Alpha Magnetic Spectrometer – 02 RID Overview & Disposition Re-baselining Outbrief July 15, 2004 Trent Martin

Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

  • Upload
    malana

  • View
    34

  • Download
    0

Embed Size (px)

DESCRIPTION

Alpha Magnetic Spectrometer – 02 RID Overview & Disposition. Re-baselining Outbrief July 15, 2004 Trent Martin. Documents for Review. http://www4.jsc.nasa.gov/eaprojects/ea-projects/flightgfe/ams_02/html/ams_02.htm. Other Items for Review. - PowerPoint PPT Presentation

Citation preview

Page 1: Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

Alpha Magnetic Spectrometer – 02

RID Overview & Disposition

Re-baselining Outbrief

July 15, 2004

Trent Martin

Page 2: Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

AMS Re-Baselining RIDsAMS Re-Baselining RIDs 15-July-200415-July-2004Alpha Magnetic

Spectrometer NASA / DOE

Documents for Review

Document #Rev/Change

# / IRNIssue Date Title

Review Assignment

JSC 29789 A-Draft June 04AMS Project Technical Requirements

SpecificationAll

JSC 27296 B-Draft June 04 Project Plan for AMS All

JSC 29095 Part I & II

(CICD)Basic

Part I – Jun 02

Part II – Dec 01AMS-02 Experiment/Payload Integration

Hardware Interface Control DocumentISS, SSP, KSC,

AMS

JSC 27542 A-Draft June 04 AMS Configuration Management Plan EA, AMS

JSC 28792 C July 03 AMS-02 SVP for ISS and STS ES, AMS

SSP 57113 Pre-baseline Jan 04 PIA for AMS ISS, SSP, EA

SSP 57213 Draft June 04 AMS-02 Attached Payload ICD ISS

http://www4.jsc.nasa.gov/eaprojects/ea-projects/flightgfe/ams_02/html/ams_02.htm

Page 3: Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

AMS Re-Baselining RIDsAMS Re-Baselining RIDs 15-July-200415-July-2004Alpha Magnetic

Spectrometer NASA / DOE

Other Items for Review

Data Title Review Assignment

RIDs Open CDR RIDs – review at AMS EA Website All

Risks AMS Risks in IRMA – review at AMS EA Website All

Schedule AMS Master Schedule – review at AMS EA Website All

Quality System Entire AMS Quality System NT, EA

Page 4: Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

Group Lead Reviewer Status RIDs Open RIDs

EA1 AMS Project ManagementSteve Porter Complete

Nancy Munoz Complete

EA2 Web-support – Project Support Stan Donahoe Complete 13 6 (5-PA)

EC MLI Production Evelyne Orndorff Complete

EP Fluid Systems Rich Schoenberg Complete 2

EP Battery Systems Judith Jeevarajan Complete

ES Structures Dan Rybicki Complete

EV SAIL Support for Avionics Susan Morgan, Mary Harris Complete 1

CB Crew Office Representative L.D. Stevenson Complete 6

DO Mission Operations Anne Vaughan Complete 2 1-PA

NC Safety Engineer Chuck Bailey Complete

NT Q&MA for PIH John Stanford, Dave Kaplan Complete 49

MA Shuttle Payload Integration Manager JJ Conwell Complete

OZ ISS Payload Integration Manager Bob Miley / Win Reid Complete 2 2-PA

GSFC Attached Payload Support Ruthan Lewis Complete

MSFC POIC – Payload Operations Director & Mission Ops Ray Echols Complete

KSC Launch Site Support Jack Keifenheim Complete 1

AMS Collaboration RepresentativeMike Capell, Klaus Luebelsmeyer,

Giuliano LaurentiComplete 5 3 (1-PA)

LMSO LMSO Project Team Trent Martin, et al Complete 3 3-PA

Review Team Status as of July 15, 2004 – 84 Total RIDs

PA – Pending Action

Page 5: Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

AMS Re-Baselining RIDsAMS Re-Baselining RIDs 15-July-200415-July-2004Alpha Magnetic

Spectrometer NASA / DOE

RID Statistics

1 15 29 43 57 71

2 16 30 44 58 72

3 17 31 45 59 73

4 18 32 46 60 74

5 19 33 47 61 75

6 20 34 48 62 76

7 21 35 49 63 77

8 22 36 50 64 78

9 23 37 51 65 79

10 24 38 52 66 80

11 25 39 53 67 81

12 26 40 54 68 82

13 27 41 55 69 83

14 28 42 56 70 84

Red – Open

Yellow – Open pending document update

Green - closed

Page 6: Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

AMS Re-Baselining RIDsAMS Re-Baselining RIDs 15-July-200415-July-2004Alpha Magnetic

Spectrometer NASA / DOE

Major RID Findings

• Project Plan editorial comments, clarifications and reorganization

• PTRS editorial comments and clarifications– Major decision to pull verification matrix out of

PTRS and write the V&VD now

• ICD & SVP editorial comments and clarifications

Page 7: Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

AMS Re-Baselining RIDsAMS Re-Baselining RIDs 15-July-200415-July-2004Alpha Magnetic

Spectrometer NASA / DOE

RID Statistics

• 3 Open– RID 19 – Remove LMSO from all documents– RID 75 – Add 2nd ACOP– RID 77 – Modify AMS Payload Goals

• 13 Open Pending Action– RIDs 1,52,53 – Updates to SVP– RIDs 3,66,67,68,78,79,81,82 – PIH to AMS ICD or VC ICD– RIDs 61,65 - New V&VD

• 68 Closed– RID 76 – Many updates to Project Plan

Page 8: Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

AMS Re-Baselining RIDsAMS Re-Baselining RIDs 15-July-200415-July-2004Alpha Magnetic

Spectrometer NASA / DOE

CDR RID Summary

• Had 38 open RIDs at the start of the rebaselining review

• 21 Open RIDs– Majority are open pending work that was either delayed

due to lack of funding or are part of the standard process for later reviews (FSR II and III)

• 17 Closed RIDs– Mostly duplicated by Rebaselining RIDs or superceded by

new document revisions

• Will bring closure plan back to first CCB (August)