Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
National Defense Industrial Association
Integrated Program Management Division
An Industry Practice Guide for Agile on Earned Value Management Programs
March 11, 2016
Version 1
National Defense Industrial Association (NDIA) 2111 Wilson Blvd., Suite 400
Arlington, VA 22201 (703) 522-1820
Fax (703) 522-1885 www.ndia.org
© 2016 National Defense Industrial Association, Integrated Program Management Division (IPMD)
Permission to copy and distribute this document is hereby granted provided that this notice is retained on all copies, that copies are not altered, and that the NDIA IPMD is credited when the material is used to form other copyrighted
documents.
© 2016 NDIA IPMD i
Table of Contents
1 Introduction: EVM for Agile Programs .................................................................................. 1 1.1 Purpose of the Guide .................................................................................................. 1 1.2 Definitions ................................................................................................................... 2
2 Agile Program Planning ....................................................................................................... 3 2.1 Product Planning ........................................................................................................ 3 2.2 Release Planning ........................................................................................................ 3 2.3 Sprint Planning ........................................................................................................... 4 2.4 Daily Planning – Scrum Standup................................................................................. 5
3 Agile EVM Performance Measurement Baseline (PMB) ....................................................... 6 3.1 The Work Breakdown Structure (WBS) ....................................................................... 6 3.2 Integrated Master Plan (IMP) ...................................................................................... 8 3.3 Integrated Master Schedule (IMS) .............................................................................. 9 3.4 Implications of the DCMA Health Metrics Generated from the IMS ........................... 12 3.5 Freeze Period Considerations ................................................................................... 13
4 Structures for Performance Metrics .................................................................................... 14 4.1 Control Account Plan ................................................................................................ 14 4.2 Aligning Agile Progress Metrics with Earned Value Reporting Levels ....................... 14 4.3 Computing & Reporting Earned Value Performance ................................................. 16 4.4 When Do You Take Credit for A Story? ..................................................................... 17 4.5 Feature Cost/Risk to be Considered When Establishing Baseline ............................. 18 4.6 Variance from the Baseline: Examples with Agile EVM ............................................. 18 4.7 How to Use Agile Metrics to Forecast ETC/EAC ....................................................... 19
5 Managing Baseline Change on Agile Programs ................................................................. 21 5.1 Baseline Change Parameters ................................................................................... 21 5.2 Baseline Assumptions ............................................................................................... 21 5.3 Baseline Change Scenarios ...................................................................................... 22 5.4 Forecast Change Scenarios ...................................................................................... 25 5.5 Agile/EV Recommendations ..................................................................................... 26
Appendix A - EVM/Agile Data Dictionary ................................................................................... 28 EVM Agile Data Dictionary ................................................................................................. 29 Agile Data Dictionary .......................................................................................................... 35 EVM Data Dictionary .......................................................................................................... 39
Appendix B - Examples of Agile EVM Progress Tracking Charts .............................................. 49
Appendix C - References .......................................................................................................... 53
Appendix D - Agile/EV Guide Contributors ................................................................................ 55
© 2016 NDIA IPMD ii
Abbreviations and Acronyms
The abbreviations and acronyms listed here are used in the main body of the guide. Additional abbreviations and acronyms are included in the appendices. ACWP Actual Cost of Work Performed AIS Automated Information System BAC Budget at Completion BCR Baseline Change Request BCWP Budgeted Cost for Work Performed CA Control Account CAM Control Account Manager CAP Control Account Plan CBB Contract Budget Baseline CDRL Contract Data Requirements List CO Contracting Officer CSCI Computer Software Configuration Item CPI Cost Performance Index DCMA Defense Contract Management Agency DoD Department of Defense EAC Estimate at Completion ETC Estimate to Complete EVM Earned Value Management EVMS Earned Value Management System GUI Graphical User Interface HW Hardware IMP Integrated Master Plan IMS Integrated Master Schedule IPT Integrated Product Team MR Management Reserve MVP Minimum Viable Product PC Percent Complete PMB Performance Measurement Baseline PO Product Owner POP Period of Performance PP Planning Package
© 2016 NDIA IPMD iii
QBD Quantifiable Backup Data SAFe® Scaled Agile Framework® SLPP Summary Level Planning Package SP Story Points SPI Schedule Performance Index STD Standard SW Software TAB Total Allocated Budget UB Undistributed Budget WBS Work Breakdown Structure WP Work Package
© 2016 NDIA IPMD 1
1 Introduction: EVM for Agile Programs The growing importance of quickly and affordably delivering software intensive systems requires programs to swiftly react to changing demands of the operational environment and has led to an increased focus on capability-based planning and iterative product development. Capability-based planning and execution focuses on delivering the highest priority system Features to the stakeholders as quickly and affordably as possible. To meet this demand, Program Managers need a planning and execution method that can quickly and efficiently react to changes across all levels of the program. Agile has emerged as the leading industry software development methodology, and has seen growing adoption across the DoD and other federal agencies. Agile implements the needed method by focusing on small, frequent capability releases, working software through demonstration of capabilities, responding rapidly to changes in operations, technology, and budgets, and actively involving users throughout development to ensure high operational value.1 These emerging needs across program levels require continual prioritization, development and delivery of major system capabilities to address the requirements needed to meet emerging operational demands. Changes at the detailed program level involve continual adjustment of implementation processes and technical approaches to meet cost, schedule and quality requirements. Agile development techniques prove to be effective in meeting these demands. The demand for responsiveness and efficiency extends to all aspects of system development and delivery, starting with negotiation of the contract, applicable Contract Data Requirements Lists (CDRLs), and effective implementation of Earned Value Management (EVM). The EVM system must support these changing demands while enabling cost and schedule performance measurement against the Performance Measurement Baseline (PMB). This need creates challenges to applying EVM to Agile development programs. This guide is created to address these challenges. Agile development methods provide a discipline process for defining work and tracking progress of this work against planned cost and schedule. Integrating Agile performance data with the EVM system provides a vertical integrated view of cost, schedule, and scope, from development activities to program performance measures.
1.1 Purpose of the Guide This Guide provides practices drawn from lessons learned by multiple aerospace and defense firms and their software development activities. This Guide provides a recommended structure for the Work Breakdown Structure (WBS), Integrated Master Plan (IMP) and Integrated Master Schedule (IMS) content, Control Accounts (CA), Work Packages (WP), and Planning Packages (PP) to be used on an Agile development program. Program performance measurement in an Agile iterative development framework is defined along with Baseline change control. Appendix A is an EVM Agile Data Dictionary, with both Agile and EVM terms and definitions. Appendix B provides examples of EVM Agile progress report charts. This Guide assumes a basic understanding of Earned Value and Agile development techniques. For introductory materials, see Appendix C, References.
1 Defense Agile Acquisition Guide, Pete Modigliani and Su Chang, Mitre Corporation, March 2014
© 2016 NDIA IPMD 2
1.2 Definitions Customer The government, commercial organization, or other entity for which one
or more program or projects are being executed. Typically, the external customer is the Government or a prime Contractor.
Project Involves planned effort to achieve an outcome, the progress toward which is directly measurable. A project will have an established scope, schedule and budget.
Program Group of related projects managed in a coordinated way to obtain benefits and control unavailable from managing them individually. This Guide uses the term “program” rather than “project”, as “program” is often referenced within an Earned Value Management context. However, the Guide is generally applicable to both programs and projects.
© 2016 NDIA IPMD 3
2 Agile Program Planning Work planning in Agile development is driven by prioritization of business value defined by the customer. This planning process focuses on the value of the functionality or capabilities needed by the customer, in the order defined in the Product Roadmap. This value is delivered through the iterative and incremental decomposition of the work of the product’s functionality. Epics or Capabilities, hereafter known as Epics/Capabilities, contain product Features decomposed into User Stories. Agile Planning is performed by the entire development Team using the needed Epics/Capabilities, Features and Stories. Therefore planning is product based, and done through iterative and incremental decomposition of Capabilities/Epics and subsequently Features into smaller components of product functionality.
2.1 Product Planning Product Planning produces a Product Roadmap for the time-phased product delivery plan. This plan is the technical basis of the Earned Value Management Performance Measurement Baseline (PMB). Every Scrum team (development team) has a Product Owner (PO), representing the customer's value. In programs with multiple Teams, there may also be a chief PO that coordinates across program POs and their teams. During Product Planning, the PO and customer representatives specify and prioritize the initial set of system capabilities needed to deliver the contractually required system, also known as the Minimum Viable Product (MVP). System capabilities are grouped into builds or capability releases, thus forming the Product Roadmap. Product Planning starting with Contract Award establishes the Cadence Release cycle, Product Roadmap, Product Backlog, and Minimum Viable Product. Product planning is performed throughout the life of the program to refine and update the Product Backlog. The PO, with Customer representatives, is responsible for managing the product planning activities. Program leadership assigns the PO, and this can be a Control Account Manager (CAM). The CAM(s) use size and productivity estimates from Product Planning along with the staffing plan to establish the time-phased budgets that comprise the initial performance measurement baseline. Product Planning defines the CAs and Planning Packages and their networking at a high level; during release planning, the Planning Packages for that release are decomposed into Work Packages. Ongoing customer involvement, regular demonstrations of Capability, and granular Agile Quantifiable Backup Data (QBD) or other supplemental information reference this baseline and define progress; to learn more about the assumptions and approach to managing change of a Baseline on an Agile program, see Section 5, Managing Baseline Change on Agile Programs. Section 5 also addresses where planned work, including MVP, is not completed within a planned release.
2.2 Release Planning Release planning is a process in which the team periodically maps the Product Backlog with its Epics/Capabilities to Features and candidate Stories that are to be delivered in a Sprint. Assigning the Stories to a Sprint, based on Customer priority, defines what the product must do and when the functionality will be delivered within a Release. The Product Backlog, Product Roadmap, and Minimum Viable Product functionality are inputs to the Release Plan. This is a process similar to creating an Integrated Master Schedule (IMS) from an Integrated Master Plan (IMP). It is within release planning and as part of the Integrated Master Schedule planning that Features are assigned to Work Packages and Planning Packages.
© 2016 NDIA IPMD 4
Each release planning cycle should be chosen to coincide with Rolling Wave planning used in an EVM program as they are similar activities.2 Prior to each Release or Rolling Wave planning cycle, the PO (or chief PO on large-scale Agile programs) conducts release planning to develop the cadenced release plan. The release plan is the set of Features that have been refined from Epics/Capabilities on the Product Roadmap and have been selected to be implemented within the Release period. The Release planning period is expressed as a number of Sprints. The Release period of performance aligns with the start of the first Sprint in the Release and the end of the last Sprint in the Release. Release planning is completed prior to the start of each Cadence Release period; the Rolling Wave planning cycle is adjusted to be completed synchronously with each Cadence Release. Prior to the release planning meeting, the person with content authority, e.g. chief PO or PO, communicates the next highest priority build capabilities for the upcoming Release period. The POs decompose build Epics/Capabilities into a set of Features that will implement the requested build capabilities. Depending on program scale, the chief PO or PO facilitates the release planning meeting. During this meeting, each Feature is reviewed in order of priority and a set of Features for the Release is chosen based on Feature priority, Feature size, productivity, and available staff. On large-scale programs with multiple Scrum teams, the release planning meeting includes coordination of Feature planning among the various POs to achieve a release plan that supports the minimum viable product deliveries and overall goals of the program. The CAM(s) use the output of release planning to implement the plan. During Release planning, Work Packages specify scope via the Features selected at release planning. The CAM, working in collaboration with PO(s), creates the Work Packages. Work Packages may align with individual Features or with logical groups of related Features. There may be one or more Features associated with a Work Package within a Control Account (CA). The budget of each Work Package is determined from assigned Scrum team labor costs, Feature size estimates and estimated productivity of the identified Scrum teams. Release Planning is the activity most closely related to developing the Integrated Master Schedule, and subsequent Rolling Wave planning represented in the IMS.
2.3 Sprint Planning Sprint planning is collaboration between the Scrum Team and the Product Owner to determine what Features and Stories will be developed in the coming Sprint. The Scrum Master ensures that the Sprint Planning event takes place and that attendees understand the purpose of the planning session. Sprint planning is the process whereby Scrum teams commit to the completion of specific Stories within the current time boxed (fixed time period) Sprint and confirms the criteria for work completion. Features selected from the planning process are decomposed into Stories in preparation for Sprint Execution. These Stories are prioritized by the Product Owner and the Agile Team. The Sprint Planning process is completed before any work starts on the Sprint. During this process, Stories are sized and decomposed into Story Tasks for implementation during the Sprint. The Scrum team’s list of Story Tasks from that Sprint are placed on the Sprint Backlog. The Scrum Master is responsible for facilitating Sprint Planning.
2 The Agile and Earned Value Management: A Program Manager’s Desk Guide, OUSD AT&L (PARCA), 03 March 2016, notes the equivalency of Cadence Release and rolling wave planning.
© 2016 NDIA IPMD 5
During the Sprint, as Stories are completed, progress is determined by the completion status of the planned number and size of Stories for the Feature. The results of Sprint planning in terms of the number and size of Stories planned for the Sprint, and therefore completed versus total planned Story Points in the Sprint, is reflected in the IMS through the QBD for the Stories and Feature. Sprint planning connects to the earned value process by finalizing the specific Stories to be implemented in the Sprint that will contribute to completion of the corresponding Feature.
2.4 Daily Planning – Scrum Standup During the Scrum standup meeting, the Team reviews development activities in the Sprint for alignment with the Sprint Plan to confirm progress of the Team’s commitment to the Sprint goals. During the daily Scrum each team member reports:
1. What they did the previous day. 2. What they plan to do today. 3. Roadblocks that are impeding their progress.
Product completion status is reviewed on a daily basis and updated to provide program performance measurement based on the number of Story Points associated with completed Stories compared to the planned Story Points for the Sprint. The tiered Agile planning levels are shown in Table 1. The hierarchy of the Planning Artifacts is described in more detail in Section 3.2. The Work Breakdown Structure, used for Agile programs, is described in more detail in section 3.1.
Table 1: Agile planning levels and their relationship to EVM processes. Sprint and daily planning
contribute to QBD that supports EVM reporting at higher levels.
