TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015 ANALIZA CENA ZIDARSKI RADOVI: 1. MALTERISANJE ZIDOVA CETVRTOG SPRATA -PRENOS KRANOM Šifra normativa: 126004 - Građevinske norme -Materijal: KRECNI MALTER 1:3 u II sloja : 0.028m 3 1:3 /m 2 zida -Radnici: RV (prvi sloj-grubo malterisanje): 0.28 Nč/ m 2 zida * 165 din/ Nč = 46.2 din/ m 2 zida RII (prvi sloj-grubo malterisanje): 0.06 Nč/ m 2 zida * 110 din/ Nč = 6.6 din/ m 2 zida RV (drugi sloj-fino malterisanje): 0.32 Nč/ m 2 zida * 165 din/ Nč = 52.8 din/ m 2 zida RII (drugi sloj-fino malterisanje): 0.06 Nč/ m 2 zida * 110 din/ Nč = 6.6 din/ m 2 zida RII (transport maltera): 0.091 Nč/ m 2 zida * 110 din/ Nč = 10.01 din/ m 2 zida Σ=R = 122.21 din/ m 2 zida 1.1 MASINSKO SPRAVLJANJE KRECNOG MALTERA 1:3 (nesejani)- BUBNJAROM OD 50L Šifra normativa: 120026 – Građevinske norme napomena: količine materijala za sejani i nesejani malter suiste -Materijal: Krec 0.311 m 3 kr / m 3 1:3 *1455 din/ m 3 kr * = 452.505 din/ m 3 1:3 Pesak 0.93 m 3 p / m 3 1:3 * 420 din/ m 3 p = 390.6 din/ m 3 1:3 Voda 0.18 m 3 v / m 3 1:3 * 40 din/ m 3 v = 7.2 din/ m 3 1:3 Σ=M=850.305din/m 3 1:3 1._______________________, 2. _______________________, 3. _______________________,

ANALIZA CENA GRADJEVINSKIH RADOVA

Embed Size (px)

DESCRIPTION

ANALIZA CENA GRADJEVINSKIH RADOVA

Citation preview

Page 1: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

ANALIZA CENA

ZIDARSKI RADOVI:

1. MALTERISANJE ZIDOVA CETVRTOG SPRATA -PRENOS KRANOMŠifra normativa: 126004 - Građevinske norme

-Materijal: KRECNI MALTER 1:3 u II sloja : 0.028m31:3/m2

zida

-Radnici: RV (prvi sloj-grubo malterisanje): 0.28 Nč/ m2zida * 165 din/ Nč = 46.2 din/ m2

zida

RII (prvi sloj-grubo malterisanje): 0.06 Nč/ m2zida * 110 din/ Nč = 6.6 din/ m2

zida

RV (drugi sloj-fino malterisanje): 0.32 Nč/ m2zida * 165 din/ Nč = 52.8 din/ m2

zida

RII (drugi sloj-fino malterisanje): 0.06 Nč/ m2zida * 110 din/ Nč = 6.6 din/ m2

zida

RII (transport maltera): 0.091 Nč/ m2zida * 110 din/ Nč = 10.01 din/ m2

zida

Σ=R = 122.21 din/ m2zida

1.1 MASINSKO SPRAVLJANJE KRECNOG MALTERA 1:3 (nesejani)-BUBNJAROM OD 50L

Šifra normativa: 120026 – Građevinske norme napomena: količine materijala za sejani i nesejani malter suiste

-Materijal: Krec 0.311 m3kr/ m3

1:3 *1455 din/ m3kr * = 452.505 din/ m3

1:3

Pesak 0.93 m3p/ m3

1:3 * 420 din/ m3p = 390.6 din/ m3

1:3

Voda 0.18 m3v/ m3

1:3 * 40 din/ m3v = 7.2 din/ m3

1:3

Σ=M=850.305din/m31:3

-Radnici: RII (spravljanje maltera): 2.310 Nč/ m31:3 * 110 din/ Nč = 254.1 din/ m3

