56 1.58333

Dewnbag hariPP 1053.2 1051.1 1.58 95 1.32911

FenGanj fenpp 1087.6 1067.9 0.5 20 39.4

RashidGF Rashidpur 1082 1081.1 1.9 250 0.47368

HGFI Manifold 1080.1 1080.1 0.006 270 0

Manifold ShahjiPP 1080.1 996.9 2.5 36 33.28

Manifold Habigonj 1080.1 1077.9 1 206.93 2.2

Manifold Katihata 1080.1 1072.7 42 25.31 0.17619

Katihata Manif 1072.7 1070.1 11.5 25.31 0.22609

Manif Ashuganj 1070.1 1070.3 2 70.26 -0.1

N61 Ktilla 1090 1090 0.02 187.66 0

Nlll N61 1088 1090 28 12.33 -0.0714

Nlll Kuchai 1088 1062.4 2.082 72.33 12.2959

Kuchai Sylhet 1062.4 970.18 0.03 80 3074

HariGF Kuchai 1065.3 1062.4 12 4 0.24167

SaldaGf Bakhrabad 1081.1 1068.2 35 15 0.36857

MeghnaGF Bakhrabad 1100.7 1068.2 28 15 1.16071

TitasGf Bbaria 1133.9 1082.9 1 300 51

Bbaria TNI 1082.9 1081.7 1 151.21 1.2

Bbaria TN2 1082.9 1082.1 1 146.74 0.8

TNI KAI 1081.7 1071 14.1 151.21 0.75887

KAI TN3 1071 1067.4 7 45.64 0.51429

TN3 Nars 1067.4 1060 30 45.64 0.24667

TN2 Daulot# 1082.1 1070.1 16 146.74 0.75

Daulot# TN4 1070.1 1060.2 29 89.72 0.34138

TN4 Nars 1060.2 1060 1 89.72 0.2

Nars Tarabo 1060 1058.6 20 12.21 0.07

141

Tarabo Demra 1058.6 1049.6 12 15.5 0.75

Nars Tarabo# 1060 1058.6 40 74.96 0.035

Tarabo# ShiddPP 1058.6 1058.3 5 70.97 0.06

ShiddPP ShiddPS 1058.3 1058.3 0.0003 52 0

ShiddPP N76 1058.3 1057.6 10 17.73 0.07

N76 Demra 1057.6 1049.6 10 17.73 0.8

Nras Ghorasal 1060 1054 8.4 259.84 0.71429

Ghorasa1 GhoraPP 1054 857.54 0.4 180 491.15

Ghorasal GhoraFF 1054 1052.1 8.4 61.44 0.22619

GhoraFF DGhoraFF 1052.1 1052.1 0.0003 40 0

GhoraFF PalashFF 1052.1 1052 0.8 20 0.125

Monohordi Nars 1068.8 1060 32 198 0.275

Daulot# Daulotkandi 1070.1 1070.1 0.1 57.02 0

BelaboGF Nars 1074.9 1060 13 15 1.14615

Rashidpur N108 1084.1 1081.8 10 741.3 0.23

N108 N109 1081.8 1075.9 30 741.3 0.197

N109 Ashugonj 1075.9 1070.7 37 392.18 0.1405405

BibyanaGF Rashidpur 1172.4 1081.1 30 300 3.0433333

KatiGF N109 1078 1075.9 1 40 2.1

N110 Dhanua 1070.7 1066.4 69 188.07 0.06232

142

Appendix 12: Simulated Results of High Pressure Transmission Lines modified

Network by using Compressor Station at Monohordi.

Source/ Delivery Name Source/ Delivery Pressure, Psig Flow Rate, MMSCFD

Titas gas field Source 1106.3 300

Habigonj Gas field Source 1103.7 270

Rashidpur Gas Field Source 1090.8 250

Jalalabad Gas Field Source 1112.3 120

Sangu Gas Field Source 1010 160

Narshindi Gas Field Source 952.47 15

Meghna Gas Field Source 1043.6 15

Sa1daGas field Source 1022.8 15

Kailashtilla(MSTE) gas Field Source 1090 200

Kailashtilla(Sillica) gas field Source 1089.9 60

Beanibazar Gas Field Source 1090.7 30

Haripur Gas Field Source 1088.9 4

Bibyana Gas Field Source 1181.4 300

Kati (Titas) Source 1059.2 40

Bakhrabad Gas Field Source 1012.2 0.005

APS Sink 952.71 140

GhoraPP Sink 857.39 180

HaripPP Sink 925.51 95

MymenPP Sink 957.64 18

ShiddPP Sink 935.27 52

FenPP Sink 1088.9 20

ShahiPP Sink 1086.9 36

ZiaFF Sink 1005.8 56

GhoraFF Sink 926.31 40

PalashFF Sink 925.21 20

JamuanaFF Sink 881.5 45

Joydevpur Sink 923.92 9

Gulshan Sink 925.09 80

Shirajgonj Sink 853.67 40

Baghabari Sink 853.5 100

Ctgcity Sink 1000.1 300

Sylhet Sink 926.37 80

Demra Sink 925.46 110

Khulna Sink 975.1 100

EP-PP Sink 990 10

BheraPP Sink 988 70

MeghPP Sink 941.11 105

143

NOMENCLATURE

u= Internal energy, ft-Ibr/ Ibm

V = fluid velocity, ft / sec

z = elevation above a given datum place, ft

p = pressure, Ibr / ft2

V = volume of a unit mass of the fluid, ftJ / Ibm

Ws = shaft work done by the fluid on the surroundings, ft-lbr / Ibm

g = gravitational acceleration, ft / sec2

go= conversion factor relating mass and weight

h = specific fluid enthalpy, ft-Ibr / Ibm

T = temperature, oR

s = specific fluid entropy, ft-Ibr / Ibm

pmax= maximum allowable internal pressure, psig

t = pipe thickness, inc = sum of mechanical allowances, corrosion, erosion, etc., in.