© 2016 NDIA IPMD 6
3 Agile EVM Performance Measurement Baseline (PMB)
3.1 The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS) defines the program in terms of hierarchically-related, product-oriented elements. The WBS is a product-oriented family tree composed of hardware, services, data, and facilities that displays and defines the product to be developed during the acquisition.3 The WBS represents all scope and work being performed on a program, both level of effort (such as program management) and discrete deliverables. For programs using Agile methodologies, the WBS should be the basis for the Product Backlog. This structure focuses on completed products that provide measurable customer value implemented in Epics and Capabilities. The Agile development Sprints and Cadence Releases, with resulting Features and Stories that deliver products, are the basis for the Performance Measurement Baseline. However this level of detail should not appear in the contract WBS, since these items emerge in the normal work processes of Agile. Therefore, it is key for successful Agile EVM application to establish a product based WBS. MIL-STD-881 provides product-based WBS templates for a variety of systems, which can be applied to an Agile Epics/Capabilities-based structure. While these terms of product hierarchy are fully defined in Appendix A, the EVM/Agile Data Dictionary, Figure 1 illustrates the two separate hierarchies used in Agile, for Product, applicable to WBS, and for Time. Separate Product and Time hierarchies allow work to be planned by periodically assigning appropriately-sized products into selected Releases or Sprints.
Figure 1: Hierarchy of Agile Products and Agile Time Boxed Elements and Relationships illustrates the
two hierarchies in Agile: for Product, based on WBS, and for Time, the basis for PMB.
The WBS defines Epics/Capabilities or Products at the highest summary levels; these are later decomposed into Features and ultimately to Stories. The program contract period of performance is broken down into “Cadence Releases”, which in Agile are strictly time boxed or calendar-driven, and further broken down into predetermined time boxed, fixed cadence Sprints 3 MIL-STD-881-C
© 2016 NDIA IPMD 7
of typically 2 weeks (1-6 week Sprint durations have been seen also), selected to best work for the program and company. Note that “Sprint” is often used synonymously with “Iteration”; since “Sprint” is a commonly used term beyond a single Agile method such as Scrum, “Sprint” will be used here for the 1-6 week time boxed cadence. While there is no single standard template for a WBS, MIL-STD-881 is a common reference used in DoD systems and automated information systems. The WBS outlined in MIL-STD-881 Appendix K is selected to create a template that illustrates the application of Agile development techniques. MIL-STD-881 allows considerable tailoring for specific programs. There are options for what defines the Agile product beyond the necessary Epics/Capabilities, as described in Table 2 for a software product (e.g. Automated Information System). Table 2 does not attempt to provide a comprehensive picture of the WBS, but instead focuses on the core Agile developed software products.
WBS Task Name Notes
1 Automated Information System (AIS)
1.1 Automated Information System Prime Mission Product Release/Increment X
Multiple elements at this level would be appropriate if the customer views major deliveries as independent products and desires a WBS organized around them (e.g., the deliveries are viewed as separate projects). From an Agile perspective the important point is that elements at this level have no relationship with the Agile cadence “release”.
1.1.1 Custom Applications SW 1..n
1.1.1.2 Subsystem SW CSCI 1..n
Appropriate if Computer Software Configuration Items (CSCIs) are viewed as key products (with Epics/Capabilities contained within them); may be at L4 or not present at all (as explained below)
1.1.1.2 or 1.1.1.2.1
Agile Epic/Capability 1..n
Would occur at Level 4 or 5. When Epics/Capabilities are the primary organizing method for products then these would be at L4 (preferred). Alternatively, Epics/Capabilities could be viewed as products within CSCIs. Epics/Capabilities are often preferred over CSCIs in the WBS, as Epics/Capabilities are organized around system functionality (value add, end user products) while CSCIs are organized around the internal architectural structure of the system, which doesn’t necessarily align directly with usable functionality and customer value.
Table 2: Example WBS, indicating WBS Number, Task Name, and comments on how best to apply in an Agile EVM program.
Products described by Features and Stories below the Epics/Capabilities will be described in later sections in the context of the IMS and performance management. Another example WBS shown in Table 3, derived from MIL-STD-881 Appendix B on Electronic Systems, indicates how Agile is incorporated into a program involving both software and
© 2016 NDIA IPMD 8
hardware development. Again, Table 3 does not attempt to provide a comprehensive picture of the WBS; instead it focuses on the core Agile developed products.
WBS Task Name Notes
1.0 Avionics System
1.1 Prime Mission Product
1.1.1 (L3) and/or
Product 1 . . n For products that are hardware only or hardware and software combined as the key deliverables
1.1.1 (L3)
Software Product 1 . . n
For software applications that are viewed as key products/deliverables
1.1.1.X (L4) and
Agile Epic/Capability 1 . . n
When Epics/Capabilities are the primary organizing method for products then these would be at L4. Epics/Capabilities are often preferred over CSCIs/Subsystems in the WBS, as Epics/Capabilities are organized around system functionality (value add, end user products) while CSCIs/Subsystems are organized around the internal architectural structure of the system, which doesn’t necessarily align directly with usable functionality and customer value. Each Capability L4 WBS Includes all systems, and development and integration of each Capability on its own.
1.1.1.Y (L4)
Agile Epic/Capability Systems, Integration and Test
Includes all systems, integration and test activities (in a host environment) associated with PMP Software product (L4). Also includes DO-178/CSCI requirements based testing activities not completed within each Capability defined in 1.1.1.x. (Note: WBS not needed if all effort covered within each 1.1.1.x, or in 1.1.Z (PMP Integration Assembly, Test and Checkout)).
1.1.Z (L3)
PMP integration assembly, test and checkout (e.g. includes system/ARP-4754 verification) of all Products
Table 3: Example WBS, indicating WBS Number, Task Name, and comments on how best to apply in an Agile EVM program.
3.2 Integrated Master Plan (IMP) The Integrated Master Plan (IMP) precedes the IMS and draws from the product-oriented WBS Statement of Work, Statement of Objectives, and Concept of Operations. In Agile the IMP Program Events can describe Epics/Capabilities of the product defined in these documents. Program Events can include major customer milestones, Capability Releases, and other customer deliveries. This is a similar paradigm to the Integrated Master Plan described in the Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide.4 The IMP is an event-based plan consisting of a hierarchy of program events, with each event being supported by specific accomplishments, and each accomplishment associated with specific criteria to be satisfied for its completion.
4 Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide, October 2005, OUSD(AT&L)
© 2016 NDIA IPMD 9
The IMP may be initially developed in conjunction with an Agile Roadmap or the Product Backlog planning activity. The IMP reflects all the major customer milestones and deliveries, showing the order of the capabilities produced by the program. The Product Roadmap and Release Planning is the basis of the “Definition of Done" (DOD). The DOD equates to IMP’s Significant Accomplishments and Accomplishment Criteria, for each Epic/Capability and their Features. Figure 2, Agile Product and Time Hierarchies, is an example graphic illustrating how the IMP, EVMS, and Agile elements are vertically and horizontally traceable in a single framework integrating Agile and Earned Value Management. IMP events that are compatible with Agile programs include planned customer deliveries aligned to customer milestones. Initial delivery of a MVP, and later deliveries, are aligned with key mission milestones. For example, if building a space vehicle system, the control system events include deliveries to support launch, Initial Operational Capability (IOC), and Full Operational Capability (FOC). The IMP events may also include customer demonstration events, e.g., formal demos of an initial flight demonstration.
Figure 2: Agile Product and Time Hierarchies. IMP events are equivalent to Releases, with Significant Accomplishments and Accomplishment Criteria representing delivered capabilities delivered in Work
Packages where Features are implemented.
3.3 Integrated Master Schedule (IMS) Epics/Capabilities are decomposed into Feature, Story, and Story Task entities. An Epic/Capability delivers one or more Features, a Feature delivers one or more Stories, and a Story is implemented with one or more Story Tasks. On larger programs, one or more “sub-Epics” may exist between Epics and Features to manage the product decomposition to usable sizes, hence the chosen term in this Guide of Epic/Capability. Features are sized to fit within Agile Cadence Releases and represent significant pieces of the delivered product. Features are the logical lowest level product to be included in the IMS. Stories and Story Tasks serve as the
© 2016 NDIA IPMD 10
implementation details of the Feature and are maintained by the development teams outside the IMS in the Agile development tool. At program start, an initial Product Roadmap with MVP functionality will be created showing a plan for Epic/Capability and Feature development across the Cadence Releases, considering architectural and product dependencies as well as customer milestones. The IMS content, Features and their associated start/end dates and dependencies, will be finalized through Rolling Wave planning, prior to the start of the execution of the associated Cadence Release. Figure 3 shows a Rolling Wave Planning process in the IMS with Cadence Release 1 planned, while the content for the next Cadence Releases still contained in Planning Packages remains to be refined in subsequent Rolling Waves.
Figure 3: Illustration of Rolling Wave Planning in an IMS
Stories and Story Tasks implement the Features in the IMS. Stories are assigned to Sprints in the Agile management tool and are vertically traceable to Features in the IMS through coding fields like WBS, Control Account Number, and Work Package Number. This traceability provides the needed visibility to Program Management from the BCWS to objectively assess accomplishments at the work performance level in accordance with EIA-748-C, Page 1. Feature period of performance may be longer in duration than typical IMS tasks on a waterfall program. The justification for this is that the Stories that will implement each Feature are maintained by the development team as QBD to provide objective completion status. Completion of each Story’s scope of effort is the recommended method for assessing credit, taken against its related Feature completion by dividing total completed Stories by total planned Stories’ weighted values for that Feature. Specifically, full credit is taken upon Story completion (100%) to mark progress towards Feature completion. Other methods for claiming progress of completed scope of effort are outlined in Sections 4.3 and 5.5. Example IMS tasks and subtasks are shown in Figure 4 below. These correspond to CAs and Work Packages. Work Packages align with a single Feature or group of related Features. Figure 4, an example of an IMS subset, is based on the example WBS in Table 2. It shows part of a program with Cadence Releases of 85 working days. Two Epic/Capabilities are developed,
© 2016 NDIA IPMD 11
each requiring three Features that would each trace to a Work Package, plus Planning Packages assigned to future Cadence Releases. The Cadence Release milestone is a fixed date as it is time boxed, and has no defined dependencies with the product IMS tasks.
Figure 4: Example of an IMS subset, based on the WBS example in Table 2.
IMS considerations drawing from the IMS example in Figure 4:
• Networking between Work Packages shows dependencies across product Features. In Figure 4, the Architectural Feature of level 1.1.1.2.2 for a Database platform infrastructure must complete before the Feature of Database accessible by GUI, level 1.1.1.2.3, can be started. Other dependencies include test equipment, power supplies, hardware, or simulation software, as well as dependencies between the to-be-developed products. The cross-functional Agile teams should minimize dependencies/handoffs between teams based on disciplines (e.g., systems engineering, development, and test). To the extent that product level dependencies still exist, they must be modeled in the IMS to establish a critical path.
• The IMS is baselined prior to any work for the Cadence Release content being started. Release Planning in the IMS defines where the IMS is synced with the Agile plan, prior to execution of the work.
• IMS progress is informed by Agile progress tracking reports through burn-up or burn-down reports. See Section 4, Metrics for more details.
• In the IMS, work or planning package tasks can span the duration of a Release given no significant inter-CAM handoffs or major Feature-to-Feature dependencies will be modelled.
© 2016 NDIA IPMD 12
3.4 Implications of the DCMA Health Metrics Generated from the IMS There are IMS considerations for Agile programs when the Defense Contract Management Agency (DCMA) 14 Point Schedule Metrics assessment is applied described in DCMA-EA PAM 200.1, EVMS Program Analysis Pamphlet (PAP) page 28 that discusses the 14 point assessment’s use and intent. Although the DCMA 14 Point Schedule Metrics assessment can be a useful tool to identify problem areas in a schedule, it is not currently used in the evaluation of EVMS compliance. DCMA evaluates compliance using the Contractor's EVM System Description Document. Modeling Agile development life cycles in the IMS has the potential to conflict with the DCMA Assessment Guidelines. Most of the detailed work on Agile programs is tracked in the Agile tools in the planning and execution of Features, Stories, and Agile Story Tasks. IMS tasks may have longer durations and more overlap. Agile Features may have longer duration than typical IMS tasks on a waterfall program. In Table 4 below, the 14 DCMA Assessment Metrics and some potential impacts due to work being performed in an Agile fashion are discussed.
Metric # Metric Name Agile Impact
1 Logic Agile products modeled in the IMS may be longer in duration than current guidance. However, critical path between IMS tasks is still modeled, providing the necessary network logic for critical path analysis. There is also additional supporting data available in the supplemental information, e.g., from an Agile tool. Care must be taken in developing the initial program vision and roadmap to define dependencies between Epics/Capabilities, and between Features for the next program increment or Cadence Release, and revisit that at subsequent release planning meetings to support this activity.
2 Leads None
3 Lags None
4 Relationship Types
If modeling of Agile results in longer tasks (missing granularity), a larger percentage of the tasks may be modelled in parallel. This would decrease the number of Finish-to-Start relationships below the 90% threshold. However, Agile metrics will provide additional clarifying information such as using interim milestones to validate estimated task completion dates.
5 Hard Constraints
None
6 High Float None
7 Negative Float
None
8 High Duration
Each task representing a Feature may span an entire Cadence Release; progress is readily captured via Agile metrics tracing to interim milestones.
9 Invalid Dates None
10 Resources None
11 Missed tasks Features planned for completion within a Cadence Release but which are not completed would result in a variance. When this occurs the work would be moved to a later Cadence Release and the forecast updated. This would only result in a baseline change as well as variance if the work was no longer required to achieve the objectives of the release.
© 2016 NDIA IPMD 13
Metric # Metric Name Agile Impact
12 Critical Path Test
The critical path in an Agile program may be at an Epic/Capability or major Capability release level, with fewer, but longer-duration, tasks to span the program. Initial and Rolling Wave planning provides the supporting detail to this critical path.
13 CPLI See Metric #12
14 BEI None
Table 4: The 14 health metrics and how they should be considered on an Agile EVM program.