1:3

Σ=R=254.10 din/ m31:3

C=M+Rx(0.5+1)= 850.305din/m31:3 + 254.10.675 din/ m3

1:3*(0.5+1)=1231.45 din/ m 3 1:3

1.2 GASENJE KRECA Šifra normativa: 120001 -Materijal: Pecen krec(krec u komadima) 450,0kg/ m3

kr* 2.6 din/kg = 1170 din/ m3kr

Voda 3 m3v/ m3

kr * 40din/ m3v = 120 din/ m3

kr

Σ=M= 1290 din/ m3kr

-Radnici: RII (gasenje kreca) 2.90 Nč/ m3kr* 110 din/ Nč = 319 din/ m3

kr

Σ=R=110 din/ m3kr

C=M+Rx(0.5+1)=1290 din/ m3kr +110 din/ m3

kr *(0.5+1)=1455 din/ m3kr

UKUPNA CENA MATERIJALA I IZRADE

1._______________________, 2. _______________________, 3. _______________________,

Page 2: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

C=M+Rx(0.5+1)= 0.028m31:3/m2

zida*1231.45 din/ m 3 1:3 +122.21 din/ m2zida*(0.5+1)=

C=217.79 din/ m2zida

CENA TRANSPORTA-Transport materijala za spravljanje maltera: deponije peska I kreca se nalaze kod mesalice, sto zanaci da je cena transporta jednaka nuli

UKUPNA CENA ZA MALTERISANJE 1m 2 ZIDA

C = 217.79 din/ m2zida

UKUPNA CENA MALTERISANJA:

Cu =217.79 din/m 2 zida * 611.77 m 2 = 133237.38 din

DEFINISANJE RADNE BRIGADE

-MALTERISANJE ZIDOVA:RV (prvi sloj-grubo malterisanje): 0.28Nč/ m2

zida RII (prvi sloj-grubo malterisanje): 0.06 Nč/ m2

zida

RV (drugi sloj-fino malterisanje): 0.32 Nč/ m2zida

RII (drugi sloj-fino malterisanje): 0.06 Nč/ m2zida

RII (transport maltera): 0.091 Nč/ m2zida

-SPRAVLJANJE MALTERA:RII (spravljanje maltera): 2.310 Nč/ m3

1:3 * 0.028m31:3/m2

zida = 0.065 Nč/ m2zida

- GAŠENJE KRECA: R II 2.90 Nč/ m3

kr * 0.311 m3kr/ m3

1:3 * 0.028m31:3/m2

zida = 0.025 Nč/ m2zida

REKAPITULACIJA:

R V (Nč) ………………………………………………………………………………….. 0.633 Nč/ m2zida

R II (Nč) ……………………………………………………………………………….. 0.301 Nč/ m2zida

1._______________________, 2. _______________________, 3. _______________________,

Page 3: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

Dimenzionisanje radne brigade – malterisanje zidova IV sprata:

Količina rada(m2)

radnikNorma

Casa(m2)Nč

Radnika dana

brigada dana

1 2 3 4=1*3 5=4/n 6 7

611.77 R V 0.633 387.25 48.41 7 7

R II 0.301 184.14 23.02 4

n-broj radnih sati u toku dana(8h)

KOLIČINA OSNOVNOG MATERIJALA ZA 1 M 2 ZIDA :

Pesak: 0.93 m3

p/ m31:3 * 0.028 m3

1:3/m2zida = 0.026 m3

p / m2zida

Pečeni kreč (kreč u komadima): 450 kg/ m3

kr * 0.311 m3kr/ m3

1:3 * 0.028 m31:3/m2

zida = 3.92 m3p / m2

zida

Voda: 0.18 m3

v/ m31:3 * 0.028 m3

1:3/m2zida + 3 m3

v/ m3kr *0.311 m3

kr/ m31:3 * 0.028 m3

1:3/m2zida = 0.031

m3v / m2

zid

BETONSKI RADOVI

2. BETONIRANJE ZIDNIH PLATNA ARMIRANIM BETONOM, MB 30, U SVEMU PREMA PROJEKTU, STATICKOM PRORACUNU I DETALJIMA. KOMBINOVANI PRENOS KRAN-KIBLOMGN 400-410 G KOLIČINA IZ PREDMERA : 186.36 m 2 platna -Materijal: OBICAN BETON: 0.2525 m3