S = allowable stress for the pipe material, psi

E = longitudinal weld joint factor, in.

do= outside diameter of the pipe, in.

Y = temperature de-rating factor

ve= erosional velocity, ft/sec

p = Fluid density, Ibm/ftJ

C = a constant ranging between 75 and 150

(qe)se= gas flow rate for onset of erosion, Mscfd

d = diameter of the pipe, ft

p = flowing pressure, PSIA

R = gas constant

Z = gas compressibility factor at pressure p and temperature T

qsc= gas flow rate measured at saturated conditions, Mscfd

psc= pressure at saturated conditions, psia

Tse= temperature at saturated conditions, OR

PI = upstream pressure, psia

P2= downstream pressure, psi a

144

Yg = gas gravity (air = I basis)

Zav= average gas compressibility factor

f = Moody friction factor

L = length of the pipe, ft

dch= choke diameter, in

T 1 = inlet temperature, oRz,~ mole fraction of vapor (gas) in the gas-liquid flow-stream

cp= fluid specific heat at constant pressure, Btu/Ibm-oF

)1d = Joule- Thomson coefficient, ft2-°F/lbr

m = mass flow rate, Ibm/sec

Q = phase-transition heat, Btu/Ibm

k = thermal conductivity, Btu/ft-sec-oF

do= outlet pipe diameter, ft

Ts = temperature of the soil or surroundings,OF

kg = Productivity index of the reservoir

F = a transmission factor that is based on the flow regime and other variables,

F=4Iog(3.7dlK), K is the relative roughness of the pipe

Pm= the mean pressure in the pipeline

Zm= the super compressibility factor at the mean pressure

H = the change in elevation of the pipeline between inlet and outlet

r

145 \" !(-,'->

\'.

REFERENCES1. Quader, A.K.M.A, and E. Gomes, "An Exploratory Review of Bangladesh Gas

Sector: Latest Evidence and Areas of Future Research", Centre for Policy

Dialogue, January 24 (2002).2. Saleque, Kh. A., Growth of Natural Gas Sector in Bangladesh - Issues and

Options, Seventh National Convention of Chemical Engineers, December 12

(1998).3. Ejaz, S., Production System Analysis of the Titas Gas Field, M.Sc. Thesis,

Chemical Engineering Department, BUET, Dhaka, 1999.

4. Khan, M.A.A. and Imamududdin, M., Mid Term Gas Demand - Supply Scenario

and Gas Reserves of Bangladesh, Presented at the 2nd Petroleum Engineering

Symposium 1999,24-25 May (1999).

5. Quader, A.K.M.A., Utilization of Natural Gas in Bangladesh and its Future,

Indian Chemical Engineering Congress, Calcutta, December 18-21, 2000.

6. Kennedy J. L., "Oil and Gas Pipeline Fundamentals", Second Edition PennWell

Books, Tulsa, Oklahoma, 1993.

7. Daily Production Reports, GTCL 2000.

8. Petrobangla MIS Division, Petro-center, Dhaka, 2002

9. Gas System Development Plan (Final report), Asian Development Bank, T.A.N°

2024 - BAN, Volume-I, July1996.

10. System Planning Department, PDB, Dhaka, 2000.

11. CLD Department, Titas Gas Transmission and Distribution Co. Ltd., Kawran

Bazar, Dhaka, 2001.12. Rashidpur-Ashugonj Gas Transmission Loop Line Project, Request for Proposal

(REP), Gas Transmission Company Ltd. (GTCL).

13. PIPESIM Operating Manual, Revision (March '1998), Baker Jardine and

Associates Limited, London, England.

14. Monthly Production Reports Petrobangla, Petro-center, Dhaka, 1999,2001.

15. Planning Department, Jalalabad Gas Transmission and Distribution System

Limited, Sylhet, 2000.

16. Planning Department, Gas Transmission and Distribution Company Limited,

Dhaka, 2000.

146

(/"."

(i

~,

17. Kumer S., " Gas Production Engineering", volume 4, Gulf Publishing company,

Houston, Texas, 1987.

18. Perry, R. H. and Cecil, H. c., Chemical Engineers' Hand book, fifth edition,

McGRA W-HlLL KOGAKUSHA, LTD., Tokyo, 1963.

19. Economides, MJ., A.D. Hill, "Petroleum Production Systems".

20. Beggs H. D., " Gas Production Operations", OGCI Publications, Tulsa,

Oklahoma, 1984.21. Gas Engineers Handbook, Fuel Gas Engineering Practice, Industrial Press Inc.,

New York, 1969.

147

r'