3.5 Freeze Period Considerations To avoid any misinterpretation of the DoD EVMSIG with respect to the freeze period, the following should occur: 1) The freeze period may be adjusted, through formal changes to a company’s system description or other supplementary guidance, to be short enough that it accommodates the Agile planning cycle, or 2) Customer direction to allow changes in the freeze period may be obtained given support and participation of the Customer in release planning activities. A key point is that planning, including detail planning of planning packages, completes prior to the start of work for any of the products in the upcoming Cadence Release. The customer should be highly integrated into the release planning process, with ample opportunity to provide input on the plan if there are concerns. For PARCA guidance on this topic, see the Agile and EVM System Compliance section, 2. Planning and Scheduling, paragraph e. in the Agile and Earned Value Management: A Program Manager’s Desk Guide.
© 2016 NDIA IPMD 14
4 Structures for Performance Metrics This section describes current best practices in industry in how to plan and then measure program earned value performance in Work Packages and CAs, using Agile progress measures.
4.1 Control Account Plan Control Account (CA) scope corresponds to Epics/Capabilities and the Features of the system. The specific technical scope and schedule of each CA is based on the system Epic/Capability decomposition into Work Packages and Planning Packages containing the Features needed to deliver those Epics/Capabilities. The schedule for delivery of system functions results from the planned Release of working software, the span of control desired by program leadership, and other similar considerations. Thus CA durations may vary from one to many Cadence Releases. However, it is recommended that CA scope correspond to a single Epic/Capability. WPs are an element of control within CAs. The number, content, size, and duration of Work Packages needed in a CA will vary subject to internal management needs and organizational policies along with the size and complexity of the program. A work package is the point where work is planned, progress is measured, and earned value is assessed. It is recommended to align one Feature or at most a small set of logically related Features with a Work Package. On Agile programs, the Work Package scope and budget corresponds to Features of the system. The budget for the Work Package is the budget of the staff assigned to the Sprints during the Period of Performance of the Work Package. A single Work Package corresponds to one or more Features and the Period of Performance may span the Cadence Release period or only a part of it. While a WP may contain multiple Features, each Feature should be entirely contained within a single WP. Whether a WP contains a single or multiple Features, there should be a logical relationship between Features and Epics/Capabilities and to Releases (either Capability or Cadence) with the program’s WBS, Control Account and Work Package structure. As an example, Figure 4’s IMS shows two Agile CAs ‒ 1.1.1.2 and 1.1.1.3. The 1.1.1.2 CA, Data Dashboard read/write, contains Work Packages that each align to a Feature, such as 1.1.1.2.1, User Graphical User Interface (GUI) to Enter/Report Data. Epic/Capability milestones align to CAs as well, such as for CA 1.1.1.3, Useage Protocol/Management, a Customer Delivery Milestone is scheduled on March 14th. After initial planning, Work Packages are defined during program execution through a series of Rolling Wave or release planning cycles. The release planning period is expressed as a fixed duration, and each WP should be scheduled to fit within one Agile Cadence Release. For Features beyond the current Agile Cadence Release, the scope is contained within Planning Packages, which will be refined during future release planning cycles.
4.2 Aligning Agile Progress Metrics with Earned Value Reporting Levels Figure 5 and Figure 6 are examples of Agile progress reporting used to status the PMB in the Earned Value Management System. In Figure 5, the completion of Agile Stories, with attributed Story Points proportional to the effort, determines the completion status (Percent Complete (PC)) for a Feature, which is the lowest reporting level. The Story Points assigned therefore create a weighted Story Value for product completion status calculations.
© 2016 NDIA IPMD 15
Figure 5: Example of Agile product completion status rolling up into EVM reporting at the Feature level. The Feature is planned to be developed over 3 Sprints, with percent complete at each Sprint calculated using the Feature’s weighted Story values. The Agile Team is working on other Features not shown in
this example; points indicate only part of their total workload.
Figure 6 shows measures of Percent Complete (PC) at the Capability level which are derived from Percent Complete at the Feature level using PC from the Feature level in Figure 5. Individual Feature Completion (PC) will still be determined based on completed Stories (similar to Figure 5); now the Feature PC is used in roll-up reporting to the higher level item. One or more features are contained in a Work Package; therefore, the Epics/Capabilities, comprising Features, would logically align to CAs.
© 2016 NDIA IPMD 16
Figure 6: Example of a higher level of rollup of Agile product completion status to EVM reporting.
Features with Work Package level earned value calculated using weighted Story Values roll up at each Cadence Release increment to weighted milestones based on Features completed within each Cadence
Release.
4.3 Computing & Reporting Earned Value Performance Using the earned value technique of Percent Complete (PC), Agile progress reports are based on Story Points completed divided by Story Points planned for the Sprint. This percent represents Percent Complete for the Sprint and is used in the calculation of Earned Value (BCWP) (EV). More information on normalizing Story Points, is provided in Appendix C, Reference 6, where a four-step method is described to normalize different teams’ estimated Story Points based on their commonly identified small Story which has been defined as equal to one Story Point. If a teams’ Story Point estimates are not normalized to a common reference, one cannot combine such QBD into a rolled-up progress report without a relative sizing calculation first to account for different team’s estimation data. One way progress can be calculated is to track Stories, their planned points, and their completion based on the Earned Value Technique chosen. Then report, at the multiple-Story Feature level, a PC that can then be translated into earned value in an EVM System based on PC inputs by Work Package/resource. See an example of this calculation of Feature level status by giving 50% Story Point credit when the Story is started and the remaining 50% when the Story is completed (shown below in Figure 7).
© 2016 NDIA IPMD 17
Figure 7: Another example of how planned Story Points, or weighted Story Values, may be applied to
create QBD to calculate earned value as a PC.
4.4 When Do You Take Credit for A Story? When to take credit for a Story is dependent, of course, on its Definition of Done, however, it is also dependent on the chosen Earned Value Technique for a WP, such as PC or Percent Complete Weighted Milestones. Given those decisions, weighted Story Values or estimated “ideal hours” effort for Stories can be readily normalized and translated into planned and then earned value and rolled up as QBD into an EV system entity such as a WP or CA (for definition of earned value techniques, see Appendix A, EVM Data Dictionary section). There are several options on when one can take credit for completing a Story. One company may choose to use 50/50, taking 50% EV credit when a Story is started and 50% at completion. Others prefer to more closely align with the binary nature of the corresponding Agile principle (“Working software is the primary measure of progress.”) and employ a 0/100 method, taking credit only when the Story is done, or meets the predetermined “Definition of Done”. Another option would be to take partial credit based upon completion of the various tasks that make up a Story. There are pros and cons to the various options. See below for a summary: 50/50: Half credit (50%) is taken when work is started on the Story, with the remainder (50%) taken upon Story completion (e.g., accepted by the PO).
• Pros – Allows partial credit to occur when some progress has been made even if the work did not completely get done before the end of the Sprint.
• Cons – Encourages starting work, which is contrary to the Agile principle of minimizing Work In Process. For longer Sprints and larger Stories there is an even greater potential for over-reporting of EV status.
0/100: No credit is taken for a Story until completed (e.g., accepted by the PO), at which time full credit is taken.
• Pros – This is easy and straight-forward and ensures that the claim is not taken until the Definition of Done and Acceptance Criteria are met. Encourages finer resolution of Stories so that multiple Stories are completed per Sprint, providing more accurate QBD to justify earned value numbers.
• Cons – If work does not get done, the claims may be low causing an artificially low Schedule Performance Index (SPI) or Cost Performance Indicator (CPI). The impact of this depends on the size of the Stories and the number of Stories that are in this state. There are likely to be open Stories that are not able to be claimed but have actuals recorded, hence causing a lower Budgeted Cost for Work Performed (BCWP) since
© 2016 NDIA IPMD 18
there is no credit for incomplete work. Shorter-duration Stories are necessary to achieve a granularity for accurate SPI/CPI reporting within financial business rhythms.
Partial Claiming: Agile Story Tasks related to a Story are relatively weighted and credit taken as Story Tasks are completed (Task Completion Based Percentage of Complete).
• Pros – Claims will be more granular resulting in a CPI and SPI more closely aligned with the detailed tasks performed (and thus budget expended), resulting in less time spent creating unnecessary variance explanations. This technique may be necessary for programs that have longer Sprint durations (e.g., 4 weeks) and larger Stories that are implemented through a full mini life-cycle of requirements, design, code, integration and verification all within the same Sprint.
• Cons – This does not support the Agile principle of measuring success in terms of completed work (i.e. working software) and allows teams to show a nearly-good SPI even if they did not meet the objectives of Working Software. Teams could mask bad actual status by starting many Stories and doing the easy stuff first while deferring high risk or complex tasks to later.
Selecting from these Earned Value Technique options is dependent on the nature of the work, which influences the Story size/duration, and how credit is to be earned. Story granularity ideally allows at least several Stories to begin and complete within each Sprint so that progress is visible throughout the Sprint rather than just at its conclusion, allowing course corrections as a team works the Sprint assigned Stories.
4.5 Feature Cost/Risk to be Considered When Establishing Baseline In Agile development, as well as in any product development, there are always uncertainties. It is recommended that these be considered when sizing the Features and establishing a Work Package cost/schedule baseline for that Feature. For identified risks, Stories should be planned as risk mitigation activities. For unknown risks, as usual in any earned value managed program, Management Reserve can be held at a higher level for use when in-scope unanticipated work is discovered and new Stories must be added to complete a product.
4.6 Variance from the Baseline: Examples with Agile EVM Variance is a natural consequence of developing complex products and there are cases where the scope achieved took more or less effort than planned. The examples below show how cost and schedule variances could be observed on an Agile program. Assume that there is a plan to complete a Feature estimated at a total of 20 Story Points, with planned labor of 400 hours in the associated work. The Feature consists of ten Stories of 2 points weighted Story Value, which translates to an estimate of 40 hours per Story or 20 hours per Story Point. During the first Sprint the team plans to complete 4 Stories of 2 points equal weighted Story Value each for a total 8 points. This equates to an estimate of 160 hours of labor (8/20 * 400 hours). The following are examples of possible variances after a Sprint:
• Consider the case where a team completes the planned amount of work in a Sprint for the Feature, but took 200 hours rather than the expected 160 hours to complete it. This will result in a cost variance at the Work Package level.
• A schedule variance would appear at the Work Package level if the team completed 3 of 4 planned Stories (6 of their planned 8 Story Points) using the hours associated with those Stories, 120 hours, and the remaining Story would need to be allocated to a later Sprint.
© 2016 NDIA IPMD 19
• During a Sprint, a team discovers a new 2-point Story is necessary to complete a planned Feature, and they decide to add that to the current Sprint. In this case, the extra Story is completed as part of the originally planned 160 labor hours; there is no variance to report into the Work Package: all planned work was completed as planned and on budget, 5 Stories of 10 points in 160 hours.
• During a Sprint, a team discovers a new 2-point Story is necessary to complete a planned Feature, and they decide to add that to the current Sprint. In this case, the extra Story is completed along with the original 4 using 200 total labor hours. This will result in a cost variance at the Work Package level.
• During a Sprint, a team discovers a new 2-point Story is necessary to complete a planned Feature, and that new Story goes into the Backlog for a future iteration assignment. The planned 4 Stories of 8 points are completed on schedule within planned hours; however, because of the additional Story in the Backlog, there is a resultant cost and schedule variance.
In each of these cases, an EVM variance appears at the Work Package level as a result of the QBD and natural Agile work flow.
4.7 How to Use Agile Metrics to Forecast ETC/EAC The Agile methodology endorses use of Planning Packages. Agile does not advocate detailed planning all the way through to program end, which traditionally enables ETC/EAC forecasting. This avoidance of detailed longer-term planning is based on the principle that it is not possible to do accurately early on given limited data and the likelihood of customer-desired outcomes changing. Yet EAC forecasting is essential in EVM-managed, or any managed program. For an Agile EVM managed program, a program’s entire budget can be plotted out at a summary level via roadmap planning and top-level IMP/IMS. At the roadmap level, Epics/Capabilities and Features are estimated and allocated to Cadence Releases, and a baseline is established. At each release planning event, the Planning Package for the next Cadence Release will be detail planned by finalizing the assignment of Features to the Cadence Release and Work Packages that have been initially allocated to the roadmap Epic/Capability plan in the form of Work Packages in the first Cadence Release and Planning Packages in subsequent Cadence Releases. In a large program where both Agile and EVM is in practice, Rolling Wave planning that typically occurred on a purely EVM program every 6 or 12 months can be replaced by this Rolling Wave planning at Cadence Release events. In this way the strong planning rhythm offered by Agile enables Rolling Wave planning in traditional EVM to be taken to a new level of currency and accuracy, supported by Agile planning practices.5 Each Sprint, within a Cadence Release, includes work activities for product development. Work performance for deliverables completed in past Sprints and Cadence Releases can be used to generate an ETC and EAC. Using the relative size of completed work, compared to future work is known and actual cost and schedule performance against past work is known, predictions can readily be performed for that future work. Note that, as in traditional EVM, changes in estimated work made as the program progresses are not changes in work scope; scope remains the same as described in the program baseline.
5 See the Agile and Earned Value Management: A Program Manager’s Desk Guide, Agile and EVM System Compliance section, 2. Planning and Scheduling, paragraph d. for guidance on developing Rolling Waves.
© 2016 NDIA IPMD 20
The formulas in Appendix A include methods to calculate an estimate to complete and are illustrated below. The formulae express how to calculate progress via PC on a single Feature as weighted Story Values expressed in Story Points (SP) completed versus the total weighted Stories planned, then how to calculate remaining hours of effort for a Feature using planned and completed weighted Stories in SP and hours used per completed Story Point.
𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹 𝑃𝑃𝐹𝐹𝐹𝐹𝑃𝑃𝐹𝐹𝑃𝑃𝐹𝐹 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐹𝐹𝐹𝐹𝐹𝐹 =𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐹𝐹𝐹𝐹𝐹𝐹𝐶𝐶 𝑊𝑊𝐹𝐹𝑊𝑊𝑊𝑊ℎ𝐹𝐹𝐹𝐹𝐶𝐶 𝑆𝑆𝐹𝐹𝐶𝐶𝐹𝐹𝑊𝑊𝐹𝐹𝑆𝑆 (𝑊𝑊𝑃𝑃 𝑆𝑆𝑃𝑃)𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝑃𝑃𝐶𝐶𝐹𝐹𝑃𝑃𝑃𝑃𝐹𝐹𝐶𝐶 𝑊𝑊𝐹𝐹𝑊𝑊𝑊𝑊ℎ𝐹𝐹𝐹𝐹𝐶𝐶 𝑆𝑆𝐹𝐹𝐶𝐶𝐹𝐹𝑊𝑊𝐹𝐹𝑆𝑆 (𝑊𝑊𝑃𝑃 𝑆𝑆𝑃𝑃)
𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹 𝑅𝑅𝐹𝐹𝐶𝐶𝐹𝐹𝑊𝑊𝑃𝑃𝑊𝑊𝑃𝑃𝑊𝑊 𝐸𝐸𝐸𝐸𝐸𝐸𝐶𝐶𝐹𝐹𝐹𝐹 𝐻𝐻𝐶𝐶𝐹𝐹𝐹𝐹𝑆𝑆
= (𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝑃𝑃𝐶𝐶𝐹𝐹𝑃𝑃𝑃𝑃𝐹𝐹𝐶𝐶 𝑆𝑆𝑃𝑃 − 𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐹𝐹𝐹𝐹𝐹𝐹𝐶𝐶 𝑆𝑆𝑃𝑃) ×𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝐻𝐻𝐶𝐶𝐹𝐹𝐹𝐹𝑆𝑆 𝐸𝐸𝐶𝐶𝐹𝐹 𝑆𝑆𝐶𝐶𝐹𝐹𝑊𝑊𝑃𝑃𝐹𝐹𝑆𝑆 𝐹𝐹𝐶𝐶 𝐷𝐷𝐹𝐹𝐹𝐹𝐹𝐹
𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐹𝐹𝐹𝐹𝐹𝐹𝐶𝐶 𝑆𝑆𝑃𝑃
The latter equation, put more simply:
𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹 𝑅𝑅𝐹𝐹𝐶𝐶𝐹𝐹𝑊𝑊𝑃𝑃𝑊𝑊𝑃𝑃𝑊𝑊 𝐸𝐸𝐸𝐸𝐸𝐸𝐶𝐶𝐹𝐹𝐹𝐹 𝐻𝐻𝐶𝐶𝐹𝐹𝐹𝐹𝑆𝑆 = (𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝑃𝑃𝐶𝐶𝐹𝐹𝑃𝑃𝑃𝑃𝐹𝐹𝐶𝐶 − 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐹𝐹𝐹𝐹𝐹𝐹𝐶𝐶 𝑆𝑆𝑃𝑃) ×𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝐻𝐻𝐶𝐶𝐹𝐹𝐹𝐹𝑆𝑆 𝐹𝐹𝐶𝐶 𝐷𝐷𝐹𝐹𝐹𝐹𝐹𝐹𝑇𝑇𝐶𝐶𝐹𝐹𝐹𝐹𝐶𝐶 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐹𝐹𝐹𝐹𝐹𝐹𝐶𝐶 𝑆𝑆𝑃𝑃
Appendix B provides examples of Agile EVM progress tracking.
© 2016 NDIA IPMD 21
5 Managing Baseline Change on Agile Programs This speaks to industry best practices for managing baseline changes on Agile development programs also using Earned Value Management. These best practices represent a knowledge network of Earned Value and Agile practitioners promoting a consolidated view. The working group recognizes there are various policies, procedures, processes, and tools within industry and this guide recognizes variability can exist. The working group laid out a set of scenarios and associated guidance that are currently occurring within industry. We encourage continuous feedback, comments, ideas and suggestions to the working group to continue to promote best practices on this topic.
5.1 Baseline Change Parameters Here are some baseline change scenarios using Agile development methodology which are also using Earned Value.
• Recognizing there are multiple Agile approaches, this section is based on Scaled Agile Framework® (SAFe®) concepts (See Appendix C, Reference 7), which is widely used in industry today.
• Recognizing that Agile development methodology is in use across a wide variety of programs and companies, this discussion is limited to contracts that would benefit from an EVMS; i.e., contracts that have some level of pre-defined goals or outcomes (requirements) tied to program events or milestones.
• Commercial programs developing product to take to market are not addressed.
• Level of Effort or staff augmentation contracts awarded in support of a government led initiative are not addressed.
5.2 Baseline Assumptions There is Agile terminology and assumptions made in the establishment of a program Performance Measurement Baseline (PMB) for EVMS, used as the basis for the change scenarios in Section 5.3. The program described here assumes an Agile implementation methodology that includes planning work within recurring time boxed boundaries such as Sprints and Releases as described in Section 3.1.
• Agile Product Hierarchy (best practice example): o The Agile product hierarchy is made up of Epics that are decomposed into
Features, which are sized to be scheduled to complete within a single release. Each Feature is further decomposed into Stories, which are sized to complete within one Sprint, as depicted in Section 3.1. Stories are developed and maintained below the level of the EVMS PMB.
• EV Hierarchy and definitions (best practice example): o CAs for this program are established at the Epic/Capability (product) level and
may span many releases. o Work Packages for EVMS are created at the Feature Level. Feature Work
Packages represent working product and have documented exit criteria (definition of done).
© 2016 NDIA IPMD 22
o Planning Packages represent working product associated with a future release. o The Product Backlog documents the technical scope of each CA. o All items listed on the Product Backlog include rough size complexity estimates
(weighted Story Value in Story Points, ideal hours, T-Shirt size (relative sizing method for typically smaller Agile efforts, in S, M, L, XL etc.), other) that are refined over time as knowledge is gained.
o All Items listed on the Product Backlog are traceable to a Work Package or Planning Package in the PMB.
• A Release Roadmap is maintained that documents the prioritized product Backlog. Epics and Features on the Product Backlog are mapped to specific releases as part of the Product Planning process.
o Backlog grooming (refining) is a continuous and normal part of Agile management and it is possible that Future Epics and Features may be reprioritized and mapped to different releases based on discovery or user feedback.
• The program does Rolling Wave planning at Cadence Release points. Rolling wave planning occurs after the Release Planning Event. The current release is detail planned and decomposed into “Feature Work Packages” (for Section 5 scenarios assume that there is only one Feature for each Work Package). Budget for future releases remains in Planning Packages.
5.3 Baseline Change Scenarios
Baseline Change Scenarios
Scenario PMB Action Product Backlog Action
1. The Work Package/Feature is not open and work has not started. It is determined the Feature is not needed for the current release. (Scenario 1 graphic included at end of Section 5.3.)
Baseline Change: Re-plan Work Package budget to future release Planning Package. If the baseline start of the Feature is inside the program’s “freeze period”, appropriate control and notification mechanisms apply.
Feature and related Stories are returned to Product Backlog and mapped to future release. The Planning Package identifier is updated.
2. The Work Package/Feature is 30% complete, but did not complete by a formal delivery date. The delivery date is held as planned. The customer accepts the delivery without the Feature functionality.
In most cases, this is not a baseline change. Although the customer accepted the delivery, the original plan was not met. In this case the Feature remains open, showing a schedule variance until the work is completed. In some limited cases, the customer may direct a baseline change, for example, if the Feature functionality is not needed for an extended period of time. In the case of a customer approved Baseline Change: Feature WP BCWS budget is set equal to cum
The unfinished Feature’s Stories are moved to the next release and planned in a Sprint. The WP identifier remains unchanged unless the Feature has been re-baselined. In the limited situations where the customer directs a baseline change, the Planning Package identifier is updated to reflect where the remaining work/budget has been allocated.
© 2016 NDIA IPMD 23
Baseline Change Scenarios
Scenario PMB Action Product Backlog Action Budgeted Cost for Work Performed (BCWP) and the remaining work and corresponding budget is re-planned to a future release Planning Package.
3. Features for the current Release are re-prioritized. A planned Feature is swapped with a different Feature from the Product Backlog of a similar size that was mapped to a future release. (This is unusual.)
Baseline Change: The swap is documented, even if the overall budget and baseline schedule dates do not change. IMS task descriptions and Feature Work Package descriptions/exit criteria are updated as necessary.
Features and related Stories are re-mapped to applicable WP and release PP. WP and PP identifiers are updated.
4. The Contracting Officer (CO) issues a contract letter which removes the scope of an Epic/Capability (requirement). The change affects a Feature which is currently baselined in an open Work Package.
Baseline Change: The in-progress WP is closed by setting BCWS equal to BCWP. The entire unclaimed budget associated with the Capability is returned to Undistributed Budget (UB) until dispositioned by contract mod (de-scope).
The unfinished Stories, Features and Epic/Capability are removed from the Product Backlog.
5. The exit criteria for Feature 1 Work Package are updated to add additional functionality (requirements) to that Feature. Stories are created to satisfy the additional requirements. The important consideration here is that the exit criteria of the Feature Work Package have changed.
Baseline Change: The scope of Feature 1 has increased. Budget must be added for that new scope. If this is the result of a customer desired enhancement (new scope) the budget will come from UB. If this is an un-planned in scope increase, the budget will come from Management Reserve (MR)
The exit criteria for Feature 1 are updated. Stories are created and added to the Product Backlog and mapped to Feature 1.
Scenario 1 Graphics: Example of a Change Modeled in the PMB and Product Backlog In scenario 1, an unstarted baselined Feature Work Package is not needed for the current release and is replanned to a future release. The two graphics below depict this scenario. The first graphic shows the current CA baseline, and how it is modeled in the Product Backlog and in the Control Account Plan (CAP). To maintain traceability from the Backlog to the CAP, a common field (the Work Package/PP ID number) is found in both.
© 2016 NDIA IPMD 24
In the second graphic below, Feature Y is re-planned to a future release and the graphic shows how the change is modeled in the Product Backlog and the CAP. The Feature and associated Stories are moved to the next release in the product Backlog, and the Feature Work Package in the CAP is re-planned, moving the budget for Feature Y into a Planning Package. This demonstrates the movement of scope and budget together.
© 2016 NDIA IPMD 25
5.4 Forecast Change Scenarios
Forecast Change Scenarios
Scenario PMB Action Product Backlog Action
1. A Feature Work Package that spans 3 Sprints has started. The team determines that some of the Stories mapped to the Feature planned in the first Sprint will not be completed and moves those Stories to the second Sprint which still falls inside the baseline finish date of the Feature.
No change to Feature Work Package baseline budget or baseline schedule. Stories can be moved from Sprint to Sprint within the planned duration of the Feature Work Package without impacting the baseline.
The product Backlog is updated to move the Stories not completed in the first Sprint into the second Sprint.
2. A Feature Work Package that spans 3 Sprints has started. The team determines that some of the Stories mapped to the Feature planned in the first Sprint will not be completed and move those Stories to Sprint 4, which is beyond the baseline finish date of the Feature.
No change to Feature Work Package baseline budget or baseline schedule. The in-progress Feature IMS task shows a slip to the baseline finish date. BCWP is only claimed for the Stories actually completed. BCWP compared to BCWS identifies a schedule variance. Reflect changes in IMS Forecast, EAC.
The Product Backlog is updated to move the Stories not completed in the first Sprint into the fourth Sprint
3. A Feature Work Package has started but will not be completed by a formal delivery date. Customer states that the functionality is needed for the formal delivery.
No change to Feature Work Package baseline budget or baseline schedule. The Feature is forecasted to slip beyond the delivery date. The IMS shows a late delivery. Critical Path (float) is impacted. Reflect changes in IMS Forecast, EAC.
The unfinished Stories are moved into the Sprint in the next release cycle where they are forecasted to be completed.
4. The PO and team determine a Story is deemed unnecessary for the accomplishment of the Feature due to an increased understanding of Feature exit criteria (requirements). The Exit Criteria for the Feature has not changed. The Feature WP is in progress. Feature QBD is the Stories mapped to the Feature.
No change to Feature Work Package baseline budget or baseline schedule. Feature QBD is updated to remove the Story. Removal of the Story from QBD may result in an increase in Feature WP percent complete since the percentage of unfinished effort has decreased. Reflect changes in IMS Forecast, EAC.
The Story is removed from the Product Backlog.
5. The PO and team determine a Story needs to be added for the accomplishment of the Feature due to an
No change to Feature Work Package baseline budget or baseline schedule. Feature QBD is updated to add the Story. Adding the Story to the QBD may result in a
The Story is added to the Product Backlog and mapped to the Feature. A Feature Work Package identifier is added.
© 2016 NDIA IPMD 26
Forecast Change Scenarios
Scenario PMB Action Product Backlog Action increased understanding of Feature exit criteria (requirements). The Exit Criteria for the Feature has not changed. The Feature WP is in progress. Feature QBD is the Stories mapped to the Feature.
decrease in Feature WP percent complete since the percentage of unfinished effort has increased. Reflect changes in IMS Forecast, EAC.
6. After a Feature Work Package and the associated Stories are accepted and claimed 100% complete, a problem is found. The defect must be corrected before the functionality can be released. A Defect Report (DR) is written.
a. If a stand-alone Work Package has already been established for DRs in the current release, the new DR is added to the QBD for that Work Package.
b. It may be appropriate in some cases to unclaim BCWP on the Feature Work Package if the work is not truly completed. The Feature QBD percent complete and forecast finish date are adjusted accordingly. Reflect changes in IMS Forecast, EAC.
a. The new DR Story is added to the product Backlog and mapped to the established DR Work Package.
b. The DR Story is added to product Backlog and mapped to the Feature Work Package.
7. Features mapped to future releases are reprioritized based on discovery and user feedback and mapped to other future releases. Budget for future releases is in a Planning Package.
No change to budget or baseline schedule. This is not a baseline change because this work has not been detail planned. This kind of re-prioritization is expected; however, the roadmap should be analyzed for potential bow-wave (work consistently moving ‘to the right’ without corresponding work moving forward) and related critical path impacts. If a bow-wave is apparent, a baseline change may be required to adjust the PP monthly budget spread. Reflect changes in IMS Forecast, EAC.
The product Backlog is updated and the Features are mapped to the resulting releases on the release roadmap.
