Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
US Army Corps of Engineers BUILDING STRONG®
Alternatives Analysis: Satisfying NEPA, Public Interest Review & 404b1
Chandler Peter Technical Specialist Regulatory Division July 24, 2014
BUILDING STRONG®
NEPA, Public Interest & 404b1 Alternatives Integration
Regulatory strives to integrate requirements of all 3 into one analysis
Generally, they match relatively well ► However, NEPA and PI can have broader range of
alternatives (reasonable) than the 404b1s (practicable)
404b1s recognize that NEPA documents prepared for other agencies may need to be revised to address Guideline requirements
BUILDING STRONG®
Intensity of Alternatives Analysis NEPA – Adaptability recognized for EA or EIS
► EAs provide brief discussions of need, alternatives and impacts
► Courts hold level of alternatives analysis (both range and intensity) for EA less than for EIS.
PI – Level of controversy drives level of review ► Considers both practicability and reasonability
404b1 - Alternatives analysis is adjustable ► Level of analysis is to be commensurate with the
impacts/scale/cost of the project • See 8/23/93 Joint EPA/USACE memo
BUILDING STRONG®
Equal Treatment
Treat all alternatives equivalently ► NEPA require the degree of analysis devoted to each
alternative is to be substantially similar to the proposed action.
► NEPA states is to include alternatives not necessarily desirable from applicant’s perspective
► 404b1s require apples to apples comparison • Critical to appropriately determining Least Environmentally
Damaging Practicable Alternative (LEDPA) • Must demonstrate proposed action is LEDPA •USACE cannot issue permit for anything else
BUILDING STRONG®
Types/Range of Alternatives
NEPA & 404b1s require that alternatives analyses include consideration of: ► Proposed action ► Geographic options including changes in location or
alignment • Some actions may be site specific & do not have off site
options ► Site specific alternatives/configurations
• Different layouts • Reduction in size or area to be developed
► No Action alternative Display options on maps/plans
BUILDING STRONG®
No Action Alternative
Regulations specify 2 options for Regulatory 1. Formulate option that does not involve regulated
discharge (e.g. avoid on site, use upland off-site location, etc.)
2. Permit denial – what will applicant do If property to stay as is or sold, describe
► Discuss consequences of other likely uses of project site ► Need to not include speculative statement/analysis
Evaluate No Action to extent necessary (variation on equal treatment allowed)
BUILDING STRONG®
Screening Criteria 404b1s specify 5 categories to screen alternatives
1. Environmental consequences to waters of the US 2. Project purpose 3. Logistics 4. Costs 5. Technology
NEPA, in general terms, identifies 4 factors 1. Project purpose 2. Common sense 3. Economics 4. Technology
Documentation justifying screening criteria, thresholds, & how applied to options critical
BUILDING STRONG®
Waters of the US Impact Screen Typically easiest screen to develop/apply Addresses “Least Environmentally Damaging”
portion of LEDPA ► Comparison of impacts to waters of the US between
alternatives should be shown • Normally based on acreage/linear feet (similar functions)
Can also include indirect, secondary and cumulative impacts • Off site options compared to proposed site
Delineations not required for all sites but methods of comparative assessment must be the same. Use proposed site delineation to validate off site method accuracy
• ID differences in impacts with on-site configurations • Can display in tabular form
BUILDING STRONG®
Waters of the US Impact Screen 404b1 Guidelines sequencing requirement
must be followed ► Cannot consider compensatory mitigation actions in
the alternatives analysis for determination of LEDPA (e.g., no buying down of impacts)
► Re-emphasized in 1990 EPA/USACE Mitigation MOA
Avoidance & minimization must be considered and is utilized
BUILDING STRONG®
Project Purpose Screen Overall project purpose must be met by any
alternative to be practicable ► Either an alternative satisfies purpose or doesn’t ► Not a “better addresses purpose” determination
Simplified Example – Project purpose is to safely accommodate current & future traffic between town X and city Y. ► Alt. 1 - 2:1 side slopes w/ guardrails – 2 acres impacted ► Alt. 2 - 4:1 side slopes no guardrails – 3 acres impacted ► Both carry traffic & are safe (based on AASHTO standards)
but 1 not as safe as 2 ► USACE can only permit option #1
BUILDING STRONG®
Project Purpose Screen Additionally, it’s not whether an alternative
“more fully or better addresses” management plans, goals, desires, political issues (non project purpose aspects) One practicable alternative provides greater social
benefits (with greater aquatic resource impacts) compared to another w/ less aquatic resource impacts & less social or economic benefits, USACE can only approve the lower aquatic resource impact alternative
BUILDING STRONG®
Logistics Screen Typically government, other impediments that
eliminate ability to implement an alternative ► Categories usually similar for project types but
applicability is very case specific • Land availability and potential designation(s) • Denial of zoning, access, variance or other development
changes • Timeliness (for some public works actions) • Other
► Factors normally not legitimate as logistics screens • Funding streams • Zoning
BUILDING STRONG®
Cost Screen Normally screen of last choice due to amount of
effort to develop, conflict & other factors 404b1s specify costs rather than economics
► Term “economic” eliminated from original 404b1s • Applicant financial standing, market share not germane
Need to establish cost “thresholds” & are to be based on: ► Type of project and applicant ► Costs associated w/ comparable type projects in
area/region
BUILDING STRONG®
Technology Screen Typically a cost screen
► Aspects of project/area may require innovative use of technologies that add significant costs (e.g., geotechnical issues at dam site)
Can result in substantial effort to determine if emerging technologies can be applied to project or alternative
BUILDING STRONG®
Second Look
404b1s require Corps only approve LEDPA ► Impacts to aquatic resources drive Corps decision
However, can consider whether LEDPA has other significant adverse environmental consequences ► Allows for considering other significant effects and
damage to other ecosystems ► EPA/Corps 8/23/93 guidance furthers that these
“other consequences” are to involve natural environmental values