B/m2p

VODA : 0.0101 m3V/m2

p

-Radnici: RV (ugradjivanje betona): 0.396 Nč/ m2p * 165 din/ Nč = 65.34 din/ m2

p

RIII (ugradjivanje betona): 0.396 Nč/ m2p * 130 din/ Nč = 51.48 din/ m2

p

1._______________________, 2. _______________________, 3. _______________________,

Page 4: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

RII (nega betona): 0.016 Nč/ m2P * 110 din/ Nč = 1.76 din/ m2

P

RII (prenos betona): 0.122 Nč/ m2p * 110 din/ Nč = 13.42 din/ m2

p

Σ=R = 132.0 din/ m2P

2.1 MASINSKO SPRAVLJANJE BETONA MB 30(GRANULISANI AGREGAT) BUBNJAROM OD 50L

GN 400-304A

-Materijal: Cement 330 kg/ m3b *15 din/ kg = 4950 din/ m3

b

Agregat 1.250 m3A/ m3

b * 1200 din/ m3A = 1500 din/ m3

b

Voda 0.19 m3v/ m3

b * 40 din/ m3v = 7.6 din/ m3

b

Σ=M=6457.6 din/m3b

-Radnici: RII (spravljanje betona): 1.860 Nč/ m3b * 110 din/ Nč = 204.6 din/ m3

b

RII (doziranje): 0.220 Nč/ m3b * 110 din/ Nč = 24.2 din/ m3

b

RII (prenos cementa): 0.396 Nč/ m3b * 110din/ Nč = 43.56 din/ m3

b

Σ=R=272.36 din/ m3b

C=M+Rx(0.5+1)= 6457.6 din/m3b + 272.36 din/ m3

b *(0.5+1)=6866.14 din/ m 3 b

TRANSPORT: Deponije materijala se nalaze pored mesalice

UKUPNA CENA BETONIRANJA 1m 2 :

C=M+Rx(0.5+1)=0.0101 m3V/m2

p *40 din/ m3V +0.2525 m3

B/m2p*6866.14

din/m3b + 132.0 din/ m2

P*(0.5+1)= 1932.10 din/ m 2 P

UKUPNA CENA BETONSKIH RADOVA

Cu= 1932.10 din/ m 2 P * 186.36 m 2 P 360 066.15 din

DEFINISANJE RADNE BRIGADE

-BETONIRANJE:RV (ugradjivanje betona): 0.396 Nč/ m2

p RIII (ugradjivanje betona): 0.396 Nč/ m2

p RII (nega betona): 0.016 Nč/ m2

P RII (prenos betona): 0.122 Nč/ m2

p

-SPRAVLJANJE BETONA:RII (spravljanje betona): 1.860 Nč/ m3

b *0.2525 m3B/m2

p=0.469 Nč/ m2p

1._______________________, 2. _______________________, 3. _______________________,

Page 5: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

RII (doziranje): 0.220 Nč/ m3b *0.2525 m3

B/m2p=0.055 Nč/ m2

p RII (prenos cementa): 0.396 Nč/ m3

b *0.2525 m3B/m2

p=0.099 Nč/ m2p

REKAPITULACIJA:

R V (Nč) ………………………………………………………………………………….. 0.396 Nč/ m2P

R III (Nč) ……………………………………………………………………………….. 0.396 Nč/ m2P

R II (Nč) ………………………………………………….…………………………….. 0.761 Nč/ m2P

Dimenzionisanje radne brigade :

Količina rada(m2)

radnikNorma

Casa(m2)Nč

Radnika dana

brigada dana

1 2 3 4=1*3 5=4/n 6 7

186.36 R II 0.761 141.8 17.62 9 2

R V 0.396 73.8 9.23 5

R III 0.396 73.8 9.23 5

n-broj radnih sati u toku dana(8h)

Betoniranje prizemlja se izvodi na dva fronta

KOLIČINA OSNOVNOG MATERIJALA ZA 1 M 2 :

Cement: 330 kg/ m3

b * 0.2525 m3B/m2

p = 0.026 m3c / m2

p

Agregat:1.250 m3

A/ m3b * 0.2525 m3

B/m2p = 0.315 m3

A/ m2p

Voda: 0.19 m3

v/ m3b *0.2525 m3

B/m2p= 0.048 m3

v/ m2p

ARMIRAČKI RADOVI:

3. MAŠINSKO SEČENJE, ISPRAVLJANJE, SAVIJANJE, RUČNO POSTAVLJANJE I VEZIVANJE ARMATURE Ø14 (GN-400-108)

1._______________________, 2. _______________________, 3. _______________________,

Page 6: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

Količina iz predmera 19.07 m3betona i pretpostavljamo da ima 100 kgarmature/m3

betona

-Materijal: Armatura : 1 kgarmature * 1,06 kgčelika/ kgarmature * 85 din/ kgčelika = 90.10 din/ kgarmature

Paljena žica : 0.0035 kgžice/kgarmature x 140 din/ kgžice = 0.490 din/ kgarmature

Σ=R = 90.59 din/ kgarmature

-Izrada:Sečenje I ispravljanje: AIV : 0.0007 Nč/ kgarmature * 150 din/ Nč = 0.105 din/kgarmature

AIII : 0.0022 Nč/ kgarmature * 130 din/ Nč = 0.286 din/kgarmature

Savijanje: AIV : 0.0007 Nč/ kgarmature * 150 din/ Nč = 0.105 din/kgarmature

AIII : 0.0022 Nč/ kgarmature * 130 din/ Nč = 0.286 din/kgarmature

Postavljanje I vezivanje: AIV : 0.0120 Nč/ kgarmature * 150 din/ Nč = 1.800 din/kgarmature

AIII : 0.0120 Nč/ kgarmature * 130 din/ Nč = 1.560 din/kgarmature

Prenos: AII : 0.0001 Nč/ kgarmature * 110 din/ Nč = 0.011 din/kgarmature

Σ=R = 4.153 din/ kgarmature

UKUPNA CENA ARMIRACKIH RADOVA

C=M + R(1+0.5) = 90.59 din/ kgarmature + 4.153 din/ m3betona*1.5 =

C=96.83 din/ kgarmature

Cu= 96.83 din/ kgarmature * 100 kgarmature/m3betona *19.07 m3

betona = 183701.31 din

DEFINISANJE RANDE BRIGADE:-Izrada:Sečenje I ispravljanje: AIV : 0.0007 Nč/ kgarmature

AIII : 0.0022 Nč/ kgarmature

Savijanje: AIV : 0.0007 Nč/ kgarmature

AIII : 0.0022 Nč/ kgarmature

Postavljanje I vezivanje: AIV : 0.0120 Nč/ kgarmature

1._______________________, 2. _______________________, 3. _______________________,

Page 7: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

AIII : 0.0120 Nč/ kgarmature

Prenos: AII : 0.0001 Nč/ kgarmature

REKAPITULACIJA:

R IV (Nč) …………………………………………………………………………………………….0.0134 Nc/ m3betona

R III (Nč) ……………………………………………………………………………………………..0.0164 Nc/ m3betona

R II (Nč) ………………………………………………….……………………………………..………0.0001 Nc/ m3betona

Dimenzionisanje radne brigade – armirački radovi u prizemlju:

Količina rada[kg]

RadnikNorma

Casa[m3]Nč

Radnika dana

brigada dana

1 2 3 4=1*3 5=4/n 6 7

1907

R III 0.0164 31.27 3.91 4

1R IV 0.0134 25.55 3.19 4

R II 0.0001 0.191 0.024 1

n-broj radnih sati u toku dana(8h)

KOLIČINE OSNOVNOG MATERIJALA ZA 1 kg ARMATURE :

Betonski čelik ......................................................................... 1.06 kgčelika/kg armature

TESARSKI RADOVI:

4. OPLATA MEĐUSPRATNE KONSTRUKCIJE

-ukupna količina oplate : 303,14 m2

Materijal : GN 601-203A

Za izradu :

daska 24 mm.............. 0,004m3d/m2

opl * 9650 din/m3d = 38,6 din/m2

opl

gredice (m3)……….. 0,002m3g/m2

opl * 10000 din/m3g = 20 din/m2

opl

ekseri (kg)………………… 0,06kg/m2opl * 30 din/kg = 1.8 din/m2

opl

Ukupno : 60,4 din/m 2 opl

1._______________________, 2. _______________________, 3. _______________________,