5.5 Agile/EV Recommendations • The Contractor should establish a Freeze Period (Appendix C, Reference 8, Guideline
29) that supports the flexible nature of Agile development. Discovery and change are a normal part of Agile development, and change assessments occur frequently, often at the end of each Sprint. Assuming a Sprint cadence of every 2 weeks, and Rolling Wave planning at 3 month Cadence Release points, the Contractor may want to establish a short freeze period, perhaps a 2 week forward window, or the current Sprint Period of Performance (POP). A traditional freeze period such as “current month plus 1” will greatly limit the program’s ability to respond to change quickly. A Contractor’s freeze period should be defined in a way to support Agile and EV.
© 2016 NDIA IPMD 27
• The Contractor should work with the customer at the start of the contract to establish a stakeholder representing customer interests that is authorized to direct changes inside the freeze period on behalf of the customer contracting officer to facilitate Agile change management.
• The Contractor should establish the definition of product and the Definition of Done at the Feature and Epic level to allow for the creation, removal, and modification of Stories that are developed to satisfy the Feature and Epic functionality without an impact to budget or scope. Requirements are understood at a high level, but we also expect some level of change to emerge as Stories/Features are built and new knowledge is gained. It comes down to having the appropriate level of granularity of the Feature exit criteria. Detailed enough to have a good foundation of “what”, but not so prescriptive as to inhibit beneficial change. “Stories are not stand-alone requirements, in that they represent a statement of intent rather than a contractually required behavior” (Leffingwell)
• The Contractor should establish budgets, or MR reserves, that are inclusive of estimated DRs related to the development effort. When establishing the PMB, some portion of the development effort’s budget is retained for eventual DR work off. This allows for risk reduction and addresses the reality of detect identification during later program phases. Proactive identification of DR budgets or reserved capacity can also be accommodated by including this in assumptions for an Epic's Features.
© 2016 NDIA IPMD 28
Appendix A - EVM/Agile Data Dictionary
This appendix is organized into three sections. 1. EVM Agile Data Dictionary. This section provides an EVM Agile Data Dictionary and
thesaurus of Agile terms and rationale. The intent is to create a common vernacular and a method to harmoniously blend EVM and Agile program management practices.
2. Agile Data Dictionary. The section is a combination of Agile terms from Scrum Alliance and Agile Alliance.
3. EVM Data Dictionary. This section includes common EV Systems Management (EVMS) terminology consistent with the EIA-748 Standard for EV Systems.
© 2016 NDIA IPMD 29
EVM Agile Data Dictionary
EVM Abv.
EVM Link Term Definition
Rationale to Agile/Scrum Term
AGILE Link Related Term
AC Actual Cost Synonymous with ACWP
ACWP Actual Cost of Work Performed
Cumulative hours and/or direct cost to time now for Sprint, Feature, Story, Epic/Capability, and Work Package, as collected by Contractor's corporate accounting system.
Sprint, Feature, Story, Epic/Capability
ASD Actual Start Date The start date for the Work Package is when work starts on the earliest Story in Work Package
Story
AFD Actual Finish Date
The finish date for the Work Package is when work ends on the latest Story in Work Package
Story
BAC Budget At Complete
Summary of the Pork Package, Planning Package, and Summary Level Planning Package budgets
Story, Feature, Epic/Capability
BAC WP Budget At Complete for Work Package
Total planned Story Points for the Work Package translated to hours, dollars, or other measureable terms based on a validated conversion formula
Story Points
© 2016 NDIA IPMD 30
EVM Abv.
EVM Link Term Definition
Rationale to Agile/Scrum Term
AGILE Link Related Term
BCWP Budgeted Cost for Work Performed
The value of work completed at a given point in time, synonymous with “Earned Value”. Expressed in dollars representing the portion of Work Package that is complete. The percent complete for work performed is calculated by (weighted Story Value complete in the WP in Story Points) / (current best estimate of total weighted Story Value in the WP in Story Points). See Figure 2, Feature PC %. This can also be the burnup metric for all the Stories associated to the Work Package. It is assumed that Story Points have been normalized across teams based on a common small Story equating to one point, or that all Stories and features a Work Package is comprised of are completed by one Agile team for consistent Story sizing before conversion to WP Percent Complete. The dollarized calculation is the sum of (Baseline cost estimate for the WP or BAC WP) * (weighted Story Value complete in the WP) / (current best estimate of total weighted Story Value in the WP). Example: BAC WP for WP xyz has a baselined estimated cost of $100,000. The team targeted to deliver 33 of 100 Story Points by the end of Sprint n for WP xyz. At time now the team delivered 28 Story Points. WP xyz The BCWP $ and % (100,000 * (28/100) = $28,000 (28/100) * 100 = 28% It is important that the WP baseline cost estimate portion of the calculation does not fluctuate as the team adds or subtracts Story Points (either through changing Stories or changing the estimates on existing Stories). Changing the total SP in a WP by default ought to yield a variance not a baseline change.
Story Points, Definition of Done,
Burnup metric, Story
BCWS Budgeted Cost for Work Scheduled
The time phased Planned Value for the Feature(s), and their Stories associated to the Work Package. This can be summed to the program level and is developed during release and Sprint planning.
Definition of Done, Features, Story,
Release Planning, Sprint Planning
© 2016 NDIA IPMD 31
EVM Abv.
EVM Link Term Definition
Rationale to Agile/Scrum Term
AGILE Link Related Term
CV Cost Variance A metric for cost performance on a program. It is the difference between budgeted cost of work performed and actual cost (CV = BCWP – ACWP.) A positive value indicates a favorable position and a negative value indicates an unfavorable condition, and is expressed in dollars or as a percentage. The calculation for CV dollars is the difference of BCWP – ACWP. The calculation for CV percentage is the ((CV divided by BCWP) * 100). Example: The team targeted to deliver 33 of 100 Story Points weighted Story Value by the end of Sprint n for WP xyz. At time now the team delivered 28 Story Points of weighted Story Value. ACWP cum to date for WP xyz is $25,000 at end of Sprint n. The Cost Variance $ and % BCWP to date – ACWP cum to date = CV (100,000 * (28/100) – $25,000 = $3000 CV / BCWP to date = CV % ($3,000 /$28,000) * 100 = 11%
Story Points, Burnup metric, Story
DUR Duration The Work Package performance period is the earliest start and latest finish of all features (and their weighted Stories) associated to the Work Package
Story
EAC Estimate at Completion
An EVM performance metric that equals Actual Cost of Work Performed plus the estimated costs to complete (Estimate To Complete (ETC)) the authorized work remaining.
ESD Early Start Date The earliest forecasted start date of the Feature, Epic/Capability, Work Package or Planning Package.
Feature, Epic/Capability
EFD Early Finish Date The earliest forecasted finish date of the Feature, Epic/Capability, Work Package or Planning Package.
Feature, Epic/Capability
ETC Estimate to Complete
Assuming a single Agile team is working the Feature(s) for a Work Package, ETC is the weighted Story Value in Story Points that a team estimates is remaining that is directly associated to a Feature and Work Package. This number is translated into hours/dollars by multiplying the remaining Stories’ Story Points by the team’s velocity. This estimate is updated regularly per team cadence based on the Sprint Backlog tasks being worked on.
Story Point, Team, Feature, Velocity,
Sprint Backlog, Tasks
EV Earned Value The value of completed work expressed in terms of the budget assigned to that work. Synonymous with rationale of BCWP.
© 2016 NDIA IPMD 32
EVM Abv.
EVM Link Term Definition
Rationale to Agile/Scrum Term
AGILE Link Related Term
EVMS EV System A program management system that establishes the relationship between the cost, schedule, and technical aspects of the work; measures progress objectively with earned value metrics. The Agile/Scrum data can be leveraged for input of the program scope, schedule and cost performance and estimate to complete into the EVMS. Typically, the Agile/Scrum data resides in the Agile tool.
EVT Earned Value Technique
Defines the method used to earn the budgeted value for performance on a Work Package. Examples are LOE, percent complete, 0/100, 25/75, 40/60, 50/50, and weighted milestones. In many examples in this document, the EVT used is Percent Complete, with Stories/Story Points representing the subordinate detail.
Story, Definition of Done
HR Hours Fundamental unit of measure for budget or performance; for example, weighted Story Values expressed as Story Points converted to effort hours.
Story Points
IMP Integrated Master Plan
An event driven plan to manage program activities, which defines measurable and traceable program Events, Accomplishments, and Criteria to satisfy programmatic, and technical product and service requirements. This planning aligns to Product Backlog refinement which aligns with the event driven concepts (Events, Accomplishments, and Criteria) of the IMP. Includes defining the Minimum Viable Product (MVP) (Epic/Capabilities and Features) for the complete system and aligning to program milestones. .
Product Backlog Refinement,
Minimum Viable Product,
Epic/Capability, Features
IMS Integrated Master Schedule
A time dependent, task oriented schedule containing the networked, detailed tasks necessary to ensure successful program execution and that is integrated with the Integrated Master Plan. This aligns with the Product Roadmap and the Product Backlog refinement resulting in scheduling the Epic/Capabilities and Features into releases, i.e. release planning throughout the development life cycle allows us to plan to a Work Package level of the IMS. The Release and Sprint planning must contain the necessary logic and time-phasing to support program requirements and provide accurate progress information toward Product Backlog completion.
Product Backlog Refinement, Release
Planning, Sprint Planning, Sprint
Backlog
IPT Integrated Product Team
Cross functional team members working together consistently in a predefined pattern. In contrast to traditional methods that bring people in as needed.
Team
LOE Level of Effort Any team member whose effort is defined as a support type task having no practicable measurable output or product that can be discretely planned and objectively measured at the Work Package level.
© 2016 NDIA IPMD 33
EVM Abv.
EVM Link Term Definition
Rationale to Agile/Scrum Term
AGILE Link Related Term
Interim Milestone
Interim Milestone In an IMS, a milestone may indicate the start, an interim step, or the end of one or more activities. The term weighted milestone as used in the Earned Value Management System represents an Earned Value Technique (EVT) and the milestone is weighted with a value of hours, dollars, or other unit of measurement for performance recognition.
Product Backlog Planning,
Epic/Capability, Features, Release, Definition of Done
Milestone Milestone Any zero duration event that marks the completion of a significant activity e.g. releases, reviews, Sprints
Releases, Reviews, Sprints
PMB Performance Measurement Baseline
The time phased budget plan against which contract performance is measured. Through product and release planning, establish budget values for Epics/Capabilities throughout the program and their Features within next Release(s) for time phased work. Nearest release Features are assigned to Work Packages, Planning Packages may be used for ensuing Releases. These Planning Packages and Work Packages have been networked, resource loaded and leveled to establish the PMB.
Features, Release
POP Period of Performance
The number of working days or calendar days, from a specified commencement date to a specified completion date. The Work Package period of performance can be aligned to the beginning of the first Sprint and end of last Sprint.
Sprint
PP Planning Package
A logical aggregation of work within a Control Account, normally far-term effort, which does not have sufficient definition to define individual Work Packages. It is collection of Epics/Capabilities or Features budgeted and time phased to corresponding future Releases.
Epic/Capability, Features, Release
RAM Responsibility Assignment Matrix
A depiction of the relationship between the Work Breakdown Structure (WBS) elements and the Organizational Breakdown Structure (OBS) assigned, and defines who is responsible for the CA budget. In Agile, the PO manages the product Backlog and coordinates with the CAM for the scope, schedule, and costs of the product being produced.
PO, Product Backlog
SOW Statement of Work
Product Backlog and Release plan should be traceable to the SOW
Product Backlog, Release Plan
Status Meeting
Status Meeting A status meeting includes Agile reporting artifacts and EVM performance metrics and reports.
Agile reporting artifacts
SRA Schedule Risk Assessment
Schedule Risk Assessment (SRA) is a technique to connect the risk information of program activities to the baseline schedule, in order to provide sensitivity information of individual program activities to assess the potential impact of uncertainty on the final program duration and cost.
© 2016 NDIA IPMD 34
EVM Abv.
EVM Link Term Definition
Rationale to Agile/Scrum Term
AGILE Link Related Term
SV Schedule Variance
A variance from baseline plan indicating an ahead-of, or behind, schedule position expressed in dollars representing the value of work that is ahead or behind the baseline plan. The calculation for SV in dollars is the difference of BCWP – BCWS. The calculation for SV percentage is the ((SV divided by BCWS) * 100). Example: BAC WP for WP xyz has a baselined estimated cost of $100,000. The team targeted to deliver 33 of 100 Story Points by the end of Sprint n for WP xyz. At time now the team delivered 28 Story Points. The Schedule Variance $ and % BCWP to date – BCWS cum to date = SV ($100,000*(28/100) – ($100,000)*(33/100) = $-5000 SV / BCWS = SV % ( -$5,000 /$33,000) * 100 = -15%
Story, Story Point, Sprint
TASK Task An IMS Task is typically a Work Package, however, in Agile, Teams typically define task at a level below the Story (outside of the IMS). Not all Agile teams explicitly track tasks.
Story, Tasks
VARs Variance Analysis Reports
An EVM systems output that provides variance information of actual performance compared to the baseline plan. Supporting documentation from the Agile system can/should support the VAR.
Agile System, Impediment List
VAC Variance at Completion
The difference between the total budget and the estimated cost at completion. The calculation is BAC minus EAC (EAC = actuals incurred to date plus estimate to complete (ETC)).
WBS Work Breakdown Structure
A hierarchical product-oriented division of product scope is typically depicted as Epic/Capability, Features, Story, Tasks, for authorization, tracking, and reporting purposes
Epic/Capability, Features, Story,
Tasks
WP Work Package A Work Package is simply a task/activity or grouping of work. A Work Package is the point at which work is planned, progress is measured, and earned value is computed. An Agile Work Package will typically contain one or more Features.
Feature
© 2016 NDIA IPMD 35
Agile Data Dictionary
AGILE TERM AGILE DEFINITION
BURNDOWN CHART
The trend of work remaining across time in a Sprint, a release or in a product. The burn down chart is a publicly displayed chart showing remaining work in the Sprint Backlog. Updated every day, it gives a simple view of the Sprint progress.
BURNUP CHART The trend of work completed across time in a Sprint, a release or in a product. The burnup chart is a publicly displayed chart showing completed work in the Sprint Backlog. Updated every day, it gives a simple view of the Sprint progress.
BACKLOG GROOMING
The team (or part of the team including the PO) meet regularly to "groom the product Backlog", in a formal or informal meeting which can lead to any of the following:
• removing Stories that no longer appear relevant • creating new Stories in response to newly discovered needs • re-assessing the relative priority of Stories • assigning estimates to Stories which have yet to receive one • correcting estimates in light of newly discovered information • splitting Stories which are high priority but too coarse grained to fit in an
upcoming Sprint
BACKLOG A Backlog is a list of Features or technical tasks which the team maintains and which, at a given moment, are known to be necessary and sufficient to complete a program or a release:
• if an item on the Backlog does not contribute to the program's goal, it should be removed;
• on the other hand, if at any time a task or Feature becomes known that is considered necessary to the program, it should be added to the Backlog.
CADENCE Refer to definition for Release: Cadence Release.
CAPABILITY Capability and Epics may be used interchangeably. Both are recognized as customer required abilities of the system that provide value and is associated with specific Feature(s) and their Stories that must be satisfied for its completion.
DAILY SCRUM MEETING
A short status meeting held daily by each team. Team members synchronize their work and progress and report any impediments to the Scrum Master for removal.
DEFINITION OF DONE
Complete as mutually agreed to by all parties and conforming to an organization’s standards, conventions and guidelines. Note that an outcome of product and release planning is to create a "Definition of Done", which equates to IMP accomplishment criteria, for Epic/Capabilities and Features respectively.
EPIC Epics may represent core business capabilities which are defined by the customer or stakeholders. A large grained definition of a need that will likely take more than one release to complete. Can be split into Features and eventually Stories. Epics are part of the product Backlog and should have some form of relative sizing estimate.
ESTIMATED WORK REMAINING
The number of estimated hours that remain to be worked for any Story/task. This estimate is updated on a regular basis until the Story/task is complete for the definition of done.
© 2016 NDIA IPMD 36
AGILE TERM AGILE DEFINITION
FEATURE A discrete or coherent functionality within an Epic/Capability, scheduled to be completed within a release (cadence or Capability), and comprised of a collection of logically cohesive Stories. This is the lowest level of earned value baseline scope definition.
IMPEDIMENT LIST
List of items or bugs impeding progress
INCREMENT Synonymous with Release (Capability Release)
ITERATION Synonymous with Sprint
MVP (Minimum Viable Product)
MVP's are defined during Product Backlog planning. It is the minimum set of functionality (capabilities of Features) that are agreed to with customer (internal/external) to release. This may be defined by the customer or stakeholders as 'must have' functionality or core capabilities.
PRODUCT BACKLOG
The master list of all functionality at the Epic and Feature level that is desired in the product and any other elements needed to produce the product, even if not in the final product. Product Backlog is prioritized from most to least important.
PRODUCT BACKLOG DELTA
Reports the difference in total Features, and/or equivalent weighted Story Value in Story Points summarized to Features, planned based on changes to the Sprint Backlog.
PRODUCT BACKLOG PLANNING
A process in which the team maps the product Epic/Capabilities to Features that are to be accomplished based on customer agreement that specifies what the product must do and when the functionality will be delivered within a time boxed schedule.
PRODUCT OWNER (PO)
The person responsible for maintaining the Product Backlog by representing the interests of the stakeholders.
RELEASE There are two broad types of releases. Capability Release - A Capability Release is typically based on customer agreement that specifies what the product must do in context to the release plan. Cadence Release - working software released on a regular or time boxed schedule. Time box length varies widely, but is static throughout the development. In either case, the content of the release is determined thru product Backlog refinement/release planning. Agile development efforts commonly use Cadence Releases.
RELEASE PLANNING
A process in which the team maps the product Backlog Epic/Capabilities to Features and Stories that are to be accomplished based on customer agreement that specifies what the product must do and when the functionality will be delivered within a time boxed schedule.
SCRUM An incremental product development methodology commonly used to manage the program when applying Agile practices. A Scrum team works in a highly collaborative and team centric manner to achieve the team objectives.
© 2016 NDIA IPMD 37
AGILE TERM AGILE DEFINITION
SCRUM MASTER The person responsible for the Scrum process, making sure it is used correctly and maximizes its benefits. Scrum is facilitated by a Scrum Master, whose primary job is to remove impediments to the ability of the team to deliver the Sprint goal. The Scrum Master is not the leader of the team (as they are self-organizing) but acts as a buffer between the team and any distracting influences. The Scrum Master ensures that the Scrum process is used as intended.
SCRUM TEAM The Scrum Team is made up of the PO, Scrum Master and Team.
SPRINT A time box of work for which the duration is defined by the team and related to their optimal work cadence. Sprint durations are typically fixed and are usually between 1 and 6 weeks in duration. During the Sprint, the team works to turn a portion of the Product Backlog it has selected into an increment of potentially shippable product functionality.
SPRINT BACKLOG
A list of tasks to be completed during the Sprint.
SPRINT BACKLOG TASK
One of the tasks that the team or a team member defines as required turning committed Product Backlog items into system functionality.
SPRINT PLANNING MEETING
A meeting at the beginning of each Sprint in which the team plans the work to be accomplished during the Sprint and confirms the criteria for work completion.
SPRINT RETROSPECTIVE MEETING
A meeting of short duration which is facilitated by the Scrum Master at which the Team discusses the just concluded Sprint that determines what could be changed that might make the next Sprint more enjoyable or productive.
SPRINT REVIEW MEETING
A short meeting at the end of every Sprint at which the team demonstrates to the PO and interested stakeholders what it was able to accomplish during the Sprint. A key objective of the review is to get product feedback from the stakeholders.
STAKEHOLDER Someone with an interest in the outcome of a program, either because he or she has funded it, will use it or will be affected by it.
STORY (USER STORY)
Part of a Feature that can be estimated in Relative size and complexity and prioritized in Sprint Backlog. Stories are sized to fit within a Sprint. The completion of Stories can be used to calculate earned value.
STORY MAPPING A recent practice intended to provide a more structured approach to release planning; Story mapping consists of ordering Stories along two independent dimensions. The "map" arranges user activities along the horizontal axis in rough order of priority (or "the order in which you would describe activities to explain the behavior of the system"). Down the vertical axis, it represents increasing sophistication of the implementation. Given a Story map so arranged, the first horizontal row represents a "walking skeleton", a barebones but usable version of the product. Working through successive rows fleshes out the product with additional functionality.
© 2016 NDIA IPMD 38
AGILE TERM AGILE DEFINITION
STORY POINTS (ESTIMATES IN)
Agile teams express estimates in units of "Story Points”, providing for the use of Story Point Velocity for planning purposes. "Velocity", in the sense Agile teams use the term, has no preferred unit of measurement. Velocity allows teams to compute the expected remaining duration of the program, as a number of Sprints, each Sprint delivering some amount of Features. Another important reason has to do with the social and psychological aspects of estimation: using units such as Story Points to estimate a weighted Story Value, emphasizing relative difficulty over absolute duration, relieves some of the tensions that often arise between developers and managers around estimation: for instance, asking developers for an estimate then holding them accountable as if it had been a firm commitment.
STORY SPLITTING
Before a Story is ready to be scheduled for implementation in an upcoming Sprint, it should be "small enough", the usual rule of thumb being "a Story that can be completed within the Sprint". However, many Stories start out larger than that. "Splitting" consists of breaking up one Story into smaller ones, while preserving the property that each Story separately has measurable business value.
STORY TASK Lowest level effort of scope associated directly with a Story that can be estimated in size and complexity and prioritized in Story Backlog.
TEAM A cross-functional group of people that is responsible for managing itself to develop product for every Sprint. Team members’ work together consistently in a predefined pattern. In contrast to traditional methods that bring people in as needed.
TIMEBOX or TIMEBOXED
A period of time that cannot be exceeded and within which an event or meeting occurs. An example is the Daily Scrum meeting which is typically time boxed to 15 minutes and ends at that time regardless.
VELOCITY At the end of each Sprint, the team adds up effort associated with Stories that were completed during that Sprint. This total is called velocity. (Completed weighted Story Value in Story Points / Sprint Length) Knowing velocity, the team can compute (or revise) an estimate of how long the program will take to complete, based on the estimates associated with remaining Stories and assuming that velocity over the remaining Sprints will remain approximately the same.
© 2016 NDIA IPMD 39
EVM Data Dictionary
EVM TERM EVM DEFINITION
ACCOUNTING PERIOD The period of time during which actuals will be collected for transfer into the EV System for reporting purposes.
ACTUAL COST (AC) The costs actually incurred and recorded in the general ledger.
ACTUAL COST OF WORK PERFORMED (ACWP)
The costs actually incurred and recorded in the EV System for accomplishing the work performed within a given accounting period. ACWP reflects the applied costs that may be expressed as a value for a specific period or cumulative to date. (See also Estimated Actuals.)
ALLOCATED BUDGET See Total Allocated Budget.
APPORTIONED EFFORT (AE) Effort that by itself is not readily measured or divisible into discrete Work Packages but is related in direct proportion to the planning and performance of other discrete effort.
AUTHORIZATION TO PROCEED (ATP)
Official authority for the Contractor to begin work. It is usually issued by the procuring contracting officer.
AUTHORIZED UNPRICED WORK (AUW)
A contract scope change which has been directed by the government contracting officer but has not yet been fully negotiated/definitized. It includes a value, excluding fee or profit, typically associated with the authorized, unpriced change order.
AUTHORIZED WORK That effort that has been definitized and is on contract plus that effort for which definitized contract costs have not been agreed to but for which written authorization has been received.
BASELINE See Performance Measurement Baseline.
BASELINE SCHEDULE The original time-phased plan incorporated into the Integrated Master Schedule against which schedule status is compared or measured.
BILL OF MATERIAL (BOM) A listing of material items required to complete the production of a single unit. When actual or expected prices are applied, it becomes the Priced Bill of Material (PBOM).
BLOCK PLANNING The periodic process of converting Summary Level Planning Packages into control accounts and Control Account Planning Packages into Work Packages. The time period chosen reflects blocks of time from a specific contractual milestone to a subsequent specific contractual milestone.
BUDGET AT COMPLETION (BAC)
The sum of all budgets established for the contract through any given WBS/OBS level. When associated with a level it becomes Control Account BAC, Performance Measurement Baseline BAC, etc. (See Total Allocated Budget.)
BUDGETED COST FOR WORK PERFORMED (BCWP)
The sum of the budgets for completed Work Packages and completed portions of open Work Packages, plus the applicable portion of the budgets for level of effort and apportioned effort. May be expressed as a value for a specific period or cumulative to date.
© 2016 NDIA IPMD 40
EVM TERM EVM DEFINITION
BUDGETED COST FOR WORK SCHEDULED (BCWS)
The sum of the budgets for all Work Packages, Planning Packages, etc., scheduled to be accomplished (including in-process Work Packages), plus the amount of level of effort and apportioned effort scheduled to be accomplished within a given time period. May be expressed as a value for a specific period, or cumulative to date.
CONTRACT BUDGET BASE (CBB)
The sum of the negotiated contract cost plus the estimated cost of authorized unpriced work. This represents the total amount of performance measurement budget that may be allocated to contract work. (See Total Allocated Budget).
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The standard format for identifying potential data requirements in a solicitation, and deliverable data requirements in a contract. The purpose of the CDRL is to provide a standardized method of clearly and unambiguously delineating the Government's minimum essential data needs.
CONTRACT PERFORMANCE REPORT (CPR)
A contractually required report, prepared by the Contractor, containing performance information derived from the internal EV System that provides status of progress on the contract (DI-MGMT-81466A). (See also Integrated Program Management Report).
CONTRACT WORK BREAKDOWN STRUCTURE (CWBS)
The complete WBS for a contract. It includes the DoD approved WBS for reporting purposes and its discretionary extension to lower levels by the Contractor, in accordance with government direction and the contract work statement. It provides for the product-oriented decomposition of contract work into major elements that include all the hardware, software, data and/or services that are the responsibility of the Contractor.
CONTRACTOR An entity in private industry which enters into contracts with the government. In this guide, the word also applies to government-owned, government-operated activities which perform work on major defense programs.
CONTROL ACCOUNT (CA) The Control Account is the intersection of one WBS element and one OBS element representing a discrete portion of program scope assigned to an individual manager. The Control Account is the minimum level where technical, schedule, and cost responsibility exists.
CONTROL ACCOUNT MANAGER (CAM)
A single manager within the Contractor’s organizational structure that has been given the authority and responsibility to manage one or more control accounts.
CONTROL ACCOUNT PLAN (CAP)
The documented representation of the time-phased integration of scope, schedule and resources for all control account authorized work.
COST ACCOUNTING STANDARDS (CAS)
Requirements established by the CAS Board to ensure consistent and proper accounting for direct and indirect costs applied to government contracts.
© 2016 NDIA IPMD 41
EVM TERM EVM DEFINITION
COST ACCOUNTING STANDARDS BOARD (CASB)
An independently established statutory Board. The Board has the exclusive authority to make, promulgate, and amend cost accounting standards and interpretations designed to achieve uniformity and consistency in the cost accounting practices governing the measurement, assignment, and allocation of costs to contracts with the United States (41 U.S.C. 1501 et seq., formerly, 41 U.S.C. 422).
COST ACCOUNTING STANDARDS BOARD (CASB) DISCLOSURE STATEMENT
A written description of a Contractor's cost accounting practices and procedures.
COST PERFORMANCE INDEX (CPI)
The ratio of earned value to actual cost expenditure.
COST VARIANCE (CV) A metric for showing cost performance derived from earned value data. It is the mathematical difference between Budgeted Cost for Work Performed and Actual Cost of Work Performed. A positive value indicates a favorable condition and a negative value indicates an unfavorable condition. It may be expressed as a value for a specific period of time or cumulative to date.
CRITICAL ACTIVITY A discrete Work Package or Planning Package (or lower level tasks/activities) that resides on the critical path.
CRITICAL PATH A sequence of discrete Work Packages and Planning Packages (or lower level tasks/activities) in the network that has the longest total duration with the least amount of total float/slack through an end point that is calculated by the schedule software application.
CRITICAL PATH ANALYSIS A network analysis technique used to predict program duration by analyzing which sequence of activities (which path) has the least amount of scheduling flexibility (the least amount of float). See Network Schedule.