Page 8: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

4.1 IZRADA OPLATE

T V : 0,2 Nč/m2opl * 165din/Nč = 33 din/m2opl

T III : 0,2 Nč/m2opl * 130din/Nč = 26 din/m2opl

Montaža :

T V: 0,23 Nč/m2opl * 165din/Nč = 37,95 din/m2opl

T III: 0,23 Nč/m2opl * 130din/Nč = 29,9 din/m2opl

Demontaža :

T II : 0,15 Nč/m2opl * 110din/Nč = 16,5 din/m2opl

Čišćenje :

R II : 0,08 Nč/m2opl * 110din/Nč = 8,8 din/m2opl

Ukupno : 152,15 din/m 2 opl

CENA MATERIJALA I IZRADE

C = M + R(0.5+1) = 60,4 din/m2opl + 152,15 din/m2opl * 1.5 = 288.625 din/m 2 opl

2. TRANSPORT MATERIJALA ZA IZRADU OPLATE

Materijal: GN 900.101 (6)

Daske I letve

Utovar : RII : 0,36 Nč/m3gradje * 110din/Nč = 39,6 din/m3gradje

Istovar :RII : 0,13 Nč/m3gradje * 110din/Nč = 14,3 din/m3gradje

Prenos na 10m :RII : 0,47 Nč/m3gradje * 110din/Nč = 51,7 din/m3gradje * 2

Ukupno : 157,3 din/m 3 gradje

C = 157,3 din/m3gradje * 1.5 = 235.95din/m 3 gradje

0,03 m3daske/m2opl + 0,02 m3gred/m2opl = 0,05 m3gradje/m2oplate

1._______________________, 2. _______________________, 3. _______________________,

Page 9: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

0,05 m3gradje/m2opl * 235.95 din/m3gradje = 11.79 din/m2oplate

Ekseri :

Materijal GN 900.101 (2)

UtovarRII : 0,550 Nč/t * 110din/Nč = 60,5 din/t

IstovarRII : 0,120 Nč/t * 110din/Nč = 13,2 din/t

Prenos na 10mRII : 0,66 Nč/t * 110din/Nč = 72,6 din/t * 2

Ukupno : 218,9 din/t

C = 218,9 din/t * (0.5+1) =328.35 din/t – eksera

0,06kg /m2opl1000kg / t

* 328.35 din/t = 0,019 din/m2opl

Ukupna cena transporta oplate : C = 11.79 + 0,019 = 11.81 din/m2opl

UKUPNA CENA OPLATE :C = 288.625 din/m2opl + 11.81 din/m2opl = 300.435 din/m 2 opl

3. Definisanje radne brigade :

Izrada, montaža I transport :T V : 0,2 + 0,23 = 0,43 Nč/m2opl

T III : 0,2 + 0,23 = 0,43 Nč/m2opl

R II : 1,43 Nč/m3 * 0,05 m3/m2opl + 1,99/1000 Nč/kg * 0,06 kg/m2opl = 0,072 Nč/m2opl

Demontaža, čišćenje I transport :

T II : 0,15 Nč/m2opl

R II : 0,08 Nč/m2opl + 0,072 Nč/m2opl = 0,152 Nč/m2opl

1._______________________, 2. _______________________, 3. _______________________,

Page 10: ANALIZA CENA GRADJEVINSKIH RADOVA

TEHNOLOGIJA I ORGANIZACIJA GRAĐENJA 1 –KONSTRUKCIJE- 2014-2015

Količina rada

[m2]

RadnikNc

m2Nč

Radnih dana

Brigada Dana

1 2 3 4=1x3 5=4/n 6 7

303,14

T V 0,43 130,35 16,29 6

3T III 0,43 130,35 16,29 6

R II 0,072 21,83 2,73 1

303,14

T III 0,15 45,47 5,68 3

2R II 0,152 46,08 5,76 3

n – broj radnih časova u jednom danu = 8h

KOLIČINE OSNOVNOG MATERIJALA PO M 2 OPLATE:

-Daska 24mm : 0,004 m3daske/m2oplate

-Gredice (m3) : 0,002 m3gred/m2oplate

-Ekseri (kg) : 0,06 kg/m2oplate

1._______________________, 2. _______________________, 3. _______________________,