CURRENT PERIOD Accounting period in which the program is currently executing, i.e., time now.
DETAIL PLANNING The act of defining the scope, schedule and budget of a Planning Package into more detailed Work Packages with earned value techniques. Or the act of further defining the scope, schedule and budget of a SLPP into more detailed control accounts.
DIRECT COSTS Any costs that may be specifically identified with a singular cost objective.
DISCRETE EFFORT Tasks related to the completion of specific end products or services and can be directly planned and measured.
DRIVING PATH The longest sequence of discrete tasks/activities from time-now to a selected interim contract milestone. Discrete tasks/activities on the driving path have the least amount of total float/slack to the interim contract milestone. Driving path may not be part of the contract critical path.
EARNED VALUE (EV) See Budgeted Cost for Work Performed (BCWP).
EV (EVM) A program management technique for measuring program performance and progress in an objective manner.
© 2016 NDIA IPMD 42
EVM TERM EVM DEFINITION
EV SYSTEM (EVMS) An integrated management system that integrates the work scope, schedule, and cost parameters of a program in a manner that provides objective performance measurement data. It measures progress objectively with earned value metrics; accumulates direct costs; allows for analysis of deviations from plans; facilitates forecasting the achievement of milestones and contract events; provides supporting data for forecasting of estimated costs; and fosters discipline in incorporating changes to the baseline in a timely manner.
EV SYSTEM COMPLIANCE The continuing implementation, operation, and maintenance of the Contractor’s EV System in accordance with the 32 Guidelines in EIA-748.
EV SYSTEM (EVMS) GUIDELINES
The 32 Guidelines contained in the EIA-748 (current version) Standard that establish the framework for a Contractor's EVMS.
EV SYSTEM SURVEILLANCE A recurring process for assessing the continuous compliance of the Contractor’s EV System against the 32 Guidelines in EIA-748.
EARNED VALUE TECHNIQUE (EVT)
A specific technique (e.g., Milestone Method, Percent Complete, 50/50, 0/100, Units Complete, Apportioned Effort, LOE, etc.) selected to represent the measurement of work scope progress and accomplishment in a Work Package.
ELEMENTS OF COSTS (EOC) Product costs are decomposed into the elements of cost. These elements are comprised of labor, materials, other direct costs and overhead. EOCs represent the cost of products that are typical across industry.
ENTERPRISE RESOURCE PLANNING (ERP)
See Manufacturing/Enterprise Resource Planning (M/ERP) System.
ESTIMATE AT COMPLETION (EAC)
The current estimated total cost for program authorized work. It equals Actual Cost of Work Performed plus the estimated costs to complete (Estimate To Complete (ETC)) the authorized work remaining. EAC does not include profit or fee.
ESTIMATE TO COMPLETE (ETC) Estimate of costs to complete all work from a point in time to the end of the program.
ESTIMATED ACTUALS (EA) A value entered into the EV System to represent direct costs for material and/or subcontracted items for which earned value has been taken but invoices or billings have not entered the accounting system.
ESTIMATED COST (ESTIMATED ACTUAL)
An anticipated cost for specified work scope. Also known as estimated actual.
FORMAL REPROGRAMMING The process of establishing an Over Target Baseline (OTB) and/or Over Target Schedule (OTS).
FORWARD PRICING RATE AGREEMENT (FPRA)
An agreement between a Contractor and a government agency in which certain indirect rates are established for a specified period of time. These rates are estimates of costs and are used to price contracts and contract modifications.
© 2016 NDIA IPMD 43
EVM TERM EVM DEFINITION
FREEZE PERIOD A period of time when baseline changes are limited. See Guideline 29 (For reference see Appendix C Item 8) for information on exceptions to making baseline changes within the freeze period.
GENERALLY ACCEPTED ACCOUNTING PRINCPLES (GAAP)
The standard framework of guidelines for financial accounting used in any given jurisdiction; generally known as accounting standards or standard accounting practice.
GENERAL LEDGER A complete record of financial transactions over the life of a company. The ledger holds account information that is needed to prepare financial statements, and includes accounts for assets, liabilities, owners' equity, revenues and expenses.
GENERAL & ADMINISTRATIVE (G&A)
Per FAR Subpart 2.1: G&A expense means any management, financial, and other expense which is incurred by or allocated to a business unit and which is for the general management and administration of the business unit as a whole. G&A expense does not include those management expenses whose beneficial or causal relationship to cost objectives can be more directly measured by a base other than a cost input base representing the total activity of a business unit during a cost accounting period.
GROUPING, PEGGING, AND DISTRIBUTION
Developed as a way to combine material requirements across programs for procurement, fabrication, and assembly purposes but still allow for exact cost assignment back to the originating requirement.
HIGH VALUE MATERIAL Major components, assemblies, or critical piece-part items, etc. that are identified based on an analysis of material categories a company needs to procure and consume in the integration and build of an end item on a program.
HORIZONTAL INTEGRATION The logical relationships and time-phasing between tasks and milestones from –program start to finish.
HOURS Unit of measure.
INDIRECT COSTS Costs that cannot be identified specifically against a particular program or activity and must be controlled and budgeted at a functional or organizational level.
INTEGRATED MASTER PLAN (IMP)
An event-driven plan that documents the significant accomplishments necessary to complete the work and ties each accomplishment to a key program event.
INTEGRATED MASTER SCHEDULE (IMS)
An integrated, networked schedule containing all of the detailed activities necessary to accomplish the objectives of a program. When coupled with the Integrated Master Plan, it provides the time spans needed to complete the accomplishments and criteria of the Integrated Master Plan events. The IMS normally contains all levels of schedules for the program (master, intermediate, and detailed).
INTEGRATED PRODUCT TEAM (IPT)
A multidisciplinary team assigned management responsibility for one or more elements of an acquisition program.
© 2016 NDIA IPMD 44
EVM TERM EVM DEFINITION
INTEGRATED PROGRAM MANAGEMENT REPORT (IPMR)
A contractually required report, prepared by the Contractor, containing performance information derived from the internal EV System. Provides status of contract cost and schedule performance (DI-MGMT- 81861). The IPMR is being phased in to replace the Contract Performance Reports (DI-MGMT-81466) and the Integrated Master Schedule (DI-MGMT-81650).
INTERIM MILESTONE A zero duration interim step within the schedule that links to an event milestone marking the due date for specified work scope criteria completed. An interim milestone may mark the start, an interim step, or the end of one or more activities.
LEVEL OF EFFORT (LOE) Work defined as having no practicable measurable output or product that can be discretely planned and objectively measured at the Work Package level.
MANAGEMENT RESERVE (MR) An amount of the total budget withheld for management control purposes for future considerations to handle execution risks. It is not part of the Performance Measurement Baseline.
MANUFACTURING RESOURCE PLANNING (MRP)
See Manufacturing/Enterprise Resource Planning (M/ERP) System.
MANUFACTURING/ENTERPRISE RESOURCE PLANNING (M/ERP) SYSTEM
A method for the effective planning of all resources of a manufacturing Contractor. It integrates planning of all aspects (not just production) of a manufacturing firm. It includes functions such as business planning, production planning and scheduling, capacity requirement planning, job costing, financial management and forecasting, order processing, shop floor control, time and attendance, performance measurement, and sales and operations planning.
MATERIAL CATEGORIES Classes of material defined in the Contractor’s EV System Description and Manufacturing/Enterprise Resource Planning System Description.
MATERIAL CONTROL SYSTEM See Manufacturing/Enterprise Resource Planning System and Material Management and Accounting System.
MATERIAL MANAGEMENT AND ACCOUNTING SYSTEM (MMAS)
A system used by a Contractor for the planning, controlling, and accounting for the acquisition, disbursements, and disposition of material. They may be stand-alone systems or may integrate with planning, engineering, estimating, purchasing, inventory, accounting, or other systems.
MILESTONE A zero duration schedule event marking the due date for accomplishment of a specified work scope or objective. A milestone may mark the start, an interim step, or the end of one or more activities.
NEAR-CRITICAL PATH The lowest float or slack paths of discrete Work Packages and Planning Packages (or lower level activities) in the network that has the next longest total duration nearest to the critical path.
© 2016 NDIA IPMD 45
EVM TERM EVM DEFINITION
NEGOTIATED CONTRACT COST (NCC)
The cost negotiated in a cost-plus-fixed-fee contract or the negotiated contract target cost in either a fixed-price-incentive contract or a cost-plus-incentive-fee contract; does not contain profit or fee. NCC does not include the estimated value of undefinitized change orders, known as Authorized Unpriced Work.
NETWORK SCHEDULE A schedule format in which the activities and milestones are represented along with the interdependencies between activities. It expresses the logic of how the program will be accomplished.
NOT TO EXCEED (NTE) The portion of an estimated price for work scope the Contractor is allowed to bill the government before reaching a final agreement on contract terms. Expenditures against this work scope are limited to this value.
ORGANIZATIONAL BREAKDOWN STRUCTURE (OBS)
The hierarchical arrangement of the organization established to manage the resources tasked with performing the work on a specific contract or program.
OTHER DIRECT COSTS (ODC) A cost that can be identified specifically with a final cost objective that is not treated as a direct material cost or a direct labor cost.
OVER TARGET BASELINE (OTB)
A new baseline for management when the original objectives cannot be met and new goals are needed for management purposes. An overrun to the Contract Budget Base (CBB) which is formally incorporated into the Performance Measurement Baseline for management purposes. The difference between the Total Allocated Budget and CBB is the amount of the overrun incorporated into the budget.
OVER TARGET SCHEDULE (OTS)
A replanned schedule baseline that extends beyond the contract milestones and/or delivery dates. An OTS is usually accompanied by an increase in budgets resulting in a corresponding Over Target Baseline (OTB).
OVERHEAD See Indirect Cost.
PERFORMANCE MEASUREMENT BASELINE (PMB)
A time-phased resourced plan against which the accomplishment of authorized work can be measured.
PERFORMING ORGANIZATION The organizational unit that applies resources to accomplish assigned work scope.
PERIOD OF PERFORMANCE (POP)
The number of working days or calendar days, from a specified commencement date to a specified completion date, as provided for in a contract.
PLANNING PACKAGE (PP) A logical aggregation of future work within a control account that cannot yet be planned in detail at the Work Package or task level.
PRICE VARIANCE A variance relative to material that is equal to the budgeted unit price less the actual unit price multiplied by the actual quantity of material used, (i.e. (Budgeted Unit Price – Actual Unit Price) x Actual Quantity.) It reflects a change between the originally budgeted price of material and the actual price.
© 2016 NDIA IPMD 46
EVM TERM EVM DEFINITION
PROGRAM BUDGET The total budget for the program including all allocated budget, management reserve, and undistributed budget.
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) COST FORMULA
An earned value technique calculating Budgeted Cost for Work Performed (BCWP) by comparing the Actual Cost of Work Performed (ACWP) of received material to the expected total cost for that material (Estimate at Complete (EAC)) and applying the resulting percentage to the originally budgeted value for the material (Budget at Complete (BAC)), BCWP = (ACWP/EAC) x BAC.
PROGRAM TARGET COST The program cost objective based on the negotiated contract target cost, or the management goal value of the authorized work, plus the estimated cost of authorized unpriced work.
RATE VARIANCE A variance relative to labor that is equal to the planned labor rate less actual labor rate multiplied by the actual labor hours used to execute the effort, (i.e., (Budgeted Rate – Actual rate) x Actual Hours.) It reflects a change between the originally budgeted labor rate and the actual labor rate.
REPLANNING A realignment of schedule or reallocation of budget for remaining effort within the existing cost and schedule constraints of the contract. In this case, the Total Allocated Budget does not exceed the Contract Budget Base, nor is the schedule adjusted to extend beyond the contractually defined milestones.
RESIDUAL MATERIAL Material procured for a contract that becomes excess to the needs of the contract.
RESOURCE PLAN The schedule for the planned expenditure of program resources for accomplishment of program work scope.
RESPONSIBILITY ASSIGNMENT MATRIX (RAM)
A chart showing the relationship between the Contract Work Breakdown Structure elements and the organizations assigned responsibility for ensuring their accomplishment. The RAM depicts the assignment of each control account to a single manager. When resource values are applied to these relationships, it may be referred to as a dollarized RAM.
RESPONSIBLE ORGANIZATION The organizational unit responsible for accomplishment of assigned work scope.
RISK ASSESSMENT The definition of risk management that identifies and analyzes potential program risk events in terms of probability and their consequences/impacts.
RISK/OPPORTUNITY REGISTER A risk/opportunity management tool used by the program manager and program personnel that provides a means of recording and quantifying the identified risks/opportunities.
ROLLING WAVE The continuous process of converting Summary Level Planning Packages into control accounts and control account Planning Packages into Work Packages.
SCHEDULE A plan that defines when specified work must be done to accomplish program objectives on time.
© 2016 NDIA IPMD 47
EVM TERM EVM DEFINITION
SCHEDULE MARGIN A management method for accommodating schedule contingencies. It is a designated buffer within the schedule and does not have assigned resources.
SCHEDULE PERFORMANCE INDEX (SPI)
The ratio of work accomplished to work planned to be accomplished, as measured by the associated budget value.
SCHEDULE RISK ASSESSMENT (SRA)
A process which uses statistical techniques to identify technical, programmatic, and schedule risks in a program and quantifies the impact of those risks on the program’s schedule.
SCHEDULE VARIANCE (SV) A metric for schedule performance on a program. It is the mathematical difference between Budgeted Cost for Work Performed and the Budgeted Cost for Work Scheduled. A positive value is a favorable condition, while a negative value is unfavorable.
SCHEDULE VISIBILITY TASKS (SVTs)
Tasks, activities or milestones in the Integrated Master Schedule (IMS) that increase management visibility and functionality of the schedule for non-Performance Measurement Baseline related items. SVTs are included in the IMS to characterize potential impacts to the logic-driven network.
SINGLE POINT ADJUSTMENT (SPA)
Process that sets existing contract cost and/or schedule variances to zero and typically accompanies a replan of all remaining effort with the goal of completing the program on schedule and on budget.
STATEMENT OF WORK (SOW) Contractual document that defines the work scope requirements for a program.
STATUS MEETING A meeting to report program progress and performance towards achieving deliverable targets and any foreseeable concerns or issues that may cause delays or problems.
SUBCONTRACTOR An entity in private industry which enters into a contract with a prime Contractor that has entered into a contract with the government.
SUMMARY LEVEL PLANNING PACKAGE (SLPP)
An aggregation of work for far-term efforts that are not able to be identified at the control account level, but can be distributed to reporting level Work Breakdown Structure elements (and, therefore, are not “Undistributed Budget”).
SYSTEM DESCRIPTION (SD) The set or series of integrated process descriptions/procedures that describe a Contractor’s EV System.
TASK An element of work performed during the course of a program. A task/activity has an expected duration, expected cost and expected resource requirements. Some systems may define task/activity at a level below the Work Package while other systems do not differentiate between the two.
TOTAL ALLOCATED BUDGET (TAB)
The sum of all budgets allocated to the contract. TAB consists of the Performance Measurement Baseline and all Management Reserve. In the event an Over Target Baseline is in place, the TAB must reconcile to the Contract Budget Base and any recognized over target budget.
© 2016 NDIA IPMD 48
EVM TERM EVM DEFINITION
UNDEFINITIZED WORK Authorized work for which a firm contract value has not been negotiated or otherwise determined.
UNDISTRIBUTED BUDGET (UB) Budget associated with specific work scope or contract changes that have not been distributed to a control account or summary level Planning Package.
USAGE VARIANCE A variance relative to material that is equal to the budgeted quantity less the actual quantity multiplied by the budgeted unit price, (i.e., (Budgeted Quantity - Actual Quantity) x Budgeted Unit Price.)
VARIANCE AT COMPLETION (VAC)
The difference between the Budget at Completion (BAC) and the Estimate at Completion (EAC) (VAC = BAC – EAC). It may be calculated at any level from the control account up to the total contract. It represents the amount of expected overrun (negative VAC) or underrun (positive VAC).
VERTICAL INTEGRATION Demonstrates the consistency of data between the various levels of schedules and consistency of data between various Work Breakdown Structure elements and/or Integrated Master Plan/Integrated Master Schedule elements (if applicable) within the schedules.
VOLUME VARIANCE A variance relative to labor that is equal to the budgeted labor hours less actual labor hours multiplied by the budgeted labor rate planned to execute the effort (i.e., (Budgeted Hours – Actual Hours) x Budgeted Rate.) It reflects a change between the originally budgeted labor hours and the actual labor hours.
WORK AUTHORIZATION DOCUMENTATION (WAD)
A Contractor’s internal process for authorizing the commencement of program work. All work within a program is described in terms of work scope, budget and schedule and authorized through the work authorization system.
WORK BREAKDOWN STRUCTURE (WBS)
A hierarchical product-oriented division of program tasks depicting the breakdown of work scope for work authorization, tracking, and reporting purposes.
WORK BREAKDOWN STRUCTURE (WBS) DICTIONARY
A listing of WBS elements with a description of the work scope content in each element. The work descriptions are normally summary level and provide for clear segregation of work for work authorization and accounting purposes.
WORK PACKAGE (WP) Natural subdivision of Control Accounts. A WP is simply a task/activity or grouping of work. A WP is the point at which work is planned, progress is measured, and earned value is computed.
© 2016 NDIA IPMD 49
Appendix B - Examples of Agile EVM Progress Tracking Charts
Graphs can be created that overlay Agile program data metrics on the EVM calculations and metrics to show how Agile may be used to perform EVM analysis for a program with the Agile-EVM model of application. For example, a graph connecting Story Points (associated with completed weighted Stories) burn-up status with Performance Management Baseline (PMB) type data as a plot. This is illustrated below in Figures 8, 9 (Lockheed Martin Platinum Card) that illustrates both PMB and completed Story burn-up in Story Points. Figures 8 and 9 are the copyright of Lockheed Martin Corporation and are included in this guide. Figure 10 is a slightly different example from Rockwell Collins that shows explicitly the progress as measured via Story Points associated with completed Stories in the Agile Tool as “bars” on the graph as indexed by the left axis, along with the costs as indexed by the right axis to be able to visually see any disconnects or trends. Figure 11 shows an example program-level remaining weighted Stories burndown chart in Story Points courtesy of Raytheon with both overall status and forecasted Sprint iteration number the program will complete. All figures were used with permission.
© 2016 NDIA IPMD 50
Figure 8: Front side of example “Platinum Card” for Agile EVM, indicating both
Agile (Burn-Up) and EVM (PMB) baseline plan and progress data.
DoD Metrics Favorable is > 1.0, Unfavorable is < 1.0 Cost Efficiency CPI = Burn Up Status / Actual Cost (BCWP / ACWP) Schedule Efficiency SPI = Burn Up Status / Release Plan (BCWP / BCWS) Program Agile Team Estimate @ Completion ETC = Velocity x Remaining Backlog EAC = Actual Cost + (Velocity x Remaining Backlog)
Independent Estimate @ Completion # = ACTUALS TO DATE + [(REMAINING WORK) / (PERFORMANCE FACTOR)] EACCPI = ACWPCUM + [Remaining Backlog / CPICUM ] = ACWPCUM + [(BAC – BCWPCUM) / CPICUM ] EACComposite = ACWPCUM + [Remaining Backlog / (CPICUM * SPICUM)] = ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)] To Complete Performance Index (TCPI) = Work Remaining / Cost Remaining TCPIEAC = Remaining Backlog / (Velocity * Remaining Backlog) = (BAC – BCWPCUM) / (EAC – ACWPCUM)
PLATINUM CARD
EVM FOR AGILE DEVELOPMENT
MR (for rate impacts, R&O liens)
Cost Variance
Schedule Variance (Actual Cost
BURN UP CHART STATUS (BCWP Cum)
RELEASE PLAN (BCWS Cum)
$
EAC
Time Now Completion
Date
PMB
Total Allocated Budget
BAC
Time
Variances Positive is Favorable, Negative is Unfavorable Cost Variance CV = Burn Up Status – Actual Cost (BCWP – ACWP) CV % = (CV / BCWP) * 100 Schedule Variance SV = Burn Up Status – Release Plan (BCWP – BCWS) SV % = (SV / BCWS) * 100 Variance at Completion VAC = BAC – EAC VAC % = (VAC / BAC) * 100
Proj
ecte
d Sl
ip
REMAINING BACKLOG
VELOCITY X REMAINING BACKLOG (ETC Cum)
©2013.Lockheed Martin Corporation. All Rights Reserved.
© 2016 NDIA IPMD 51
Figure 9: Back side of example “Platinum Card” for Agile EVM.
AGILE DEVELOPMENT
EVM HIERARCHY
Agile Terminology Backlog Collection of features and user Stories the agile team will work on at some point in the future Burn Up Chart Representation of the amount of user Stories completed Feature Coherent business function or attribute of the product or system. A single feature typically is
implemented through many Stories. Features provide the basis for organizing Stories Iteration (Sprint) Time period of fixed length during which the agile development team produces an increment of
completed product Release Plan Schedule for releasing products into productive use, made up of features and user Stories Stories (User) Small system function with well defined success criteria that can be developed by one team
within one iteration. User Stories define the work that must be done to create and deliver a feature
Story Points Characteristics of a user Story; relative size measurement used by agile teams for work product estimation
Velocity Measures amount of work a team can complete in an iteration, typically in Story Points; used to measure how long it will take a particular team to deliver future outcomes by extrapolating on the basis of prior performance
Acronyms ACWP Actual Cost of Work Performed Cost actually incurred in accomplishing work performed PC Percent Complete (BCWP) BCWP claiming criteria for Feature (completed/planned Stories) BAC Budget At Completion Total budget for contract through any given level BCWP Budgeted Cost for Work Performed Value of completed work in terms of the assigned budget BCWS Budgeted Cost for Work Scheduled Time-phased Budget Plan for work currently scheduled CA Control Account Management point for planning/controlling scope/schedule/budget EAC Estimate At Completion Estimate of total cost for contract through any given level ETC Estimate To Complete Estimate of total cost for remaining work MR Management Reserve Budget withheld by PM for unknowns/risk management PMB Performance Measurement Baseline Contract time-phased budget plan, cost/schedule/technical objectives PP Planning Package Far-term CA activities not yet defined into Work Packages SPs Story Points Characteristics of a user Story. Relative size measurement TAB Total Allocated Budget Sum of all budgets for work on contract TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve the EAC WP Work Package Near-term, detail-planned activities within a CA
©2013.Lockheed Martin Corporation. All Rights Reserved.
© 2016 NDIA IPMD 52
Figure 10: Example of a progress tracking report indicating both Agile and EVM progress data on graph.
Figure 11: Example of a program level burndown chart across multiple teams, indicating
overall status and predicted completion Sprint.
© 2016 NDIA IPMD 53
Appendix C - References
1. Agile Planning and Estimating, Mike Cohn, 2006, Pearson Education, Inc., ISBN 0-13-147941-5
2. Scaling Lean & Agile Development, Craig Larman, Bas Vodde, 2009 Pearson Education Inc., ISBN-13: 978-0-321-48096-5
3. The Software Project Manager’s Bridge to Agility, Michele Sliger and Stacia Broderick, 2008, Pearson Education, Inc., ISBN-13: 978-0-321-50275-9
4. A Compendium on The Application of EVM to Agile Development and The Application of Agile Development to EVM, Glen Alleman, Eric Christoph, Luis C Contreras, Andrea Nibert, Ray W Stratton, Ron Terbush, Howard Zillman, The Measurable News, 2015.01 Issue, pp 11-38.
5. Digital Playbook – TechFAR Handbook, draft 6. Dean Leffingwell et al, the Scaled Agile Framework® creator’s website; specifically, Story
Point normalization method under the section titled Normalizing Story Point Estimating: http://www.scaledAgileframework.com/iteration-planning/
7. Scaled Agile Framework® (Leffingwell, et. all). http://www.scaledAgileframework.com/ The Scaled Agile Framework® (“SAFe®”) is a proven knowledge base for implementing Agile practices at enterprise scale. The SAFe® Big Picture describes three levels of scale; Team, Program and Portfolio. Each of these scales the essential Agile elements of Value (requirements and Backlogs) Teams, and Time box.
8. DoD EVMS Interpretation Guide, EVMS GUIDELINES:PLANNING, SCHEDULING, AND
BUDGETING and REVISIONS AND DATA MAINTENANCE CATEGORIES: Guidelines (10, 28 – 32) http://www.acq.osd.mil/evm/docs/DoD%20EVMSIG.pdf
© 2016 NDIA IPMD 54
General References on EVM Systems, Program Management, and Work Breakdown Structure 1. MIL-STD-881, Department of Defense Standard Practice: Work Breakdown Structures for
Defense Materiel Items, 3 October 2011 2. DoD IPMR Implementation Guide, January 24, 2013 3. PMBOK, A Guide to the Project Management Body of Knowledge, PMI 4. Practice Standard for EV, PMI 5. Practice Standard for Work Breakdown Structures, PMI 6. DoD Instruction 5000.02, Operation of the Defense Acquisition System
7. SAE International EIA-748-C EV System (EVMS) Standard (EIA-748) 8. EVM Systems EIA-748-C Intent Guide, April 29 2014, NDIA 9. DCMA Health Metrics assessment. See http://www.dcma.mil/policy/200-1/PAM-200-1.pdf. 10. Performance Assessments and Root Cause Analyses (PARCA);
http://www.acq.osd.mil/parca/ 11. Scrum Alliance, http://www.scrumalliance.org/ 12. The Agile Alliance, http://www.agilealliance.org/ 13. The Software Project Manager’s Bridge to Agility, Sliger, Michele; Broderick, Stacia, 2008
© 2016 NDIA IPMD 55
Appendix D - Agile/EV Guide Contributors
This guide was compiled by the NDIA Integrated Program Management Division (IPMD) Agile/Earned Value Working Group. The contributors are listed below.
Name Organization Role Neil Albert MCRI WBS/IMS Subgroup Glen Alleman Ivan Bembers
Niwot Ridge, LLC Government
Reviewer Managing Change Subgroup
David Bulkin Grow-Lean, LLC Data Dictionary Subgroup Juana Collymore Government WBS/IMS Subgroup Heidi Crookston GE Aviation Data Dictionary Subgroup
Chair & WBS/IMS Subgroup Kathy Dailey General Dynamics IT Agile/EV Working Group Co-Chair Kimberly Davis ASRC Federal Mission Solutions Managing Change Subgroup Singi De Silva Delta Resources Managing Change Subgroup Jim Duffy Raytheon WBS/IMS Subgroup Robert Eisenberg Lockheed Martin WBS/IMS Subgroup Renee Frazier Rockwell Collins WBS/IMS Subgroup Dale Gilliam SAIC CPM Representative Dennis Hall NDU WBS/IMS Subgroup Jessica Kaspari Rockwell Collins Managing Change Subgroup Matthew Kennedy DAU Data Dictionary Subgroup Gordon Kranz Enlightened Integrated Program
Management, LLC Reviewer
Howard Leibowitz SGT, Inc. Managing Change Subgroup Chair Amy Martz Raytheon Data Dictionary Subgroup Managing
Change Subgroup Larry Mattivi Government Data Dictionary Subgroup Andrea Nibert Leidos Managing Change Subgroup AnnMarie Oien Lockheed Martin Agile/EV Working Group Co-Chair
WBS/IMS Subgroup Chair Barbara Phillips Eagle One Solutions Managing Change Subgroup Scott Rummel Raytheon Data Dictionary Subgroup Leo Rodriguez AISC Data Dictionary Subgroup Dave Scott KM Systems Group Data Dictionary Subgroup Melissa Slaughter Delta Resources WBS/IMS Subgroup Jim Taylor Raytheon Data Dictionary Subgroup Ron Terbush Lockheed Martin Managing Change Subgroup Dave Tervonon Government Data Dictionary Subgroup Jeffery Thomas Raytheon Data Dictionary Subgroup Brian Valenti Rockwell Collins WBS/IMS Subgroup Pamela Walter Leidos Managing Change Subgroup Robin Yeman Lockheed Martin WBS/IMS Subgroup